    Kaiser San Leandro Medical Center Date Initiated:

    HOSPITAL/THP OIL Submittal FCO CP RFI(CIRCLE ONE)

    #ScheduleActivity:

    ROUTING: EB _____ HPS _____ TRIAGE: INITIAL FINAL

    R&C _____ M+NLB _____ Sandis _____ CONTRACT COMPLIANT: NO YES

    EDAW _____ URS _____ _____ _____ CLOSED: NO YES

    IOR _____ _____ _____ _____ _____Date Due:

    ITEM IDENTIFICATION PREVENTABLE: N/A NO YES

    SUBMITTAL REVIEW1, 2

    NET MCN RNR REJ

    REASONABLY FOUND IN CDs1 COMMENTS (PER 01 2600-1.3.2 NOTE 1 DENOTES NON-COMPLIANT RFI; NOTE 2 DENOTES BACK CHARGE MAY BE DUE)

    SUBSTITUTION REQUEST1

    REQUEST TIME/COST CHANGE1

    DIFFERENT from APPD DOCUMENTS1

    CLARIFICATION

    CORRECTIVE WORK2

    SCOPE CHANGE: NO ADD DELETE

    DOCUMENT CONFLICT DESIGN BACKCHARGE: NO YES

    UNFORESEEN CONDITIONS

    Other PRIORITY [1 = CRITICAL, 2 = NORMAL or 3 = EXTENDED]:

    INITIAL TRIAGERATIONALE: AOR Referral: NO YES

    IOR Referral: NO YES

    A/E Team concurrence with AOR Referral?

    NO YES

    FINAL TRIAGE

    JUSTIFICATION: PAD REQUIRED: NO YES

    ARCHITECT RESPONSE: Signed: Date: MODEL UPDATE:

    REQUIRED

    DONE or n/aOWNER REVIEW : Signed: Date:

    WHEN POST APPROVAL DOCUMENT (PAD) FOLLOW-UP REQUIREDSCOPE:

    DISCIPLINES: ARCH STRUC MECH ELECT CIVIL Other___________________

    DOCUMENTS:

    1/12/12

    1986

    2

    Not Noted

    1/22/12

    1/16/12 MWM: Optional mud ring required on valve box toposition boc as required to meet penetration requirements ofapproved drawings & CO 0186. Mud ring size will differ fromprior sketch by 1/4".

    1/16/12 MWM: No material change. Provision ofoptional mud ring is to maintain required edge distancesfor penetrations.

    1/16/12 MWM:

    MWM 1/16/12

    AR/GN

    AP/MWM

    CR/TS/MM

    CWW

    HP

    NON-PREVENTABLE (01 2600-1.12.4) PREVENTABLE (01 2600-1.12.3)N/A

    Per OSHPD CAN 1-7-153(a)

    Per OSHPD CAN 1-7-153(a)

  • 7/31/2019 1986 Stud Header Penetration at MVBs - Final Response

    2/11

    With Routing-Author-Drwg Ref.

    RFI Detailed 1986

    Kaiser San Leandro Hospital Rudolph and SlettenProject # 3106-0

    1755 Fairway Drive

    San Leandro, CA 94577

    Tel: (510) 667-9347 Fax: (510) 346-4159

    RFI #: 1986 Importance: Normal Date Created: 1/12/2012From: William Bartley - Rudolph and Sletten Sent: 1/11/2012 To:Michael Moores - Ellerbe Becket (Aecom)Rec'v: Via: Email

    Subject

    MMCI RFI0277.2 - Stud & Header Penetration Clarification at MVBs

    Specification Section Reference DrawingsDiscipline Category

    Author Company Authored By Author RFI Number

    0277.2Pamela AmesMarelich Mechanical

    Question Date Required: 1/22/2012

    DWG/Location: A9.1.17, P2.1.C3, A2.1.C3

    Per R&S RFI # 1289R2 response / CO# 0186, the SK-158 (attached) calls for minimum requirement for penetrations to

    the face of stud. For penetrations greater than 1 diameter and the offset from the valve box assembly, the minimum

    distance for penetrations cannot be met. After field review of the valve box detail (see attached) that was provided, please

    confirm the following is acceptable:

    1) Due to the minimum requirement by SK-158 in CO# 186, the valve box will need to be installed further back on the

    stud to meet the design intent. In order to install the valve box and meet the minimum requirement and not penetrate theflange, the box will need to be installed further back. This will require the valve box to be set back and will require a

    x mud ring to be installed between the valve box and face of drywall to compensate for the added depth.

    2) The Valve Box Detail calls for x , 16 GA steel C shape channel attached to the perimeter of the valve box. As

    previously stated, the valve box will need to be installed back and will require a x mud ring. Confirm that x ,

    16 GA tube steel can be utilized for the valve box detail in lieu of the x 16 GA steel C channel.

    See attached photo for an example of the mud ring that will be used for valve box installation. Note that this tied to schedule

    activity H3190.

    Attachments: CO# 186 SK-158, Valve Box Detail @ Partition

    Answer Date Answered:

    1/16/12 MWM1 & 2) 3/4" mud ring to permit positioning of MGVB and maintain required penetrationclearances of approved drawings and CO0186 is acceptable Configuration of mud ring as

  • 7/31/2019 1986 Stud Header Penetration at MVBs - Final Response

    3/11

    With Routing-Author-Drwg Ref.

    RFI Detailed 1986

    Kaiser San Leandro Hospital Rudolph and SlettenProject # 3106-0

    1755 Fairway Drive

    San Leandro, CA 94577

    Tel: (510) 667-9347 Fax: (510) 346-4159

    Ellerbe Becket (Aecom) Greg Miller 1

    Ellerbe Becket (Aecom) Sami Arim 1

  • 7/31/2019 1986 Stud Header Penetration at MVBs - Final Response

    4/11

    To: Rudolph & Slet ten, Inc.

    1755 Fairway Drive

    San Leandro, CA 94577

    Attent ion: Jam es Young

    Job Nam e: Kai ser San Leandro - Hospit al

    Marel ich Mechanical J ob No: #21003

    SUBJECT: Stud & Header Penetrat ion Clarif ication at MVBs

    Via : E-Mai l R&S RFI#: 1289R3

    DWG/Loc at ion: A9.1.17, P2.1.C3, A2.1.C3 Spec if ic at ion:

    Information Requested:

    Per R& S RFI # 1289R2 response / CO# 0186, the SK-158 (at t ached) cal l s for m in imum requi rem ent for

    penet ra t ions to the fac e o f s tud . For penet ra t ions g rea ter than 1 d iameter and the o f f se t f rom t he va lve

    box assembly , the min imum d is tance fo r penet ra t ions cannot be met . A f te r f i e ld rev iew o f the va lve box

    deta i l (see at tac hed) tha t w as prov ided, p lease con f i rm the fo l l ow ing i s acceptab le :

    1 ) Due to t he min imum requ i rement by SK-158 in CO# 186, the va lve box w i l l need to be ins ta l led fu r ther

    back on the s tud to meet the des ign in ten t . I n o rder to ins ta l l t he va lve box and meet t he min imum

    requ i rement and no t penet ra te t he f l ange, the box w i l l need to be ins ta l led fu r ther back. Th is w i l l requ i re

    the va lve box to be se t back and w i l l requ ire a x m ud r ing to be insta l led be tw een the va lve box

    and face o f d rywa l l t o com pensate fo r the added depth .

    2 ) The Valve Box Deta i l ca l l s fo r x , 16 GA s tee l C shape channe l a t tached to t he per imeter o f the

    va lve box. As p revious ly s ta ted , the va lve box w i l l need to be ins ta l led back and w i l l requ i re a x

    mud r ing . Conf i rm tha t x , 16 GA tube s tee l c an be u t i l i zed fo r the va lve box de ta i l i n l i eu o f the x

    16 GA s tee l C channe l .

    See a t tached photo fo r an example o f t he mud r ing tha t w i l l be used for va lve box ins ta l la t ion . Note tha t th i s

    t ied to schedu le ac t i v i t y H3190.

    At t achm ents: CO# 186 SK-158, Valve Box Deta i l @Part i t ion

    Poten t ia l Impact :

    Requestor : Pamela Ames Dated Issued: 01/05/11 Date Requi red:

    Response: R& S RFI#: Answ ered By: Date:

    MARELICH MECHANICAL CO., INC.

    Request For In form at ion MM/RFI No: H 027 7.2RFI 1986

  • 7/31/2019 1986 Stud Header Penetration at MVBs - Final Response

    5/11

    MVB 1-6

    Marelich Mechanical

    MMRFI# H-0277.2

  • 7/31/2019 1986 Stud Header Penetration at MVBs - Final Response

    6/11

    Marelich Mechanical

    MMRFI# H-0277.2

  • 7/31/2019 1986 Stud Header Penetration at MVBs - Final Response

    7/11

    Marelich Mechanical

    MMRFI# H-0277.2

  • 7/31/2019 1986 Stud Header Penetration at MVBs - Final Response

    8/11

    Marelich Mechanical

    MMRFI# H-0277.2

  • 7/31/2019 1986 Stud Header Penetration at MVBs - Final Response

    9/11

    Marelich Mechanical

    MMRFI# H-0277.2

  • 7/31/2019 1986 Stud Header Penetration at MVBs - Final Response

    10/11

    Marelich Mechanical

    MMRFI# H-0277.2

  • 7/31/2019 1986 Stud Header Penetration at MVBs - Final Response

    11/11

    Marelich Mechanical

    MMRFI# H-0277.2


Recommended