Regional Connector Transit Project 1 st /Central Community Leadership Council monthly meeting Construction Update February 8, 2016
Transcript

Regional Connector Transit Project 1st/Central Community Leadership Council monthly meeting

Construction Update February 8, 2016

Construction Update

> Ongoing construction activities

> Mangrove yard

> 1st/Central yard

> 1st/Alameda intersection work

> Construction schedule & Look-ahead

> 2nd St. grouting

> Central Ave. 20” water line

> 1st/Alameda pile and deck

> Excavation of 1st/Central Station

2

Ongoing Construction Activities

> Eastbound 1st St widening completed

> Street light improvements completed

3

Ongoing Construction Activities

> Mangrove yard— Gold Line track demolition & relocation

> 1st/Central yard & 1st/Alameda— Continuation of piling

4

2nd Street Grouting Potholing

> January 26 for two weeks; complete February 9

> 9 a.m.–3:30 p.m.; parking restricted

> One lane in each direction

5

Zanja Madre Brick Pipe

2nd Street Grouting Potholing

Zanja Madre Brick Pipe

2nd Street Grouting Potholing

Construction Schedule – 2016 Look-Ahead

8

Construction Schedule – 4-Week Look Ahead

9

Schedule & Sequence of Work

Activity Proposed Dates

> 2nd St. Grouting

> Between San Pedro and Central Ave.

> Motorist traffic: one lane in each direction

> Pedestrian access maintained

> Potholing is necessary to confirm utilities prior to activity

> Removal of two trees

> As early as March 11 for four months

> Jan. 26 for two weeks;

complete Feb. 9

> 20” water line work on Central Ave. between 1st St and 2nd St.

> Outreach on-going with the affected stakeholders

> One night water service interruption to tie in the water lines

> Southbound Central Ave. open; northbound directional closure > Local access and driveways will be maintained

> As early as Feb. 15 for two weeks

> Feb. 29—water service

interruption

> Pile & deck at 1st/Alameda

55 hour full weekend closure, piling & decking

> Alameda between Temple and 3rd St. > 1st St. between Alameda and Vignes

> Ongoing through Summer 2016

10

2nd Street Grouting/Soil Improvement Video

11

2nd Street Grouting – Street Parking Maintained East of the Mid-block Crosswalk

Existing Phase 1 -

North side

Phase 2 -

South side

Meter parking

38 spaces 17 spaces 20 spaces

Commercial

loading zone

4 – north side

1 – south side

2 – north side

1 – south side

2 – north side

1 – south side

12

2nd Street Grouting - North side

13

2nd Street Grouting - North side

14

2nd Street Grouting - South side

Sidewalk open

15

2nd Street Grouting - South side

16

Central Ave. Water Line Work

> February for approx. three weeks

> Southbound access open

> Northbound access restricted (nights only)

> Pedestrian access maintained

17

Track Relocation at 1st/Alameda January 8–February 5

18

Utility, Pile & Deck at 1st/Alameda 55 Hour Weekend Closures

> Jan. 29–Feb. 1

> Feb. 5–7

> Local access maintained

19

Track, Utility, Pile & Deck at 1st/Alameda February 5–May 2016

20

Utility, Pile & Deck at 1st/Alameda May–August 2016

21

Steady State Summer 2016

22

Community Outreach

> Distributed construction notices since 1/25 meeting

> Utility investigation on 2nd St. between Central Ave. and San Pedro St.

> 55-hour weekend closure at 1st St./Alameda St.

> Construction activities behind K-rail at 1st St./Alameda St. intersection

> Mangrove Yard sound wall installation

> Start of station excavation at 1st St./Central Ave. yard

> Reached stakeholders through the following methods:

> E-blast to over 3,600 email addresses

> Door-to-door briefing

> Door-to-door distribution with in ½ mile radius

> Website

> Social Media posts to audience of 5,000

23

Community Outreach

> Individual briefings to approx. 50 businesses on the following activities:

> Temporary commercial loading zone on 2nd St

> Permeation grouting on 2nd St

> Ongoing coordination with stakeholders on upcoming 20’ water line relocation and tie-in on Central Ave. between 1st St. and 2nd St.

> One night—water service interruption to 14 businesses

> Assessing water needs and mitigations with individuals

24

Construction Mitigation Banners

> Bulleted copy.

> Bulleted copy.

`

Southeast Corner of 1st/Alameda

West Side of 1st/Alameda Intersection

Eastbound 1st St across from Buddhist Temple

East 1st/Central Intersection Crosswalk

Along Westbound 1st St Sidewalk 25

Contact Us