+ All Categories
Home > Documents > 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

16.12.12 - CVA Rotunda Specifications Div 1 thru 16

Date post: 22-Feb-2022
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
43
PROJECT MANUAL ROTUNDA ROOF REPLACEMENT CENTER FOR THE VISUAL ARTS BUILDING #030 ILLINOIS STATE UNIVERSITY 401 SOUTH SCHOOL STREET NORMAL, MCLEAN COUNTY, ILLINOIS 61761 FOR: BOARD OF TRUSTEES - ILLINOIS STATE UNIVERSITY NORMAL, ILLINOIS BY: FACILITY PLANNING AND CONSTRUCTION ISU FP&C NO. 170049 Date: 17.01.20 ISSUED FOR BIDDING
Transcript
Page 1: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

PROJECT MANUAL

ROTUNDA ROOF REPLACEMENT CENTER FOR THE VISUAL ARTS BUILDING #030 ILLINOIS STATE UNIVERSITY 401 SOUTH SCHOOL STREET NORMAL, MCLEAN COUNTY, ILLINOIS 61761

FOR: BOARD OF TRUSTEES - ILLINOIS STATE UNIVERSITY NORMAL, ILLINOIS

BY: FACILITY PLANNING AND CONSTRUCTION ISU FP&C NO. 170049 Date: 17.01.20 ISSUED FOR BIDDING

Page 2: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

This Page Left Blank

Page 3: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

PROJECT MANUAL TOC - Table of Contents

Illinois State University ISU FP&C NO: 170049

Rounda Roof Replacement at Center for the Visual Arts Building #030 Illinois State University 401 South School Street Normal, McLean County, Illinois 61761

DIVISION

01

SECTION TITLE

GENERAL REQUIREMENTS

PAGES

01 10 00

Summary

01 10 00-1-3 01 60 00 Product Requirements 01 60 00-1-2 01 71 00 Closeout Procedures 01 71 00-1-2 01 74 19 Construction Waste Management and Disposal 01 74 19-1-2

02

EXISTING CONDITIONS

02 41 19

Selective Demolition

02 41 19-1

06

WOOD & PLASTICS

06 10 53

Miscellaneous Rough Carpentry

06 10 53-1-3

07

THERMAL & MOISTURE PROTECTION

07 54 23

Elastomeric Membrane Roofing (EPDM)

07 54 23-1-11 07 62 00 Sheet Metal Flashing and Trim 07 62 00-1-5 07 92 00 Joint Sealants 07 92 00-1-4

END TOC

Page 4: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

This Page Left Blank

Page 5: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

01 10 00-1

DIVISION 1 - GENERAL REQUIREMENTS Section 01 10 00 - Summary

1. GENERAL

1.01. WORK COVERED BY CONTRACT DOCUMENTS

A. Work shall include roof replacement work including the removal of the existing Ballasted EPDM roofing system which is over the original built up Roof system down to the existing 2” poured gypsum deck. Then install a new fully adhered roofing system including insulation set in low rise foam, sheet metal, etc.

B. Note: There are ASBESTOS Ceilings below the roof deck. It is important to reduce the

amount of vibration on the deck as possible as a precaution. Contractor shall utilize carts to move heavy materials and equipment and insulation. Do not roll the bundles of insulation on the roof deck.

C. Staff and students WILL NOT occupy the building during construction. The Contractor

shall coordinate the work schedule with ISU’s Project Manager. Work may start on or after May 22, 2017 and 100% completed prior to August 4, 2017.

D. Specific site conditions and restrictions:

1. The Contractor’s personnel working on this project will be required to obtain a photo

I.D. for each worker at a cost of $5 per worker. I.D. must be worn at all times on campus.

2. All building entrances must be maintained clear and accessible to emergency personnel

and authorized staff at all times. a. If a portion of existing walks are to be blocked by the Contractor, the Contractor shall

install barricades (Snow Fencing), flashing warning lights, audible barricades and signs as required to adequately protect students, staff, workmen and other personnel at all times. Coordinate with ISU PM prior to blocking off any walks.

3. Contractor’s personnel are required to wear shirts at all times while on site. 4. Contractors and their personnel shall not interact with staff and/or students during the

course of construction activities at the site.

E. Existing utilities serving the facility shall be maintained throughout the project. Coordinate any utility disruptions with ISU Project Manager (PM).

F. For Contractor’s personnel and construction vehicle parking, see the “Terms of Campus

Labor”. G. All construction vehicle traffic occurring along existing walks shall be accompanied by a

walking escort.

1. Maintain existing vehicular access to site to provide uninterrupted access for use by persons and equipment involved in facility operations, project construction and for use by emergency vehicles including, but not limited to, fire trucks and ambulances.

2. Contractor shall not park, drive or store materials within the drip lines of trees.

Page 6: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

01 10 00-2

H. Provide and maintain construction snow fencing, a minimum of 4 feet high around the

perimeter of hoists, or other fixed or movable operating equipment and work vehicles. In addition to this fencing, provide flashing warning lights, audible barricades and signs to adequately protect students and staff at all times. Caution or Danger tape is not acceptable.

I. Contractor’s duties:

1. Except as specifically noted, provide and pay for:

a. Labor, materials and equipment. b. Freight and transportation. c. Tools, construction equipment and machinery. d. Acceptance of products and product handling at the job site. e. Protection of materials and equipment from physical damage and to the weather until

the work is complete. f. Other facilities and services necessary for proper execution and completion of the

work. g. Insurance in accord with Certificate of Insurance. h. Portable toilets for contractor’s staff.

2. Owner is exempt from sales tax on products permanently incorporated in the work.

a. Sales tax exemption certificate number will appear on the Purchase Order. b. Place exemption certificate number on invoices for materials incorporated in work. d. Upon completion of work, file with Owner notarized statement that all purchases

made under exemption certificate were entitled to be exempt. e. Pay legally assessed penalties for improper use of exemption certificate number.

3. Secure, and pay for, as necessary for proper execution and completion of work, and as

applicable at time of receipt of bids:

a. Permits. b. Government fees. c. Licenses.

5. Comply with codes, ordinances, rules, regulations, orders and other legal requirements

of public authorities which bear on performance of work.

6. Promptly submit written notice to ISU Project Manager of observed variance of contract documents. Contractor assumes the responsibility of work known to be contrary to requirements without written notice.

1.02. CONTRACTS

A. All work is under one contract. 1.03. PRODUCTS

A. Products furnished by the contractor and/or described in specifications: No asbestos containing materials, lead paint, or other hazardous materials shall be furnished or incorporated into this Project.

Page 7: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

01 10 00-3

1.04. CONTRACTORS’ USE OF PREMISES

A. Confine operation at site to areas permitted by:

1. Law. 2. Ordinances. 3. Permits. 4. Contract documents.

B. Ensure that all employees and employees of subcontractors do not eat, smoke or chew

tobacco, use e-cigs, consume alcoholic beverages or be in the possession of firearms, liquor, illegal drugs and other similar items on ISU’s property. Workers shall not come to the job site under the influence of intoxicants or drugs. ISU is a Smoke Free Campus.

C. Do not load structure with weight that will endanger structure.

D. Assume full responsibility for protection and safekeeping of products stored on premises.

E. Move any stored products or materials which interfere with operations of ISU promptly. 1.05. DEFINITIONS

A. Definitions:

1. Dates: Reference codes, regulations and standards are the issue current at date of bidding documents, unless otherwise specified.

2. Codes: Codes are rules, regulations or statutory requirements of government agencies. 3. Standards: Standards are requirements set by authorities, custom or general consent

and established as accepted criteria. 4. Provide: Provide means furnish and install. 5. Fabricated: Fabricated pertains to items specifically assembled or made of selected

materials or components to meet individual design requirements. 6. Manufactured: Manufactured means standard units, usually mass produced by an

established manufacturer of the respective item. 7. Shop fabricated or shop made: Shop fabricated or shop made refers to items made by

the contractor in his own shop.

B. Abbreviations:

1. ANSI American National Standards Institute. 2. ASHRAE American Society of Heating, Refrigeration and Air-Conditioning Engineers. 3. ASTM American Society for Testing and Materials. 4. A/E Architect/Engineer. 5. FM Factory Mutual Engineering Corp. 6. IDOT Illinois Department of Transportation. 7. IEPA Illinois Environmental Protection Agency. 8. NFPA National Fire Protection Association. 9. OSFM Office of State Fire Marshal.

10. UL Underwriter’s Laboratories, Inc. END 01 10 00

Page 8: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

01 10 00-4

This Page Left Blank

Page 9: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

01 60 00 – 1

DIVISION 1 - GENERAL REQUIREMENTS Section 01 60 00 – Product Requirements

1. GENERAL

1.01. DESCRIPTION

A. The Contractor shall submit to shop drawings, product data and samples as outlined and thoroughly check and correct before submitting to ISU Project Manager.

1.02. SHOP DRAWINGS

A. Original drawings prepared by Contractor, subcontractor, supplier or distributor which illustrate

a portion of the work showing fabrication, layout, setting or erection details which vary from the contract document drawings or specifically requested.

1.03. PRODUCT DATA

A. Manufacturer’s standard schematic drawings:

1. Clearly define on schematic what is being provided for this project.

B. Manufacturer’s catalog sheets, MSDS Sheets, brochures, diagrams, schedules, performance

charts, illustrations and other standard descriptive data.

1. Clearly mark each copy to identify pertinent materials, products or models. 2. Show dimensions and clearances required. 3. Shop performance characteristics and capacities.

1.04. SAMPLES – When Requested

A. Provide physical examples to illustrate materials, equipment or workmanship and to

establish standards by which completed work is judged as requested.

B. Submit sample of sufficient size and quantity to clearly illustrate:

1. Functional characteristics of products or materials with integrally related parts and attachment devices.

2. Full range of color samples. 3. After review, samples will be retained by ISU.

1.05. CONTRACTOR’S RESPONSIBILITIES

A. Thoroughly check and review shop drawings, product data and samples prior to submission.

B. The Contractor shall submit for each and every product an affidavit by the manufacturer stating that no asbestos-containing materials or lead-based paints have been utilized in the products furnished by that manufacturer.

C. Verify: 1. Field measurements. 2. Field construction criteria. 3. Catalog numbers and similar data.

Page 10: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

01 60 00 - 2

D. Coordinate each submittal with requirements of work and contract documents.

E. Contractor’s responsibility for errors and omissions in submittals is not relieved by ISU’s review

of submittals.

F. Contractor’s responsibility for deviation in submittals from requirements of contract documents is not relieved by ISU’s review of submittals unless a written acceptance of specific deviations is given to the roofing contractor.

1.06. SUBMISSION REQUIREMENTS

A. Schedule submissions for review at least 20 work days before dates submittals will be

needed.

B. Submit number of copies of shop drawings, product data and samples which Contractor requires for distribution and one copy for ISU’s PM.

C. Submit one sample if a sample if requested.

D. All submittals shall be submitted for final approval no later than 45 days after signing contract.

E. Accompanying submittals with transmittal letter in duplicate containing:

1. Date. 2. Project title and number. 3. Contractor’s name and address. 4. The number of each shop drawing, product data and sample submitted. 5. Notification of deviations from contract documents.

F. MSDS sheet to be submitted in an electronic form.

1.07. DISTRIBUTION OF SUBMITTALS AFTER REVIEW

A. Distribute copies of shop drawings and product data which carry ISU’s reviewed stamp to:

1. Contractor’s file. 2. Job site file. 3. Record documents file. 4. Subcontractors. 5. Suppliers. 6. Fabricators.

END 01 60 00

Page 11: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

01 71 00-1

DIVISION 1 - GENERAL REQUIREMENTS Section 01 71 00 – Closeout Procedures

1. GENERAL

1. 01. CLEANING UP

A. Roofing Contractor shall, prior to final inspection, perform final cleaning work area with

material and methods recommended by manufacturers of installed materials.

B. Upon completion of work, remove temporary structures, fences, scaffolding, surplus materials and rubbish from work site.

1. 02. AS-BUILT DRAWINGS

A. Contractor(s) shall maintain one (1) set of prints and one bound set of specifications on which

he shall record every deviation that is made from original drawings and specifications at the time the change is made.

B. Contractor(s) shall keep a neat and complete record of exact manner in which work is in-

stalled. Dimension shall be included to accurately locate items that will be concealed in finished work and which may later be necessary to locate for service.

C. This record set of drawings and specifications shall be kept at job site for inspection.

D. At completion of the work, arrange above submittals in order, properly indexed and marked

for each Division of the Work, and certify the revised prints of drawings and specifications are complete and accurate.

E. Before final payment is made, Contractor shall deliver the record drawings and

specifications to ISU’s Project Manager (PM). 1. 03. PUNCH LIST

A. After project is 100% complete as determined by Contractor, notify ISU’s PM in writing

requesting a site visit for the preparation of a punch list of items needing corrected and/or completed. This punch list is not to be considered a list to tell Contractor what needs to be finished. A copy of this punch list will then be submitted to the Contractor. If the ISU’s PM determines the work is to an acceptable point, a Certificate of Substantial Completion will be executed.

1. After Contractor has completed all items on the punch list, the ISU’s PM shall be

notified in writing as to its completion, and will make a final site visit to verify that corrections have been made in compliance with punch list. A Certificate of Final Completion will be executed.

Page 12: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

01 71 00 -2

1. 04. MAINTENANCE AND OPERATION INSTRUCTIONS

A. Manuals: Furnish two (2) sets of manuals for all Divisions of the Work as required in bound

form, hard cover.

B. Instruction books may be standard booklets but should be clearly marked to indicate applicable equipment and paragraphs.

1. 05. WARRANTIES AND GUARANTEES

A. Prior to final payment, Contractor shall furnish all warranties and guarantees as called for in

the project manual, including specifications, along with furnishing a general one (1) year guarantee letter signed by an authorized agent of the Contractor stating compliance with the terms established in the General Conditions. Contractor to fill out a Guarantees. Warranty and Bonds Form (GWB) at the end of the project. ISU Project Manager will provide form to the contractor.

END 01 71 00

Page 13: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

01 74 19 - 1

DIVISION 1 - GENERAL REQUIREMENTS Section 01 74 19 – Construction Waste Management & Disposal

1. GENERAL

1. 01. DESCRIPTION

A. The work in this section is required of the contractor unless otherwise specified.

1. Contractor:

a. Maintain premises and adjacent properties free of waste, debris and rubbish caused by construction operations.

b. At completion of work, or at such other times as directed by ISU’s Project Manager (PM), remove all waste, debris, rubbish, tools, equipment, machinery and surplus materials.

c. At completion of project, leave project clean.

B. Related requirements specified elsewhere:

1. 01 10 00 - Summary. 2. 01 71 00 – Closeout Procedures.

1. 02. SAFETY REQUIREMENTS

A. Standards: Maintain project in accordance with the following safety and insurance standards:

1. Applicable Federal and State requirements. 2. National Fire Protection Association (NFPA).

B. Hazards control:

1. Store volatile wastes in covered metal containers, and remove from premises daily. 2. Prevent accumulation of wastes which create hazardous conditions. 3. Provide adequate ventilation during use of volatile or noxious substances.

C. Conduct cleaning and disposal operations to comply with applicable Federal and State anti-

pollution laws.

1. Do not burn or bury rubbish and waste materials on project site. 2. Do not dispose of volatile wastes such as mineral spirits, oil or paint thinner in storm or

sanitary drains. 3. Do not dispose of wastes into streams or waterways.

2. PRODUCTS

2.01. DUMPSTER EQUIPMENT

A. If a means has not been provided to remove waste materials, debris and rubbish on a daily

basis in trucks and trailers, provide containers (dumpster) for deposit of waste materials, debris and rubbish. Coordinate location of all covered containers with ISU’s PM in order to avoid conflicts with site restrictions.

Page 14: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

01 74 19 -2

2. 02. CLEANING MATERIALS

A. Select and use all cleaning materials and equipment with care to avoid scratching, marring, defacing, staining or discoloring surfaces cleaned.

B. Use only cleaning materials recommended by manufacturer of surface to be cleaned.

3. EXECUTION

3. 01. DURING CONSTRUCTION

A. Execute cleaning to ensure that building, grounds and adjacent properties are maintained

free of waste, debris and rubbish.

B. Wet down materials and rubbish to prevent dust from forming and blowing.

C. During progress of work, clean project area and adjacent properties and dispose of waste materials, debris and rubbish.

D. Provide on-site enclosed dumpsters for collection of waste materials, debris and rubbish if

debris is not removed daily.

E. Remove waste materials, debris and rubbish from site, and legally dispose of at public or private dumping areas off Owner’s property in a legal manner.

F. All nails, fasteners, trim, etc. which are dropped onto grade or other surfaces shall be picked

up and removed on a daily basis. G. Do not use ISU Dumpsters.

3. 02. FINAL CLEANING

A. Remove grease, dust, dirt, stains, labels, fingerprints, protection and other foreign materials

from finished surfaces.

END 01 74 19

Page 15: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

02 41 19 - 1

DIVISION 2 - SITE WORK Section 02 41 19 – Selective Demolition

1. GENERAL

1.01. WORK INCLUDES

A. The contractor shall remove and dispose of existing roofing systems as indicated along with rubbish and debris resulting from demolition operations.

1.02. RELATED WORK

A. Specified elsewhere:

1. 07 54 23 – Elastomeric Membrane Roofing (EPDM). 2. 07 62 00 – Sheet Meal Flashing & Trim.

1.03. EXISTING CONDITIONS

A. Conduct demolition to minimize interference with adjacent building areas and ISU’s

operations along with operations of other contractor working at this facility. Maintain protected egress and access at all times.

B. Provide, erect and maintain temporary barriers in accord with OSHA regulations.

2. PRODUCTS (Not Applicable.)

3. EXECUTION

3.01. PREPARATION

A. Protect existing portions of structure to remain and items not indicated to be removed or demolished.

3.02. EXECUTION

A. Demolish and remove existing construction as specifically noted on drawings in an orderly and

careful manner. Protect existing construction and equipment to remain from damage or deterioration.

1. Except where noted otherwise, immediately remove demolished materials from site as

work progresses. Upon completion of work, leave areas in a clean condition.

2. Do not burn or bury materials on site.

END 02 41 19

Page 16: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

02 41 19 - 2

This Page Left Blank

Page 17: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

06 10 53 -1

DIVISION 6 - WOOD & PLASTICS Section 06 10 53 – Miscellaneous Rough Carpentry

1. GENERAL

1.01. WORK INCLUDES

A. Provide all labor, materials, equipment and services necessary to the furnishing and installation of all rough carpentry and accessories, complete, in place, as shown on the drawings, specified herein and needed for a complete and proper installation.

1.02. RELATED WORK

A. Specified elsewhere:

1. 07 54 23 – Elastomeric Membrane Roofing (EPDM). 2. 07 62 00 - Sheet Metal Flashing and Trim.

1.03. QUALITY ASSURANCE

A. Lumber standard: Comply with PS-20 for each indicated use, including moisture content and

actual sizes related to the indicated nominal sizes except as otherwise indicated.

B. Plywood Standard: Comply with PS-1 for Softwood Plywood - Construction and Industrial.

C. Factory-mark each piece of lumber and plywood with type, grade, mill and AWPB grading agency identifications.

1.04. DELIVERY, STORAGE & HANDLING

A. Keep carpentry materials dry during delivery, storage and installation. Store lumber in

stacks with provisions for air circulation within stacks. Protect bottom of stacks against contact with damp surfaces. Protect exposed materials against weather with a waterproof covering.

1.05. WARRANTY, in accord with General Conditions: One year.

2. PRODUCTS

2.01. MATERIALS

A. Dimensional and board lumber: Southern Pine, No. 1 (SPiB). All lumber shall be S4S unless

noted otherwise.

1. All lumber, blocking and furring in conjunction with roofing work, shall be pressure preservative treated in accordance with American Wood Protection Association Standard AWPA U-1, Use Category 3B (for normal exposure) and shall be so labeled. Kiln-dry wood to a maximum moisture content of 15% after treatment with water-borne preservatives.

B. Plywood sheathing shall be APA Grade-Trademark Standard C-D with exterior glue.

Thickness shall be as called for on the drawings.

Page 18: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

06 10 53 - 2

1. All plywood in conjunction with roofing work, shall be pressure preservative treated in accordance with American Wood Protection Association Standard AWPA U-1, Use Category 3B (for normal exposure) and shall be so labeled. Kiln-dry wood to a maximum moisture content of 15% after treatment with water-borne preservatives.

C. Anchorage and fastening materials: Select proper type, size, material and finish for each

application. Rough hardware needed for the proper installation of all carpentry work shall be provided. Nails, spikes, screws, bolts and similar items shall be of proper type, size, material and finish to fasten and hold the various members securely in place.

1. All fasteners and anchors for use in exterior locations, high humidity locations and at all

treated wood locations shall be stainless steel or have a corrosion-resistant coating, a resistants that is documented in writing as resistant to treated wood characteristics.

2. Refer to drawings and other areas of this specification for specific anchorage requirements. Power actuated fasteners are not acceptable for wood blocking attachment at roof areas.

3. EXECUTION

3.01. REMOVE EXISTING CONSTRUCTION

A. Refer to drawings for specific locations for limited rough carpentry work required for removal

due to installation of new carpentry work required in conjunction with the installation of the new roofing system.

3.02. INSTALLATION

A. Discard units of material which are unsound, warped, bowed, twisted, improperly treated, not

adequately seasoned or too small to fabricate the work with a minimum of joints or the optimum jointing arrangement.

B. Set carpentry work accurately to indicated levels and lines with members plumb and true to

other work and existing site conditions. Scribe and cope for accurate fit.

C. Securely attach carpentry work to structure by anchoring and fastening as specifically shown on the drawings and in accord with recognized standards and as follows.

1. Anchoring devices shall be either a friction, keying or bonding types as recommended

by fastener manufacturer along with depth of embedment and size of fastener.

a. Fasteners associated with blocking and nailers in conjunction with roofing work shall be sized to achieve adequate pull-out strengths to resist a minimum pull-out resistance of 200 lb/ft in all directions.

1) Minimum anchorage size for attachment or securement shall be 3/8” diameter

bolts spaced as indicated on drawings. 2) All wood blocking shall be pre-drilled prior to installation of bolt type fasteners. 3) Provide washers under bolt heads and nuts in contact with wood. Recess all

wood blocking with a minimum thickness of 1½”. 4) All bolt type anchors shall be staggered in all wood blocking wider than 6". 5) A fastener shall be placed within 3" of the end of each section of wood blocking.

Page 19: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

06 10 53 -3

b. Use wire nails or screws to secure multiple nailers with a minimum penetration into the base wood blocking of 1¼”. All multiple layers of roof blocking shall be installed in double rows spaced 24" o.c. staggered with a fastener within 3" of the end of each section of wood blocking. Do not wax or lubricate fasteners.

1) If nails are utilized, install at an angle to increase the withdrawal resistance. 2) Screw diameter shall be a minimum #12. 3) Install fasteners without splitting of wood by predrilling.

D. Provide wood nailers and blocking where shown on the drawings. Use member sizes as

shown.

E. Plywood: Comply with the recommendations of the American Plywood Association (APA) for the fabrication and installation of plywood work. Provide thickness as shown on the drawings.

1. Nail or screw to fasten plywood to framing systems to comply with requirements as

specifically noted above. 3.03. CLEAN UP

A. Remove all scrap and debris, and dispose off-site and leave all work areas clean. END 06 10 53

Page 20: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

06 10 53 -4

This Page Left Blank

Page 21: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

07 54 23 -1

DIVISION 7 - THERMAL & MOISTURE PROTECTION Section 07 54 23 – Elastomeric Membrane Roofing (EPDM)

1. GENERAL 1.01. WORK INCLUDES

A. Base Bid: 1. Provide all labor, materials, equipment and services necessary to the removal of the

existing ballasted roofing/insulation system and the original Built-up roofing system, and for furnishing and installation of a new fully-adhered membrane roofing systems, insulation, low-rise foam attachment and accessories, complete, in place, as shown on the drawings, specified herein, and needed for a complete and proper installation.

1.02. RELATED WORK

A. Specified elsewhere:

1. 01 60 00 - Product Requirements. 2. 02 41 19 - Selective Demolition. 3. 06 10 53 – Miscellaneous Rough Carpentry. 4. 07 62 00 - Sheet Metal Flashing & Trim.

1.03. REFERENCES

A. Referenced specifications: The specified system manufacturer’s standard long form

specifications shall be fully complied within all aspects, as they may be termed applicable and is hereby made a part of this project specification. In case of conflict between this referenced specification and the project specifications, notify the ISU’s Project Manager (PM).

1.04. QUALITY ASSURANCE

A. Roofing Contractor shall be a firm approved or franchised by roofing system manufacturer.

1. Be certified by the State of Illinois in accord with the Illinois Roofing Industry Licensing Act,

225 ILCS 335, as amended. 2. All removal and installation of roofing membranes and insulation shall be performed by

crews directly employed by roofing firm. No subcontracting of this work will be permitted.

B. The roofing system manufacturer and ISU’s PM will be on-site to review all conditions and installation requirements to verify conformance with the bid documents and manufacturer’s warranty.

1. It is the responsibility of the Contractor to schedule the date for this initial roof replacement

at least 10 days in advance with the ISU’s PM. All submittal requirements shall be completed and reviewed by the ISU’s PM prior to scheduling this work.

2. It is the Roofing Contractor’s responsibility to review all conditions and installation

requirements to verify conformance with the bid documents and manufacturer’s warranty.

Page 22: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

07 54 23 -2

1.05. SUBMITTALS

A. Shop drawings:

1. Submit only manufacturer approved shop drawings for review and comment. 2. Minimum scale for roof plan: 1/8”= 1'-0". 3. Minimum scale for details: 1½" = 1'-0". 4. Submit the following:

a. Tapered insulation plan layout(s).

5. Submit the following shop drawings if different from the contract documents: a. Base flashing details. b. Flashing and sheet metal work. c. Membrane terminations. d. Roof flashings.

B. Product data: All individual items shall be properly labeled and identified.

1. EPDM manufacturer’s specifications for all roofing system components. 2. Thermal board. 3. Rigid insulation board. 4. Low-rise foam insulation adhesive. 5. Joint seal or tape. 6. Pipe and conduit supports. 7. Walkway pads 8. Sample copy, manufacturer’s warranties. 9. Material Safety Data Sheet (MSDS) on all products.

D. Samples: (1 set of each) All individual items shall be properly labeled and identified,

(If Requested):

1. EPDM membranes: 5" x 5" of flashing and field membrane. 2. Insulation and thermal boards: 5" x 5". 3. Termination bars: 6" long.

D. Certificates:

1. Prior to the start of any work, the Contractor shall submit to ISU’s PM their firm’s Illinois Roofing Industry Licensing Certificate along with a letter that lists every item to be incorporated into the roofing system by name, i.e., brand and thickness of insulation, etc., which is signed by the roofing system manufacturer and attests to the compatibility of the various items with the roofing system.

1.06. PRODUCT DELIVERY, STORAGE AND HANDLING

A. All roofing materials, insulation, and EPDM membrane, shall be handled and stored in

accord with manufacturer’s recommendations. Damaged or wet materials shall not be used. Follow respective manufacturer’s recommendations. The contractor shall use carts and buggies to move materials around on roof. The ceiling below contains Asbestos and vibrations are to be held to a minimum. Do not roll bundles of insulation on the roof.

Page 23: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

07 54 23 -3

B. Deliver all materials in manufacturer’s original, unopened containers and rolls with all labels intact and legible.

1. Deliver materials requiring fire resistance classification packaged and with labels attached

as required by labeling service. 2. Deliver materials in sufficient time and quantity to allow continuity of work and compliance

with approved construction schedule.

C. Handle rolled goods in a manner to prevent damage.

D. Store materials on clean raised platforms with weather protective covering when stored outdoors.

1. Bundles of insulation and roofing materials shall remain in manufacturer’s wrapping or

covered with canvas tarps. 2. Store rolled goods on end or as required by manufacturer. 3. Comply with fire and safety regulations. 4. Store emulsions and other temperature-sensitive products in ambient temperature above

40° F. (4° C.).

5. Provide continuous protection of materials against damage or deterioration.

E. DO NOT STORE MATERIALS OR PALLETS ON FINISHED ROOFING.

F. Remove damaged or defective materials from site. 1.07. JOB CONDITIONS

A. Existing conditions Site Visit: For terms of Site visits see “Terms of on Campus Labor”.

B. Environmental requirements: Follow manufacturer’s written request for variance:

1. Apply roofing in dry weather. 2. Do not apply roofing when ambient temperature is below 40° F. (4° C.).

C. Protection:

1. Do not traffic over completed membrane roofing work.

2. If completed roofing work is damaged, restore to original condition, or replace all

work or materials damaged during roofing operations.

Page 24: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

07 54 23 -4

3. Protect paving, building surface, landscaping and all other work adjacent to hoists and

other roofing equipment prior to start of work. All other locations around building shall have a suitable protection from overspray of bead foam adhesive, spilling or other accidents.

a. Lap suitable materials, of type as recommended by roofing system manufacturer. b. Secure protective coverings against wind. c. Maintain protective covering in place for duration of roofing work. d. Remove on completion of roofing work.

4. Provide Material Safety Data Sheets (MSDS) on location at site at all times during the

transportation, storage and application of low-rise foam adhesive. D. Schedule all roofing operations, and delegate responsibility of each subcontractor for:

1. “On roof” operations. 2. Proper protection of work in place, including work of others.

E. Installation requirements:

1. Do not proceed with the removal of existing roofing system/components and installation of roof insulation unless the material, equipment and tradesmen required for the complete installation of the new roofing system are at project site and ready to follow with work immediately (same day). Install no more insulation each day than can be covered with roofing membrane by the end of the working day and before the start of inclement weather of that day.

a. The roof deck must be cleaned as per Manufacturer requirements. Surface

shall be free from ice, snow, moisture or other conditions that would interfere with manufacturer’s recommended installation.

2. All roofing work is to be continuous from project start through completion, weather

permitting, during the course of a standard five-day work week as a minimum. Discontinuance of work may be construed as to mean abandonment of the job and sufficient cause for cancellation of the contract between the ISU and the Contractor.

F. All EPDM membrane base flashings shall be installed in conjunction with and immediately

following installation of membrane roofing. Coordinate roofing work with sheet metal work; installing sheet metal immediately as roof areas are completed.

1.08. WARRANTY

A. Roofing warranty starts on date of manufacturer’s acceptance of the completed work. All

warranties shall have a no dollar limit to correct, repair or replace defects in the roofing membrane and all associated components manufactured and/or furnished by the roofing membrane manufacturer including, but not limited to the insulation and thermal boards including adhesive and covering both labor and material with no dollar limitation.

1. The Contractor shall furnish to the Owner, the roofing membrane manufacturer’s

standard Twenty (20) year Total Systems Warranty.

a. Warranty shall include wind speed coverage of 90-mph measured 10 meters above ground level.

Page 25: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

07 54 23 -5

b. The ISU Project Manager shall receive one exact copy of all warranty inspection reports and one copy of the repairs for warranty listing.

2. The Contractor shall furnish, in addition to the above warranty, a two (2) year warranty without any monetary limit to correct, repair or replace any and all work as herein identified and outlined.

a. The warranty shall include the following components listed on Contractor’s letterhead:

1) Name and address of Contractor. 2) Name and address of ISU. 3) Type and name of building. 4) Location of building. 5) Area of roofs. 6) Date of final acceptance by ISU. 7) Date warranty expires. 8) Contractor’s signature, title and corporate seal.

b. The two (2) year warranty shall include the following defects, imperfections or faults in:

1) Materials: a) Sheet metal work. b) Sealant other than material provided by EPDM system manufacturer. c) New perimeter blocking and attachment.

2) Workmanship:

a) Faulty workmanship in the application of the insulation, roof membrane or composition flashings.

b) Bare spots, blisters, fish mouths, ridges, splits, crushed membrane, excessive foreign objects under membrane, buckles, wrinkles or slippage in the roof membrane or flashings.

c) Water standing on any portion of the roof for an extended period of time, for any reason, provided that the Contractor has advised the ISU PM in writing of such a condition prior to the completion of the roofing work.

d) Roof membrane damage or failure due to faulty workmanship or blow off of the roof insulation, cants or edge strips.

e) Roof insulation, cant or edge strip damage due to leaks in the roof membrane or composition flashings.

f) Adhesive overspray or drippings inside or outside building. g) Faulty workmanship in the Contractor’s correcting of defects, imperfections

or faults. h) The Contractor’s damages to other parts of the building(s). i) If contractor scores / cuts the insulation boards excessively,

contractor will replace the entire insulation board. The ISU PM has the authority to make the determination of excessive scores / cuts.

j) No debris will be allowed between Thermal board and the membrane.

3) The above listed conditions are considered defects whether or not such conditions are causing water leaks.

Page 26: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

07 54 23 -6

2. PRODUCTS

2.01. ROOFING SYSTEMS

A. All products and components (including, but not limited to the insulation and mechanical

fasteners) shall be manufactured and supplied by the roofing system manufacturer and covered by the membrane manufacturer’s standard twenty (20) year Total Systems Warranty. Manufacturer’s supplying Membrane made by others are not acceptable.

B. Approved fully-adhered single-ply EPDM membrane system manufacturers:

1. CAR . . . . Carlisle SynTec Systems, Carlisle, PA. 2. FST . . . . Firestone Building Products Co., Carmel, IN. 3. VER . . . . Versico, Inc., Carlisle, PA. 4. JM ……… Johns Maniville, Denver, CO.

C. EPDM single-ply, fully-adhered membrane systems: Elastomeric single-ply fully-adhered membrane systems (EPDM): Provide a black, 60 mil membrane conforming to the minimum physical properties of ASTM D4637, non-reinforced uniform, flexible sheet made from EPDM that is formulated fire-retardant sheet. All sheets shall have factory applied tape along leading edge.

1. CAR . . . . Sure-Seal Design “A”, 60 mil thick membrane, fire rated. 2. FST . . . . Rubbergard Adhered System, 60 mil thick membrane, fire rated. 3. VER . . . . VersiGard Roofing System, 60 mil thick membrane, fire rated. 4 . J M … … . J M E P D M N R 6 0 m i l , f i r e r a t e d .

2.02. FLASHING SYSTEMS

A. Provide .060 mil EPDM base flashing system as manufactured by the respective roofing system manufacturer. Utilize EPDM flashing material to the greatest extent as allowed by the system manufacturer.

2.03. ROOF INSULATION, type, thickness and locations as shown on the drawings.

A. Insulation material shall be a brand that is approved and acceptable by the roofing system

manufacturer.

TYPE ASTM R / INCH

1. ½” Thermal Board (Fiberglass Mat) C1177 or C1278 0.56 @ 1/2" 2. Polyisocyanurate Boards C1289 5.6 (LTTR)

B. Provide a 1/2" thick thermal board consisting of either a pre-primed glass mat faced gypsum

or non-primed fiber reinforced gypsum panel board over top layer of insulation as indicated on drawings. Overall board sizes shall be 4' x 4'.

C. Provide a polyisocyanurate foam board panels bonded to glass fiber facers as (Flat and

tapered at specified locations) as indicated on the drawings.

1. Minimum board thickness shall be provided at low points (3” of Polyiso. plus ½” Thermal Board. Starting at the roof Drain sumps) or as shown on the drawings with an overall board sizes shall be 4' x 4’.

Page 27: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

07 54 23 -7

2. All roof saddles and crickets shall be manufactured and comply with the above

requirements with a ½” per ft. slope. All roof drain tapered sumps shall utilize a ½” per ft. slope.

3. All fill insulation for utilization with tapered polyisocyanurate foam insulation shall be the

manufacturer’s standard polyisocyanurate fill insulation board furnished in increments compatible with tapered system of the type as specified above.

D. Polyisocyanurate foam insulation board: Shall be polyisocyanurate foam board with glass mat

facer laminated to both sides of board. Insulation boards shall have a minimum density of 25 psi for the first layer (bottom) complying with ASTM C1289-01, Type II, Class 1, Grade 3 and 25 psi complying with ASTM C1289, Type II, Class 1, Grade 3 for the second layer (top).

E. Roof insulation shall be manufactured or approved by the membrane roofing system

manufacturer as a suitable substrate for the membrane roofing and included in the total systems warranty.

2.04. ACCESSORY ITEMS

A. Provide accessory items as recommended by systems’ manufacturer for a particular system used unless otherwise specifically detailed or as called for on the drawings or specifications. If Manufacturer and contract documents conflict, contact ISU’s PM for direction.

2.05. OTHER MATERIALS

A. Membrane and flashing system adhesive: cold applied, high-strength, rubber type bonding adhesive as manufactured by the EPDM system manufacturer for attachment of the EPDM Membrane to the thermal board and for attachment of the EPDM flashing system membrane to substrates at all locations.

B. Sheet metal flashings: Flashings shall be furnished and installed as specified in Section 07 62 00, Flashing & Sheet Metal.

C. Fasteners: 1. Nails: 12-ga. annular threaded, minimum 1" long shank, non-ferrous, cement-coated or

galvanized 1" square or round solid cap head barbed roofing nails. 2. Metal discs (Type as required by roofing system manufacturer):

a. Flat caps, minimum 1" in diameter. b. Minimum 30-gauge sheet metal. c. Form to prevent dishing. d. Bell or cup shaped caps: NOT PERMITTED.

3. Drive-type mechanical fasteners of a type and size as required by EPDM roofing

membrane system manufacturer for securement of termination bar.

E. Low-rise foam adhesive: Adhesive for attachment of insulation shall be a two-part, low rise expanding, insulation type, which shall be applied with beads spaced at 4” o.c. (max.). Adhesive shall be supplied by roofing system manufacturer and included in the system warranty. No asphaltic or cold applied products will be allowed.

1. CAR . . . . . . Two part insulating foam adhesive as required to meet warranty. 2. FST . . . . . . . Two part insulating foam adhesive as required to meet warranty. 3. VER . . . . . . Two part insulating foam adhesive as required to meet warranty. 4. JM …………. Two part insulating foam adhesive as required to meet warranty.

Page 28: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

07 54 23 -8

F. Water cut-off mastic: Membrane manufacturer’s mastic designed to prevent moisture

migration at drains, compression terminations and beneath conventional metal edging.

G. Termination bars are required at all wall terminations. Provide EPDM roofing membrane system manufacturer’s standard termination bar or types as follows: (Provide drive-type mechanical fasteners at all locations except where screw type fasteners are required at wood substrate locations, both of which shall be of a type and size as required by EPDM roofing membrane system manufacturer for securement of termination bar at 6" o.c. max.)

1. 1/8” x 1" aluminum bar under counter flashing or other restricted spaces. 2. 1/8” x 1½" aluminum bar with 45° sealant pocket at all locations where space permits.

H. Wood nailers: Treated wood nailers shall be installed at the perimeter of the entire roof and

around all projections and penetrations as required by the roofing manufacturer and/or where specifically noted or detailed on the drawings. Refer to specification Section 06100.

I. Vent pipe and roof drain flashings: Refer to drawings for specific details and notes for

conformance to EPDM membrane roofing system manufacturer’s requirements.

J. Infill and detail foam shall consist of an E-84, Class 1 field applied polyurethane foam, specifically manufactured to allow for expansion and contraction, as recommended by roofing system manufacturer. Joints shall be completely filled (without voids). After foaming of joints have been completed, carefully remove any excess foam above joint surfaces to allow installation of EPDM membrane.

L. Rubber Walkway pads: Reprocessed rubber walkway pads with a texture non-skid

surface as manufactured by or approved by the roofing membrane manufacturer. Size shall be standard 30”x30”.

M. Warning Stripe: – 6” wide yellow warning strip adhered to the EPDM roofing

Membrane. 3. EXECUTION

3.01. INSPECTION AND REMOVAL

A. Prior to removal of existing roofing, verify that all work which penetrates roof deck or requires

men and equipment to traverse roof deck has been completed. B. Remove existing roofing system including, but not limited to roofing membranes, insulation

systems, flashing and related components down to the roof deck on all areas indicated on the drawings.

C. Examine all surfaces for inadequate anchorage, foreign materials, moisture, unevenness or

other conditions which would prevent execution and quality of installation of roofing and flashing system and accessory items as specified.

D. The roofing installer shall report all irregularities or other conditions of the existing roof deck

and system that would adversely affect the insulation, roofing and flashing installations to the Contractor who shall make all required corrections so that the deck is in an acceptable condition to the roofing system manufacturer.

Page 29: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

07 54 23 -9

1. Do not proceed with work until all defects are corrected to the satisfaction and with the written approval of the roofing system’s manufacturer.

2. Application of the insulation or roofing will be considered as evidence of acceptance of

the existing roof deck and system and approval by the roofing installer as an acceptable surface for roofing and base flashing. The roofing installer shall not be required to proceed with their work until the roof deck is in an acceptable condition. Any disagreement regarding the condition of the roof deck or roof system shall be promptly referred to the ISU PM in writing.

3. Prior to the application of the membrane roofing, the Contractor shall examine the roof

to insure that adequate roof drainage exists to positively direct storm water to its outlet without obstructions or low points that would permit ponding of water at any point on the deck.

3.02. PREPARATION

A. Thoroughly clean all surfaces against or into which work will be installed. Ensure that all

surfaces are clean free of dust and dry before starting and during performance of work. Follow roofing system manufacturer’s recommendations.

3.03. ENVIRONMENTAL CONDITIONS

A. Remove and install roof insulation and roofing only in dry weather. Comply with the

manufacturer’s climatic restrictions. B. Installation during weather conditions other than those permitted in the manufacturer’s

specifications must be acknowledged and approved in writing by the manufacturer and ISU’s PM.

3.04. INSTALLATION

A. Install roofing insulation, membrane and flashing systems along with all accessory items in

accordance with system manufacturer’s printed instructions current at date of bidding documents.

B. Anchor to existing deck with low rise foam as required by the roofing membrane

manufacturer to achieve 90 mph wind speed and 20 year warranty. Install the layers of tapered and/or flat insulation. Then install a ½” thick thermal board. Thermal boards (with no exceptions) shall be applied with staggered joints and with end joints staggered at mid-point. Thermal board and the insulation in low rise foam adhesive as per manufacturer’s recommendations. Continuously roll insulation boards after being set in low rise adhesive, weight and buckets are not acceptable.

C. All insulation boards (with no exceptions) shall be applied with staggered joints at mid-point

in each layer with all layers. Offset all joints between layers a minimum of six inches.

1. After all insulation boards have been installed, Contractor shall verify that all insulation boards are fully secured, including all corners of boards and within all layers between insulation boards, prior to installation of the EPDM membrane. Verify all waste insulation pieces, rocks and other debris is removed from insulation prior to installation of the EPDM Roofing membrane.

2. Install the insulation as shown on the drawings. Cut and fit tightly around

obstructions, and fill voids with insulation. Install crickets and tapered areas as shown on the drawings and as required for proper drainage.

Page 30: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

07 54 23 -10

D. All EPDM membrane roofing systems shall be installed by starting at the low point and

working up to high point perpendicular to the roof slope. All lap joints in membranes shall be with upper membrane lapped over lower membrane a minimum distance as indicated on the drawings or as recommended by membrane manufacturer.

1. Unroll and position membrane in-place without stretching to allow membrane to relax as

per recommendation by the roofing manufacturer prior to bonding. Comply with manufacturer’s recommendations for all temperature conditions. This requirement and time period shall be strictly enforced and will be a cause for rejection if not maintained.

2. All side laps in membranes shall be staggered. No intersections of four sheets will be allowed.

3. The final membrane covering shall be carefully installed (without stretching) in a manner

acceptable to the system manufacturer for a smooth, fully adhered and wrinkle free installation.

a. Under no exception will wrinkles or field repairs or debris between thermal board and membrane will acceptable or permissible. If wrinkles or repairs or debris occur, the entire EPDM membrane sheet shall be removed and replaced.

b. Install the 60 mil EPDM single-ply membrane utilizing the membrane manufacturers cold applied, high-strength, rubber type bonding adhesive to the membrane and the surface to which it is being bonded at a rate as recommended by manufacturer.

4. Membrane lap splices shall utilize the EPDM system Manufacturer’s pre-applied 5” or 6” wide seam tape.

a. Seams shall be cleaned and prepared prior to adhering of seams as recommended by EPDM system manufacturer.

b. All intersecting joints of flashings shall be covered with “T” joint cover as recommended by EPDM manufacturer.

E. Install new vent pipe flashings and walkway pads as shown on the drawings.

F. Install flashings over the top of all new termination bars on vertical wall surfaces, unless specifically detailed otherwise on drawings.

3.05. FIELD QUALITY CONTROL

A. The final inspection for warranty shall be conducted by the system manufacturer’s inspector upon completion of all work. Contractor shall notify manufacturer of construction schedule whereas manufacturer can adequately schedule visitation time. All costs associated (if any) with this requirement shall be borne by the Contractor.

B. Refer to paragraph 1.04., B. for terms and conditions regarding the installation requirements

for roofing system manufacturer’s review and approval prior to starting entire roofing replacement operations at any location at this facility. The acceptance of the roof installation at this location will be the standard for judging the remainder of the work.

Page 31: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

07 54 23 -11

C. Refer to paragraph 1.08., A., 1, b. for warranty inspection report, listing repairs for warranty by manufacturer for acceptance of completed work.

a. Accompany the manufacturer's technical inspector and assist with equipment and

workmen if necessary to provide access to the roof. Correct all defects noted during the inspection.

3.06. PROTECTION

A. Do not permit construction traffic over completed insulation and membrane

work. If new membrane is dirty from construction traffic on it, contractor shall clean the new membrane per recommendation of the EPDM manufacturer to the satisfaction of the ISU PM.

B. Protect insulation work from exposure to moisture, damage and deterioration primarily by

prompt installation of roofing work. Remove and replace insulation work which has become wet, damaged or deteriorated before proceeding with other work.

1. Test wet areas for moisture content by suitable means wherever there is possibility that

exposed insulation work has acquired moisture in excess of the maximum content for optimum application of roofing.

C. At the end of the work day the water cut-offs shall be made by extending the membrane

beyond the insulation and setting the end of the membrane in adhesive or of a type of termination as recommended by the roofing membrane manufacturer. 1. It is imperative that the water cut-offs be completely sealed to prevent any water

infiltration into the building structure due to the sensitivity of some equipment that is housed in each facility.

a. The Contractor will be held fully responsible for all associated costs for failure to

ensure infiltration of water into structure.

2. All temporary water cut-offs shall be removed prior to proceeding with the next work period by cutting off that portion of the membrane that has been in contact with adhesive and disposing of it.

3.07. ADJUST AND CLEAN

A. Carefully inspect all completed work, and correct all defects.

B. Clean up foam adhesive overspray, mastic spills and spattering along with removing surplus

materials from job site. C. Provide adequate protection of completed work until substantial completion. Prevent traffic,

storage or movement of equipment on completed roofing or existing roof.

D. Clean up all debris, surplus materials, tools and equipment, and remove from site. Leave the roof surface and all work areas in a clean condition.

1. Provide clean-up of all work as previously described around building on a daily basis

to keep site clean and uncluttered due to construction operations. END 07 54 23

Page 32: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

07 54 23 -12

This Page Left Blank

Page 33: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

07 62 00 - 1

DIVISION 7 - THERMAL & MOISTURE PROTECTION Section 07 62 00 - Sheet Metal Flashing & Trim

1. GENERAL

1.01. WORK INCLUDES

A. Base Bid:

1. General Contractor: Provide all labor, materials, equipment and services necessary to the furnishing and installation and reinstallation of all flashing, sheet metal, metal edge fascia system and accessories, complete, in place as shown on the drawings and specified herein and needed for a complete and proper installation. Refer to drawings for specific locations of materials and products.

1.02. RELATED WORK

A. Specified elsewhere:

1. 01 60 00 - Product Requirements. 2. 02 41 19 - Selective Demolition. 3. 06 10 53 – Miscellaneous Rough Carpentry. 4. 07 54 23 – Elastomeric Membrane Roofing (EPDM). 5. 07 92 00 – Joint Sealants.

1.03. QUALITY ASSURANCE

A. Referenced catalogs: The catalogs, current as of date of bidding documents, of the

manufacturer's specified are incorporated herein by reference. 1.04. SUBMITTALS:

A. Shop drawings: Submit shop drawing showing, size, detail for construction, types, location of fasteners and recommended attachment.

B. Product data: Submit manufacturer’s product literature describing materials and installation

requirements for each product.

C. Samples: Submit color samples for the sheet metal. 1.05. DELIVERY, STORAGE AND HANDLING

A. Deliver materials to project site, with labels intact and legible, in sufficient time and quantity to

allow continuity of work and compliance with approved construction schedule.

B. Store all materials off ground on raised platforms and cover with weather tight protective coverings, if stored outdoors.

C. Handle materials carefully to prevent damage. Promptly remove damaged or defective

materials from site and replace with new, acceptable materials.

Page 34: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

07 62 00 – 2

1.06. PROJECT/SITE CONDITIONS

A. Prior to submitting a bid, each Bidder visit the site and thoroughly inspect the premises with plans and specifications in hand, whereas to fully inform themselves as to the scope of the work and all existing conditions, facilities, difficulties and restrictions affecting the execution and completion of the contracted work.

1. Failure to be so informed will not relieve the bidder, to whom the contract is awarded, from

the necessity of furnishing any and all materials and installation requirements that may be required, in strict accordance with drawings and specifications, and without any additional costs.

1.07. SEQUENCING/SCHEDULING

A. Schedule and coordinate the installation of all sheet metal work with membrane roofing

work. Sheet metal work shall follow immediately as roof areas are completed. 1.08. PROTECTION

A. Protect work and EPDM Membrane from damage during installation of sheet metal work.

Contractor shall be responsible for cost of all repairs or replacements required as a result of any damages due to such lack of protection.

1. Where sheet metal abuts into adjacent dissimilar materials or receives drainage from

dissimilar metals, the junctures shall be executed in a manner to prevent electrolysis, or the metal shall be coated as required to prevent electrolysis.

1.09 WARRANTY

A. General Contractor: Two years.

B. Manufacturer’s standard minimum 20 year warranty against color fade, chalking and performance of coating finish film integrity.

2. PRODUCTS

2.01. Materials shall be of types as indicated on drawings.

A. All materials and products as specified in this section shall be either supplied by or

acceptable to the roofing system manufacturer as specified in Section 07 54 23. All warranties herein specified shall apply.

1. The anchor bar to be an extruded 6063-T6 alloy aluminum, pre-slotted at 12" o.c. along

primary fastening line and 24" o.c. along secondary fastening line. Corner miters seams shall be factory welded and watertight.

B. Metal fascia system: The system shall consist of anchor bars, fasteners and fascia cover

system with a height as indicated on the drawings and as follows:

Page 35: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

07 62 00 -3

2. Fasteners shall be corrosion-resistant wood screws with hexagonal heads bonded washers

with EPDM washer seal. Size of fasteners as per manufacturer’s requirements. 3. Sheet metal shall be thickness as called for on the drawings. Covers shall have a Kynar

finish. Fascia cover shall have a protective film covering for removal after installation. Fascia covers shall be given a 70% high performance PPG “Duranar”, Valspar “Fluropon”, BASF “Fluoroceran” or Akzo Nobel “Trinar” coating finish containing Kynar 500 resin to conform to AAMA Specifications 605. Color to be selected by ISU.

4. Provide all accessories and other miscellaneous components as detailed on drawings.

C. Bituminous paint for separating dissimilar metals shall be: 1. Acceptable manufacturers and products:

Manufacturer Product

a. b.

BASF Corp. Building Systems, Sonneborn Bldg. Products Div., Shakopee, MN (800) 433-9517 Tnemec Co., Inc., Kansas City, MO (816) 483-3400

Hydrocide

Asphalt Base Coating c. W.R. Meadows, Inc., Elgin, IL (800) 342-5976 Sealmastic

D. Provide accessories, including discs, screws, bolts, nuts, washers, rivets, expansion devices

and splice plates. Metal fasteners and accessories shall be compatible with or of same metal and finish as flashings.

E. Sealants shall be either a one-part or two-part urethane rubber sealant in full compliance with

Specification Section 07 92 00. 1. Provided pourable sealant as per the requirements and by the EPDM roofing system

manufacturer. 2.02. FABRICATION AND MANUFACTURE

A. Contractor shall carefully examine the drawings and specifications of the other trades and shall

carefully coordinate the work of this section with the work of the other trades.

B. Before fabricating sheet metal, verify shapes and dimensions of surfaces to be covered by making and recording all field measurements.

C. All sheet metal work shall comply with the details and recommendations of the SMACNA

“Architectural Sheet Metal Manual”. E. Contractor shall furnish and install all accessories or other items, whether or not specifically

shown or specified, that are essential to the completeness of the work included in this section. All such items shall be of the same kind of materials, quality and weight as other similar materials and shall conform to the standards referenced in this section.

F. Fabricate and install sheet metal with lines, arises, angles sharp and true, and plane surfaces free from objectionable wave, warp or buckle. Exposed edges of sheet metal shall be folded back to form a ½" wide hem on the side concealed from view. Finished work shall be free from water leakage under all weather conditions. The workmanship and methods employed for forming, anchoring, cleating and the expansion and contraction of sheet metal work shall be as detailed on the drawings and specified herein.

Page 36: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

07 62 00 – 4

G. Provide provisions for expansion and contraction of the sheet metal work at intervals indicated

on the drawings and when not indicated as required to relieve damaging stress in the sheet metal in compliance with SMACNA.

H. Lapped sections of exposed sheet metal work shall be made with lock seams, clevis seams or

welded seams, whichever is appropriate, or as detailed on the drawings.

1. Lapped sections of exposed sheet metal work mechanically attached by screws or which depend on roofing cement or sealant for attachment are not acceptable.

3. EXECUTION

3.01. INSPECTION

A. Surfaces to which flashing and sheet metal work will be applied shall be even, smooth, sound,

thoroughly clean and dry and free from projecting nail heads or other defects that would affect the application. Make all corrections so that all surfaces are in an acceptable condition to the Contractor prior to receiving the sheet metal work.

1. Application and installation of the sheet metal work will be considered as evidence of

acceptance of the surfaces to which sheet metal is to be applied.

B. Proceed with flashing and sheet metal work when curb, blocking and other construction to receive the work is complete, sound, dry, clean and free of defects.

3.02. PREPARATION

A. Schedule and coordinate sheet metal installation with the work to avoid delays to

construction progress.

B. Where sheet metal is in contact with concrete or dissimilar metals, the sheet metal contact surface shall be protected with a heavy coating of bituminous paint, or the surfaces shall be separated with a layer of membrane.

C. Where water can flow across dissimilar metals, drainage shall be arranged to minimize the

possibility of galvanic action. 3.03. INSTALLATION/APPLICATION/PERFORMANCE

A. SMACNA details: Except as otherwise shown or specified, comply with applicable

recommendations and details of the “Architectural Sheet Metal Manual” by SMACNA.

B. Except as otherwise shown or specified, comply with recommendations and instructions of manufacturer of flashing and sheet metal work, along with EPDM membrane manufacturer being installed.

C. All sheet metal work shall be water and weather tight, free from defects which impair strength

or mar appearance. Conceal fasteners and expansion provisions wherever possible in exposed work and locate to eliminate the possibility of leakage.

1. Refer to the drawings for miscellaneous configurations of sheet metal work.

Page 37: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

07 62 00 – 5

D. Sealants shall be used in strict accordance with the sealant manufacturer’s specifications. Joints to be sealed shall be sound, dry and free of laitance, loose surfaces and contaminates that adversely affect adhesion. Bond breakers and back-up materials shall conform to the requirements of Specification Section 07920.

3.04. ADJUST AND CLEAN

A. Examine complete work for damage and remove damaged pieces and replace with new,

acceptable material meeting the requirements of the specifications.

B. Remove all scrap and debris and dispose of off-site; leave all work areas clean.

END 07 62 00

Page 38: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

07 62 00 – 4

This Page Left Blank

Page 39: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

07 92 00-1

DIVISION 7 - THERMAL & MOISTURE PROTECTION Section 07 92 00 – Joint Sealants

1. GENERAL

1. 01. WORK INCLUDES

A. Base Bid:

1. General Contractor shall provide all labor, materials, equipment and services necessary to the furnishing and installation of all sealing and calking of joints, including joint fillers and accessories, as shown on the drawings, herein specified and needed for a complete and proper installation.

1. 02. RELATED WORK

A. Specified elsewhere:

1. 01 60 00 - Product Requirements. 2. 07 62 00 - Sheet Metal Flashing & Trim.

1. 03. QUALITY ASSURANCE

A. Employ only experienced craftsmen skilled in the installation of specified products.

1. 04. REFERENCES

A. The acceptable manufacturer’s catalogs, current at date of bidding documents, are

incorporated by reference to the same force and effect as if repeated herein at length. 1. 05. SUBMITTALS

A. In accordance with 01 60 00:

1. Product data:

a. Materials’ description. b. Manufacturer’s current printed installation instructions for each product.

2. Samples:

a. Color charts: 3 samples.

1. 06. DELIVERY, STORAGE & HANDLING

A. Deliver all products in manufacturer’s original containers with seals unbroken, labels, product

and manufacturers’ names intact and legible.

B. Store all products in a manner to prevent damage in a secure place out of way of construction operations. Provide protection until ready for use.

C. Handle in accord with manufacturer’s recommendations.

Page 40: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

07 92 00-2

1. 07. PROJECT/SITE CONDITIONS

A. Environmental conditions:

1. Weather: Do not install products during adverse weather conditions. 2. Temperature: Ensure that surface and ambient temperatures are within the range

recommended by the manufacturer. 1. 08. SEQUENCING/SCHEDULING

A. Coordinate installation of materials with other trades whose work may be affected or have

effect. 1. 09. WARRANTY.

A. General Contractor: Two years.

2. PRODUCTS

2. 01. ACCEPTABLE MANUFACTURERS

A. Use only the specified products of the following manufacturers:

CODE MANUFACTURER

1. DOW - DOW Chemical Co., Midland, MI. 2. MEAD - W. R. Meadows, Inc., Elgin, IL. 3. PECO - Pecora Chemical Corp., Harleysville, PA. 4. PRCC - Products Research & Chemical Corp., Gloucester City, NJ. 5. SIKA - Sika Chemical Corp., Lyndhurst, NJ. 6. SON - Contech, Inc., Sonneborn Building Products Div., Minneapolis, MN. 7. SUR - Surebond, Inc., Elk Grove Village, IL. 8. S-W - The Sherwin-Williams Co., Cleveland, OH. 9. WIL - Williams Products, Inc., Troy, MI.

2.02. SEALANTS

A. Type:

1. S-1: One component urethane, non-sag, gun grade elastomeric sealant. Use in all joints

one-inch wide or less wherever movement may occur at metal to metal and sheet metal to masonry/stone. Color shall match adjacent metal finish color.

B. Acceptable products:

MFGR/TYPE S-1

1.

PECO

Dynatrol I 2. PRCC Permapol RC1 3. SIKA Sikaflex 15LM 4. SON Sonalastic NPI

Page 41: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

07 92 00-3

5. SUR SB 188 6. S-W Stampede -1 7. WIL Dynaseal W-100

2.03. JOINT FILLERS

A. Type:

1. JF-1: Backer rod for elastomeric sealants. Extruded closed-cell polyethylene foam or polyethylene jacketed polyurethane foam, non-bleeding, non-staining, oversized 30 to 50 percent.

B. Acceptable products:

MFGR/TYPE JF-1

1. DOW Ethafoam 2. MEAD Backer Rod 3. SON Sonofoam Backer Rod 4. WIL Expand-O-Foam Cord

2.04. JOINT CLEANER

A. Type recommended by the manufacturer of the sealing compound for the specific joint surface

and condition. 2.05. BOND BREAKER

A. Polyethylene tape: Pressure sensitive as recommended by sealant manufacturer to suit

application. 3. EXECUTION

3.01. REMOVE EXISTING CONSTRUCTION

A. Completely remove all existing sealants, calking, joint fillers and other accessory items when

encountered or as necessary for the proper installation of new sealants. B. Pourable sealant pockets: install pourable sealant as per EPDM roofing manufacturer’s

recommendations. 3.02. INSPECTION

A. Thoroughly inspect all existing construction and the conditions under which the work will be

performed.

B. Verify that all joint dimensions are in accord with manufacturer’s recommendations.

C. Start of work constitutes acceptance of construction and conditions.

3.03. PREPARATION

A. Clean, prepare and size joints in accord with manufacturer’s instructions. Remove all loose materials and other foreign matter which might impair adhesion of sealant.

Page 42: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

07 92 00 - 4

3.04. INSTALLATION

A. Install with sealant as per manufacturer’s printed instructions.

B. Install bond breaker tape wherever recommended by manufacturer to ensure that elastomeric sealants will perform properly.

C. Install sealant backer rod for liquid elastomeric sealants.

D. Install sealants in uniform, continuous ribbons, without gaps or air pockets. Ensure complete

“wetting” of the joints. Bond surfaces equally on opposite sides. Fill sealant rabbet to a slightly concave surface, slightly below adjoining surfaces.

E. Install sealants to depths shown; when not shown, within the following limitations:

1. For normal moving joints sealed with elastomeric sealants, fill joints to a depth equal to

50% of joint width but not more than ½" deep or less than ¼" deep.

F. Spillage: Do not allow sealants or compounds to overflow or spill onto adjoining surfaces. 3.05. CURING

A. Cure sealant compounds in compliance with manufacturer’s instructions to obtain high early

bond strength, internal cohesive strength and surface durability. 3.06. ADJUST AND CLEAN

A. Upon completion, carefully examine all sealant work. Remove all damaged and defective

work, and replace with new materials.

B. Clean up and remove all surplus products, containers and rubbish, and dispose of offsite.

C. Remove spilled or spattered materials from all surfaces. When adjacent surfaces or other work has been damaged or stained as a result of sealing work, repair all damages, and remove all stains to the satisfaction of the ISU’s PM.

3.07. PROTECTION

A. Protect installed work during remainder of construction period. Ensure that it will be without

damage or deterioration at substantial completion. END 07 92 0

Page 43: 16.12.12 - CVA Rotunda Specifications Div 1 thru 16

Recommended