Date post: | 04-Jun-2018 |
Category: |
Documents |
Upload: | vanu-vamalai |
View: | 214 times |
Download: | 0 times |
of 282
8/14/2019 13MProgress.xlsx
1/282
Ground
Floor
First
Floor
1 13 Marla 001+1
2 13 Marla 2+3 3,790
3 13 Marla 4+5 B-6 3,790 2,220
4 13 Marla 6+7 B-4 3,790 1,782
5 13 Marla 8+9 B-3 3,790 2,658
6 13 Marla 10+11 10 (B2), 11 (B3) 3,790 2,476
7 13 Marla 12+13 12 (B-1), 13 (B-2) 3,790 2,658
8 13 Marla 14+15 B-5 3,790 2,515
9 13 Marla 16 B-6 1,978 1,374
10 13 Marla 17+18 B-6 3,956 2,678
11 13 Marla 19+20 B-5 3,956 3,126
12 13 Marla 21+22 B-6 3,956 2,748
13 5 Marla 23+24
14 5 Marla 25+26
15 5 Marla 27+28
16 7 Marla 30+31 B-5 2676 2456
17 7 Marla 32+33 B-5 2604 2199
18 7 Marla 34 B-6 1302 1242
19 5 Marla 35+36
20 5 Marla 37+38 B-4 2,175 1,131
21 5 Marla 39+40 B-5 2,175 1,390
22 5 Marla 41+42 B-5 2,175 1,505
23 5 Marla 43+44 B-4 2,175 1,853
24 10 Marla 45+46 B-6 3,400 2,542
25 10 Marla 47+48 B-3 3,400 1,668
26 10 Marla 49+50 49 (B-1), 50 (B-3) 3,400 2,850
27 10 Marla 51 B-6 1,760 1,271
28 10 Marla 52 B-6 1,760 1,271
29 10 Marla 53+54 Modle House -- --
30 10 Marla 55+56 B-3 3,400 2,542
31 10 Marla 57+58 B-4 3,400 2,542
32 7 Marla 59+60 B-4 2,604 2,400
33 7 Marla 61+62 62 (B-1), 61 (B-2) 2,604 2,402
Cantt Cottages, Multan
Subject: Detail of Houses
Sr. No.Area
Category
House/
Duplex No.Batch No.
Covered Area (Sft)
Progress Report 13 Marla Houses
Please Click on House no.
8/14/2019 13MProgress.xlsx
2/282
34 7 Marla 63+64 B-1 2,604 1,604
35 7 Marla 65+66 65 (B-2), 66 (B-3) 2,674 2,511
36 7 Marla 68+69 Modle House -- --
37 7 Marla 70+71 B-1 2,674 2,511
38 7 Marla 72+73 B-3 2,674 2,511
39 7 Marla 74+75 B-4 2,674 2,511
40 5 Marla 76 B-6 1088 63341 5 Marla 77+78 B-4 2175 1618
42 7 Marla 79+80 80 (B-1), 79 (B-3) 2,639 2,190
43 7 Marla 81+82 82 (B-1), 81 (B-3) 2,674 2,511
44 7 Marla 83+84 B-2 2,674 2,511
45 7 Marla 85+86
46 7 Marla 87+88
47 7 Marla 89+90
48 7 Marla 91
8/14/2019 13MProgress.xlsx
3/282
13 Marla
5 Marla
7 Marla
10 Marla
--
Supervisor Name
8/14/2019 13MProgress.xlsx
4/282
--
8/14/2019 13MProgress.xlsx
5/282
Description Total %age Work Done
Ground Floor 85.5% 0.0%
First Floor 83.0% 0.0%
External Work 100.0% 0.0%
Electric Work 100.0% 0.0%
Overall work in house # 001+01 368.5% 0.0%
Brick Work upto DPC Level 15.0%
Brick work in substructure upto 9" 7.0%
DPC Completion 6.0%
Earth Filling 2.0%
Brick Work upto Roof Level 15.0%
Brick work upto 3'-0" Height 4.0%
Upto Lintel Level 4.0%
Casting of Lintel 3.0%
Above Lintel upto Roof Level 4.0%
Casting of RCC Slab & Stair 21.0%
Shuttring at Site 6.5%
Casting of Porch Slab 2.0%
Casting of Slab (Shuttering, Steel fixing &
pouring) 10.0%
Casting of Stair 2.5%
Internal Plaster with Wabrobe Platform,
Kitchen Slab and Bath vanity 20.0%
Plaster under sofit (Ceiling) 5.0%
Internal Plaster inculding Edge plastering complete8.5%
All Bath & Kitchen walls inculding Edge plasteringcomplete 4.0%
Wardrobe Platforms , Bath Vanity slab, Kitchen
Slab etc. 2.5%
External Plastering 7.0%
Front Elevation 2.5%
Side/Back walls &other External Plaster4.5%
Earth filling, Brick Ballast, PCC, Stair Marble
& Window sill 7.5%
Earth filling & compaction 0.5%
PCC flooring 3.0%
Stair Marble 2.0%Window Sill 2.0%
Total Work for Ground Floor: 85.5% 0.0%
Brick Work upto Roof Level 21.0%
Brick work upto 3'-0" Height 5.0%
Upto Lintel Level 5.0%
Casting of Lintel 5.0%
Above Lintel upto Roof Level 6.0%
Ground Floor
First Floor
8/14/2019 13MProgress.xlsx
6/282
Casting of RCC Slab & Front Crown 20.0%
Shuttring at site 7.0%
Casting of Slab 12.0%
Front Crown 1.0%
Internal Plaster with Wabrobe Platform,
Kitchen Slab and Bath vanity 22.0%
Plaster under sofit (Ceiling) 5.0%
Internal Plaster complete 11.0%
All Edge plastering of Doors, Windows etc.
2.5%
Wardrobe Platforms , Bath Vanity slab, Kitchen
Slab etc. 3.5%
External Plastering 9.0%
Front Elevation external plaster 4.0%
Side wall And other external plaster with perpet
plaster 5.0%
Roof Treatment 6.0%
Roof Treatment 6.0%
Brick Ballast, PCC & Window sill 5.0%
PCC flooring 3.0%
Extra Amount in PCC flooring 1.3%
Window Sill 2.0%
Total Work for First Floor: 83.0% 0.0%
1 Altration Work 0.0%
i) Altration According to Drawing 0.0%
ii) Qibla Altration 0.0%
iii) Marketing Altration 0.0%iv) Architect Altertaion 0.0%
2
Side & Back Boundary Wall , inculding
excavation, PCC, Brick work in F&P,
DPC, Bick work in other than building,
Cement plaster & copping.
Plan No.
Amount @ 182/- Per Rft
7.00%
3 Out of Covered Area Work
i) Front Balcony 7.3%
Shuttering 0.71%Concrete with Steel 1.17%
Parapet Wall With Shuttering 1.12%
Plaster of Balcony 2.44%
P.C.C.(1:3:6) with Brick Ballast in Floor 0.49%
Tile Work in Floor 0.97%
Skirting 0.39%
ii) Side Balcony 2.6%
Shuttering 0.39%
External Works
8/14/2019 13MProgress.xlsx
7/282
Concrete with Steel 0.21%
Brick Work for Parapet Wall 0.30%
Plaster of Balcony 1.10%
P.C.C.(1:3:6) with Brick Ballast in Floor 0.11%
Tile Work in Floor 0.48%
iii) Laundry
ShutteringConcrete with Steel
Brick Work for Parapet Wall
Plaster of Balcony
P.C.C.(1:3:6) with Brick Ballast in Floor
Tile Work in Floor
iv) Big Arch with Projection 3.9%
Shuttering
Concrete with Steel
Plaster of Balcony
v) Back Tarrace Parapet Wall 4.6%
Brick Work for Parapet Wall 1.31%
Plaster of Parapet Wall 3.29%
vi) Back Terrace Flooring Work 2.7%
P.C.C.(1:3:6) with Brick Ballast in Floor 2.7%
vii) Front Terrace Parapet Wall Pouring 4.2%
vii - a) Front Terrace Parapet Wall Plaster 1.7%
viii) Top Parapet Wall Pouring 13.8%
viii - a) Top Parapet Wall Plaster 5.5%
4 External Work
i)
Front Boundary Wall , inculdingexcavation, PCC, Brick work in F&P,
DPC, Bick work in other than building,
Cement plaster, copping & steel railing .
Plan No.
Amount @ 200/- Per Rft
8.35%
ii) Toe Wall 3.5%
iii) External Flooring Work 7.2%
Earth filling in passages 1.85%
P.C.C(1:3:6) with Brick Ballast 4.51%
Earth filling in Lawn 0.84%
iv) Manholes 5.97%
vii) Ramp 2.0%
ix) Over Head Water Tank Civil Works 4.4%
x) AC Sills 0.8%
xi) Front crown plaster 1.7%
xii) Patio PCC inculding Tile & skirting 3.65%
xiii) Front Terrace Common wall complete 3.1%
xiv) Front Terrace PCC complete 5.3%
3.9%
8/14/2019 13MProgress.xlsx
8/282
xv) Patio wall plaster complete 0.9%
Total Work for External Area: 100.0% 0.0%
1 Electric Condute work of slab 6.00%
2 Down Piping on Wall with boxing 11.50%
3 Wiring with UPS Completion 11.50%4 Gate light,Gardon light,M,C,B and 4.50%
5 Service line completion 3.50%
6
Switch light with Arthaning A,C Drain pipe
Completion 10.00%
7
Home light compeltion hand over to
project Manager 3.00%
8 Electric Condute work of slab 6.00%
9 Down Piping on Wall with boxing 11.50%
10 Wiring with UPS Completion 11.50%
11 Gate light,Gardon light,M,C,B 4.50%
12 Service line completion 3.50%
13
Switch light with Arthaning A,C Drain pipe
Completion 10.00%
14
Home light compeltion hand over to
project Manager 3.00%
Total Work for Electric: 100.0% 0.00%
Ground Floor
First Floor
Electric Works
8/14/2019 13MProgress.xlsx
9/282
0.0% 0.0% 0.0% 0.0%
0.0%
10.0%
20.0%
30.0%
40.0%
50.0%
60.0%
70.0%
80.0%
90.0%
100.0%
Ground Floor First Floor External Work Electric Work
Overall work in house # 001+01
Overall work in house # 001+01
8/14/2019 13MProgress.xlsx
10/282
8/14/2019 13MProgress.xlsx
11/282
Not
included
Not
included
8/14/2019 13MProgress.xlsx
12/282
8/14/2019 13MProgress.xlsx
13/282
8/14/2019 13MProgress.xlsx
14/282
8/14/2019 13MProgress.xlsx
15/282
8/14/2019 13MProgress.xlsx
16/282
8/14/2019 13MProgress.xlsx
17/282
8/14/2019 13MProgress.xlsx
18/282
8/14/2019 13MProgress.xlsx
19/282
8/14/2019 13MProgress.xlsx
20/282
8/14/2019 13MProgress.xlsx
21/282
9100 7.00% 130059
9462 7.28% 130059
3346 2.57% 130059
5018 3.86% 130059
6040 4.64% 130059
5406 4.16% 1300592163 1.66% 130059
18000 13.84% 130059
7200 5.54% 130059
10864 8.35% 130059
4524 3.48% 130059
9374 7.21% 130059
7760 5.97% 130059
2622 2.02% 130059
5672 4.36% 130059
1040 0.80% 130059
2200 1.69% 130059
4750 3.65% 130059
3988 3.07% 130059
6900 5.31% 130059
1140 0.88% 130059
880 0.714731 8988
1440 1.169559 8988
1380 1.120828 8988
3000 2.436582 8988 1629.666 1.306364 5738.416
608 0.493814 8988 4108.75 3.293062 5739.416
1200 0.974633 8988
480 0.389853 8988
478.8 0.391632
258.4 0.211357
2282.408 1.845379 8905.129 368.6 0.301494
5580.619 4.511551 8906.129 1349 1.103407
1042.103 0.842374 8907.129 133 0.108787
8/14/2019 13MProgress.xlsx
22/282
590.9 0.483323
8/14/2019 13MProgress.xlsx
23/282
8/14/2019 13MProgress.xlsx
24/282
8/14/2019 13MProgress.xlsx
25/282
3178.7
3178.7
3178.7
3178.7
3178.7
8/14/2019 13MProgress.xlsx
26/282
3178.7
8/14/2019 13MProgress.xlsx
27/282
Description Total %age Work Done
Ground Floor 85.5% 23.0%
First Floor 83.0% 0.0%
External Work 100.0% 2.6%
Electric Work 100.0% 0.0%
Overall work in house # 2+3 368.5% 25.6%
Brick Work upto DPC Level 15.0%
Brick work in substructure upto 9" 7.0%complete
DPC Completion 6.0%complete
Earth Filling 2.0%complete
Brick Work upto Roof Level 15.0%
Brick work upto 3'-0" Height 4.0%complete
Upto Lintel Level 4.0%complete
Casting of Lintel 3.0%
Above Lintel upto Roof Level 4.0%
Casting of RCC Slab & Stair 21.0%
Shuttring at Site 6.5%
Casting of Porch Slab 2.0%
Casting of Slab (Shuttering, Steel fixing &
pouring) 10.0%
Casting of Stair 2.5%
Internal Plaster with Wabrobe Platform,
Kitchen Slab and Bath vanity 20.0%
Plaster under sofit (Ceiling) 5.0%
Internal Plaster inculding Edge plastering complete8.5%
All Bath & Kitchen walls inculding Edge plasteringcomplete 4.0%
Wardrobe Platforms , Bath Vanity slab, Kitchen
Slab etc. 2.5%
External Plastering 7.0%
Front Elevation 2.5%
Side/Back walls &other External Plaster4.5%
Earth filling, Brick Ballast, PCC, Stair Marble
& Window sill 7.5%
Earth filling & compaction 0.5%
PCC flooring 3.0%
Stair Marble 2.0%Window Sill 2.0%
Total Work for Ground Floor: 85.5% 23.0%
Brick Work upto Roof Level 21.0%
Brick work upto 3'-0" Height 5.0%
Upto Lintel Level 5.0%
Casting of Lintel 5.0%
Above Lintel upto Roof Level 6.0%
Ground Floor
First Floor
8/14/2019 13MProgress.xlsx
28/282
Casting of RCC Slab & Front Crown 20.0%
Shuttring at site 7.0%
Casting of Slab 12.0%
Front Crown 1.0%
Internal Plaster with Wabrobe Platform,
Kitchen Slab and Bath vanity 22.0%
Plaster under sofit (Ceiling) 5.0%
Internal Plaster complete 11.0%
All Edge plastering of Doors, Windows etc.
2.5%
Wardrobe Platforms , Bath Vanity slab, Kitchen
Slab etc. 3.5%
External Plastering 9.0%
Front Elevation external plaster 4.0%
Side wall And other external plaster with perpet
plaster 5.0%
Roof Treatment 6.0%
Roof Treatment 6.0%
Brick Ballast, PCC & Window sill 5.0%
PCC flooring 3.0%
Extra Amount in PCC flooring 1.3%
Window Sill 2.0%
Total Work for First Floor: 83.0% 0.0%
1 Altration Work 0.0%
i) Altration According to Drawing 0.0%
ii) Qibla Altration 0.0%
iii) Marketing Altration 0.0%iv) Architect Altertaion 0.0%
2
Side & Back Boundary Wall , inculding
excavation, PCC, Brick work in F&P,
DPC, Bick work in other than building,
Cement plaster & copping.
Plan No.
Amount @ 182/- Per Rft
7.00%
3 Out of Covered Area Work
i) Front Balcony 7.3%
Shuttering 0.71%Concrete with Steel 1.17%
Parapet Wall With Shuttering 1.12%
Plaster of Balcony 2.44%
P.C.C.(1:3:6) with Brick Ballast in Floor 0.49%
Tile Work in Floor 0.97%
Skirting 0.39%
ii) Side Balcony 2.6%
Shuttering 0.39%complete
External Works
8/14/2019 13MProgress.xlsx
29/282
Concrete with Steel 0.21%complete
Brick Work for Parapet Wall 0.30%complete
Plaster of Balcony 1.10%complete
P.C.C.(1:3:6) with Brick Ballast in Floor 0.11%complete
Tile Work in Floor 0.48%complete
iii) Laundry
ShutteringConcrete with Steel
Brick Work for Parapet Wall
Plaster of Balcony
P.C.C.(1:3:6) with Brick Ballast in Floor
Tile Work in Floor
iv) Big Arch with Projection 3.9%
Shuttering
Concrete with Steel
Plaster of Balcony
v) Back Tarrace Parapet Wall 4.6%
Brick Work for Parapet Wall 1.31%
Plaster of Parapet Wall 3.29%
vi) Back Terrace Flooring Work 2.7%
P.C.C.(1:3:6) with Brick Ballast in Floor 2.7%
vii) Front Terrace Parapet Wall Pouring 4.2%
vii - a) Front Terrace Parapet Wall Plaster 1.7%
viii) Top Parapet Wall Pouring 13.8%
viii - a) Top Parapet Wall Plaster 5.5%
4 External Work
i)
Front Boundary Wall , inculdingexcavation, PCC, Brick work in F&P,
DPC, Bick work in other than building,
Cement plaster, copping & steel railing .
Plan No.
Amount @ 200/- Per Rft
8.35%
ii) Toe Wall 3.5%
iii) External Flooring Work 7.2%
Earth filling in passages 1.85%
P.C.C(1:3:6) with Brick Ballast 4.51%
Earth filling in Lawn 0.84%
iv) Manholes 5.97%
vii) Ramp 2.0%
ix) Over Head Water Tank Civil Works 4.4%
x) AC Sills 0.8%
xi) Front crown plaster 1.7%
xii) Patio PCC inculding Tile & skirting 3.65%
xiii) Front Terrace Common wall complete 3.1%
xiv) Front Terrace PCC complete 5.3%
3.9%
8/14/2019 13MProgress.xlsx
30/282
xv) Patio wall plaster complete 0.9%
Total Work for External Area: 100.0% 2.6%
1 Electric Condute work of slab 6.00%
2 Down Piping on Wall with boxing 11.50%
3 Wiring with UPS Completion 11.50%4 Gate light,Gardon light,M,C,B and 4.50%
5 Service line completion 3.50%
6
Switch light with Arthaning A,C Drain pipe
Completion 10.00%
7
Home light compeltion hand over to
project Manager 3.00%
8 Electric Condute work of slab 6.00%
9 Down Piping on Wall with boxing 11.50%
10 Wiring with UPS Completion 11.50%
11 Gate light,Gardon light,M,C,B 4.50%
12 Service line completion 3.50%
13
Switch light with Arthaning A,C Drain pipe
Completion 10.00%
14
Home light compeltion hand over to
project Manager 3.00%
Total Work for Electric: 100.0% 0.00%
First Floor
Electric Works
Ground Floor
8/14/2019 13MProgress.xlsx
31/282
23.0%
0.0%
2.6%
0.0%
0.0%
5.0%
10.0%
15.0%
20.0%
25.0%
Ground Floor First Floor External Work Electric Work
Overall work in house # 2+3
Overall work in house # 2+3
8/14/2019 13MProgress.xlsx
32/282
8/14/2019 13MProgress.xlsx
33/282
Not
included
Not
included
8/14/2019 13MProgress.xlsx
34/282
8/14/2019 13MProgress.xlsx
35/282
8/14/2019 13MProgress.xlsx
36/282
8/14/2019 13MProgress.xlsx
37/282
8/14/2019 13MProgress.xlsx
38/282
8/14/2019 13MProgress.xlsx
39/282
8/14/2019 13MProgress.xlsx
40/282
8/14/2019 13MProgress.xlsx
41/282
8/14/2019 13MProgress.xlsx
42/282
8/14/2019 13MProgress.xlsx
43/282
9100 7.00% 130059
9462 7.28% 130059
3346 2.57% 130059
5018 3.86% 130059
6040 4.64% 130059
5406 4.16% 1300592163 1.66% 130059
18000 13.84% 130059
7200 5.54% 130059
10864 8.35% 130059
4524 3.48% 130059
9374 7.21% 130059
7760 5.97% 130059
2622 2.02% 130059
5672 4.36% 130059
1040 0.80% 130059
2200 1.69% 130059
4750 3.65% 130059
3988 3.07% 130059
6900 5.31% 130059
1140 0.88% 130059
880 0.714731 8988
1440 1.169559 8988
1380 1.120828 8988
3000 2.436582 8988 1629.666 1.306364 5738.416
608 0.493814 8988 4108.75 3.293062 5739.416
1200 0.974633 8988
480 0.389853 8988
478.8 0.391632
258.4 0.211357
2282.408 1.845379 8905.129 368.6 0.301494
5580.619 4.511551 8906.129 1349 1.103407
1042.103 0.842374 8907.129 133 0.108787
8/14/2019 13MProgress.xlsx
44/282
590.9 0.483323
8/14/2019 13MProgress.xlsx
45/282
8/14/2019 13MProgress.xlsx
46/282
8/14/2019 13MProgress.xlsx
47/282
3178.7
3178.7
3178.7
3178.7
3178.7
8/14/2019 13MProgress.xlsx
48/282
3178.7
8/14/2019 13MProgress.xlsx
49/282
Description Total %age Work Done
Ground Floor 85.5% 65.5%
First Floor 83.0% 40.0%
External Work 100.0% 0.0%
Electric Work 100.0% 23.5%
Overall work in house # 4+5 368.5% 129.0%
Brick Work upto DPC Level 15.0%
Brick work in substructure upto 9" 7.0%complete
DPC Completion 6.0%complete
Earth Filling 2.0%complete
Brick Work upto Roof Level 15.0%
Brick work upto 3'-0" Height 4.0%complete
Upto Lintel Level 4.0%complete
Casting of Lintel 3.0%complete
Above Lintel upto Roof Level 4.0%complete
Casting of RCC Slab & Stair 21.0%
Shuttring at Site 6.5%complete
Casting of Porch Slab 2.0%completeCasting of Slab (Shuttering, Steel fixing &
pouring) 10.0%complete
Casting of Stair 2.5%
Internal Plaster with Wabrobe Platform,
Kitchen Slab and Bath vanity 20.0%
Plaster under sofit (Ceiling) 5.0%complete
Internal Plaster inculding Edge plastering complete8.5%complete
All Bath & Kitchen walls inculding Edge plasteringcomplete 4.0%
Wardrobe Platforms , Bath Vanity slab, Kitchen
Slab etc. 2.5%
External Plastering 7.0%
Front Elevation 2.5%
Side/Back walls &other External Plaster4.5%
Earth filling, Brick Ballast, PCC, Stair Marble
& Window sill 7.5%
Earth filling & compaction 0.5%complete
PCC flooring 3.0%complete
Stair Marble 2.0%Window Sill 2.0%
Total Work for Ground Floor: 85.5% 65.5%
Brick Work upto Roof Level 21.0%
Brick work upto 3'-0" Height 5.0%complete
Upto Lintel Level 5.0%complete
Casting of Lintel 5.0%complete
Above Lintel upto Roof Level 6.0%complete
Ground Floor
First Floor
8/14/2019 13MProgress.xlsx
50/282
Casting of RCC Slab & Front Crown 20.0%
Shuttring at site 7.0%complete
Casting of Slab 12.0%complete
Front Crown 1.0%
Internal Plaster with Wabrobe Platform,
Kitchen Slab and Bath vanity 22.0%
Plaster under sofit (Ceiling) 5.0%
Internal Plaster complete 11.0%
All Edge plastering of Doors, Windows etc.
2.5%
Wardrobe Platforms , Bath Vanity slab, Kitchen
Slab etc. 3.5%
External Plastering 9.0%
Front Elevation external plaster 4.0%
Side wall And other external plaster with perpet
plaster 5.0%
Roof Treatment 6.0%
Roof Treatment 6.0%
Brick Ballast, PCC & Window sill 5.0%
PCC flooring 3.0%
Extra Amount in PCC flooring 1.3%
Window Sill 2.0%
Total Work for First Floor: 83.0% 40.0%
1 Altration Work 0.0%
i) Altration According to Drawing 0.0%
ii) Qibla Altration 0.0%
iii) Marketing Altration 0.0%iv) Architect Altertaion 0.0%
2
Side & Back Boundary Wall , inculding
excavation, PCC, Brick work in F&P,
DPC, Bick work in other than building,
Cement plaster & copping.
Plan No.
Amount @ 182/- Per Rft
7.00%
3 Out of Covered Area Work
i) Front Balcony 7.3%
Shuttering 0.71%Concrete with Steel 1.17%
Parapet Wall With Shuttering 1.12%
Plaster of Balcony 2.44%
P.C.C.(1:3:6) with Brick Ballast in Floor 0.49%
Tile Work in Floor 0.97%
Skirting 0.39%
ii) Side Balcony 2.6%
Shuttering 0.39%
External Works
8/14/2019 13MProgress.xlsx
51/282
Concrete with Steel 0.21%
Brick Work for Parapet Wall 0.30%
Plaster of Balcony 1.10%
P.C.C.(1:3:6) with Brick Ballast in Floor 0.11%
Tile Work in Floor 0.48%
iii) Laundry
ShutteringConcrete with Steel
Brick Work for Parapet Wall
Plaster of Balcony
P.C.C.(1:3:6) with Brick Ballast in Floor
Tile Work in Floor
iv) Big Arch with Projection 3.9%
Shuttering
Concrete with Steel
Plaster of Balcony
v) Back Tarrace Parapet Wall 4.6%
Brick Work for Parapet Wall 1.31%
Plaster of Parapet Wall 3.29%
vi) Back Terrace Flooring Work 2.7%
P.C.C.(1:3:6) with Brick Ballast in Floor 2.7%
vii) Front Terrace Parapet Wall Pouring 4.2%
vii - a) Front Terrace Parapet Wall Plaster 1.7%
viii) Top Parapet Wall Pouring 13.8%
viii - a) Top Parapet Wall Plaster 5.5%
4 External Work
i)
Front Boundary Wall , inculdingexcavation, PCC, Brick work in F&P,
DPC, Bick work in other than building,
Cement plaster, copping & steel railing .
Plan No.
Amount @ 200/- Per Rft
8.35%
ii) Toe Wall 3.5%
iii) External Flooring Work 7.2%
Earth filling in passages 1.85%
P.C.C(1:3:6) with Brick Ballast 4.51%
Earth filling in Lawn 0.84%
iv) Manholes 5.97%
vii) Ramp 2.0%
ix) Over Head Water Tank Civil Works 4.4%complete
x) AC Sills 0.8%
xi) Front crown plaster 1.7%
xii) Patio PCC inculding Tile & skirting 3.65%
xiii) Front Terrace Common wall complete 3.1%
xiv) Front Terrace PCC complete 5.3%
3.9%
8/14/2019 13MProgress.xlsx
52/282
xv) Patio wall plaster complete 0.9%
Total Work for External Area: 100.0% 0.0%
1 Electric Condute work of slab 6.00% complete
2 Down Piping on Wall with boxing 11.50% complete
3 Wiring with UPS Completion 11.50%4 Gate light,Gardon light,M,C,B and 4.50%
5 Service line completion 3.50%
6
Switch light with Arthaning A,C Drain pipe
Completion 10.00%
7
Home light compeltion hand over to
project Manager 3.00%
8 Electric Condute work of slab 6.00% complete
9 Down Piping on Wall with boxing 11.50%
10 Wiring with UPS Completion 11.50%
11 Gate light,Gardon light,M,C,B 4.50%
12 Service line completion 3.50%
13
Switch light with Arthaning A,C Drain pipe
Completion 10.00%
14
Home light compeltion hand over to
project Manager 3.00%
Total Work for Electric: 100.0% 23.50%
First Floor
Electric Works
Ground Floor
8/14/2019 13MProgress.xlsx
53/282
65.5%
40.0%
0.0%
23.5%
0.0%
10.0%
20.0%
30.0%
40.0%
50.0%
60.0%
70.0%
Ground Floor First Floor External Work Electric Work
Overall work in house # 4+5
Overall work in house # 4+5
8/14/2019 13MProgress.xlsx
54/282
8/14/2019 13MProgress.xlsx
55/282
Not
included
Not
included
8/14/2019 13MProgress.xlsx
56/282
8/14/2019 13MProgress.xlsx
57/282
8/14/2019 13MProgress.xlsx
58/282
8/14/2019 13MProgress.xlsx
59/282
8/14/2019 13MProgress.xlsx
60/282
8/14/2019 13MProgress.xlsx
61/282
8/14/2019 13MProgress.xlsx
62/282
8/14/2019 13MProgress.xlsx
63/282
8/14/2019 13MProgress.xlsx
64/282
8/14/2019 13MProgress.xlsx
65/282
9100 7.00% 130059
9462 7.28% 130059
3346 2.57% 130059
5018 3.86% 130059
6040 4.64% 130059
5406 4.16% 1300592163 1.66% 130059
18000 13.84% 130059
7200 5.54% 130059
10864 8.35% 130059
4524 3.48% 130059
9374 7.21% 130059
7760 5.97% 130059
2622 2.02% 130059
5672 4.36% 130059
1040 0.80% 130059
2200 1.69% 130059
4750 3.65% 130059
3988 3.07% 130059
6900 5.31% 130059
1140 0.88% 130059
880 0.714731 8988
1440 1.169559 8988
1380 1.120828 8988
3000 2.436582 8988 1629.666 1.306364 5738.416
608 0.493814 8988 4108.75 3.293062 5739.416
1200 0.974633 8988
480 0.389853 8988
478.8 0.391632
258.4 0.211357
2282.408 1.845379 8905.129 368.6 0.301494
5580.619 4.511551 8906.129 1349 1.103407
1042.103 0.842374 8907.129 133 0.108787
8/14/2019 13MProgress.xlsx
66/282
590.9 0.483323
8/14/2019 13MProgress.xlsx
67/282
8/14/2019 13MProgress.xlsx
68/282
8/14/2019 13MProgress.xlsx
69/282
3178.7
3178.7
3178.7
3178.7
3178.7
8/14/2019 13MProgress.xlsx
70/282
3178.7
8/14/2019 13MProgress.xlsx
71/282
Description Total %age Work Done
Ground Floor 85.5% 79.0%
First Floor 83.0% 68.8%
External Work 100.0% 10.4%
Electric Work 100.0% 58.0%
Overall work in house # 6,7 368.5% 216.2%
Brick Work upto DPC Level 15.0%
Brick work in substructure upto 9" 7.0%complete
DPC Completion 6.0%complete
Earth Filling 2.0%complete
Brick Work upto Roof Level 15.0%
Brick work upto 3'-0" Height 4.0%complete
Upto Lintel Level 4.0%complete
Casting of Lintel 3.0%complete
Above Lintel upto Roof Level 4.0%complete
Casting of RCC Slab & Stair 21.0%
Shuttring at Site 6.5%complete
Casting of Porch Slab 2.0%completeCasting of Slab (Shuttering, Steel fixing &
pouring) 10.0%complete
Casting of Stair 2.5%completeInternal Plaster with Wabrobe Platform,
Kitchen Slab and Bath vanity 20.0%
Plaster under sofit (Ceiling) 5.0%complete
Internal Plaster inculding Edge plastering complete8.5%complete
All Bath & Kitchen walls inculding Edge plasteringcomplete 4.0%complete
Wardrobe Platforms , Bath Vanity slab, Kitchen
Slab etc. 2.5%complete
External Plastering 7.0%
Front Elevation 2.5%
Side/Back walls &other External Plaster4.5%complete
Earth filling, Brick Ballast, PCC, Stair Marble
& Window sill 7.5%
Earth filling & compaction 0.5%complete
PCC flooring 3.0%complete
Stair Marble 2.0%Window Sill 2.0%
Total Work for Ground Floor: 85.5% 79.0%
Brick Work upto Roof Level 21.0%
Brick work upto 3'-0" Height 5.0%complete
Upto Lintel Level 5.0%complete
Casting of Lintel 5.0%complete
Above Lintel upto Roof Level 6.0%complete
Ground Floor
First Floor
8/14/2019 13MProgress.xlsx
72/282
Casting of RCC Slab & Front Crown 20.0%
Shuttring at site 7.0%complete
Casting of Slab 12.0%complete
Front Crown 1.0%complete
Internal Plaster with Wabrobe Platform,
Kitchen Slab and Bath vanity 22.0%
Plaster under sofit (Ceiling) 5.0%complete
Internal Plaster complete 11.0%complete
All Edge plastering of Doors, Windows etc.
2.5%complete
Wardrobe Platforms , Bath Vanity slab, Kitchen
Slab etc. 3.5%
External Plastering 9.0%
Front Elevation external plaster 4.0%
Side wall And other external plaster with perpet
plaster 5.0%complete
Roof Treatment 6.0%
Roof Treatment 6.0%
Brick Ballast, PCC & Window sill 5.0%
PCC flooring 3.0%complete
Extra Amount in PCC flooring 1.3%complete
Window Sill 2.0%
Total Work for First Floor: 83.0% 68.8%
1 Altration Work 0.0%
i) Altration According to Drawing 0.0%
ii) Qibla Altration 0.0%
iii) Marketing Altration 0.0%iv) Architect Altertaion 0.0%
2
Side & Back Boundary Wall , inculding
excavation, PCC, Brick work in F&P,
DPC, Bick work in other than building,
Cement plaster & copping.
Plan No.
Amount @ 182/- Per Rft
7.00%
3 Out of Covered Area Work
i) Front Balcony 7.3%
Shuttering 0.71%completeConcrete with Steel 1.17%complete
Parapet Wall With Shuttering 1.12%
Plaster of Balcony 2.44%
P.C.C.(1:3:6) with Brick Ballast in Floor 0.49%
Tile Work in Floor 0.97%
Skirting 0.39%
ii) Side Balcony 2.6%
Shuttering 0.39%
External Works
8/14/2019 13MProgress.xlsx
73/282
Concrete with Steel 0.21%
Brick Work for Parapet Wall 0.30%
Plaster of Balcony 1.10%
P.C.C.(1:3:6) with Brick Ballast in Floor 0.11%
Tile Work in Floor 0.48%
iii) Laundry
ShutteringConcrete with Steel
Brick Work for Parapet Wall
Plaster of Balcony
P.C.C.(1:3:6) with Brick Ballast in Floor
Tile Work in Floor
iv) Big Arch with Projection 3.9%
Shuttering
Concrete with Steel
Plaster of Balcony
v) Back Tarrace Parapet Wall 4.6%
Brick Work for Parapet Wall 1.31%complete
Plaster of Parapet Wall 3.29%complete
vi) Back Terrace Flooring Work 2.7%
P.C.C.(1:3:6) with Brick Ballast in Floor 2.7%
vii) Front Terrace Parapet Wall Pouring 4.2%
vii - a) Front Terrace Parapet Wall Plaster 1.7%
viii) Top Parapet Wall Pouring 13.8%
viii - a) Top Parapet Wall Plaster 5.5%
4 External Work
i)
Front Boundary Wall , inculdingexcavation, PCC, Brick work in F&P,
DPC, Bick work in other than building,
Cement plaster, copping & steel railing .
Plan No.
Amount @ 200/- Per Rft
8.35%
ii) Toe Wall 3.5%
iii) External Flooring Work 7.2%
Earth filling in passages 1.85%
P.C.C(1:3:6) with Brick Ballast 4.51%
Earth filling in Lawn 0.84%
iv) Manholes 5.97%
vii) Ramp 2.0%
ix) Over Head Water Tank Civil Works 4.4%complete
x) AC Sills 0.8%complete
xi) Front crown plaster 1.7%
xii) Patio PCC inculding Tile & skirting 3.65%
xiii) Front Terrace Common wall complete 3.1%
xiv) Front Terrace PCC complete 5.3%complete
3.9% complete
8/14/2019 13MProgress.xlsx
74/282
xv) Patio wall plaster complete 0.9%
Total Work for External Area: 100.0% 10.4%
1 Electric Condute work of slab 6.00% complete
2 Down Piping on Wall with boxing 11.50% complete
3 Wiring with UPS Completion 11.50% complete4 Gate light,Gardon light,M,C,B and 4.50%
5 Service line completion 3.50%
6
Switch light with Arthaning A,C Drain pipe
Completion 10.00%
7
Home light compeltion hand over to
project Manager 3.00%
8 Electric Condute work of slab 6.00% complete
9 Down Piping on Wall with boxing 11.50% complete
10 Wiring with UPS Completion 11.50% complete
11 Gate light,Gardon light,M,C,B 4.50%
12 Service line completion 3.50%
13
Switch light with Arthaning A,C Drain pipe
Completion 10.00%
14
Home light compeltion hand over to
project Manager 3.00%
Total Work for Electric: 100.0% 58.00%
First Floor
Electric Works
Ground Floor
8/14/2019 13MProgress.xlsx
75/282
79.0%
68.8%
10.4%
58.0%
0.0%
10.0%
20.0%
30.0%
40.0%
50.0%
60.0%
70.0%
80.0%
90.0%
Ground Floor First Floor External Work Electric Work
Overall work in house # 6,7
Overall work in house # 6,7
8/14/2019 13MProgress.xlsx
76/282
8/14/2019 13MProgress.xlsx
77/282
Not
included
Not
included
8/14/2019 13MProgress.xlsx
78/282
8/14/2019 13MProgress.xlsx
79/282
8/14/2019 13MProgress.xlsx
80/282
8/14/2019 13MProgress.xlsx
81/282
8/14/2019 13MProgress.xlsx
82/282
8/14/2019 13MProgress.xlsx
83/282
8/14/2019 13MProgress.xlsx
84/282
8/14/2019 13MProgress.xlsx
85/282
8/14/2019 13MProgress.xlsx
86/282
8/14/2019 13MProgress.xlsx
87/282
9100 7.00% 130059
9462 7.28% 130059
3346 2.57% 130059
5018 3.86% 130059
6040 4.64% 130059
5406 4.16% 1300592163 1.66% 130059
18000 13.84% 130059
7200 5.54% 130059
10864 8.35% 130059
4524 3.48% 130059
9374 7.21% 130059
7760 5.97% 130059
2622 2.02% 130059
5672 4.36% 130059
1040 0.80% 130059
2200 1.69% 130059
4750 3.65% 130059
3988 3.07% 130059
6900 5.31% 130059
1140 0.88% 130059
880 0.714731 8988
1440 1.169559 8988
1380 1.120828 8988
3000 2.436582 8988 1629.666 1.306364 5738.416
608 0.493814 8988 4108.75 3.293062 5739.416
1200 0.974633 8988
480 0.389853 8988
478.8 0.391632
258.4 0.211357
2282.408 1.845379 8905.129 368.6 0.301494
5580.619 4.511551 8906.129 1349 1.103407
1042.103 0.842374 8907.129 133 0.108787
8/14/2019 13MProgress.xlsx
88/282
590.9 0.483323
8/14/2019 13MProgress.xlsx
89/282
8/14/2019 13MProgress.xlsx
90/282
8/14/2019 13MProgress.xlsx
91/282
3178.7
3178.7
3178.7
3178.7
3178.7
8/14/2019 13MProgress.xlsx
92/282
3178.7
8/14/2019 13MProgress.xlsx
93/282
Description Total %age Work Done
Ground Floor 85.5% 81.5%
First Floor 83.0% 82.3%
External Work 100.0% 61.7%
Electric Work 100.0% 58.0%
Overall work in house # 8,9 368.5% 283.5%
Brick Work upto DPC Level 15.0%
Brick work in substructure upto 9" 7.0%complete
DPC Completion 6.0%complete
Earth Filling 2.0%complete
Brick Work upto Roof Level 15.0%
Brick work upto 3'-0" Height 4.0%complete
Upto Lintel Level 4.0%complete
Casting of Lintel 3.0%complete
Above Lintel upto Roof Level 4.0%complete
Casting of RCC Slab & Stair 21.0%
Shuttring at Site 6.5%complete
Casting of Porch Slab 2.0%completeCasting of Slab (Shuttering, Steel fixing &
pouring) 10.0%complete
Casting of Stair 2.5%completeInternal Plaster with Wabrobe Platform,
Kitchen Slab and Bath vanity 20.0%
Plaster under sofit (Ceiling) 5.0%complete
Internal Plaster inculding Edge plastering complete8.5%complete
All Bath & Kitchen walls inculding Edge plasteringcomplete 4.0%complete
Wardrobe Platforms , Bath Vanity slab, Kitchen
Slab etc. 2.5%complete
External Plastering 7.0%
Front Elevation 2.5%complete
Side/Back walls &other External Plaster4.5%complete
Earth filling, Brick Ballast, PCC, Stair Marble
& Window sill 7.5%
Earth filling & compaction 0.5%complete
PCC flooring 3.0%complete
Stair Marble 2.0%Window Sill 2.0%
Total Work for Ground Floor: 85.5% 81.5%
Brick Work upto Roof Level 21.0%
Brick work upto 3'-0" Height 5.0%complete
Upto Lintel Level 5.0%complete
Casting of Lintel 5.0%complete
Above Lintel upto Roof Level 6.0%complete
Ground Floor
First Floor
8/14/2019 13MProgress.xlsx
94/282
Casting of RCC Slab & Front Crown 20.0%
Shuttring at site 7.0%complete
Casting of Slab 12.0%complete
Front Crown 1.0%complete
Internal Plaster with Wabrobe Platform,
Kitchen Slab and Bath vanity 22.0%
Plaster under sofit (Ceiling) 5.0%complete
Internal Plaster complete 11.0%complete
All Edge plastering of Doors, Windows etc.
2.5%complete
Wardrobe Platforms , Bath Vanity slab, Kitchen
Slab etc. 3.5%complete
External Plastering 9.0%
Front Elevation external plaster 4.0%complete
Side wall And other external plaster with perpet
plaster 5.0%complete
Roof Treatment 6.0%
Roof Treatment 6.0%complete
Brick Ballast, PCC & Window sill 5.0%
PCC flooring 3.0%complete
Extra Amount in PCC flooring 1.3%complete
Window Sill 2.0%
Total Work for First Floor: 83.0% 82.3%
1 Altration Work 0.0%
i) Altration According to Drawing 0.0%
ii) Qibla Altration 0.0%
iii) Marketing Altration 0.0%iv) Architect Altertaion 0.0%
2
Side & Back Boundary Wall , inculding
excavation, PCC, Brick work in F&P,
DPC, Bick work in other than building,
Cement plaster & copping.
Plan No.
Amount @ 182/- Per Rft
7.00% complete
3 Out of Covered Area Work
i) Front Balcony 7.3%
Shuttering 0.71%completeConcrete with Steel 1.17%complete
Parapet Wall With Shuttering 1.12%complete
Plaster of Balcony 2.44%complete
P.C.C.(1:3:6) with Brick Ballast in Floor 0.49%complete
Tile Work in Floor 0.97%
Skirting 0.39%
ii) Side Balcony 2.6%
Shuttering 0.39%complete
External Works
8/14/2019 13MProgress.xlsx
95/282
Concrete with Steel 0.21%complete
Brick Work for Parapet Wall 0.30%complete
Plaster of Balcony 1.10%complete
P.C.C.(1:3:6) with Brick Ballast in Floor 0.11%complete
Tile Work in Floor 0.48%complete
iii) Laundry
ShutteringConcrete with Steel
Brick Work for Parapet Wall
Plaster of Balcony
P.C.C.(1:3:6) with Brick Ballast in Floor
Tile Work in Floor
iv) Big Arch with Projection 3.9%
Shuttering
Concrete with Steel
Plaster of Balcony
v) Back Tarrace Parapet Wall 4.6%
Brick Work for Parapet Wall 1.31%complete
Plaster of Parapet Wall 3.29%complete
vi) Back Terrace Flooring Work 2.7%
P.C.C.(1:3:6) with Brick Ballast in Floor 2.7%complete
vii) Front Terrace Parapet Wall Pouring 4.2%complete
vii - a) Front Terrace Parapet Wall Plaster 1.7%complete
viii) Top Parapet Wall Pouring 13.8%complete
viii - a) Top Parapet Wall Plaster 5.5%complete
4 External Work
i)
Front Boundary Wall , inculdingexcavation, PCC, Brick work in F&P,
DPC, Bick work in other than building,
Cement plaster, copping & steel railing .
Plan No.
Amount @ 200/- Per Rft
8.35%
ii) Toe Wall 3.5%complete
iii) External Flooring Work 7.2%
Earth filling in passages 1.85%complete
P.C.C(1:3:6) with Brick Ballast 4.51%complete
Earth filling in Lawn 0.84%complete
iv) Manholes 5.97%complete
vii) Ramp 2.0%
ix) Over Head Water Tank Civil Works 4.4%complete
x) AC Sills 0.8%complete
xi) Front crown plaster 1.7%complete
xii) Patio PCC inculding Tile & skirting 3.65%complete
xiii) Front Terrace Common wall complete 3.1%complete
xiv) Front Terrace PCC complete 5.3%complete
3.9% complete
8/14/2019 13MProgress.xlsx
96/282
xv) Patio wall plaster complete 0.9%complete
Total Work for External Area: 100.0% 61.7%
1 Electric Condute work of slab 6.00% complete
2 Down Piping on Wall with boxing 11.50% complete
3 Wiring with UPS Completion 11.50% complete4 Gate light,Gardon light,M,C,B and 4.50%
5 Service line completion 3.50%
6
Switch light with Arthaning A,C Drain pipe
Completion 10.00%
7
Home light compeltion hand over to
project Manager 3.00%
8 Electric Condute work of slab 6.00% complete
9 Down Piping on Wall with boxing 11.50% complete
10 Wiring with UPS Completion 11.50% complete
11 Gate light,Gardon light,M,C,B 4.50%
12 Service line completion 3.50%
13
Switch light with Arthaning A,C Drain pipe
Completion 10.00%
14
Home light compeltion hand over to
project Manager 3.00%
Total Work for Electric: 100.0% 58.00%
Electric Works
Ground Floor
First Floor
8/14/2019 13MProgress.xlsx
97/282
81.5% 82.3%
61.7%58.0%
0.0%
10.0%
20.0%
30.0%
40.0%
50.0%
60.0%
70.0%
80.0%
90.0%
Ground Floor First Floor External Work Electric Work
Overall work in house # 8,9
Overall work in house # 8,9
8/14/2019 13MProgress.xlsx
98/282
8/14/2019 13MProgress.xlsx
99/282
Not
included
Not
included
8/14/2019 13MProgress.xlsx
100/282
8/14/2019 13MProgress.xlsx
101/282
8/14/2019 13MProgress.xlsx
102/282
8/14/2019 13MProgress.xlsx
103/282
8/14/2019 13MProgress.xlsx
104/282
8/14/2019 13MProgress.xlsx
105/282
8/14/2019 13MProgress.xlsx
106/282
8/14/2019 13MProgress.xlsx
107/282
8/14/2019 13MProgress.xlsx
108/282
8/14/2019 13MProgress.xlsx
109/282
9100 7.00% 130059
9462 7.28% 130059
3346 2.57% 130059
5018 3.86% 130059
6040 4.64% 130059
5406 4.16% 1300592163 1.66% 130059
18000 13.84% 130059
7200 5.54% 130059
10864 8.35% 130059
4524 3.48% 130059
9374 7.21% 130059
7760 5.97% 130059
2622 2.02% 130059
5672 4.36% 130059
1040 0.80% 130059
2200 1.69% 130059
4750 3.65% 130059
3988 3.07% 130059
6900 5.31% 130059
1140 0.88% 130059
880 0.714731 8988
1440 1.169559 8988
1380 1.120828 8988
3000 2.436582 8988 1629.666 1.306364 5738.416
608 0.493814 8988 4108.75 3.293062 5739.416
1200 0.974633 8988
480 0.389853 8988
478.8 0.391632
258.4 0.211357
2282.408 1.845379 8905.129 368.6 0.301494
5580.619 4.511551 8906.129 1349 1.103407
1042.103 0.842374 8907.129 133 0.108787
8/14/2019 13MProgress.xlsx
110/282
590.9 0.483323
8/14/2019 13MProgress.xlsx
111/282
8/14/2019 13MProgress.xlsx
112/282
8/14/2019 13MProgress.xlsx
113/282
3178.7
3178.7
3178.7
3178.7
3178.7
8/14/2019 13MProgress.xlsx
114/282
3178.7
8/14/2019 13MProgress.xlsx
115/282
Description Total %age Work Done
Ground Floor 85.5% 81.5%
First Floor 83.0% 78.8%
External Work 100.0% 59.1%
Electric Work 100.0% 58.0%
Overall work in house # 10,11 368.5% 277.4%
Brick Work upto DPC Level 15.0%
Brick work in substructure upto 9" 7.0%complete
DPC Completion 6.0%complete
Earth Filling 2.0%complete
Brick Work upto Roof Level 15.0%
Brick work upto 3'-0" Height 4.0%complete
Upto Lintel Level 4.0%complete
Casting of Lintel 3.0%complete
Above Lintel upto Roof Level 4.0%complete
Casting of RCC Slab & Stair 21.0%
Shuttring at Site 6.5%complete
Casting of Porch Slab 2.0%completeCasting of Slab (Shuttering, Steel fixing &
pouring) 10.0%complete
Casting of Stair 2.5%completeInternal Plaster with Wabrobe Platform,
Kitchen Slab and Bath vanity 20.0%
Plaster under sofit (Ceiling) 5.0%complete
Internal Plaster inculding Edge plastering complete8.5%complete
All Bath & Kitchen walls inculding Edge plasteringcomplete 4.0%complete
Wardrobe Platforms , Bath Vanity slab, Kitchen
Slab etc. 2.5%complete
External Plastering 7.0%
Front Elevation 2.5%complete
Side/Back walls &other External Plaster4.5%complete
Earth filling, Brick Ballast, PCC, Stair Marble
& Window sill 7.5%
Earth filling & compaction 0.5%complete
PCC flooring 3.0%complete
Stair Marble 2.0%Window Sill 2.0%
Total Work for Ground Floor: 85.5% 81.5%
Brick Work upto Roof Level 21.0%
Brick work upto 3'-0" Height 5.0%complete
Upto Lintel Level 5.0%complete
Casting of Lintel 5.0%complete
Above Lintel upto Roof Level 6.0%complete
Ground Floor
First Floor
8/14/2019 13MProgress.xlsx
116/282
Casting of RCC Slab & Front Crown 20.0%
Shuttring at site 7.0%complete
Casting of Slab 12.0%complete
Front Crown 1.0%complete
Internal Plaster with Wabrobe Platform,
Kitchen Slab and Bath vanity 22.0%
Plaster under sofit (Ceiling) 5.0%complete
Internal Plaster complete 11.0%complete
All Edge plastering of Doors, Windows etc.
2.5%complete
Wardrobe Platforms , Bath Vanity slab, Kitchen
Slab etc. 3.5%
External Plastering 9.0%
Front Elevation external plaster 4.0%complete
Side wall And other external plaster with perpet
plaster 5.0%complete
Roof Treatment 6.0%
Roof Treatment 6.0%complete
Brick Ballast, PCC & Window sill 5.0%
PCC flooring 3.0%complete
Extra Amount in PCC flooring 1.3%complete
Window Sill 2.0%
Total Work for First Floor: 83.0% 78.8%
1 Altration Work 0.0%
i) Altration According to Drawing 0.0%
ii) Qibla Altration 0.0%
iii) Marketing Altration 0.0%iv) Architect Altertaion 0.0%
2
Side & Back Boundary Wall , inculding
excavation, PCC, Brick work in F&P,
DPC, Bick work in other than building,
Cement plaster & copping.
Plan No.
Amount @ 182/- Per Rft
7.00% complete
3 Out of Covered Area Work
i) Front Balcony 7.3%
Shuttering 0.71%completeConcrete with Steel 1.17%complete
Parapet Wall With Shuttering 1.12%complete
Plaster of Balcony 2.44%complete
P.C.C.(1:3:6) with Brick Ballast in Floor 0.49%complete
Tile Work in Floor 0.97%
Skirting 0.39%
ii) Side Balcony 2.6%
Shuttering 0.39%
External Works
8/14/2019 13MProgress.xlsx
117/282
Concrete with Steel 0.21%
Brick Work for Parapet Wall 0.30%
Plaster of Balcony 1.10%
P.C.C.(1:3:6) with Brick Ballast in Floor 0.11%
Tile Work in Floor 0.48%
iii) Laundry
ShutteringConcrete with Steel
Brick Work for Parapet Wall
Plaster of Balcony
P.C.C.(1:3:6) with Brick Ballast in Floor
Tile Work in Floor
iv) Big Arch with Projection 3.9%
Shuttering
Concrete with Steel
Plaster of Balcony
v) Back Tarrace Parapet Wall 4.6%
Brick Work for Parapet Wall 1.31%complete
Plaster of Parapet Wall 3.29%complete
vi) Back Terrace Flooring Work 2.7%
P.C.C.(1:3:6) with Brick Ballast in Floor 2.7%complete
vii) Front Terrace Parapet Wall Pouring 4.2%complete
vii - a) Front Terrace Parapet Wall Plaster 1.7%complete
viii) Top Parapet Wall Pouring 13.8%complete
viii - a) Top Parapet Wall Plaster 5.5%complete
4 External Work
i)
Front Boundary Wall , inculdingexcavation, PCC, Brick work in F&P,
DPC, Bick work in other than building,
Cement plaster, copping & steel railing .
Plan No.
Amount @ 200/- Per Rft
8.35%
ii) Toe Wall 3.5%complete
iii) External Flooring Work 7.2%
Earth filling in passages 1.85%complete
P.C.C(1:3:6) with Brick Ballast 4.51%complete
Earth filling in Lawn 0.84%complete
iv) Manholes 5.97%complete
vii) Ramp 2.0%
ix) Over Head Water Tank Civil Works 4.4%complete
x) AC Sills 0.8%complete
xi) Front crown plaster 1.7%complete
xii) Patio PCC inculding Tile & skirting 3.65%
xiii) Front Terrace Common wall complete 3.1%complete
xiv) Front Terrace PCC complete 5.3%complete
3.9% complete
8/14/2019 13MProgress.xlsx
118/282
xv) Patio wall plaster complete 0.9%complete
Total Work for External Area: 100.0% 59.1%
1 Electric Condute work of slab 6.00% complete
2 Down Piping on Wall with boxing 11.50% complete
3 Wiring with UPS Completion 11.50% complete4 Gate light,Gardon light,M,C,B and 4.50%
5 Service line completion 3.50%
6
Switch light with Arthaning A,C Drain pipe
Completion 10.00%
7
Home light compeltion hand over to
project Manager 3.00%
8 Electric Condute work of slab 6.00% complete
9 Down Piping on Wall with boxing 11.50% complete
10 Wiring with UPS Completion 11.50% complete
11 Gate light,Gardon light,M,C,B 4.50%
12 Service line completion 3.50%
13
Switch light with Arthaning A,C Drain pipe
Completion 10.00%
14
Home light compeltion hand over to
project Manager 3.00%
Total Work for Electric: 100.0% 58.00%
Electric Works
Ground Floor
First Floor
8/14/2019 13MProgress.xlsx
119/282
81.5%78.8%
59.1% 58.0%
0.0%
10.0%
20.0%
30.0%
40.0%
50.0%
60.0%
70.0%
80.0%
90.0%
Ground Floor First Floor External Work Electric Work
Overall work in house # 10,11
Overall work in house #
10,11
8/14/2019 13MProgress.xlsx
120/282
8/14/2019 13MProgress.xlsx
121/282
Not
included
Not
included
8/14/2019 13MProgress.xlsx
122/282
8/14/2019 13MProgress.xlsx
123/282
8/14/2019 13MProgress.xlsx
124/282
8/14/2019 13MProgress.xlsx
125/282
8/14/2019 13MProgress.xlsx
126/282
8/14/2019 13MProgress.xlsx
127/282
8/14/2019 13MProgress.xlsx
128/282
8/14/2019 13MProgress.xlsx
129/282
8/14/2019 13MProgress.xlsx
130/282
8/14/2019 13MProgress.xlsx
131/282
9100 7.00% 130059
9462 7.28% 130059
3346 2.57% 130059
5018 3.86% 130059
6040 4.64% 130059
5406 4.16% 1300592163 1.66% 130059
18000 13.84% 130059
7200 5.54% 130059
10864 8.35% 130059
4524 3.48% 130059
9374 7.21% 130059
7760 5.97% 130059
2622 2.02% 130059
5672 4.36% 130059
1040 0.80% 130059
2200 1.69% 130059
4750 3.65% 130059
3988 3.07% 130059
6900 5.31% 130059
1140 0.88% 130059
880 0.714731 8988
1440 1.169559 8988
1380 1.120828 8988
3000 2.436582 8988 1629.666 1.306364 5738.416
608 0.493814 8988 4108.75 3.293062 5739.416
1200 0.974633 8988
480 0.389853 8988
478.8 0.391632
258.4 0.211357
2282.408 1.845379 8905.129 368.6 0.301494
5580.619 4.511551 8906.129 1349 1.103407
1042.103 0.842374 8907.129 133 0.108787
8/14/2019 13MProgress.xlsx
132/282
590.9 0.483323
8/14/2019 13MProgress.xlsx
133/282
8/14/2019 13MProgress.xlsx
134/282
8/14/2019 13MProgress.xlsx
135/282
3178.7
3178.7
3178.7
3178.7
3178.7
8/14/2019 13MProgress.xlsx
136/282
3178.7
8/14/2019 13MProgress.xlsx
137/282
Description Total %age
Ground Floor 85.5%
First Floor 83.0%
External Work 100.0%
Electric Work 100.0%
Overall work in house # 12,13 368.50%
Brick Work upto DPC Level 15.0%
Brick work in substructure upto 9" 7.0%
DPC Completion 6.0%
Earth Filling 2.0%
Brick Work upto Roof Level 15.0%
Brick work upto 3'-0" Height 4.0%
Upto Lintel Level 4.0%
Casting of Lintel 3.0%
Above Lintel upto Roof Level 4.0%
Casting of RCC Slab & Stair 21.0%
Shuttring at Site 6.5%
Casting of Porch Slab 2.0%
Casting of Slab (Shuttering, Steel fixing & pouring) 10.0%
Casting of Stair 2.5%
Internal Plaster with Wabrobe Platform, Kitchen Slab and
Bath vanity 20.0%
Plaster under sofit (Ceiling) 5.0%
Internal Plaster inculding Edge plastering complete 8.5%
All Bath & Kitchen walls inculding Edge plastering complete4.0%
Wardrobe Platforms , Bath Vanity slab, Kitchen Slab etc.
2.5%
External Plastering 7.0%
Front Elevation 2.5%
Side/Back walls &other External Plaster4.5%
Earth filling, Brick Ballast, PCC, Stair Marble & Window
sill 7.5%
Earth filling & compaction 0.5%
PCC flooring 3.0%
Stair Marble 2.0%
Window Sill 2.0%
Total Work for Ground Floor: 85.5%
Brick Work upto Roof Level 21.0%
Brick work upto 3'-0" Height 5.0%
Upto Lintel Level 5.0%
Casting of Lintel 5.0%
Above Lintel upto Roof Level 6.0%
Casting of RCC Slab & Front Crown 20.0%
Ground Floor
First Floor
8/14/2019 13MProgress.xlsx
138/282
Shuttring at site 7.0%
Casting of Slab 12.0%
Front Crown 1.0%
Internal Plaster with Wabrobe Platform, Kitchen Slab and
Bath vanity 22.0%
Plaster under sofit (Ceiling) 5.0%
Internal Plaster complete 11.0%
All Edge plastering of Doors, Windows etc.
2.5%
Wardrobe Platforms , Bath Vanity slab, Kitchen Slab etc.
3.5%
External Plastering 9.0%
Front Elevation external plaster 4.0%
Side wall And other external plaster with perpet plaster 5.0%
Roof Treatment 6.0%
Roof Treatment 6.0%
Brick Ballast, PCC & Window sill 5.0%
PCC flooring 3.0%
Extra Amount in PCC flooring 1.3%
Window Sill 2.0%
Total Work for First Floor: 83.0%
1 Altration Work 0.0%
i) Altration According to Drawing 0.0%
ii) Qibla Altration 0.0%
iii) Marketing Altration 0.0%
iv) Architect Altertaion 0.0%
2
Side & Back Boundary Wall , inculding excavation,
PCC, Brick work in F&P, DPC, Bick work in other
than building, Cement plaster & copping.
Plan No.
Amount @ 182/- Per Rft
7.00%
3 Out of Covered Area Work
i) Front Balcony 7.3%
Shuttering 0.71%
Concrete with Steel 1.17%
Parapet Wall With Shuttering 1.12%Plaster of Balcony 2.44%
P.C.C.(1:3:6) with Brick Ballast in Floor 0.49%
Tile Work in Floor 0.97%
Skirting 0.39%
ii) Side Balcony 2.6%
Shuttering 0.39%
Concrete with Steel 0.21%
Brick Work for Parapet Wall 0.30%
External Works
8/14/2019 13MProgress.xlsx
139/282
Plaster of Balcony 1.10%
P.C.C.(1:3:6) with Brick Ballast in Floor 0.11%
Tile Work in Floor 0.48%
iii) Laundry
Shuttering
Concrete with Steel
Brick Work for Parapet WallPlaster of Balcony
P.C.C.(1:3:6) with Brick Ballast in Floor
Tile Work in Floor
iv) Big Arch with Projection 3.9%
Shuttering
Concrete with Steel
Plaster of Balcony
v) Back Tarrace Parapet Wall 4.6%
Brick Work for Parapet Wall 1.31%
Plaster of Parapet Wall 3.29%
vi) Back Terrace Flooring Work 2.7%
P.C.C.(1:3:6) with Brick Ballast in Floor 2.7%
vii) Front Terrace Parapet Wall Pouring 4.2%
vii - a) Front Terrace Parapet Wall Plaster 1.7%
viii) Top Parapet Wall Pouring 13.8%
viii - a) Top Parapet Wall Plaster 5.5%
4 External Work
i)
Front Boundary Wall , inculding excavation, PCC,
Brick work in F&P, DPC, Bick work in other than
building, Cement plaster, copping & steel railing .
Plan No.
Amount @ 200/- Per Rft
8.35%
ii) Toe Wall 3.5%
iii) External Flooring Work 7.2%
Earth filling in passages 1.85%
P.C.C(1:3:6) with Brick Ballast 4.51%
Earth filling in Lawn 0.84%
iv) Manholes 5.97%
vii) Ramp 2.0%
ix) Over Head Water Tank Civil Works4.4%
x) AC Sills 0.8%
xi) Front crown plaster 1.7%
xii) Patio PCC inculding Tile & skirting 3.65%
xiii) Front Terrace Common wall complete 3.1%
xiv) Front Terrace PCC complete 5.3%
xv) Patio wall plaster complete 0.9%
Total Work for External Area: 100.0%
Electric Works
3.9%
8/14/2019 13MProgress.xlsx
140/282
1 Electric Condute work of slab 6.00%
2 Down Piping on Wall with boxing 11.50%
3 Wiring with UPS Completion 11.50%
4 Gate light,Gardon light,M,C,B and 4.50%
5 Service line completion 3.50%
6 Switch light with Arthaning A,C Drain pipe Completion 10.00%
7 Home light compeltion hand over to project Manager 3.00%
8 Electric Condute work of slab 6.00%
9 Down Piping on Wall with boxing 11.50%
10 Wiring with UPS Completion 11.50%
11 Gate light,Gardon light,M,C,B 4.50%
12 Service line completion 3.50%
13 Switch light with Arthaning A,C Drain pipe Completion 10.00%
14 Home light compeltion hand over to project Manager 3.00%
Total Work for Electric: 100.0%
Ground Floor
First Floor
8/14/2019 13MProgress.xlsx
141/282
Work Done
85.5%
84.3%
63.1%
58.0%
290.91%
complete
complete
complete
complete
complete
complete
complete
complete
complete
complete
complete
complete
complete
complete
complete
complete
complete
complete
complete
complete
complete
85.5%
complete
complete
complete
complete
85.5% 84.3%
63.1%
0.0%
10.0%
20.0%
30.0%
40.0%
50.0%
60.0%
70.0%
80.0%
90.0%
Ground Floor First Floor External Work Ele
Overall work in house # 12,13
Overall work in house #
8/14/2019 13MProgress.xlsx
142/282
complete
complete
complete
complete
complete
complete
complete
complete
complete
complete
complete
complete
complete
84.3%
complete
complete
complete
completecomplete
complete
complete
complete
complete
complete
complete not
8/14/2019 13MProgress.xlsx
143/282
complete
complete
complete
complete
complete
complete
complete
complete
complete
complete
complete
complete
complete
complete
complete
complete
complete
complete
complete
complete
complete
86.0%
included
notincluded
complete
8/14/2019 13MProgress.xlsx
144/282
complete
complete
complete
complete
complete
complete
58.00%
8/14/2019 13MProgress.xlsx
145/282
58.0%
ctric Work
8/14/2019 13MProgress.xlsx
146/282
8/14/2019 13MProgress.xlsx
147/282
8/14/2019 13MProgress.xlsx
148/282
8/14/2019 13MProgress.xlsx
149/282
8/14/2019 13MProgress.xlsx
150/282
8/14/2019 13MProgress.xlsx
151/282
8/14/2019 13MProgress.xlsx
152/282
8/14/2019 13MProgress.xlsx
153/282
9100 7.00% 130059
9462 7.28% 130059
3346 2.57% 130059
5018 3.86% 130059
6040 4.64% 130059
5406 4.16% 1300592163 1.66% 130059
18000 13.84% 130059
7200 5.54% 130059
10864 8.35% 130059
4524 3.48% 130059
9374 7.21% 130059
7760 5.97% 130059
2622 2.02% 130059
5672 4.36% 130059
1040 0.80% 130059
2200 1.69% 130059
4750 3.65% 130059
3988 3.07% 130059
6900 5.31% 130059
1140 0.88% 130059
880 0.714731 8988
1440 1.169559 8988
1380 1.120828 8988
3000 2.436582 8988 1629.666
608 0.493814 8988 4108.75
1200 0.974633 8988
480 0.389853 8988
2282.408 1.845379 8905.129
5580.619 4.511551 8906.129
1042.103 0.842374 8907.129
8/14/2019 13MProgress.xlsx
154/282
8/14/2019 13MProgress.xlsx
155/282
8/14/2019 13MProgress.xlsx
156/282
8/14/2019 13MProgress.xlsx
157/282
1.306364 5738.416
3.293062 5739.416
478.8 0.391632 3178.7
258.4 0.211357 3178.7
368.6 0.301494 3178.7
1349 1.103407 3178.7
133 0.108787 3178.7
590.9 0.483323 3178.7
8/14/2019 13MProgress.xlsx
158/282
Description Total %age Work Done
Ground Floor 85.5% 74.0%
First Floor 83.0% 73.8%
External Work 100.0% 7.3%
Electric Work 100.0% 35.0%
Overall work in house # 14,15 368.5% 190.1%
Brick Work upto DPC Level 15.0%
Brick work in substructure upto 9" 7.0%Complete
DPC Completion 6.0%Complete
Earth Filling 2.0%Complete
Brick Work upto Roof Level 15.0%
Brick work upto 3'-0" Height 4.0%Complete
Upto Lintel Level 4.0%Complete
Casting of Lintel 3.0%Complete
Above Lintel upto Roof Level 4.0%Complete
Casting of RCC Slab & Stair 21.0%
Shuttring at Site 6.5%Complete
Casting of Porch Slab 2.0%CompleteCasting of Slab (Shuttering, Steel fixing &
pouring) 10.0%Complete
Casting of Stair 2.5%
Internal Plaster with Wabrobe Platform,
Kitchen Slab and Bath vanity 20.0%
Plaster under sofit (Ceiling) 5.0%Complete
Internal Plaster inculding Edge plastering complete8.5%Complete
All Bath & Kitchen walls inculding Edge plasteringcomplete 4.0%Complete
Wardrobe Platforms , Bath Vanity slab, Kitchen
Slab etc. 2.5%
External Plastering 7.0%
Front Elevation 2.5%
Side/Back walls &other External Plaster4.5%Complete
Earth filling, Brick Ballast, PCC, Stair Marble
& Window sill 7.5%
Earth filling & compaction 0.5%Complete
PCC flooring 3.0%Complete
Stair Marble 2.0%Window Sill 2.0%
Total Work for Ground Floor: 85.5% 74.0%
Brick Work upto Roof Level 21.0%
Brick work upto 3'-0" Height 5.0%Complete
Upto Lintel Level 5.0%Complete
Casting of Lintel 5.0%Complete
Above Lintel upto Roof Level 6.0%Complete
Ground Floor
First Floor
8/14/2019 13MProgress.xlsx
159/282
Casting of RCC Slab & Front Crown 20.0%
Shuttring at site 7.0%Complete
Casting of Slab 12.0%Complete
Front Crown 1.0%
Internal Plaster with Wabrobe Platform,
Kitchen Slab and Bath vanity 22.0%
Plaster under sofit (Ceiling) 5.0%Complete
Internal Plaster complete 11.0%Complete
All Edge plastering of Doors, Windows etc.
2.5%Complete
Wardrobe Platforms , Bath Vanity slab, Kitchen
Slab etc. 3.5%
External Plastering 9.0%
Front Elevation external plaster 4.0%
Side wall And other external plaster with perpet
plaster 5.0%Complete
Roof Treatment 6.0%
Roof Treatment 6.0%Complete
Brick Ballast, PCC & Window sill 5.0%
PCC flooring 3.0%Complete
Extra Amount in PCC flooring 1.3%Complete
Window Sill 2.0%
Total Work for First Floor: 83.0% 73.8%
1 Altration Work 0.0%
i) Altration According to Drawing 0.0%
ii) Qibla Altration 0.0%
iii) Marketing Altration 0.0%iv) Architect Altertaion 0.0%
2
Side & Back Boundary Wall , inculding
excavation, PCC, Brick work in F&P,
DPC, Bick work in other than building,
Cement plaster & copping.
Plan No.
Amount @ 182/- Per Rft
7.00%
3 Out of Covered Area Work
i) Front Balcony 7.3%
Shuttering 0.71%Concrete with Steel 1.17%
Parapet Wall With Shuttering 1.12%
Plaster of Balcony 2.44%
P.C.C.(1:3:6) with Brick Ballast in Floor 0.49%
Tile Work in Floor 0.97%
Skirting 0.39%
ii) Side Balcony 2.6%
Shuttering 0.39%
External Works
8/14/2019 13MProgress.xlsx
160/282
Concrete with Steel 0.21%
Brick Work for Parapet Wall 0.30%
Plaster of Balcony 1.10%
P.C.C.(1:3:6) with Brick Ballast in Floor 0.11%
Tile Work in Floor 0.48%
iii) Laundry
ShutteringConcrete with Steel
Brick Work for Parapet Wall
Plaster of Balcony
P.C.C.(1:3:6) with Brick Ballast in Floor
Tile Work in Floor
iv) Big Arch with Projection 3.9%
Shuttering
Concrete with Steel
Plaster of Balcony
v) Back Tarrace Parapet Wall 4.6%
Brick Work for Parapet Wall 1.31%complete
Plaster of Parapet Wall 3.29%complete
vi) Back Terrace Flooring Work 2.7%
P.C.C.(1:3:6) with Brick Ballast in Floor 2.7%complete
vii) Front Terrace Parapet Wall Pouring 4.2%
vii - a) Front Terrace Parapet Wall Plaster 1.7%
viii) Top Parapet Wall Pouring 13.8%
viii - a) Top Parapet Wall Plaster 5.5%
4 External Work
i)
Front Boundary Wall , inculdingexcavation, PCC, Brick work in F&P,
DPC, Bick work in other than building,
Cement plaster, copping & steel railing .
Plan No.
Amount @ 200/- Per Rft
8.35%
ii) Toe Wall 3.5%
iii) External Flooring Work 7.2%
Earth filling in passages 1.85%
P.C.C(1:3:6) with Brick Ballast 4.51%
Earth filling in Lawn 0.84%
iv) Manholes 5.97%
vii) Ramp 2.0%
ix) Over Head Water Tank Civil Works 4.4%complete
x) AC Sills 0.8%complete
xi) Front crown plaster 1.7%
xii) Patio PCC inculding Tile & skirting 3.65%
xiii) Front Terrace Common wall complete 3.1%
xiv) Front Terrace PCC complete 5.3%complete
3.9%
8/14/2019 13MProgress.xlsx
161/282
xv) Patio wall plaster complete 0.9%complete
Total Work for External Area: 100.0% 7.3%
1 Electric Condute work of slab 6.00% complete
2 Down Piping on Wall with boxing 11.50% complete
3 Wiring with UPS Completion 11.50%4 Gate light,Gardon light,M,C,B and 4.50%
5 Service line completion 3.50%
6
Switch light with Arthaning A,C Drain pipe
Completion 10.00%
7
Home light compeltion hand over to
project Manager 3.00%
8 Electric Condute work of slab 6.00% complete
9 Down Piping on Wall with boxing 11.50% complete
10 Wiring with UPS Completion 11.50%
11 Gate light,Gardon light,M,C,B 4.50%
12 Service line completion 3.50%
13
Switch light with Arthaning A,C Drain pipe
Completion 10.00%
14
Home light compeltion hand over to
project Manager 3.00%
Total Work for Electric: 100.0% 35.00%
Electric Works
Ground Floor
First Floor
8/14/2019 13MProgress.xlsx
162/282
8/14/2019 13MProgress.xlsx
163/282
8/14/2019 13MProgress.xlsx
164/282
.
8/14/2019 13MProgress.xlsx
165/282
74.0% 73.8%
7.3%
35.0%
0.0%
10.0%
20.0%
30.0%
40.0%
50.0%
60.0%
70.0%
80.0%
Ground Floor First Floor External Work Electric Work
Overall work in house # 14,15
Overall work in house # 14,15
8/14/2019 13MProgress.xlsx
166/282
All Most
8/14/2019 13MProgress.xlsx
167/282
Not
included
Not
included
8/14/2019 13MProgress.xlsx
168/282
8/14/2019 13MProgress.xlsx
169/282
8/14/2019 13MProgress.xlsx
170/282
8/14/2019 13MProgress.xlsx
171/282
8/14/2019 13MProgress.xlsx
172/282
8/14/2019 13MProgress.xlsx
173/282
8/14/2019 13MProgress.xlsx
174/282
8/14/2019 13MProgress.xlsx
175/282
8/14/2019 13MProgress.xlsx
176/282
8/14/2019 13MProgress.xlsx
177/282
8/14/2019 13MProgress.xlsx
178/282
8/14/2019 13MProgress.xlsx
179/282
8/14/2019 13MProgress.xlsx
180/282
8/14/2019 13MProgress.xlsx
181/282
8/14/2019 13MProgress.xlsx
182/282
8/14/2019 13MProgress.xlsx
183/282
8/14/2019 13MProgress.xlsx
184/282
8/14/2019 13MProgress.xlsx
185/282
8/14/2019 13MProgress.xlsx
186/282
9100 7.00% 130059
9462 7.28% 130059
3346 2.57% 130059
5018 3.86% 130059
6040 4.64% 130059
5406 4.16% 1300592163 1.66% 130059
18000 13.84% 130059
7200 5.54% 130059
10864 8.35% 130059
4524 3.48% 130059
9374 7.21% 130059
7760 5.97% 130059
2622 2.02% 130059
5672 4.36% 130059
1040 0.80% 130059
2200 1.69% 130059
4750 3.65% 130059
3988 3.07% 130059
6900 5.31% 130059
1140 0.88% 130059
880 0.714731 8988
1440 1.169559 8988
1380 1.120828 8988
3000 2.436582 8988 1629.666 1.306364 5738.416
608 0.493814 8988 4108.75 3.293062 5739.416
1200 0.974633 8988
480 0.389853 8988
478.8 0.391632
258.4 0.211357
2282.408 1.845379 8905.129 368.6 0.301494
5580.619 4.511551 8906.129 1349 1.103407
1042.103 0.842374 8907.129 133 0.108787
8/14/2019 13MProgress.xlsx
187/282
590.9 0.483323
8/14/2019 13MProgress.xlsx
188/282
8/14/2019 13MProgress.xlsx
189/282
8/14/2019 13MProgress.xlsx
190/282
8/14/2019 13MProgress.xlsx
191/282
8/14/2019 13MProgress.xlsx
192/282
8/14/2019 13MProgress.xlsx
193/282
3178.7
3178.7
3178.7
3178.7
3178.7
8/14/2019 13MProgress.xlsx
194/282
3178.7
8/14/2019 13MProgress.xlsx
195/282
Description Total %age Work Done
Ground Floor 85.5% 69.5%
First Floor 83.0% 62.8%
External Work 100.0% 28.1%
Electric Work 100.0% 35.0%
Overall work in house # 16 368.5% 195.4%
Brick Work upto DPC Level 15.0%
Brick work in substructure upto 9" 7.0%complete
DPC Completion 6.0%complete
Earth Filling 2.0%complete
Brick Work upto Roof Level 15.0%
Brick work upto 3'-0" Height 4.0%complete
Upto Lintel Level 4.0%complete
Casting of Lintel 3.0%complete
Above Lintel upto Roof Level 4.0%complete
Casting of RCC Slab & Stair 21.0%
Shuttring at Site 6.5%complete
Casting of Porch Slab 2.0%completeCasting of Slab (Shuttering, Steel fixing &
pouring) 10.0%complete
Casting of Stair 2.5%
Internal Plaster with Wabrobe Platform,
Kitchen Slab and Bath vanity 20.0%
Plaster under sofit (Ceiling) 5.0%complete
Internal Plaster inculding Edge plastering complete8.5%complete
All Bath & Kitchen walls inculding Edge plasteringcomplete 4.0%complete
Wardrobe Platforms , Bath Vanity slab, Kitchen
Slab etc. 2.5%
External Plastering 7.0%
Front Elevation 2.5%
Side/Back walls &other External Plaster4.5%
Earth filling, Brick Ballast, PCC, Stair Marble
& Window sill 7.5%
Earth filling & compaction 0.5%complete
PCC flooring 3.0%complete
Stair Marble 2.0%Window Sill 2.0%
Total Work for Ground Floor: 85.5% 69.5%
Brick Work upto Roof Level 21.0%
Brick work upto 3'-0" Height 5.0%complete
Upto Lintel Level 5.0%complete
Casting of Lintel 5.0%complete
Above Lintel upto Roof Level 6.0%complete
Ground Floor
First Floor
8/14/2019 13MProgress.xlsx
196/282
Casting of RCC Slab & Front Crown 20.0%
Shuttring at site 7.0%complete
Casting of Slab 12.0%complete
Front Crown 1.0%
Internal Plaster with Wabrobe Platform,
Kitchen Slab and Bath vanity 22.0%
Plaster under sofit (Ceiling) 5.0%complete
Internal Plaster complete 11.0%complete
All Edge plastering of Doors, Windows etc.
2.5%complete
Wardrobe Platforms , Bath Vanity slab, Kitchen
Slab etc. 3.5%
External Plastering 9.0%
Front Elevation external plaster 4.0%
Side wall And other external plaster with perpet
plaster 5.0%
Roof Treatment 6.0%
Roof Treatment 6.0%
Brick Ballast, PCC & Window sill 5.0%
PCC flooring 3.0%complete
Extra Amount in PCC flooring 1.3%complete
Window Sill 2.0%
Total Work for First Floor: 83.0% 62.8%
1 Altration Work 0.0%
i) Altration According to Drawing 0.0%
ii) Qibla Altration 0.0%
iii) Marketing Altration 0.0%iv) Architect Altertaion 0.0%
2
Side & Back Boundary Wall , inculding
excavation, PCC, Brick work in F&P,
DPC, Bick work in other than building,
Cement plaster & copping.
Plan No.
Amount @ 182/- Per Rft
7.00% complete
3 Out of Covered Area Work
i) Front Balcony 7.3%
Shuttering 0.71%Concrete with Steel 1.17%
Parapet Wall With Shuttering 1.12%
Plaster of Balcony 2.44%
P.C.C.(1:3:6) with Brick Ballast in Floor 0.49%
Tile Work in Floor 0.97%
Skirting 0.39%
ii) Side Balcony 2.6%
Shuttering 0.39%
External Works
8/14/2019 13MProgress.xlsx
197/282
Concrete with Steel 0.21%
Brick Work for Parapet Wall 0.30%
Plaster of Balcony 1.10%
P.C.C.(1:3:6) with Brick Ballast in Floor 0.11%
Tile Work in Floor 0.48%
iii) Laundry
ShutteringConcrete with Steel
Brick Work for Parapet Wall
Plaster of Balcony
P.C.C.(1:3:6) with Brick Ballast in Floor
Tile Work in Floor
iv) Big Arch with Projection 3.9%
Shuttering
Concrete with Steel
Plaster of Balcony
v) Back Tarrace Parapet Wall 4.6%
Brick Work for Parapet Wall 1.31%complete
Plaster of Parapet Wall 3.29%complete
vi) Back Terrace Flooring Work 2.7%
P.C.C.(1:3:6) with Brick Ballast in Floor 2.7%complete
vii) Front Terrace Parapet Wall Pouring 4.2%
vii - a) Front Terrace Parapet Wall Plaster 1.7%
viii) Top Parapet Wall Pouring 13.8%complete
viii - a) Top Parapet Wall Plaster 5.5%
4 External Work
i)
Front Boundary Wall , inculdingexcavation, PCC, Brick work in F&P,
DPC, Bick work in other than building,
Cement plaster, copping & steel railing .
Plan No.
Amount @ 200/- Per Rft
8.35%
ii) Toe Wall 3.5%
iii) External Flooring Work 7.2%
Earth filling in passages 1.85%
P.C.C(1:3:6) with Brick Ballast 4.51%
Earth filling in Lawn 0.84%
iv) Manholes 5.97%
vii) Ramp 2.0%
ix) Over Head Water Tank Civil Works 4.4%complete
x) AC Sills 0.8%complete
xi) Front crown plaster 1.7%
xii) Patio PCC inculding Tile & skirting 3.65%
xiii) Front Terrace Common wall complete 3.1%
xiv) Front Terrace PCC complete 5.3%
3.9%
8/14/2019 13MProgress.xlsx
198/282
xv) Patio wall plaster complete 0.9%
Total Work for External Area: 100.0% 28.1%
1 Electric Condute work of slab 6.00% complete
2 Down Piping on Wall with boxing 11.50% complete
3 Wiring with UPS Completion 11.50%4 Gate light,Gardon light,M,C,B and 4.50%
5 Service line completion 3.50%
6
Switch light with Arthaning A,C Drain pipe
Completion 10.00%
7
Home light compeltion hand over to
project Manager 3.00%
8 Electric Condute work of slab 6.00% complete
9 Down Piping on Wall with boxing 11.50% complete
10 Wiring with UPS Completion 11.50%
11 Gate light,Gardon light,M,C,B 4.50%
12 Service line completion 3.50%
13
Switch light with Arthaning A,C Drain pipe
Completion 10.00%
14
Home light compeltion hand over to
project Manager 3.00%
Total Work for Electric: 100.0% 35.00%
First Floor
Electric Works
Ground Floor
8/14/2019 13MProgress.xlsx
199/282
69.5%
62.8%
28.1%
35.0%
0.0%
10.0%
20.0%
30.0%
40.0%
50.0%
60.0%
70.0%
80.0%
Ground Floor First Floor External Work Electric Work
Overall work in house # 16
Overall work in house # 16
8/14/2019 13MProgress.xlsx
200/282
8/14/2019 13MProgress.xlsx
201/282
Not
included
Not
included
8/14/2019 13MProgress.xlsx
202/282
8/14/2019 13MProgress.xlsx
203/282
8/14/2019 13MProgress.xlsx
204/282
8/14/2019 13MProgress.xlsx
205/282
8/14/2019 13MProgress.xlsx
206/282
8/14/2019 13MProgress.xlsx
207/282
8/14/2019 13MProgress.xlsx
208/282
8/14/2019 13MProgress.xlsx
209/282
8/14/2019 13MProgress.xlsx
210/282
8/14/2019 13MProgress.xlsx
211/282
9100 7.00% 130059
9462 7.28% 130059
3346 2.57% 130059
5018 3.86% 130059
6040 4.64% 130059
5406 4.16% 1300592163 1.66% 130059
18000 13.84% 130059
7200 5.54% 130059
10864 8.35% 130059
4524 3.48% 130059
9374 7.21% 130059
7760 5.97% 130059
2622 2.02% 130059
5672 4.36% 130059
1040 0.80% 130059
2200 1.69% 130059
4750 3.65% 130059
3988 3.07% 130059
6900 5.31% 130059
1140 0.88% 130059
880 0.714731 8988
1440 1.169559 8988
1380 1.120828 8988
3000 2.436582 8988 1629.666 1.306364 5738.416
608 0.493814 8988 4108.75 3.293062 5739.416
1200 0.974633 8988
480 0.389853 8988
478.8 0.391632
258.4 0.211357
2282.408 1.845379 8905.129 368.6 0.301494
5580.619 4.511551 8906.129 1349 1.103407
1042.103 0.842374 8907.129 133 0.108787
8/14/2019 13MProgress.xlsx
212/282
590.9 0.483323
8/14/2019 13MProgress.xlsx
213/282
8/14/2019 13MProgress.xlsx
214/282
8/14/2019 13MProgress.xlsx
215/282
3178.7
3178.7
3178.7
3178.7
3178.7
8/14/2019 13MProgress.xlsx
216/282
3178.7
8/14/2019 13MProgress.xlsx
217/282
Description Total %age Work Done
Ground Floor 85.5% 64.5%
First Floor 83.0% 57.0%
External Work 100.0% 15.1%
Electric Work 100.0% 23.5%
Overall work in house # 17,18 368.5% 160.1%
Brick Work upto DPC Level 15.0%
Brick work in substructure upto 9" 7.0%complete
DPC Completion 6.0%complete
Earth Filling 2.0%complete
Brick Work upto Roof Level 15.0%
Brick work upto 3'-0" Height 4.0%complete
Upto Lintel Level 4.0%complete
Casting of Lintel 3.0%complete
Above Lintel upto Roof Level 4.0%complete
Casting of RCC Slab & Stair 21.0%
Shuttring at Site 6.5%complete
Casting of Porch Slab 2.0%completeCasting of Slab (Shuttering, Steel fixing &
pouring) 10.0%complete
Casting of Stair 2.5%completeInternal Plaster with Wabrobe Platform,
Kitchen Slab and Bath vanity 20.0%
Plaster under sofit (Ceiling) 5.0%complete
Internal Plaster inculding Edge plastering complete8.5%complete
All Bath & Kitchen walls inculding Edge plasteringcomplete 4.0%
Wardrobe Platforms , Bath Vanity slab, Kitchen
Slab etc. 2.5%
External Plastering 7.0%
Front Elevation 2.5%
Side/Back walls &other External Plaster4.5%
Earth filling, Brick Ballast, PCC, Stair Marble
& Window sill 7.5%
Earth filling & compaction 0.5%
PCC flooring 3.0%
Stair Marble 2.0%Window Sill 2.0%
Total Work for Ground Floor: 85.5% 64.5%
Brick Work upto Roof Level 21.0%
Brick work upto 3'-0" Height 5.0%complete
Upto Lintel Level 5.0%complete
Casting of Lintel 5.0%complete
Above Lintel upto Roof Level 6.0%complete
Ground Floor
First Floor
8/14/2019 13MProgress.xlsx
218/282
Casting of RCC Slab & Front Crown 20.0%
Shuttring at site 7.0%complete
Casting of Slab 12.0%complete
Front Crown 1.0%complete
Internal Plaster with Wabrobe Platform,
Kitchen Slab and Bath vanity 22.0%
Plaster under sofit (Ceiling) 5.0%complete
Internal Plaster complete 11.0%complete
All Edge plastering of Doors, Windows etc.
2.5%
Wardrobe Platforms , Bath Vanity slab, Kitchen
Slab etc. 3.5%
External Plastering 9.0%
Front Elevation external plaster 4.0%
Side wall And other external plaster with perpet
plaster 5.0%
Roof Treatment 6.0%
Roof Treatment 6.0%
Brick Ballast, PCC & Window sill 5.0%
PCC flooring 3.0%
Extra Amount in PCC flooring 1.3%
Window Sill 2.0%
Total Work for First Floor: 83.0% 57.0%
1 Altration Work 0.0%
i) Altration According to Drawing 0.0%
ii) Qibla Altration 0.0%
iii) Marketing Altration 0.0%iv) Architect Altertaion 0.0%
2
Side & Back Boundary Wall , inculding
excavation, PCC, Brick work in F&P,
DPC, Bick work in other than building,
Cement plaster & copping.
Plan No.
Amount @ 182/- Per Rft
7.00%
3 Out of Covered Area Work
i) Front Balcony 7.3%
Shuttering 0.71%Concrete with Steel 1.17%
Parapet Wall With Shuttering 1.12%
Plaster of Balcony 2.44%
P.C.C.(1:3:6) with Brick Ballast in Floor 0.49%
Tile Work in Floor 0.97%
Skirting 0.39%
ii) Side Balcony 2.6%
Shuttering 0.39%
External Works
8/14/2019 13MProgress.xlsx
219/282
Concrete with Steel 0.21%
Brick Work for Parapet Wall 0.30%
Plaster of Balcony 1.10%
P.C.C.(1:3:6) with Brick Ballast in Floor 0.11%
Tile Work in Floor 0.48%
iii) Laundry
ShutteringConcrete with Steel
Brick Work for Parapet Wall
Plaster of Balcony
P.C.C.(1:3:6) with Brick Ballast in Floor
Tile Work in Floor
iv) Big Arch with Projection 3.9%
Shuttering
Concrete with Steel
Plaster of Balcony
v) Back Tarrace Parapet Wall 4.6%
Brick Work for Parapet Wall 1.31%complete
Plaster of Parapet Wall 3.29%
vi) Back Terrace Flooring Work 2.7%
P.C.C.(1:3:6) with Brick Ballast in Floor 2.7%
vii) Front Terrace Parapet Wall Pouring 4.2%
vii - a) Front Terrace Parapet Wall Plaster 1.7%
viii) Top Parapet Wall Pouring 13.8%complete
viii - a) Top Parapet Wall Plaster 5.5%
4 External Work
i)
Front Boundary Wall , inculdingexcavation, PCC, Brick work in F&P,
DPC, Bick work in other than building,
Cement plaster, copping & steel railing .
Plan No.
Amount @ 200/- Per Rft
8.35%
ii) Toe Wall 3.5%
iii) External Flooring Work 7.2%
Earth filling in passages 1.85%
P.C.C(1:3:6) with Brick Ballast 4.51%
Earth filling in Lawn 0.84%
iv) Manholes 5.97%
vii) Ramp 2.0%
ix) Over Head Water Tank Civil Works 4.4%complete
x) AC Sills 0.8%
xi) Front crown plaster 1.7%
xii) Patio PCC inculding Tile & skirting 3.65%
xiii) Front Terrace Common wall complete 3.1%
xiv) Front Terrace PCC complete 5.3%
3.9%
8/14/2019 13MProgress.xlsx
220/282
xv) Patio wall plaster complete 0.9%
Total Work for External Area: 100.0% 15.1%
1 Electric Condute work of slab 6.00% complete
2 Down Piping on Wall with boxing 11.50% complete
3 Wiring with UPS Completion 11.50%4 Gate light,Gardon light,M,C,B and 4.50%
5 Service line completion 3.50%
6
Switch light with Arthaning A,C Drain pipe
Completion 10.00%
7
Home light compeltion hand over to
project Manager 3.00%
8 Electric Condute work of slab 6.00% complete
9 Down Piping on Wall with boxing 11.50%
10 Wiring with UPS Completion 11.50%
11 Gate light,Gardon light,M,C,B 4.50%
12 Service line completion 3.50%
13
Switch light with Arthaning A,C Drain pipe
Completion 10.00%
14
Home light compeltion hand over to
project Manager 3.00%
Total Work for Electric: 100.0% 23.50%
Electric Works
Ground Floor
First Floor
8/14/2019 13MProgress.xlsx
221/282
64.5%
57.0%
15.1%
23.5%
0.0%
10.0%
20.0%
30.0%
40.0%
50.0%
60.0%
70.0%
Ground Floor First Floor External Work Electric Work
Overall work in house #