EHP4 for SAP ERP6.0
June 2010
English
Logistics Planning (144)
SAP AGDietmar-Hopp-Allee 1669190 Walldorf Germany
Business Process Documentation
7/29/2019 144_BPP_EN_US
http://slidepdf.com/reader/full/144bppenus 2/25
SAP Best Practices Logistics Planning (144): BPD
Copyright© Copyright 2010 SAP AG. All rights reserved.
No part of this publication may be reproduced or transmitted in any form or for any purpose without the expresspermission of SAP AG. The information contained herein may be changed without prior notice.
Some software products marketed by SAP AG and its distributors contain proprietary software components of other software vendors.
Microsoft, Windows, Excel, Outlook, and PowerPoint are registered trademarks of Microsoft Corporation.
IBM, DB2, DB2 Universal Database, System i, System i5, System p, System p5, System x, System z, Systemz10, System z9, z10, z9, iSeries, pSeries, xSeries, zSeries, eServer, z/VM, z/OS, i5/OS, S/390, OS/390,OS/400, AS/400, S/390 Parallel Enterprise Server, PowerVM, Power Architecture, POWER6+, POWER6,POWER5+, POWER5, POWER, OpenPower, PowerPC, BatchPipes, BladeCenter, System Storage, GPFS,HACMP, RETAIN, DB2 Connect, RACF, Redbooks, OS/2, Parallel Sysplex, MVS/ESA, AIX, Intelligent Miner,WebSphere, Netfinity, Tivoli and Informix are trademarks or registered trademarks of IBM Corporation.
Linux is the registered trademark of Linus Torvalds in the U.S. and other countries.
Adobe, the Adobe logo, Acrobat, PostScript, and Reader are either trademarks or registered trademarks of Adobe Systems Incorporated in the United States and/or other countries.
Oracle is a registered trademark of Oracle Corporation.
UNIX, X/Open, OSF/1, and Motif are registered trademarks of the Open Group.
Citrix, ICA, Program Neighborhood, MetaFrame, WinFrame, VideoFrame, and MultiWin are trademarks or registered trademarks of Citrix Systems, Inc.
HTML, XML, XHTML, and W3C are trademarks or registered trademarks of W3C®, World Wide WebConsortium, Massachusetts Institute of Technology.
Java is a registered trademark of Sun Microsystems, Inc.
JavaScript is a registered trademark of Sun Microsystems, Inc., used under license for technology invented andimplemented by Netscape.
SAP, R/3, SAP NetWeaver, Duet, PartnerEdge, ByDesign, SAP Business ByDesign, and other SAP productsand services mentioned herein as well as their respective logos are trademarks or registered trademarks of SAP AG in Germany and other countries.
Business Objects and the Business Objects logo, BusinessObjects, Crystal Reports, Crystal Decisions, WebIntelligence, Xcelsius, and other Business Objects products and services mentioned herein as well as their respective logos are trademarks or registered trademarks of Business Objects S.A. in the United States and inother countries. Business Objects is an SAP company.
All other product and service names mentioned are the trademarks of their respective companies. Datacontained in this document serves informational purposes only. National product specifications may vary.
These materials are subject to change without notice. These materials are provided by SAP AG and its affiliatedcompanies ("SAP Group") for informational purposes only, without representation or warranty of any kind, andSAP Group shall not be liable for errors or omissions with respect to the materials. The only warranties for SAPGroup products and services are those that are set forth in the express warranty statements accompanyingsuch products and services, if any. Nothing herein should be construed as constituting an additional warranty.
© SAP AG Page 2 of 25
7/29/2019 144_BPP_EN_US
http://slidepdf.com/reader/full/144bppenus 3/25
SAP Best Practices Logistics Planning (144): BPD
Icons
Icon Meaning
Caution
Example
Note
Recommendation
Syntax
External Process
Typographic Conventions
Type Style Description
Example text Words or characters that appear on the screen. These include field names,screen titles, pushbuttons as well as menu names, paths, and options.
Cross-references to other documentation.
Example
text
Emphasized words or phrases in body text, titles of graphics and tables.
EXAMPLETEXT
Names of elements in the system. These include report names, programnames, transaction codes, table names, and individual key words of aprogramming language, when surrounded by body text, for example, SELECTand INCLUDE.
Example
text
Screen output. This includes file and directory names and their paths,messages, source code, names of variables and parameters as well as namesof installation, upgrade and database tools.
EXAMPLE TEXTKeys on the keyboard, for example, function keys (such as F2) or the ENTER key.
Exampletext
Exact user entry. These are words or characters that you enter in the systemexactly as they appear in the documentation.
<Exampletext>
Variable user entry. Pointed brackets indicate that you replace these words andcharacters with appropriate entries.
© SAP AG Page 3 of 25
7/29/2019 144_BPP_EN_US
http://slidepdf.com/reader/full/144bppenus 4/25
SAP Best Practices Logistics Planning (144): BPD
Contents
Logistics Planning............................................................................................................................... 5
1 Purpose ........................................................................................................................................... 5
2 Prerequisites.....................................................................................................................................5
2.1 Master Data and Organizational Data........................................................................................ 5
2.2 Business Conditions ..................................................................................................................6
2.3 Preliminary Steps....................................................................................................................... 6
2.4 Roles.......................................................................................................................................... 7
3 Process Overview Table...................................................................................................................8
4 Process Steps.................................................................................................................................10
4.1 Sales and Operation Planning..................................................................................................10
4.2 Long Term Planning.................................................................................................................13
5 Follow-Up Processes...................................................................................................................... 235.1 Operational Production Planning and Control........................................................................ ..23
6 Appendix......................................................................................................................................... 24
6.1 Reversal of Process Steps.......................................................................................................24
6.2 SAP ERP Reports ..................................................................................................................24
© SAP AG Page 4 of 25
7/29/2019 144_BPP_EN_US
http://slidepdf.com/reader/full/144bppenus 5/25
SAP Best Practices Logistics Planning (144): BPD
Logistics Planning
1 PurposeThe purpose of logistics planning is to make sure that future demand can be satisfied by your company’s available resources and to point out situations where demand cannot be met in time or inthe desired quantities.
This process sometimes is called Sales and Operations Planning . The process usually takes placein a simulative mode and at an aggregated (usually product group) level. Once a feasible productionplan is found that satisfies demand it can be used as the basis for operational production planning(MRP and Detailed Capacity Scheduling).
The Best Practices scenarios in this section cover the following planning workflow:
• Planning/forecasting of future demand
• Aggregated production planning including capacity check to check at product group level if
demand can be satisfied (using the SOP functionality)
• Transfer of results to Long Term Planning (using the LTP module) to enable simulation of
material requirements, based on the production plans
• Planning takes place in separate (simulative) planning versions within LTP
• Review and adjustments of planned requirements as needed
• Once the simulated requirements are accepted, the demand (independent requirements) is
then transferred to active demand management for detailed MRP and Production Planning /Scheduling in the active version.
2 Prerequisites2.1 Master Data and Organizational Data
A range of indispensable master and organizational data was created in your ERP system in theimplementation phase, such as the data that reflects the organizational structure of your company,and master data that suits its operational focus, such as master data for materials, vendors,customers, and so on.
This master data usually consists of standardized SAP Best Practices default values and enablesyou to go through the process steps of this scenario.
You can test the scenario with other material, or organizational data for which you havecreated master data. To find out how to create master data, refer to the Master DataProcedures documentation.
Use the following master data in the process steps described in this document:
© SAP AG Page 5 of 25
7/29/2019 144_BPP_EN_US
http://slidepdf.com/reader/full/144bppenus 6/25
SAP Best Practices Logistics Planning (144): BPD
Master data
Value Other Master Data
Bus. Condition Comments
ProductGroup
Level 1
00001B001 You have completed all steps described in theBusiness ProcessDocumentation Sales Qty Budget and Transfer toSOP (with CO-PA),Revenue Planning (172).
The productgroupscorresponds tothe producthierarchiesProduct
Group
Level 2
00001B000100000001
ProductGroup
Level 2
00001B000100000002
ProductGroup
Level 2
00001B000100000003
Plant 1000(1100)
SOPversion
001 Use theseversions in thedemo script
LTPVersion
001 Use theseversions in thedemo script
2.2 Business Conditions
The business process described in this Business Process Documentation is part of a bigger chain of integrated business processes or scenarios. As a consequence, you must have completed thefollowing processes and fulfilled the following business conditions before you can start going throughthis scenario:
Business condition Scenario
You have completed all steps described in the Business ProcessDocumentation Prerequisite Process Steps (154).
Prerequisite ProcessSteps (154)
You have completed all steps described in the Business ProcessDocumentation Sales Qty Budget and Transfer to SOP (with CO-PA), Revenue Planning (172). In this scenario, you performrevenue planning. The result is a sales plan in value and/or quantity. Usually the sales plan is based on the sales history and
is in quarterly, monthly, or weekly buckets.
Sales Qty Budget and Transfer to SOP (with CO-PA),Revenue Planning (172)
You have completed all steps described in the Business ProcessDocumentation Sales Quantity forecast (179).
Sales Quantity forecast (179)
2.3 Preliminary Steps
No preliminary steps are required to test this scenario.
© SAP AG Page 6 of 25
7/29/2019 144_BPP_EN_US
http://slidepdf.com/reader/full/144bppenus 7/25
SAP Best Practices Logistics Planning (144): BPD
2.4 Roles
Use
The following roles must have been installed to test this scenario in the SAP NetWeaver BusinessClient (NWBC). The roles in this Business Process Documentation must be assigned to the user or
users testing this scenario. You do not need these roles if you are not using the NWBC interface, butthe standard SAP GUI.
Prerequisites
The business roles have been assigned to the user who is testing this scenario.
Business role Technical name Process step
Employee(Professional User)
SAP_NBPR_EMPLOYEE-S Assignment of this role isnecessary for basic functionality.
Strategic Planner SAP_NBPR_STRATPLANNER-S
All process steps
© SAP AG Page 7 of 25
7/29/2019 144_BPP_EN_US
http://slidepdf.com/reader/full/144bppenus 8/25
SAP Best Practices Logistics Planning (144): BPD
3 Process Overview TableProcess step External
processreference
Businesscondition
Businessrole
Trans-actioncode
Expectedresults
Sales Qty Budget and Transfer toSOP (with CO-PA), RevenuePlanning
See scenario
Sales Qty Budget and Transfer toSOP (withCO-PA),RevenuePlanning (172)
Seescenario
(172)
Seescenario
(172)
The sales planis created.
Sales Quantity forecast (179)
See scenario
SalesQuantity
forecast (179)
Seescenario
(179)
Seescenario
(179)
The sales planis created.
DemandVerification(Check SalesPlan)
After salesfigures havebeentransferredto SOP
StrategicPlanner
MC76 Sales Plan hasbeen verified
Create Rough-Cut ProductionPlan
After Salesplan hasbeenchecked
StrategicPlanner
MC76 ProductionPlan created
Transfer Rough CutProductionplan to InactiveDemandManagement
ProductionPlan hasbeenchecked
StrategicPlanner MC75 The ProductionPlan from SOPhas beentransferred toinactivedemandmanagement
Create LongTerm PlanningScenario
BeforerunningsimulatedLTP MRP
StrategicPlanner
MS31 LTP Planningscenario iscreated
Execute LTPMRP Run
StrategicPlanner
MS01 The LTP MRPrun issimulated.
EvaluateCapacityRequirements
StrategicPlanner
CM38 Capacityconsumptionupdated oncost center
Activate aplannedindependent
You haveevaluatedand
StrategicPlanner
MS32 Plannedindependentrequirements
© SAP AG Page 8 of 25
7/29/2019 144_BPP_EN_US
http://slidepdf.com/reader/full/144bppenus 9/25
SAP Best Practices Logistics Planning (144): BPD
Process step Externalprocessreference
Businesscondition
Businessrole
Trans-actioncode
Expectedresults
requirementsversion
adjusted thesimulativeplanningresult
version isactivated for planningscenario
Copy toDemandManagement(active version)
StrategicPlanner
MS64 Active versioncreated inDemandManagement
Operational ProductionPlanning and Control
See allproductionscenarios
See allproductionscenarios
See all productionscenarios
See all productionscenarios
© SAP AG Page 9 of 25
7/29/2019 144_BPP_EN_US
http://slidepdf.com/reader/full/144bppenus 10/25
SAP Best Practices Logistics Planning (144): BPD
4 Process Steps
4.1 Sales and Operation Planning
Sales & Operation Planning (SOP) is the link between sales planning and manufacturing.
It is a forecasting and planning transaction to enable sales, production, inventory targets to bereached based on historical, existing, and estimated future data. In the process described below weuse SOP to:
o Verify the sales (demand) plan coming from COPA or other sources
o Create a Rough-cut production plan aimed to satisfy demand and to meet inventory targets
o Visualize capacity utilization of the critical resources (usually the bottleneck resources) to
verify the feasibility of the plan at an aggregated level.
SOP is suitable for long- and medium-term planning.
In this process, you view the S&OP figures. This is done after sales figures have been transferred
from CO-PA to SOP.You can visualize the following key figures
• Sales plan
• Production plan
• Projected Stock
4.1.1 Demand Verification (Check Sales Plan)
Use
In this activity, you check the sales plan at material level. In this scenario it is assumed that the sales
plan has been created at product group level.Therefore you can disaggregate your sales figures to a material to verify demand at an aggregatedlevel.
Also the opposite direction is possible (but not shown in this scenario): If your sales plan has beencreated at product group level you can disaggregate the plan according to predefined proportionalfactors to the material level. In this case it is useful to define the proportional factors according tohistorical sales figures to come to realistic forecasts at material level.
Prerequisites
This can be done after sales figures have been transferred to SOP from CO-PA.
Procedure1. Access the transaction choosing one of the following navigation options:
Option 1: SAP Graphical User Interface (SAP GUI)
SAP menu Logistics Production SOP Disaggregation Break Down
PG Plan
Transactioncode
MC76
© SAP AG Page 10 of 25
7/29/2019 144_BPP_EN_US
http://slidepdf.com/reader/full/144bppenus 11/25
SAP Best Practices Logistics Planning (144): BPD
Option 2: SAP NetWeaver Business Client (SAP NWBC) via business role
Business role Strategic Planner
(SAP_NBPR_STRATPLANNER-S)
Business rolemenu
Production→ SOP → Disaggregation→ Disaggregation:
Planning
2. On the initial screen, make the following entries:
Fieldname
Description User actionand values
Comment
Product group
00001B000100000001 Product group ID defined incentral master data BB in layer 2.
Plant 1000 Production Plant
Inactiveversion
Select thebutton.
Version 001 Check which version must beused
3. Choose Inactive version.
4. In the Product group members dialog box, select the materials.
5. In the Disaggregation dialog box, select Create sales plans and Disaggregate sales plan andchoose Enter .
6. If the Check proportions dialog box displays, choose Yes.
7. Save your entries.
Result
You have viewed the S&OP figures on product group level and created the sales plan on materiallevel based on the sales plan on product group level.
4.1.2 Create Rough-Cut Production Plan
Use
In this activity, you generate the rough cut production plan based on your sales forecast. For this youhave several options (see below).
Procedure
1. Access the transaction choosing one of the following navigation options:
Option 1: SAP Graphical User Interface (SAP GUI)
SAP menu Logistics Production SOP Disaggregation Break Down
PG Plan
Transactioncode
MC76
Option 2: SAP NetWeaver Business Client (SAP NWBC) via business role
Business role Strategic Planner
© SAP AG Page 11 of 25
7/29/2019 144_BPP_EN_US
http://slidepdf.com/reader/full/144bppenus 12/25
SAP Best Practices Logistics Planning (144): BPD
(SAP_NBPR_STRATPLANNER-S)
Business rolemenu
Production→ SOP → Disaggregation→ Disaggregation:
Planning
You are still in the transaction for Demand verification (see previous chapter) andcontinue without leaving it. If you have left the transaction run through step 1 - 5 of thisprocess before continuing with the next step.
2. From the menu, choose Edit → Create production plan → Synchronous to sales. This makes
production figures equal to sales at product group and material levels.
3. In standard SOP, additional strategies for generating production plants exist. These can beactivated from the following menu path:
Edit → Create production plan → <create production plan option>
a. Production quantities are the same as sales quantities in each period ("synchronous tosales")
b. Production quantities are such that target stock levels are reached
c. Production quantities are such that target days’ supplies are reached
d. Production quantities are such that the stock level at the end of each period is zero.
Result
You have created the production plan on material level based on the sales plan on product grouplevel.
4.1.3 Transfer Rough-Cut Production Plan to Inactive DemandManagement
UseIn this activity, you transfer the inactive version of the production plan from SOP to DemandManagement where the quantities are posted as planned independent requirements.
For several purposes you can post the production plan at first in an inactive version.
In our scenario we use inactive versions for the following purposes:
• Version 001 for simulation and long term procurement purposes (forecast)
described in this document
• Version 002: for supporting the annual budgeting process (see 173: SOP through Long
Term Planning Transfer to LIS/PIS/Capacity )
Procedure
1. Access the transaction choosing one of the following navigation options:
SAP menu Logistics Production SOP Planning For Product Group
Transfer Product Group to Planning
Transactioncode
MC75
© SAP AG Page 12 of 25
7/29/2019 144_BPP_EN_US
http://slidepdf.com/reader/full/144bppenus 13/25
SAP Best Practices Logistics Planning (144): BPD
Option 2: SAP NetWeaver Business Client (SAP NWBC) via business role
Business role Strategic Planner
(SAP_NBPR_STRATPLANNER-S)
Business rolemenu
Production→ SOP → Product Group → Transfer PG to Demand
Management
2. Make the following entries:
Field name Description User action and values Comment
Product group 00001B000100000001
Plant 1000 Production Plant
Version 001 Selectable fromdropdown.
Depends on versionused in scenario:Quarterly Plan - SalesQuantity Forecast withCO-PA (179)
Production planfor material or PGmember
Selected
From date <earliest date of change> Typically first day of current month
To date <earliest date of changePLUS 18 months>
Eighteen months in thefuture
Requirementstype
Leave blank
Version 01
Active Deselected
Make sure that you deselect Active on the initial screen to make sure it is inactive indemand management. To transfer a single material, use transaction MC74.
3. Choose Transfer now .
Result
The inactive version is transferred to demand management. To display the inactive version for a
single material in Demand Management, use transaction MD63 (or menu path Logistics→
Production→ Production Planning → Demand Management → Planned Independent Requirements
→ Display ).
4.2 Long Term Planning
In long-term planning, future demand programs are simulated within a planning run. This allows youto calculate capacity requirements, activity type requirement of the cost centers, and of therequirement of purchased parts.
© SAP AG Page 13 of 25
7/29/2019 144_BPP_EN_US
http://slidepdf.com/reader/full/144bppenus 14/25
SAP Best Practices Logistics Planning (144): BPD
The demand programs that can be simulated may include planned independent requirements and/or sales orders.
You can evaluate and optimize the simulation regarding material requirements planning, capacityplanning, order volumes, purchasing budget, cost center planning, and inventory controlling.Following the evaluation of the simulative planning results, you can replace the current demandprogram with the preferred version in long-term planning and can continue it there.
You can transfer the data for external procurement to the purchasing information system using aspecial report and evaluate it there.
The principle of long-term planning is to simulate different versions of the demand program. Thesimulation can take into account operative data (for example, master data, sales orders, purchaseorders, production orders).
The simulation can be used to optimize the demand program and the production and procurementdata regarding material requirements planning, capacity planning, order volumes, purchasingbudget, cost center planning, and inventory controlling.
Long-term planning can also be executed based on operative master data: BoMs, routings, workcenters, and material masters. This means you do not have to create any new operative data.
4.2.1 Create Long Term Planning Scenario
Use
For simulation purposes, you set up LTP-Planning scenarios that represent planning areas you canuse independently from each other.
In this activity, you create the LTP Planning Scenario.
If the LTP planning scenario already exists, use transaction MS32 to make changes.
Procedure
1. Access the transaction choosing one of the following navigation options:
SAP menu Logistics Production Production Planning Long-Term
Planning scenario Create
Transactioncode
MS31
Option 2: SAP NetWeaver Business Client (SAP NWBC) via business role
Business role Strategic Planner
(SAP_NBPR_STRATPLANNER-S)
Business role
menu
Production→ Production Planning → Long-Term Planning → Create
Planning Scenario
Always use scenario 001. If the scenario already exists, change the scenario according
to the steps described below. Choose Planning Scenario → Change or switch to change
mode. Choose Edit → Cancel Release to reset the released status to change the
existing values.
© SAP AG Page 14 of 25
7/29/2019 144_BPP_EN_US
http://slidepdf.com/reader/full/144bppenus 15/25
SAP Best Practices Logistics Planning (144): BPD
2. Make the following entries:
Field name Description User actionand values
Comment
Planning
scenario
001 <enter a new number and description>
Always use planning scenario 001. If thescenario already exists skip this processstep.
Long-term planning
Selected
3. Choose Enter .
4. Make the following entries:
Field name Description User action andvalues
Comment
From date <current date>
To date <current date PLUS18 months>
Eighteen months inthe future
Dep.reqmts for reorder point materials
Selected
Consider sales orders Selected
Include firm receipts Selected
Include firm purchaserequisitions
Selected
Include firm planned
orders
Selected
5. Choose Planned Independent Requirements.
6. In the dialog box, choose New entry .
7. Make the following entries:
Fieldname
Description User action and values Comment
Version 01 Inactive version from demandmanagement
From date <current date>
To date <current date PLUS 18
months>
Eighteen months in the future
8. Choose Confirm.
9. Choose Plants.
10. In the dialog box, choose New entry .
11. Make the following entries:
Field name Description User action and Comment
© SAP AG Page 15 of 25
7/29/2019 144_BPP_EN_US
http://slidepdf.com/reader/full/144bppenus 16/25
SAP Best Practices Logistics Planning (144): BPD
values
Planning plant
1000 You can repeat the steps for allplanning plants.
12. Choose Confirm.
13. Choose Release and Save.
Result
The LTP Planning scenario is created. Make a note of the Planning Scenario number here:
_________
4.2.1.1 Execute LTP MRP Run
Use
In this activity, you simulate the execution of the LTP MRP run.
Procedure1. Access the transaction choosing one of the following navigation options:
Option 1: SAP Graphical User Interface (SAP GUI)
SAP menu Logistics Production Production Planning Long-term Planning
Long-term planning Planning run Online
Transactioncode
MS01
2. On the Long-Term Planning Run screen, enter the following entries:
Field name Description User action andvalues
Comment
Planning Scenario
<from previousstep>
Plant 1000 Production Plant
Display material list
Selected
Scheduling 2 Lead time scheduling andcapacity planning
3. Choose Enter .
4. The system displays the message Please check input parameters.
5. Choose Enter .6. The system displays the message To start the planning run, press enter . Choose Enter .
© SAP AG Page 16 of 25
7/29/2019 144_BPP_EN_US
http://slidepdf.com/reader/full/144bppenus 17/25
SAP Best Practices Logistics Planning (144): BPD
Use transaction MS04 to check the planning results for planning scenario 001, materialFinished Good MTO (for example F1000-M1) in plant 1 (1000) or in the NWBC role
menu Production→ Production Planning → Long-Term Planning → Planning Scenario:
Stock/Reqmts List
Option 2: SAP NetWeaver Business Client (SAP NWBC) via Business Role
Business role Strategic Planner
(SAP_NBPR_STRATPLANNER-S)
Business rolemenu
Production→ Production Planning → Long-Term Planning → Long-
Term Planning: Total Planning
1. Select the planning scenario you created one step before, choose button Long-Term Planning and select Long-Term Planning Run Online from the menu.
2. On the Long-Term Planning Run screen, check the following parameters and press enter.
Field name Description User action andvalues
Comment
Planning Scenario
<from previousstep>
Plant 1000 Production Plant
Display material list
Selected
Scheduling 2 Lead time scheduling andcapacity planning
3. The system displays the message Please check input parameters.
4. Choose Enter .
5. The system displays the message To start the planning run, press enter . Choose Enter .
Use transaction MS04 to check the planning results for planning scenario 001, materialFinished Good MTO (for example F1000-M1) in plant 1 (1000) or in the NWBC role
menu Strategic Planning → Long-Term Planning (LTP) → Planning Scenario:
Stock/Reqmts List
Result
You have run the simulated LTP MRP.
4.2.1.2 Evaluate Capacity Requirements
Use
In this activity, you perform capacity planning for all relevant work centers you want to check.
After you run this activity, you can assess if the plan is acceptable.
© SAP AG Page 17 of 25
7/29/2019 144_BPP_EN_US
http://slidepdf.com/reader/full/144bppenus 18/25
SAP Best Practices Logistics Planning (144): BPD
Procedure
1. Access the transaction choosing one of the following navigation options:
SAP menu Logistics Production Production Planning ® Long-Term Planning
Evaluations Capacity requirements Work centers
Transactioncode CM38
2. Enter Profile YBLTP01 - LTP: Capacity requirements for AOP.
Use transaction SU01 or SU3 (SAPGUI) to predefine the profile in your user parameter
or in the role menu (NWBC) IT-Administration→ User Management → User
Maintenance (Role: SAP_NBPR_IT_ADMIN-S)
Parameter ID: CYX
Parameter Value: YBLTP01
3. Make the following entries
Field name Description User action and values Comment
Planning Scenario Long-Term Planning
From previous steps
Work Center Select a work center such as Assembly
Plant Plant 1 (1000)
4. From the menu, choose Settings → General and make / check the following entries:
Field name User action and values
Cumulation of requirements X
Hierarchy TOT_PLANT
Plant 1000
Entry type D
Start ( ) <Start of budget period>
Int.finish (mm/yyyy) <End of budget period>
5. Choose Standard Overview .
6. Repeat this activity for each work center of your planning model (which is used in the routings of the materials that have been planned).
Option 2: SAP NetWeaver Business Client (SAP NWBC) via Business Role
Business role Strategic Planner
(SAP_NBPR_STRATPLANNER-S)
Business rolemenu
Production→ Production Planning → Long-Term Planning →
Capacity Leveling L-T Planning
© SAP AG Page 18 of 25
7/29/2019 144_BPP_EN_US
http://slidepdf.com/reader/full/144bppenus 19/25
SAP Best Practices Logistics Planning (144): BPD
1. Select the planning scenario you created before.
2. On the Capacity Planning: Selection screen, choose More→ Planning → Profiles→ Overall
profile.
3. Select the profile YBLTP01 - LTP: Capacity requirements for AOP and choose Continue.
Use transaction SU01 or SU3 (SAPGUI) to predefine the profile in your user parameter
or in the role menu (NWBC) Administration → User Management → User Maintenance
(Role: SAP_NBPR_IT_ADMIN-S)
Parameter ID: CYX
Parameter Value: YBLTP01
4. Make the following entries
Field name Description User action and values Comment
Planning Scenario Long-Term Planning
From previous steps
Work Center Select a work center for example Assembly
Plant Plant 1 (1000)
5. From the menu, choose More…→ Settings → General and make / check the following entries:
Field name Description User action and values Comment
Cumulation of requirements X
Hierarchy TOT_PLANT
Plant 1000
Entry type D
Start ( ) <Start of budget period>
Int.finish (mm/yyyy) <End of budget period>
6. Choose Continue and Standard Overview .
7. Repeat this activity for each work center of your planning model (which is used in the routings of your planed materials).
Result
Capacity planning has been checked. If the plan is acceptable, you can execute the next step.
4.2.1.3Activate a planned independent requirements version
Use
Once you have evaluated and adjusted the simulative planning result, you can activate a plannedindependent requirements version in the planning scenario and, if necessary, you can give it a newversion number. As the validity period of the new version, the system either enters the periodrecorded when maintaining the simulative planned independent requirements version, or, if no
© SAP AG Page 19 of 25
7/29/2019 144_BPP_EN_US
http://slidepdf.com/reader/full/144bppenus 20/25
SAP Best Practices Logistics Planning (144): BPD
period has been maintained here, the system records the planning period of the planning scenario.Once you have activated the planned independent requirements version, it is valid for operativeplanning.
Procedure
1. Access the transaction choosing one of the following navigation options:
SAP menu Logistics Production Production planning Long-Term
Planning scenario > Change
Transactioncode
MS32
2. Make the following entries:
Field name Description User action and values Comment
Planning scenario Enter a new number and description.
3. Choose Activate ind.req.
4. Make the following entries:
Field name Description User action and values Comment
Version Selected
Target version 00 Active version
Test mode Deselected
Create list Selected
5. Choose Activate.
Option 2: SAP NetWeaver Business Client (SAP NWBC) via Business Role
Business role Strategic Planner
(SAP_NBPR_STRATPLANNER-S)
Business rolemenu
Production→ Production Planning → Long-Term Planning → Change
Planning Scenario
1. Make the following entries and choose Enter :
Field name Description User action and values Comment
Planning scenario Choose an existing scenario (001).
2. Choose Activate Independent Requirements.
3. Make the following entries:
Field name Description User action and values Comment
Version Selected
Target version 00 Active version
Test mode Deselected
Create list Selected
© SAP AG Page 20 of 25
7/29/2019 144_BPP_EN_US
http://slidepdf.com/reader/full/144bppenus 21/25
SAP Best Practices Logistics Planning (144): BPD
4. Choose Activate.
Result
You have activated your planned independent requirements version.
4.2.1.4 Copy to Active Demand Management
Use
Alternatively to the previous step you can copy the LTP Version 01 into an active version (such as00). In this activity, you create an active version in Demand Management by the following procedure.
The advantage of this step is the activation in batch mode.
Procedure
1. Access the transaction choosing one of the following navigation options:
SAP menu Logistics Production Production Planning Long-Term Planning
Planned indep.reqmts Copy version
Transactioncode
MS64
Option 2: SAP NetWeaver Business Client (SAP NWBC) via business role
Business role SAP_AIO_STRATEGICPLANNER-S(Strategic Planner-Professional User)
Business rolemenu
Production→ Production Planning → Demand Management ( DM) →
Create Simulation Version
2. Make the following entries:
Field name Description User action andvalues
Comment
Plant Enter all plants.
Material Leave blank
From date <first day of currentmonth>
To date <From date PLUS18 months>
Eighteen months in thefuture
Source version 01 Inactive version fromdemand management
Target version 00
Target version active Selected
No database changes(Simulation)
Deselected
3. Choose Execute.
Result
© SAP AG Page 21 of 25
7/29/2019 144_BPP_EN_US
http://slidepdf.com/reader/full/144bppenus 22/25
SAP Best Practices Logistics Planning (144): BPD
An active version is created in Demand Management. To display the active version for a single
material in Demand Management, use transaction MD63 (or menu path Logistics→ Production→
Production Planning → Demand Management → Planned Independent Requirements → Display ).
© SAP AG Page 22 of 25
7/29/2019 144_BPP_EN_US
http://slidepdf.com/reader/full/144bppenus 23/25
SAP Best Practices Logistics Planning (144): BPD
5 Follow-Up ProcessesYou have finished all activities that are part of the business process described in this document.
To accomplish subsequent activities of this business process, carry out the process steps described
in one or more of the following scenarios, using the master data from this document.
5.1 Operational Production Planning and Control
Use
In this activity, you may run the different production scenarios.
Procedure
To execute this activity, run the following scenarios
• Make-to-Stock Production - Discrete Industry (145)
• Make-to-Stock Production - Process Industry (146)
• Make-to-Order Production with Variant Configuration (147)
• Make-to-Order Production w/o Variant Configuration (148)
• Repetitive Manufacturing (149)
.
© SAP AG Page 23 of 25
7/29/2019 144_BPP_EN_US
http://slidepdf.com/reader/full/144bppenus 24/25
SAP Best Practices Logistics Planning (144): BPD
6 Appendix
6.1 Reversal of Process Steps
In the following section, you can find the most common reversal steps that you can take to reversesome of the activities described in this document,
Create Long Term Planning Scenario
Transaction code( SAP GUI)
MS31
Reversal: Change Planning scenario
Transaction code( SAP GUI)
MC75
Business role SAP_BPR_STRATEGICPLANNER-S
Business role menu Strategic Planning → Long-Term Planning (LTP) → Change
Planning Scenario
Comment You can change the planning scenario
6.2 SAP ERP Reports
Use
The table below lists the most frequently used reports that help you to obtain additional informationon this business process.
You can find detailed descriptions of the individual reports in the following BPDdocuments that provide a comprehensive compilation of all important reports:
• Financial Accounting: SAP ERP Reports for Accounting (221)
• Logistics Processes: SAP ERP Reports for Logistics (222)
The descriptions of some reports that are an indispensable part of the process flow may be locateddirectly in the section where they belong.
Reports
Report title Transactioncode (SAPGUI)
BusinessRole(NWBC)
Business Role Menu(NWBC) Comment
Long-TermCapacityPlanning
CM38 StrategicPlanner
Production→ Production
Planning → Long-Term
Planning → Capacity
Leveling L-T Planning
The capacityevaluation isdisplayed.
Change Plan MC82 Strategic Production→SOP → Display of
© SAP AG Page 24 of 25
7/29/2019 144_BPP_EN_US
http://slidepdf.com/reader/full/144bppenus 25/25
SAP Best Practices Logistics Planning (144): BPD
Planner Change Plan for Product Group
planningversion.
Evaluation of ProductGroupPlanning
MD47 ProductionPlanner
Production→
Evaluations→ Reports→
Product Group Planning
Evaluation
Planningsituation isdisplayed.
Long-TermPlanning:MRP-list
MS05 StrategicPlanner
Production→ Production
Planning → Long-Term
Planning → Long-Term
Planning: Display MRP List
Simulation of MRP-list