Northumberland County Council – Technical Services
HB157290_ECMS_01 2
Document History
Job Number: HB157290 Document Ref: HB157290_ECMS_01
Version Status Date Originator Checked Authorised
1 Draft 06/03/2019 GAS RC PTS
Northumberland County Council – Technical Services
HB157290_ECMS_01 3
Contents
Section
1. Introduction 4
2. Proposed Method of Refurbishment 8
3. Environmental Management 13
4. Accident Plan 21
5. Complaints Procedure 26
6. Staff Competence and Training Records 28
7. Keeping Records 29
8. Reviewing the Management Plan 30
9. Appendix A – Supplementary Reports and Drawings 31
Northumberland County Council – Technical Services
HB157290_ECMS_01 4
1. Introduction
1.1. Overview
This Ecological Method Statement sets out the ecological requirements for the Main Works
during the delivery phase of the National Lottery Heritage Funded (NLHF) Union Chain Bridge:
Crossing borders, inspiring communities project.
Figure 1 - Union Chain Bridge Spanning the River Tweed
Figure 2 - Union Chain Bridge View from Scottish bank looking downstream
Northumberland County Council – Technical Services
HB157290_ECMS_01 5
1.2. Description of the project
Union Chain Bridge: Crossing borders, inspiring communities is an ambitious project involving
the conservation of the internationally significant historic Union Chain Bridge and an extensive
programme of public engagement. Co-owned by two local authorities, the Union Chain Bridge is
symbolic of this uniquely collaborative project that comprises of a partnership between
Northumberland County Council (NCC), Scottish Borders Council, Museums Northumberland
and supported by the Friends of the Union Chain Bridge.
Set in a beauty spot which was once a hive of engineering ingenuity, the Category A/Grade I
Listed Union Chain Bridge majestically spans the River Tweed. Completed in 1820, it was then
the longest chain suspension bridge in the world and heralded a new era in bridge building in
the UK. It was the first suspension bridge in Europe to carry wheeled traffic and remains the
oldest still in use worldwide. The innovative manufacturing and engineering techniques
employed on the Bridge were hugely influential in the development of suspension bridges
around the world.
Today, the engineering and technology skills gap is a huge problem for the UK. Reports show
that in short, nationally we need to buck the trend of dwindling STEM skills. This project affords
a unique opportunity to enthuse children and young people in engineering by using the world's
oldest vehicular chain link suspension bridge as a catalyst for change.
Union Chain Bridge is extraordinary, not only in an engineering sense, but owing to the social
context in which it was built. It unifies Scotland and England across the Tweed and as it was
constructed during the Radical War at a time of social unrest and uncertainty for the union, the
risk of the venture has much in common with our contemporary context. Drawing on the inequity
which sparked the Peterloo Massacre in 1819 and the Radical War in 1820, the historical
context can be utilised as a platform for understanding and making sense of contemporary
issues such as identity, workers’ rights, gender imbalance, economic drivers, access and
transition.
1.3. Project Vision
The project will forge stronger connections between border communities through the
conservation and celebration of the Union Chain Bridge. An ambitious public engagement and
Northumberland County Council – Technical Services
HB157290_ECMS_01 6
learning programme will provide exciting opportunities for people to explore its heritage, stories
and setting; raising aspirations in young people and inspiring a new generation of engineers.
1.4. Project Aims
To conserve and raise awareness of the internationally significant Union Chain Bridge,
and celebrate its historical and engineering importance
To provide impactful and sustainable STEM learning opportunities for young people
inspired by the innovative engineering of the Union Chain Bridge
To develop sustainable cross border heritage projects and partnerships between
communities and organisations in the Scottish Borders and Northumberland
To promote the rich heritage of the Union Chain Bridge, its nearby attractions and the
Tweed Corridor through a joint cross border approach.
1.5. Delivery Team Structure
Figure 3: Delivery Team Organogram
Northumberland County Council – Technical Services
HB157290_ECMS_01 7
1.6. Scope
This report details the works required to undertake conservation of Union Chain Bridge. Within
this, the overall main works are to be outlined, with potential ecological impacts identified.
Mitigation measures shall be implemented and vulnerable locations surrounding the works
identified. Finally, an accident plan is to be produced providing avoidance and mitigation
measures against potential risk. Through the Main Works Contractor liaising with the appointed
Project Manager from Northumberland County Council and all supervisors, all potential
ecological impacts can be negated or reduced to an acceptable level.
Northumberland County Council – Technical Services
HB157290_ECMS_01 8
2. Proposed Method of Refurbishment
2.1. Scheme Synopsis
The proposed method of construction will involve the complete removal of the entire bridge,
enabling off-site refurbishment. This method significantly reduces the amount of works required
to be carried out over and in the watercourse, reducing the ecological risk associated with the
proposals.
2.2. Main Works
Detailed discussions between all concerned parties for the works included a review of Health
and Safety, Environmental, Heritage, Quality, Stakeholder Impact, Programme, Cost, and Risk.
Resultantly, the final refurbishment option has been decided upon as the best approach to
conserve the bridge, ensuring its longevity and is outlined below
2.3. Duration of Works
The works are anticipated to last approximately 14 to 16 months from December 2019.
The current timetable for the works is as follows:
NLHF delivery round application planned for submission in May 2019 with a decision in
September 2019.
If successful in securing HLF funding, the delivery phase will commence in December
2019 and finish in April 2021.
The contract for the third party Main Contractor who will be undertaking the works will
be in place from December 2019.
2.4. Timing of the Works
Works within the watercourse will be carried out in the period between March and September,
to avoid the fish spawning season. No tree removal will take place on the site within the nesting
bird season, March to August inclusive, unless a suitably qualified and experienced ecologist
has confirmed the absence of active nests.
Northumberland County Council – Technical Services
HB157290_ECMS_01 9
2.5. Proposed Sequencing of Works
The Stages of construction should be read in conjunction with the following drawings:
HB157290-B-C02-TBT-02-0050 Proposed Reconstruction Sheet 1 of 4
HB157290-B-C02-TBT-02-0051 Proposed Reconstruction Sheet 2 of 4
HB157290-B-C02-TBT-02-0052 Proposed Reconstruction Sheet 3 of 4
HB157290-B-C02-TBT-02-0053 Proposed Reconstruction Sheet 4 of 4
Stage 1 - Site Establishment and Clearance
Creation of site compounds, fencing, road closures, removal of trees and vegetation in line with
the site clearance drawings.
Stage 2 - Removal of Wire Rope
Tirfors and temporary kentledge installed, tirfors are then connected to the wire rope and
associated hangers are cut and removed from site. The wire rope is then gradually lowered to
the ground using the tirfors and then cut into sections and removed from site.
Stage 3 - Installation of access – Unifloat system
The uni/linkfloat (pontoon) system involves the creation of a platform within the watercourse to
create a solid area for access underneath the bridge. The system comes in standard sections
that are connected in the watercourse. The pontoon can take loads in excess of what can be
carried by the bridge, which allows cranes and mobile elevated working platforms (MEWP’s) to
gain access to the bridge deck. Jack up legs lift the platform off the watercourse level to provide
stability, where units are manoeuvred into position via a small vessel. It is planned that
approximately 25m width of unifloat would be installed to provide access to as much of the
underside as possible. Please refer to attached datasheets of possible floating platform
systems.
Stage 3 - Removal of Handrail
The handrail will be removed and transported from site to be refurbished with suitable
temporary edge protection installed on the bridge.
Stage 4 - Full Removal of the Timber Deck & Hangers
Northumberland County Council – Technical Services
HB157290_ECMS_01 10
Using the unifloat system for access, a complete removal of the deck will be carried out working
from deck level and underneath the bridge. The full removal of the deck will allow for a
comprehensive assessment of the timbers to maximise the reuse of the timber elements. The
removal will start from the centre of the bridge and working towards the Scottish and English
sides.
Stage 5, 6 & 7 - Removal of the Chains
With the deck and hangers entirely removed, it is proposed that the chains are disconnected
and removed from site. This will be done by establishing temporary towers and winches on the
Scottish and English side of the bridge. The chains will be taken down in sections and stripped
and tagged before being blasted and painted in a controlled environment. Any repairs or
fabricated new elements will be undertaken following a full detailed examination of the chains
and linkages.
With the chains removed from the bridge, they are to be fully inspected to highlight all potential
defects. As all surfaces are visible, Non-Destructive Testing (NDT) can be undertaken on all
chains of the structure, highlighting further potential defects not apparent during visual
inspections. All defects highlighted, will be repaired fully, removing any ambiguity with the
condition of the chains enabling the 120 year design life to be achieved.
In addition, as the chains will be accessible within the site compounds, this provides learning
opportunities for the public. Schools and universities will be able to see up close the
composition of the chains, repair techniques and analyse the heritage of the elements. This
provides an insight into the structure that would not have been possible if any other proposed
construction technique was undertaken. The Main Works Contractor is to make an allowance
for these inspections.
Stage 8 - New Chain Anchorage Points
Following chain removal, the new anchor blocks and associated ground engineering will be
undertaken. Access from the top of the English tower shall be established to enable the ground
anchor works. Excavation of the existing Scottish anchorages shall enable piled foundations to
be installed.
Northumberland County Council – Technical Services
HB157290_ECMS_01 11
Inspection chambers are to be installed to both anchorage locations, enabling the continued
inspection of the anchorage systems which is currently not possible. This will enable all defects
within the anchorage systems to be identified within inspections, enabling effective maintenance
to be undertaken.
Stage 9 - Reinstallation of the Chains
Once the anchor blocks have reached sufficient strength, the chains will be reinstalled in the
same manner as they were removed. The temporary works will then be removed and masonry
works carried out.
The deconstruction and subsequent reconstruction activity is to mirror the same
techniques/principles that were used by Captain Samuel Brown during the original construction
of the bridge. As discussed in Stage 5, 6 & 7 - Removal of the Chains, it will provide a major
engagement activity for both worldwide industry involvement and STEM interaction, of which the
Main Works Contractor will be required to make allowance for.
Within this stage, the masonry repairs are to be undertaken to the English and Scottish Towers.
Following the inspection of the masonry by the Conservation Architect, repairs have been
specified throughout all faces. These include:
New / replacement stone to be inserted,
Mortar repairs to deeper crevices, striations or fissures,
Pointing of fissures,
Resin bond, grout cracks and pin loose sections of stone, repointing with lime mortar
following completion,
Deshale and inspect stones,
Remove existing mortar repairs and repaint with lime mortar,
Remove rendered brickwork and replace with stone.
Stage 10 - Reconstruction of the Deck and Hangers
Once the chains are reconnected to the new anchorages the new deck and hangers will be
reinstalled utilising the unifloat access.
Northumberland County Council – Technical Services
HB157290_ECMS_01 12
The deck flap is to be replaced like for like in accordance with the current composition of the
element. The current fixity of the deck flap cast into the concrete capping is to be inspected
following its removal to determine if it can be reused. The concrete capping will then be recast
and the new deck flap installed. In addition, shock transmission units are to be installed to
reduce the inertial response of the deck under load and wind effects.
Stage 11 - Installation of Handrail
The refurbished handrail and new section will be installed along the deck. Minor adjustments to
the hangers are to be undertaken to replicate the original camber of the walkway and
carriageway. This can be achieved through systematically fine tuning and adjusting the tension
within the hangers until the desired profile is achieved.
Stage 12 - Site Demobilisation and Approach Roads
Landscaping will be undertaken and the site demobilised. Landscaping to be undertaken
includes:
Relaying and realigning approach roads, with road markings applied,
Parking to the English and Scottish ends of the bridge to be formalised,
Pedestrian walkways and congregation areas to be formalised,
All interpretation works to be installed, including interpretation boards and statues,
Grass to be reseeded.
Northumberland County Council – Technical Services
HB157290_ECMS_01 13
3. Environmental Management
3.1. Environmental Issues
An extended Phase 1 Habitat Survey was undertaken by E3 Ecology to identify any protected
species on the site, or any habitat that has the potential to support any protected species.
Please refer to report “5490 Union Chain Bridge R02 – Ecological Appraisal and Bat Survey”
An environmental risk assessment process has been undertaken during the design process.
The risk assessment identified the following risks:
River in spate and sudden flash floods,
Potential collapse of the structure,
Invasive species,
Works within the watercourse,
Site and Tree Clearance
Protected species,
Damage to river bed,
Pollution of river by sediments and/or leachates from site operations,
Contamination of the river environment by plant and equipment.
Further risks identified during site operations will be placed on the Risk Register and managed
accordingly.
3.2. Ecological Clerk of Works
An Ecological Clerk of Works (ECow) will be employed for the construction period to provide
ongoing advice and support. The ECoW will have the following responsibilities:
Provide a tool box talk to site managers (Main Works Contractor, Site Operatives) on
the ecological sensitivities of the site.
Provide input into the site induction process such that it includes ecology as a topic.
Provide advice on and monitor the protection of sensitive and designated sites, habitats,
and protected species.
Monitor construction exclusion zones and construction methods in sensitive areas.
Northumberland County Council – Technical Services
HB157290_ECMS_01 14
Provide advice on construction methods where there may be conflicts between the
development and the environment.
Monitor the success of measures and provide feedback to the local authority.
Ensure that the Main Works Contractor conforms to wildlife legislation and best
practice.
Keep records on a fortnightly basis of site visits, incidents and near misses and
remedial action which has been taken.
3.3. Species Specific Method Statements
All works on site are to adhere to the following method statements which are included within the
Construction Environment Management Plan (CEMP) report, refer to Appendix A.1:
Badger Method Statement,
Otter Method Statement,
Reptile Method Statement,
Bat Method Statement,
Invasive Species Method Statement,
Fish Protection Method Statement.
3.4. High water levels
Weather forecasts and river levels are to be monitored on a daily basis. If the conditions
indicate that there is the likelihood of a flood event or adverse weather, work shall cease and all
plant, materials and equipment will be removed from the working area. Pontoon shall be
removed from the watercourse and placed in secure storage within site compound. Works shall
not recommence until weather conditions return to a suitable level, for example, during a
flooding event, works shall not begin until the river returns to its pre-flood levels.
3.5. Sediment Management Procedure
Sediment Control Methods
Control of sediment and filtration of water arising from the working areas is key to the successful
delivery of this scheme. The Main Works Contractor shall adopt the following measures at all
times during construction operations.
Northumberland County Council – Technical Services
HB157290_ECMS_01 15
Where appropriate hay bales/Sedimats/Geotextile will be installed downstream of the works
to trap any sediment released by site operations.
The mats will be renewed as necessary. Monitoring of the river downstream of works will
be undertaken to ensure there is no excessive sediment generated, works will be halted
until sufficient sediment has dispersed.
River rescue boats shall be in operation during pontoon works, and will be required to
capture any floating debris generated.
Floating booms shall be utilised where necessary
Floating Silt Screens and Turbidity barriers shall be utilised where necessary
3.6. Pollution Management Procedure
Spill kits shall be located with machines and working areas. Machines/plant shall not be
refuelled within 10m of the river bank and drip trays will be used when refuelling vehicles or on
stationary items. Mitigation measures listed below shall be implemented in the event of a spill or
leak:
1. Materials and equipment shall be placed within drip trips, and mobile bunded areas.
2. COSHH Sheets for all required materials shall be available onsite.
3. The source of the spill/leak shall be stemmed/stopped,
4. The spill shall be contained,
5. Absorbent pads or granules shall be used,
6. Used pads or granules shall be double bagged and sealed,
7. Sealed bags shall be deposited into a COSHH skip for disposal by a licenced contractor,
8. Relevant Statutory Body informed of the incident,
9. Relevant Cleaning Contractor informed of the incident.
3.7. Plant, Equipment and Materials Maintenance and Operation
Plant Control Methods
All plant and machinery which are required to work within the river (including the gravel shoals
or the dry riverbed) shall be sprayed thoroughly with a soluble disinfectant and then power
washed before first entering the river. This operation shall take place at least 50m away from
the river and the washings must not be allowed to enter the river environment. If the plant and
Northumberland County Council – Technical Services
HB157290_ECMS_01 16
machinery is taken off site, or moves from one part of the site to another via public highways
then this process must be repeated before re-entering the river. Entry into the river corridor
environment will be in accordance with this Method Statement and any restrictions required by
the Statutory Authorities.
All refuelling of plant and machinery shall be undertaken away from the river environment, with
all fuel and chemicals shall be stored away from any watercourse. In addition, plant and
machinery on site will utilise vegetable rather than mineral oils as a lubricant.
Material Control Methods
All materials to be incorporated within the works, shall be unloaded and stored in one of three
dedicated site compounds until they are required within the working area. All materials will be
stored at least 100m from the River Tweed when not in use. All materials shall be where
possible environmentally friendly.
Only material which can be realistically incorporated into the works within any one period shall
be brought to the working area, additional material shall be securely stored in compounds.
The main compound shall be located at the Chain Bridge Honey Farm, with two further
compounds based at both the English and Scottish ends of the structure. The English and
Honey Farm compounds are located away from the river, on higher ground, so are unlikely to
be affected by low to medium flood events. The Scottish compound will be liable to flood,
therefore, all materials, equipment and plant shall be transported to the two other compounds
when a flooding event may occur. All other items shall be weighted down to avoid being
displaced downstream during a flooding event, and located as far away as physically possible
from the flood plan.
All non-cohesive material brought to site, for example to rock armour or gabion stone, shall be
of an appropriate type to match that already present within the river environment. If possible, all
material shall be clean stone, and be locally sourced.
Any variation to this statement and/or the method of working proposed in this document shall
require detailed Method Statements and Risk Assessments.
Northumberland County Council – Technical Services
HB157290_ECMS_01 17
The Main Works Contractor shall be responsible for the maintenance of all plant, equipment and
materials on site, essential for an efficient refurbishment process. Site based maintenance will
involve daily inspections, checking that the machine is complete, with all safeguards fitted, no
leaks, and free from defects. Any defective machinery/equipment must be immediately removed
from site. Procedures shall be in place which allows operatives to report damage or faulty
equipment. Maintenance, records, and compliance with the relevant regulations shall be
undertaken by the supplier, for all equipment is provided by 3rd party suppliers
3.8. Staff Competencies
Those who use plant are to be competent to use it safely, with training provided where
necessary. For some plant a formal qualification is needed Construction Plant Competence
Scheme (CPCS Card). Maintenance is to be carried out by a competent person (someone who
has the necessary skills, knowledge and experience to carry out the work safely). Plant must be
used in accordance with manufacturer’s instructions, and comply with the Provision and Use of
Work Equipment Regulations 1998 (PUWER). Staff will be required to be holders of
Construction Skills Certification Scheme (CSCS) cards. The Main Contractor shall ensure all
staff onsite and all sub-contractors are competent for their respective role.
3.9. Pontoon Works
Assembly
The pontoon is an off the shelf product and will be designed for the proposed refurbishment
works and shall be assembled and installed by competent persons in accordance with
manufacturer’s instructions. The pontoon is built up from modular flotation units; these are
securely connected together in a floating platform configuration. Strong sledge-type runners,
fitted to the base of the modular units, assist with skidding the units on shore and lifting points
are provided, as an integral part of each unit, to facilitate handling by crane.
Northumberland County Council – Technical Services
HB157290_ECMS_01 18
Figure 4 – Example of a Pontoon
Spud (legs) pontoons are constructed with a central sleeve opening which accommodates a
spud pole. Spud (legs) poles are generally lifted using on-board winches. A spud leg is used as
an anchor for securing floating work platforms to their watery bed to prevent general movement
and drifting from their work area.
The modular flotation units are connected on the water from deck level with personnel
positioned on each pontoon. The units are pulled together and secured with locking pins. Once
the deck is formed a key clamp safety handrail is installed around the perimeter. Images of
proposed pontoons are shown below. The maximum size of the pontoon will be 20 x 10 metres,
although at times, the size of the pontoon in use may be smaller, depending upon works
requirements. Once completion of the works is achieved, the pontoon will be dismantled and
removed without delay.
Proposed Works
A temporary scaffold tower and Mobile Elevated Working Platform (MEWP) will be situated
upon the pontoon deck in order to facilitate access to the underside of the timber deck level.
Access to pontoon will be from single dedicated mooring area located on the Scottish
Compound side, minimising requirements for Contractor access to the watercourse.
Northumberland County Council – Technical Services
HB157290_ECMS_01 19
Figure 5 – Example of a Pontoons
Pontoon works involving providing access to the underside of the timber deck, enabling
operatives to remove connections and incrementally lift off timber deck beams and boards,
working from the centre span of the bridge and moving towards England and Scotland.
It will be of sufficient capacity to accommodate construction loadings. The scaffold access tower
and MEWP will be erected & controlled by competent persons in accordance with
manufacturer’s instructions.
Pontoon access tower and MEWP will only be within underside of the bridge during working
hours. It will not be utilised if poor weather that may result in significant increases in flow volume
is forecast. When not in use the pontoon will be securely moored against the Scottish bank of
the river. Several mooring points will be utilised as a failsafe measure in case one should
inadvertently break loose. The scaffold tower, MEWP and tools will be removed from the
pontoon and placed in secure storage and locations at the end of each working shift.
Material Storage and Debris Mitigation
Materials and flotation units will be delivered to site on a flatbed wagon. The materials will be
unloaded and lifted to the designated river access point, with no mechanical plant entering the
confines of the watercourse. All vehicles will remain on the public highway, in the designated
car parks of each site compound or established working areas.
Northumberland County Council – Technical Services
HB157290_ECMS_01 20
The pontoon deck will feature additional protective measures, including a boarded membrane
which will prevent any material inadvertently dropped onto the pontoon entering the water. If
deemed necessary debris netting shall be installed along the perimeter of the edge protection to
prevent equipment and materials falling into the watercourse.
The deck areas shall be cleared of any detritus at the end of each working day, with no
materials stored on the pontoon when not in use.
The pontoon access platform use will not present an increase in environmental risk; however,
materials used for maintenance purposes may cause harm if discharged into watercourse.
Materials permitted on pontoon will be restricted to small quantities for immediate use. Any
spillages will be cleaned up immediately.
Ecological Impact
The measures and working methods proposed are considered to mitigate any perceived
increase in flood risk. A toolbox talk will be given to those working on the pontoon by the
scheme ecologist who will emphasise the need to mitigate any effects on the river bed and
minimise silt disturbance and ensuring no construction material is allowed to enter the water.
In the event of excessive silt generation from the pontoon works, the pontoon shall be
temporarily enclosed with a range of floating booms, floating silt curtains and turbidity barriers to
contain materials and silt.
Northumberland County Council – Technical Services
HB157290_ECMS_01 21
4. Accident Plan
4.1. Introduction
This document details how any accidents or events that could result in a flood risk or pollution of
the River Tweed are dealt with during the course of the construction operations. The working
areas are defined in drawing
HB157290-B-C02-TBT-02-0036 SITE COMPOUNDS LOCATION PLAN.
4.2. Potential Incidences
Potential Incident Equipment Breakdown Likelihood of incident happening
Unlikely
Consequences of incident happening
Minor delay to scheme completion.
Avoidance measures Ensure equipment is maintained and serviced regularly. Undertake daily checks of equipment before use. Any defective equipment shall not to be used within the working area.
Measures to minimise impact if incident occurs
The defective plant or machinery shall be removed from the working area to the nearest site compound. If it can be easily repaired on site then it will be carried out but not within the working area. If not then a replacement item will be delivered to the site. Any replacement machinery shall comply with the environmental method statement before first entering the working area.
Potential Incident Enforced Shutdown.
Likelihood of incident happening
There is the potential for one or more shutdowns occurring during site operations. The most likely reason for the shutdown will be due to adverse weather and/or rise in river level causing inundation of the working area.
Consequences of incident happening
Delay to scheme completion.
Avoidance measures
Monitor weather forecasts and river levels on a daily basis. If the conditions indicate that there is the likelihood of a flood event or inundation of the works by a rise in river level then all plant, materials and equipment will be removed from the working area. Any other enforced shutdowns will be dealt with as, and when, they occur. The objective will be to minimise the duration of the shutdown and to ensure that works continue in a timely manner.
Measures to minimise impact if incident occurs
The site shall be checked after the enforced shutdown to ensure that no damage or deterioration has occurred. Any damage found shall be repaired before work re-commences.
Potential Incident Vandalism Likelihood of incident happening
Remote.
Consequences of incident happening
Delay to completion, potential pollution risk
Avoidance measures Ensure site is fenced off, particularly the working area. This is a requirement of health and safety legislation.
Northumberland County Council – Technical Services
HB157290_ECMS_01 22
All plant and equipment to be either removed from site at the end of each shift or secured against vandalism. Out of hours security detail will be in operation during periods of inactivity i.e. 18:00-08:00 and weekends.
Measures to minimise impact if incident occurs
Any damage shall be removed from the working area and replaced.
Potential Incident Flooding and Adverse Weather. Likelihood of incident happening
It is possible that the bridge site will experience a high flow level due to a flood event during the course of the works.
Consequences of incident happening
Delay to scheme completion, loss of plant, material and equipment from the works due to being swept away, and damaged to constructed access routes to the works. Any extensive rainfall is likely to cause the river levels to rise and inundate the site. Debris is likely to be deposited within the working area. Potential loss of plant, materials and equipment from the working area.
Avoidance measures
Monitor weather forecasts and river levels on a daily basis. If the conditions indicate that there is the likelihood of a flood event or inundation of the works by a rise in river level then all plant, materials (not incorporated into the works) and equipment will be removed from the working area. At the end of each working day all non-essential plant and equipment will be removed from the working area. Materials not incorporated into the works will not be stored within the working area overnight. Items that need to remain within the river shall be weighted down to prevent them being washed away. Any displaced/missing elements of the water management works shall be replaced before work can restart. Works shall not recommence until the river returns to its pre-flood levels. The pontoon will be removed from the watercourse should a period of adverse weather be forecast that is likely to result in significant water level rises.
Measures to minimise impact if incident occurs
Ensure that all plant, materials and equipment are removed from the working area minimising the effect on the River Tweed downstream of the works. Any debris deposited within the working area shall be removed. When safe to do so, the site will be inspected to ascertain the damage to the works. Any items swept immediately downstream will be recovered to ensure they do not become a nuisance. All items must be accounted for.
Potential Incident Pollution of River Tweed downstream of works Likelihood of incident happening
Negligible due to the works being undertaken within the river from a pontoon.
Consequences of incident happening
Pollution of the River Tweed downstream of the works with the potential loss of aquatic life and/or loss of spawning grounds.
Avoidance measures
Vegetable based hydraulic oils shall be used in all machinery permitted to work within the vicinity or in the watercourse. All plant/machinery will be inspected daily for evidence of leakages etc. Floating booms, floating silt curtains and turbidity barriers to contain materials and silt. River bed surveys by Ecologists to determine current condition.
Measures to minimise impact if incident occurs
Components/materials likely to cause pollution will be stored away from the watercourse, in a secure area, and sufficiently sealed. All machinery will either be refuelled in depots or site compounds. Spill kits will be kept on site to mop up any small spills. Large spills will be notifiable to the necessary Statutory Bodies, and relevant specialist Contractors.
Potential Incident Sediment discharge downstream of works. Likelihood of incident Due to the nature of the work – works within the existing river bed – it is
Northumberland County Council – Technical Services
HB157290_ECMS_01 23
happening likely that there will be sediment discharge.
Consequences of incident happening
Inundation of the River Tweed downstream of the works by disturbed sediment from the works. This will reduce the water quality along with the potential loss of aquatic life and/or loss of spawning grounds.
Avoidance measures
Where practicable a line of sedimats/hay bales will be placed immediately downstream of the working area to collect any sediment washed downstream of the works. These will be regularly inspected and if they become full then they will be removed and replaced by new sedimats.
Measures to minimise impact if incident occurs
Staged construction methods shall be adopted whereby works will start and stop once a certain amount of sediment has been generated. Works will then only recommence once sufficient sediment has dispersed. Regular inspection of the downstream river flow will be undertaken to monitor the level of sediment being generated, and if works need to be temporarily suspended. Floating booms, floating silt curtains and turbidity barriers to contain materials and silt.
Potential Incident Disturbance of protected species (nesting birds, roosting bats, otters etc).
Likelihood of incident happening
Likely. The Ecological Appraisal Report indicated that, there may be nesting birds in the surrounding trees. The report also identified that there are foraging bats present but no signs of roosting bats within the works area.
Consequences of incident happening
Disturbing nesting birds and roosting bats is illegal under Wildlife and Countryside Act 1981. If the birds and / or bats are disturbed then it will result in a caution from the police wildlife crimes officer.
Avoidance measures
Detailed ecology surveys will be undertaken, and will identify any protected species and their location in relation to the works, works shall be sequence to comply with fish spawning, bird nesting requirements. Any areas identified as containing protected species shall be adequately demarcated. In advance of the works under supervision of a site ecologist install bird netting into inspection chambers, etc.
Measures to minimise impact if incident occurs
If site staff find, or encroach on an area containing, a protected species they shall immediately withdraw from that area. They shall then inform the supervisor who will decide if additional ecological inspection will be required. If anyone is unsure about whether there is a protected species then they should not enter the area. By undertaking nesting bird and bat surveys immediately prior to works starting then the likelihood of an incident occurring is minimal. If any nesting birds, or roosting bats, are found between the survey and works starting then all work in that area shall stop immediately. A qualified ecologist shall undertake a survey of the affected area and recommend mitigation measures to be implemented. Work shall not recommence in the area until the mitigation measures have been put in place.
Potential Incident Spreading of invasive species (Himalayan Balsam and Japanese Knotweed)
Likelihood of incident happening
Low risk of spreading the invasive species as they will remain undisturbed for the duration of the works.
Consequences of incident happening
Himalayan Balsam and Japanese Knotweed are notifiable species under Schedule 9, Section 14 of the Wildlife and Countryside Act 1981. If mitigation measures are not put in place the there is a risk of transferring these species to unaffected areas. This will result in a potential prosecution by the Health and Safety Executive under the above act.
Avoidance measures
A suitably qualified ecologist will undertake a survey of the working area prior to site operations starting. If the survey finds any invasive species then the following procedures will be put into place. Areas containing invasive species will be sufficiently demarcated, apply
Northumberland County Council – Technical Services
HB157290_ECMS_01 24
herbicide and removed to a license tip, adhering to industry guidelines. The area will be covered with a geotextile and overlaid with temporary stone to form access routes and compounds. The geotextile will serve as a separation barrier between the treated contamination and our works. No new materials shall be stored adjacent to contaminated areas. Anyone who does not dispose off-site of any material containing Japanese knotweed appropriately may be prosecuted. Any plant operating near the watercourse shall be fully cleaned and appropriately disinfected before commencing operations at the site. They will also be treated again before being removed from the works area.
Measures to minimise impact if incident occurs
Identify new areas of contamination; assess extent and location in relation to the existing contaminated area. Begin by treating the area with herbicide approved for use in or near water e.g. glyphosate. After fourteen days of herbicide application area to be excavated and removed from site implementing methods outlined within Environment Agency “Managing Japanese knotweed on development sites (version 3, amended in 2013)”
Potential Incident Preventing fish migration Likelihood of incident happening
Unlikely. The pontoon will not hinder the passage of fish through the site.
Consequences of incident happening
The remaining river width is sufficient to maintain fish passage
Avoidance measures Watercourse will not be obstructed at any time. Site to be monitored daily with supervision provided by an appointed Ecological Clerk of Works
Measures to minimise impact if incident occurs
Incident is not likely given the nature of the works.
4.3. Substances Stored on Site
To be completed once site operations start.
4.4. Storage Facilities
To be completed once site operations start.
4.5. Emergency Contacts
Name and Organisation Telephone Number Email Greg Simpson, Northumberland County Council – Principal Designer
01670 62 2957 [email protected]
Patrick Smith, Northumberland County Council – Principal Engineer
01670 62 2961 [email protected]
Kris Westerby, Northumberland County Council – Principal Contractor
07767 391 680 [email protected]
Main Works Contractor – once appointed
Out of Hours Contact Number – 0345 600 6400
Northumberland County Council – Technical Services
HB157290_ECMS_01 25
4.6. Accident Forms
The Main Works Contractor’s standard accident forms will be used to record any accidents on
site.
Northumberland County Council – Technical Services
HB157290_ECMS_01 26
5. Complaints Procedure
The following complaints procedure shall be in operation.
Whoever receives the complaint shall record the following details (as a minimum):
Contact details of the person/organisation making the complaint;
Details of the complaint;
Date which the activity/task which caused the complaint was undertaken.
If the complaint is received on site then the site foreman shall record the above details.
The main works Contractor shall inform the Construction Manager and Project Manager.
The main works Contractor will contact the complainant to obtain any other relevant
information. If possible, the Project Manager shall give a date by which the complaint is to
be resolved.
Depending upon the seriousness of the complaint, the main works Contractor may contact
any relevant authorities to inform them of the issues and the processes for dealing with it.
If the complaint involves a site activity then that activity will stop until the complaint is
investigated and resolved.
The main works Contractor will ask the Site Manager to prepare a report regarding the
complaint, giving details of the procedures that were undertaken that gave rise to the
complaint and what remedial measures are proposed to rectify the issue.
The Project Manager will review the completed report from the Site Manager and either
accepts, or requests amendments to, the proposals.
Upon acceptance of the proposals the Site Manager will then implement the agreed
remedial action, subject to approval from the Statutory Bodies.
The main works Contractor will then respond to the complainant giving details of the
remedial actions undertaken to prevent the incident from reoccurring.
The main works Contractor will update the relevant documents to reflect the changes to the
works.
The main works Contractor will send the amended documents to all relevant parties to
ensure ongoing compliance with the permit.
Northumberland County Council – Technical Services
HB157290_ECMS_01 27
All Complaints - Informal Resolution Stage
When an issue is raised by a complainant, wherever possible an informal resolution for the
complainant will be sought within 24 hours. If the issue can be dealt with informally and the
customer is satisfied with the outcome, an informal resolution enquiry would be recorded rather
than a complaint.
Stage 1
If no immediate resolution can be found in 24 hours, or a service fails to carry out the agreed
informal resolution, and the Council is re-contacted about the matter, a formal complaint will be
recorded onto the relevant complaints system and acknowledged by the responsible service
within 3 working days of the complaint being made.
Stage 2
Services will also be responsible for seeking a resolution to the issue and responding directly to
customers within 15 working days (inclusive of the 3 days for acknowledgement).
If the customer expresses dissatisfaction following the result of the stage 1 investigation, the
complaint will be escalated to stage 2. Stage 2 will consist of an independent investigation of
both the original complaint and the Council’s response. The results of this investigation will be
provided to the customer within 20 working days of escalation to stage 2.
Stage 3
Customers who remain dissatisfied following the Stage 2 investigation may refer their complaint
to the Local Government Ombudsman (LGO). The LGO will investigate the Council’s response
to the initial complaint and provide a decision as to whether further action is required from the
Council. The Contact Centre will act as a gateway for the LGO in relation to complaints.
Individual services will be required to provide any required information in a timely manner
should an LGO investigation take place.
Northumberland County Council – Technical Services
HB157290_ECMS_01 28
6. Staff Competence and Training Records
6.1. Staffing
The working areas shall be adequately staffed and resourced to ensure that the work can be
carried out safely.
Key Site Personnel – Northumberland County Council
All staff undertaking works covered by the Environmental Permit shall be suitably qualified and
experienced in the tasks they are to undertake. Copies of the site staff’s training and
qualification records for all those working on site can be supplied to the Environment Agency
upon request. Any updated training/qualification records can be supplied to the Environment
Agency as they become available.
Responsibilities:
Northumberland County Council
o Provides Scheme Project Management for the works.
Main Works Contractor
o Supervision of All Subcontractors,
o Installation, maintenance and removal of silt busters and pumps,
o In charge of the complete construction works
o Site safety.
All Sub-Contractors will be required to supply quality plans detailing appropriate experience,
training and qualification to the Main Works Contractor. Any updated training/qualification
records shall be supplied to the Main Works Contractor as they become available.
Northumberland County Council – Technical Services
HB157290_ECMS_01 29
7. Keeping Records
7.1. Scope
Records shall either be kept for the period stated in the Granted Consent Permit or, if there is
no duration stated in the permit, for two years after completion of the works. The records to be
kept shall be, as a minimum, those identified below, including documents submitted as part of
the Statutory Bodies permit applications, as well as the permit itself.
The site file produced for this scheme, as a minimum, shall contain a copy of the following
documentation:
Permits issued for the works and any associated documentation,
Plans submitted as part of the application or associated with the permit,
Risk assessments and management system, including the method of work and any
associated plans,
All operating procedures,
Records and results of any monitoring undertaken, for example water or sediment samples,
Staff competence and training records,
Copies of any compliance checks undertaken by the Statutory Bodies, the findings of any
investigations carried out and actions taken where applicable,
Records of any complaints made, findings of investigation and actions taken where
applicable,
Audits of the management system, findings (reports) and actions taken where applicable,
Certification audit reports along with any actions taken, where applicable,
Record and frequency of management system reviews including records of any changes
made to the management system and reasons for the change.
Northumberland County Council – Technical Services
HB157290_ECMS_01 30
8. Reviewing the Management Plan
8.1. Procedure
Ownership of this Ecological Method Statement will be the responsibility of the Main Works
Contractor. They will regularly review all the documents to ensure that they remain relevant.
The Ecological Method Statement shall update all documents if the following occurs:
Changes to site operations that affect the activities covered by the permit.
Any required changes to the permit.
Any accident, complaint or breach of the permit.
Any flood or environmental problem or issue.
Any new control measures.
Changes to the approved method of works.
Implementation of any new control measures along with the reasons for the change.
The Main Works Contractor will update the documents and notify all relevant parties of the
changes along with sending the updated copy of the reports. All previous copies of the reports,
documents, and site diaries shall be retained, within an electronic archive system.
8.2. Awareness
During the site induction process, the Main Works Contractor will brief any staff who are
carrying out works on the site, the requirements of the Environmental Permit. They will be
informed of the details and location of the Environmental Permit Management System and in
particular, any aspects of it that relates to their work.
Each member of staff will be asked to sign a document that confirms they are aware of their
obligations under the permit.
9. Appendix A – Supplementary Reports and Drawings
9.1. Reports
The following reports are provided to supplement the Ecological Method Statement
9.1.1. E3 Ecology
5490 CEMP R01 – Construction Environmental Management Plan
5490 Report to Inform AA R02 –Report to Inform an Appropriate Assessment in Relation to
Natura 2000 Sites and Appended SSSI Assessment
5490 Union Chain Bridge R02 – Ecological Appraisal and Bat Survey
9.1.2. Total Ecology
Extended Phase 1 Survey report UCB
9.2. Drawings
Please refer to the following drawings which supplement the Ecological Method Statement
HB157290-B-C02-TBT-02-0022-A COMPOUND DRAWING HONEY FARM
HB157290-B-C02-TBT-02-0032 SITE COMPOUND - ENGLISH SIDE
HB157290-B-C02-TBT-02-0034 - Proposed site compound Scottish end
HB157290-B-C02-TBT-02-0036 SITE COMPOUNDS LOCATION PLAN
HB157290-B-C02-TBT-02-0040 Pontoon Routing
HB157290-B-C02-TBT-02-0050 Proposed Reconstruction Sheet 1 of 4
HB157290-B-C02-TBT-02-0051 Proposed Reconstruction Sheet 2 of 4
HB157290-B-C02-TBT-02-0052 Proposed Reconstruction Sheet 3 of 4
HB157290-B-C02-TBT-02-0053 Proposed Reconstruction Sheet 4 of 4