GAIL (INDIA) LIMITED 16, BHIKAIJI CAMA PLACE, R.K.PURAM, NEW DELHI-110066 Dated : 25.02.2009 Sub: Issue of Corrigendum No.1 & Reply to Bidders Queries Ref: Bidding Document No. 8000000820 for Hiring of PMC Services for Focus Energy Project Dear Sirs, Please find enclosed herewith (i) Corrigendum No.1 alongwith attachment for Revised Milestone List for Payment and (ii) Clarifications to the queries raised by bidders during pre-bid meeting held on 18.02.2009. The Corrigendum No.1 and Clarifications to the bidder’s queries shall form an integral part of the above bidding document No.8000000820 and shall be submitted duly signed along with the original tender document through e- Tendering. Thanking you. Yours faithfully, For & behalf of GAIL (India) Limited J P SINGH Sr.Manager (C&P) Encl: As above
Transcript

GAIL (INDIA) LIMITED 16, BHIKAIJI CAMA PLACE,

R.K.PURAM, NEW DELHI-110066 Dated : 25.02.2009 Sub: Issue of Corrigendum No.1 & Reply to Bidders Queries Ref: Bidding Document No. 8000000820 for Hiring of PMC Services for

Focus Energy Project

Dear Sirs, Please find enclosed herewith (i) Corrigendum No.1 alongwith attachment for Revised Milestone List for Payment and (ii) Clarifications to the queries raised by bidders during pre-bid meeting held on 18.02.2009. The Corrigendum No.1 and Clarifications to the bidder’s queries shall form an integral part of the above bidding document No.8000000820 and shall be submitted duly signed along with the original tender document through e-Tendering. Thanking you.

Yours faithfully, For & behalf of GAIL (India) Limited

J P SINGH Sr.Manager (C&P)

Encl: As above

CORRIGENDUM No. 1 DATED 25.02.2009 BID DOCUMENT NO. 8000000820 FOR HIRING OF PMC SERVICES FOR FOCUS ENERGY PROJECT

Page 1 of 1

Sr No.

Clause No. of Bid document Page No.

Description / amendment

1 Section V, Part-A: Scope of Consultants Work 50-90 The scope of work towards Procurement of Line pipes, Coating work of Line pipes and Procurement of Metering Skid has been deleted from PMC’s scope of work. PMC to quote accordingly. The revised milestone payment considering the scope of work is enclosed as per Attachment-A

2 Clause 12.3 of ITB: Bid Prices 14 The clause is modified as under:

“12.3 Prices quoted should be inclusive of fees towards complete scope of work, all taxes, duties, levies, license fees and also payment towards third party charges towards surveys etc. but excluding service tax + education cess thereon. However, applicable rate of statutory taxes & duties must be indicated separately.”

ATTACHMENT-A

Sl. Description % Payment % Cumulative payment

A Engineering 101 Finalisation of Design Basis along with Submission of Final Document

& review of DFR1.5 1.5

2 Finalisation of Process P&IDs along with Submission of Final Document

2 3.5

3 Completion of HAZOP Study along with Submission of Final P&IDs & HAZOP Closure report

0.5 4

4 Finalization of Tender document for Geotechnical, Hydrological, Topological Survey, EIA & EMP .

0.5 4.5

5 Finalisation of Tender Document for Mainline Valves 0.5 56 Finalisation of Tender Document for Scrapper Traps, Flow Tee and

Insulating joint.0.5 5.5

7 Finalisation of Tender Document for Pipe Laying & Composite works 2 7.5

8 Finalisation of Tender Document for Power Source 0.5 89 Finalisation of Tender Document for SCADA System 0.5 8.510 Finalisation of Tender Document for Telecom System 0.5 911 Finalization of Material Take-off (MTO) for Assorted pipes. 0.5 9.512 Finalization of Material Take-off (MTO) for Fittings, Flanges, Valves. 0.5 10

B Planning & Scheduleing 1.0013 Finalisation of Level 3 Internal Schedule 0 15 10 15

Revised Milestone for Release of Payment

Tender No.8000000820 for Hiring of PMC Services for Focus Energy Project

13 Finalisation of Level -3 Internal Schedule. 0.15 10.1514 Finalisation and Submission of List of Milestones for Internal

Monitoring & Ministry Monitoring0.15 10.3

15 Finalisation of Level-3 Ministry Schedule as per MMC requirement 0.15 10.45

16 Finalisation of Project Execution Plan/ Methodology 0.25 10.717 Finalisation of WBS structure 0.15 10.8518 Submission of Organogram for Project Office & Construction site along

with deployment of manpower0.15 11

C Tendering 719 Issue & Publication of NIT for Geotechnical, Hydrological,Topological

survey, EIA & EMP. 0.25 11.25

20 Issue & Publication of NIT for Procurement of Mainline Valves 0.25 11.521 Issue & Publication of NIT for Procurement of Scrapper Traps, Flow

Tee and Insulating joint.0.25 11.75

22 Issue & Publication of NIT for Pipe Laying & Composite works 0.5 12.2523 Issue & Publication of NIT for Procurement of Power Source 0.25 12.524 Issue & Publication of NIT for SCADA System 0.25 12.7525 Issue & Publication of NIT for Telecom System 0.25 1326 Issue & Publication of NIT for Procurement of Assorted Pipes 0.25 13.2527 Issue & Publication of NIT for Fittings, Flanges, Valves 0.25 13.528 Submission of PBO recommendations and approval for Geotechnical,

Hydrologcal, Topological Surveys, EIA & EMP.0.5 14

29 Submission of PBO recommendations and approval for Procurement of Mainline Valves

0.5 14.5

30 Submission of PBO recommendations and approval for Scrapper Traps, Flow Tee and Insulating joint

0.5 15

31 Submission of PBO recommendations and approval for Pipe Laying & Composite Works

0.5 15.5

Page 1 of 4

ATTACHMENT-A

Sl. Description % Payment % Cumulative payment

32 Submission of PBO recommendations and approval for Procurement of Power Source

0.5 16

33 Submission of PBO recommendations and approval for SCADA System

0.5 16.5

34 Submission of PBO recommendations and approval for Telecom System

0.5 17

35 Submission of PBO recommendations and approval for Assorted pipes 0.5 17.5

36 Submission of PBO recommendations and approval for Fittings, Flanges, Valves

0.5 18

D Ordering 937 Submission of Award/ Order Placement recommendations and

approval for Geotechnical, Hydrological, Topological survey, EIA & EMP.

0.25 18.25

38 Submission of Award/ Order Placement recommendations and approval for Procurement of Mainline Valves

1 19.25

39 Submission of Award/ Order Placement recommendations and approval for Procurement of Scrapper Traps, Flow Tee and Insulating joint

0.75 20

40 Submission of Award/ Order Placement recommendations andapproval for Pipe Laying & Composite Works

1.5 21.5

41 Submission of Award/ Order Placement recommendations andapproval for Power source

0.5 22

42 Submission of Award/ Order Placement recommendations and 0.5 22.5approval for SCADA System

43 Submission of Award/ Order Placement recommendations andapproval for Telecom System

0.5 23

44 Submission of Award/ Order Placement recommendations andapproval for Assorted Pipes

0.5 23.5

45 Submission of Award/ Order Placement recommendations andapproval for Fittings, Flanges, Valves etc

0.75 24.25

46 Submission of Draft LOA, Loading of PR/SR in SAP & placement of Order for Geotechnical, Hydrological, Topological survey, EIA & EMP.

0.5 24.75

47 Submission of Draft LOA, Loading of PR/ SR in SAP & placement of Order for Procurement of Mainline Valves

0.25 25

48 Submission of Draft LOA, Loading of PR/ SR in SAP & placement of Order for Procurement of Scrapper Traps, Flow Tee and Insulating joint

0.25 25.25

49 Submission of Draft LOA, Loading of PR/ SR in SAP & placement ofOrder for Pipe Laying & Composite Works

0.5 25.75

50 Submission of Draft LOA, Loading of PR/ SR in SAP & placement ofOrder for Power source

0.25 26

51 Submission of Draft LOA, Loading of PR/ SR in SAP & placement ofOrder for SCADA System

0.25 26.25

52 Submission of Draft LOA, Loading of PR/ SR in SAP & placement ofOrder for Telecom System

0.25 26.5

53 Submission of Draft LOA, Loading of PR/ SR in SAP & placement ofOrder for Assorted Pipes

0.25 26.75

54 Submission of Draft LOA, Loading of PR/ SR in SAP & placement ofOrder for Fittings, Flanges, Valves

0.25 27

E Inspection, Expediting, Manufacturing & Delivery 1855 Approval of Drawings / Documents for commencement of

manufacturing for Line pipes & coating0.75 27.75

Page 2 of 4

ATTACHMENT-A

Sl. Description % Payment % Cumulative payment

56 Approval of Drawings / Documents for commencement ofmanufacturing for Mainline Valves

0.5 28.25

57 Approval of Drawings / Documents for commencement ofmanufacturing for Scrapper Traps, Flow Tee & Insulating joint

0.5 28.75

58 Approval of Drawings / Documents for Pipe laying & Composite works 1.5 30.25

59 Approval of Drawings / Documents for commencement ofmanufacturing for Power Source.

0.5 30.75

60 Approval of Drawings / Documents related to SCADA System forcommencement of manufacturing.

0.5 31.25

61 Approval of Drawings / Documents related to Telecom System forcommencement of manufacturing.

0.5 31.75

62 Approval of Drawings / Documents for commencement ofmanufacturing for Metering Systems

0.75 32.5

63 Approval of Drawings / Documents for commencement ofmanufacturing for Assorted Pipes

0.5 33

64 Approval of Drawings / Documents for commencement ofmanufacturing for Fittings, Flanges, Valves

0.5 33.5

65 Finalization of Geotechnical, Hydrological, Topological survey , EIA &EMP survey Reports

0.5 34

66 25 % Delivery at designated dumpsite / construction site store forcoated Pipes

0.75 34.75

67 50 % Delivery at designated dumpsite / construction site store forcoated Pipes

0.75 35.5

68 75 % Delivery at designated dumpsite / construction site store forcoated Pipes

0.75 36.25

69 100 % Delivery at designated dumpsite / construction site store forcoated Pipes

0.75 37

70 Delivery complete at designated dumpsite / construction site store forMainline Valves

1 38

71 Delivery complete at designated dumpsite / construction site storeScrapper Traps, Flow Tee & Insulating joint

1 39

72 Delivery, installation & commissioning complete for Power Source. 1 40

73 Delivery, installation & commissioning complete for SCADA System 1 41

74 Delivery, installation & commissioning complete for Telecom System 1 42

75 Delivery complete at designated construction site store for MeteringPackage

1 43

76 Delivery complete at designated construction site store for AssortedPipes

1 44

77 Delivery complete at designated construction site store for Fittings,Flanges, Valves

1 45

F Construction & Commissioning 5078 Complete Mobilisation of Consultant Manpower at Site as per

requirement & Submission of Organogram 2.5 47.5

79 Cumulative Construction Progress - 10 % 2.5 5080 Cumulative Construction Progress - 25 % 2.5 52.581 Cumulative Construction Progress - 40 % 2.5 5582 Cumulative Construction Progress - 50 % 2.5 57.583 Cumulative Construction Progress - 75 % 2.5 6084 Cumulative Construction Progress - 85 % 3 6385 Cumulative Construction Progress - 100 % 4 67

Page 3 of 4

ATTACHMENT-A

Sl. Description % Payment % Cumulative payment

86 Submission of Mechanical Completion certificate 4 7187 Commissioning & Gas In for Pipeline System and submission of

Commissioning certificate4 75

88 Commissioning & Gas In for all Stations & Terminals 4 7989 Accurate Cost Estimate for all Purchase orders and Work orders 2 81

90 Submission of all PO Closure statements 2 8391 Submission of all WO closure statements 2 8592 Acceptance of all PO Closure Statements prepared by Consultant 2 87

93 Acceptance of all WO Closure Statements prepared by Consultant 2 89

94 Submission of Performance Cards of all vendors 1 9095 Submission of Performance Cards of all contractors 1 9196 Handover of list of surplus and Non generation of Surplus material

beyond 3 %.2 93

97 Handover of complete Material Reconciliation in SAP to GAIL 2 95G Project-Close out 598 Project Closeout and submission of project Closure Report 5 100

Total 100.00

Page 4 of 4

CLARIFICATIONS TO THE QUERIES RAISED BY BIDDERS BID DOCUMENT NO. 8000000820 FOR PMC SERVICES FOR FOCUS ENERGY PIPELINE PROJECT

Page 1 of 6

Sr No

Section Detail Clause/Description Bidder’s Query GAIL Reply / Clarifications

1 Section-V Part-A Scope of work

- The qualification of exact scope depends upon the recommendations of the DFR. The same may kindly be provided about a week before the bid due date.

The brief project feasibility report is enclosed as Attachment-I

2 General - Please furnish the gas composition and phase (single phase/multi phase), This is required to decide the software to be deployed for Hydraulics/Simulation.

Gas composition/quality is indicated as per Attachment-II.

3 Section-V Part-A Scope of work

- There is no mention about Topographic survey & drawings for Pipeline route (survey route maps, alignment sheets, crossing drawings etc.) Kindly clarify the scope split (Bidders scope / Client’s scope) for the same..

Route Map/alignment sheets/PDI/ crossing details/soil resistivity reports are available with GAIL.

4 Section-V Part-A Scope of work

- The tender document mentions about Admin. Bldg., Control room & sub station buildings but the same are not mentioned in the facilities envisaged at dispatch & receiving terminal. Please clarify.

Control Room building with electrical, AC provisions at dispatch & receiving terminal.

5 Section-V Part-A Scope of work

- Please clarify the requirement of control building at intermediate installations.

Only Security room is envisaged in SV stations

6 Section-V Part-A Scope of work

- Please confirm whether master control room will be planned blast proof or non blast proof.

Non-blast proof

7 Section-V Part-A Scope of work

- Under Telecom scope, it is presumed that the requirement of GAIL’s Telecom business is limited to providing additional fibers for the OFC

OFC based telecom system and SCADA RTU has been proposed

8 Section-V Part-A Scope of work

- Kindly clarify whether suitable tap – off point already exists at Langatala or Hot tapping shall be required.

Tap-off point will be made available.

9 Section-V Part-A Scope of work

- Kindly confirm the power source for remote locations – Grid backed up by CCVT/ TEG Solar power?

Grid or solar power, as the case may be.

10 Section-V Part-B Payment Terms

- It is presumed that all payments to Third Party such as Surveys, Clearing, forwarding, Transportation of Material etc. shall be made by GAIL. Please confirm.

Yes. GAIL will reimburse the cost incurred by the PMC on Clearing, Forwarding, Transportation of material etc.

CLARIFICATIONS TO THE QUERIES RAISED BY BIDDERS BID DOCUMENT NO. 8000000820 FOR PMC SERVICES FOR FOCUS ENERGY PIPELINE PROJECT

Page 2 of 6

Sr No

Section Detail Clause/Description Bidder’s Query GAIL Reply / Clarifications

11 Section-V Part-A Scope of work

- It is requested that Lodging & realization of Insurance claims is deleted from PMC Scope.

Tender conditions prevails.

12 Section-V part-5 Time schedule

- The job involves procurement of Line Pipes, Coating, Metering & Pressure Reduction, Control Valves, SCADA, Telecom and Construction of Buildings, Pipeline Laying etc. for the activities, the Completion period of 12 months upto commissioning + 3 months for Project Close out appears to be too tight. It is suggested that the increase of completion time to 18 months upto commissioning + 3 months for Project Close out may be reviewed.

Tender conditions prevails

13 Section-V Part-A Scope of work

- It is presumed that all statutory approvals will be obtained by GAIL. The role of PMC shall be limited to technical assistance (drawings/documents) only.

Bidder’s understanding is in order.

14 General Conditions of the

Contract

Limitation of Liability It is presumed that PMC, s liabilities on all accounts (including on account of material reconciliation, accuracy of cost estimates, delays etc.) will be limited to 10% of Contract Value. Please confirm.

The limitation of liability is exclusive of the other terms and conditions of the tender document.

15 Section-V Part-A Scope of work

- It is presumed that soft and hard copies of As-built drawings / documents of existing facilities shall be provided to PMC soon after award of work. Please confirm.

Facilities at receiving terminal will be built up. Dispatch terminal drawing (Hard Copy) will be provided.

16 IFB Page 6 of 119, clause No. 3.3.2 second line: Bidder shall furnish necessary

documentary evidence i.e. attested copy.

Whether self attested copies are acceptable. Kindly clarify.

The attestation is required from notary public..

17 ITB Page 14 of 119, Clause No. 12.3, Price quoted

shall be inclusive of fees towards complete scope of

work all taxes, duties, levies, license fees,

service tax.

Page 20 of 119, Clause No

Kindly clarify whether price to be quoted inclusive or exclusive of Service tax and education cess. This clause contradicts with the above clause. Kindly clarify

Bidder to quote prices as per SOR. Please refer enclosed corrigendum No. 1

CLARIFICATIONS TO THE QUERIES RAISED BY BIDDERS BID DOCUMENT NO. 8000000820 FOR PMC SERVICES FOR FOCUS ENERGY PIPELINE PROJECT

Page 3 of 6

Sr No

Section Detail Clause/Description Bidder’s Query GAIL Reply / Clarifications

32.0 Evaluation and Comparison of Bids

18 ITB Page No 15 of 119, Quoted price shall also be

inclusive of all costs towards carrying out any

surveys.

Please clarify apart from Soil Investigation, Geotechnical and Hydrological Survey any other survey is considered for the project.

No

19 Section-V Part-A Scope of work

Page 77 of 199, ix, Approval from GAIL.

Time frame for approval from GAIL shall be specified in order to adhere to time milestone.

No time frame can be fixed for the inter-connecting activities which are to be processed based on PMC recommendations. However, the endeavor will be to process the case at the earliest.

20 Section-V Part-A Scope of work

Page 78 of 119, clause No. 14.0, Key Result Area.

All KRA recoveries should be reviewed at the end to the project and refunded if the project is completed within time As long as the total project is completed within contractual completion period, the recoveries made under KRAs should be refunded. Hence the clause shall be modified as given below: “in case project is completed within the contractual completion schedule i.e. 15 months including 3 months period for project close out time from date of FOI, retention / recoveries made against key result area if any shall be reimbursed to the consultant and in case final time extension is granted without PRS, no recovery shall be made.”

Tender Conditions prevails.

21 SOR No. 3 Demobilization & remobilization charges and

Compensation for Suspension of services.

Demobilization & Remobilization charges and Suspension charges shall be fixed by GAIL.

Tender Conditions prevails. Bidder to quote charges as per SOR.

22 Section-V Part-A Scope of work

Page 54 of 119, Clause 1.3.1, iii) The pipeline will be protected b 3 Layer PE

external, Internal Epoxy Coating.

Internal Epoxy Coating is not required for 10” pipeline. Please clarify.

Internal coating is required.

CLARIFICATIONS TO THE QUERIES RAISED BY BIDDERS BID DOCUMENT NO. 8000000820 FOR PMC SERVICES FOR FOCUS ENERGY PIPELINE PROJECT

Page 4 of 6

Sr No

Section Detail Clause/Description Bidder’s Query GAIL Reply / Clarifications

23 Section-V Part-A Scope of work

Page 55 of 119, Clause 2.0, i) General Scope

Please clarify, whether DFR is available with GAIL. Yes, a brief feasibility report is available with GAIL.

24 Section-V Part-A Scope of work

Page 59 of 119, Clause 3.13, Safety, iv) PMC to carry out EIA and EMP

EIA/ EMP is in the scope of PMC, if yes it is not reflected in Milestone Payment terms. Kindly clarify

Milestone payment revised accordingly.

25 Section II Instructions to

Bidders (ITB) & its Addendum.

Clause 38.1 pages 21 of 119: CPBG & provision at

Page 92 of 119

The validity of PBG is mentioned as 3 months beyond the completion of 12 months after the contractual completion period whereas the schedule completion time is 15 months. GAIL may please clarity the understanding.

The validity of PBG as per tendered condition is 30 months from the date of award of work.

26 Under Attachment III- Agreed terms and Conditions page 112 of 119

Sl. No. 11. We would request the following to be

added in the last line

“if the delay is solely attributable to the consultant: Tender Conditions prevails

27 Section-V Part-A Scope of work

Clause 3.13 (iv), page 59 of 119

“PMC to carryout Environment Impact Assessment (EIA) and prepare Environment Management Plan (EMP) as per prevailing protection Act for obtaining statutory Clearance”. In our opinion, the above is required during FR preparation and not during project execution. Only measures for EMP to be implemented during the construction period by PMC. Moreover obtaining statutory clearances is not in PMC scope. GAIL may please clarify.

EIA/EMP shall be in the scope of PMC

28 Section-V Part-A Scope of work

Clause 4.1 XV on page 60 of 119

As per this Clause clearing and forwarding charges will be reimbursed to PMC by GAIL. Under clause 11 (V) on page 76 of 119 payment of custom duty amount and transportation charges of impo0rted material is excluded from the scope of PMC. Similarly clearing and forwarding charges as per above clause should also be included under exclusions.

Tender Conditions prevails

29 Section-V Part-A Scope of work

Clause 12.3 page 77/119 – under Preamble to price

schedule

GAIL may please allow bidder to claim reimbursement for any re-working/re-tendering/re-designing due to Owner’s change.

Tender Conditions prevails

CLARIFICATIONS TO THE QUERIES RAISED BY BIDDERS BID DOCUMENT NO. 8000000820 FOR PMC SERVICES FOR FOCUS ENERGY PIPELINE PROJECT

Page 5 of 6

Sr No

Section Detail Clause/Description Bidder’s Query GAIL Reply / Clarifications

30 ITB Clause 3.8.1 page no 30 of 119

Regarding Services tax this clause says consultant shall pay any and all taxes including service tax duties whereas in SOR price have been asked for inclusive of all taxes except Service tax. GAIL may please clarify.

Bidder to quote prices as per SOR. Please refer enclosed corrigendum No. 1

31 Section III General

Conditions of Contract

Clause 3.15.3 The amount of liability will be limited to 10% of Contract Value - Please confirm that the above cap will include all liabilities such as - clause 14 of Section V - Key Result Areas and

Recoveries - clause 3.12.1 of Section III – PRS - clause 4.1 (xvii) of Scope of Work – Surplus

Generation - clause 4.5 (v) of Scope of Work - deviation in Cost

Estimates

The limitation of liability is exclusive of the other terms and conditions of the tender document.

32 Section V Part A Scope of

Consultant's Services

Clause 2.0 vi) GAIL to clarify whether the proposed Pipeline route crosses any Railway line, Water body or State / National Highways

The details of crossing on proposed pipeline route is as under: 1) 2 Nos. of Canal Crossing of Width

26 Mtr & 8.5 Mtr 2) 6 Nos. of Asphalted Roads of avg.

Width 3.5 Mtr 3) A portion of pipeline is passing

through sand dune 33 Clause 3.11 GAIL to confirm that actual cost of carrying out the Soil

Investigation, Geo-Technical, Hydrological Surveys will be borne by GAIL.(Under article 3.23 of Section II it is mentioned that CONSULTANT shall be responsible for carrying out any surveys and acquisition of data from necessary sources.)

Bidder’s understanding is in order.

34 Clause 4.1 xv) GAIL to clarify whether the contracts for Customs clearance, Transportation will be awarded by GAIL on the recommendations of the PMC or whether PMC is expected to award these contracts by himself. In the first case the payments to Contractor will be directly made by GAIL.

PMC shall be responsible for the work. GAIL will reimburse the cost for such activities.

35 Clause 5.2 viii Please clarify the scope of Stores infrastructure facilities. Whether these will be arranged by GAIL or whether PMC is expected to provide for these facilities and get reimbursement from GAIL later.

The bidder’s understanding is in order.

CLARIFICATIONS TO THE QUERIES RAISED BY BIDDERS BID DOCUMENT NO. 8000000820 FOR PMC SERVICES FOR FOCUS ENERGY PIPELINE PROJECT

Page 6 of 6

Sr No

Section Detail Clause/Description Bidder’s Query GAIL Reply / Clarifications

36 Clause 9.6.4 By Expatriate Project Manager do you mean "Western Expatriate" or Non-Resident Indian will be accepted in case of foreign PMC bidders?

The Project Manager should be Expatriate.

37 Clause 12.3 There is unlimited scope for Re-working/Re-engineering/Re-designing/Retendering. Can GAIL put a limit on PMC scope in respect of these activities ?

Tender Conditions prevail.

38 Clause 13.0 x Any activity required to be carried out for completion of the project though not specifically mentioned in the tender document shall be carried out at no extra cost to GAIL - The PMC scope of work is required to be specifically spelt out in the tender. and can not be unlimited.

Tender Conditions prevail.

39 Clause 13.0 xvi What is expected to be role of one senior level PMC person to be stationed at GAIL Project office in Delhi ?

The stationed person at Delhi is required for coordination with GAIL.

40 Section VI Price Schedule

Clause (i) Please clarify regarding the Camp facilities, Office facilities at construction site for PMC personnel etc

Camp facility shall be provided by GAIL.

                                                                                    Tech. study report for M/s Focus Energy case  

File Ref. GS/1(27)/07‐08   PD‐Pipeline group 

 

In‐house study report for providing pipeline connectivity for transportation of gas available from Focus energy consortium to RRVUNL, Ramgarh 

INTRODUCTION – 

In house study has been carried out on the request of Gas Marketing group to develop a scheme for transportation through pipeline system. The gas to be available at Langtala fields of M/s Focus Energy consortium in Jaisalmer area of Rajasthan with Power Plant of RRUVNL at GAIL  terminal at Ramgarh in Jaiselmer area.  

Recii survey of the proposed route is carried out by S&RL dept. Their report is also enclosed in the last. Three different alternative route were surveyed by the agency M/s S M Associates, Navi Mumbai engaged by S&LR group, as below: 

Sl no. 

Description  Alt.1 Alt.2  Alt.3 

1  Length (KM)  90  87  85 2  Inaccessible pipeline 

route length 18  26  40 

3  Accessible pipeline route length 

72  61  45 

4  Terrain Flat  72  69  40 5  Terrain undulating  18  18  45 6  Soil condition shifting 

sand dunes 25  25  50 

7  Soil condition sandy  65  62  35  

Alternative 1 route was suggested by S&LR group for considerations because of the availability of approach for constructions and maintenance of pipeline in desert. 

In house study has been carried out based on the input provided by Gas Marketing group on customer data like volume, pressure etc. and other details provided in survey report. 

BASIS OF STUDY 

1. Total gas available from the fields: 0.95 MMSCMD 

2. Volume considered in the study : 1.20 MMSCMD 

(as per Marketing group, the daily nominated qty. can be 1.20 times the DCQ) 

ATTACHMENT-I

                                                                                    Tech. study report for M/s Focus Energy case  

File Ref. GS/1(27)/07‐08   PD‐Pipeline group 

 

3. Pressure available at source: 58 Kg/cm^2g 

4. Temperature of gas available at source: Ambient temperature. 

5. Heating value of gas: 6000 Kcal/SCM 

6. Pressure of gas required by RRVUNL: 27 KG/cm^2g(min.) 

 

7. Starting point of pipeline ‐ 

Gas shall be delivered by the Seller to Gail at the delivery point, which shall be the outlet flange of seller’s facilities located at the onshore gas Well identified as SGL‐[1/2] which  

shall be the point at which the seller’s facilities shall be interconnected to gas off take and transportation facilities of Gail. 

 

8. End point of pipeline‐ 

Pipeline shall be terminated at the Gail’s terminal of Power Plant of M/s RRUVNL at Ramgarh. Gail has existing terminal at Power Plant for gas supply to RRUVNL; gas is being sourced from OIL India Ltd. and ONGC.  

The proposed terminal shall be built near to the existing terminal. Sufficient land is available at Power Plant. Utilities like power, air and control room building etc. will be shared and if required control room building may be extended for accommodating panels for SCADA and electrical etc. 

9. Pipeline length: 90 KM. (as a alternative I, suggested by S&LR group in survey report) 

10. Size of new pipeline: 10 Ø (Hydraulics copy enclosed) 

Facilities at starting point or delivery point 

Dispatch terminal consisting of‐ 

• Pig launcher 

• Fire fighting facilities 

ATTACHMENT-I

                                                                                    Tech. study report for M/s Focus Energy case  

File Ref. GS/1(27)/07‐08   PD‐Pipeline group 

• Metering Skid consisting of Filters, PSV, PCV, SDV, Ultrasonic meters with Flow Computers, FCV, Gas Chromatograph etc. 

• Control room building with Electricals, AC etc. 

• Provision of Power from Grid & Backup Power 

Note‐ Meter of Focus Energy consortium is excluded, meter proposed as above will be the check meter for Gail. 

 

 

Facilities at Receiving terminal at RRVUNL 

• Pig Receiver 

• Fire fighting facilities 

• Metering Skid consisting of Filters, PSV, PCV, SDV, Ultrasonic meters with Flow Computers, FCV, etc. 

• Extension of control room building if required. 

• Provision of power from RRUVNL. 

Note‐ Gas chromatograph is not proposed at receiving terminal since gas being received from single source, i.e, Focus Energy.               

 Sectionalizing Valves 

Three number of SV stations have been proposed on the route, however, exact location of these SVs will be finalized during detail engineering stage. 

Telecom/SCADA 

OFC based telecom system and SCADA  RTU have been proposed. Cost has been built up in estimates accordingly. 

Crossing details 

Sl no 

Type of crossing 

Chainge  Width  Description 

1  Open cut  0.48  20  Langtala Village road 

ATTACHMENT-I

                                                                                    Tech. study report for M/s Focus Energy case  

File Ref. GS/1(27)/07‐08   PD‐Pipeline group 

2  Open cut  18.00  20  Shahagad road 3  Open cut  43.87  30  Austar Jaiselmer road 4  Open cut  52.37  30  Distributory crossing 5  Open cut  59.20  20  Bandah – Ranatur road 6  Boring  73.83  60  Indra Gandhi main Canal 7  Open cut  74.07  20  Ramgarh – Bandha road  

Other facilities 

One number 10Ø spare tap‐off shall be provided at upstream of RRVUNL terminal for taking the gas to Jodhpur and other reasons in future. 

Completion Schedule: 12 months from date of approval. 

 

Project cost: Rs 99.16 Crores (detailed sheet enclosed) 

Operating cost‐ Rs. 3.28 Crores/year 

Basis of operating cost: 

• Gail man power: 3 nos. @ Rs 16lakhs/annum 

• Plant and Administration: 100% of man power cost 

• Repair and maintenance: 1% of pipeline cost 

• Security: 3 nos. @ Rs. 2.4 lakhs/annum 

• Power: 60 KWH @ Rs.5/KWH 

• Line pack: 0.22MMSCM 

Transport tariff 

Fixed monthly transport tariff have been calculated by Pricing group as Rs. 21, Rs. 276, 149/‐ for a period of 12 years from start date. The tariff has been calculated with opex as mentioned above and following financial parameters: 

• Gas price: $5/MMBtu with NCV of 7999 Kcal/SCM 

• Economic life: 12 years 

ATTACHMENT-I

                                                                                    Tech. study report for M/s Focus Energy case  

File Ref. GS/1(27)/07‐08   PD‐Pipeline group 

• Debit‐Equity ratio: 0‐100% 

• Revenue exclamation: 0% 

• Working days: 335 

• Volume build up: 1st year‐ 0.20 MMSCMD 

                                2nd year onwards‐ 0.95 MMSCMD 

• Unaccounted gas: 0.30% 

• Exchange rate: USD1= INR 43.5 

Note‐ since project cost falls under Rs. 100 Crores category doesn’t call for Financial Appraisal and Sensitivity Analysis. 

 

Way Forward 

1 Gas Mtkg. gp to sign agreement with upstream customer i.e. M/s Focus Energy Consortium for sourcing of gas. 

2 Gas Mtkg. gp also to sign the agreement with downstream customer i.e. M/s RRVUNL for gas sales and transportations. 

3 Investment Committee meeting to be arranged for their recommendation to c a for approval. 

4 PAC to be apprised for their recommendation to GAIL Board for approval 

 

 

5 Board agenda to be put before GAIL Board for their approval 

6 Project group to be conveyed the approval of Board for execution. 

 

 

 

 

ATTACHMENT-I

                                                                                    Tech. study report for M/s Focus Energy case  

File Ref. GS/1(27)/07‐08   PD‐Pipeline group 

 

ATTACHMENT-I

ATTACHMENT-II


Recommended