+ All Categories
Home > Documents > 2. Community and stakeholder engagement - Amazon S3 · 2. Community and stakeholder engagement 2.1...

2. Community and stakeholder engagement - Amazon S3 · 2. Community and stakeholder engagement 2.1...

Date post: 03-Jun-2020
Category:
Upload: others
View: 11 times
Download: 0 times
Share this document with a friend
12
Works Approval Application RO097400.WAA.23.04.2018 18 2. Community and stakeholder engagement 2.1 Overview AP is committed to engaging with all stakeholders, including community members, local businesses, associations, agencies, regulatory authorities and State/Commonwealth government members. AP aims to engage in meaningful dialogue with stakeholders so they can be adequately informed of the EfW Project and AP’s activities. This chapter provides a summary of the community and stakeholder engagement activities undertaken by AP, or on their behalf, for the EfW Project and details the engagement activities planned for the future. The chapter will outline key issues and concerns raised during these engagement efforts and how they will be addressed by AP to alleviate any community concern and minimise any potential risk. This chapter also sets the broader context of AP’s relationship with the community by describing the existing framework for public consultation in relation to operation of the Maryvale site. While it will touch on the existing consultation activities undertaken in association with the Mill’s operations, this chapter is focussed on the issues within the scope of the WAA, specifically the issues relating to the addition of the EfW facility to the Maryvale Mill and key works required in delivering the feedstock waste to site. AP is well known to the local community - it is the largest private employer in the region and has existed on the Maryvale site since 1937. Through the engagement and consultation efforts undertaken to date, the community has shown significant interest in the Project and what it means for the region. As the Project is important to the long-term viability of a major employer in the region, the local community is one of a range of important stakeholders that has significant interest in the proposed development. The potential for the EfW Project was first discussed with community members through the ‘Maryvale Community Consultation Committee’ (MCCC) in May 2017, set up by AP in 1994 to provide a regular interface between AP and representatives of the community. Since then, AP has undergone a series of engagement activities to inform the community of the proposed Project, to take stock of the opinions of stakeholders and address any issues raised. This has involved a number of focus groups to gauge their views on an EfW plant to service the Mill and the establishment of a Project Office and Information Centre in the Morwell CBD. Key issues about the proposed Project and its operations raised during these activities have included air quality, odour, social impacts, employment, community engagement, noise, management of feedstock, waste and water quality. 2.2 Principles of community engagement The purpose of the stakeholder engagement undertaken for the Project and the broader Maryvale Paper Mill has been to interact with stakeholders to: Disseminate information to inform key stakeholders and the community about the Project Define the extent of potential impacts and risks to the environment and the community, and to identify community perceptions and concerns Mitigate the concerns and provide a communication channel between the community and AP. The principles used as the basis of engaging with stakeholders on this project have been to: Initiate and maintain open and transparent communications between stakeholders and AP Build on existing stakeholder relationships whilst also identifying other relevant stakeholders Develop consultation appropriate to the diversity of stakeholders (and their interests) affected by the proposed Project Deliver consultation that is appropriate and accessible to affected parties
Transcript
Page 1: 2. Community and stakeholder engagement - Amazon S3 · 2. Community and stakeholder engagement 2.1 Overview AP is committed to engaging with all stakeholders, including community

Works Approval Application

RO097400.WAA.23.04.2018 18

2. Community and stakeholder engagement

2.1 Overview

AP is committed to engaging with all stakeholders, including community members, local businesses, associations, agencies, regulatory authorities and State/Commonwealth government members. AP aims to engage in meaningful dialogue with stakeholders so they can be adequately informed of the EfW Project and AP’s activities.

This chapter provides a summary of the community and stakeholder engagement activities undertaken by AP, or on their behalf, for the EfW Project and details the engagement activities planned for the future. The chapter will outline key issues and concerns raised during these engagement efforts and how they will be addressed by AP to alleviate any community concern and minimise any potential risk.

This chapter also sets the broader context of AP’s relationship with the community by describing the existing framework for public consultation in relation to operation of the Maryvale site. While it will touch on the existing consultation activities undertaken in association with the Mill’s operations, this chapter is focussed on the issues within the scope of the WAA, specifically the issues relating to the addition of the EfW facility to the Maryvale Mill and key works required in delivering the feedstock waste to site.

AP is well known to the local community - it is the largest private employer in the region and has existed on the Maryvale site since 1937. Through the engagement and consultation efforts undertaken to date, the community has shown significant interest in the Project and what it means for the region. As the Project is important to the long-term viability of a major employer in the region, the local community is one of a range of important stakeholders that has significant interest in the proposed development.

The potential for the EfW Project was first discussed with community members through the ‘Maryvale Community Consultation Committee’ (MCCC) in May 2017, set up by AP in 1994 to provide a regular interface between AP and representatives of the community. Since then, AP has undergone a series of engagement activities to inform the community of the proposed Project, to take stock of the opinions of stakeholders and address any issues raised. This has involved a number of focus groups to gauge their views on an EfW plant to service the Mill and the establishment of a Project Office and Information Centre in the Morwell CBD. Key issues about the proposed Project and its operations raised during these activities have included air quality, odour, social impacts, employment, community engagement, noise, management of feedstock, waste and water quality.

2.2 Principles of community engagement

The purpose of the stakeholder engagement undertaken for the Project and the broader Maryvale Paper Mill has been to interact with stakeholders to:

Disseminate information to inform key stakeholders and the community about the Project

Define the extent of potential impacts and risks to the environment and the community, and to identify community perceptions and concerns

Mitigate the concerns and provide a communication channel between the community and AP.

The principles used as the basis of engaging with stakeholders on this project have been to:

Initiate and maintain open and transparent communications between stakeholders and AP

Build on existing stakeholder relationships whilst also identifying other relevant stakeholders

Develop consultation appropriate to the diversity of stakeholders (and their interests) affected by the proposed Project

Deliver consultation that is appropriate and accessible to affected parties

Page 2: 2. Community and stakeholder engagement - Amazon S3 · 2. Community and stakeholder engagement 2.1 Overview AP is committed to engaging with all stakeholders, including community

Works Approval Application

RO097400.WAA.23.04.2018 19

Deliver consultation that is timely and considerate of the time required for stakeholders to absorb and respond to detailed information

Maintain and/or establish an open and transparent process for stakeholders to help identify and address key concerns

Manage project obstacles by actively involving stakeholders in the identification and understanding of issues and, where appropriate, the development of solutions

Provide information about how project approvals will be undertaken and the role of stakeholders in these processes.

2.3 Identification of project stakeholders and community

Table 2.1 shows the local context of the Maryvale Mill, situated north of Morwell and west of Traralgon – the EfW Plant will be located wholly within the existing Maryvale Mill.

AP has conducted a thorough process for the identification of stakeholders, reaching out to existing contacts in the local community, advertising in the broader media and meeting with a range of regulatory authorities. In producing a Communications and Engagement Plan for the Project, AP has identified the following stakeholders listed in Table 2.1 below.

Table 2.1 : Identified project stakeholders

Stakeholder group Stakeholders Stakeholder interest in the project

Commonwealth

Government

Departments or

Agencies

Department of Environment and Energy

Department of Health

Department of Infrastructure and

Regional Development

Clean Energy Regulator

Co-ordinating ‘whole of Government’ response to the introduction

of the EfW technology: benefits to regional, state and national

economy, introducing renewable baseload energy, environmental

and public health compliance and reuse solution

Inter-Government and interagency co-ordination

Consistent and accurate messaging to community and

stakeholders

Demonstrating environmental and public health compliance

measures

Commonwealth

Elected Members

Prime Minister – The Hon Malcolm

Turnbull

Former Minister for Infrastructure and

Transport – The Hon Barnaby Joyce MP

(National)

Minister for the Environment and Energy

- The Hon Josh Frydenberg (Liberal)

Minister for Health - The Hon Greg Hunt

(Liberal)

Minister for Regional Development -

Senator The Hon Fiona Nash (National)

Member for Gippsland and former

Minister for Infrastructure and Transport -

The Hon Darren Chester MP (Nationals)

Whole of the Government response

Managing reputational risk to Government

Consistent and accurate messaging to community and

stakeholders relating to benefits and compliance

Understanding of the project, the capability of the technology and

its application in the setting

Victorian

Government

Departments &

Agencies

Department of Premier & Cabinet

Latrobe Valley Authority (LVA)

Environment Protection Authority (EPA)

Department of Environment, Land, Water

and Planning (DELWP)

Department of Economic Development,

Jobs, Transport and Resources

Co-ordinating ‘whole of Government’ response to the introduction

of the technology: benefits to regional, state and national economy,

introducing renewable baseload energy, environmental and public

health compliance and reuse solution

Inter-Government and interagency co-ordination

Consistent and accurate messaging to community and

stakeholders

Demonstrating environmental and public health compliance

Page 3: 2. Community and stakeholder engagement - Amazon S3 · 2. Community and stakeholder engagement 2.1 Overview AP is committed to engaging with all stakeholders, including community

Works Approval Application

RO097400.WAA.23.04.2018 20

Stakeholder group Stakeholders Stakeholder interest in the project

(DEDJTR)

Regional Development Victoria (RDV)

Department of Health and Human

Services (DHHS)

Sustainability Victoria (SV)

measures

Victorian

Government Elected

State Members

The Premier of Victoria – Hon Daniel

Andrews MP

Minister for Health – Hon Jill Hennessy

MP

Minister for Industry & Employment – The

Hon Ben Carroll MP (and previously the

Hon. Wade Noonan MP)

Minister for Energy, Environment and

Climate Change - Hon Lily D’Ambrosio

MP

Minister for Planning – Hon. Richard

Wynn MP

Minister for Agriculture and Regional

Development – Hon. Jaala Pulford MP

Whole of the Government response

Managing reputational risk to Government

Consistent and accurate messaging to community and

stakeholders relating to benefits and compliance

Understanding of the project, the capability of the technology and

its application in the setting

Local Government

(Elected Members &

Administration)

Latrobe City Council,

Baw Baw Shire Council,

Cardinia Shire Council,

City of Casey,

Mornington Peninsula Shire

City of Greater Dandenong,

Bass Coast Shire Council

South Gippsland Shire Council

East Gippsland Shire Council

Wellington Shire Council

Approving any relevant planning controls

Understanding of the project, the capability of the technology and

its application in the setting

Consistent and accurate messaging to community and

stakeholders relating to benefits and compliance

Ensuring the interests of their local constituents are protected and

queries responded to

Other Authorities and

Peak Bodies

Infrastructure Victoria

Metropolitan Waste and Resource

Recovery Group (MWRRG),

Gippsland Waste and Resource

Recovery Group (GWRRG)

Gippsland Local Government Network

(GLGN)

Gippsland Water Factory

Australian Industry Group

Understanding of the project, the capability of the technology and

its application in the setting particularly with regard to the treatment

of municipal waste

Consistent and accurate messaging to community and

stakeholders relating to benefits and compliance

Representing the interests of their membership to deliver them the

best outcomes

Community Communities within proximity of Mill, and

townships within Latrobe City or near

transfer stations upstream of the Mill

Risks of impacts to human health and the environment, reduction in

the quality of life in the suburbs or towns surrounding the

operations and impact on property values and businesses.

Scepticism relating to previous environmental performance from

the Mill and the legacy of previous environmental accidents within

the region and the real or perceived risk and impact to human

health.

Page 4: 2. Community and stakeholder engagement - Amazon S3 · 2. Community and stakeholder engagement 2.1 Overview AP is committed to engaging with all stakeholders, including community

Works Approval Application

RO097400.WAA.23.04.2018 21

Stakeholder group Stakeholders Stakeholder interest in the project

Business Groups or

Commercial

organisations

Committee for Gippsland (C4G)

Traralgon Chamber of Commerce &

Industry Inc.

Advance Morwell (incorporating Morwell

Chamber of Commerce and Industry)

Moe Traders

Victorian Chamber of Commerce and

Industry

Qube Logistics

AUSNET

Potential Financiers

DASMA Recycling

Multifuel Energy (UK)

FCC (UK)

Ballast Phoenix (UK)

Carbon8 (UK)

Hitachi Zosen Inova

Keppel Seghers

Martin GMBH

Understanding of the project, the capability of the technology and

its application in the setting

Consistent and accurate messaging relating to benefits and

compliance

Representing the interests of their membership or organisation to

deliver them the best outcomes

Community or

Interest Groups

Voices of the Valley

Committee for Gippsland (C4G)

Maryvale Community Consultative

Committee (CCC)

Champions of the Bush

Federation University

Planet Ark

Understanding of the project, the capability of the technology and

its application in the setting

Consistent and accurate messaging relating to benefits and

compliance

Challenging the project and representing the interests of their

members or community to deliver them the best outcomes

Media Latrobe Valley Express

Gippsland Times

South Gippsland Sentinel Times

Weekly Times

ABC Gippsland

Prime 7

WIN TV

Channel 9 Gippsland

Gippsland FM 104.7

Hit Gippsland (FM)

3mFM (Community radio)

Local interest news

Understanding of the project, the capability of the technology and

its application in the setting

Representing the views of their listenership / readership and asking

questions and seeing information about the project

Unions Relevant unions associated with AP

operations (need specifics)

Industrial implications for their members

AP workforce Workforce at Maryvale Mill and Preston

sites

Impact on the stability and opportunities for their roles, the long

term viability of AP and any impact on their specific roles.

AP Board The Australian board of directors includes

AP Chief Executive Officer, AP Chief

Financial Officer, NPI Representative

Director and NPI Tokyo based directors.

The Australian board of directors is

comprised of five males and one female.

Review and endorsement (or otherwise) of the business case for

the EfW Plant

Page 5: 2. Community and stakeholder engagement - Amazon S3 · 2. Community and stakeholder engagement 2.1 Overview AP is committed to engaging with all stakeholders, including community

Princes Hwy

Strzel ecki H

wy

Ba ss

Hwy

Princes

FwyHyland

Hwy

Sout h Gippsla

ndHw

y

MORWELL

GDA 1994 MGA Zone 55

COPYRIGHT: The concepts and information contained in this documentare the copyright of Jacobs. Use or copying of the document in whole orin part without the written permission of Jacobs constitutes an infringementof copyright. Jacobs does not warrant that this document is definitive norfree of error and does not accept liability for any loss caused or arising fromreliance upon information provided herein.

DATA SOURCES© Commonwealth of Australia (Geoscience Australia) 2006 Geodata Topo 250k Series 3; Vicmap Data © State of Victoria 2017;Department of Environment, Land, Water and Planning 23/04/2017; Jacobs 2017DATA SOURCES © ESRI BaseMap

Boyds

Creek

AndersonCreek

Loy

Yang Creek

Bennetts

Creek

Whites

Cree

k

WildernessCreek

Plough

Creek

MorwellRiver

Bank Street

Mattingley Hill Road

Traral

gon-m

affra

Road

TraralgonCreek

Road

TanjilEast

Road

Maryval

eRo

adMo

nash

Way

Grey Street

Princes Street

LatrobeRiver

Road

Strzel

ecki

Highway Sanders Road

Alexan

ders

Road

Traralgo n WestRoad

NorthRoad

Morwe

ll-mary

vale

Road

Brown Coalmine R oad

Comme r cialRoad

Haun te d HillsRoad

Firmins Lane

Purvis Road

Tramw

ayRo

ad

Princes Freeway

Hazelwood

Road

PrincesDrive

Bartons Lane

Tyers-wa lhallaRoad

Glengarry

West

Road

Ma inRoad

DeCa

mpo

Drive

Cairnbrook Road

TyersRo ad

PrincesHighway

Latrob

e Ro

ad

John Field

Dr i ve

YALLOURNNORTH

TRARALGON

MORWELL

HAZELWOODNORTH

GLENGARRY

LegendProject Area Maryville Mill Complex

! Population centreMajor roadWatercourse

0 42kilometres

Document Path: J:\IE\Admin\03_Southern\Env_Spatial\10_Section_Resources\03_Spatial\RO097400\Spatial\ArcGIS\RO097400_RegionalContext.mxd

0 2010 km

Figure 2.1 : Regional context Australian Paper Energy from Waste Feasibility Study

RO097400

Date Published: 22 Mar 2018

±

Page 6: 2. Community and stakeholder engagement - Amazon S3 · 2. Community and stakeholder engagement 2.1 Overview AP is committed to engaging with all stakeholders, including community

Works Approval Application

RO097400.WAA.23.04.2018 23

2.4 History of community engagement and current engagement framework

Throughout the decades that AP has been operating within the Latrobe Valley, it has held a consistent focus on being approachable and maintaining transparent relationships with the key stakeholders and the local community relating to its operations and initiatives.

Over recent years, AP has established a track record participating in the local community by providing sponsorships to community and sporting organisations, as well as maintaining open and accessible relationships with local media outlets, either proactively or reactively in response to questions or issues.

AP’s Maryvale sponsorship committee provides financial support to and houses the Maryvale CFA Fire Brigade, and AP’s various operations provide financial and in-kind support to the following organisations and events:

Doxa Youth Foundation

KIDS Foundation

Christmas Party for Special Kids

Traralgon Apex Club

Lions Club of Morwell

The Flagstaff Group

Various local sporting groups, health support groups, schools and kindergartens, aged care and scouting groups.

AP is also a member of the Committee for Gippsland (C4G). This group includes small, medium and large businesses, industry, community organisations and education providers, where AP can contribute a voice in making Gippsland a more socially, environmentally and economically sustainable region.

The organisation maintains a clear and demonstrated commitment to a range of safety, quality, sustainability and environmental certifications across its operations. These efforts, around maintaining and exceeding compliance in these areas also contributes to AP’s reputation within the local community.

AP is committed to keeping their workforce informed about all areas of the business including production, financial performance, market related updates and other external matters of interest through various channels and on a regular basis. Briefings are also provided to trade union officials who represent AP employees.

Recent research which incorporated data collection from the Maryvale workforce demonstrates their strong engagement and interest in the role they and the Mill play in the local community and the role they and AP more generally can play in enhancing its reputation in the Latrobe Valley through increasing their efforts around grass roots engagement activities. Some community concerns relating to noise and odours from existing operations have been raised, however this has not adversely affected goodwill or the company’s reputation in the community over recent years.

AP also has the long established MCCC which meets quarterly to discuss the Maryvale Mill and its operations with selected community representatives. This regular meeting provides community members the opportunity to engage with AP about their operations and communicate any concerns on behalf of the Maryvale community.

2.5 Energy from Waste Project consultation

This section discusses the engagement activities conducted by AP specifically in relation to the development of the EfW Project. It highlights the efforts that AP has made to inform the community about the proposed Project and the outcomes of the engagement activities, ensuring the community has the opportunity to provide feedback.

AP initially undertook community consultation regarding its potential investment in an EfW plant. The first three community focus groups took place in August 2017 and were held in Traralgon, Moe and Morwell with

Page 7: 2. Community and stakeholder engagement - Amazon S3 · 2. Community and stakeholder engagement 2.1 Overview AP is committed to engaging with all stakeholders, including community

Works Approval Application

RO097400.WAA.23.04.2018 24

participants independently recruited so as to represent a broad cross section of the region. A second community consultation focus group was held in September 2017. This time AP advertised for interest in attending with the aim of encouraging community members with a particular interest or who were engaged to attend.

There was strong interest in the concept and important feedback on areas where the community wanted greater information was received.

Central to the engagement of the local community and businesses has been the establishment of the Project Office and Information Centre in the Morwell CBD (126 George St). This provides the public, interest groups and government agencies an opportunity to meet with Project personnel and ask questions about the Project and also highlights AP’s strong commitment to meaningful consultation and engagement. AP has actively encouraged community members and interested stakeholders to visit the Information Centre to learn more about the project and the technology being considered. This has included extensive advertising in local media outlets as well as distribution of project posters to local businesses in Morwell, Traralgon and Moe.

Table 2.2 : Stakeholder engagement activities completed to date

Dates Activity Detail

13/1/17 State Minister Briefing Minister D’Ambrosio visit to Maryvale Mill, with EfW briefing from David Jettner

and Julian Mathers

16/3/17 State Premier Briefing Premier Andrews briefed on EfW by senior NPI and AP executives

16/3/17 Prime Minister Briefing Prime Minister Turnbull briefed on EfW by senior NPI and AP executives

11/05/17 Presentations to the Maryvale

Community Consultative

Committee (CCC)

Presentation of the EfW concept and how this could integrate into the operations

of AP’s Maryvale plant and what will be covered by the feasibility study

Update of progress 10/08/17

09/11/17

09/07/17 European Technology Study

Tour

Visit leading technology options for thermal treatment – Moving Grate,

Circulating Fluidised Bed, and Bubbling Fluidised Bed. To provide additional

input into the evaluation of the most appropriate technology for the AP Proposal

Throughout 2017 Regular briefings to staff of AP’s

Maryvale plant

AP’s Maryvale staff were kept up to date with the status of the EfW feasibility

study at staff briefings throughout 2017

21-22/08/17 Focus groups One group of employees and three groups of community members were

recruited through a specialist market research firm to represent a broad cross

section of the region

The primary purpose was to gain insights into what the community understood

about EfW technology, and any concerns they may have about its adoption in the

Latrobe Valley and/or by Australian Paper

25/09/17 Community Forum Discussed the EfW concept and the AP Maryvale site in general with community

members who attended in response to advertisements in the local paper.

The primary focus was to understand the views of the local residents who were

actively engaged in the local community and/or Australian Paper / Energy from

Waste.

1/10/17 onwards Regular advertisements in the

Latrobe Valley Express

Advertisements to raise awareness of the EfW feasibility study and to encourage

community members to visit the Information Centre

05/10/17 Meetings with EPA staff Meetings were organised with various EPA personnel to discuss the project

01/11/17 High level discussion with senior managers at EPA

22/11/17 Discussion with different experts within EPA regarding details required for Works

Approval submission

08/12/17 Visit to the Morwell Project Office and Information Centre

19/10/17 Meeting with Regional

Development Victoria (RDV)

Meetings were organised with various RDV personnel to discuss the project and

which government departments and agencies had been brief and consulted.

Page 8: 2. Community and stakeholder engagement - Amazon S3 · 2. Community and stakeholder engagement 2.1 Overview AP is committed to engaging with all stakeholders, including community

Works Approval Application

RO097400.WAA.23.04.2018 25

Dates Activity Detail

October 2017 European Study Tour Tour of 4 EfW plants in Europe attended by representatives of Planet Ark,

Federation University, CFMEU, Jacobs, AP and Nippon Paper Industries

04/11/17 Meeting with Japanese Consul-

General

Provided the Japanese consul general an overview of the EfW feasibility study

Regular staff

briefings

22/11/2017

Maryvale employee engagement

briefings

The EfW concept was discussed with site staff and how an EfW plant could

integrate into Maryvale operations and what will be covered by feasibility study

23/11/2017 Meeting with Latrobe City

Council

Meeting to discuss AP’s consultation program

30/11/2017 Meeting with Latrobe City -

Planning

Overview of the Project, Statutory planning considerations and a planning

approvals pathway

1/12/2017 Meeting with Latrobe Valley

Authority (LVA) and RDV

Meeting to discuss progress of EfW feasibility study and inclusion in LVA New

Energy Jobs and Investment Prospectus

11/12/17 Information Centre opens to

public

Providing the community information on energy from waste as a concept and

what the Project would mean for the region. Includes interactive displays,

factsheets and tours

12/12/17 Meeting with Traralgon Chamber

of Commerce

Meeting with President to discuss EfW feasibility study and opportunities to

engage with members

12/12//17 Meeting with Advance Morwell Meeting with President to discuss EfW feasibility study and opportunities to

engage with members

13/12/2017 Meeting with DELWP Discussion on the need for an EES Referral and the timing of submission

13/12/17 Media release Media release updating on feasibility study

13/12/2017 Interview with ABC Gippsland

and Latrobe Valley Express

Interview on Energy from Waste feasibility study

15/12/17 Traralgon Chamber of

Commerce

Presentation to Members’ meeting to provide an overview of the EfW Feasibility

Study

15/12/17 EPA Regional Office tour of

Information Centre

Tour of Project information centre

16/12/17 Interview with Gippsland FM 25 min live interview with Gippsland FM on Energy from waste project

10/01/18 Tour of info centre- State MP Victorian Member of Parliament for Morwell Russell Northe toured the

information centre

11/01/18 Public notice about the

information centre

Win News ran a 30 second piece notifying the public that the Information Centre

is open for the public to visit

19/01/2018 Tour of the Information Centre by

the Gippsland Local Government

Network (GLGN)

Members of the GLGN toured the Project Information Centre, with a follow-up

briefing back at Latrobe City Council offices including the provision of an

Information Pack with Renewable Energy HuB & 5 Factsheets.

15/2/18 Presentation to Traralgon

Chamber of Commerce

Presentation by AP representative to TCCC’s AGM updating on progress of the

EfW feasibility study

19/02/18 Committee for Gippsland policy

update

Circulation to C4G members of policy update explaining EfW feasibility study

process

23/02/18 Committee for Gippsland

presentation

Present a project update to the board of the Committee for Gippsland

27/02/18 Morwell Business Information

Night

Invited local Morwell businesses to attend an information evening and briefing.

14/03/18 Interview with Gippsland FM 25 min live interview with Gippsland FM on Energy from waste project

14-17/03/18 Pop Up Info Centre – Traralgon Providing the community information on energy from waste as a concept and

Page 9: 2. Community and stakeholder engagement - Amazon S3 · 2. Community and stakeholder engagement 2.1 Overview AP is committed to engaging with all stakeholders, including community

Works Approval Application

RO097400.WAA.23.04.2018 26

Dates Activity Detail

Centre Plaza what the Project would mean for the region. Includes interactive displays,

factsheets.

103 groups of people engaged with over 4 days.

19/03/18 Opening of the Information

Centre

Providing the community information on energy from waste as a concept and

what the Project would mean for the region

21/03/18 DELWP Young Professional

Network (YPN)

Tour of Project information centre, presentation on sustainability at AP.

To date, the project Information Centre in Morwell has had 105 visitors and has hosted 25 delegations.

2.5.1 Key outcomes from consultation activities

The stakeholder engagement and consultation activities completed as detailed in Sections 2.4 and 2.5 have enabled AP to identify a range of considerations and concerns that stakeholders have in regards to the development of an EfW Plant at the Maryvale site. The key considerations and concerns include:

Air quality: A concern around air pollution and the impact of potential gases that would result from burning waste such as plastics and a related concern regarding the potential health impacts caused by air emissions

Odour: Concern that transporting, storing and burning rubbish may cause additional odour issues

Social impacts: Concern regarding the impact of rubbish trucks on local roads on local traffic

Social

- Concern that the Project would create the perception of the local community as ‘Melbourne’s dumping ground’

- Consideration regarding the future security of employment for employees of the existing Maryvale Mill

- Opportunities for future employment associated with direct roles and indirect downstream roles and business opportunities.

Community engagement: A desire for AP to keep the community informed with full open and transparent consultation and to take a proactive approach to engagement for the Project

Noise: Concern regarding legacy noise issues from the existing mill and the possibility the EfW plant could compound this

Waste: A concern surrounding the handling and disposal of the waste product from the incineration process

Water quality: A concern that leakage of contaminated material may contaminate groundwater.

2.5.2 Future planned consultation activities

AP intends to continue dialogue with stakeholders as the Project progresses so that all stakeholders can have the opportunity to be adequately informed about the Project and how it may relate to their circumstances. Table 2.3 outlines the key stakeholder engagement activities.

Table 2.3 : Planned stakeholder engagement activities

Timing Activity Detail

As required following

an approval

Meet with representatives from government

departments

The following government agencies will need to be met with to

engage with and educate on the project at various stages,

including:

DELWP

EPA

Page 10: 2. Community and stakeholder engagement - Amazon S3 · 2. Community and stakeholder engagement 2.1 Overview AP is committed to engaging with all stakeholders, including community

Works Approval Application

RO097400.WAA.23.04.2018 27

Timing Activity Detail

DPC

RDV

WorkSafe

Latrobe Valley Authority

MWRRG

GWRRG

Latrobe City Council

CFA

Quarterly Maryvale Community Consultative Committee

meetings

Present regular project updates to the MCCC, and use these

opportunities to identify any issues that community has with

the project.

Throughout 2018 Maryvale employee briefings Will be used to communicate the progress of the EfW

feasibility study to employees at the AP Maryvale site

Throughout 2018 Ongoing community engagement Advertising, Information Centre visits and public dissemination

of material to communicate the progress of the EfW feasibility

study

Throughout 2018 Ongoing business and community group

engagement

Continued presentations and dissemination of material to

business and community groups updating them on progress of

EfW feasibility study

19 February 2018 Committee for Gippsland policy update Circulation to C4G members of policy update explaining EfW

feasibility study process

23 February 2018 Committee for Gippsland presentation Present a project update to the board of the Committee for

Gippsland

April 2018 Public Information Session AP intends to hold a Public Information Session around the

time of submission of the EPA Works Approval and council

Planning Permit Applications. The purpose of the Information

Session is to update the public on the status of the approvals

and the Project and to hear any comments and feedback.

March 2018 Travelling Information Centre AP is constructing a portable Information Centre (‘Pop-up

shop’) which will be temporarily located in public areas in

Morwell, Traralgon and Moe. The purpose is to further raise

awareness with the public of the EfW project

March 2018 Committee for Gippsland Round table event Presentation to C4G Round table event on the EfW feasibility

study

March 2018 (tbc) Release of LVA New Energy Jobs and

Investment Prospectus

Inclusion in Prospectus of details of the EfW project and

potential impacts and benefits for the Latrobe Valley

25/3/2018 Maryvale Mill Open Day AP will have an Open Day at the Maryvale Mill. This is an

opportunity for the public to look around the Maryvale Mill and

meet with AP personnel.

March / April 2018 Community engagement campaign on EfW

emissions

Public information session to provide information to interested

community members on EfW plant emissions

2.6 Management of issues raised by the community and other stakeholders

Table 2.4 below lists the key issues and concerns raised throughout the community and stakeholder engagement activities completed to date, and how the concerns will be addressed throughout the construction and operation phases of the Project.

Page 11: 2. Community and stakeholder engagement - Amazon S3 · 2. Community and stakeholder engagement 2.1 Overview AP is committed to engaging with all stakeholders, including community

Works Approval Application

RO097400.WAA.23.04.2018 28

Table 2.4 : Community issues and concerns raised to date

Issue How the issue will be addressed

Air quality and

Health

Construction

Construction Environmental Management Plans (CEMPs) will be prepared in accordance with Environmental

Guidelines for Major Construction Sites (EPA Publication 480, 1996) prior to the commencement of construction.

These will include appropriate control measures for dust and emissions from construction equipment.

Operations

The plant is being designed to meet the State Environment Protection Policy for Air Quality Management (SEPP

(AQM)) and site specific emission limits set out by the EPA (outlined in the site licence which will be updated prior

to or during commissioning of the plant). The plant is also being design to meet the stack emissions standards set

in the European Union’s the Industrial Emissions Directive 2010/75/EU (IED).

Odour Operations

The plant will be designed to meet the State Environment Protection Policy for Air Quality Management (SEPP

(AQM)). Municipal waste will only be stored in a negatively pressured waste bunker, with air extracted sent to the

boilers to be combusted, destroying odorous gasses.

The waste transported to site will be in sealed or enclosed containers to minimise fugitive odour.

Water quality Construction

Construction activities will meet EPA guidelines. Construction environmental management plans will be prepared

demonstrating appropriate erosion and sediment control measures and other controls (e.g., no refuelling near

waterways). These plans may need to be approved by relevant government departments prior to construction

commencing.

Construction environmental management plans will also be prepared demonstrating appropriate control measures

for managing any construction impacts on groundwater.

Operations

Surface water runoff has been successfully managed on the site during its many years of operation. Limited water

outside of cooling tower water make up, dust and ash suppressant and for boiler steam production, is to be used

during operation of the EfW plant. Waste water is able to be handled by the Maryvale site’s water management

system.

The plant will be designed to meet the State Environment Protection Policy (Groundwaters of Victoria).

Social

(Traffic)

Construction

Throughout construction, the high level estimates of traffic accessing the site are 780-800 cars and approximately

26 trucks per day. Where practicable, construction traffic will also be directed to use the route mentioned below to

avoid impacts on local traffic.

Operations

During operations an additional 79 vehicles (assuming worst case of no rail logistics) are anticipated to be required

to visit the site per day.

Vehicles will access the site via the Princess Freeway (M1) and then Alexanders Road or Tramway Road.

Alexanders Rd carries 7,900 vehicles a day, while Tramway Rd carries an estimate 10,200 vehicles a day. Neither

are considered close to their capacity. By restricting the majority of vehicles to this route, the additional vehicles will

be largely able to avoid local traffic as these roads only have a minor residential access role.

Local Refuse Collection Vehicles (RCV) will likely travel directly to the EfW facility from their points of collection.

A Traffic Management Plan (TMP) covering construction and operations of the EfW plant will be developed in

consultation with the Latrobe City Council and VicRoads, and to the satisfaction of the Minister for Roads and Road

Safety, and this TMP may also form part of the planning permit for the Project.

Social (Reputation) Construction & Operation

AP will look to educate the wider community of the benefits that the EfW plant will have on the community and how

the EfW process actually works, providing facts of how existing plants and technology around the world have had

minimal negative impacts on their communities.

The community Information Centre in Maryvale, interviews with media outlets and empowering Maryvale

employees to promote the project are examples of how AP are working to ensure the Project earns a positive

reputation that matches its anticipated environmental performance.

Page 12: 2. Community and stakeholder engagement - Amazon S3 · 2. Community and stakeholder engagement 2.1 Overview AP is committed to engaging with all stakeholders, including community

Works Approval Application

RO097400.WAA.23.04.2018 29

Issue How the issue will be addressed

Noise impacts Construction

Construction activities will meet EPA guidelines for noise levels and working hours - Noise Control Guidelines,

Publication 1254 (Construction Noise)

Operations

The plant is designed to meet EPA Publication 1411 Noise from Industry in Regional Victoria (NIRV) requirements;

i.e. the EfW Plant will have no net contribution to the overall noise level experienced at the respective nearby

residences (houses) and hence no adverse impacts during operation. Details of these limits are outlined in Chapter

8: Noise Emissions of this WAA.

Community

Engagement

Construction

AP will ensure they are providing all interested stakeholders with updates about all relevant Project developments

throughout the approvals and construction phases of the Project. A community Information Centre has been

established for the Project in Morwell and a Project specific webpage and email address will be updated to ensure

that all stakeholders are able to access up to date Project information.

Operation

The Maryvale CCC, AP Maryvale site employee updates and maintenance of the Project webpage including AP

contact information will enable ongoing updates and provide a communication link with the community regarding

the operation and environmental performance of the EfW plant

Waste Operations

Modelling has shown that residual waste from the EfW plant will fall within the category of Industrial Waste. This will

require the waste to be transported and disposed of in accordance with the Industrial Waste Resource Guidelines.

Options for beneficial reuse are also actively being pursued.

Periodic testing will be undertaken in accordance with the Industrial Waste Resource Guidelines- Sampling and

Analysis of Waters, Wastewater, Soils and Waste, to ensure that the residual waste for the plant aligns with the

modelling that has taken place, ensuring that all waste materials are handled and disposed of appropriately.

2.7 Further information

Further information on the Project can be obtained from numerous sources, including the company website, via email, or in person at the EfW Information Centre, as described in the table below. AP welcomes all feedback from the community and agencies.

Contact details

Website https://www.australianpaper.com.au/about-us/creating-energy-from-waste/

Email [email protected]

Energy from Waste Information Centre 126 George Street

Morwell

Victoria, Australia


Recommended