1
IMACS:Inamori-Magellan Areal Camera and
Spectrograph
Magellan SAC Status Report
13-14 April 2002
OCIW, Pasadena, Ca
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
2
IMACS project team:
A. Dressler Pr. Investigator
B. Bigelow Instrument Scientist
B. Sutin, H. Epps Optical des./eng.
B. Bigelow, T. Hare
S. Gunnels, G. Luppino,
R. Cleary Mechanical des.
V. Kowal, R. Storts, J. Castillo Mechanical fab.
A. Bagish, D. Carr, J. Asa Electronics
G. Burley, I. Thompson, J. Estrada Detector systems
C. Birk, K. Clardy Software eng.
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
3
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
4
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
5
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
6
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
7
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
8
Optics Status:
Collimator:
C01 (Field lens) Done, ready to mount in cell
C02 - C05 Done, mounted in structure
Long Camera:
L01 Done, mounted in cell
L02/L03/L04 Lenses done, will be
re-mounted in cells
L05, L06 Done, mounted in cells
Long camera should be fully assembled by end of April 2002
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
9
Optics Status cont.
Short Camera:
S01, S08 (aspheres) At Tinsley, due 6/02
S07 At TORC, due end of April?
S02-S09 Ready to be coated at STF
Filters:
2 sets of CTIO B,V,I, Done
2 sets of CTIO R Due end of April ‘02
CTIO U (LCAM) Awaits ADC coating results
Sloan u’, g’, r’, i’, z’ Not ordered
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
10
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
11
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
12
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
13
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
14
Current grating selection:
RulingDensity
Lines/mm
BlazeAngle
Degrees
Order CentralWavelength
um
WavelengthRange
um
DispersionR/0.5 arcsec
slit300 4.3 1 0.665 0.365-0.974 2163
300 36.87 5-11 0.336-0.738 0.308-0.799 20687
600 8.63 1 0.518 0.365-0.675 3494600 13 1 0.841 0.684-1.0 6120
1200 17.45 1 0.444 0.365-0.523 65351200 26.7 1 0.924 0.864-1.0 20694
1200 26.7 2 0.404 0.365-0.443 15776
1200 26.7 2 0.520 (max) 0.482-0.557 28082
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
15
Optics Status cont.
Grisms:
200 l/mm Undersized mat’l re-ordered
300 l/mm Material due in August
600 l/mm Material due in May
Imaging Mirror: Mirror is being re-coated
following failure of
over-coated silver.
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
16
Mechanical Engineering Status:
Guide camera stages (Hare) Done, mods. IP
Mask server (Bigelow) Done, on structure
*Field Lens (Hare) Ready for mounting
LCAM shutter (Hare) Done, ready to install
Filter servers (Bond) Done, ready to install
*Disperser server (Hare) Assy. IP, drive remaining
*Grating cells Assy. IP
*Grism cells Designed, ready for draft.
Mirror cell Done
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
17
Mechanical Engineering cont.
Collimator mech. (Bigelow) Done, installed
*Long camera mech. (Bigelow) Final Assy. in April
Short camera mech. (Bigelow) Done, ready for optics
Dewar (Luppino) Done, ready for CCDs
Instrument Structure (Gunnels) Done, installed
*Instrument Carriage (Gunnels) Done, minor mods. IP
*Instrument Enclosures (Gunnels) Design IP
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
18
Center-field guide camera assembled and tested
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
19
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
20
Long camera with shutter, FS, and dewar mounted
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
21
Electronic Engineering:
Alan Bagish (OCIW) is completing the electronics design for IMACS. Joe Asa is providing final assembly services on a consulting basis. Status of electronics:
Schematics design (all motion stages) Done
(4) Motion control (MC) chassis, Done
(1) Power supply chassis, Done
(1) Shutter control chassis Done
(2) Electronics racks for chassis IP
Instr. wiring harnesses IP
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
22
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
23
Detector systems:
Guide cameras:
- 23 cameras have been fabricated
- IMACS currently has one of three needed
- Remainder by May ‘02?
Science array:
- Detector array (8 CCDs) has been flattened to 7.5 microns
- Individual detectors flat to 13 microns
- Dewar and detector system mechanics done
- Cold test of array in May
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
24
Software:
Guiding (Clardy):
- Guider position control GUI Done
- Guider position graphical display Done
- Interface to telescope control ****
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
25
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
26
Slit Mask Cutting (Clardy) :
- Mask Generation (MG) ****
inputs - images, data files, other
output - text file with targets, names, etc.
- Mask Definition (MD) Done
- inputs - text file from MG, other text files
- output - mask definition file
- database for observing, data reduction
- Mask Fabrication (MF) Done
- inputs - mask definition file
- output - test, laser G-code, mill G-code, .ps files
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
27
Software:
Instrument Control (Birk)
Individual module testing:
Module GUI status H/W testsPr. Guider done 75%SH guider done 75%CF guider done 90%Slit Mask Server done 75%Disperser Server 25% 0%Long Camera Focus done 90%Filter Servers (2) done 90%Flexure Control done 75%Detector Focus 25% 0%HP Sensor System done 50%
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
28
Software:
Instrument Control cont.
Integrated instrument testing:
- One GUI at this level, showing all critical aspects of each module (encoder positions, limit status, temperatures, etc).
- This GUI is written and 75% tested, unfinished stages remain (Disperser Server, Grating tilts, detect. focus)
User Level Software:
- Two GUIs at this level:
- Instr. control interface (select a grating, etc.) - 50% done
- Graphical Instr. Status Display - 25% done
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
29
Examples of individual stage test GUIs
Filter server GUI
SH guider GUI
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
30
Engineering GUI, shows status of all stage functions and sensors, operates in parallel for all modules.
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
31
User/Observer instrument control GUI
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
32
Graphics-based instrument GUI
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
33
Software:
Science Array Control (Birk)
Shutter control:
- micro-controller for linear motors 90% done
CCD readout / camera control:
- ‘ccdserver’ for array readout
- ‘camgui’ for user interface
- both are functional 75% done
Quick-Look Tool:
- functional with simulated data 90% done
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
34
Detector GUI
Quick-look tool
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
35
Slit Masks:
Laser system:
- Convergent Gemini 150 W. CO2 laser cutting system
- Ordered November 7, 2001 - $280K
- Acceptance testing completed March 18-22, 2002
- Currently in shipment to Chile
- Due at LCO May 1, 2002
ASB Facility:
- 200A electrical service required
- Air compressor delivered, installation required
- Ventilation, fire, and fume extraction systems still required
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
36
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
37
Slit Masks:
Slit mask blanks:
- Fabricated by California Hydroforming
- Current order of 100 mask blanks in progress
- Order of 1000 parts to follow first delivery
Mask cost:
- Estimated to about $100 per mask, including laser
(500 masks/year for 10 years)
13-14 April 2002 Inamori-Magellan Areal Camera & Spectrograph
38
Coming up:
- First light through optics - end of April
- Grating tilt mechanism assembly and testing - flexure
- Cold testing of CCD array - May
- Instrument enclosures - August
- All short camera optics coated - September