Date post: | 13-Aug-2015 |
Category: |
Law |
Upload: | dhruv-goel |
View: | 26 times |
Download: | 0 times |
SUMMER INTERNSHIP PROJECT
2014-2016
“TO STUDY THE VARIATIONS IN THE DEMAND PATTERN OF VEHICLES AND
ANALYZE IT’S EFFECT ON PRODUCTION PLANNING”
“TO DEVELOP A SYSTEM FOR IDENTIFICATION AND MANAGEMENT OF TROLLEY SO
AS TO REDUCE THE INCURRED PRODUCTION LOSS”
“DESIGN A DATA DASHBOARD FOR PRODUCTION PLANNING TEAM TO IMPROVE VISIBILITY AND MAKE DATA VISULALIZATION SIMPLER”
SYMBIOSIS INSTITUTE OF OPERATIONS MANAGEMENT, NASHIK
SUBMITTED BY
DHRUV GOEL-14020741056
COMPANY GUIDE
MR. ASHISH WANKEDE
SENIOR MANAGER, PPC
VOLVO EICHER COMMERCIAL
VEHICLES LTD , INDORE
FACULTY GUIDE
MR.BHIBUTI TRIPATHY
(PROFESSOR, SIOM)
1 | P a g e
Table of content
S.NO CONTENT Pg. No
1 INTRODUCTION 7
2 REVIEW OF LITERATURE 8
3 INDUSTRY BACKGROUND 10
3.1 Major developments and investments in commercial vehicles Industry 11
4 COMPANY’S BACKGROUND 13
4.1 VECV at a glance 13
4.2 VECV enterprise 13
4.3 VECV strategic directions 14
4.4 New product Line 15
4.5 Time Line Of Eicher Motors 17
4.6 SCM at VECV 18
4.7 Production Planning and Control at VECV 19
4.7.1 Steps followed 24
4.8 Functions of procurement and Logistics 25
5 PROJECT1: Study variations in the demand pattern and analyze it’s
effect on Production Planning.
5.1 Objective of the project 26
5.2 Research Methodology 26
5.3 Current Production Planning System at VECV 29
5.4 Study approach 31
5.5 Data collection method 32
5.5.1 Primary data 32
5.5.2 Secondary Data 32
5.6 Observations 33
6 PROJECT2: To develop a system for identification and management of
trolleys so as to reduce incurred production losses.
6.1 Need and scope of the project 43
6.2 Capital asset and asset management system 44
6.3 Current scenario at VECV 45
6.4 Concept of 5‟s 47
6.5 Suggested Solution 49
6.6 Conclusion 50
6.7 Further Steps 49
2 | P a g e
7 PROJECT3: Design a data dashboard to improve the visibility and
make data visualization simpler for PPC team.
7.1 Objective of the project 51
7.2 Need of the project 51
7.2.1 Advantages of dashboard 52
7.2.2 Expected project deliverables 52
7.2.3 Project Plan 53
7.3 Dashboard 54
7.3.1 Dashboard Designing 55
7.3.2 Design principles for dashboard 57
7.4 Software requirement for the project 58
7.5 Solution Requirement(dashboards) 58
7.6 Data Input analysis 59
7.6.1 Marketing Plan 59
7.6.2 Dashboard view of parameters 59
7.7 Conclusion 64
8 References 65
3 | P a g e
Declaration
I declare that the work presented in this report titled “Studying the variations in the demand
pattern of the vehicles and analyzing its effect on production planning, Developing a system for
the management and identification of trolleys to reduce the incurred production losses,
Designing a data dashboard to reduce incurred production losses ” submitted to Volvo Eicher
Commercial Vehicles Ltd Pithampur Plant, Indore and Symbiosis Institute of Operations
Management, Nashik as a part of Summer Internship Project curriculum is my original work. I
have not plagiarized or submitted the same work for the award of any other degree. In case this
undertaking is found incorrect, I accept that our report can be disregarded.
Date: 28.05.2014 Name - Dhruv Goel
4 | P a g e
List of Figures
S.NO FIGURES Pg. No
1 Units sold by companies 12
2 LMD Trucks 15
3 HD Trucks 15
4 Buses 16
5 Shows a basic model of any supply chain 18
6 Study approach 31
7 Data collection format 32
8 Owner Identification of Trolleys 46
9 Details on New Trolleys 47
10 Trolley areas, space available and color coding 47
11 5s Red Tag for Trolleys 49
5 | P a g e
List of Graphs
S.NO Graphs Pg. No
1 Shows the variations in demand in I,II and III period 33
2 Month wise variations in demand in I Period 34
3 Month wise variations in demand in II Period 34
4 Month wise variations in demand in III Period 34
5 Sales variations 35
6 Monthly variations for Terra 25 Bogie 35
7 Monthly variations for Terra 25 36
8 Planned Vs actual production for Terra 25 36
9 Monthly variations for Terra 16 37
10 Planned Vs actual production for Terra 16 37
11 Sales variations for Terra 16 38
12 Monthly variations for 10.50 model in BS3 and BS4category 38
13 Monthly variations for 10.59 model 39
14 Sales variations for 10.59 model 39
15 Monthly variations for 8X2 cab 40
16 Sales variations for 8X2 cab 41
17 Monthly variations for 8X2 cowl 42
18 Sales variations for 8X2 cowl 42
19 Delivery Precision graph for HD 53
20 Delivery precision showing quarterly actual Vs targeted comparison 54
21 Delivery precision showing Yearly actual Vs targeted comparison 54
22 Marketing plan showing projections for LMD and HD 55
23 % variations from the market wrt 25th and 5th plan for LMD and
HD
55
24 Number of vehicles added and deleted for LMD and HD 56
25 Graph showing the monthly variations in the various line losses 56
26 Dvdd Graph showing the monthly Roll out for HD and LMD 57
6 | P a g e
Acknowledgement
I would like to propose my sincere acknowledgements to Mr. Ashish Wankhade Senior
Manager, PPC for allowing me to work as a trainee with his competent team and giving useful
inputs time to time whenever needed for the betterment of the project work. His guidance as an
instructor and friend are certainly going to help me in my days ahead in the professional world.
I would also like to thank Mr. B Sudhakaran Dy Manager, MPP and Mr. Mukesh Soni for their
guidance, suggestions, understanding, patience, and most importantly their criticism and
appraisal , which made the working challenging and enjoyable.
Finally I would like to express my heartfelt appreciation to Dr. Vandana Sonwaney (Director,
SIOM), Prof. P.N. Parameshwaran (Head Corporate Relations and Placements), Prof Bibhuti
Tripathy (Faculty, SIOM) and all SIOM staff members, my batch mates, seniors for their
guidance and last but not the least my parents for their constant support and guidance right from
the inception of this project to its closure.
In the end I would like to thank all those people whose name I have not mentioned here and who
has helped me directly or indirectly in in completing this project successfully.
DHRUV GOEL
MBA (Operations Management)
Symbiosis Institute of Operations Management, Nasik
7 | P a g e
1.Introduction
This report presents my analysis and recommendations for the two month internship at VECV. In
my two months summer internship I worked on three projects. My first project was to study the
variations in the demand pattern of vehicles and analyze its effect on production planning. The
main objective of this project was to understanding the current production planning system of the
company, study the major sources of uncertainty in the marketing plan/demand and look for
patterns, relationship among variables and make a series of observations on the treatment of
uncertainty in production planning in practice.
My second project was to develop a system for identification and management of trolleys so as
to reduce incurred production losses on the line. The current system at VECV didn‟t had a proper
management system for the trolleys that lead to production losses because of non-availability
,Occupancy –availability,OEE ( Overall Equipment effectiveness )- Health of Trolleys and lack
of traceability of trolley. This led to huge production loss. So my tack was to understand the
current system at VECV, identify the need for change and create an improvement strategy so as
to reduce losses.
My third project was to design a PPC data dashboard to improve the visibility and make data
visualization simpler. Its main objective was to develop a tool that will provide a complete
overview of the key performance indicators and other parameters, useful in studying the
production plan. Provide multidimensional visual representation of data and reduce the time
spent by the production planning and control team in analyzing data and taking decisions and to
improve the current process and increase the efficiency of the supply chain as well as employees.
8 | P a g e
2. Review of literature
Production Planning is one of the most challenging task that organizations around India are
facing today. It is always an issue of concern that because of huge variations in the marketing
plan it becomes difficult to plan production and it leads to inventory being stocked.
To start with, a detail literature review is done. Some of the most relevant papers and articles
related to the study have been illustrated below:
Author Objective Findings
Arnoldo C. Hax and Harlan C.
Meal
This paper provide a
framework for a hierarchical
decision making approach in
which the aggregate results of
capacity planning provide
constraints for detailed
scheduling decisions
The paper describes the
characteristics of the
production and distribution
problems presented in the firm
and discusses the detail of
each of those components.
Stephen C. Graves
This paper discuss how
uncertainty is handled in
production planning as well as
describe and critique current
practices and then prescribe
possible improvements to these
practices.
The current planning systems
do not provide adequate
decision support for these
tactical decisions and this
shortcoming is an opportunity
for new research and
development, which could
significantly improve the
practice of production planning.
Ananth V Iyer, Roy Vasher
and Sridhar Seshadri
This book discuss about
Toyotas SCM strategies and
its two distinct core values:
Toyotas Way and TPS
It shows how the company has
applied such principles to work
with its suppliers, dealers, and
manufacturers and coordinated
9 | P a g e
the plans across the supply
chain.
Linea Kjell This paper describes the
general framework for
planning and scheduling.
It shows how manufacturing
planning address decisions on
the acquisition, utilization and
allocation of production
resources to satisfy customer
requirements.
10 | P a g e
3. Industry Background
Commercial Vehicles form an essential part of the Indian automobile industry. They are
manufactured in various models and designs, and are used for transporting industrial outputs and
other commodities to their allocated destinations. Commercial Vehicles Industry in India has
witnessed speedy growth post-independence and at present is considered as one of the
flourishing sector of Indian economy. As per statistics, the expansion in commercial vehicles
sales in 2009 stood at 92.6% besides witnessing a decline in product prices by 20% in the first
quarter of FY 10 assisting the CV industry growth. The steady development in Commercial
Vehicles Industry has led to cutthroat rivalry among the various Commercial Vehicles
Manufacturers in India. To survive in the competitive market every CV manufacturer is coming
up with something new yet affordable to meet the Indian market requirement. A customer can
now select among the various commercial vehicle deluging the markets in reasonable rates.
Urging the need of better infrastructure and technology development for the growth of CVs in
India, the long-term growth potential of the commercial vehicle segment is conditional on the
economy accelerating back to 7%–8% GDP growth per annum and the Government expediting
policies that foster infrastructure development and support the growth of manufacturing
sector. The industry is seeking favourable policy support from the Government and continued
focus on reforms to reinvigorate investment sentiment and bring the auto sector back on track.
Apart from focusing on R&D to develop products for the Indian market and introducing fuel
efficient technologies, the industry needs to secure resources, particularly talent, through
investments in training and upgrading skills of the workforce.
There are six mega trends that will impact the revenues, costs and profitability of participants in
the Indian commercial vehicle industry:
Economic slowdown, delays in infrastructure projects and evolving regulations
create demand uncertainty and impact OEMs’ product strategies: Policies such as
deregulation of fuel prices and the new bus-body building code drive OEMs to introduce
compatible products and adopt process-oriented bus-body manufacturing.
11 | P a g e
Fleets increase focus on total cost of ownership (TCO) and restructure composition
to include more LCVs: Fleets consider using TCO as an important procurement and
fleet management criterion. In addition, freight transporters add more LCVs to support
hub-and-spoke distribution model and increase adoption of used trucks to reduce fleet
acquisition cost.
Global OEMs design products for the domestic market and look at developing India
as an export hub: Global OEMs will also be looking to make their alliances with
domestic players successful; to leverage the latter‟s understands of the local market and
their distribution infrastructure.
Suppliers increase localisation, improve quality standards and diversify to related
sectors: Suppliers diversifying to related sectors, such as the off-road CV, the railways
and defence industries to reduce exposure to uncertain CV demand.
OEMs balancing the need to be flexible while securing access to talent, supply chain
and technology: Set up technical centres to strengthen R&D capabilities and overcome
skill constraints.
OEMs to focus on raising after-sales service standards, while dealers adopt
measures to improve operational efficiency: OEMs encourage dealers to implement IT
systems for efficient inventory management and enable fleets to order vehicle parts and
book servicing online.
3.1 Major Developments & Investments in commercial vehicles Industry
The country's top commercial vehicle manufacturers such as Tata Motors, Eicher Trucks and
Buses, Mahindra & Mahindra and Asia Motor Works (AMW), which command a share of 83 per
cent of the domestic CV market, have together posted a growth of 28 per cent selling over
60,000 units in July. Chennai-based Ashok Leyland is yet to issue its sale numbers for the
month.
The rise in CV sales is a result of a favourable mix of several reasons such as planned execution
of scheduled infra-related works sponsored by the government and private parties, imposition of
anti-overloading law by some states and new product introduction.
12 | P a g e
Figure1: Units sold by companies
The growth, according to CV manufacturers, has come despite broader inflationary pressures,
high fuel costs and peaking interest rates even as car sales, which are more sensitive to such
reasons, buckled under pressure during the same month.
Tata Motors, the country's biggest manufacturer of light and heavy trucks and buses, posted a
growth of 14 per cent during July, selling 40,798 units in the domestic market as compared to
35,694 units sold last year.
The biggest growth driver for the Mumbai-based company was the passenger and goods carrying
light commercial vehicle range which grew by 22 per cent. Medium and heavy commercial
vehicles achieved a growth of four per cent.
Somnath Bhattacharjee, president, Volvo Trucks India and executive vice-president, sales,
marketing and aftermarket, VE Commercial Vehicles said, "The CV industry as a total is still not
impacted as the cars segment. The light and medium trucks, which generally cater to the
agricultural and service sector, have been doing well. In addition, the heavy trucks segment has
seen an uptick due to constant implementation of the compliance of anti-overloading law."
Eicher trucks and buses, a business area of the company VE Commercial Vehicles and the fourth
largest CV maker in India, posted a growth of 34 per cent in sales. The company is expecting
demand to stay high .
Mahindra & Mahindra, India's third biggest CV maker and new entrant Mahindra Navistar
Automotive (MNAL) is confident of growth possibilities and would, thus, launch more products
to maintain consumer interest. While M&M grew by 91 per cent at 13,472 units, MNAL grew by
13 per cent at 1,144 units during July.
13 | P a g e
While those heavy trucks are expected to see a minor correction in demand moving forward
other segments such as the tippers are witnessing stronger demand.
Nalin Mehta, chief operating officer, Mahindra Navistar Automotive, said, "We have been in the
LCV business for some time now, which is doing reasonably well there. We are adding to our
range in the heavy commercial vehicle (HVC) segment. Yes, the market has become a little tight,
this is a difficult scenario with fuel and finance having gone up. But we hope to do well with
further addition to the range. The school buses are witnessing good demand. We added the 25
tonne long-wheel base as well as started with 40 tonne tractor trailer."
While those heavy trucks, which ply only on highways, are expected to see a minor correction in
demand moving forward other segments such as the tippers, which are used extensively in
construction and infrastructure building areas, are witnessing stronger demand.
4. Company’s Background
4.1 VECV at a glance
This section aims to give a little bit more information about the business and the company where
the project is performed before the theoretical framework and the methodology is presented. A
more extensive description of the company and its business is presented later.
4.2 The VECV enterprise
VE Commercial Vehicles Limited is a 50:50 joint venture between the Volvo Group (Volvo) and
Eicher Motors Limited (EML). It is a partnership that brings together Global leadership in
technology, quality, safety and environmental care, along with the deep knowledge and
understanding of the Indian Commercial Vehicle (CV) market. VE Commercial Vehicles Ltd.
(VECV) owes its inception to the compelling intent of driving modernization in commercial
transportation, in India and other developing markets.
Eicher Trucks and Buses (ETB) are present in the L/MD segment with a strong presence in the
5T-12T-truck segment. Eicher‟s 15-65 seater buses have a growing presence in the LD school
14 | P a g e
bus, staff and route-permit segments. ETB has also made strong inroads into heavy-duty trucks
segment of 16T-40T with their “VE” series of Fuel Efficient heavy-duty trucks.
ETB, completed 28 years of operations in India in the month of June 2014. The first Eicher truck
was rolled out from its manufacturing plant in Pithampur, Madhya Pradesh in 1986 and over the
past 28 years, the products have got endorsement from happy customers of over 500,000
vehicles.
Since its inception, the company‟s efforts have been towards providing value to its customers the
result of which is reflected through the growing sales numbers. In addition to being customer
centric, the geographical expanse of its service network has also ensured a dominant position for
EICHER TRUCKS AND BUSES (ETB). Eicher trucks and buses are also evidently visible in
South Asian markets of Bangladesh, Nepal and Sri Lanka. ETB plans to tap the distribution
network and the international requirements in South East Asia, Middle East and Africa.
Production capacity: 50,000 per annum
Established in: 2009 (Greenfield facility)
Products: Tipper (8T - 25T); Haulage (5T - 31T); Articulated Tractor (40T); Special
Applications; School Bus; City Bus; Staff Bus; Chassis; Gen Set Application Engines; Agro
Application Engines; Marine Application Engines
4.3 VECV Strategic Direction
To be recognized as the industry leader driving modernization in commercial transportation in
India and the developing world
Ambition to reach 100,000 unit Sales by 2015
Innovative products covering the entire product range
Comprehensive network with complete geographical coverage
15 | P a g e
4.4 New products and segments at VECV
LMD TRUCKS
10.55 10.80 XP TIPPER 11.10XP 10.59 XP CNG
Figure2: LMD Trucks
HD TRUCKS
TERRA 25 TERRA 16XP 30.25 35.31 26ft
Figure3: HD Trucks
BUSES
SKYLINE STARLINE 10.90L CNG
Figure4: Buses
16 | P a g e
20.15 CHASSES SKYLINE 20.15 REAR ENGINE SFL
Figure5: Buses
VECV Business Areas Components and Engineering Solutions
Eicher Engineering Components (EEC) Eicher Engineering Solutions (EES)
Strategic supplier of drive line components to Eicher
Trucks and Buses, with ambition to supply to the
Volvo Group in the future
Annual turnover of 2700 MINR / 385 MSEK in 2011.
Three production facilities: Thane, Dewas and SEZ,
Pithampur .
New plant under construction in Dewas
Annual turnover of 581 MINR / 83 MSEK in
2011.
Comprehensive product developent services
Class A surfacing, CAD, CAE, prototyping,
etc.
Supplying to Global Clients such as JCB,
TEREX, Navistar, GM, Nissan etc besides in-
house Eicher requirements.
17 | P a g e
4.5 Time line of Eicher Motors
1948: Goodearth Company setup to sell & service imported tractors.
1958: Eicher Tractor Corporation of India Pvt. Ltd. incorporated.
1959: First indigenous Eicher tractor built at Faridabad factory.
1960: Name changed to Eicher Tractors India Ltd.
1982: Collaboration agreement with Mitsubishi for the manufacturing of Light
Commercial Vehicles signed in Tokyo.
1982: Incorporation of Eicher Motors Ltd.
1986: EML springs to operation.
1991: Eicher takes over Ramon & Demm.
1992: Eicher Tractors Ltd. selected as „Company of the Year‟ for 1990-91.
1994: EML ends technical assistance agreement with Mitsubishi.
1994: Enfield India changed name to Royal Enfield Motors Ltd.
2008: Volvo Group & EML establish VE Commercial Vehicles (VECV).
2013: VEPT (Volvo Eicher Power Train), India‟s first Euro-VI plant takes off.
18 | P a g e
4.6 Supply Chain at VECV
A Supply Chain is a system of organizations, people, activities, information and resources
involved in moving a product or service from supplier to customer. Supply chain activities
transform natural resources, raw materials and components into a finished product that is
delivered to end customer. In sophisticated supply chain systems, used products may re-enter the
supply chain at any point where residual value is recyclable. Supply chains link value chains.
Figure.7: shows a basic model of any supply chain.
Supply Chain is broadly divided into two areas:
1) In-Bound
2) Out-Bound
In-bound is the part from vendor end to the store room and out-bound is the part from store room
to customer. Managing both sides is necessary as all the links are like bottle necks for an
industry.
Supply Chain Management (SCM) is the systematic, strategic coordination of traditional
business functions and the tactics across these business functions within a particular company
and across businesses within the supply chain, for the purpose of improving the long term
performance of individual companies and the supply chain as a whole. It has also been defined as
design, planning, execution, control and monitoring of supply chain activities with the objective
19 | P a g e
of creating net value, building a competitive infrastructure, leveraging worldwide logistics,
synchronizing supply with demand and measuring performance globally.
Main functions of SCM are:
Production Planning and control
Inventory Management
Distribution Management
Channel Management
Payment Management
Financial Management
Supplier Management
Transportation Management
Customer Service Management
Inventory management is the overseeing and controlling the ordering, storage and use of
components that a company will use in the production of items it will sell as well as the
overseeing and controlling of quantities of finished products for sale. Since for many companies
inventory is the largest item in the current assets category, inventory problems can and do
contribute to losses or even business failures. One such inventory problem aspect is of the shelf
life of materials. Controlling inventory on the basis of shelf life is of dire need as it may lead to
line stoppage and hence the delay in product supply which in turn is reflected in the company‟s
name.
4.7 Production Planning and Control
For efficient, effective and economical operation in a manufacturing unit of an organization, it is
essential to integrate the production planning and control system. Production planning and
subsequent production control follow adaption of product design and finalization of a production
process.
20 | P a g e
Production planning and control address a fundamental problem of low productivity, inventory
management and resource utilization.
Production planning is required for scheduling, dispatch, inspection, quality management,
inventory management, supply management and equipment management. Production control
ensures that production team can achieve required production target, optimum utilization of
resources, quality management and cost savings.
Planning and control are an essential ingredient for success of an operation
unit. The benefits of production planning and control are as follows:
It ensures that optimum utilization of production capacity is achieved, by proper
scheduling of the machine items which reduces the idle time as well as over use.
It ensures that inventory levels are maintained at optimum levels at all time, i.e. there is
no over-stocking or under-stocking.
It also ensures that production time is kept at optimum level and thereby increasing the
turnover time.
Since it overlooks all aspects of production, quality of final product is always maintained.
Production Planning
Production planning is one part of production planning and control dealing with basic concepts
of what to produce, when to produce, how much to produce, etc. It involves taking a long-term
view at overall production planning. Therefore, objectives of production planning are as follows:
To ensure right quantity and quality of material, equipment, etc. are available during
times of production.
To ensure capacity utilization is in tune with forecast demand at all the time.
A well thought production planning ensures that overall production process is streamlined
providing following benefits:
Organization can deliver a product in a timely and regular manner.
21 | P a g e
Suppliers are informed will in advance for the requirement of materials.
It reduces investment in inventory.
It reduces overall production cost by driving in efficiency.
Production planning takes care of two basic strategies, product planning and process planning.
Production planning is done at three different time dependent levels i.e. long-range planning
dealing with facility planning, capital investment, location planning, etc.; medium-range
planning deals with demand forecast and capacity planning and lastly short term planning
dealing with day to day operations.
Production Control
Production control looks to utilize different type of control techniques to achieve optimum
performance out of the production system as to achieve overall production planning targets.
Therefore, objectives of production control are as follows:
Regulate inventory management
Organize the production schedules
Optimum utilization of resources and production process
The advantages of robust production control are as follows:
Ensure a smooth flow of all production processes
Ensure production cost savings thereby improving the bottom line
Control wastage of resources
It maintains standard of quality through the production life cycle.
Production control cannot be same across all the organization. Production control is dependent
upon the following factors:
Nature of production (Job oriented, service oriented, etc.)
Nature of operation
Size of operation
22 | P a g e
A planning system starts with a forecast of future demand over some forecast horizon of length
H periods. The long-term portion of this forecast is an input into a capacity and/or aggregate
planning module that assesses whether or not there is sufficient capacity to satisfy the demand
forecast.
Four common ways
Seasonal demand, one might develop an aggregate production plan that builds inventory
during the off season in anticipation of a seasonal demand peak.
Second, the mismatch might be addressed by adding to or augmenting current capacity, for
instance through overtime or subcontracting.
Third, when it is not possible to build anticipation inventory or add capacity, one would
delay meeting demand. This is usually done in terms of extending the backlog by quoting
8longer and longer delivery lead times to customers.
Finally, there may be some downward revision of the forecast so as to eliminate the gap
between the firm‟s supply capacity and the anticipated demand; this might be an outcome
from a sales and operations planning (S&OP) process that equates the forecast to a sales
plan and then aligns the sales plan to the production plan
The next step is to convert the forecast over the shorter term into a detailed master production
schedule, subject to the guidelines or constraints from the aggregate capacity plan. The aggregate
capacity plan determines, at a gross level, how and when customer demand is met. Given the
aggregate capacity plan and the current finished goods (FG) inventory, the master production
schedule determines the necessary production output to meet the demand forecast over the short
term. Relative to the aggregate capacity plan, the master production schedule is at a much more
detailed level, both in terms of products and time periods. In some contexts, production lot or
batch sizing is done as part of the master scheduling, so as to account for economies of scale in
the production process. Also, there is sometimes an additional iteration to check the feasibility of
the master schedule relative to the available capacity.
To determine the inputs into the production system, we need to convert the master production
schedule into a plan for the raw materials (RM) and intermediate products. This is traditionally
23 | P a g e
done with the logic of materials requirement planning (MRP), based on a bill of materials and
process recipes for each final product. The key assumption is that we have planned lead times for
each required activity to produce the product; that is, for the procurement of each raw material,
as well as for each process and transportation step, we assume that the activity takes a known
deterministic amount of time, termed the planned lead time. With this assumption, we can
readily translate the master production schedule into time-phased requirements for each of the
raw materials, intermediate products and subsystems required to produce each final product. For
the raw materials, these requirements trigger replenishment requests from outside suppliers. For
the intermediate products and subsystems, these requirements are input to the shop floor control
system, which determines the work releases into production and the job priorities throughout the
production system. Again, these decisions are based on and guided by the planned lead times for
the process steps in the production operation.
Most implementations for production planning systems make no effort to recognize the
uncertainty in their environment. Indeed, in many planning systems that I have observed, there is
limited, if any, attempt to track and measure the uncertainty in the demand forecast or the
replenishment processes. For instance, we find that most planning systems do not retain and
measure forecast errors
Once a forecast has been revised, we observe that the old forecast is written over by the new
forecast, and the old forecast is lost. As a consequence, there is no record from which to measure
the forecast errors. Similarly, we still find implementations of planning systems that do not track
the actual replenishment times from suppliers, although this is slowly changing as lead-time
performance becomes a more common metric in supply contracts. The execution component of
most planning systems now has the capability to track the actual flow times within the
production operations; however, again we seldom see this data used to understand the
uncertainty in these processes. On the other hand, yield data does get recorded more routinely,
and at least the statistics on average yield seem to be more routinely used in the planning
systems.
24 | P a g e
4.7.1 Steps followed
Initially PPC department shares the production schedule with all the concerned
departments. This production plan is for 3 months, in which schedule of first month is
fixed while the schedule of next 2 months is tentative. Based on this plan, buyers procure
the material.
Vendor will dispatch the parts according to the schedule which is given by the buyers
based on the production plan.
Raw material arrives at Material Gate.
If material comes from warehouse then in that case only Eicher vehicles are allowed.
Vehicles of other companies are allowed in only 2 cases:-
o If that types of vehicles are not produced by Eicher.
o Or if that vehicle is coming from too far.
GE number is prepared at material gate after confirming shortages.
Material arrives at Unloading Dock with Bar code label specifying GE number and ASN
number.
TVS employee checks packaging standard of each part number by searching in files
containing hard copies of each part number.
TVS employee also checks for actual quantities, defect, and storage location specified
etc.
TVS employee scans the bar code that automatically creates GR number and sends one
copy of Invoice to Excise and 1 copy to Finance Department.
Material is taken inside CMS and stored at specific location allotted to it.
Based on the BOM and production plan, material will be released to the production line.
And after assembly and inspection, vehicle will be finally dispatched.
25 | P a g e
4.8 Functions of Procurement & Logistics
The Procurement & Logistics department negotiates and manages contracts with third party
suppliers for the acquisition of everything that a company needs to carry out its operations,
within time, in full and under competitive competition and pressure.
Procurement is the act of obtaining or buying goods and services. The process includes
reparation and processing of a demand as well as the end receipt and approval of payment. It
often involves
(1) Purchase planning,
(2) Standards determination,
(3) Specifications development,
(4) Supplier research and selection,
(5) Value analysis,
(6) Financing,
(7) Price negotiation,
(8) Making the purchase,
(9) Supply contract administration,
(10) Inventory control and stores, and
(11) Disposals and other related functions.
The process of procurement is often part of a company's strategy because the ability to purchase
certain materials will determine if operations will continue. A business will not be able to survive
if it is price of procurement is more than the profit it makes on selling the actual product.
Logistics is the coordination of projected requirement, procurement, physical movement, and
storage of components, parts, raw materials, and semi-finished and finished goods, to achieve
optimum demand-service level at minimal cost. It includes both inbound and outbound
movements, and is a larger concept than distribution management which does not include
activities such as forecasting and procurement.
26 | P a g e
5. Project 1: Study the variations in the demand pattern of vehicles and
analyze its effect on production planning.
5.1 Objective of the project The objective of the project can be divided into two parts.
Phase1
a) Understanding the current production planning system of the company.
b) Studying the monthly and weekly variations in the demand of different models.
c) Ascertain the data collection techniques and data requirement.
d) Data collection
Phase2
e) Data analysis
f) Recommendations
g) Report Making
5.2 Research Methodology
The project is carried out at Volvo Eicher commercial vehicles Ltd. Pithampur Plant, Indore. The
entire project comprised of the following major steps.
Identifying Management Dilemma: Triggers need for decision and symptoms of actual
problem. As per the discussion, it was found that for some of the models high
fluctuations in the demand made it difficult for the PPC department to plan their
production and lead to huge inventory being piled up.
Study the major sources of uncertainty in the marketing plan, realizing these uncertainties
and how these uncertainties affected the production plan.
27 | P a g e
Discuss the current production planning system framework for providing a basis for the
subsequent discussion and critique of production planning under uncertainty.
Data Collection: Primary data and Secondary Data. A mix of primary and secondary data
was used for the project..
Editing of data: To ensure consistency in the data and reduces recording errors.
Data Analysis & Interpretation: Managers need information not data. Develops
summaries, look for patterns by application of statistical tools, relationship among
variables. Making a series of observations on the generic treatment of uncertainty in
production planning in practice and understanding whether the current system accounts
for the uncertainty in the production plan.
Finally, identifying a set of tactical decisions that are being viewed as being critical for
handling uncertainty in production planning and describe how these tactics can be
incorporated into production planning systems as proactive countermeasures to address
various forms of uncertainty.
Reporting Results: Necessary to report and transmit the findings & recommendations to
managers for the intended purpose of decision making. Report should be developed from
the client‟s perspective.
28 | P a g e
1 • Identifying Management Dilemma
2 • Study the the current production planning system
3 • Study the major sources and types of uncertainty in the marketing plan
4 • Data Collection and data cleasing
5 • Look for patterns , relationship among variables. and make a series of
observations on the generic treatment of uncertainty in production planning in practice.
6
• Identifying a set of tactical decisions that are being viewed as being critical for handling uncertainty in production planning and reporting results
29 | P a g e
5.3 Current Production Planning System
INPUT PROCESS OUTPUT
1.2 Introdu
1.2.1 Ba
Marketing plan
released on 25th,
6th
and 15th of
the current
month
Review the plan for the
confirmed vehicles and the
tentative requirement
Week wise planning and
send the plan to all the team
members
Release the EDD of
monthly plan to mktg team
Convert the monthly RO
map into N+2 RO plan by
discussing with the
materials for any change in
RO sequence as per material
confirmation
Continuous monitoring and
ensuring that RO is
according to the EDD
Material
confirmation
received from
materials
department for
plan execution
Shortage list generated by
the store
Bulky items-1/2day
Rest of the items-N+2
days
Capacity planning and shift
planning
30 | P a g e
Analyze the problem so that
RO takes places according
to the EDD Back flushing in
SAP
OK Tagging
Delivery of the vehicle
Actual RO
Yes No
31 | P a g e
5.4 Study Approach
Figure8: Study approach
To get deep insights and study the variations in the demand pattern of various models of trucks
and busses the demand of these models was subdivided under the three classifications of Sales,
,BS and Brakes. Under each of these categories a detailed analysis was done to understand how
the demand fluctuated based on the three plans received by the PPC team.
Under the sales subcategory there were three classifications domestic, institutional and export.
Similarly the Brakes category was further subdivided into hydraulic, air, MCV and HCV. Under
the BS category it was divided into BS1, BS2, BS3 and TCI to get better insights of the
fluctuations in the demand.
32 | P a g e
5.5 Data Collection Methods
The data collection methods explain how the data in this research has been collected and has
been used to do further analysis.
5.5.1 Primary Data Primary data is data that is collected for the first time, i.e., the data did not exist before the
collection. Primary data was collected by observations and informal interviews to understand the
current production planning system. The entire approach towards the project was data based.
5.5.2 Secondary Data
Secondary data consists of data, which has been collected from VECV‟s system that contains
the complete one year demand of different models of truck and busses models under various
classifications.
The complete analysis was done using MS EXCEL tool.
The following format was used to collect and analyze data.
Figure9: Data collection format
33 | P a g e
5.6 Observations
I-Represents the demand for the vehicles received on 25
th
II-Represents the revised plan on 5th
III-Represents the revised plan on 15th
+
Graphs 1: Shows the variations in demand in I,II and III period
The above graph represents the combined demand of 2014 for all the models received on 25th
, 5th
and 15th
of every month.
38750
35771
34798
32000
33000
34000
35000
36000
37000
38000
39000
40000
I II III
No of vehicles demanded in I , II, III period
I-25th
plan
II-5th
Plan
III-15th
Plan
34 | P a g e
Graphs 2: Month wise variations in demand in I Period
Graphs 3: Month wise variations in demand in II Period
Graphs 4: Month wise variations in demand in III Period
The above graphs represents the moth wise fluctuations in demand based on I ,II and III plan.
M1 M2 M3 M4 M5 M6 M8 M9 N10 N11 N12
Total 3013 3108 3175 4380 4522 3152 3692 2522 3010 2824 2373
0
1000
2000
3000
4000
5000
I
M1 M2 M3 M4 M5 M6 M8 M9 N10 N11 N12
Total 3115 3198 3989 4158 4335 3720 3750 3516 3205 2660 3104
0
2000
4000
6000
II
M1 M2 M3 M4 M5 M6 M8 M9 N10 N11 N12
Total 3038 3114 3220 4423 3900 3359 3478 2286 2988 2554 2438
0
1000
2000
3000
4000
5000
III
35 | P a g e
Graphs 5: Sales variations
TERRA 25 BOGI
Graphs 6: Monthly variations for Terra 25 Bogie
0
2
4
6
8
10
12
I II III I II III I II III
Domestic Export IS
Av
er
ag
e v
alu
e
Plan based on country
10
20 20
10 10 10
21 21
10
50
35 35 41
28 28 30
21
36 30
25 25
10 10 10
0
25
18
7 10 10
15 21
7
0
10
20
30
40
50
60
I II III I II III I II III I II III I II III I II III I II III I II III I II III I II III I II III
M1 M2 M3 M4 M5 M6 M8 M9 N10 N11 N12
Domestic
I 33835
II 30265
III 29254
Export
I 4279
II 4779
III 4880
IS
I 544
II 727
III 664
36 | P a g e
TERRA 25
Graphs 7: Monthly variations for Terra 25
13 18 18 15
25 25
75 70
64
85 85 85
50
15 21
14
22 27
67
82 82 87
65 60
47 47 47
34 41 41 40
49
36
0
10
20
30
40
50
60
70
80
90
100
I II III I II III I II III I II III I II III I II III I II III I II III I II III I II III I II III
M1 M2 M3 M4 M5 M6 M8 M9 N10 N11 N12
III III III III III III III III III III III
M1 M2 M3 M4 M5 M6 M8 M9 N10 N11 N12
Sum of QUANTITY 18 25 64 85 21 27 82 60 47 41 36
Sum of PRODUCTION 31 11 64 80 21 27 78 60 47 42 83
0
10
20
30
40
50
60
70
80
90
37 | P a g e
Graphs 8: Planned Vs actual production for Terra 25
TERRA 16
Graphs 9: Monthly variations for Terra 16
Graphs 10: Planned Vs actual production for Terra 16
112 104 104
85
35 40 42 37 42 31
16 16
45 37 37 37
15 22
50
75 75 70 67 67 53
79 79
25
56 56
33
79
140
0
20
40
60
80
100
120
140
160
I II III I II III I II III I II III I II III I II III I II III I II III I II III I II III I II III
M1 M2 M3 M4 M5 M6 M8 M9 N10 N11 N12
III III III III III III III III III III III
M1 M2 M3 M4 M5 M6 M8 M9 N10 N11 N12
Sum of QUANTITY 104 40 42 16 37 22 75 67 79 56 140
Sum of PRODUCTION 145 39 42 16 39 24 75 67 82 73 86
0
50
100
150
200Planned Vs Actual production
38 | P a g e
Graphs 11: Sales variations for Terra 16
10.50
Graphs 12: Monthly variations for 10.50 model in BS3 and BS4category
I II III I II III
Domestic Export
Total 7.552238806 7.314285714 7.128571429 2.961538462 3.034482759 6.172413793
012345678
Sales
I II III I II III I II III I II III I II III I II III I II III I II III I II III I II III I II III
M1 M2 M3 M4 M5 M6 M8 M9 N10 N11 N12
BS4-CRDI 0 7 7 9 9 9 5 4 4 11 11 11 19 20 17 3 3 3 0 0 0 41 41 2 2 2 0 4 4 1 0 10
BS-3 Mech 7 63 57 62 79 79 82 45 55 70 81 83 13 11 76 96 69 74 72 64 64 61 43 43 64 46 46 37 36 33 15 11 7
0
50
100
150
200
250
BS4-CRDI
BS-3 Mech
39 | P a g e
Graphs 12: Sales variations for 10.50 model in BS3 and BS4category
10.59
Graphs 13: Monthly variations for 10.59 model
I II III I II III I II III
Domestic Export IS
BS4-CRDI 151 156 163 1 47 47
BS-3 Mech 662 614 569 37 38 48
0
100
200
300
400
500
600
700
800
900Sales
BS4-CRDI
BS-3 Mech
58 62 58
30 27 26
54 57 64
37 44
34
70 63
50
76 79 80
54 50 49 44 57 57
20 18 18 8
18 15
38 27 31
I II III I II III I II III I II III I II III I II III I II III I II III I II III I II III I II III
M1 M2 M3 M4 M5 M6 M8 M9 N10 N11 N12
0
20
40
60
80
100
40 | P a g e
Graphs 14: Sales variations for 10.59 model
10.35(8X2 cab)
Graphs 15: Monthly variations for 8X2 cab
Graphs 16: Sales variations for 8X2 cab
I II III I II III
Domestic Export
Total 228 220 227 261 282 255
050
100150200250300
Sales
I II III I II III I II III I II III I II III I II III I II III I II III I II III I II III I II III
M1 M2 M3 M4 M5 M6 M8 M9 N10 N11 N12
BS3 27 17 17 45 42 42 85 90 85 20 20 20 11 12 12 35 21 54 95 65 65 14 34 34 0 0 0 0 0 0 4 2 12
VEPT 3 0 3 17 17 17 10 10 10 1 5 5 0 0 0
0
50
100
150
200
250
BS3
VEPT
731
571 601
14 28 36 0 1 1 31 32 35
0
200
400
600
800
I II III I II III I II III
Domestic Export IS
BS3
VEPT
41 | P a g e
35.35(8X2 cowl)
Graphs 17: Monthly variations for 8X2 cowl
Graphs 18: Sales variations for 8X2 cowl
10 10 10
20 20 20
50 55 55
70 67 67
62
47 47
65
50 55
45
37 37
30
5 5
20 20 20
5 5 5
15
40
I II III I II III I II III I II III I II III I II III I II III I II III I II III I II III I II III
M1 M2 M3 M4 M5 M6 M8 M9 N10 N11 N12
0
10
20
30
40
50
60
70
80
345 322 331
32 9
30
0
50
100
150
200
250
300
350
400
I II III I II III
Domestic Export
Sales
43 | P a g e
The above diagram shows a matrix multiplication where we have initially assumed that
whatever was bought was consumed.
45 | P a g e
6.Project 2: To develop a system for identification and management of trolleys
so as to reduce incurred production losses.
Non Availability
Occupancy –availability
OEE (Overall Equipment effectiveness) - Health of Trolleys
Traceability
6.1 Need & Scope of Project
In this project:
A system of identification of various trolleys by putting a red tag on them will be
developed.
A digital information system for trolley calling will be proposed.
Trolley classification on the basis of their health shall be done.
6.2Capital Asset and Capital Asset Management
A capital asset is defined to include property of any kind held by any possessor, whether
connected with their business or profession or not connected with their business or profession. It
includes all kinds of property, movable or immovable, tangible or intangible, fixed or circulating.
Trolleys for material movement are a capital asset of any company and they need to be managed
properly for better productivity.
6.3 Current scenario in VECV
Material movement in VECV is done in either:
Trolleys
Steel Pallets
Wooden Pallets
46 | P a g e
Major losses up to 50% were faced due non availability, supply delay etc. of trolleys.
For identification:
If “VECV – XXX – VECV” is painted, then it is property of VECV, else”XXX – VECV
– XXX” is painted on all outgoing trolleys (Figure 8).
Trolley details like, part number and name, quantity and visually, the way of storing are
painted on new trolleys only (Figure 9).
For area identification, color coding on top rack is done.
No proper system support present, only in-warding and out-warding details can be
gathered.
Fig8.Owner Identification of Trolleys Fig.9 Details on New Trolleys
Table10: Enlists the various trolley storage areas along with their color coding and the floor area.
47 | P a g e
Table 10: Trolley areas, space available and color coding
*Approx Values of Space Available
Washing & Maintenance
Separate areas for bin and trolley washing.
Bin washing is done in a washing machine, but grease, chemicals stains are removed
manually.
No proper system support and records for trolley movement and maintenance.
6.4 Concepts of 5s
5S is the name of a workplace organization method that uses a list of five Japanese words: seiri,
seiton, seiso, seiketsu, and shitsuke. Transliterated or translated into English, they all start with
the letter "S". The list describes in order, how to organize a work space for efficiency and
effectiveness by identifying and storing the items used, maintaining the area and items, and
sustaining the new order.
48 | P a g e
Seiri (Segregation)
It means to look around the work place and to sort out the use-full and non-use-full items.
The non-use-full items should be checked for use-fullness and then disposed off properly.
In no case, the on-use-full items be kept near the workplace.
Seiton (Systematic Arrangemet)
All the items, which are necessary, should be kept according to a fixed arrangement from
where they can be most conveniently retrieved and used. All the useful things should be
kept in proper order. In other words “A Place for Everything and Everything in its Place
(PEEP)” should be strictly followed
Seiso (Shine)
The work area along with all the equipment‟s should be properly cleaned. Ideally the
floor should be sparkling clean. It should not be the duty of any one specific person, but
all the people associated with that area.
Seiketsu (Standardize)
Standardization of best practices in the work place. It is the maintenance of Seiri, Seiton
and Seiso constantly. If standardization is not done and followed properly, then work
place is bound to deteriorate.
Shitsuke (Sustain)
Shitsuke is to install work practices that will ensure and enable the implementation of all
the aspects of 5-S.Everyone should be self-disciplined to strictly follow the rules and
standards while working. All the set rules like punctuality should be strictly followed.
Applying these concepts definitely improves the productivity of the machines and people. Hence,
to improve trolley problems, these concepts have been used.
49 | P a g e
6.5 Suggested Solutions
The following solutions are suggested:
Seiri: the first step is to identify the bad trolleys/pallets and separate them from the good
ones. If the bad trolleys could be mended or made to use somehow, then it should be done,
else they shall be written off from the company.
For all the good trolleys, “5s Red Tagging” must be done. It will not only identify various types
of trolleys, but also give a good count and better traceability (fig 15).
Fig 11 5s Red Tag for Trolleys
Seiton: After “Red Tagging”, a clear data of frequency of movement of all the trolleys can
be gathered easily. Then accordingly, proper floor area division for filled and empty
trolleys can be demarcated easily. For system support in SAP, a digital information system
for trolley calling at various locations can be developed. This will help in effective
movement of all the trolleys as well as their traceability.
Seiso: Since currently, no proper cleaning system is present, it is suggested that all the
trolleys should be mandatorily be sent for service every six months, over a period of 2
weeks. Repainting should be done every alternate year. Moreover, in SAP a classification
of trolleys on their health shall be done as follows: Superb, Satisfactory and Unpleasant.
50 | P a g e
Seiketsu: PFMEA for trolleys handling for critical and fragile parts should be done.
Along with this, the Overall Equipment Effectiveness (OEE) and Mean Time Between
Failure (MTFB) should be calculated.
OEE = Availability * Performance * Quality
Also, since there is no standard documentation for trolleys, a new documentation similar
to PPAP should be developed, signed between Stores Engineering, Stores Management
and Stores In-Charge.
Shitsuke: Sense of ownership should be developed in all the individuals related to stores.
The 3 PL people should be the first line of defense in case of a breakdown. Surveillance
through CCTV cameras by a trusted person should be done and finally, accolades to the
workers with best trolley health should be given
6.6 Conclusion
Implementing the above solutions is definitely bound to improvement in the line loss incidents
occurring due to trolleys. Though it may be difficult initially, to incorporate the above mentioned
solutions, but once done it will drastically help the company.
6.7 Further Steps
The next step is execution. For that the heads of stores, engineering, TVS etc will sit
together.
A person completely responsible for the trolleys (specifically from TVS) will be decided
upon.
Red tagging of all the trolleys at CMS entrance from plant will be done (say within 2-3
days).
General records & physical maintenance will be done from the red tags.
51 | P a g e
7 Project3: Design a data dashboard to improve the visibility and make data
visualization simpler for PPC team.
7.1 Objective of the project
The objective of this project is to identify various aspects of production planning and display
them using dashboard tool so as to improve visibility and make data visualization simpler. The
dashboard is prepared using inputs from the production planning and control department. As per
the current system the data is being recorded in SAP and the individual team members extracts
data as per need and carries out analysis. So this process is more time consuming and the
analysis is carried out at month end. To improve this process and increase the efficiency of the
supply chain as well as employee, we have to identify the parameters those will act as lead
indicators and provide multidimensional visual representation of data that will reduce the time
spent by the team in analyzing data and taking decisions. This project will help to reduce the
non-value added time wasted by PPC team to compile it into a form on which decisions could be
taken. Effective decision-making is based on having the right information available and easily
accessible.
7.2 Need of the project
To achieve this visibility it is essential to develop a tool that will provide a complete overview of
the key performance indicators and other parameters that are useful in analyzing and studying the
changes in production plan. Dashboard is tool through which this information can be displayed
in an effective and an easy manner. The dashboard must efficient to provide the SCM with
different aspects of production plan, thus providing an improved visibility.
52 | P a g e
7.2.1 Benefits of dashboard are:
Improved data visibility
Time saving process
Eliminate redundant operations (duplicate folders, workbooks, etc.)
Increased productivity and efficiency of employee
Makes decision making easy
The major aspects that should be included in dashboard are:
Marketing plan variations
o Projections as well as actual roll out of HD and LMD
o Monthly Plan variations wrt 25th
Plan and 3rd
Plan for HD and LMD
o Date wise addition and deletion of the components
Direct runner and Delivery precision for HD and LMD
Line utilization and various types of losses
Monthly roll out for HD and LMD\
Budgeted vs Actual roll out
Day wise plan changes
7.2.2 Expected project deliverables:
Once the project is successfully completed it is expected to deliver the following:
A dashboard.
The dashboard will incorporate Key performance indicators that will support decision
making process.
Display of data graphically and tabular form for easy analysis, comparison.
Better visibility
53 | P a g e
Displays trends of performance with respect to target that will simplify decision making.
Provides real time trend analysis
A standardize data visibility and analysis approach.
Highlight grey areas to management which requires attention.
7.2.3 Project Plan
1 •Understanding the need of the project
2 •Study on dashboards. and PPC system of the comapny
3 •Gathering requirements and expectations from users and identifying the KPI'S
4 •Developing of data needed for preparing dashboard
5 •Initiate designing of the dashboard in excel
6 •Finalizing the outlook of the dashboard in excel
7 •Identify possible flaws and problems
8 •Fix and improve problems in dashboard outlook
9 •Testing of final dashboard
10 • Training to end user about the dashboard usage
54 | P a g e
7.3 Dashboards
Mr. Hans Peter Schaefer from The Gillette Company once said, “I want a supply-chain
dashboard that looks like the dash in my 911 Carrera, with all of the dials set to my specific
supply-chain metrics. And when any one goes out of tolerance, I want the dial to redline and let
me drill into the specific issue, and resolve it”. This is the role played by a dashboard, i.e. to
provide a complete inventory visibility to the management to simplify the decision making
process and monitoring the inventory for its performance.
A dashboard basically provide the user with the trends of various performance measures based
on the requirement of the user, these trends are updated on a real time basis simplifying the
decision making process for the user. Stephen Few‟s defined dashboard as, “A dashboard is a
visual representation of important parameters that are essential to achieve organizations goals,
these parameters are put together and displayed on single screen, to attain effective decision
making”, (2006,34).
Alexander and Walkenbach, stated that there are three main characteristics of dashboard (2010):
Dashboards are mostly graphical, providing visual representation of important trends,
comparisons and exceptions.
It displays only the information desired by the user
Dashboards are designed towards a specific goal or purpose with predefined conclusions
and essentially reduce the need of its user to perform an analysis regarding the
information.
Dashboard is not a report that just provide data to the user, it is basically an analysis tool
that represent the data in more concluding way that makes decision making easier for the
user.
55 | P a g e
Dashboards can be classified as per the role in the project. The role will be to support the
business activities. The dashboards are classified into 3 types.
Strategic: These dashboards provide managers with quick view of the organizations
health. The display performance measure and forecasts. Strategic dashboards benefit
from static snapshots of data (daily, weekly, monthly, and quarterly) that are not
constantly changing from one moment to the next. They help track progress of attainment
of strategic objectives. (eg. Balanced Scorecard)
Analytical: Analytical dashboards include more context, comparisons, and history. These
dashboards support more data interaction like drilling down into details. They are used to
analyze the performance and measure the performance level towards achieving goal.
Operational: Operational dashboards are used to monitor operational processes, events,
and activities as they occur (every minute, hour, or day).
The above mentioned types of dashboards are only a framework that describes these three
dashboard types. Wayne Eckerson says in his book that it is not necessary to determine
which type of dashboard you want to build before beginning a project. In reality, many
dashboards don‟t fit cleanly within the boundaries described. The purpose of this
framework is to help you understand the various purposes for which dashboards are built
and the range of functionality that they can exhibit, (2010, 121).
7.3.1 Dashboard Designing
The most important step in the development and designing of the dashboard is to
understand the user needs. This includes identifying the KPI‟s which need to be
incorporated into the dashboard, what output to be displayed, how the dashboard should
appear, information sources, performance measures, etc. These inputs acts as a database
for the dashboard to function. These are the data source which contains all the
56 | P a g e
information that is made visible to the user in more informative way. The dashboard must
be designed in such a way that it should simple and easy to interpret.
According to Eckerson, (2010) there are some points that should be taken into
consideration while designing of the dashboard. These are as follows:
Identify the requirements and data.
Understand the user requirements & expectations.
Take account of the design principles
Develop a prototype.
Test the dashboard for its functionality and efficiency.
Identify improvements
Perform corrective action and finalize the design
Eckerson has also mentioned two important points on dashboard designing: the first is on
creation of display and the other is on chart design. The following things should be taken into
consideration while creating display:
There should not be too much data displayed as it may create confusion.
Design an outlook that will have a single screen to display information.
Keep charts as simple as possible.
Display only important data that will give maximum of information.
Arrange the charts/ tables more intelligently and sequentially linked.
The following things should be taken into consideration while designing charts:
Comparing data should be easier.
Provide options to toggle between table and charts.
Provide slicing dicing options to represent data that is required.
Use the right graph as per the data and outcome expected from it.
57 | P a g e
7.3.2 Design Principles for Dashboard
Below are some principles which were described by Alexander and Walkenbach, (2010, 17).
These principles also correlate to the guidelines described in dashboard design:
Avoid unnecessary information in chart
No gridlines
No borders
Skip usage of trend lines
Avoid unnecessary usage of data labels
Remove unnecessary legends and templates
Keep formatting as simple as possible avoid complications
Do not keep axis that doesn‟t add value
Avoid usage of color and background fills.
Avoid using clip arts or pictures
Have a layout and placement of data that draws focus, study shows that user pays
attention to the upper left and middle left of a document.
Display monetary values only where required.
Use separators like comma between numbers
Effective usage of titles and labels:
Include timestamp
Have some text that provides information when the data was extracted
Use descriptive titles
Dashboard should be user friendly
Navigation should be easy
It should reflect data on real time basis
Data displayed should be of high accuracy and error free
58 | P a g e
7.4 Software’s required for the project
Microsoft Excel
Microsoft excel is a spreadsheet application provided by Microsoft. It has basic features that has
cells arranged in rows and columns forming a spreadsheet in which desired formulae‟s can be
put up to organize data as required. Excel can be used to perform various mathematical
operations as well as for data representation. Various types of charts can also be made using
excel.
As per the current system data is extracted from SAP and excel is used to study the data by
preparing desired charts. Excel is flexible and dashboards can be prepared in excel as per the
user requirements
7.5 Solution Requirements (Dashboard)
In order to make the dashboard successful many inputs are required. These inputs are essential to
carry out the inventory management at. This information will be displayed on to the dashboard
for effective monitoring and management. A thorough study and requirements identification was
done to define the parameters that will the form output of the dashboard. By reviewing the
factory that will have an impact on production planning and expectations of the user, we have
classified these into
Monthly variations in the marketing plan.
Number of vehicles added and deleted wrt 25th
and 3rd
/5th
plan for every month.
Day wise details of the addition and deletion of the vehicles.
Monthly details of line utilization and losses.
Direct runner and delivery precision details for both Heavy duty and Light and Medium
duty vehicles.
Budgeted v/s Actual roll out.
Plan change for each day.
59 | P a g e
7.6 Data input Analysis
7.6.1Marketing Plan
On the 25th
of every month the PPC department gets a requirement of the number of vehicles to
be produced from the marketing team. Based on that data production planning is done to meet
the demand of the customer at the right time. But this demand suffers a high fluctuation for both
HD and LMD models and these fluctuations in the demand affects the production planning, line
utilization, manpower utilization and the inventory. So the dashboard will provide a complete
overview of the month wise variations in the marketing plan for HD and LMD vehicles, monthly
addition and deletion of vehicles wrt 25th
and 3rd
/5th
Plan as well as day wise addition and
deletion of the vehicles for each month
7.6.2Dashboard view of parameters
Below are dashboard views of the parameters identified .
Graphs 19: Delivery Precision graph for HD
60 75
67 59 56
43 41
5
56
75 67
59 55 44
56 56 43 41
5 0
10
20
30
40
50
60
70
80
20
11
20
12
20
13
20
14
Q1
20
14
Q2
20
14
Q3
20
14
Q4
Jan
'14
Feb
'14
Mar
'14
Ap
r'1
4
May
'14
Jun
;14
Jul'
14
Au
g'1
4
Sep
'14
Oct
'14
No
v'1
4
Dec
'14
Delivery Precision HD
60 | P a g e
Graphs 20: Delivery precision showing Quarterly actual Vs targeted comparison
Graphs 21: Delivery precision showing Yearly actual Vs targeted comparison
The above graphs shows a comparative analysis of the actual Vs targeted value of Direct runner and
Delivery precision for HD and LMD vehicles. This will help the user to make yearly, quarterly and
monthly comparative analysis.
5
56
75 67
50 50 50 50
0
10
20
30
40
50
60
70
80
2014 Q1 2014 Q2 2014 Q3 2014 Q4
Actual Target
60
43 41
50 50 50
0
10
20
30
40
50
60
70
2011 2012 2013
Actual Target
61 | P a g e
Graphs 22: N-3 and N-6 days compliance for HD and LMD
The above graph shows N-3 and N-6 days compliance for both HD and LMD vehicles. It means
that the production planning team fix a duration of 6 and 3 days for HD and LMD vehicles
respectively after which the specifications of the product can‟t change
44 54 56
66 77 78
34
78
56
78
98
44 54 56
95 95 95 95 95 95 95 95 95 95 95 95 95 95
0
20
40
60
80
100
120
2013 2014 Jan'15 Feb'15 Mar'15 Apr'15 May'15 Jun'15 Jul'15 Aug'15 Sep'15 Oct'15 Nov'15 Dec'15
LMD N-6 days plan adherence
Actual
Target
62 | P a g e
Graphs 23: Marketing plan showing projections for LMD and HD
Graphs 24: % variations from the market wrt 25th
and 5th
plan for LMD and HD
2360 2343
4322
2223
3432
2267 2289 2311 2333 2355
572 579 586 593 453
988
614 621 628 635
0
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
15th 25th Nov 1stPlan
25th Nov2nd Plan
28-Nov 04-Dec 05-Dec 11-Dec 12-Dec 20-Dec 23-Dec
LMD PROJECTIONHD PROJECTION
oct'13 Nov'13 Dec'13 Jan'14 Feb'14 Mar'14 Apr'14 May'14 Jun'14 July'14 Aug'14 Sept'14 Oct'14 Nov'14 Dec'14
wrt 25th Plan 72 54 65 32 43 23 43 43 45 67 66 55 90 34 56
3rd/5th Plan 45 67 66 55 90 34 56 72 54 65 32 43 23 43 43
0
10
20
30
40
50
60
70
80
90
100 Variations(addn/deletion)
63 | P a g e
Graphs 25: Number of vehicles added and deleted for LMD and HD
Graphs 26: Graph showing the monthly variations in the various line losses and utilization
2.2 2.3 2.5 2.4
2.6 2.7 2.8
0.5
4.9
2.2
3.7
4.1
5.1
0
1
2
3
4
5
6
Jan Feb Mar March April May Jun Jul Aug Sep Oct Nov Dec
64 | P a g e
This line graph provides us month wise details of the various losses like material-NPD, material-
Regular, MFG, Piloting etc. and line utilization. Based on the model (LMD and HD) and the year
the user can extract information and understand the trend for further analysis.
Graphs 27: Graph showing the monthly Roll out for HD and LMD
The above graph shows the Roll out analysis for HD and LMD vehicles. User can understand the
yearly and monthly variations in the Roll out for vehicles.
7.7 Conclusion
A data dashboard for Production Planning and Control
The dashboard includes KPI‟S that will support decision making process
Display of data graphically and tabular form for easy analysis and comparisons.
There will be a multidimensional display of information.
Displays trends of performance with respect to target that will simplify decision making.
A standardize data visibility and analysis approach in the PPC team Highlight grey areas
to management which requires attention.
65 | P a g e
8.References
http://www.ibef.org/industry/india-automobiles.aspx
http://en.wikipedia.org/wiki/Automotive_industry_in_India
http://business.gov.in/Industryservices/automobile_industry.php
Caridi et al. (2010), “Measuring visibility to improve supply chain performance: a
quantitative approach”, Benchmarking: An International Journal, Vol. 17, No. 4, pp. 593-615.
Francis, V. (2008), “Supply chain visibility: lost in translation?”Supply Chain Management: An
International Journal, Vol. 13, No. 3, pp. 180-184.
Russell,S.R & Taylor,W.B.(2011),”Operations Management”,New York,7th Addition,John
Wiley & Sons,Inc.