+ All Categories
Home > Documents > 12 July 92 Doug Cunningham

12 July 92 Doug Cunningham

Date post: 02-Jun-2018
Category:
Upload: gorgogetk
View: 219 times
Download: 0 times
Share this document with a friend

of 22

Transcript
  • 8/10/2019 12 July 92 Doug Cunningham

    1/22

    PRODUCED BY THE ENGINEERING DIRECTORATEOF THE ENERGY NETWORKS ASSOCIATION

    EngineeringRecommendation

    G55/2

    Issue 2- September 2008Safe Tree Working in Proximity to Overhead Electric Lines

    www.energynetworks.org

  • 8/10/2019 12 July 92 Doug Cunningham

    2/22

    2008 Energy Networks Association

    All rights reserved. No part of this publication may be reproduced,

    stored in a retrieval system or transmitted in anyform or by any means, electronic, mechanical, photocopying,recording or otherwise, without the prior written consent of

    Energy Networks Association. Specific enquiries concerning thisdocument should be addressed to:

    Engineering DirectorateEnergy Networks Association

    6th Floor

    Dean Bradley House52 Horseferry Road

    London

    SW1P 2AF

    This document has been prepared for use by members of theEnergy Networks Association to take account of the conditions

    which apply to them. Advice should be taken from an

    appropriately qualified engineer on the suitability of this

    document for any other purpose.

  • 8/10/2019 12 July 92 Doug Cunningham

    3/22

    Engineering Recommendation G55/2

    Page 1 September 2008

    CONTENTS Page

    1 INTRODUCTION 2

    1.1 Purpose 2

    1.2 Background 3

    1.3 Scope 3

    1.4 Basic Principles 3

    1.5 Definitions 4

    2 ADVICE TO THIRD PARTIES 6

    3 MANAGEMENT ACTION FOR NETWORK OPERATOR WORK 6

    3.1 Competence and Authorisation of Persons 6

    3.2 Standards of Arboricultural Work 7

    3.2.1 Planning Stage 7

    3.2.2 Execution Stage 8

    3.2.3 Measure and Correct Stage 8

    4 RISK ASSESSMENT REQUIREMENTS FOR NETWORK OPERATOR WORK 9

    4.1 Generic Risk Assessment Principles 9

    4.2 Site Specific Risk Assessment Principles 9

    5 SAFE EXECUTION OF NETWORK OPERATOR WORK 11

    5.1 Working Within the Proximity Zone 11

    5.2 Work Planning Principles 11

    5.3 Conditions Required for Working with the Line Live 12

    5.4 Categories of Tree Work and Procedures to Control Risk 12

    5.5 Effectively Insulated Conductors 19

    5.6 Use of Machinery 19

    5.7 Tidy-up Operations 19

    5.8 Emergency Procedures 20

    5.9 Performance Monitoring 20

    5.10 Review of Procedures 20

  • 8/10/2019 12 July 92 Doug Cunningham

    4/22

    Engineering Recommendation G55/2

    Page 2 September 2008

    1 INTRODUCTION

    1.1 Purpose

    The purpose of this Engineering Recommendation (ER) is to provide a common basis for

    safe working practices for tree work in Proximityto any Network Operatorsequipment. It

    sets out to differentiate between works carried out by or on behalf of Network Operatorsandworks carried out by third parties not in their employ. The primary focus of this document is

    to provide detailed advice to ENA member companies. Third parties will be steered towards

    existing publications for guidance.

    Where relevant, this ER supports the standards and guidance set out in the following

    publications:

    Electricity at Work Regulations 1989 (EAWR)

    HSE Guidance Booklet HSG 85 Electricity at Work - safe working practices

    The Electricity, Safety, Quality and Continuity Regulations 2002 as amended 2006(ESQCR)

    BS EN 50110 - 1 :1997: Operation of Electrical Installations

    HSE Guidance Booklet HSG 47 Avoiding danger from underground services

    HSE Guidance Note GS6 Avoidance of Danger from Overhead Electric Lines

    Arboriculture and Forestry Advisory Group (AFAG) guide 804 Electricity at Work:

    Forestry and Arboriculture

    ENA ETR 136 (Vegetation Management Near Electricity Equipment - Principles of GoodPractice)

    ENA SHE Standard 04 - G55/1 Live Zone LV Distances

    This ER also provides guidance in the establishment and use of management procedures to

    achieve the safest possible working practices.

    Revision Note

    The ER has been revised to take in to account the development in a maturing vegetation

    management industry and to avoid any confusion in relating to the above documents.

  • 8/10/2019 12 July 92 Doug Cunningham

    5/22

    Engineering Recommendation G55/2

    Page 3 September 2008

    1.2 Background

    Working in Proximityto live overhead electric lines and underground electric cables isresponsible for many incidents every year. These incidents frequently result in the serious

    injury of people, damage to equipment and disruption of electricity supplies. Some of theseincidents are related to tree work in Proximityto live electrical equipment.

    The risk of injury associated with any task may be minimised with a work plan based onrisk assessment, the use of Competentstaff, the provision of suitable equipment and theapplication of safe work procedures. These are the actions that should be taken when preparingto work on trees in Proximityto all types of electrical equipment to ensure that the risk of anincident is minimised.

    Tree work in Proximityto live overhead electric lines and other equipment is subject to theprovisions of the Electricity at Work Regulations (EAWR). This ER sets out to comply with

    these provisions.

    1.3 Scope

    The approach set out in this ER is recommended for all tree work carried out in Proximityto

    any Network Operatorslive electrical equipment.

    The management procedures established by this ER should be applied to work initiated by the

    Network Operator. Any work initiated by Third Partiesshould refer to Section 2.

    Where the staff of any other employers are working in Proximityto live electrical equipmentthen the Network Operatorwill provide guidance to assist those employers to meet theirresponsibilities to provide a safe place of work. For tree work and related activities, theprinciples on which that guidance is to be founded are set down in this ER.

    This ER gives recommendations for tree work with specific regard to the electrical hazard and

    does not seek to give guidance on managing the non-electrical hazards.

    1.4 Basic Principles

    To allow tree work in Proximityto live electrical equipment to be carried out safely it isrecommended that the following principles are followed.

    All tree work is carried out:

    in accordance with this ER

    in accordance with appropriate working procedures established by the NetworkOperatorconcerned

    by appropriately qualified and Competentpersons

  • 8/10/2019 12 July 92 Doug Cunningham

    6/22

    Engineering Recommendation G55/2

    Page 4 September 2008

    1.5 Definitions

    For the purposes of this ER the following definitions will apply:

    Approved A tool including attachments approved by the Network OperatorasInsulated Tool being insulated and fit for purpose to the extent that it may be used in

    close proximity to live electrical equipment without presenting a dangerto the operator or network. The tools must be suitable for the voltagethat they are being used for.

    Circuit Conductor An electrical conductor arranged to be electrically connected to anetwork.

    Competent A suitably trained person, who is recognised as having sufficienttechnical knowledge, experience and ability to enable him or her toavoid danger in respect of the electrical overhead line network; is

    authorised by the Network Operatorand engaged to work on its

    behalf.

    In the case of a tree cutter an example of this would be to have been

    awarded the appropriate NPTC competency certificates and be

    authorised by the Network Operator.

    Effectively A line conductor which is insulated for continuous phase to phaseInsulated or phase to earth contact and is protected, so far as is reasonablyConductor practicable, against mechanical damage or interference having regard

    to its accessibility.

    Note: The implication here is that Effectively Insulated Conductors

    (such as low voltage aerial bundled conductors but not high voltage

    covered conductors) may be placed such that they are ordinarilyaccessible, providing they are safe in the particular circumstances.

    For the purposes of this ER all other conductors shall be treatedas non-insulated.

    Live Zone The zone around an exposed live Circuit Conductoror supporting

    insulators where there is a danger of burn or electric shock if any partof a persons body or non-insulated tool they are using enters the

    Zone. For HV and EHV circuit conductors this is related to the Safety

    Distanceas described by the Network Operator. The distances,

    which depend on voltage, are shown in Table 1.

    Network Operator The organisation that owns and/or operates a distribution networkand is responsible for keeping vegetation clear of overhead lines. A

    Network Operatormight also be referred to as a Distribution NetworkOperator (DNO) or Transmission Systems Operator (TSO).

  • 8/10/2019 12 July 92 Doug Cunningham

    7/22

    Engineering Recommendation G55/2

    Page 5 September 2008

    Proximity Close enough to electrical equipment to present a danger. Depending

    on the type of operation, the definition of Proximityis split in to

    Proximity Zone 1and Proximity Zone 2:

    Proximity Zone 1 In the case of felling works then this includes all trees that are within two

    tree lengths of any live equipment. This will be measured horizontally

    from a point directly beneath the nearest conductor to the base of the

    tree.

    Proximity Zone 2 Includes all trees that are to be dismantled, pruned or have other

    arboricultural work carried out on them that are within:

    9m of any live equipment up to and including 66kV

    15m of any live equipment greater than 66kV

    Note that if there is any doubt about the voltage then the advice of the

    Network Operatorshould be sought.

    This distance will be measured horizontally from a point directly

    beneath the nearest conductor to a point directly under the nearest

    point of the canopy of the tree.

    Where mechanical plant is being used e.g. harvesters or forwarders,

    then the stated distances will be measured to the nearest point to the

    line that any part of the machine or load can reach.

    Third Party A person or organisation that needs to carry out tree works in

    Proximityto a Network Operatorselectrical equipment for their own

    purposes.

    Vicinity Zone The zone around an exposed live Circuit Conductor , which if

    maintained will ensure that the danger of burn or electric shock is

    prevented because the Live Zoneis not breached. The Live Zoneis

    included within the measurement of the Vicinity Zone. The distances,

    which depend on Voltage, are shown in Table 1. (Do not use Working

    and Access Clearances, as described by some Network Operators,

    for the Vicinity Zoneas they have different values.)

    Table 1 Live and Vicinity Zone Distances

    System Voltage Live Zone Vicinity Zone

    Up to and including 1 kV 0.3m* 1m

    Up to and including 11 kV 0.8m 2m

    Up to and including 33 kV 0.8m 2.5m

    Up to and including 66 kV 1.0m 3m

    Up to and including 132 kV 1.4m 3.5m

    Up to and including 275 kV 2.4m 4m

    Up to and including 400 kV 3.1m 5m

    *see reference - ENA SHE Standard 04 - G55 Live ZoneLV Distances

  • 8/10/2019 12 July 92 Doug Cunningham

    8/22

    Engineering Recommendation G55/2

    Page 6 September 2008

    2 ADVICE TO THIRD PARTIES

    Any Third Partynot in the employ of the Network Operatorwishing to carry out tree work in

    Proximity(see Section 1.5, Definitions) to the Network Operatorslive electrical equipment

    should consult the following documents:

    HSE Guidance Note GS6

    Avoidance of Danger from Overhead Electric Lines

    Arboriculture and Forestry Advisory Group (AFAG) Guide 804 Electricity at Work:

    Forestry and arboriculture

    Energy Networks Association Public Safety Leaflet: Safe Tree Working in Proximityto

    Overhead Lines

    These documents will direct the Third Party to consult with the Network Operator before

    proceeding.

    For advice telephone your local Network Operator. The telephone number is in the telephone

    book under Electricity.

    Further guidance on public safety can be found on the Energy Networks Association

    Website:

    http://www.energynetworks.org

    3 MANAGEMENT ACTION FOR NETWORK OPERATOR WORK

    It is recommended that Network Operatorsensure that their procedures meet the requirements

    of this ER. Although it is outside the scope of this ER, it must be remembered that non electrical

    hazards in connection with surveying, gaining consents and clearing vegetation must be

    adequately taken in to account in line with ENA ETR 136 (Vegetation Management Near

    Electricity Equipment - Principles of Good Practice).

    3.1 Competence and Authorisation of Persons

    The Network Operatorshould ensure that all staff involved in tree work in Proximityto

    their overhead lines are Competentfor both tree work and for working in Proximityto their

    electrical network.

    Competence in tree work should be demonstrated through training, assessment and qualification

    under a nationally recognised utility arboricultural training scheme, or the Network Operators

    own tree working training scheme.

    For Network electrical competence the Network Operatorwill ensure that training, assessment

    and authorisation awarded to staff engaged meet the individual Network Operators

    requirements.

    In the light of this revised Engineering Recommendation it is possible that certain certificates of

    competence may not reflect best practice. There may then be a delay until these competency

    units are updated and personnel retrained and reassessed. It will be the responsibility of each

    Network Operatorto ensure that in the interim period they have robust systems in place to

    ensure that personnel are adequately inducted and are deemed to be Competentto carry out

    works in accordance with the best practice outlined in this document.

    Trainees may be involved in site work only when they are subject to appropriate supervision,limitations and control, as determined by the Network Operator. Where trainees are engaged

  • 8/10/2019 12 July 92 Doug Cunningham

    9/22

    Engineering Recommendation G55/2

    Page 7 September 2008

    in works adjacent to power lines then adequate arrangements for their supervision must be

    agreed with the Network Operator. It is recommended that these arrangements be recordedon the site risk assessment with specific reference to:

    the operative(s) being supervised;

    the supervisor(s); and,

    the level of supervision.

    3.2 Standards of Arboricultural Work

    The standards referenced in this section address good practiceprinciples of work associated

    with safe tree work in Proximityto overhead electric lines.

    The key safety management factors that should be applied by the Network Operatormay begrouped within the recognised and accepted management process stages represented as:

    PLAN - EXECUTE - MEASURE - CORRECT

    3.2.1 Planning Stage

    The following should be considered:

    Training and qualification in utility arboriculture practice (as referenced in section 3.1)

    The Network Operator will ensure that where relevant, project planning adopts the principlesof the following Engineering Technical Reports to ensure a safe and effective procedural

    framework for the delivery of site specific requirements:

    ENA ETR 132 (Improving Network Performance Under Abnormal Weather Conditions

    by Use of a Risk Based Approach to Vegetation Management Near Electric OverheadLines)

    ENA ETR 136 (Vegetation Management Near Electricity Equipment - Principles of

    Good Practice)

    Surveys of the assets and associated vegetation to capture the data that will provide the

    information for the risk assessment.

    Vehicle and plant access with regard to the electrical hazard.

    Reference should be made to the geographical and electrical location of the work site.

    Defined asset to vegetation clearance objectives designed to maintain the statutoryclearance requirements.

    Specific methods of delivery such as a system outage or working in Proximityto the liveequipment.

    Site specific public safety risk control procedures; and the delivery and maintenance ofsurvey data to enable compliance with the relevant ESQCR requirements. Record of the

    vegetation condition identified as non compliant will require prioritisation e.g. accessible

    assets via vegetation in a publicly utilised area.

    The asset condition risk and the site environment condition risk assessment are specificto the project location. The information/data recorded will be essential to facilitate safedelivery activities. Example of the items referenced may be asset conductor and fitting

    condition, New Roads and Street Works Acts requirements (traffic management) other

    environmental impact and risk such as water courses.

  • 8/10/2019 12 July 92 Doug Cunningham

    10/22

    Engineering Recommendation G55/2

    Page 8 September 2008

    The vegetative material risk should be assessed specific to the project location. The

    information/data recorded will be essential to facilitate safe delivery activities. Example ofthe items referenced may be species specific regarding projected growth, individual tree

    structure condition, and the consequential risk of the works such as wind blow effect.

    Selection of appropriate plant, equipment and vehicles for the work to be carried out.

    3.2.2 Execution Stage

    During the Execution stage it must be ensured that:

    Critical customer/landowner details enable safe delivery of the planned works e.g. access

    and egress routes.

    Robust site specific planning processes are demonstrated. All the required information willbe collated into a site specific document/file. Sound process will ensure the information is

    clear, concise and relevant. The information will be communicated to those staff associated

    with the physical delivery of the work. Site specific planning will ensure sufficient resourcefor the works. The relevant safety and environmental control information will be shared

    with all customers and stakeholders as necessary to ensure safe working and acceptableconduct.

    Equipment utilised for the delivery and execution of the work is fit for purpose. Items willconform to the basic requirements of being tested, certified, registered and maintained to

    the approved Network Operatorprocedures.

    Guidance on suitable PPE to be worn is given in the AFAG guides relevant to each tree

    related task. In addition the requirements of individual Network Operatorproceduresmust be adhered to.

    3.2.3 Measure and Correct Stage

    During the Measure and Correct stage it must be ensured that:

    Safety event reporting and recording will be sufficiently robust to enable the Network

    Operator to identify all tree related incidents and ensure that they are reported both locally

    and nationally via recognised electricity industry channels.

    Compliance measurement is ensured via audit activity. Checks and assessment are

    recommended regarding:

    Quality of tree work

    Safety practice compliance

    Clearance from vegetation to assets achieved

    Clearance sustainability

    Compliance with environmental constraints

    Customer communication, understanding and satisfaction.

    Processes will be sufficiently flexible to accommodate modification required as a result of

    non compliances identified within the audit check cycle.

  • 8/10/2019 12 July 92 Doug Cunningham

    11/22

    Engineering Recommendation G55/2

    Page 9 September 2008

    4 RISK ASSESSMENT REQUIREMENTS FOR NETWORK OPERATOR WORK

    The Network Operatorshould ensure the principles of Risk Assessment are embedded in the

    process from project conception through to the delivery and execution phase of the work

    The risk assessments will be available to all staff and associated stakeholders (as appropriate)

    involved in the works.

    Network Operatorsshould ensure that a suite of generic risk assessments covering all

    activities involved in this type of work is available to all.

    4.1 Generic Risk Assessment Principles

    The generic risk assessment should include the following (the list is for example and not

    exhaustive):

    Procedures for live working (and its avoidance)

    Working at height (and its avoidance); the provision and use of Mobile Elevating Work

    Platforms (MEWPs), ladders and fall protection equipment.

    Plant and machinery e.g. wood chippers, stump grinders, MEWPs.

    All tools and equipment to be used should be agreed with the Network Operator.

    All tools and equipment must be serviceable, fit for purpose and properly used, maintainedand inspected. All tools and equipment must be used in accordance with any specific

    instructions within Network Operatorprocedures.

    Arboricultural cutting equipment e.g. chain saws, pruning shears, chainsaw pole pruners

    and mechanical plant e.g. harvesters.

    4.2 Site Specific Risk Assessment Principles

    The risk assessment will then be subject to and complimented by site specific risk

    assessment.

    It is essential that the risk assessment process deals separately and adequately with both the

    electrical and tree related hazards.

    The site specific risk assessment will be available to all staff and associated stakeholders

    involved in the works.

    The site specific risk assessment should contain the following (the list is for example and not

    exhaustive):

    Justification for any live working proposed

    Evaluation of the risks regarding the planned work environment should be detailed.

    Consideration will be made regarding the location of Network Operatorequipment inrelation to highways and roads, weather and ground conditions.

    The planned work methodology should be referenced regarding the electrical hazards,

    namely the category of the works as defined in Section 5.4. Access methods should bedetailed e.g. MEWPs, tree climbing, rope ascent, ladders. Consideration should also be

    made and referenced to the management of materials produced as a result of the works

    e.g. moving and stacking of timber and waste.

    The physical condition of the vegetation involved in the works should be assessed from a

  • 8/10/2019 12 July 92 Doug Cunningham

    12/22

    Engineering Recommendation G55/2

    Page 10 September 2008

    risk control perspective. Previous survey and condition data may be used to support the

    pre-work on site assessment.

    Public safety should be assessed regarding provision for overall site management and

    specifically public exclusion (as appropriate), safe passage through the site if rights of

    wayexist, prevention of damage to property leading to compromising safety e.g. damaging

    fences containing animals.

    Emergency procedures specific to the site should include the geographical and electrical

    location, phone signal coverage, hospital locations, provision of communication with the

    Network Operatorcontrol centre, site safe areafor staff welfare and maintenance.

    Section 5.8 gives more guidance.

    All staff allocated to undertake the works should be informed sufficiently to recognise and

    understand the risks and the control measures to be applied and it is suggested that a formal

    sign-off should be obtained. It is expected that all staff involved should record their acceptance

    of the risk assessment and the control measures detailed e.g. tailboard conference. In the

    event that any member of the working party identifies safety concerns that are not adequately

    addressed then work should not continue unless suitable control measures can be agreed andimplemented.

    It is a fundamental requirement that the on site risk assessment is updated and amended

    to take account of any changes in conditions that take place during the execution of the

    works e.g. a designated access/egress route may be altered. The change of risk state should

    always prompt a review and as appropriate, action to control the situation e.g. a change in the

    weather.

    Anyone visiting the site of work or joining the work team should be briefed on the risk assessment

    process and the control measures in place.

  • 8/10/2019 12 July 92 Doug Cunningham

    13/22

  • 8/10/2019 12 July 92 Doug Cunningham

    14/22

    Engineering Recommendation G55/2

    Page 12 September 2008

    5.3 Conditions Required for Working with the Line Live

    All tree cutting shall be carried out where reasonably practicable with the line dead.

    However, the Electricity at Work Regulations (EAWR) allow for situations where isolating an

    electrical supply raises the risks to the customer or staff to a high level. Regulation 14 of the

    EAWR permits operations to take place provided that the following conditions prevail:

    It is unreasonable in all circumstances for the line to be dead; and

    It is reasonable in all circumstances for a person to work on or near the line while it is live;

    and

    Suitable precautions (including where necessary the provision of suitable protectiveequipment) are taken to prevent injury.

    In addition to these conditions each Network Operatorshould have in place an approved

    method of carrying out the work safely that is fully understood by the staff and includes details

    of the authorisation levels, supervision, assessment and appropriate equipment to be used.

    Provided that the Network Operatorhas an approved method of work which includes ajustification process then trees can be cut with the line live using only trained, Competentandauthorised staff. This justification must be recorded as part of the risk assessment process(see also Section 4.2).

    5.4 Categories of Tree Work and Procedures to Control Risk

    The risks associated with each work site with respect to the electrical hazard must be assessedto determine the correct methods to be used to remove or prune the trees. The findings must

    be recorded as part of the risk assessment process detailed in Section 4.

    A tree will be categorised in terms of thepositionof its branches relative to any conductors or

    electrical equipment. The assessment will not take into account any work methods thatmay be intended to be used. The assessment shall be made immediately prior to workstaking place.The control methods to be used will then be determined as directed later in thissection.

    There are four categories A, B, C and D with A generallybeing the most hazardous and D the

    least. Where there is any doubt as to the category, default to the safer option.

    In general a work site should be categorised as a whole and the most hazardous tree(s)

    will determine the category. If a work site is complex, requiring various work methods then

    consideration should be given to breaking it down in to more manageable sections.

    Particular care should be taken when assessing climbing plants such as ivy on poles. It can

    be difficult to determine exactly where the vegetation stops and in these cases again always

    default to the safer option.

    Having determined the category of the work site then the appropriate method(s) shouldbe decided and recorded. Work can then progress until the work site is completed or the

    category of the work site has reduced and different control methods can be adopted. Followinga re-assessment, in this way a logical sequence of work can be developed where the mosthazardous trees are removed first with higher levels of control. The removal of the most

    hazardous categories of trees first will lessen the likelihood of reduced levels of control being

    used inappropriately.

  • 8/10/2019 12 July 92 Doug Cunningham

    15/22

    Engineering Recommendation G55/2

    Page 13 September 2008

    There will be occasions when this sequence can not be strictly adhered to if, for example, less

    hazardous trees (Category D) need to be cleared to allow access to others (Category A), these

    works need to be carefully planned with all on site fully briefed on the hazards. Considerationshould be made on work sites like this to indicate clearly those trees that must not be worked

    on with the reduced control measures.

    It must be noted that although a work site may have been categorised in advance it must

    always be re-assessed on the day of the works to take in to account any site changes, recent

    growth or temperature variations causing changes in line sag. This process must be repeatedif works continue on subsequent days.

    The preferred method to control the electrical hazard is to carry out the work with the network

    isolated and earthed in accordance with the Network OperatorsSafety Rules.

    Where a decision making process has taken place in line with Section 5.3 and the works are

    to be carried out with the line live, then:

    For non-insulated conductors the control measures to be used should be determined bychoosing the most appropriate from those available under the following diagrams for each

    category. However, the following will always apply for all categories of tree:

    No part of any persons body shall ever breach the Vicinity Zone.

    No tools or equipment (except Approved Insulated Tools) shall breach the VicinityZone.

    No person shall work above any live conductor.

    For Effectively Insulated Conductorssee Section 5.5.

    In the event that works are not carried out in accordance with the recommended controls then

    it should be ensured that the works are carried out with further supervision and a method

    statement approved by the Network Operatormust be in place.

    The Tree Category Decision Flowchart is given on the following page.

  • 8/10/2019 12 July 92 Doug Cunningham

    16/22

    Engineering Recommendation G55/2

    Page 14 September 2008

    Tree Category Decision Flowchart

    Is any part of the

    tree in the VicinityZone?

    Yes

    Are branches

    above the

    height of the

    conductors?

    No

    No

    Yes Is the tree Nocapable of

    breaching the

    Vicinity Zone?

    Category A Yes

    Category B

    Category C

    Category D

    A more detailed explanation of the four categories and recommended control measures is

    given on the following pages.

  • 8/10/2019 12 July 92 Doug Cunningham

    17/22

    Engineering Recommendation G55/2

    Page 15 September 2008

    Category A

    Within the Vicinity Zone(including the Live Zone), at or above the level of conductors orequipment. All of the trees illustrated below in Figures 1 and 2 are Category A trees.

    V Z

    L Z V Z

    L Z

    Figure 1 Figure 2

    With the line live the method of work should be established by incorporating the following

    control measures:

    Where the voltage is greater than 33kV then the works will be carried out dead.

    The only exception to this will be where no branches breach the Live Zoneand thereis further supervision and a method statement approved by the Network Operatorthat

    ensures there is no breach of the Live Zone. Branches can be reduced by using Approved Insulated Tools.

    Approved Insulated Toolsmay only be allowed to be used in the Live Zonewhere a

    procedure approved by the Network Operatoris in place. Trees with branches in the Live Zone must not be climbed. Trees with branches in the Vicinity Zonebut not in the Live Zoneshould only be climbed where a procedure approved

    by the Network Operatoris in place.

    If branches protrude through the Vicinity Zone and up above the height of the Vici Zoneand overhang the extent of the Live Zonethen the works will be carried out dead. Where Approved Insulated Tools or any cut materials have the potential to cause aphase to phase or phase to earth flashover then this work must be carried out dead.

    The length of cut section must be determined by risk assessment and recorded, particularly

    taking in to account distances between phases A dedicated lookout groundsman capable of stopping work will be required to ensure that

    the required control measures are being adhered to.

    Works must be planned such that contact with electrical equipment is avoided. The saw head should not be used in the Live Zoneor on thin branches less than 25mm

    diameter that protrude into the Live Zone; this prevents excessive movement andunintentional contact of branches with conductors.

  • 8/10/2019 12 July 92 Doug Cunningham

    18/22

    Engineering Recommendation G55/2

    Page 16 September 2008

    Category B

    Outside (but capable of breaching) the Vicinity Zoneincluding the Live Zone, adjacent toconductors or equipment (see figures 3 & 4). All of the trees illustrated below in Figures 3 and

    4 are Category B trees.

    V Z

    L ZV Z

    L Z

    Figure 3 Figure 4

    With the line live the method of work should be established by incorporating the following

    control measures:

    In the particular circumstance where branches are overhanging the Live Zone on HV as

    shown in Figure 4 then the works shall be carried out dead.The only exception to this will be where there is further supervision and a method statement

    approved by the Network Operator. This must incorporate further controls that ensure no

    breach of the Live Zoneand may incorporate the use of hand held sections, loweringequipment or rope assisted felling. Full account of the weather conditions must be taken.

    Control measures should, where necessary, include preparatory work to remove branchesin a logical manner to avoid the risk of small branches cut higher up in the crown outside

    the Vicinity Zonebouncing or cart-wheeling onto the line. If branches have the potential to breach the Vicinity Zonethen Approved Insulated

    Toolsmust be used.

    If branches have the potential to breach the Live Zone then only small sections shouldbe removed to avoid a phase to phase contact or damage to the network. The maximum

    length of cut section should be recorded on the risk assessment.

    These trees can be climbed and dismantled with suitable control measures, it must beensured that in the event of a fall or swing there is no possibility of a climber breaching the

    Vicinity Zone.

    A dedicated groundsman capable of stopping work must be used to maintain clearances ifa climber or MEWP is above the level of conductors.

    Straight fell trees away with appropriate control measures (such as the use of two ropes)to ensure no breach of the Vicinity Zone. Suitable procedures must be approved by theNetwork Operator.

  • 8/10/2019 12 July 92 Doug Cunningham

    19/22

    Engineering Recommendation G55/2

    Page 17 September 2008

    Category C

    Within the Vicinity Zone(including the Live Zone), beneath the level of conductors orequipment. All of the trees illustrated below in Figures 5 to 8 are Category C trees.

    V Z V Z

    L Z L Z

    V Z

    L Z

    Figure 5 Figure 6

    V Z

    L Z

    V Z

    L Z

    L Z

    V Z

    Figure 7 Figure 8

    With the line live the method of work should be established by incorporating the following

    control measures:

    Remove branches in the Live Zonewith Approved Insulated Tools If the trees are below the level of the Live Zone, with no possibility of breaching the

    Live Zone(such as the trees shown in Figure 6) then they may be felled or pruned with

    non-insulated tools such as a chainsaw. If the tree to be felled is below the level of the Live Zone with a possibility of breaching th Live Zone(such as the tree shown in Figure 7) then remove the branches with Approved

    Insulated Toolsprior to felling.

    If the trees are below the level of the Live Zone then they may be climbed ensuringthat no part of the climbers body, tools or equipment can breach the Vicinity Zoneand

    that branches are not caused to breach the Live Zone. A dedicated lookout groundsman

    capable of stopping work should be used in this instance.

  • 8/10/2019 12 July 92 Doug Cunningham

    20/22

    Engineering Recommendation G55/2

    Page 18 September 2008

    Category D

    Within Proximityof the overhead electric line but not capable of breaching the Vicinity Zone.All of the trees illustrated below in Figure 9 are Category D trees.

    V Z

    L Z

    Figure 9

    With the line live the method of work should be established by incorporating the following

    control measures:

    Use non-insulated tools and avoid any breach of the Vicinity Zoneby operatives, tools orequipment

    Wherever possible trees should be felled away from conductors. Trees must be felled into a cleared area to avoid the risk of a dominoeffect with other

    trees.

  • 8/10/2019 12 July 92 Doug Cunningham

    21/22

    Engineering Recommendation G55/2

    Page 19 September 2008

    5.5 Effectively Insulated Conductors

    Provided that the conductors are deemed to be Effectively Insulated Conductorsby the

    Network Operator, the insulation is intact and the Network OperatorsProcedures allow,

    then it is acceptable to clear vegetation with the line live using conventional non-insulatedtools, ensuring that there is no breach of the Live Zoneby persons, tools or equipment.

    However, it must be borne in mind that where trees are present and have been touchingconductors then there will be a strong possibility that abrasion has caused damage to the

    insulation. Older insulation may be subject to degradation and may not offer full insulation.Thorough inspection and constant vigilance is required. Where there is any doubt then the

    conductors must be treated as non-insulated.

    To ensure that works are carried out safely the following controls should be adhered to:

    The Network Operatormust deem the conductor type to be Effectively InsulatedConductors.

    Inspect the insulation to ensure that it is intact, if there is any doubt; assume the insulationis not effective.

    Inspect the network for non-insulated joints or jumper connections, if these are found then

    the control measures for non-insulated conductors (section 5.4) apply.

    Ensure that there is no breach of the Live Zone by persons, tools or equipment.

    It must be noted that even where cable guards are fitted around cables on poles that extreme

    caution must be used when using any cutting equipment, but particularly with chainsaws and

    brush cutters.

    5.6 Use of Machinery

    The use of mechanical equipment such as harvesters, front, side, and rear flails and timber

    forwarders are increasingly being used during clearance operations in Proximityto overheadlines.

    All timber harvesting equipment should only be used in accordance with a method statement

    approved by the Network Operatorand in accordance with the control measures outlined inSection 5.4. This must incorporate measures for the safe access of machinery with respect tooverhead equipment.

    5.7 Tidy-up Operations

    On completion of works in Proximityto power lines then consideration must be given toany subsequent tidy up operations and to the safety of the general public. In particular the

    following should be considered:

    Stacking branches or timber directly underneath the conductors should be avoided wherethere is any potential fire hazard or possibility of reducing ground clearances to below

    minimum levels.

    Any long branches must be reduced in length where there is any possibility of them beinglifted to give access to conductors or electrical equipment.

    Timber and branches must not be stacked where it could give access to substations or

    electrical equipment or where it is known that mechanical plant would be required to be

    used within minimum safety distances of overhead lines, as defined in HSE Guidance

    Note GS6 Avoidance of Danger from Overhead Electric Lines.

  • 8/10/2019 12 July 92 Doug Cunningham

    22/22

    Engineering Recommendation G55/2

    Page 20 September 2008

    5.8 Emergency Procedures

    All staff must be trained in dealing with emergency situations. In the event of an incident

    then the emergency procedures detailed below should be followed. On no account should an

    attempt be made to remove a tree or a branch that has landed on and remains in contact withthe conductors.

    The sequence of actions will depend on the type and severity of incident and the number of

    people on site:

    If a vehicle comes in contact with an overhead line stay in the vehicle if it is safe to do so

    or follow the procedure for safe exit.

    Stop all work and make site safe.

    Contact the appropriate Network Control Centre as specified by the Network Operator.

    Keep everyone away from live conductors, fences or equipment and vegetation in contact

    with conductors

    Call emergency services if necessary, give exact location and access details.

    Carry out aerial rescue only if safe to do so.

    Carry out First Aid if necessary or take the casualty to the nearest Accident and Emergencydepartment.

    Contact a supervisor to report the incident.

    Do nothing else until instructed by a suitably authorised person representing the Network

    Operator.

    5.9 Performance Monitoring

    Network Operators should have suitable monitoring systems that ensure that the standards

    set out in this ER are achieved.

    To achieve this, competent assessors must carry out regular assessments of a representative

    sample of tree work.

    These should cover working practices and equipment.

    It is the responsibility of the Network Operator to adjust the frequency of the safety checks

    in line with the findings.

    Take prompt and appropriate corrective action if performance standards are not being

    met.

    It is recommended that every Manager/Supervisor maintains a record showing how this

    monitoring is carried out in respect of the staff under his control.

    5.10 Review of Procedures

    It is recommended that the operation of all procedures established to meet the requirementsof this ER should be regularly reviewed in respect of their effectiveness in ensuring that all

    those carrying out tree work on behalf of the Network Operator enjoy a safe, healthy workingenvironment and incident free operations. These reviews should lead to appropriate timely

    action.


Recommended