QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION
Transcript

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES2011 EDITION

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES

GUIDELINES AND SUPPORTING DOCUMENTS FOR IMPLEMENTATION OF POLICIES AND PROCEDURES TO ENSURE THAT ALL ROAD, BRIDGE AND UTILITY DESIGN SUBMITTALS TO THE DESIGN SECTION MEET MUNICIPALITY OF ABU DHABI CITY QUALITY STANDARDS.

Content

1 Quality Assurance Plan 4

1.1 Introduction 6

1.2 Quality Assurance Form 8

1.3 Design Completion Certificates 10

1.4 Design Review Checklists 12

1.5 Submittals for Roads, Structures & Utilities 14

2 Quality Control Plan 16

3 Consultant Evaluation 20

3.1 Introduction 22

3.2 Design Submittal Evaluation 24

3.3 Rating Definitions 26

3.4 How the ADM Reviewers Evaluate the Submittal 28

Appendix 30

Form 1 32

Quality Assurance Form 32

Form 2 33

Design Completion Certificates 33

Form 3 34

Consultant Evaluation Form 34

Checklists 36

Checklist No. 1 – Plans to be submitted at Each Stage 36

Checklist No.2 - CIVIL – (Conceptual Design Stage) 38

Checklist No.3 – CIVIL – (Preliminary Design Stage) 40

Checklist No.4 – CIVIL (For all stages) 41

Checklist No.5 – CIVIL (for all stages) 42

Checklist No.6 – Structures (Concept Design Stage) 50

Checklist No.7 – Structures (Approval in Principle Report) 54

Checklist No.8 – Structures (Preliminary Design Stage) 61

Checklist No.9 – Structures (Detailed Design/Final Design Stage) 62

Checklist No.10 – Structural Drawings for all Stages 63

Checklist No.11 – Utilities (For Concept Design Stage) 66

Checklist No.12 – Utilities (Preliminary Design Stage) 67

Checklist No.13 – Utilities (For all stages) 68

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

1. QUALITY ASSURANCE

PLAN

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

6

1.1 Introduction

The purpose of these

procedures is to

enable consultants to

demonstrate to the

Municipality of Abu

Dhabi City (ADM) that

they are incorporating

effective quality control

measures into the

design process.

The increased awareness and

documentation from following

these procedures will provide ADM

with heightened confidence in the

quality of design submittals and

promote uniformity, consistency,

and reduced review time, resulting

in quicker turnaround times for

design submittals.

These procedures are not intended

to replace the quality control

measures that are currently in use,

but rather to promote awareness

regarding the importance of

quality control throughout the

design process. Computation

sheets and drawings must still be

initialled by the designer and the

checker, as per current practice,

and the review of items should still

be carried out independently by

qualified assessors.

8

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

The project manager must

complete the Quality Assurance

Form (Form 1) and include it

with each submittal stage. The

consultant’s reviewer must sign

the form and type his name below

the signature line. The item blank

will generally correspond to the

appropriate checklist in Appendix,

which must be completed by the

reviewer. If any numbered items

are not applicable for a specific

project, they should be marked

with a “N/A” (Not Applicable) in

the reviewer space. When items to

be reviewed do not correspond to

a number in the checklist, a short

description should be included in

the item space.

The Quality Assurance Form must

be signed by the designer and the

consultant’s reviewer, and then

approved by a professional or

qualified engineer. Prior to each

submittal, the project manager

must review the plans to ensure

consistency between sheets,

completeness and overall content.

This will include verifying that

the proper number of plans and

items, such as construction cost

estimates, are included with the

submittal. The project manager

should submit a design review log

sheet that includes all comments,

which will confirm that all

requested revisions from previous

submittals have been made or

communicated.

Providing the name and the

contact details of the consultant’s

project manager is important for

future communication between

him and the ADM project manager.

Telephone conversations are

encouraged to clarify items or

answer questions during the review

process. The remarks section can

also be used to list any requested

revisions that were not made with

an acceptable reason; however, the

project manager is encouraged to

discuss these items with the ADM

reviewer prior to the submittal.

1.2 Quality Assurance Form

10

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

1.3 Design Completion Certificates

Similar to the Quality Assurance

Form, the Design Completion

Certificates Form must be

completed and signed by the

project manager, the designer

and the verifier to certify that

the consultant has used his

professional skill and care to

produce the submittal.

This form is to be submitted at

each design stage. Refer to Form 2

of the appendices for the form and

the certificate.

12

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

The Municipality of Abu Dhabi City Roads Design Section has prepared these checklists to serve as guidelines for design consultants during the design review process and to submit to ADM as part of each design submittal. ADM expects consultants to use design review checklists for all design submittals. Care must be taken to ensure that the checklists cover the most critical aspects and considerations of a design. The consultant’s reviewer must sign the applicable checklists and type his name at the bottom.

For design review checking to be effective, the reviewer must be an individual with in-depth knowledge of the relevant discipline. It is also important that he not be the creator of the calculation or drawing being checked. This enables the ADM reviewer to bring an impartial perspective to the review, helping to ensure that the intentions of the designer are accurately conveyed to the calculations and drawings.

The size of the project will dictate how much information is contained on each drawing. More than one drawing checklist may have to be applied to check a single drawing, if it contains more than one design discipline. For example, under

certain circumstances, a single drawing may contain utilities, existing conditions and proposed plans. In this case, each of the three relevant checklists would be applied to the drawing. In other cases, a single checklist may have to be applied to several drawings.

In order to ensure the accuracy of calculations, calculation checking should be a two-step process. The first step is to verify the validity of all assumptions, given parameters, and formulation. The second step is checking the numerical values for accuracy.

The purpose of checking is to ensure that everything is accurate and consistent, and that each drawing properly and adequately relates to the others in the set, reflects the design analysis, uses the current standards of presentation, and provides all details needed for construction. All design review checklists for common design elements can be found in the appendices. It should be noted that these samples are not comprehensive, and ADM expects consultants’ reviews, prior to submittal, to be more thorough and exacting, when and where required.

1.4 Design Review Checklists

14

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

15

Bridges and HighwayStructures

5. Conceptual Design Stage

(10%); Checklist No.1

and Checklist No.10

(Design Drawings), the

conceptualisation of

solutions and development

of alternative concepts is

outlined in Checklist No.6

(Concept Design Report)

6. Preliminary Design Stage

(60%); Consultant will use

the Approval in Principle

(AIP) document for selected

alternative based on ADM’s

structural design guidelines

and criterion mentioned in

Checklist No.7 (Approval

in Principle) for ADM’s

approval. Checklist No.1,

Checklist No.10 (Design

Drawings) and Checklist

No.8 (Preliminary Design)

7. Detailed Design/Final

Design (100%); Checklist

No.1 and Checklist No.10

(Design Drawings), Checklist

No.7 (Updated Approval in

Principle), Checklist No.9

(Detailed Design/Final Design)

Utilities

8. Conceptual Design Stage

(20%); Checklist No.1 and

Checklist No.11 (Design

Concept Report)

9. Preliminary Design Stage

(30%); Complete Design –

Checklist No.1, Checklist

No.12 (Preliminary Design

Report) and Checklist No.13

(Drawings)

10. Detailed Design/Final Design

(50%); Complete Design –

Checklist No.1, Checklist

No.12 and Checklist No.13

These checklists are meant to

be used as guides and are not

all-inclusive. Their purpose is to

provide a minimum acceptable

list of items that are to be

independently reviewed prior to

submittal; the consultant may

propose additional items to be

checked in the development of

the design for approval. With the

completion of each design stage,

the consultant is required to make

a formal presentation to ADM,

describing the work completed and

the details of the design itself.

All checklist forms can be found

in the appendices. Checklist No.1

details the plans to be submitted

at each stage. It should be

seen as a guide for consultants,

although the ADM project

manager or reviewer may request

additional drawings at any stage.

Consultants are not required to

submit a complete set of drawings

at every stage, but rather only to

submit those required by ADM for

the particular design stage.

Design Review Checklists should

be used for all stages of the design

process, as follows:

Roads

1. Pre-Study Stage (10%)

2. Conceptual Design Stage

(30%); Checklist No.1,

Checklist No.2 (Design

Concept Report)

3. Preliminary Design Stage

(60%); Checklist No.1,

Checklist No.3 (Preliminary

Design Report), Checklist

No.4 and Checklist No.5

(All Drawings)

4. Detailed Design/Final Design

(100%); Checklist No.1,

Checklist No.4 and Checklist

No.5

1.5 Submittals for Roads, Structures & Utilities

2. QUALITY CONTROL

PLAN

18

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

2.0 Quality Control Plan

Consultants bear full responsibility for the accuracy, completeness, consistency and uniformity of their plans, calculations, and related documents furnished under the scope of services. To help ensure that accuracy and completeness, ADM requires consultants to implement and follow a quality control plan.

A meaningful quality control plan must be in place before design work begins, and must remain in effect throughout the duration of the design contract. At a minimum, a functional quality control plan establishes processes to ensure the following:

• All final plans and calculations are checked, back-checked, verified and approved. Checking should be done independently by a second party. The assessor must be an experienced engineer who has not participated in the production of the design plans. Check prints of all drawings and calculations are to be maintained for a minimum of seven years from the completion of a design contract.

• All related correspondence and memoranda are received by authorised persons and maintained in the project files within an established document control system.

• Cross-checking has been carried out to avoid any mismatch and/or discrepancy between the documents (e.g. profiles match plans, drawings match specifications and BOQ, etc.).

• Overall appearance, format and content of the deliverables correspond to the expectations of ADM.

The consultant is expected to perform an internal quality control review of deliverables at all stages of design completion. These reviews are to be carried out by experienced engineers in the relevant disciplines. The purpose of these reviews is to satisfy the consultant that deliverables are of a quality that is acceptable to ADM and to the consultant itself. ADM may request that the consultant update its quality control plan at any stage of the design process, in order to enhance its functionality.

3. CONSULTANT EVALUATION

22

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

3.1 Introduction

To monitor the quality of

deliverables prepared by

consulting firms and to

evaluate the performance

of consultants at each

design stage, ADM project

managers must complete

consultant evaluation

forms, and provide a

copy of each evaluation

to the consultant for their

records and necessary

corrective actions.

The consultant has the right to

question any or all of the ratings.

The results of evaluations will be

referenced by ADM when selecting

consultants for future projects.

24

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

3.2 Design Submittal Evaluation

The blank Consultant Evaluation

Form (Form 3) must be attached

to all submittals of plans and/or

reports to be reviewed.

ADM project managers use this

form when a consultant makes a

submittal. He must complete the

general project information and the

coordination team rating items. On

the middle left of the evaluation

form, the project manager indicates

the type of plans and/or reports that

have been submitted. Items to be

rated are located on the right of the

evaluation form. The ADM reviewer

rates the items found in the middle

right, under “ADM Reviewer’s

Rating Items”.

The rating to be used is found at

the lower right of the evaluation

form. At the very bottom of

the form is the final area to be

completed by the reviewer. In this

area, the reviewer can indicate

what plans and/or reports are to be

submitted next. The last line on the

form is for the reviewer to sign and

date the completed evaluation.

26

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

3.3 Rating Definitions

The review of each submittal will

be performed by ADM, providing

the consultant with a clear

understanding of how the quality

of work is being perceived by ADM

as the project progresses. The

review of completed evaluations

is extremely important to the

consultant’s project manager

because the evaluation reflects

the comments within the reviewed

plans and/or reports. If the

consultant has any questions

regarding the given rating, the

ADM reviewer must answer these

questions.

The ratings range from a high

of 5 to a low of 1. A rating of

3, 2, or 1 indicates that the

reviewer assessed the item under

consideration as not satisfactory.

The general interpretations of the

ratings are as follows:

5. Excellent: Consultant performed beyond expectations; submittal approved with very minor comments.

4. Good: Several revisions required; submittal approved with comments to be incorporated in next stage.

3. Average: Many revisions required, mostly minor but several major comments; submittal returned for revision and resubmittal.

2. Poor: Many major comments; submittal not accepted.

1. Unsatisfactory: Full of mistakes and major comments, poor document quality; submittal not accepted and returned to consultant with notice of concern from ADM.

28

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

29

4. Plan/Report Quality: All

material submitted at each

stage of development, such as

plans, Design Summary Report

(DSR), design computations,

special provisions, and any

other supporting material, will

be evaluated. Ratings will be

based on presentation, legibility,

structure and print quality.

5. Engineering Judgement: The

rating of this item is subjective

to the evaluator. If it is felt that

good or poor judgement was

used, this will be reflected in

the given rating. Engineering

Judgement will be evaluated

for areas such as value

engineering, rehabilitation

options, project constructability,

selection of construction

materials, and maintenance of

traffic scheme.

6. Documentation of Work:

This item will be rated based

on how well each design

decision is documented, or if

the decisions were documented

at all. The majority of the

documentation will be found in

the Design Summary Report,

but documentation may also be

found elsewhere.

7. Procedure/Standard

Compliance: This category

will evaluate how well the

consultant is familiar with local

policies, and will consider

how well the consultant uses

the available standards and

guidelines, as well as whether

the standards and guidelines

were effectively implemented

in the design. This category

will also evaluate how well the

consultant follows established

procedures for specific

items, including foundation

reviews, final plans submittal

memorandum to the Contract

Section, etc.

8. Quality Assurance: The ADM

reviewer will rate this category

based upon the consultant’s

compliance with the Quality

Assurance Guidelines. Design

computations should be

initialled by both the design

engineer and a second

engineer, who has reviewed

the design engineer’s work.

This item rating is intended to

monitor how well the consultant

has performed the evaluation of

checks and balances required

for quality assurance, including

the submittal of the Quality

Assurance Evaluation Form.

9. Cooperation: This rating

is based on how well the

consultant cooperates with

the ADM reviewer when

changes are required and

requested. Willingness to attend

meetings, timely response

to ADM’s queries, and ease

of participation for project

development will also be

reflected in this category.

Form 3 illustrates the items to be

evaluated at each project stage.

The following briefly describes

each item:

1. Design Concept: The

consultant’s submittal will be

evaluated on the completeness

of the proposed design concept.

The term completeness

encompasses how well the

consultant has thought through

all of the necessary factors that

result in the best possible design.

If certain items omitted from the

design concept are detrimental to

the design, a lower rating will be

issued. The evaluation will also

consider how well the consultant

addressed any encountered

obstacle that was not foreseen

at the time of completion of the

Engineer’s Report.

2. Critical Design Elements:

Failure to satisfactorily address

all applicable design criteria will

result in a rating no higher than 3.

3. Calculations: The operations

of mathematical computations

and deletions and/or additions

to the computations are

areas of scrutiny. With the

implementation of the Quality

Assurance Program, how

well the computations were

executed will not be examined

as thoroughly as in the past.

However, spot-checking will

occur and the rating of this item

will reflect the spot-checking.

The scoring will be as follows:

a. A major error is defined as

an error originating from the

computations that would result

in a significant design change.

b. A minor error is one that would

pose no significant change to

any element of the design. If

computations are not submitted

because of the nature of the

submittal or because they are not

warranted, this item will not be

rated. If the reviewer believes that

some computations were needed

but failed to be submitted, the

reviewer will not rate this category

on this basis alone; this would be

addressed in the Documentation

of Work item, thereby avoiding

double penalties.

3.4 How ADM Reviewers Evaluate Submittals

APPENDIX

32

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

33

Form 1Quality Assurance Form

Form 2Design Completion Certificates

ADM Quality Assurance Form(Consultant to complete this section)

Consultant:

Project No.:

Project Description:

Submittal Stage:

This submittal has been reviewed with regard to consistency, completeness, and overall content prior to

submittal by , Project Manager, on _ , 2011, telephone number __________

(Reviewer to complete this section)

The submittal described above has been reviewed for quality in accordance with ADM Quality Control and

Quality Assurance Procedures

The consultant is responsible for checking all of their work as outlined in ADM Quality Control and Quality

Assurance Procedures. The table shown below indicates which of the reviewer’s personnel has reviewed

which checklist.

Checklist No. Designer Reviewer Approved By Date

Please insert the following as part of the submission:

Design Revision Log

NOC’s Status

Design Certificate

Form of Certificate to be used by the Designer for certifying the design of the Works in accordance with the

Client’s requirements.

WE CERTIFY THAT -

1. We have used reasonable professional skill and care in preparation of the Design Data for ………. Design listed below which:

(a) Satisfy the Employer’s Requirements, the Contractor’s Proposals, and the following:(List, if any, the changes covered by any Change Certificate received and countersigned by the Employer’s Agent); and

(b) Comply with the design requirements of the Contract; and

2. We have used reasonable professional skill and care in translating the Design Data into safe design and drawings whose unique numbers is listed below.

3. The Design Data where used as part of the Temporary Works will have no adverse effect on the Permanent Works; and

4. Where required a Safety Audit Certificate for Stage *[2] *[3] is attached.

LIST OF DESIGN DATADesigner Name: ............................………………........…Signed: ..........................…………………........ Date: ...........................……………….......….

Verifier Name: ............................………………........…Signed: ..........................…………………........ Date: ............................……………….......….

Project Manager/ ApproverName: ............................………………........…Signed: ..........................…………………........ Date: ...........................……………….......….

34

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

Form 3Consultant Evaluation Form

Project No.: Contract: Location:

Work Type:

Consultant:

Consultant Project Manager:

Description:

Submittal Stage:

Reviewer’s Rating Items Score

Design Concept __

Critical Design Elements __

Calculations __

Plan/Report Quality __

Value Engineering / Engineering Judgment __

Documentation of Work __

Procedure Compliance __

Quality Assurance __

Scheduling / Cooperation __

Included With This Submittals Are:

Markups of:

Computations: __

Cost Estimate: __

Quantities: __

Q.A. Form: __

Other: Remarks

ADM Reviewer’s Signature: Date:

ADM Reviewer’s Printed Name and Phone Number

5 = Excellent 4 = Good 3 = Marginal 2 = Poor 1 = unsatisfactory

36

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

37

2.0 STRUCTURAL

2.1 S0 – List of Drawings X X X

2.2 S1 – General and Design Notes X X X

2.3 S2 – Site Location and Bore Holes Location Plans X X X

2.4 S3 – General Arrangement Drawings X X X

2.5 S4 – Dimensional Details X X

2.6 S5 – Bearings and Expansion Joints Details X X

2.7 S6 – Reinforcement and Post Tensioning Details X

2.8 S7 – Miscellaneous Details X X X

3.0 UTILITIES

3.1 U1 – Existing Condition X X X

3.2 U2 – Utility Plans X X X

3.3 U3 – Service Reservations and Duct Plans X X X

3.4U4 – Miscellaneous Utilities Details, Compliance with ADM and other stakeholders’(i.e. UPC, DOT, PRFD, etc.) guidelines and criteria are specified

X

3.1 ELECTRICAL

3..1.1E1 - Electrical, Lighting, / CCTV Plan , Scada System and Lightning Protection if it is required.

X X X

3.1.2 E2 - Decorative Lighting or not decorative Plan X X X

3.1.2 E3 - Lighting Plan for Miscellaneous Roadway Structures X X X

3.1.3 E4 - Lighting Plan for Miscellaneous Other Facilities X X

3.2 MECHANICAL

3.2.1 M1 - Mechanical Services for Pedestrian Underpass, Bridges X X X

3.2.2M2 - Mechanical Services for Stormwater, Fountains and Fire Protection

X X X

3.2.3M3 - Mechanical Services for Miscellaneous Facilities and Scada System

X X

ChecklistsChecklist No. 1 – Plans to be submitted at Each Stage

Item No

Drawings to be submitted Conceptual

Design StagePreliminary

Design StageDetailed/ Final Design Stage

1.0 CIVIL

1.1 G1- Location Plan X X X

1.2 G2 – List of Drawings X X X

1.3 C1 – Typical Cross Sections X X X

1.4 C2 - Existing Conditions X X X

1.5 C3 – General Plan and Profiles X X X

1.6 C4 – Design Detail Plans X

1.7 C5 – Grading Plans X

1.8 C6 – Proposed Plans X X X

1.9C7 – Survey Control and Alignment

PlansX X

1.10 C8 – Ramp Terminal Details X

1.11C9 – Maintenance of Traffic and

Construction StagingX X

1.12C10 – Traffic Control Devices – Signs

and Pavement MarkingsX X

1.13 C11 – Miscellaneous Details X

38

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

39

ChecklistsChecklist No.2 - CIVIL – (Conceptual Design Stage)

Item No Document Type:Design Concept Report

(DCR) and Alternative Design Concepts

Item to be Checked Y N N/A Remarks

1 The scope of work is clearly defined

2 All applicable codes and standards are specified

3Compliance with ADM and other stakeholders’(i.e. UPC, DOT, PRFD, etc.) guidelines and criteria are specified

4

Survey and geotechnical investigation requirements and methods are defined (i.e. coordinate system, datum, benchmarks, soil investigation requirements for compaction and structures)

5 Existing site data

6Roadway classifications, design vehicle, design/posted speed are specified.

7Horizontal curve radius, normal cross slope, maximum super elevation (SE), SE transition, curve widening requirements are specified

8Typical cross section details; lane width, number of lanes, shoulder width, sidewalk and median widths, landscape zone and bikeway dimensions (if applicable), parking dimensions

9 Horizontal and vertical sight distance computation

Item No Document Type:Design Concept Report

(DCR) and Alternative Design Concepts

Item to be Checked Y N N/A Remarks

10 Vertical grades, K values, vertical clearance are specified

11 DOT’s circular for parking demand rates

12 Kerb/barrier parameters and clear zone are specified

13Bus/taxi stop requirements, geometric details and proposed locations

14 Tram routes and dimensions (if applicable)

15 Roundabout geometric details (if applicable)

16Interchange alternatives (if applicable); pros and cons of each alternative, interchange spacing, ramp terminal computation, etc.

17 Pavement design parameters and formula

40

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

41

ChecklistsChecklist No.3 – CIVIL – (Preliminary Design Stage)

ChecklistsChecklist No.4 – CIVIL (For all stages)

Item No

Document Type:Preliminary Design

Report (PDR)

Item to be Checked Y N N/A Remarks

1 NOI’s (Notice of Intent) sent to consultants and authorities

2Liaison with the other stakeholders; minutes of coordination meetings held, design review log, critical issues, etc.

3Detailed Site Data; survey and investigation results, and information received from consultants and agencies. In depth analysis of the data.

4Traffic Impact Study (TIS) report and findings; average daily traffic (ADT), existing and proposed traffic circulation, parking demand/supply, existing and proposed pedestrian and bike paths, access/egress details, weaving analysis, etc.

5 Detailed cross sections (including existing and proposed service corridors)

6 Design progress report on the selected alternative by the Department

7 Approval of ADM and/or other stakeholders for the design items departing from standards

8Feasibility Study (FS) - Preliminary engineering calculations according to FS IRI ADM requirements.

9 Value Engineering (VE) proposals including MEP Services

10Constructability issues and solutions (i.e. excavation limits for tunnels, availability of detour areas, existing utility constraints, etc.) based on IRI ADM Sustainability Guideline

11Proposed location of critical utilities and structures (i.e. substations, pump stations…etc), and coordination with relevant agencies

12 Proposed guide sign locations and destination names (if applicable)

13 Cost Estimate

Item No

Document Type: All Drawings

Item to be Checked Y N N/A Remarks

1 Correctness of line weights, lettering sizes, and style

2 Correctness spelling, punctuation, and grammar

3 Details are clear and easy to read

4Title block has correct formats; project name and number, Department name, consultant name, signature boxes (design/review/approve), drawing title and number

5 Drawing title and number is consistent with the “List of Drawings”

6Consistency of project title and identification with specifications, the Bill of Quantities, and other Contract Documents

7 North arrow, street names, sector names, plot numbers, directions are shown

8 Location map (if needed) is accurate and proper area is highlighted

9Legend is included (if needed) and representing the elements on the drawing (i.e. no unnecessary legend)

10 Notes referring to standards and/or other drawings are accurate

11 Match lines are consistent with referenced drawings

12 Drawing is on accurate coordinate system; Northing and Easting gridlines are accurate

13 Limit of construction (LOC) is shown

14 Symbols and abbreviations are matching with the typical details

42

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

43

ChecklistsChecklist No.5 – CIVIL (for all stages)

Item No

Document Type:Drawings Specific to Each

Discipline

Item to be Checked Y N N/A Remarks

1.0 G1 – Location Plan

1.1 Scale is correct (as per ADM Consultant Procedure Manual)

1.2Existing and future developments in the vicinity of the project is shown

1.3 Traffic directions and destinations are shown

2.0 G2 – List of Drawings

2.1Drawing sequence, numbering and titles are as per ADM Consultant Procedure Manual

2.2Drawing number and title shown in the list is consistent with the information on the drawings

2.3 Amendments are shown (i.e. addendum, revision, deletion)

3.0 C1 – Typical Cross Sections

3.1All typical sections in the project are shown; check the cross section against the plan view

3.2 Typical section is as per the approved design criteria

Item No

Document Type:Drawings Specific to Each

Discipline

Item to be Checked Y N N/A Remarks

3.3Pavement section is designed as per the pavement calculation which is reviewed and approved by the Department

3.4Kerbs, barriers, pavement type, geometric details, cross slope/SE, definitions (i.e.lane, aux. Lane, median, shoulder, sidewalk, landscape, SR,etc.), centerline are properly shown.

3.5The limits (from/to station) should represent the correct typical section, any transition section should be shown seperately; check the stationing against the proposed plans

3.6 Side slopes, toe/top of slope are shown

3.7 Limit of construction, plot/building lines are shown

3.8The section contains the proposed improvement and removal of existing features; identifies all payment items

4.0 C2 – Existing Conditions

4.1 Existing centreline and road names are shown

4.2 Existing service reservation and surface utility features are shown

4.3Existing buildings/plots, trees, and other structures (i.e. seawall, bridge, etc.) are shown

4.4 Existing traffic directions/circulation and destinations are shown

44

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

45

ChecklistsChecklist No.5 – CIVIL (for all stages)

Item No

Document Type:Drawings Specific to Each

Discipline

Item to be Checked Y N N/A Remarks

5.0 C3 – General Plan and Profiles

5.1 All roadway paving types are hatched on the plan

5.2 Paving types are matching with the typical cross sections

5.3Service reservation (existing to remain and proposed) is shown on the plan

5.4 Kerb/barrier types are shown on the plan

5.5Existing and proposed structures (i.e. bridges, wingwalls, outfall structure, lifting station, etc.) are shown on the plan

5.6Cross section locations to be shown on the plan and shall be consistent with C1 series drawings

5.7All removals are shown on the plan, and materials to be salvaged are covered by notes or specifications

5.8 Check existing ground elevations against the survey data

5.9Vertical alignment calculations are as per the approved design criteria; i.e. minimum grade for proper drainage, K values, cross slope and superelevation, vertical sight distance, etc.

5.10Compare vertical alignment data against calculations and design software output

Item No

Document Type:Drawings Specific to Each

Discipline

Item to be Checked Y N N/A Remarks

5.11Structures (i.e. bridges, tunnels, walls) and major utilities (i.e. pipelines, power lines) are shown on profile with the vertical clearance information

5.12Locations of crossing and intersecting roads shown on the profile and proposed elevations are matching with crossing and intersecting roads’ elevations

6.0 C4 – Design Detail Plans

6.1 Project specific details as required by the Department

7.0 C5 – Grading Plans

7.1Grading plans prepared for all intersections and merging/diverging roads; i.e. roundabouts, signalized/unsignalized intersections, T-junctions, ramp terminals, etc.

7.2 Grading plan is matching with the profile(s) and typical section

7.3Roadway drainage is properly maintained with the proposed grading plan

7.4Finish-grade elevations are specified at 10 -meter intervals at the roadway centerline, curb lines, and at geometric break points. The intervals shall be reduced as needed.

7.5Grading plans for roundabouts are as per AASHTO and other international desing guidelines for roundabouts

8.0 C6 – Proposed Plans

46

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

47

ChecklistsChecklist No.5 – CIVIL (for all stages)

Item No

Document Type:Drawings Specific to

Each Discipline

Item to be Checked Y N N/A Remarks

8.1Centerline / reference line information is shown (i.e. centerline name, stationing every 100m, POB/POE, CT/TC/CTC, any stationing equation)

8.2All dimensions are shown; widths, radius, tapers, transitions, island nose locations (Station/Offset), begin/end kerbs and barriers, etc.

8.3All geometric details are as per the approved design criteria by the Department

8.4 Traffic circulation/directions are shown

8.5 Service reservation corridor is shown

8.6Location of structures (i.e. bridges, tunnels, walls) and major utilities (i.e. pipelines, power lines) are shown

8.7 Work to be done by others is properly annotated

8.8 Limits of construction cover entire area of construction

9.0 C7 – Survey Control and Alignment Plans

9.1All control points are approved by ADM/TPD, and checked/verified by the Consultant by setting up traverse

9.2Coordinate system and datum are as per the approved design criteria by the Department

Item No

Document Type:Drawings Specific to

Each Discipline

Item to be Checked Y N N/A Remarks

9.3Horizontal alignment calculations and data are as per the approved design criteria by the Department

9.4Alignment calculations and design software output is matching with the alignment data on the drawings

9.5Alignment data and curve data information is matching with the geometry on the plan

9.6 Horizontal sight distance is checked

9.7 Numbering for alignment points and curves to sequential and not repeated

10.0 C8 – Ramp Terminal Details

10.1Exit and entrance ramp terminal details (acceleration/deceleration length, auxiliary lane, taper lengths, weaving distance) are as per the approved design criteria by the Department and other international standards (i.e.AASHTO)

10.2Ramp terminal geometry is matching with the horizontal alignment data (i.e. no kinks or mismatch coordinates)

11.0 C9 – Maintenance of Traffic and Construction Staging

11.1 Check constructability of the project with the proposed detour

11.2Maintenance of traffic and construction staging has been reviewed and coordinated with the other stakeholders (AD Traffic Police, DOT, utility agencies), and verify any necessary permits and licenses have been obtained

48

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

49

ChecklistsChecklist No.5 – CIVIL (for all stages)

Item No

Document Type:Drawings Specific to

Each Discipline

Item to be Checked Y N N/A Remarks

11.3Access to sectors, plots, pedestrian paths have been maintained at all times during construction

11.4 Alternative routes proposed for the drivers with adequate signage

11.5 Transition between construction stages is adequately addressed

11.6All temporary works are properly labelled as such and that descriptions match the pay items

11.7Safety has been considered by all means; i.e. proper lane drops, proper signage and marking, additional traffic control devices such as crush cushions and portable VMS (variable message signs) have been proposed

12.0 C10 – Traffic Control Devices – Signs and Pavement Markings

12.1Traffic signs and pavement markings are as per ADM’s Traffic Control Devices Manual and approved design criteria by the Department (i.e. all signs and markings are as per the approved design speeds and roadway classifications)

Item No

Document Type:Drawings Specific to

Each Discipline

Item to be Checked Y N N/A Remarks

12.2Existing structures and utilities are considered while locating the proposed signs in order to avoid any obstruction to signs.

12.3 Pedestrian walkways and bikeways are not interrupted by the signs

12.4Proposed pavement marking is tieing in with the existing pavement marking properly (i.e. no kinks, no sudden change in width and type)

12.5Signs and pavement markings has been reviewed and coordinated with the other stakeholders (AD Traffic Police, DOT)

12.6Safety has been considered by all means; i.e. proper lane drops, proper signage and marking, additional traffic control devices such as crush cushions, etc.

13.0 C11 – Miscellaneous Details

13.1 Project specific details as required by the Department

50

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

51

ChecklistsChecklist No.6 – Structures (Concept Design Stage)

Item No

Document Type: Concept Design Stage

Item to be Checked Y N N/A Remarks

1.0 General

1.1 ADM Structural Design Guidelines Adopted

1.2 Applicable Codes and Standards Adopted

1.3 Purpose/Function of the Structure Identified

1.4 ADM IRI Sustainability Guideline

2.0 Roadway Design Features

2.1Horizontal Clearances, Vertical Clearances. Existing Restrictions, Typical Cross Sections etc. considered

3.0 Geotechnical Investigation

3.1 Available Information and Recommendations

4.0 Selection of Structural Elements

4.1 Span Arrangement

Item No

Document Type: Concept Design Stage

Item to be Checked Y N N/A Remarks

4.2 Typical Cross Section

4.3 Initial Dimensions

4.4 Type of Hand/ Traffic Railing

4.5 Type of Superstructure

4.6 Articulation Arrangement /Type of Bearings/Type of Expansion Joints

4.7 Type of Abutment, Pier, Foundation

4.8 Type of Retaining wall

4.9 Signage Structures

4.10 Protection Structures

4.11 Other Structures

5.0 Selection of Materials

52

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

53

ChecklistsChecklist No.6 – Structures (Concept Design Stage)

Item No

Document Type: Concept Design Stage

Item to be Checked Y N N/A Remarks

5.1 Concrete, Reinforcement Steel, Pre stressing Steel, Structural Steel

6.0 Design Considerations

6.1 Design Specifications

6.2 Service Life

6.3 Durability Considerations

6.4 Analysis and Design Methodology

6.5 Construction Sequence

6.6Operational Considerations Crack Sensitivity (Gas Tightness/Liquid Retaining) Vibration, Wind and Fire Sensitivity

6.7 Permanent Loads

6.8 Live Loads

6.9 Other Loads

6.10 Deflection/Camber (Vertical/Incremental/Lateral)

7.0 Other Considerations

7.1 Structure Drainage and Stormwater Systems

7.2Lighting System over and under Structure Compliance with ADM and other stakeholders’(i.e. UPC, DOT, PRFD, etc.) guidelines and criteria are specified

7.3Existing Site Condition/ Constructability and IRI ADM Sustainability Guideline

7.4 Proposed Arrangements for Maintenance and Inspection

7.5 Utilities Carried through or Affected by the Structure

7.6Environmental & IRI ADM Sustainability Guideline & Environmental &Considerations

7.7 Risk and Hazards Considerations

7.8 Execution of Work, Traffic Management and Utilities Diversion

7.9 Coordination with all Concerned Authorities and Any Special Conditions

7.10 Time (Design, Coordination and Execution)

7.11 Cost (Initial, Final and Maintenance)

54

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

55

ChecklistsChecklist No.7 – Structures (Approval in Principle Report)

Item No

Document Type:Approval in

Principle (AIP)

Item to be Checked Y N N/A Remarks

1.0 General

1.1 ADM Structural Design Guidelines

1.2 Applicable Codes and Standards and Other References

1.3 Design Verification Process

2.0 Architectural/ Aesthetics

2.1 Overall Scheme

2.2Pedestrian/ Traffic Railing, Pier, Abutment, Retaining Wall, Movement Joints, Drainage System etc.

3.0 Roadway Design Features

3.1 Proposed Horizontal and Vertical Clearances and Existing Restrictions

3.2Proposed Geometric Design (Typical Cross Sections, Type of Road, Permitted Speed etc.)

4.0 Geotechnical Information

Item No

Document Type:Approval in

Principle (AIP)

Item to be Checked Y N N/A Remarks

4.1 Available Information

4.2 Acceptance of Recommendations of the Geotechnical Report

5.0 Description of Structure

5.1 Pedestrian/ Traffic Railing

5.2 Superstructure

5.3 Sub Structure

5.4 Articulation Arrangement

5.5 Foundation

5.6 Others

6.0 Materials

6.1 Concrete

56

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

57

ChecklistsChecklist No.7 – Structures (Approval in Principle Report)

Item No

Document Type:Approval in

Principle (AIP)

Item to be Checked Y N N/A Remarks

6.2 Reinforcement

6.3 Pre-stressing Strands

6.4 Structural Steel

7.0 Durability Considerations

7.1 Concrete Strength/ Steel grade

7.2 Minimum Concrete Cover

7.3 Concrete Crack Control

7.4 Concrete and Steel work protection

7.5 Concrete Surface Finish

7.6 Waterproofing

7.7 Other Durability Considerations

Item No

Document Type:Approval in

Principle (AIP)

Item to be Checked Y N N/A Remarks

8.0 Structural Design

8.1 Design Specifications

8.2 Service Life

8.3 Structural Analysis and design Methodology

8.4 Construction Methodology

8.5Operational Considerations Crack Sensitivity (Gas tightness/Liquid and retaining) Vibration, Wind and Fire Sensitivity

8.6 Load Modifier, Load Factor , Resistance Factors etc.

8.7 Permanent Loads

8.8 Dead Load

8.9 Superimposed Load

8.10 Utilities Load

58

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

59

ChecklistsChecklist No.7 – Structures (Approval in Principle Report)

Item No

Document Type:Approval in

Principle (AIP)

Item to be Checked Y N N/A Remarks

8.11 Live Loads

8.12 Pedestrian Live Load

8.13 Vehicular Live Load including Dynamic, Centrifugal and Braking Effects

8.14 Exceptional Abnormal Load

8.15 Rail Transit Load

8.16 Live Load Surcharge

8.17 Vehicular Collision Load

8.18 Earth Load

8.19 Earth Fill

8.20 Earth Pressure (Earth pressure coefficients)

8.21 Water Load/ Uplift Load

Item No

Document Type:Approval in

Principle (AIP)

Item to be Checked Y N N/A Remarks

8.22 Temperature, Shrinkage, Settlement

8.23 Friction Force

8.24 Vessel Collision Load

8.25 Other Loads

8.26 Wind load

8.27 Earthquake load

8.28 Fatigue

8.29 Plant and equipment load

8.30 Construction Load

8.31 Any Special loading not covered above

8.32 Deflection/ Camber (Vertical/incremental/Lateral)

60

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

61

ChecklistsChecklist No.7 – Structures (Approval in Principle Report)

ChecklistsChecklist No.8 – Structures (Preliminary Design Stage)

Item No

Document Type:Approval in

Principle (AIP)

Item to be Checked Y N N/A Remarks

9.0 Other Considerations

9.1Structure Drainage System Compliance with ADM and other stakeholders’ (i.e. UPC, DOT, PRFD, etc.) guidelines and criteria are specified

9.2Lighting system on and under structure Compliance with ADM and other stakeholders’(i.e. UPC, DOT, PRFD, etc.) guidelines and criteria are specified

9.3 Farthing and Stray Currents requirements

9.4 Existing Site Condition

9.5 Proposed arrangements for Maintenance and Inspection

9.6Utilities Carried Through or Affected by the Structure Compliance with ADM and other stakeholders’(i.e. UPC, DOT, PRFD, etc.) guidelines and criteria are specified

9.7 Environmental & IRI ADM Sustainability Guideline considerations

9.8 Risk and Hazards considerations

9.9 Execution of work, Traffic Management and Utilities Diversion

9.10 Coordination with all Concerned Authorities and any Special Conditions

Item No

Document Type:Preliminary Design

Stage

Item to be Checked Y N N/A Remarks

1 Updated Approval in Principle (AIP) Report

2 Compliance of AIP to the Preliminary Design

3 Architectural Plans

4 Applicable Roadway/ Utilities Design Plans

5 Structural Design Drawings

6 Structural Design Calculations

7 Geotechnical Report

8 Bill of Quantities

9 Construction Specifications

10 Design Verification Report

62

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

63

ChecklistsChecklist No.9 – Structures (Detailed Design/Final Design Stage)

Item No

Document Type:Detailed/ Final Design Stage

Item to be Checked Y N N/A Remarks

1 Final Approval in Principle (AIP) Report

2 Durability Report

3 Compliance of AIP to the Final Design

4 Final Architectural Plans

5 Final Applicable Roadway/ Utilities Design Plans

6 Final Structural Design Drawings

7 Final Structural Design Calculations

8 Final Geotechnical Report

9 Bill of Quantities

10 Construction Specifications

11 Design Verification Report

12 Any Other Relevant Details not Stated Above

ChecklistsChecklist No.10 – Structural Drawings for all Stages

Item No

Document Type:Drawings Specific to

Each Discipline

Item to be Checked Y N N/A Remarks

1.0 S0 – List of Drawings

2.0 S1 – General and Design Notes

2.1Design criteria, necessary information and assumptions to develop design drawings.

2.2Notes common to all structures such as design code, basic loading values, surface finish etc.

2.3Notes specific to a particular structure e.g. bridges, underpass, concrete structures, steel structures etc. as applicable.

2.4Unless otherwise covered above, each drawing may have specific notes related to that particular drawing.

3.0 S2 – Site Location and Bore Holes Location Plans

3.1 Project location, existing and future developments in the vicinity of the project.

3.2 Project location Plan

3.3 Existing site conditions and bore holes location Plans.

3.4Proposed Structure location with project key plan highlighting structure location including.

64

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

65

ChecklistsChecklist No.10 – Structural Drawings for all Stages

ChecklistsChecklist No.10 – Structural Drawings for all Stages

Item No

Document Type:Drawings Specific to

Each Discipline

Item to be Checked Y N N/A Remarks

4.0 S3 – General Arrangement Drawings

4.1 Architectural drawings

4.2Structure plan, elevation and typical cross sections showing Span arrangement and types of structural elements.

4.3 Setting out details, key levels, Clearance envelope, and radius of curves*

4.4 Bore holes location and bore log details.*

4.5Existing/ proposed utilities crossing or affecting structures, deck drainage, lightings and other necessary features.

4.6 Construction sequence

5.0 S4 – Dimensional Details*

5.1 Foundation including footing and pile caps

5.2 Substructure elements

5.3 Superstructure elements

5.4 Box structures

5.5 Retaining walls

5.6 Other Structures

6.0 S5 – Bearings & Expansion joints Details*

Item No

Document Type:Drawings Specific to

Each Discipline

Item to be Checked Y N N/A Remarks

7.0 S6 – Reinforcement and Post tensioning Details*

7.1 Foundation including footing and pile caps

7.2 Substructure elements

7.3 Superstructure elements

7.4 Box structures

7.5 Retaining walls

7.6 Other Structures

7.7 Bar cutting and bending schedules

8.0 S7 – Miscellaneous Details

8.1 Waterproofing.

8.2 Joints.

8.3 Drainage and structure lightings.

8.4 Wearing course. Curbs, Sidewalks, and pedestrian and traffic railings.

8.5 Surface protection.

8.6 Other necessary details.

*Not required for submission of Concept Design stage.

*Except S6, all above drawings are required for submission of Preliminary Design Stage. However

approximate quantities of steel with bar diameter is required for pricing purposes.

* Detailed drawings of S0, S1 to S7 are required for submission of detailed design/ Final Design Stage.

66

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

67

ChecklistsChecklist No.11 – Utilities (For Concept Design Stage)

ChecklistsChecklist No.12 – Utilities (Preliminary Design Stage)

Item No

Document Type: All Drawings

Item to be Checked Y N N/A Remarks

1

Sustainability Strategy: to follow Estidama requirement for 2 Pearl rating for the Building Areas and will implement accordingly in our Design IRI ADM Sustainability Guideline for mentioned areas but not limited because the proposed HVAC (A/C) shall be VRF (VRV) System or equivalent

2 The Parking Garage: to coordinate with CD the Induction Fan system

3Plumbing: design according to the last version of ADM implemented standard for materials.

4All temporary works are properly labelled as such and that descriptions match the pay items

4

Electrical Systems based on :

a- Electrical Power: A breakdown (calculations) required for Total Load of the project such as electrical power and LED Lighting or equivalent using ADM Specification and Standard.

b- CCTV and Security ( control access)Systems will be provided

c- Elevators (Elec. Or Hyd.)

d- Fire Alarm System

e- Scada System

f- Lightning Protection if it is required.

More over, study the possibility to provide gas line .

Item No

Document Type: All Drawings

Item to be Checked Y N N/A Remarks

1 Submittal form filled, stamped & singed

2 Letter from consultant stamped & singed

3 Key plan (show the location of project).

4 Proposed roads layout

5 Existing roads layout

6 Existing roads lighting services.

7 Existing roads lighting poles with mention height and luminaries.

8 Watts and type as per standard legend

9 Existing cable with size and circuits

10 Existing feeder pillar location

11 Existing roads lighting ducts

12 Estimated cost

13 Total proposed roads length.

14 Existing substations location

15 Height of poles (Columns)

16 Pole spacing.

68

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

ChecklistsChecklist No.13 – Utilities (For all stages)

Item No

Document Type: All Drawings

Item to be Checked Y N N/A Remarks

1 Submittal form filled, stamped & singed.

2 Key plan (show the location of project).

3 Four set of color drawing

4 CD digital copy as drawing index layout.

5 Bill of Quantities

6 Existing & proposed substation with location & number

7 DEWA overhead lines (Proposed).

8 Details for DEWA overhead with lighting poles section & profile

9Single line diagram with each circuit load & total load for FP. Voltage drop on each circuitmaximum 4% to be show.

10 Under bridge lighting & design calculation

11 Tunnel lighting drawing & design calculation

12 Roads lighting design calculation

13 Prepare a schedule of work.

14 Copy of Updates/new standards from the Consultant implemented for the designQUALITY CONTROL & QUALITY ASSURANCE PROCEDURES

2011 EDITION