+ All Categories
Home > Documents > 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of...

19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of...

Date post: 04-Apr-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
40
19 th National Award for Excellence in Energy Management 2018 UltraTech Cement Limited Unit: Kotputli Cement Works Presenting Team Members :– Mr. Rajnish Roshan (Manager Electrical) Mr. Neeraj Pundir (Asst. Manager WCM/ ISO)
Transcript
Page 1: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

19th National Award for Excellencein Energy Management 2018

UltraTech Cement Limited

Unit: Kotputli Cement Works

Presenting Team Members :–

Mr. Rajnish Roshan (Manager Electrical)

Mr. Neeraj Pundir (Asst. Manager WCM/ ISO)

Page 2: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

Equipment Make Rated Capacity Benefits

Raw Mill Loesche GMBH 735 TPH Improved energy

efficiency, Easy

maintenanceCoal Mill Loesche GMBH

50 TPH for Pet

Coke

First Vertical

Cement Mill in

UTCL

Loesche GMBH 2 X 215 TPH

Kiln KHD GMBH

8000 TPD on

100% Pet coke

Mechanically

designed for

10000TPD

Six- Stage Pre-

heater twin stringKHD GMBH -

Enhanced heat &

mass transfer

Pyro floor clinker

cooler with roller

crusher

KHD GMBH -

High heat

recuperation

efficiency

Online Cross Belt

Analyzer, XRF (02

nos.), XRD (01 no.)

Thermoscientific,

PAnalytical-

Efficient Quality

Control System

Company Profile

KCW was

commissioned in

the year 2009 with

clinker production

capacity of 3.3

MTPA (10,000

TPD)

Page 3: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

GOOD

670

675

680

685

FY16 FY17 FY18

680.4

675.5 675.4

Cement Dispatch (Million MT)Specific Heat Consumption

9300

9500

9700

9900

FY16 FY17 FY18

9494

9753 9772

Cement Dispatch (Million MT)Kiln TPD

Unit Performance – Last Three Years

GOOD

50

52

54

56

58

FY16 FY17 FY18

57.0155.33

53.65

Cement Dispatch (Million MT)Sp. Power Upto Clinkerisation (KWH/MT Clk)

72

74

76

FY16 FY17 FY18

74.43

75.57

73.53

Cement Dispatch (Million MT)Overall Sp. Power Cons. (KWH/MT cement)

GOOD

GOOD

Page 4: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

Unit Energy Performance Comparison: At A GlanceWith benchmark/cluster units performance (Year 2017-18)

Overall sp. Power Consumption (Kwh/MT cement)

Sp. Heat Consumption (Kcal/kg clinker)

647

675 677 675

687

650

660

670

680

690

International Benchmark

National Benchmark ACC Cement Kotputli Cement(UTCL)

Vikram Cement(UTCL)KCW

64.00 65.05 64.50

73.53

65.70

40

60

80

100

International Benchmark

National Benchmark Reddipalyam(UTCL)

Kotputli Cement(UTCL)

J K Cement

Ref- For International Benchmark report of Industrial Energy Efficiency Benchmarking Report for Cement Sector by United Nations Industrial Development Organization. Ref. For National Benchmark Data Best Thermal energy efficiency award by NCCBM & CII Energy benchmarking for cement Industry Ver-2 May-15

GOOD

GOOD

Page 5: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

➢ Adopting Digitization by Installation of plant optimizer in Raw Mill, Cement Mill

operation for performance improvement.

➢ Installation of WHR (16 MW)

➢ Retrofitting/ replacement of Energy efficient fans at Major Fans.

➢ Increasing TSR by executing CAPEX for AFR feeding system.

➢ Modification in Pre heater by increase in height of stage –II cyclone roof along

with riser duct, cyclone inlet portion modifications for both Strings for pressure

drop reduction.

➢ Replacement of existing Cooler with high efficiency cooler

Road Map for Benchmarking

Page 6: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

GtG energy consumption status

993

937

711670 641 656

400

600

800

1000

1200

2009-10(Baseline year)

Target SEC forPAT cycle 1

ActualPAT Cycle 1

BaselinePAT Cycle 2

TargetPAT Cycle 2

Status PATCycle 2

Kcal

/kg

PP

C E

qu

iv.

No. of Energy Saving Certificates 37153

Unit is registered as Designated Consumers (DC) under PAT scheme.Target given for 4.32 % reduction in GtG Specific Energy Consumption for PAT

Cycle-2 (FY18-19)

28.40 % reduction

PAT Status

Page 7: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

SN. Energy Saving theme

Energy Saved/yr Savings(Rs.Lac/yr)

Elect (MWH)

Thermal (Mkcal)

1Start of cold meal injection system for eliminating coating formation & reducing cleaning process by water jet

- 6499 67.5

2 Raw Mill cyclone dip tube modification 231.9 - 67.5

3Heat of formation reduction by Raw Mix optimization

- 2559 22.1

4

Reduction in Limestone, Additives & Coal transport Idle run hours for power optimization by DCS interlocking w.r.t to load (KW).

850 - 34.0

5Maintaining A/S ratio for enhanced petcokeutilization with stable operation by Raw Mix optimization

- 2973 25.6

Energy saving initiatives with Zero Investment

Page 8: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

SN. Energy Saving theme Energy Saved/yr Savings(Rs.Lac/yr)

Elect (MWH)

Thermal (Mkcal)

6Pressure drop reduction of cooler fans (11 Nos.) by removing louvre dampers

643 - 22.50

7Removal of all Flow regulators(MFR) from chamber-2 ,3,4 & 5 of cooler resulting in chamber pressure reduction

428 4284 53.30

8Optimization of 2 coal firing blowers by line modification &running at low air to material ratio

257 - 9.0

9Cement mills power reduction by optimizing the reject circuit running hrs

82.2 - 2.90

10Reduction in packing plant bag filter fan power by change in drive system

576 - 20.20

11 Reduction in idle running of cooling tower fan 12.96 - 0.50

Energy saving initiatives with Zero Investment

Page 9: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

SN. Energy Saving theme Energy Saved/yr Savings(Rs.Lac/yr)

Elect (MWH)

Thermal (Mkcal)

12Optimization of preheater water spray system

362 18.10

13Optimization of coal firing blower RPM after burner modification

161 8.0

14Stopping of cooling air fan after burner modification

137 6.80

15Reduction in Gypsum feeding circuit idle running hrs

21 1.0

16Scoop plate installation to enhance cement mill productivity

27 1.40

17Power reduction by changing 56 nos. motor connection from delta to star

113 5.60

Total 3902 16315 366

Energy saving initiatives with Zero Investment

Page 10: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

SN. Energy Saving theme

Energy Saved/yr Savings(Rs.

Lacs/yr)

Invest(Rs. in Lacs)

Payback (months)Elect

(MWH)Thermal (Mkcal)

2015-16

1Fuzzy logic installation for Kiln /Cooler

269 584 15.8 47.0 36

2Installation of castableretainer in DSC toenhance refractory life

- 1038 8.90 3.0 4.0

3

Increased therecuperation efficiencycooler by airflowmodification

- 6225 28.9 1.0 0.42

4

Modification in cooler water spray for minimizing water cons. & cooler outlet temp.

- 6225 53.7 0.5 0.11

Energy saving initiatives with Investment

Page 11: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

SN. Energy Saving theme

Energy Saved/yr Savings(Rs.

Lacs/yr)

Invest(Rs. in Lacs)

Payback (months)Elect

(MWH)Thermal (Mkcal)

5

Reduction in pressuredrop by installing baffleplate in all 4 nos. topcyclones of Preheater

1345 - 53.8 1.0 0.22

6

Preheater top cyclone water spray system installation for reducing power

721 - 28.9 94 39

7Installation of Static synchronous compensator (STATCOM)

591 - 23.6 18.7 9

8Replacement of kiln firing root blower with screw compressor

232 - 9.3 5.4 70

Energy saving initiatives with Investment

Page 12: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

SN . Energy Saving theme

Energy Saved/yr Savings(Rs.

Lacs/yr)

Invest(Rs. inLacs)

Payback (months)Elect

(MWH)Thermal (Mkcal)

9Removed venturi from Cement Mill 1 Bag House fan inlet duct

221 - 8.8 5 7

10Removed venturi from Raw mill fan inlet ducts

311 - 28.0 3 1.28

118 Watt CFL in colony replaced by 5W LED lamps

1.4 - 0.1 0.5 105

Energy saving initiatives with Investment

Page 13: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

SN . Energy Saving theme

Energy Saved/yr Savings(Rs.

Lacs/yr)

Invest(Rs. inLacs)

Payback (months)Elect

(MWH)Thermal (Mkcal)

2016-17

12Pressure drop reduction of cooler fans (11 Nos.) by removing Silencers

279 - 9.70 1.50 2

13Optimization of compressor run hrs by various modifications

236 - 8.20 8.0 12

14PH Fan inlet duct enlargement

300 - 10.50 11.0 13

15Removal of venturi from Cement Mill-2 Fan inlet duct

198 - 6.10 0.50 1

Energy saving initiatives with Investment

Page 14: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

SN . Energy Saving theme

Energy Saved/yr Savings(Rs.

Lacs/yr)

Invest(Rs. inLacs)

Payback (months)Elect

(MWH)Thermal (Mkcal)

16Raw Mill table liners & rollers replacement

3342 - 117 107 11

17

Radiation losses reduction by attending all areas of refractory wear & tear

- 2142 19.10 1.0 1

18Extending the Thermal wall(Null point) by 800mm for retaining heat

- 3213 28.70 1.0 0.4

19Installed PID based VFD at Post clinker compressor house

277 - 9.70 8.50 11

20Installed PID based VFD at Pre Clinker compressor house

149 - 5.20 8.50 20

Energy saving initiatives with Investment

Page 15: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

SN . Energy Saving theme

Energy Saved/yr Savings(Rs.

Lacs/yr)

Invest(Rs. inLacs)

Payback (months)Elect

(MWH)Thermal (Mkcal)

21Installed Energy Efficient Pump at Pre Clinker Pump House

30.5 - 1.10 11.0 124

22Cement Mill -1 Bag house Fan Inlet Box enlargement

95.13 - 3.30 0.50 2

23Cement Mill -2 Bag house Fan Inlet Box enlargement

94.18 - 3.30 0.50 2

24Reduction in separator power of cement mills by removing slave roller

113 - 4.0 2.80 8

25Energy saving by replacing existing conventional light fittings with LED light

53 - 1.90 21.0 136

Energy saving initiatives with Investment

Page 16: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

SN . Energy Saving theme

Energy Saved/yr Savings(Rs.

Lacs/yr)

Invest(Rs. inLacs)

Payback (months)Elect

(MWH)Thermal (Mkcal)

2017-18

26VFD installation in Raw mill bag filter fans

237 - 11.90 1.50 2

27Lower RPM motor installation in bag filter fan

119 - 5.90 1.50 3

28Installation of VFD in Pyro-1 coal firing blower

241 - 12.10 4.50 4

29Raw Mill fan inlet duct enlargement

151 - 7.50 10.0 16

30Installation of energy efficient pump in post Clinkerisation pump house

257 - 12.90 4.20 4

31Usage of AFR in place of petcoke

- 7277 20.20 3.06 2

Energy saving initiatives with Investment

Page 17: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

SN . Energy Saving theme

Energy Saved/yr Savings(Rs.

Lacs/yr)

Invest(Rs. inLacs)

Payback (months)Elect

(MWH)

Thermal (Mkcal)

32Energy saving through change drive system of packer bag filter fans.

346.6 - 16.04 3.28 2.5

32Power saving by replacing existing conventional light fittings with LED light fitting.

85 - 4.20 24.20 68

33Enhancement in burner pipe castable life by using new generation hasle castable

- 455 24.4 8.0 4

34Classifier area reduction of cement mill separator

544 - 2.70 4.0 18

Total 10839 27159 605.44 426.14 9

Energy saving initiatives with Investment

Page 18: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

Project 1 – Energy saving through change drive system

Objective:-

Energy saving through change drive system of packer bag filter fans (8 nos fan)

Project Description

➢ Packer bag filter fans was direct coupled drive and run at 1500RPM consuming

around 35-37 KW per fan

➢ All the fans were damper controlled

➢ We worked out the optimum RPM to control the dust emission and resulting

power reduction.

➢ Changed the drive system from coupling to belt drive, installed 265 PCD pulley

at motor and 315 PCD pulley at fan side.

Page 19: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

Before

After

Results:-

1. Reduction in fan RPM from 1485 to

1260

2. Power saving of 12 KW per fan.

3. Cost Saving of 16.08Lacs/annum

Project 1 – Energy saving through change drive system

Page 20: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

Project 2 - Energy Saving by installing energy efficient Pump

Objective:-Installing energy efficient pump at Post Clinker Pump house to minimise power consumption of parallel pumping system.

Project Description:-For post clinker cooling water system two pumps are operating in parallel and supplies cooling water from underground water tank mainly to compressor house, Cement Mill-1 & 2.

Parallel operating efficiency of pumps 531WP-1 & 2 is 67.4%. It is less than design value of 76%. Individual pump efficiency is measured 68%. (less than design).

Considering above energy efficient pump of 45KW (2 no’s) at 531WP-1 and 531WP-2 is installed.

Page 21: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

Post clinker – Cooling water system layout

Results:-

1. Saving of 32.0 KW achieved on overall loading of post clinker pumping system

2. Cost Saving of 12.90Lacs/annum

Project 2 - Energy Saving by installing energy efficient Pump

Page 22: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

Project 3 - Energy saving through by modification in identified bag filters fans

Objective:-

Energy saving through by modification in identified bag filters fans at Raw Mill.

Project Description:-➢ 331BF1 bag filter fan was running with 60% damper opening to have effective

purging and pressure loss across the damper is 300mmwc.

We Installed VFD for above bag filter fan, and removed damper control

➢ 331BF2 bag filter fan was running with 60% damper opening but pressure loss across the damper is 310mmwc.

We Installed VFD for above bag filter fan, and removed damper control

Page 23: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

Results:-

➢ Total reduction of 60KW achieved.

➢ Cost Saving of 16.5Lacs/annum

Project 3 - Energy saving through by modification in identified bag filters fans

➢ 361BF5 bag filter fan was running with 60% damper opening to have effective purging and pressure loss across the damper is 380mmwc.

Installed Lower KW (37 to 30KW) and RPM (1500 to1000) Motor.

Page 24: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

S.N. Energy Saving theme

Potential Energy Saving Target For

CompletionElect (MWH)

Thermal (Mkcal)

1. Installation of expert optimizer in Raw mill 1200 - Jun-18

2.Installation of expert optimizer in Cement Mills

1350 - Jun-18

3.Installation of VFD in raw mill transport bag filter fan

59 - Nov-18

4.Incorporating the baffle plates in stage IV cyclone riser duct for both the strings

950 - Jul-18

5.To increase the height of stage –II cyclone roof along with riser duct, cyclone inlet portion modifications for both Strings

634 - Jul-18

6.VFD installation in Clinker silo top bag filter fan

95 - Dec-18

Plan matrix for Future ENCon Projects

Page 25: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

S.N. Energy Saving theme

Potential Energy Saving Target For

CompletionElect (MWH)

Thermal (Mkcal)

7.Retrofit of bag house fan (kiln bag house) with high design operating efficiency fan

836 - July-19

8.Improve efficiency of Pre heater fan-2

514 - July-18

9.Installation of VFD at compressor (Pre and Post clinker)

524 - Dec’18

10.Optimising efficiency of pre and post pumping system

296 - Mar-19

11.VFD installation in Pyro-2 coal firing blower

238 - Jul-18

Plan matrix for Future ENCon Projects

Page 26: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

S.N. Energy Saving theme

Potential Energy Saving Target For

CompletionElect (MWH)

Thermal (Mkcal)

12.VFD installation in cement mill bag filter fans

198 - Dec-18

13.Retrofit of cement mill bag house fans due to low efficiency of fans

1350 - Jan-19

14. Installation of WHR system 3960 - Mar-19

15.Installation of modular lining (Hasle) in all feed pipes of cyclones.

- 4148 Jul-18

16. Usage of AFR upto 1.0% TSR - 22000 Mar-19

Total 12204 26148

Plan matrix for Future ENCon Projects

Page 27: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

Utilization of Renewable Energy sources/ Waste Material

➢ Solar Power Generation (kwh)

0

50000

100000

150000

2015-16 2016-17 2017-18

10

81

26

10

01

36

11

19

97

Utilization of waste material

➢Use of Fly ash up to 34.2 % in PPC production

➢Use of Rubber chips, Plasticwaste,FMCG Waste in fuel firing

➢Use of wet Flyash about 10% of total PPC production.

➢ REC purchased 12499 solar certificates under RPO

Page 28: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

2000400060008000

1000012000

FY15 FY16FY17

FY18

4543 4762 5792

11715GOOD

Municipal Solid Waste PLANT : JAIPUR

102% increase over last year Production

Utilisation of Waste Material as Fuel

0

0.2

0.4

0.6

0.8

% TSR

2017-18 2018-19 (YTD-July'18)

Enrichment in TSR by increasing usage of AFPLASTICWASTE, AFRUBBERCHIPS and AFFMCGWASTE as an AFR

Page 29: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

Proposed AFR feeding arrangement .

Capacity - 3000 Tons Per

TSR - 25%

Status:

• Proposal prepared and submitted,

• Capex proposal to be submitted by 10th

Sept’18

• Estimated cost Rs. 1800 lacs.

Utilisation of Waste Material as Fuel

Page 30: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

GOOD

CO2 Emissions (kg CO2/ton of Cementitious product)

660

670

680

690

700

FY15-16 FY16-17 FY17-18

677.00

699.00

680.00

GHG Inventorisation

Page 31: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

Green Supply Chain

❖ While procuring the Motors, AC’s, luminous products & refrigerators we are incorporating the Clause of Energy efficient Products needs to be supplied with ratings mentioned.

❖ Implemented usage of Day light in Main Stores/Brick go down there by decreasing the Power consumption.

❖ Implementation of RTGS/NEFT for making online payment instead of Cheque Process there by reducing the Paper Consumption.

❖ Increasing the Vendor Management inventory to save multi packing & Shipments.

❖ Re-use of incoming boxes for outgoing materials.

❖ Reduction of carbon foot print by developing the reverse logistics & reduce the Co2 emissions.

Page 32: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

Unit Head

FH(Tech)

Crusher & RMCH Raw Mill

Kiln & Coal Mill

Cement Mill

Packing Plant

S.No. Monitoring and reporting

1 Daily Power Report

2Daily Section Performance Review Report

3 Daily Compressor Power Report

4 Daily HOF Optimization Report

5 Daily Idle run hrs report

Page 33: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

Opportunity identification

Energy mapping

Bench marking

Lost cost matrix

Suggestion

Idea generation

Idea screening

Feasibility study

Returnable CAPEX

proposal and

sanction

Separately budgeted

Team formation

Project Execution

Review of progress

Result Achieved

Reward & Recognition

Methodology for identification of improvement projects

Page 34: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

EVALUATION TEAMAPPROVER

COMMITTEECONCERN (dpt)

ENGINEERSFIELD OPERATOR AND

WORK MAN

Suggestion and kaizen steps

Kaizen Award

13001350140014501500

13

68 14

26 14

84

Approved Kaizens

Manthan program for idea sharing

Page 35: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

Celebration of Energy conservation month

Training program on Energy Conservation and efficiency / ISO-

50001 system

Page 36: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

ISO 50001-2011 Energy Policy Carbon Policy

Page 37: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

Major Achievements

Reduction in sp. water consumption by proper monitoring & metering in each Section

➢ Water Balance Index of Ultratech Cement Limited - 2.18 (Positive)

➢ Water Balance Index Kotputli Cement Works - 2.46 (Positive)

Result declared on Apr’30 2018 by External agency DNV.GL

Consequently won second cycle of ABG WCM Gold award in 2017 (Previous -2015)

Page 38: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

38

Under category of Thermal Power Stations

(Less than 100MW Coal & Gas) Sector.

Award received on 14th Dec 2017 at Vigyan Bhavan, New Delhi by honorable

President of India

National Energy Conservation Award 2017 (First Prize)

Page 39: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

NCCBM National Award for Best Thermal Energy Performance

Received on 08th Dec 2017 At New Delhi in 15th NCB International Seminar

National Benchmark in Specific Heat Consumption

Page 40: 19th National Award for Excellence in Energy Management 2018 · 2018-09-13 · consumption of parallel pumping system. Project Description:-For post clinker cooling water system two

CII Energy Efficient AwardConsecutively 6th year..


Recommended