+ All Categories
Home > Documents > 1998 SPE49130 Day Griffin Martins

1998 SPE49130 Day Griffin Martins

Date post: 06-Apr-2018
Category:
Upload: juan-m-villalobos-ii
View: 213 times
Download: 0 times
Share this document with a friend

of 13

Transcript
  • 8/3/2019 1998 SPE49130 Day Griffin Martins

    1/13

    Copyright 1998, Society of Petroleum Engineers, Inc.This paper was prepared for presentation at the 1998 SPE Annual Technical Conference andExhibition held in New Orleans, Louisiana, 2730 September 1998.This paper was selected for presentation by an SPE Program Committee following review ofinformation contained in an abstract submitted by the author(s). Contents of the paper, as

    presented, have not been reviewed by the Society of Petroleum Engineers and are subject tocorrection by the author(s). The material, as presented, does not necessarily reflect anyposition of the Society of Petroleum Engineers, its officers, or members. Papers presented atSPE meetings are subject to publication review by Editorial Committees of the Society ofPetroleum Engineers. Electronic reproduction, distribution, or storage of any part of this paper

    for commercial purposes without the written consent of the Society of Petroleum Engineers isprohibited. Permission to reproduce in print is restricted to an abstract of not more than 300words; illustrations may not be copied. The abstract must contain conspicuous

    acknowledgment of where and by whom the paper was presented. Write Librarian, SPE, P.O.Box 833836, Richardson, TX 75083-3836, U.S.A., fax 01-972-952-9435.

    AbstractMagnus is the most northerly field in the UK North Sea, with

    14 platform and two subsea producers, and 13 injectors of

    which 8 are subsea. After 12 years of plateau production at

    140,000 bopd, the field went on precipitous decline in 1995,

    with an underlying decline rate of 60% per annum. Although

    there had been significant preparation and investment for

    decline, the severity of the well-related problems had not been

    anticipated. Wells producing over 20,000 bopd fell over in a

    matter of hours as a result of severe barium sulphate scaling,

    amongst other factors.

    This paper discusses the causes of the severe declines, theincreasing evidence of reservoir complexity, and the re-

    engineering of the reservoir development that equipped the

    field for post-plateau production. During the first three years

    of decline, all production wells were either side-tracked or had

    major interventions to maintain production, as we moved from

    multi-zone to single zone completions. Crucial to the success

    of the performance recovery has been the drilling of several

    injectors, targeted to support specific zones/areas. Facilities

    upgrades were also made with increased water-handling

    capacity, gas lift capability, upgraded water injection pumps

    and a subsea injection manifold all being added.

    The subsequent reservoir and well management strategies

    used are discussed, together with a summary of lessons from

    the new wells. The main keys to success of the programme are

    presented, including base production focus and scale

    management operations. As a result of the re-engineering, the

    base decline rate has been substantially reduced and

    manageability has been restored to the field. The lessons

    learned on Magnus may have relevance for future

    developments reliant on a small number of wells, particularly

    if they are subsea.

    Field BackgroundMagnus is the most northerly of the presently producing

    fields on the UKCS. Discovered in 1974, the reservoir is a

    Upper Jurassic turbidite reservoir, with a high net to gross

    upper reservoir (Magnus Sandstone Member - MSM) and a

    low net to gross lower reservoir (Lower Kimmeridge Clay

    Formation - LKCF), both averaging approximately 100mTVT

    (Figures 1&2). The reservoir is a South-East dipping tilted

    fault block of 14km by 3.5km, overlain by Cretaceous

    mudstones. Reservoir quality improves towards the crest of

    the structure, with only limited permeability remaining at the

    oil water contact. Some faults can be seen on the seismic but

    these are of limited throw. Only the upper MSM sands were

    recognised when the development was sanctioned in 1978.

    The field was developed with a single platform with

    subsea wells on the flanks of the field to access areas that the

    drilling technology of the day could not reach. A two platform

    development was considered but rejected on the grounds of

    excessive cost in the deep waters (186m) and harsh

    environment of the Northern North Sea. Due to the limited

    permeability in the water leg, the development plan was for pre-produced injectors, completed in the oil leg then later

    converted, to sweep oil in a line drive towards the main

    producers. The first line of producers would in turn be

    converted to injection as the flood front advanced up dip. The

    pressure support from the water aquifer was inadequate due to

    its limited extent and poor permeability. STOIIP is presently

    estimated to be ~1650 MMSTB with recoverable reserves

    797 MMSTB of sweet light 39o

    API oil (GOR 750scf/stb).

    The MSM has the majority of the reserves and STOIIP with

    an expected final recovery factor of ~65%; LKCF recovery

    factor ~30%. Initial reservoir pressure was 6653psi at datum

    (3050 mTVDSS) with a bubble point of 2750psi. The Magnus

    field is operated by BP on behalf of the Magnus LicensePartners (BP 85%; AGIP UK 5%; Nipon Oil E&P UK Ltd

    5%; Petrobras (UK) Ltd 2.5%; Talisman Energy (UK) Ltd

    2.5%)

    On plateau, production was processed through two

    identical trains, with first a high pressure (HP) separator, then

    a low pressure (LP) separator and finally a flotation unit,

    cleaning the produced water prior to overboard discharge. Oil

    was exported through a pipeline via Ninian to Sullom Voe.

    Gas was exported via the Northern Leg Pipeline System to

    Brent and finally St. Fergus. Gas compression was the main

    SPE 49130

    Redevelopment and Management of the Magnus Field for Post-Plateau ProductionSimon Day, Tim Griffin and Paul Martins, BP Exploration

  • 8/3/2019 1998 SPE49130 Day Griffin Martins

    2/13

    2 SIMON DAY, TIM GRIFFIN AND PAUL MARTINS SPE 49130

    facilities limitation during plateau production.

    The highly productive nature of the Magnus sands (PIs of

    100-200 stb/day/psi were common in conventional wells)

    allowed the field to be developed with relatively few wells.

    The platform was installed with only 20 well slots and space

    for 9 subsea wells. The field was brought onto production in

    August 1983 with water injection start-up following in August

    1984 (delay due to the pre-produced injectors). Initial plateaurate was an annualised average 125 mstbd (daily peak

    145 mstbd) but this was steadily increased to an annualised

    average 140 mstbd (daily peak 163mstbd) in 1988 as the

    facilities were debottlenecked. Water injection initially

    averaged ~150 mbwd but a major upgrade in 1991 increased

    this to ~240 mbwd (Figure 3).

    Due to the initial lag in starting water injection and the

    subsequent facilities upgrades, the field was under-voided

    throughout most of the 12 years of plateau production

    (Figure 3). In an attempt to keep a straight line drive, two of

    the highest injectors (M17:C5, M13:C7 on Figure 1) were

    choked back which also contributed to the under-voidage. Asa result, the average reservoir pressure steadily dropped until,

    in the early 1990s, the crestal pressure was close to the oil

    bubble point. In 1993, all the injectors were opened to

    maximise injection and increase the reservoir pressure,

    regardless of whether the flood-front was skewed.

    Despite the pressure drop in the crest, the high

    productivity of the wells meant plateau production could

    easily be maintained. Plans were considered for dedicated

    crestal injectors but not carried out due to the difficulty of

    justifying the benefit with the existing reservoir description

    and a field limited by production facilities.

    Production and injection were generally perforated in all

    reservoir intervals encountered. These large multi-zone wellswere PLT logged throughout their lives to track zonal pressure

    differences. Some wells were also perforated in stages to

    monitor the productivity of different zones. Although pressure

    differences were found in wells, these were never extensive

    and it appeared that most reservoir zones were in

    communication. Compartmentalisation was found in two

    places: The Northern area had some pressure differences from

    the North Central area, although compartmentalisation was not

    total; The Brent High held back significant pressure support

    from the Crestal area (Figure 1). The latter was the most

    significant from a reservoir development viewpoint - M6:B3

    was planned to be one of the first wells in the field to water

    out, when it would be converted to injection, in fact it was oneof the last wells to suffer significant water breakthrough in

    January 1995. The lack of support from M5:C4 to the crest

    contributed to the pressure decline in that area. In fact, the

    Crestal area was only being significantly supported from

    M17:C5 and M13:C7. The Brent High is the most significant

    pressure barrier in the field, holding back up to 4000 psi

    pressure difference. Other barriers marked on Figure 1 are at

    best leaky, generating some pressure difference but also

    allowing some sweep.

    Water analysis and the behaviour of the first wells to

    water-out under waterflood had shown Magnus was very

    susceptible to barium sulphate scale formation. This scale

    forms when barium from the formation water mixes with

    sulphate from the injected seawater. The resultant compound

    is very insoluble and precipitates out in the well liner, limiting

    production and well access (scale can also form in the topsides

    pipe-work if the conditions are appropriate). Calcium

    carbonate scale formation was not expected (nor has proved)to be a significant problem.

    Performance Coming Off Plateau ProductionWater breakthrough had occurred in several flank producers

    during the plateau period, but none of the crestal producers

    (Figure 1) had significant water breakthrough until late 1994.

    The field well potential averaged very close to the plant

    capacity during most of 1994, but for approximately six

    months the well capacity was slightly lower than plant

    capacity. However, the field annualised average was still

    above the average plateau rate due to strongly increased plant

    efficiency - in fact the 1994 average of 144 mstbd was thehighest in field history despite the marginal well stock.

    However, by late 1994 increasing signs of reservoir decline

    were visible and the field came off plateau production at the

    end of 1994 / beginning of 1995. The decline was in several

    wells but was driven in particular by three wells:

    A5 The first crestal well to break significant water in

    October 1994. The water-cut rose very rapidly, reaching 55%

    by the end of January 1995. A significant point is that the

    average reservoir pressure measured in this well only rose

    slowly and lagged the water-cut rise. As a result the lift

    performance and oil production from the well declined sharply

    - by the end of January the well was producing ~5 mstbd,

    down from ~28 mstbd in November. By June the well wasessentially dead.

    A4 Another crestal well that broke water at a low level in

    April 1994. The water-cut remained low, usually averaging 2-

    3%. This well was not scale squeezed as field strategy had

    been to scale squeeze wells when they reached 5% to avoid

    any formation damage. A PLT in August 1994 showed a

    blockage just below the highest perforations, due to scale

    formation. From January 1995, production declined rapidly

    from ~20 mstbd as scale plugged off the well-bore. By March

    production was

  • 8/3/2019 1998 SPE49130 Day Griffin Martins

    3/13

    SPE 49130 REDEVELOPMENT AND MANAGEMENT OF THE MAGNUS FIELD FOR POST-PLATEAU PRODUCTION 3

    rapidly from ~15 mstbd to

  • 8/3/2019 1998 SPE49130 Day Griffin Martins

    4/13

    4 SIMON DAY, TIM GRIFFIN AND PAUL MARTINS SPE 49130

    the wells as it was well performance that was driving the

    production decline.

    Production Wells: The most significant change in the field

    development strategy was a move from large multi-zone

    producers to dedicated single zone producers. Though not

    initially seen as a strategy for the entire field, this process was

    actually started in July 1994 when M22:B7 was completed in

    one zone shortly before the field came off plateau. Single zonecompletions improved the lift performance of the wells by

    reducing water-cuts and stopping cross-flow between zones.

    Production could now be optimised and interventions

    performed with confidence that the well would not die due to

    cross-flow.

    Single zone completions also enabled more effective scale

    squeezes as the reservoir pressures within the well were more

    uniform. Combined with more effective inhibition chemicals1,2

    scale squeeze life was approximately tripled. It is likely that

    once pressures in the field are more uniform and the scaling

    tendency has reduced as the sea-water cut of the field

    increases, a return will be made to multi-zone wells.In a field with such a large well spacing, it was often not

    possible to predict the order in which layers watered out nor

    their individual water-cuts. As stated above, scale usually

    formed rapidly after water breakthrough, precluding the use of

    PLTs to measure layer water-cuts after breakthrough. In

    addition, due to the poor lift performance of the wells, if a

    scale mill-out was performed to regain access then the wells

    would likely cross-flow and die, making any PLT virtually

    worthless (although the drier zones were usually lower

    pressure this could not be guaranteed). The solution was to

    perform a series of liner sidetracks (8.5 sidetrack, usually

    ~50m from the original wellbore) and install gas lift

    completions instead of the originally intended gas lift work-overs. Liner sidetracks offered numerous advantages

    including: assured shut-off of water intervals behind new liner

    and cement; open-hole logs, including accurate pressure for

    reservoir monitoring and perforation decisions; clean well

    bore without residual scale problems; only minimal increase in

    time required over a simple work-over and much quicker and

    more reliable if a water shut-off was planned as part of the

    work-over. Three wells didhave a successful zonal shut-off to

    change them to single zone production - two with plugs

    immediately below the topmost zone and one with a more

    complicated cement squeeze shut-off. Two other wells were

    also directly worked over to gas lift rather than sidetracked.

    One was successful from a reservoir viewpoint but later faileddue to mechanical problems. The other well struggled from

    difficulties in shutting off one zone and from much higher

    than expected zonal water-cuts (95% water under steady flow

    conditions 11months after first water breakthrough - zone

    ~50m thick).

    Obviously not all wells could be converted to single zone

    production immediately and interventions were required to

    maintain flow from existing wells. One of the most intractable

    problems was controlling scale in multi-layered wells with

    cross-flow - inhibitor had to be injected into the higher

    pressure layers in the well. One solution was to inject

    inhibition squeezes at higher rates - Magnus now injects

    chemicals using the water injection system and can inject at up

    to 21bpm, depending on the fracture gradient in the well.

    The other solution was to reduce the injectivity of the

    lower pressure zone to divert chemicals to the higher pressure

    wet zones. First, mechanical diversion was considered but

    rejected due to lack of reliability in wells where scale hadalready formed in the liner (assuming access was even

    possible in the first place). The chosen method was to inject

    the inhibition chemicals in a series of stages, separated by wax

    diverters to progressively block the low pressure injectivity3.

    The reservoir interval was first cooled with sea-water and then

    the first stage of chemicals pumped followed by wax divertor.

    The wax was designed to solidify on the cooled rock, reducing

    the injectivity. Successive stages injected inhibitor and

    blocked the injectivity until all the open intervals had been

    inhibited. During the soak period the well would heat up, the

    wax melted and was subsequently back produced and

    processed normally with the oil stream. This method has beensuccessfully used on several Magnus wells and has helped to

    extend squeeze lives. Wax diverted squeezes have been

    combined with PLTs to confirm diversion was successful.

    Injection: As Magnus has a limited aquifer, injection is of

    crucial importance to maintain production. The under-voidage

    had been a concern during plateau and efforts were made to

    improve injection volumes during the last 4 years of plateau.

    However, this focus has increased sharply post-plateau when

    the benefits of increasing individual well production rates

    through injection are more clear if the field production is

    limited by the well potential rates. Three routes were pursued

    to improve injection support in the field:

    Drilling Dedicated Zonal Water Injectors: As theunderstanding of field complexity improved, it was possible to

    target injectors to particular zones or compartments and

    locally boost production. In addition, the opportunity has been

    taken to convert one producer to injection duty where this was

    higher value. The programme has been very successful, with

    several wells doubling in oil production rate.

    Water Injection Upgrades: Several major injection

    upgrade options have been investigated, from additional main

    injection, boosting SWIFT manifold wells or boosting a single

    well (with an ESP). The highest value option was to add a

    sixth injection pump (cost ~6MM) and this may be

    implemented during late 1998 / early 1999. However, these

    investigations also highlighted the possibility of impellerupgrades for the present main injection pumps. The new

    impellers were optimised for the expected range in pressure

    and injection rates forecast for the field (short term, high

    pressure lower rates, longer term lower pressure higher rates).

    The pumps were upgraded on a rolling basis to minimise the

    injection loss. The performance improvement was equivalent

    to the addition of a new pump but at a cost of ~0.5MM.

    Water Injection Optimisation: As field oil rate dropped

    below plateau rates, the drop in reservoir barrel offtake was

    sufficient to take the field into positive voidage on an annual

  • 8/3/2019 1998 SPE49130 Day Griffin Martins

    5/13

    SPE 49130 REDEVELOPMENT AND MANAGEMENT OF THE MAGNUS FIELD FOR POST-PLATEAU PRODUCTION 5

    basis for the first time (1995). This, combined with zonal

    dedicated injection wells and upgrades outlined above allowed

    the water injection system to be more closely optimised than

    the few years previously. The overall aim was to maintain

    field voidage balance while targeting water at the highest

    value (in terms of oil production) areas. The reservoir model

    was used to value each well in terms of barrels of oil

    production supported. A model of the water injection systemusing Petroleum Experts Prosper / Gap software was then used

    to optimise the injection to each well. The injection system

    was now optimised for maximum oil production rather than

    water injection.

    Production Result Post-PlateauMagnus production base decline rate reached 60% per annum

    for the first year post-plateau. Only a rapid succession of new

    wells and liner side-tracks sustained production - in January

    1996, 58% of production was from wells drilled in the

    previous year. The focus on base well management, water

    injection optimisation and the move to single zonecompletions gradually stabilised the annual decline rates

    (Figure 5). Indeed, in recent months the decline rate has

    actually become negative as the field production rate has

    steadily risen due to improved injection support for two key

    zones in the crestal area of the field (G and A sands). This

    production is a combination of new oil and acceleration and

    base decline rates are expected to grow again during the latter

    half of 1998. However, manageability has be restored to the

    field and it is not expected that the high decline rates of 1995

    will return. Wells are now more predictable and can in general

    be choked back or turned off if required for field management

    reasons without the fear that the well will die. As stated above,

    scale squeeze life has approximately tripled due to acombination of new chemicals and the single zone

    completions.

    Figure 6 shows the source of production since the end of

    plateau by year and type of operation. In this case

    interventions have been separated out from the base

    production rate used to calculate decline rates above. The high

    level of activity, spread almost evenly between new

    production wells, new injection wells and interventions can

    easily be seen. The pre-1995 base (i.e. base before end of

    plateau without new wells or interventions) drops close to zero

    in mid 1996 (~5 mstbd, 0 mstbd by March 1997). No wells in

    Magnus were side-tracked or had major interventions unless

    they had died, so this gives a good indication of the likely production rate without investment (although the lack of

    competition as wells died would probably have allowed the

    remaining wells to last longer). The present Magnus

    production of ~90 mstbd is entirely due to the investment

    carried out 1995-1998.

    The change in strategy to recomplete wells as single zone

    producers has essentially been completed within three years.

    Figure 7 shows the dramatic change from multi-zone

    producers to a pattern of single zone wells. The field now has

    several oil bearing zones behind pipe awaiting perforation

    when the well performance allows it. The next stage of

    development where the present zones are shut-off and other

    zones opened up is presently just beginning. It is likely the

    field will gradually move back to multi-zone completions

    were pressure differences are not great and the scale can be

    controlled. This will be required in late life in order to cycle

    water and improve recovery.

    With such a high level of new wells and liner side-trackactivity, only one producer now remains that produced before

    the end of plateau. Figure 8 shows the cumulative percentage

    of production by the age of the well for the last months

    production. Even the one well still existing from before the

    end of plateau has had a major intervention and is actively

    supported by two new injectors, drilled or converted since the

    end of plateau.

    Water injection optimisation is estimated to have increased

    production by 1-2 mstbd over the last few years. However the

    drilling of new injectors (and conversion of one producer to

    injection) has produced more significant levels of new

    production as can be seen in Figure 6. Of the 19 platform andsubsea wells drilled on Magnus since coming off plateau, 6

    were injectors (not including the producer converted to

    injection). Injectors were targeted at particular zones and

    compartments - two deserve further description as they also

    show the increasing complexity of the reservoir description:

    Crestal A Sands This zone is a high net to gross sand of

    limited extent in the crest of the field. M26:A4 was a

    dedicated A sand producer completed in July 1995

    (production rate ~16 mstb/d). The reservoir pressure was low,

    close to bubble point, pressure support coming from other

    zones and areas of the field. M5:C4 was originally planned to

    be the injector supporting the Crestal A sand, but the Brent

    High prevented adequate water flux. M5:C4 was highly pressured (~6500 psi) compared to M26:A4 (~2800 psi). It

    was decided to sidetrack M5:C4 to a location in better

    communication with the low pressure reservoir around

    M26:A4. The Brent High is not a single fault, but a line of

    thinned reservoir with small faults relating to a high in the

    underlying sediments. It was therefore extremely difficult to

    pick the exact structure that was causing the pressure barrier.

    The A sand thins and narrows updip, so the associated

    reserves were reduced rapidly the further updip the well was

    targeted. This tension between maximising reserves and

    achieving communication led to a stepwise approach, where

    the well was sidetracked a short distance first and tested. If the

    first location was a failure then the well would be sidetrackedagain over the final barrier on the seismic before M26:A4.

    M31:C4 completed drilling in October 1996 and encountered

    a high pressure but water swept A sand. As this was not in

    communication with M26:A4, the well was immediately

    sidetracked as M31z:C4. This well encountered low pressure

    unswept A sand, the same pressure as M26:C4. The well was

    completed and brought on to injection in early November

    1996. Initial injection rates were >40 mbwd, but rapidly

    declined to ~4 mbwd over two days. The well was shut-in for

    a PFO and later returned to injection when it followed a

  • 8/3/2019 1998 SPE49130 Day Griffin Martins

    6/13

    6 SIMON DAY, TIM GRIFFIN AND PAUL MARTINS SPE 49130

    similar pattern (40 mbwd dropping to 4 mbwd). The pattern

    was repeated several times in the following weeks and the

    sustainable injection rate remained at 4 mbwd. The PFO

    showed no problems with the well and the reservoir was

    interpreted as being connected to M26:A4 by long thin

    channels, thereby limiting the steady state injection rate.

    Injection of 4 mbwd was not sufficient to actively support

    M26:A4 production rate, so a further sidetrack was required.No further features were detectable on the seismic so defining

    the well target was problematic. In the intervening time,

    advantage was taken of the upper sands encountered by

    M31z:C4 as outlined below, therefore a different slot was

    used for the next updip sidetrack. M34:C3 was completed in

    September 1997, again encountering low pressure dry oil

    bearing A sands. The well was brought on to injection at a

    steady rate of 50 mbwd with the well choked back (rates of up

    to 70 mbwd were achievable). No problems were found with

    decreasing injection rates. M26:A4 production rate started

    rising within 2 days and eventually more than doubled to

    ~35 mstbd (Figure 9). Water breakthrough at low levelsoccurred in January 1998 and the main water breakthrough is

    expected June / July 1998. A second producer, further updip

    than M26:A4 is planned for late 1998 / early 1999 to take

    advantage of the good injection support from M34:C3.

    Crestal G Sands As the main sands in the crest watered

    out during 1995/6, three wells (M10:A3, M6:B3 and M24:B4

    - Figure 1) produced the majority or all of their production

    from the topmost sand in the MSM (G sands). This sand

    remained at lower pressure than the main crestal sands and

    one of the new SWIFT injectors (F2) was targeted as a crestal

    injector to support these wells. F2 was completed in the upper

    MSM on January 1996 And brought on to injection at a rate of

    ~30 mstbd. M24:B4 showed a steady improvement inproduction rate, increasing by 50% in 3 months (Figure 10).

    However, neither M10:A3 nor M6:B3 showed any response,

    despite the fact that M6:B3 was the closest well to F2 and that

    M10:A3 was only 300m from M24:B4 - two of the closest

    wells in the field. The second sidetrack of C4 (M31z:C4), to

    support the A sands as outlined above, had a top hole section

    that passed within 50m of F2. The majority of the upper MSM

    showed high pressures (~5500psi), as would be expected so

    close to an active injector. However, one sand section within

    the G (it was split into two sands) showed much lower

    pressures (~3500psi). After the failure of the A sand injection,

    it was decided to perforate this lower pressure G sand to

    confirm whether it was in communication with M10:A3(M6:B3 had died through raised water-cut and low reservoir

    pressure). M10:A3 showed a steady rise in production,

    confirming the connection (Figure 11). Although shut-in,

    M6:B3 had also showed a reservoir pressure rise. M6:B3 was

    lifted back onto production on August 1997 but produced at

    very high water-cut. It was decided to convert M6:B3 to

    injection duty to more actively support M10:A3. This was

    completed in late December 1997 and the well began injection

    at ~30 mbwd. M10:A3 production rate again showed a

    significant rise (Figure 11). In addition, M10:A3 water-cut

    dropped from ~15% to ~8% as the sweep patterns in the field

    were changed.

    The patterns of connectivity between the above wells

    introduced a significant problem for sand correlation. Figure

    12 shows the sand bodies as described by well picks and

    confirmed reservoir communication. For F2 and M24:B4 to be

    directly connected, the two sand bodies between the wells

    would have to cross - not geologically possible. No definitivesolution to this has yet been determined - the present reservoir

    description has the sands between F2 and M24:B4 thinning

    and injection communication occurring via other lower sand

    bodies (Figure 13).

    The increasing complexity of the G sand can easily be seen

    on a plot of crestal RFT and PLT reservoir pressures taken in

    the zone during field life (Figure 14). During plateau, the

    pressures were relatively uniform. Post-plateau, the

    combination of dedicated crestal injection and the move to

    single zone producers has given rise to a wide range in zone G

    pressures, sometimes within the same well, as discussed

    above. The offtake from this zone has increased post-plateau,so the differences are probably the result of reservoir

    constraints rather than complete pressure barriers. However

    the plot shows how the real reservoir complexity may not be

    apparent while on plateau.

    Conclusions and Lessons LearntThe Magnus field has obviously required a substantial

    investment, both in plant and well facilities, to maintain

    production. Indeed, without the investment since the end of

    plateau, production would be close to zero instead of the

    present daily average of ~90mstb/d. All investments have been

    justified on the basis of the production / reserves that they

    accessed or protected. However, such a degree of late lifeinvestment had not been anticipated in the original

    development plan. The risk of requiring late life investment

    (and well access) to maintain production should be included in

    the planning of new developments.

    The relatively few highly productive wells means the field

    is very similar in concept to a number of developments taking

    place today, albeit that non-conventional well technology is

    now often used to achieve the high well productivity.

    Reservoir simulation and extensive PLT data gathering had

    not shown the extent of the problems the Magnus field would

    face as it came off plateau. Zonal pressure differences within

    wells were relatively modest during plateau production with

    no indication of the large changes that would rapidly occur.Although many of the main reservoir features could be

    identified, the full complexity of the reservoir was not

    apparent until the field came off plateau (and the degree of

    complexity is continually increasing). With relatively few

    wells and large inter-well spacing, reservoir description and

    performance uncertainty is substantially increased - prediction

    of the performance during decline is especially problematic.

    New developments that rely on small numbers of wells should

    include this uncertainty in their predictions. Developments

    that assume limited well access may especially be at risk.

  • 8/3/2019 1998 SPE49130 Day Griffin Martins

    7/13

    SPE 49130 REDEVELOPMENT AND MANAGEMENT OF THE MAGNUS FIELD FOR POST-PLATEAU PRODUCTION 7

    AcknowledgmentsThis paper is written by three reservoir engineers but

    obviously the successful redevelopment of Magnus has

    involved many hundreds of people, both onshore and offshore,

    past and present. We extend our thanks and congratulations to

    them. In particular, we would like to thank David Richards for

    the use of his illustrations.The authors would like to thank the Magnus License

    partners for their permission to publish this paper.

    The views expressed in this paper are those of the authors

    and do not necessarily represent those of BP Exploration.

    References1. Collins, I.R., et al.: Extending Scale Squeeze Lifetimes Using a

    Chemical Additive: From the Laboratory to the Field, paper

    presented at the "Solving Oilfield Scale" Conference, Aberdeen

    Jan. 22nd - 23rd 1997

    2. Bourne, H.M. et al.: Combining Innovative Technologies to

    Maximise Scale Squeeze Cost Reduction: A Laboratory to Field

    Study, paper presented at 9th International Oilfield ChemicalSymposium, 22 - 25 March 1998 Geilo, Norway.

    3. Ravenscroft, P.D., Cowie, L.G. and Smith, P.S.: Magnus Scale

    Inhibitor Squeeze Treatments - A Case History, paper SPE

    36612 presented at the 1996 Annual Technical Conference and

    Exhibition, Denver, Oct. 6-9

  • 8/3/2019 1998 SPE49130 Day Griffin Martins

    8/13

    8 SIMON DAY, TIM GRIFFIN AND PAUL MARTINS SPE 49130

    M32:A2

    M36:B7

    Brent High

    OWC

    M29:A7

    12A-21:D9

    12A-17:D4

    M25:A1

    M37:B1

    M4:C2

    M30Z:A5

    M10:A3

    M24:B4

    M27:B2

    M6:B3M26:A4

    M28:A6F2

    M31Z:C4

    M23:B6 M17:C5

    12A-16:D3

    F1

    M35z:B5

    12A-11Z:D5

    PLATFORM

    SWIFTF3

    M33:C7

    Production

    Injection

    M32Z:A2

    M34:C3

    Figure 1: Magnus field map with areas

    F4z

    F4

    M35:B5

    Southern

    Crest

    North Central

    Northern

  • 8/3/2019 1998 SPE49130 Day Griffin Martins

    9/13

    SPE 49130 REDEVELOPMENT AND MANAGEMENT OF THE MAGNUS FIELD FOR POST-PLATEAU PRODUCTION 9

    GR0 250

    NET20 0

    RHOBG/CC1.95 2.95

    NPHIV/V0.45 -0.15

    ILM0.2 200

    ILD0.2 200

    3250

    3300

    3350

    3400

    3450

    3500

    3550

    Depth

    METRES

    2900

    2950

    3000

    3050

    3100

    3150

    3200

    CKHL0.5 5000

    KHA980.5 5000

    PHITV/V0.3 0

    PERF15 0

    CPORPU30 0

    VSHV/V0 1

    PHITV/V1 0

    FOIL1 0

    Figure 2: Typical log showing MSM and LKCF reservoirs

  • 8/3/2019 1998 SPE49130 Day Griffin Martins

    10/13

    10 SIMON DAY, TIM GRIFFIN AND PAUL MARTINS SPE 49130

    0

    25000

    50000

    75000

    100000

    125000

    150000

    175000

    200000

    225000

    250000

    275000

    300000

    A

    ug-83

    J

    an-84

    J

    un-84

    N

    ov-84

    A

    pr-85

    S

    ep-85

    F

    eb-86

    Jul-86

    D

    ec-86

    M

    ay-87

    Oct-87

    M

    ar-88

    A

    ug-88

    J

    an-89

    J

    un-89

    N

    ov-89

    A

    pr-90

    S

    ep-90

    F

    eb-91

    Jul-91

    D

    ec-91

    M

    ay-92

    Oct-92

    M

    ar-93

    A

    ug-93

    J

    an-94

    J

    un-94

    N

    ov-94

    A

    pr-95

    S

    ep-95

    F

    eb-96

    Jul-96

    D

    ec-96

    M

    ay-97

    Oct-97

    M

    ar-98

    ProductionandInjection(Barrels

    /day)

    -10

    -9

    -8

    -7

    -6

    -5

    -4

    -3

    -2

    -1

    0

    1

    2

    VoidageReplacementRatio(V

    RR)

    Water Injection

    Oil Production

    Water Production

    Monthly VRR

    Cumulative VRR

    Figure 3: Magnus production, injection and voidage history from start of field life

    0

    5

    10

    15

    20

    25

    0:00 2:00 4:00 6:00 8:00 10:00 12:00 14:00

    Time in Hours

    Gr

    oss

    Fluid

    Rate

    (mbbl/d)

    0

    20

    40

    60

    80

    100

    120

    WH

    FP

    (barg)

    and

    Choke

    (%)

    M10:A3 Gross Rate

    M10:A3 Choke

    M10:A3 WHFP

  • 8/3/2019 1998 SPE49130 Day Griffin Martins

    11/13

    SPE 49130 REDEVELOPMENT AND MANAGEMENT OF THE MAGNUS FIELD FOR POST-PLATEAU PRODUCTION 11

    Figure 6: Magnus recent production by source

    0

    20000

    40000

    60000

    80000

    100000

    120000

    140000

    160000

    180000

    Sep-94

    Nov-94

    Jan-95

    Mar-95

    May-95

    Jul-95

    Sep-95

    Nov-95

    Jan-96

    Mar-96

    May-96

    Jul-96

    Sep-96

    Nov-96

    Jan-97

    Mar-97

    May-97

    Jul-97

    Sep-97

    Nov-97

    Jan-98

    Mar-98

    Production(stb/d)

    Base pre 1994

    Interventions

    New Producers New Injectors

    JAN. 1994 A1 A3 A4 A5 A6 A7 B1 B3 B5 B7 D6G G G G G G E G G G G

    11 Wells E E E E E E D E E E E36 Open Zones D C C A L C C C C D3.3 zones/well C A A A

    L L

    JUN. 1998 A1 A2 A3 A4 A5 A6 A7 B1 B2 B3 B4 B5 B6 D9G E G G G G G E G G G G G G

    14 Wells E D E E L E E E E E E E E17 Open Zones D C C C L C C C C C D1.2 zones/well C A A L A L C

    L L

    Figure 7: Showing wells with zones present and open perforations in black (D9 is a subsea well)

    0%

    25%

    50%

    75%

    100%

    125%

    0 1 2 3 4 5 6 7 8 9 10 11 12 13 14

    Number of Years Well on Production

    CumulativeP

    ercentageof

    OilPo

    tential

    Figure 8: Age of well versus cumulative percentage of present (June 1998) production. The remaining well

    existing from before the end of plateau has had one major intervention to restore production and is supported

    by two new injectors.

  • 8/3/2019 1998 SPE49130 Day Griffin Martins

    12/13

    12 SIMON DAY, TIM GRIFFIN AND PAUL MARTINS SPE 49130

    0

    10000

    20000

    30000

    40000

    50000

    60000

    Aug-95

    Sep-95

    Oct-95

    Nov-95

    Dec-95

    Jan-96

    Feb-96

    Mar-96

    Apr-96

    May-96

    Jun-96

    Jul-96

    Aug-96

    Sep-96

    Oct-96

    Nov-96

    Dec-96

    Jan-97

    Feb-97

    Mar-97

    Apr-97

    May-97

    Jun-97

    Jul-97

    Aug-97

    Sep-97

    Oct-97

    Nov-97

    Dec-97

    Jan-98

    Feb-98

    Mar-98

    Apr-98

    Producti

    on/Injectionbbl/d

    M31z:C4 INJECTION

    M34:C3 INJECTION

    M26:A4 GROSS PRODUCTION RATE

    0

    5000

    10000

    15000

    20000

    25000

    30000

    35000

    40000

    45000

    50000

    Apr-95

    Jun-95

    Aug-95

    Oct-95

    Dec-95

    Feb-96

    Apr-96

    Jun-96

    Aug-96

    Oct-96

    Dec-96

    Feb-97

    Apr-97

    Jun-97

    Aug-97

    Oct-97

    Dec-97

    Feb-98

    Apr-98

    Production/Injectionbbl/d

    F2 INJECTION

    M31z:C4 INJECTION

    COMPETITION FROM

    M30z:A5

    M24:B4 GROSS

    PRODUCTION RATE

    0

    5000

    10000

    15000

    20000

    25000

    30000

    35000

    40000

    Jul-96

    Aug-96

    Sep-96

    Oct-96

    Nov-96

    Dec-96

    Jan-97

    Feb-97

    Mar-97

    Apr-97

    May-97

    Jun-97

    Jul-97

    Aug-97

    Sep-97

    Oct-97

    Nov-97

    Dec-97

    Jan-98

    Feb-98

    Mar-98

    Apr-98

    Production/Injectionbbl/d

    M31z:C4 INJECTION

    M6:B3 INJECTION

    FLUSH PRODUCTION FROM

    INJECTION DURING

    PRODUCTION SHUTDOWN

    M10:A3 GROSS PRODUCTION RATE

    M10:A3

    M2 7:B2

    M26:A4 M6:B3

    M24:B4

    M31z:C4

    12A-F2M34:C3

    MSMESupport

    M10 :A 3

    M2 7:B2

    M26:A4

    M 24:B4

    12A-F2

    M6:B3

    M31z:C4

    M33:C7

    Figure 12: Shows the correlation,

    evolved through time, of the crestal G

    sands using well picks and connectivity

    information from production data. Wells

    M24:B4 and F2 apparently have the same

    sand bodies in different depth order - a

    geological problem.

    Figure 13: Problem resolved by

    assuming reservoir thinning (possible

    from seismic) and that connectivity

    between M24:B4 and F2 is via lower

    sands. Given the changes in G sand

    description to date, this is probably an

    interim resolution.

  • 8/3/2019 1998 SPE49130 Day Griffin Martins

    13/13

    SPE 49130 REDEVELOPMENT AND MANAGEMENT OF THE MAGNUS FIELD FOR POST-PLATEAU PRODUCTION 13

    Initial Reservoir Pressure

    Plateau Decline

    0

    1000

    2000

    3000

    4000

    5000

    6000

    7000

    83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98

    Year (start)

    D

    atu

    m

    Pr

    essu

    re(psia

    )

    RFT Data

    Surveillance D ata

    Figure 14: Shows RFT and PLT pressure data from the crestal G sands. The

    increasing range in pressures due to dedicated injection and zonal completions

    illustrates how the level of complexity of a field can be masked during plateau.


Recommended