+ All Categories
Home > Documents > 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver...

170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver...

Date post: 07-Apr-2018
Category:
Upload: lamthuan
View: 219 times
Download: 6 times
Share this document with a friend
40
Welcome speech The Honourable Jackie Trad, Deputy Premier
Transcript
Page 1: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

Welcome speechThe Honourable Jackie Trad, Deputy Premier

Page 2: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

A region wide transformationMr Graeme Newton, CEO

Page 3: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

Most intense population growth

Estimated SEQ population by 2036 – 4.9m

Page 4: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

Most intense population growth

Most intense employment growth

Estimated SEQ population by 2036 – 4.9m

Page 5: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

Taking a closer look at our CBD…

Page 6: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

Taking a closer look at our CBD…

Page 7: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

Taking a closer look at our CBD…

Page 8: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

Taking a closer look at our CBD…

Page 9: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

Anticipated commercial growth…

Page 10: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

RBWH

PAH

Mater

UQ

QUT

Griffith

Knowledge & health precincts…

CSIRO

Page 11: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

QWB

Suncorp

Gabba

RNA

Riverstage

South Bank

Leisure & entertainment…

Page 12: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

Growing our city centre from an area like this…

Page 13: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

To an area more like this…

Page 14: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

And at each precinct…

Page 15: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

And at each precinct…

Page 16: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

And at each precinct…

Page 17: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

And at each precinct…

Page 18: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

And at each precinct…

Page 19: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

Coming next

Technical project overview Alex de Aboitiz, Technical Advisor – Arup

Packaging, Procurement & Commercial Jason Malouf, Project Development Director – CRRDA

Page 20: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

Technical project overviewMr Alex de Aboitiz, Lead Technical Advisor

Page 21: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

DRAFT FOR DISCUSSION

21

Reference design alignment

Page 22: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

Packaging & procurementMr Jason Malouf, Project Development Director

Page 23: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

DRAFT FOR DISCUSSION

23

Cross River Rail - works packaging

The CRR Project comprises two major packages of work, a tunnel, stations and development PPP and a rail, integration and systems alliance

OVERVIEW

Salisbury Woolloongabba Albert St Roma St Exhibition Mayne Yard

Boggo RdDutton Park

Property Development(Exhibition)

Property Development

(Boggo Road)Property Development

(Woolloongabba)Property Development

(Roma St)

Tunnel, Stations &Development PPP Rail, Integration & Systems alliance

Early works

Southern portal

surface works

StationStation Station StationUpgrade UpgradeUpgrades

OSD

Surface works

Underground works

Page 24: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

DRAFT FOR DISCUSSION

24

Early worksTargeted early works will be undertaken in preparation for construction commencement with works already underway at Woolloongabba

OVERVIEW

EARLY WORKS – SCOPE

Works at Woolloongabba being prioritised to support major tunnelling operations from this site

• Woolloongabba

‒ Demolition of Goprint building

‒ Demolition of Landcentre building

‒ High-voltage power supply

• Roma Street

‒ Temporary coach terminal

Page 25: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

DRAFT FOR DISCUSSION

25

Tunnel, Stations & Development PPP – scope

PPP PACKAGE

The PPP Package includes underground elements of the Project, Over Station Development at Albert Street and ‘brownfield’ rail surface works in the southern area

OVERVIEW

• Tunnel and Stations

‒ Tunnel, underground stations, station access and associated mechanical, electrical and safety systems‒ Northern and southern dive structures and portals‒ Installation of selected works (e.g. track and traction power, certain signalling and communications

works)‒ Southern area ‘brownfield’ rail surface works, including installation of rail systems ‒ In-station retail at underground stations, plus above-ground retail plaza at Roma Street

• Station precinct connectivity and public realm

• Asset maintenance and facilities management (20-30 years)

‒ Tunnel and stations • Commercial development

‒ Delivery of a co-timed over station development at Albert St• Debt and equity financing

Page 26: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

DRAFT FOR DISCUSSION

26

Tunnel, Stations & Development PPP – work areas

The PPP Package will primarily deliver works in the tunnel areaOVERVIEW

Salisbury Woolloongabba Albert St Roma St Exhibition Mayne Yard

Boggo RdDutton Park

Tunnel

Station

Returned works to QR, State and BCC

Station Station Station

Asset Maintenance and Facilities Management Services(Tunnel & Stations)

F2S Southern area Northern areaTunnel MayneWORK AREAS

OSD

Page 27: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

DRAFT FOR DISCUSSION

27

Tunnel, Stations & Development PPP – Albert Street In addition to station precinct connectivity and public realm, CRRDA has a strong preference for the PPP consortium to deliver an integrated, co-timed over station development at Albert Street

OVERVIEW

LOCATION OF OSD (LOT 2) ALBERT ST

PPP consortia to propose use for Lot 1

Page 28: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

DRAFT FOR DISCUSSION

28

Tunnel, Stations & Development PPP – Albert Street

The figure below is an artistic impression of the ‘green spine’ along Albert Street in the vicinity of station entrances

OVERVIEW

Page 29: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

DRAFT FOR DISCUSSION

29

Rail, Integration & Systems alliance – scope

The alliance package will deliver rail systems and surface works as well as integration of the project into the QR network

OVERVIEW

RELATED PROJECTS

A single ETCS provider will be

procured separately by

Queensland Rail, including CRR

scope

ALLIANCE PACKAGE

• Rail civil and electrical works‒ Signalling civil assets, track systems, LV power systems, civil and structural

assets and systems, other (incl. utility assets & systems, HV cabling and OHLE)

• Rail operational systems works ‒ Security systems, passenger information systems, control systems, platform

screen doors• Rail signalling and communications works

‒ Conventional signalling works, and communications • CRR-ETCS works

‒ ETCS L2 trackside equipment, data radio, fixed telecoms• Integration and commissioning activities

‒ Includes the testing, integration and commissioning in relation to the RIS works; and managing and coordinating integration & commissioning activities for other CRR works

ETCS inner city project

Page 30: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

DRAFT FOR DISCUSSION

30

Rail, Integration & Systems alliance – work areasWhile the focus of the alliance construction works is in the brownfield areas, the integration and commissioning responsibilities will be for the project as a whole

OVERVIEW

Salisbury Woolloongabba Albert St Roma St Exhibition Mayne Yard

Boggo RdDutton Park

Integration & Commissioning Activities

Rail Operational Systems

Rail Signalling and Comms

Rail Civil and Electrical Works

CRR-ETCS Works

Mayne Yard

F2S Southern Area Northern AreaTunnel MayneWORK AREAS

Page 31: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

DRAFT FOR DISCUSSION

31

TimelineThe procurement will commence with a registration for EOI of 5 September for the PPP (TSD) and 19 September for the alliance (RIS).

OVERVIEW

30 AugIndustry Briefing

5 Sepregistration

for EOI

19 Sepregistration

for EOI

Late Sepinvitation for EOI

Mid NovEOI

responses

Mid-late Sepinvitation for EOI

Mid Nov EOI

responses

EOI shortlisting and RFP release

EOI shortlisting and RFP release

TIMELINE TO EARLY 2018:

August September October November December January/February

Delivery

DeliveryRFPEOI

2017 2018 2019

EOI Alliance Development

TSD

RIS

TSD

RIS

~~

~

Page 32: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

DRAFT FOR DISCUSSION

• Up to 3 respondents shortlisted for the TSD PPP package• 2 respondents shortlisted for the RIS alliance development phase

32

EOI processThe EOI process will identify respondents with the best capability, capacity and track record to successfully deliver the CRR project.

OVERVIEW

• Key contact information

• Business overview

• General capability and experience relevant to the project / package

• Execution of deed poll –confidentiality and non-reliance

REGISTRATION REQUIREMENTS

• Mandatory requirements

• Evaluation criteria

• Comments on the commercial principles

• Feedback on selected key project issues

EOI RESPONSES

Bid costs

EOI Shortlisting

CRRDA recognises the importance of well developed bids and has a clear intention to make a significant financial contribution to the RFP phase bid costs of unsuccessful bidders, in return for conforming offers and IP rights

Page 33: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

CommercialMr Jason Malouf, Project Development Director

Page 34: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

DRAFT FOR DISCUSSION

34

Project contractual framework

CRRDA will be the state representative entering into primary agreements for each CRR package

OVERVIEW

QR Project Agreement

Cooperation

PPP Alliance

Project Agreement Project Alliance Agreement

Interface and Commissioning

Over Station Development

State Works AgreementCommercial

Development Agreement

The State(through CRRDA)

Tunnel, Stations and Development

Rail, Integration and Systems

Queensland Rail

Page 35: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

DRAFT FOR DISCUSSION

35

Tunnel, Stations and Development PPP – contract structurePPP contractual framework is expected to include an availability-based PPP project agreement, a state works agreement and a commercial development agreement over Albert Street

OVERVIEW

Project Co

Project Agreement

The State(through CRRDA)

Dev Co

State Works AgreementCommercial Development Agreement

D&C Contractor D&C Contractor

Interface Agreement

Commercial Development

D&C Contract D&C Contract

Debt / Equity

Finance Documents

Debt / Equity

Finance Documents

Tunnel and Stations

Payment arrangements for the tunnel and stations

will include significant capital contributions from

the State

Page 36: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

DRAFT FOR DISCUSSION

PPP availability payments

36

Government contribution model

Final acceptance (“FA”)

Financial close

Provisional acceptance (“PA”)

DESIGN & CONSTRUCTION PERIOD BETWEEN PA & FA OPERATIONS ~

State contributions during construction

~50%Further state

contribution payment at (or after) PA

The TSD package is expected to include government contributions during the D&C phase with the potential for further payments at (or after) provisional acceptance

OVERVIEW

Page 37: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

DRAFT FOR DISCUSSION

• Queensland Rail as alliance participant• ETCS L2 signalling supplier procured separately by Queensland Rail• Queensland Rail as RTO will retain reserved matters including rail safety, ONRSR accreditation and

network operational issues • Contribution to reasonable external costs incurred during the alliance development phase

37

Rail, Integration & Systems alliance – contract structure

Alliance will be based on a price competitive (dual TOC) process OVERVIEW

The State(through CRRDA)

(Owner Participant)

Alliance Development Phase

Shortlisted RIS

Respondent 2

Alliance Development

Agreement

Alliance Development

Agreement

Shortlisted RIS

Respondent 1

NOP(s)

NOP(s)

RIS ALLIANCE

Delivery Phase

The State(through CRRDA)

(Owner Participant)

Project Alliance

Agreement

Queensland Rail

(Participant)

RIS Contract Award

NOP Core capabilities

Integrator Construction

Design Systems

RIS alliance is expected to

involve:

Page 38: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

DRAFT FOR DISCUSSION

38

Probity

CRRDA is committed to a fair and equitable procurement processOVERVIEW

Bid RequirementsRespondents and CRRDA advisors or QRfull confidentiality and exclusivity

TSD & RIS cross-package participationseparate teams and probity deed requirements

Respondents and ETCS inner city participationseparation and probity deed requirements

CRRDA AdvisorsARUP, TechnicalKPMG, Commercial and financialClayton Utz, LegalCorview, Transaction process

CRRDA ContactsProbity [email protected]

TransactionTSD –[email protected][email protected]

CRRDA require strict adherence toprobity and communication protocols

Page 39: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

An industry perspectiveMr Steve Abson, CEO – Infrastructure Association of Queensland

Page 40: 170830 Industry Briefing Presentation Combined Slide Deck ... · The alliance package will deliver rail systems and surface works as well as integration ... Integrator Construction

Questions:[email protected]


Recommended