+ All Categories
Home > Documents > 122080198-EARTHWORKS

122080198-EARTHWORKS

Date post: 14-Aug-2015
Category:
Upload: jjahaddin
View: 35 times
Download: 0 times
Share this document with a friend
Description:
earthworks
Popular Tags:
90
EARTHWORKS EARTHWORKS
Transcript
Page 1: 122080198-EARTHWORKS

EARTHWORKSEARTHWORKS

Page 2: 122080198-EARTHWORKS

• EARTHWORKS• Areas and Volumes of earthworks• Distribution Analysis (HAQL and MASS

DIAGRAM)

• ROUTE SURVEYING• DEFINITION• Route Surveying is a survey which supplies data

necessary to determine the alignment, grades, and earthworks quantities necessary for the location and construction of engineering projects. This includes highways, drainage, canal, pipelines, railways, transmission lines, and other civil engineering projects that do not close upon the point of beginning

Page 3: 122080198-EARTHWORKS

ROUTE LOCATIONSTAGES OF HIGHWAY SURVEYS• Development of the interstate highway system

and more general acceptance of the limited access principle for major highways have resulted in a more and more highway projects being to serve local traffic, surveys for highway projects where new location is being considered start with a general study of the entire area between termini, proceed to more specific studies of possible alternative routes, and finally conclude with a detailed survey of the selected route and staking of the final centerline on the ground.

Page 4: 122080198-EARTHWORKS

• These procedures are generally carried in three stages:

• RECONAISSANCE

• PRELIMINARY SURVEY

• LOCATION SURVEY

Page 5: 122080198-EARTHWORKS

RECONAISSANCE

• Includes a general study of the entire area the development of one or more alternative routes or corridors, and the study of each of these corridors in sufficient detail to enable the proper officials to decide which will provide the optimum location.

Page 6: 122080198-EARTHWORKS

PRELIMINARY SURVEY

• Is a survey of selected corridors in sufficient detail to permit staking of the final centerline on the ground in some cases, the preliminary survey may be completed and staked in the field without variation in other instances, Minor adjustments may be required during the location survey.

Page 7: 122080198-EARTHWORKS

LOCATION SURVEY

• Consists in staking the final centerline and obtaining all additional information necessary to enable the design engineer to prepare completed plans, specifications, and estimates of earthwork quantities and to prepare deeds and descriptions covering the rights of way to be acquired.

Page 8: 122080198-EARTHWORKS

EARTHWORKSEARTHWORKS• EARTHWORKS – the construction of large open

cuttings or excavations involving both cutting and filling of material other than rock.

• EXCAVATION – is the process of loosening and removing earth or rock from its original position in a cut and transporting it to a fill or to a waste deposit.

• EMBANKMENT – the term embankment describes the fill added above the low points along the roadway to raise the level to the bottom of the pavement structure material for embankment commonly comes from roadway cuts or designated borrow areas.

Page 9: 122080198-EARTHWORKS

• SETTING STAKES FOR EARTHWORK

• The first step in connection with earthwork is staking out or setting slope stakes as it is commonly called.

• Two important parts of the work of setting slope stakes:

• Setting the Stakes

• Keeping the Notes

Page 10: 122080198-EARTHWORKS

The data for setting the stakes are:• The ground with center stakes set at every

station.• A record of benchmarks and of elevations

and rates of grades established.• The base and side slopes of the cross

section for each class of material.• In practice, notes of alignment, a full

profile, and various convenient data are commonly given in addition to the above mentioned data.

Page 11: 122080198-EARTHWORKS

• Side Slopes most commonly employed for cuts and fills.

• MATERIAL EXCAVATION SIDE SLOPE• ORDINARY EARTH 1.50 : 1.00• COURSE GRAVEL 1.00 : 1.00• LOOSE ROCK 0.50 : 1.00• SOLID ROCK 0.25 : 1.00• SOFT CLAY OR SAND 2 or 3 : 1.00

Page 12: 122080198-EARTHWORKS

• SETTING THE STAKES

• Setting the stakes work consists of:

• Making upon the back of the center stakes the cut or fill in feet or meters and tenths, as C 2 3 or F 4 7

• Setting side stakes or slope stakes at each side of centerline at the point where the side slope intersects the surface of the ground and marking upon the inner side of the stake, cut or fill at that point.

Page 13: 122080198-EARTHWORKS

FIGUREFIGURE

Page 14: 122080198-EARTHWORKS

FIGUREFIGURE

Page 15: 122080198-EARTHWORKS

• Process of determining the height of cut or fill at the center stake or at any other points between the center space and slope stake.

Page 16: 122080198-EARTHWORKS

FIGUREFIGURE

Page 17: 122080198-EARTHWORKS

• Let HI = elevation of the line of sight or telescope refereed fro known or assumed datum.

• Grade ROD = difference in elevations between the line of sight (HI) and the grade elevation

• Ground ROD = HI – Grad Elevation

• CUT = Grade ROD – Ground ROD

Page 18: 122080198-EARTHWORKS

FIGUREFIGURE

Page 19: 122080198-EARTHWORKS

• When the instrument is set up above the grade or subgrade:

• Grade ROD A = (HI)A – Grade Elevation

• FILL = Ground ROD A – Grade ROD A– When the instrument is set up below the

grade or subgrade:

• Grade ROD B = Grade Elevation – (HI)B

• FILL = Grade ROD B + Ground ROD B

Page 20: 122080198-EARTHWORKS

SETTING SIDE OF SLOPE

(FIELD PROCEDURES)

• The cross – sectioning is done after the grade lines have been determined in the office. The amounts of cut and fill at the center are computed, the distances and their heights above the base, or below it of the slope stakes are determined as follows:

Page 21: 122080198-EARTHWORKS

An engineer’s level is set up and rod readings are taken at the center and at trial point. Assume that the third trial point is on the slope, compute the distance fro the center using the following formulas:DL = B / 2 + SHL S = Horizontal / VerticalDR = B / 2 + SHR

Where:S = Side Slope HL = Side Height LeftB = Base pr Width HR = Side Height RightDL = Distance out leftDR = Distance out right

Page 22: 122080198-EARTHWORKS

• Measure the distance from the center to the trial point, if this distance is less than the calculated distance, the rod is to be moved out for another trial point; if greater, the rod is to be moved in, if equal, the point is correctly located. A stake is placed here indicating the right of the slope point above or below the base or sub grade.

Page 23: 122080198-EARTHWORKS

• ILLUSTRATION:– If the measured distance is greater than the

calculated distance, then the trial point is too far out the center line of the roadway and the direction to the rodman is to move in.

• Figure

Page 24: 122080198-EARTHWORKS

– If the measured distance is less than the calculated distance, the trial point is too near to the centerline of the roadway and the direction to the rodman is to move out.

• Figure

Page 25: 122080198-EARTHWORKS

• C. If the measured distance is exactly equal to the calculated distance, the point is correctly located and the slope stake is at on the ground indicating the height of the slope point above or below the ground.

• Figure

Page 26: 122080198-EARTHWORKS

ROAD CROSS SECTIONROAD CROSS SECTION

A. LEVEL SECTION• If the ground level in a direction

transverse to the centerline, the only rod reading necessary is that the centerstake, and the distance to the slope stake can be calculated once the center cut or fill has been determined, such a cross-section is called level section.

Page 27: 122080198-EARTHWORKS

1.LEVEL SECTION IN CUT1.LEVEL SECTION IN CUT• Figure

Centerheight = 1.83m

Base for Cut = 8.00m

SS for Cut = 1:1

DR = DL = B / 2 + SC

= 4 + 1 (1.83)

= 5.83

Page 28: 122080198-EARTHWORKS

2.LEVEL SECTION IN FILL2.LEVEL SECTION IN FILL• FigureCenterheight = 1.50m Base for Fill = 7.00m

SS for Fill = -1.50 : 1.00 DR = DL = B / 2 + SC

= 3.50 + 1.50 (1.50) = 5.75

Page 29: 122080198-EARTHWORKS

B.THREE LEVEL SECTIONB.THREE LEVEL SECTION

• When Rod readings are taken at each slope stake in addition to readings taken at the center as will normally be done whEre the ground is sloping the cross-section is called Three Level Section.

Page 30: 122080198-EARTHWORKS

• FIGURE:

• Base for Cut = 8.00m SS for Cut = 1.00:1.00

• DL = B / 2 + SHL = 4.00 + 1(0.63) = 4.63m

• DR = B / 2 + SHR = 4.00 + 1(4.96) = 8.96m

Page 31: 122080198-EARTHWORKS

• FIGURE:

• Base for Fill = 7.00m SS for Fill = 1.50:1.00• DL = B / 2 + SHL = 3.50 + 1.50(3.12) = 8.18m• DR = B / 2 + SHR = 3.50 + 1.50(2.62) = 7.43

Page 32: 122080198-EARTHWORKS

C.FIVE LEVEL SECTIONC.FIVE LEVEL SECTION

• When rod reading is taken at the centerside the slope stake and at points on each side of the center of the distance of half the width of the road bed, the cross section is called a FIVE LEVEL SECTION.

Page 33: 122080198-EARTHWORKS

• FIGURE:

• Base for Fill = 7.00m SS for Fill = 1.50:1.00

• DL = B / 2 + SHL = 3.50 + 1.50(2.42) = 7.13m• DR = B / 2 + SHR = 3.50 + 1.50(3.28) = 9.23m

Page 34: 122080198-EARTHWORKS

SAMPLE PROBLEM (Setting SAMPLE PROBLEM (Setting Slope Stakes)Slope Stakes)

In setting slope stakes, the height of cut at the center has been found to be 1.43m, the ground readings at center “M” and trial point A on the slope are 2.33m and 1.46m, respectively, and the measured distance from the center line of the roadway to the trial point is 8.24m. If the base of the roadway is 9m and the side slope is 1.50:1.00, should the trial point be moved in or out?

Page 35: 122080198-EARTHWORKS

• FIGURE:

Page 36: 122080198-EARTHWORKS

SOLUTIONSOLUTION• Grade Rod – Grade Rod @ M = 2.33+ 1.43 =

3.76• Measured Distance (DM) = 8.24• Calculated Distance (DC) = B / 2 + SHR • Where: B / 2 = 4.5m• HR = 3.76 – 1.46 = 2.30m• 1.50 / 1.00 = SHR / 2.30• SHR = 2.30 (1.50) / 1.00• SHR = 3.45• DC = 4.5 + 3.45 = 7.95• Since DC < DM --- Move In

Page 37: 122080198-EARTHWORKS

• FIGURE:

Base for Cut = 8.00m SS for Cut = 1:1

DL = B / 2 + SHL = 4.00 + 1(2.75) = 6.75m

DR = B / 2 + SHR = 4.00 + 1(3.60) = 7.60m

Page 38: 122080198-EARTHWORKS

• FIGURE:

• Base for Fill = 7.00m SS for Fill = 1.50:1.00

• DL = B / 2 + SHL = 3.5 + 1.50(2.84) = 7.76m• DR = B / 2 + SHR = 3.50 + 1.50(2.92) = 7.88m

Page 39: 122080198-EARTHWORKS

D. IRREGULAR SECTION IN CUTD. IRREGULAR SECTION IN CUT

• A cross section for which observation is taken to points between center and slope stakes at irregular intervals is called irregular section.

Page 40: 122080198-EARTHWORKS

• FIGURE:

• Base for Cut = 8.00m SS for Cut = 1:1

• DL = B / 2 + SHL = 4.00 + 1(2.60) = 6.60m

• DR = B / 2 + SHR = 4.00 + 1(3.47) = 7.47m

Page 41: 122080198-EARTHWORKS

E. SIDE HILL SECTIONE. SIDE HILL SECTION• Where the cross-section passes through

from cut to fill, it is called a SIDE HILL SECTION and an additional observation is made to determine the distance from center to the grade point. That is the point where subgrade will intersect the natural ground surface. A peg is usually driven to grade at this point and its position is indicated by a guard stake marked “Grade”. In this case also cross-section is taken additional plus station.

Page 42: 122080198-EARTHWORKS

• Base for Cut = 8.00m Base for Fill = 7.00m• DL = B / 2 + SHL = 3.50 + 1.50(3.60) = 8.99m• DR = B / 2 + SHR = 4.00 + 1(3.67) = 7.47m

Page 43: 122080198-EARTHWORKS

• PROBLEMS:

• In two ways, find the areas of each of the following cross-section note, given the corresponding bases and side slope if not given they are to be computed

Page 44: 122080198-EARTHWORKS

• A. BASE WIDTH 8.00m• SIDE SLOPE 1.50:1.00 ? / 2.84• ? / 12.84 + 2.84

• B. BASE WIDTH?• SIDE SLOPE ?• 5.79 / -1.86 – 1.27 6.03 / -2.02

• C. BASE WIDTH ?• SIDE SLOPE ?• 7.85 / 3.08 4.00 / 3.65 + 3.27

4.00 / 2.83 8.05 / 3.24

Page 45: 122080198-EARTHWORKS

• D. BASE WIDTH 8.00m• SIDE SLOPE 1.50:1.00• ? / -3.56 6.28 / -2.28 -2.32• 1.00 / -1.11 7.50 / -3.82• ? / -2.74

• E. BASE WIDTH8.00m (Cut) 5.00 (Fill)• SIDE SLOPE 1.00:1.00• 6.97 / -3.47 -0.61 1.04 / 0.00• 3.66 / -5.94 3.44 / 2.44

Page 46: 122080198-EARTHWORKS

a. LEVEL SECTION IN CUTa. LEVEL SECTION IN CUT• figure

Page 47: 122080198-EARTHWORKS

b. THREE LEVEL SECTION IN b. THREE LEVEL SECTION IN FILLFILL

• figure

Page 48: 122080198-EARTHWORKS

c. FIVE LEVEL SECTION IN CUTc. FIVE LEVEL SECTION IN CUT

• Figure:

Page 49: 122080198-EARTHWORKS

d. IRREGULAR SECTION IN FILLd. IRREGULAR SECTION IN FILL

• Figure:

Page 50: 122080198-EARTHWORKS

e. SIDE HILL SECTIONe. SIDE HILL SECTION• Figure:

Page 51: 122080198-EARTHWORKS

METHODS OF DETERMINING METHODS OF DETERMINING VOLUMES OF EARTHWORKSVOLUMES OF EARTHWORKS

Page 52: 122080198-EARTHWORKS

figurefigure

Page 53: 122080198-EARTHWORKS

A. By Average End AreasA. By Average End Areas

• V = L / 2 (A1 + A2)• Where:• V = Volume of Section of

Earthworks between Sta 1 and 2, m³• A1 , A2 = Cross – sectional area of

end stations, m²• L = Perpendicular Distance between

the end station, m

Page 54: 122080198-EARTHWORKS

• NOTES:• The above volume formula is exact only when

A1 = A2 but is approximate A1 <> A2. • Considering the facts that cross-sections are

usually a considerable distance apart and that minor inequalities in the surface of the earth between sections are not considered, the method of end areas is sufficiently precise for ordinary earthwork.

• By where heavy cuts or fills occur on sharp curves. The computed volume of earthwork ay be corrected for curvature out of ordinarily the corrected is not large enough to be considered.

Page 55: 122080198-EARTHWORKS

B. By Prismoidal FormulaB. By Prismoidal Formula

• V = L / 6 (A1 + 4AM + A2)• Where:• V = Volume of section of earthwork

between Sta 1 and 2 of volume of prismoid, m³

• A1 , A2 = cross – sectional area of end sections, m²

• AM = Area of mid section parallel to the end sections and which will be computed as the averages of respective end dimensions, m³

Page 56: 122080198-EARTHWORKS

• NOTES:• A Prismoidal is a solid having for its two ends

any dissimilar parallel plane figures of the same no. of sides, and all the sides of the solid plane figures. Also, any prismoid may be resolve into prisms, pyramids and wedges, having a common altitudes the perpendicular distance between the two parallel end plane cross – section.

Page 57: 122080198-EARTHWORKS

• As far as volume of earthworks are concerned, the use of Prismoidal formula is justified only if cross-section are taken at short intervals, is a small surface deviations are observed, and if the areas of successive cross-section cliff or widely usually it yields smaller values than those computed from average end areas.

Page 58: 122080198-EARTHWORKS

C. PRISMOIDAL CORRECTION C. PRISMOIDAL CORRECTION FORMULAFORMULA

• Figure:

Page 59: 122080198-EARTHWORKS

• CD = L / 12 (b1 – b2)(h1 – h2)• Where:• CD = Prismoidal Correction, It is subtracted

algebraically from the volume as determined by the average and the areas method to give the more nearly correct volume as determined by the Prismoidal formula, m³

• L = Perpendicular distance between 2 parallel and sections, m

• b1 = Distance between slope stakes at end section ABC where the altitude is h1, m

• b2 = Distance between slope stake at end section DEF where the altitude is h2, m

• h1 = Altitude of end section ABC at Sta 1, m• h2 = Altitude of end section DEF at Sta 2, m

Page 60: 122080198-EARTHWORKS

PRISMOIDAL CORRECTION FOR IRREGULAR SECTION

• In prismoid, there should be equal number of slope in both bases so that on equal number triangles can be found. The Prismoidal correction can then be found. The Prismoidal correction can then be found using either the fundamental formula of correction, CD = L / 12 (b1 – b2)(h1 – h2)

• or any of the formulas derive from it, where, however one base or any a five level section or three level section and other.

Page 61: 122080198-EARTHWORKS

• A five level section (or irregular section) or both bases are irregular sections or, if one base is a five level section and the other irregular section, the formulas cannot be directly applied without making certain assumptions because there are more triangles formed in one section than in the other. The determination of the correction is at best only approximate. For the purpose of determining the Prismoidal correction, the following may be used:

Page 62: 122080198-EARTHWORKS

– Neglect the intermediate heights thereby reducing the sections into three level or level sections this is the most convenient method.

– Plot the irregular or five level sections on cross sections paper. Draw on this section two equalizing lines starting from the same point or the center height such that the error added equal the areas subtracted approximately by estimating the center height as well as the distances in the right or in the left can then be scaled. This is more accurate than method A but involves more work.

– Reduce the five level or irregular section by calculation to equivalent level or three level sections as follows:

Page 63: 122080198-EARTHWORKS

1. To LEVEL SECTIONS

• The area of a level section BC + SC (B is the base, C is the center point, and S is the side slope.)

• Equate this area forced per the irregular or five-level section

• Base SS being known, a quadratic formula in one unknown is formed from which C is determined.

• Solve for the corresponding value of C.

Page 64: 122080198-EARTHWORKS

2.To THREE LEVEL SECTIONS2.To THREE LEVEL SECTIONS• Figure:

Page 65: 122080198-EARTHWORKS

• Total Area of three level section in cut• A = A1 + A2 • Where:• A1 = B / 4 (HL + HR)• A2 = C / 4 (B + S) (HL + HR)• Then K = BC / 2 + (HL + HR) (B / 4 – CS /

2)• NOTE:• The unknowns are C, HR and HL. Two

these should be assumed and the third computed. It is simpler to covert to level section.

Page 66: 122080198-EARTHWORKS

• PROBLEM:– Given the following cross-section notes of a

roadway with a base of 6m and SS of 1.25:1.00, between the volume of the prismoid between the two-end sections by the following methods:

• END AREA METHOD

• PRISMOIDAL FORMULA

• END AREA METHOD and PRISMOIDAL CORRECTION FORMULA

Page 67: 122080198-EARTHWORKS

• Given:

STATION CROSS – SECTION NOTES

10 + 000 +6.55 + 2.84+2.84 +6.55 + 2.84

10 + 020 +7.55 + 3.64+1.85 +3.65 + 0.52

Page 68: 122080198-EARTHWORKS

• SOLUTION:• Compute for the area at each station cross-

section and at mid-section

Figure:

Page 69: 122080198-EARTHWORKS

• Check for Cut distances

• DR1 = DL1

• = B / 2 + SHR

• = 1 / 2 (6m) + 1.25(2.84)

• = 6.55m

• Area by method of triangle and rhombus

• A1 = BC + SC² = 27.12m²

Page 70: 122080198-EARTHWORKS

• Figure:

Page 71: 122080198-EARTHWORKS

• Check for the distances• DR2 = B / 2 + SHR2 • = 1 / 2 (6) + 1.25(0.52)• = 3.65m• DL2 = B / 2 + SHL2 • = 1 / 2 (6) + 1.25(3.64)• = 7.55m• Area by method of triangle• A2 = Aa + AL + Ac + Ad • = 1 / 2 (3)(3.64) + 1 / 2 (1.85)(7.55) + 1 / 2 (1.85)

(3.65) + 1 / 2 (0.52)(3) • • A2 = 16.60m²

Page 72: 122080198-EARTHWORKS

• Compute for the dimensions of the mid sections

Figure

Page 73: 122080198-EARTHWORKS

DRm = 1 / 2 (DR1 + DR2) = 1 / 2 (2.84 + 0.52)

DRm = 5.10mDLm = 1 / 2 (DL1 + DL2)

= 1 / 2 (2.84 + 3.64)DLm = 7.05mHCm = 1 / 2 (HC1 + HC2) = 1 / 2 (2.84 + 1.85)HCm = 2.345mHRm = 1 /2 (HR1 + HR2) HLm = 1 / 2 (HL1 + HL2)= 1 / 2 (6.55 + 3.65) = 1 / 2 (6.55 +

7.55) HRm = 1.68m HLm = 3.24m

Page 74: 122080198-EARTHWORKS

Check for Cut distancesDRm = B / 2 SHRm = 1 / 2 (6) + 1.25(1.68)DRm = 5.10mDLm = B / 2 SHLm = 1 / 2 (6) + 1.25(3.22)DLm = 7.05mArea by method of triangleAm = Ae + Af + Ag + Ah = 1 / 2 (3)(3.24) + 1 / 2 (7.05)(2.345) + 1 / 2

(5.10)(2.345) + 1 / 2 (3)(1.68)Am = 21.68m

Page 75: 122080198-EARTHWORKS

COMPUTE FOR THE VOLUME OF COMPUTE FOR THE VOLUME OF EARTHWORK VOLUME OF CUT INEARTHWORK VOLUME OF CUT IN

BETWEEN THE TWO STATIONSBETWEEN THE TWO STATIONS• Figure

Page 76: 122080198-EARTHWORKS

1. By End Area Method• Ve = L / 2 (A1 + A2)• Where:• L = (10 + 020) – (10 + 000)• = 20m• A1 = 27.12m²• A2 = 16.60m²• Then,• Ve = 20 / 2 (27.12 + 16.60)• = 437.20m²

Page 77: 122080198-EARTHWORKS

2. By Prismoidal Formula

• Vp = L / 6 (A1 + 4Am + A2)

• Where:

• L = 20m

• A1 = 27.12m²

• A2 = 16.60m²

• Am = 21.67m²

• Then,

• Vp = 20 / 6 (27.12 + 4*21.67 + 16.60)

• = 434.13m³

Page 78: 122080198-EARTHWORKS

Prismoidal Formula for CorrectionCp = L / 12 (A1 + A2)(b1 – b2)Note:Resolve the given prismoid into a series of triangular prismoid into a series of triangular prismoid.Cp = Cpa + Cpb + Cpc + Ppd

Page 79: 122080198-EARTHWORKS

Where:

Cpa = 20 / 12 (2.84 – 3.64)(3-3) = 0

Cpb = 20 / 12 (2.84 – 1.85)(6.55 – 7.55) = -1.65m³

Cpc = 20 / 12 (2.84 – 1.85)(6.55 – 3.65) = 4.785m³

Ppd = 20 / 12 (2.84 – 0.52)(3-3) = 0

Then,

Cp = -1.65 + 4.785

= 3.135m³

Page 80: 122080198-EARTHWORKS

4. Corrected Volume

• Vc = Ve - Cp

• = 437.20 – 3.135

• Vc = 434.065m³

• Given the following cross section notes, determine the volume of the prismoid b end areas method and apply the Prismoidal formula. The roadway base is 6m with side slope of 1.25:1.00

Page 81: 122080198-EARTHWORKS

• STATIONSCROSS-SECTION NOTES• 10 + 040 +4.05 +3.00 +2.85 +3.00 +7.05• +0.84 +3.50 +2.12 +3.24• 10 + 050 +7.80 +2.00 +3.25 +4.00 +5.65

+3.84 +2.24 +2.50 +2.12

Page 82: 122080198-EARTHWORKS

• SOLUTION:• Compute for the end areas of the end sections• figure:

Page 83: 122080198-EARTHWORKS

• Check for distances:• DR1 = B / 2 + SHR1 DL1 = B / 2 + SHL1• = 3 + 1.25(3.24) = 3 + 1.25(0.84)• DR1 = 7.05 DL1 = 4.05

• A1 = A1 + A2 + A3 + A4 • = 1 / 2 (3.5)(1.05) + 1 / 2 (2.85) + 3.5(3) + 1 / 2

(2.12 + 2.85)(3) • + 1 / 2 (2.12)(4.05)• A1 = 23.11m²

Page 84: 122080198-EARTHWORKS

• Figure:

Page 85: 122080198-EARTHWORKS

• Check for distances:• DR2 = B / 2 + SHR2 DL2 = B / 2 + SHL2• = 3 + 1.25(2.12) = 3 + 1.25(3.85)• DR2 = 5.65m DL2 = 7.80m

• A2 = Aa + Ab + Ac + Ad + Ae + Af • = 1 / 2 (2.12 + 3.84)(5.80) + 1 / 2 (2.42 +

3.25)(2) • + 1 / 2 (2.50 + 3.25)(4) + 1 / 2 (2.12 +2.50)

(1.65) • – 1 / 2 (4.00)(3.84) – 1 / 2 (2.65)(2.52)• A2 = 27.11m²

Page 86: 122080198-EARTHWORKS

CONVERT THE END SECTIONS TO AN

EQUIVALENT LEVEL SECTIONS

Page 87: 122080198-EARTHWORKS

• Figure

Page 88: 122080198-EARTHWORKS

• A1 = five level section – A1 (equivalent level section)

• 1.11= 13 HCe1 + S (HCe1)²• 3.11 = 6 HCe1 + 1.25 (HCe1)²; Let C1 = HCe1 • 3.11 = 6 C1 + 1.25 C1²

• By quadratic formula• C1 = 2.52m• DRe1 = B / 2 + SHCe1; DRe1 = DLe2 • = 3 + 1.25(2.52)

Page 89: 122080198-EARTHWORKS

• Figure:

Page 90: 122080198-EARTHWORKS

• A2 = irregular section = A2 (equivalent level section)

• 27.11 = BHCe2 + S(HCe2)²

• 27.11 = 6HCe2 + 1.25(HCe2)²

• Let Ce = HCe2

• By quadratic formula

• C2 = HCe2

• Dre2 = B / 2 + SHRe2

• = 3 + 1.25

• DLe2 = DRe2


Recommended