Date post: | 18-Jan-2016 |
Category: |
Documents |
Upload: | hilda-hunt |
View: | 221 times |
Download: | 0 times |
18-Nov-98
W.A. Zajc
IntroductionIntroduction
PHENIX TAC Follow-up Meeting
18-Nov-98
W.A. Zajc
OutlineOutline
Results of Aug-98 TAC
PHENIX response to same
Purpose of this mini-TAC
PHENIX Status
18-Nov-98
W.A. Zajc
Aug-98 TACAug-98 TAC Focussed specifically on
the overall plan to complete PHENIX the installation and commissioning
schedules related cost issues
Findings Substantial progress since the May 1997
review (all sub-systems) Mechanical construction of baseline
detector components is proceeding well. Rate of progress on the Front End
Electronics systems continues to improve, although, as noted in the June mini-review, “progress must continue to accelerate in order for completion in time for the Engineering Run and Day-One physics.”
Schedules remain tight The collaboration’s management has
done a good job of maintaining an integrated plan for installation and commissioning which provides some flexibility for schedule changes and for optimizing the physics capability at “Day-One”.
18-Nov-98
W.A. Zajc
Aug-98 TAC Aug-98 TAC (Cont’d)(Cont’d)
Findings (Continued) Despite good progress, the
aggressive scheduling goals given a year ago have, in most cases, not been met.
Major concern is with the continuing increase in the cost of PHENIX
Required deferral of $3.6M of readout and DAQ
TAC estimated probable shortfall in excess of $5M
Recommendations: PHENIX and RHIC project
management, BNL management, and DOE should develop a plan that
Deals with the probable shortfall. Addresses probable shortfalls in AEE
funds for Muon Arm construction. In PHENIX project management is
strongly encouraged to look at the possibility of permanently descoping subsystems of the detector.
18-Nov-98
W.A. Zajc
Task ForcesTask Forces
Convened to address a specific problem
Members: A representative selection of
interested parties Avoidance of affected line managers
Process: Intensive study of status, schedule,
finances Report to management on same plus
explicit recommendations for action Duration of ~ 1 month Conclusions considered (in turn) by
Project Management Executive Council Detector Council Collaboration (Town Meeting) Project Management
End Result:A complete analysis of available options
by all elements of the collaboration
18-Nov-98
W.A. Zajc
Baseline Task Baseline Task ForceForce
Charge-- produce a plan which: Allows us to finish the Year-1 detector
on the funds available in FY99; Defines a scope that can be completed
within 3 years of the end of the Baseline construction project.
Preserves the broad, unique physics program attainable in Year-1 and long-term.
Chair: Hans-Ake Gustafsson Members:
Y. Akiba, B. Cole, T. Hemmick, J. Mitchell and R. Seto.
Outcome: A plan which
Reduces mortgage substantially by combination of deferrals and descoping
Preserves most of initial physics capability
(Details in H-A. Gustafsson’s presentation)
A recommendation that similar task force examine Muon systems.
18-Nov-98
W.A. Zajc
Muon Task Muon Task ForceForce
Charge:1. Review present scope and
technical/cost/schedule status of the muon system.
2. Make recommendations on a Plan-to-Complete for the system that
a. Can be completed within the remaining AEE and RIKEN funds;
b. Can provide muon measurements at some point in the first year of RHIC operations and spin physics data during the second year of RHIC operations.
c. Describes any deferrals and/or descoping necessary to obtain Items 2a and 2b.
d. Allows those deferred items to be built and installed within 3 years from the end of construction.
Chair: Soren Sorensen Members:
T. Awes, C.Y. Chi, A. Drees, M. Leitch, E. O'Brien, S. Pate, N. Saito
Outcome: A complete review of PHENIX muons
Physics Status Schedule Finances
Detailed discussion of two schemes for mortgage reduction
18-Nov-98
W.A. Zajc
This Follow-UpThis Follow-Up
Purpose: To evaluate the overall PHENIX
plan to complete the construction and commissioning of the detector
Assess our plan to deal with the funding deficits projected for PHENIX in a way that does not incur an unrealistically large mortgage against future funding
Specifically: Is the plan technically feasible,
and consistent with the RHIC End-Game and startup schedules? Are the estimated costs-to-complete realistic?
What are the compromises in physics capability?
Is the plan to recover deferred costs acceptable?
18-Nov-98
W.A. Zajc
TremendousTremendous progress since last year.
Infrastructure:
Experiment Experiment StatusStatus
~TAC97
~TAC98(-5 months)
18-Nov-98
W.A. Zajc
TremendousTremendous progress continues in the hall:
All EmCal, RHIC mounted on West Arm
Surveying indicates positioned to < 1 mm of design location
Choreography underway now
Experiment Experiment StatusStatus
18-Nov-98
W.A. Zajc
Experiment Experiment StatusStatus
TremendousTremendous progress since last TAC:
muID Installation complete 15-Sep-98
18-Nov-98
W.A. Zajc
MagnetMagnet
Central Arm: Mapping in progress Primary goal:
Evaluate performance of the field reconstruction software before the production mapping starts at the end of November.
Question: Green’s functions (MIT) vs. finite element (Efremov)
Great opportunity for (dedicated) student contributions
MMS: Tested at full field Began fixture assembly
MMN: Fixture installed
18-Nov-98
W.A. Zajc
Status (Cont’d)Status (Cont’d) MVD
QA First 14 Si Pads MCM output cables 24 Evaluation MCM’s (LockMart)
Clean room prepared at BNL Working PC MCM
DC Started production-line testing and insertion of
wire modules into the first Drift Chamber. Orders placed for some production-level items Received first production modules for the DC
FEM. TOF
9 of 10 panels complete (at BNL) BB
Detector at BNL Prototype board done
L1 Testing complete on GL1-1, Clock and Accept,
6Rx boards GL1-2 Board, fabricated, assembled and under
test GL1-3 board ready for fab
18-Nov-98
W.A. Zajc
PCPC
Have a PC1 and a PC3 prototype
Position dependence of gains measured, certified as acceptable
Encouraging efficiency studies with full FEM readout
PC1 efficiency studies with cosmics:
18-Nov-98
W.A. Zajc
TECTEC Details:
11 chambers mechanically complete
Work started on #19 First 64 channel FEM board
Stuffed Test pulses read out in VME
Good progress on grounding studies
Summary: Sector 3: frame assembly
started Sector 2: winding Sector 1: Cosmics!
18-Nov-98
W.A. Zajc
EmCalEmCal PbSc:
All four sectors mounted on West Arm:
All six have completed internal cabling
Laser testing in progress PbGl:
Completed enclosures on Sector 1 Prepared test system for LED/PMT’s
18-Nov-98
W.A. Zajc
MuonsMuons muTR
Encouraging bids on Station 3 honeycomb, FR-4
Continued tests with wire-laying boom on mock panels
First final south frames from BARC arrived, found satisfactory
All drawings for the south arm detectors are complete and procurement ready.
Simplifications in FEE Grounding and LV distribution Timing distribution
Muon ID Gas system specs written completed basic testing of
all installed small MuID panels 21 out of 40 large panels in situ
with very good results.
18-Nov-98
W.A. Zajc
DAQDAQ
DCM’s All FE1, FE2 cards stuffed, tested Two full DCM’s fabbed, tested
before full production
EvB Version 1 of all component
classes (SEB, EvB controller, ATP) written
2 x 2 EvB working in hardware
Collect the Data!
Collect the Data!
Collect the Data!
18-Nov-98
W.A. Zajc
OfflineOffline
“MDC 1 happened”: Transferred 500 GB of simulated data into the new
HPSS storage hierarchy. Demonstrated sustained transfer rates of nearly 9
MB/sec. Successfully used RCF-developed reconstruction
control software to stage simulated data to nodes of the reconstruction farm and run PHENIX reconstruction software. The aggregate CPU power of the nodes used by PHENIX during MDC1 was equivalent to about 25,000 VAX-11/780's.
Developed several significant improvements in the RCF control software (job auto-submission, web-based monitoring tools) and fed these back to the RCF staff.
Upon completion, each reconstruction job updated an Objectivity production control database (using the RCF developed port of Objectivity to Linux).
At the start of each reconstruction job, geometry parameters for the drift chamber were read from an Objectivity-based calibration database (again, using the RCF port of Objectivity to Linux).
GEANT simulations of muon arm data were successfully converted into the PHENIX raw data format (this has since been done for the central arms too). The reconstruction of muon arm events used this realistic "raw" data as its starting point.
Used ORNL-developed tape access optimizing batch system to retrieve reconstructed data files from HPSS in an efficient way. This improved our effective bandwidth for reading DSTs by a factor of five.
18-Nov-98
W.A. Zajc
ComputingComputing
MDC: Proof-of-principle in
reconstructing from PRDF Some physics studies
underway from MDC DST’s Extensive “experience” with
Network problems Disk back-ups Disk space management
Very useful in development of analyses within Physics Working Groups
18-Nov-98
W.A. Zajc
PHENIX PhysicsPHENIX Physics
PHENIX provides unique insights into heavy ion collisions at RHICRoughly equal sensitivity to phenomena at all
time scales Initial conditions (hard scattering) Medium effects (vector mesons) Thermalization (photons) Final state (hadrons)
The same apparatus allows world-class measurements on the spin structure of the proton
We have endeavored to preserve as much of these capabilities as possible Initially (available in Day-1) Potentially (upon recovery of deferrals)
Descoping has however, affected our ability to Control systematics Preserve aperture and rate Trigger(!) A small shortfall has resulted in a large loss
Details in G.R. Young’s talk
18-Nov-98
W.A. Zajc
Baseline Baseline PriorityPriority
Essential for allocation of resources
Stated on 15-Sep-98 by PHENIX Management: The recently accepted
recommendations of the Gustafsson task force leave unchanged the PHENIX priority for the first year of running. Specifically, the highest priority for Year-1 remains the completion of the East Arm and its use for the Au-Au program outlined by the Day-1 Task Force last year.”
Note: Application of this (necessary) prioritization will put early pair physics at substantial risk
18-Nov-98
W.A. Zajc
Site ActivitySite Activity A tremendous
convergence of workat various sites around BNL outside the lab
18-Nov-98
W.A. Zajc
Progress Progress SummarySummary
10-Jan-98
24-Sep-98
20-Oct-98
09-Nov-98
Summary: Accelerating
progress that is indicative of
overall experimental
effort
18-Nov-98
W.A. Zajc
Collaboration Collaboration ViewView
The Task Forces (and subsequent discussion) have played an essential role in building consensus
The proposed descopings Baseline Task Force
Loss of TEC in West Arm Loss of PC2 in East Arm Loss of EmCal Trigger
Muon Task Force Loss of anode readout
have been viewed as “acceptable” risks. There is recognition that the SE&I costs are
necessary to build an infrastructure that is Safe Durable Flexible
But There is serious concern in the
collaboration that these costs jeopardize (at least) the successful implementation of the Baseline Task Force’s recommended plan.
18-Nov-98
W.A. Zajc
SummarySummary
Collaboration commitment?
Institutional resources used to provide 7% solutions
Yesterday:
35+ vehicles at PHENIX Experimental Hall
5+ tables in cafeteria(in spite of BSA-mandated
descopings/deferrals in service)
3+ examples of second-generation PHENIX-ians.
18-Nov-98
W.A. Zajc
SummarySummary
Purpose: To evaluate the overall
PHENIX plan to complete the construction and commissioning of the detector
We have a plan that projects our current status into an essential physics program for Year-1 (and beyond) at RHIC.
Assess our plan to deal with the funding deficits projected for PHENIX in a way that does not incur an unrealistically large mortgage against future funding
$1.4M on baseline $1.6M on muons
18-Nov-98
W.A. Zajc
Summary Summary (cont’d)(cont’d)
Specifically: Is the plan technically feasible, and
consistent with the RHIC End-Game and startup schedules?
Yes Are the estimated costs-to-complete
realistic? (Yes)
What are the compromises in physics capability?
Central arm pair physics at risk in Year-1 (West Arm robustness, schedule)
J/ physics at risk in Year-2 (!) (MMS schedule)
Central arm tracking efficiency (PC2 in East Arm)
Triggers for Spin High luminosity heavy ion operations
Is the plan to recover deferred costs acceptable?
(Yes) Help here is most appreciated!
18-Nov-98
W.A. Zajc
Forms of HelpForms of Help
Baseline:PC2 restoration in East Arm
~ $320K Restores East Arm to complete CDR
version (I.e., the best implementation of PHENIX central arms detectors we can build).
AEE Muons
$1000K profile relief Insures J/ physics in Year-2
High pT triggers and rare processes $1300K in Gelbke plan Leverages PHENIX bandwidth
capabilities Restores (otherwise descoped) EmCal
trigger
BNL Assistance in performing (and
supporting) essential SE&I activities in PHENIX Experimental Hall