BUILDING CONSTRUCTION 1 ARC 1523PROJECT 1 : DOCUMENTATION AND ANALYSIS PREPARED BY : WONG PEAKKY (1101A13474) 10
First, Excavation
Secondly, commencent of excavation to the desired level
Thirdly, a layer of concrete is laid for a clean and firm base
Fourth, Formwork is prepared
Fifth, placement of spacer block
Sixth, lay the reinforcement main bar
Seventh, add tranverse rebar Seventh, add tranverse rebar
Eighth, erect the reinforcement for stumps
Nineth, add more ties to the formworks
Tenth, lay concrete on to the formwork
Lastly, formwork will be dismantled after the curing of concrete.
Process of Pad Foundation
4.0 FOUNDATION