Date post: | 07-Aug-2015 |
Category: |
Documents |
Upload: | syed-muhammad-danish |
View: | 115 times |
Download: | 0 times |
Mechanical and Chemical Removal
of Organic Bridge Deposits and
Acid Stimulation of Extended
Reach Offshore Wells
Presented By: Syed Danish
Account Representatives – Halliburton Coiled Tubing
Coauthors: Jose Noguera, Halliburton Saudi Arabia; James Arukhe and Hussain Al-Saiood, Saudi Aramco
© Copyright 2014, Saudi Aramco. All rights reserved.
2
▌ Abstract
▌ Manifa Field – Introduction
▌ Objective
▌ Downhole Challenges
▌ Execution Challenges
▌ Stimstar (Stimulation Vessel) and Kinoa (CT Barge)
▌ PWI – Generic Stimulation Procedure
▌ OP – Generic Stimulation Procedure
▌ Case Studies
▌ Conclusion
Contents
3
▌ The Manifa field – Saudi Arabia:
Peripheral matrix water injection as a pressure maintenance scheme.
Unique placement of both onshore and offshore PWI and OP.
Wells are extended reach, highly deviated, with deep open holes.
▌ Stimulation is a required to restore reservoir productivity or injectivity with multiple challenges:
A heavy tar mat zone characterizes the field.
Hardened mixed sludge results in stable bridges.
▌ The scope of this presentation is to review:
Remedial coiled tubing stimulations performed during this campaign.
Interventions executed for removing wellbore organic obstruction by both chemical and mechanical means.
▌ Two case histories in an offshore PWI candidates are offered.
Abstract
4
Manifa Field – Introduction
▌ Largest offshore carbonate project of the region with target production:
900 MBPD heavy crude oil.
90 MMSCFD sour gas.
65 MBPD condensate.
▌ Unique engineering design:
Water drive mechanism.
Unique placement of both power water injector and oil producer wells.
Onshore footprint on artificial man-made islands.
Offshore footprint on shallow platforms with ~10 m water depth.
5
Objective
▌ Main objective is to acid stimulate and/or nitrogen lift every offshore and onshore newly drilled/ workover well.
▌ Formation has limited injectivity and productivity indices:
Post-drilling and workover operations residual mud damages/loads up the OPs.
PWI wells drilled in heavy oil mat zones have hardened sludge and tar bridges.
Mixed deposits limit production due to commingled inorganic scale and tar generation.
6
Downhole Challenges
▌ 80% of these wells are extended reach, with measure depth (MD) to total vertical depth (TVD) ratio exceeding 2.
Need to utilize hydraulic tractor and agitator assemblies to reach TD.
▌ 90% of the wells are highly deviated, with maximum deviation angle reaching 90° for more than 50% of the open hole region.
Excessive wash out regions in the open hole cause multiple tags, need to utilize hydraulic indexing and knuckle joint assemblies to jump over wash outs.
▌ 30% of the measured depth coverage is for open hole production or injection:
Open hole results in excessive drag while RIH, slick friction reducer is placed in the 45° deviated zone.
▌ 2% of the wells have multilateral profiles:
Lateral finding technology is required like MWD assembly or live downhole CCL telemetry.
7
Execution Challenges
▌ Offshore Wells (Assigned to HAL):
Barge Deck Loading/Capacity:
− Limited in terms of CT string length.
− Limited to use other services, including full surface testing package, stimulation package, slick line or wireline.
− Without flare booms small equipment off loading is not possible.
Crane Capacity and Length – 45 ton port side and 25 ton starboard side:
− Limited in terms of lubricator height, tool deployment is restricted.
Barge Technology:
− Self-propelled barge without dynamic positioning, weather plays a important role during barge positioning.
Barge Leg Lengths – 52 m and Barge Draft – 4.5 m:
− Cannot perform deep water or shallow water operations in nearby fields.
8
Stimstar (Stimulation Vessel) and Kinoa (CT Barge)
Exp
osive
Carg
o
2.3
02.4
0
538
554
Mean
Dra
ft
2.4
8
trans. P
um
ps
iso. T
anks
ch. In
j. Pum
ps
569
585
2.5
52.6
6
1716
1514
1312
1110
-9-8
-7-6
-5-4
-3-2
-10
12
34
56
78
910
1112
1314
1516
17
Min
us
"-"P
lus
"+"
1
43
21
Dry
Store
10
Chill
er 12
Free
zer
Muste
r
№2
89
H2
S
№1
H2S
№2
2
Muste
r
№ 1
24
7 Paint
Store
Bosun store
10
PWI – Generic Stimulation Procedure
▌ Power Water Injectors:
BHT 210 °F
BHP 3,500 psi
Average depth ~ 20,000 ft
Completion 7” tubing, 7”
liner and 6.125” open hole
Average open hole length ~
8,000 ft
Max deviation 90°
Extended reach
Single or multilaterals
Treatment Fluid Loading Placement Method
H2S Scavenger Bullheaded from surface to
push the migrated H2S
Friction Reducer Bullheaded from surface and
placed at 45° deviation
Pre-Flush
Treated Water 6 gal/ft
CT RIH, from liner shoe to
maximum depth
Main Acid
15% HCl 3 gal/ft
CT POOH from maximum
depth reached, 500 ft stages
with 36 bbl main acid
Visco Elastic Agent
in 15% HCl 3 gal/ft
CT POOH, 500 ft stages with
36 bbl diversion
Main Acid Spacer
15% HCl 3 gal/ft
CT POOH, 500 ft stages with
36 bbl main acid
Emulsified Acid
15% HCl 6 gal/ft
CT POOH, 500 ft stages with
71 bbl main acid
Post-Flush
Treated Water 3 gal/ft
CT static from liner shoe,
displace treatment
11
OP – Generic Stimulation Procedure
▌ Oil Producers:
BHT 210 °F
BHP 3,500 psi
Average depth ~ 15,000 ft
ESP lift completion 4.5”
tubing, 7” liner and 6.125”
open hole
Average open hole length ~
4,500 ft
Max deviation 90°
Extended reach
Single laterals
Treatment Fluid Loading Placement Method
H2S Scavenger Bullheaded from surface to
push the migrated H2S
Friction Reducer Bullheaded from surface and
placed at 45° deviation
Pre-Flush
Treated Water 3 gal/ft
CT RIH, from liner shoe to
maximum depth
Diverter
Visco Elastic Agent
in 15% HCl
5 gal/ft CT POOH, 500 ft stages with
60 bbl diversion
Main Acid
15% HCl 10 gal/ft
CT POOH, 500 ft stages with
119 bbl main acid
Post-Flush
Treated Water 3 gal/ft
CT static from liner shoe,
displace treatment
12
Case Study – Organic Bridge Deposits
▌ Well-X PWI (Newly Drilled):
High injection pressures were observed with scavenger and friction reducer.
While RIH CT experienced multiple soft tags at different depths.
Hard bridge of mixed organic deposits were accumulated just above the end of liner shoe.
After multiple attempts CT was POOH and tar deposits were observed on the BHA.
▌ Well-Y PWI:
No injection was observed with scavenger and friction reducer.
While RIH CT experienced very similar hard tag near surface.
After multiple attempts CT was POOH and tar deposits were observed on the BHA.
13
Case Study – Chemical and Mechanical Solution
▌ Solution:
Acid Compatible Motor and Bit – Mechanical Milling.
Lab Test – Chemical Solubility:
− Tests showed deposits retrieved from Well-X were mixed heavy
tar with drilling mud residue.
− Tests showed deposits retrieved from Well-Y were heavy tar.
− An organic solvent emulsion in 20% HCl was proposed as
treating solvent. Treatment Fluid
Solubility for
Well-X
Solubility for
Well-Y
Organic Solvent 31.4% in 4 hrs
at 185 °F
94% in 4 hrs at
95 °F
20% HCl 54.2% in min at
95 °F N/A
Emulsified Organic
Solvent + 20% HCl Acid
84% in 4 hrs at
185 °F
94% in 4 hrs at
97 °F
14
Case Study – Well-X Job Plot
7/12/201400:00 08:00 16:00
7/13/201400:00 08:00 16:00
7/14/201400:00
7/14/201408:00
Time
-5000
0
5000
10000
15000
20000
25000
30000
35000
A
0
1000
2000
3000
4000
5000
6000
7000
B
0
2500
5000
7500
10000
12500
15000
17500
EU1 Pipe Weight (lbf) U1 Pressure (psi)
U1 Tubing Depth (ft) U1 Wellhead Pressure (psi)
A B
E B
Customer: SAUDI ARAMCO Job Date: 11-Jul-2014 Sales Order #: 12345
Well Description: MNIF-746 UWI:INSITE for Well Intervention v4.6.0
08-Sep-14 20:41
15
Case Study – Well-Y Job Plot
7/18/201406:00 14:00 22:00 06:00 14:00 22:00 06:00
7/20/201414:00
Time
-10000
0
10000
20000
30000
40000
50000
60000
A
0
1000
2000
3000
4000
5000
6000
7000
B
0
2500
5000
7500
10000
12500
15000
17500
EU1 Pipe Weight (lbf) U1 Pressure (psi)
U1 Tubing Depth (ft) U1 Wellhead Pressure (psi)
A B
E B
Customer: SAUDI ARAMCO Job Date: 18-Jul-2014 Sales Order #: 11112013
Well Description: UWI:INSITE for Well Intervention v4.6.0
08-Sep-14 20:54
16
▌ CT intervention led to the removal of mixed deposit bridges and successful completion of large scale stimulation on the mentioned wells.
▌ Successfully completed 58 interventions and 50 stimulations. Injectivity results post-stimulation revealed 300% improvement.
▌ Execution time per well has been reduced to 1/4th of the original time.
Customized CT stack rig up reduced R/U and R/D time.
Flexibility in operations from chemicals solvents, dispersants to tool tractors, agitators, indexing/knuckle joints, acid compatible motor and mill assembly.
Jack Up Barge and Stimulation Vessel combination helped improve logistics and resource availability.
▌ Planning to introduce CT fiber optic technology for DTS – stimulation assessment on PWI and logging operations for PLT – production logs on OP.
Conclusion