Date post: | 30-Mar-2015 |
Category: |
Documents |
Upload: | zechariah-paddy |
View: | 218 times |
Download: | 0 times |
1. R&D for HTS cable and FCL
2. Grid application Program - Outline
Hyun, Ok-Bae
IEA THS ExCo Meeting/18 May 2009, Tampere
AMERICAN SUPERCONDUCTOR RECEIVES WIRE ORDER FOR FIRST SUPERCONDUCTOR POWER CABLE TO BE DEPLOYED IN KOREA’S COMMERCIAL GRID- LS Cable to Manufacture and Install 22.9 Kilovolt Superconductor Power Cable System in Korea Electric Power Corporation’s Grid Near Seoul- World’s Largest Commercial Order for Second Generation Superconductor Wire to be Delivered in 2009; Cable to be Energized by End of 2010 HANNOVER, Germany – April 20, 2009 – American Superconductor Corporation (NASDAQ: AMSC), a leading energy technologies company, today announced at Hannover Fair 2009 that LS Cable Ltd. (LS Cable) has ordered approximately 80,000 meters (50 miles) of 344 superconductors, which is AMSC’s proprietary brand of second generation (2G) high temperature superconductor (HTS) wire. LS Cable will utilize the wire to manufacture a 22.9 kilovolt (kV) cable system that it will install in Korea Electric Power Corporation’s (KEPCO) commercial power delivery network near the city of Seoul in 2010. Founded in 1962 and based in Anyang, South Korea, LS Cable is Korea’s largest power cable manufacturer with nearly 8,200 employees worldwide and annual sales in excess of US$6 billion. This is the single largest commercial order for 2G HTS wire in the world. “With the ability to carry vast amounts of electricity in a small right of way,
Test application of HTS cable and FCL) at the real grid under KETEP - KEPCO program
R&D for HTS cable and FCL
R&D under DAPAS and ETEP program1.Development under 21C Frontier Program, DAPAS
1. 22.9 kV, 1,250 A HTS cable
2. 22.9 kV, 630 A HTS FCL
2.Operation test at KEPCO Gochang Test Center
1. 2 HTS Cable Tests, 22.9 kV, 1,250 A, 3 phases
1. KEPRI – Sumitomo cable
2. LS Cable
3. Each installed and operated at isolated power system
2. 1 HTS FCL, 22.9 kV, 630 A, 3 phases
1. Installed and being operated at an no-load power line
Performance testOperation skillReliability test
Commercial Operation at an real power grid
KEPCO Gochang Test Center
Gochang Test center
Daejeon
• Electrical Operation Characteristics : 22.9 kV, 1250 A, 50 MVAManufactured by Sumitomo Electric
• Physical Characteristics : 100 m long, Cold dielectric Three phase in one cryostat Three in one termination
LS HTS cable
KEPCO HTS cable
KEPCO HTS cable test system
HTS Cable Acceptance Tests have been done
1. Factory Witness Test2. Long Term Rated Load Test - 1250 A rated current was
loaded continuously for approximately 32 days 3. Load Cycle Test
Cryogenic System Response Dielectric Properties During Load Cycle Test
4. Thermal Cycle Test5. History of the Critical Current6. Heat loss dependence on Thermal Cycle Test7. Simulated overload cooling test 8. Unbalanced 3Φ Load Test9. And more
Evaluation of 100 m long 22.9 kV 50 MVA HTS Cable System
HTS Cable and Test by LS Cable
HTS Cable System Cold Dielectric 22.9kV (Nominal), 13.2kV(Phase) 3 Types of cryo-coolers incorporated
for comparison
HTS Cable Diameter : 145mm (Nominal) Aluminum Cryostat PVC Sheath ~ 35kV Insulation level (Nominal) 3 - phases in one cryostat FC Stabilizer incorporated
Physical and electrical layouts
Ground level
Joint box
Tunnel (55 m)
Pipe Duct [15 m]
Termination (Power source)Termination (Load)
Jointbox
U-bend
Termination (Load) Termination (Power source)
On the ground[30 m]
Configuration of system installation
( Fully simulating real grid conditions )
100 m
Configuration and thermal layouts
HTS+Cryostat Fast Switch CLR
Control & Monitoring PartsH 1.2 m × L 2.4 m × H 2.5 m
DevelopmentFabrication and short-circuit test of a SFCL (22.9 kV/630 A 3)Line commutation type, small size and low costSatisfying local requirements (ratings, size, reclosing, limitation time, etc)
item rating
Rated V 25.8 kV
Rated I 630 A
Ic 900 A
Rated withstand V
50 kV, 1 min
HTS recovery < 50 ms
ReclosingLess than 0.1 s, next
event ready
CL 2 Ω
Vacuum Interrupter
15 kV, 1,250 A, 31.5 kA
Cryocooler 220 W at 80K
Operation Temp.
70~72K(T: 0.5K)
Development and operation test of HTS FCL
0 20 40 60 80-10
-5
0
5
10
15
20
CLR: 24.7kArms
Cu
rren
t (k
A)
Time (msec)
Fault current Limited current
R-phase 5kA Fault test at PT&T in LSIS
14kApeak
0 20 40 60 80 100 120 140-40
-30
-20
-10
0
10
20
30
403-phases 10kA Fault test at PT&T in LSIS
Fault current R S T
Limited current R S T
Time (msec)
Cu
rren
t (k
A)
SFCL development and tests
Operation test facility
Test items Content
Short circuit test and protection coordination
1. Short circuit tests2. SFCL - CB – recloser coordination
Long term operation 1. Long term operation, remote control2. Operation assessment, Operation cost, etc
Emergency case 1. Handling emergency2. Bypassing the line in emergency
Load test 1. Short term load test
Maintenance practice 1. Part (HTS, …) replacements2. Cryocooler maintenance w/o bypassing
Operation test – to be done
A project for HTS cable and FCL application in the real grid1. Planned and approved in 20082. Project started by Nov. 2008 (SFCL starts by Nov. 2009)
Project Goal : 1. Grid application of 22.9 kV, 50 MVA HTS cable (500 m)
and 22.9 kV, 630 A SFCL – O & M technology2. 22.9 kV, 150 MVA HTS cable and 22.9 kV, 3,000 A SFCL
Grid application program
Title : Development of O&M Technology for Applying 22.9kV HTS Cables and FCLs to the Commercial Power Grid Sub1 : Power System Analysis for Applying 22.9kV HTS Cables and FCLs to the Commercial Power Grid Sub2 : Development of O&M Technology for Applying 22.9kV HTS Cables to the Commercial Power Grid Sub3 : Development of 22.9kV SFCL Fabrication and Operation Technology for Application to Commercial Power Grids
Period : November 2008 ~ October 2013 (60 Months) Sub3 : Nov. 2010 ~ Oct. 2013 (48 Months)
Fund : 24.28 Billion Won (Government : 12.12 BWon, KEPCO : 8.66 BWon, LSC : 3.50 BWon)
Project Overview
Targets
Phase 1
(Nov.’08 ~
Oct. ‘11)
• 22.9 kV, 50 MVA 500m HTS cable design, fabrication, installation
• Development of O & M Technology for 22.9 kV, 50 MVA, 500m
HTS cable
• 22.9 kV, 630 A SFCL grid application and 22.9 kV, 3,000 A SFCL
design, fabrication and test run
Phase 2
(Nov.’12 ~
Oct. ‘13)
• 22.9 kV, 150 MVA(100m or longer) HTS cable design, fabrication,
installation
• Development of O & M Technology for 22.9kV 150 MVA HTS cable
• 22.9 kV, 3,000 A SFCL real grid application
Project Targets
Prime Contractor
KEPCO HQ
Y. J. Won
Ministry of Knowledge Economy,
MKE
KETEP(Korea Institute of Energy and
Resources Technology Evaluation and Planning)
System Analysis
KEPRI
Co-worked with KERI, CBPC
HTS FCL
KEPRI
Co-worked with LSIS
HTS Cable
KEPRI
Co-funded by LSCCo-worked with LSC,
KERI, CNU, KBSI * LSC: LS Cable Inc. LSIS: LS Industrial Systems Co. KBSI: Korea Basic Science Institute KERI: Korea Electromagnetic Research Institute CNU : Chonnam National University CBPC : Chungbuk Province Colledge
Project Team
[Location of HTS cables]
154/22.9kV MTR
DS
CB
load load load
HTS Cable 500m
HTS Cable 500m
HTS Cable 500m
HTS cable installation schemes - proposed
D/L
154/22.9 kV M.Tr
SFCL
SFCL 3,000 A SFCL
630 A SFCL
DSCB
D/LD/L
SFCL installation scheme
HTS Cable1. AMSC 2G wire (AMSC 344) by October 2009
The largest contract of 2G wireTo be delivered till October 2009
2. HTS cable systemCable system to be completed by DecemberTo be installed in 2010
SFCL1. Operation test will continue through 20102. SFCL system (upgraded) to be completed by upper half
of 2010, and to be installed by the end of 2010
Installation by 2010
Icheon
Incheon
Seoul
Icheon S/S
Icheon substation
이천 변전소
Simulated duct on a breast wall
slope
On the ground
Manhole, joing box (on the surface)
Duct
열거동 관측지점(Off-Set)
Terminals2 Sets
Cooling & Control
On the ground
Cable layout – One of the 3 proposals
1
A underground feeder surfaced to connect the SFCL near the fence
SFCL layout - A proposal
22.9 kV HTS cable and SFCL have been developed and operation-
tested
Real grid application and test-commercial operation of
1. 22.9 kV 50 MVA (500 m) HTS cable
2. 22.9 kV, 630 A and 3,000 A SFCL
3. To be installed in 2010 in Icheon S/S
Summary
Demand for 22.9 kV line protection – SFCL proposed
KEPCO is seeking a solution to control the increased fault current associated with the system upgrade in the 22.9 kV grid
1. BackgroundIncreased power demandUpgrade the 154/22.9 kV substationsReplace the 154 kV/22.9 kV MTR 60 MVA 100 MVA
2. ProblemIncreased fault current at the 22.9 kV sideFault current > the Max. allowed value
• Search a solutionUpgrade all feeders, %Z increase, … : No!
• SFCL proposed at MTR 22.9 kV sideCost effectiveSimple procedures
For MTR protection or bus-bar connectionIrated 3 kA, To be developed
Y∆ MTR
154 kV/22.9 kV100 MVA
Y∆
SFCL
CB
For feeder protection