Critical Path Method (CPM)
7/28/2019 2. Cpm
2/21
Sift Marketing Pvt Ltd 2
Network Diagram / Arrow Diagram / Node diagram
1
2
3
4
5
6
7
8
Source /
Start
Sink /
End
Nodes
3A
3G
7B
5C
9D
6E
7F 3
I
2H
7/28/2019 2. Cpm
3/21
Sift Marketing Pvt Ltd 3
Activity
Smallest subdivision of the work is called a job or activity
1 2Tail Event /
Starting Event
Head Event /
End Event
Fix up the chief guest (A)
Activity Activity Label
5 Days
Duration
Event Label
Hunt for chief guest begins Hunt for chief guest ends
7/28/2019 2. Cpm
4/21
Sift Marketing Pvt Ltd 4
Tips for drawing a network diagram
Correct ways to represent an activity:
1
2
2
2
1
1
A
A
A
5
5
5
7/28/2019 2. Cpm
5/21
Sift Marketing Pvt Ltd 5
Tips for drawing a network diagram . . . contd
Incorrect ways to represent an activity:
A
521
1) Gaps not allowed
A
5
2) Labeling of events
2A
5
3) Should have a definite start
1
4) Should have a definite end
? ?
7/28/2019 2. Cpm
6/21
Sift Marketing Pvt Ltd 6
Tips for drawing a network diagram . . . contd
Incorrect ways to represent an activity:
A
511
5) Equal event labels not allowed
21
6) Extra activity not allowed
A
5
12
7) Tail event label smaller than
head event label
A
5
81
8) Arrow is in centre of line
7/28/2019 2. Cpm
7/21
Sift Marketing Pvt Ltd 7
Tips for drawing a network diagram . . . contd
A, B, & C start together (parallel events)
1
2
3
4
3A
7B
5C
1
1
1
2
3
4
3A
7B
5C
Correct Method Incorrect Method
7/28/2019 2. Cpm
8/21
Sift Marketing Pvt Ltd 8
Tips for drawing a network diagram . . . contd
Series events:
1 2 37A
6B
B starts after A
1
2
3
3A
5B
4
8C
3D
52
E
A & B start together
C start after A
D start after B
E start after C & D
7/28/2019 2. Cpm
9/21
Sift Marketing Pvt Ltd 9
Problem - 1
Succeeding activityP Q R S T U V
Preceding activity
- P P Q R S,T UDraw Network Diagram
P
Q
R
S
T
U V765
4
3
21
7/28/2019 2. Cpm
10/21
Sift Marketing Pvt Ltd 10
Problem - 2
ActivityA B C D E F G H I
Preceding activity
- A A B B C E D,F G,HDraw Network Diagram
A
B
C
E
D
F
G
H I 876
5
4
3
21
7/28/2019 2. Cpm
11/21
Sift Marketing Pvt Ltd 11
Problem - 3
1 2 1 3 2 4 3 4 3 5 4 5 5 - 6Activity
Draw Network Diagram and identify different paths
65
4
2
3
1
1 3 5 6
1 2 4 5 6
1 3 4 5 - 6
7/28/2019 2. Cpm
12/21
Sift Marketing Pvt Ltd 12
Problem 4 (Practice)
Activity A B C D E F G H I J K
Draw Network Diagram and identify different paths
4
3
2
1
5
96
7
8K
J
A
H
G
F
E
D
C
B
A
1-2-5-8-9 1-3-6-8-9
1-3-7-9 1-4-7-9
7/28/2019 2. Cpm
13/21
Sift Marketing Pvt Ltd 13
Problem 5
a) A,C & D can start immediately b) E > B,C c) F,G > D
d) H,I > E,F e) J > I,G f) K > H g) B > A
1-2-3-5-7-8 1-2-3-5-6-
81-3-5-7-8 1-3-5-6-8
1-4-5-7-8 1-4-5-6-8
1-4-6-8
2
1
K
J
I
G
H
F
E
D
C
BA
8
7
6
5
4
3
Draw Network Diagram and identify different paths
7/28/2019 2. Cpm
14/21
Sift Marketing Pvt Ltd 14
Problem 6 (Practice)
a) A & B are start jobs b) A controls C, D & E c) B controls F & K
d) G depends on C e) H depends on E f) F control I
g) D controls J h) G, H, I , J & K are last activities
Draw Network Diagram and identify different paths
1-2-3-8 1-2-4-8
1-2-5-8 1-6-7-8
1-6-8
5
4
3
2
1
I
H
J
G
F
E
D
C
B
A8
76
K
7/28/2019 2. Cpm
15/21
Sift Marketing Pvt Ltd 15
Dummy Activity
A & B start together. C starts after A & B. Here two activities start together and alsoend together.
1 2B
A
Incorrect way
3C
7/28/2019 2. Cpm
16/21
Sift Marketing Pvt Ltd
16
Dummy Activity
A & B start together. C starts after A & B. Here two activities start together and
also end together. In this case insert a new activity called DUMMY activity. This
activity is inserted just for representation purpose with duration mentioned as = 0
1
2
3
3A
5B
42
C
1
3
2
3A
5B
42
C
00
D0 D0
Correct ways
7/28/2019 2. Cpm
17/21
Sift Marketing Pvt Ltd
17
Problem - 7
ActivityA B C D E F G
- A B B C C,D E,FPreceding activityDraw Network Diagram and identify different
paths
A B
D
CE
D0
F
G6
5
4
3217
1 2 3 - 4 6 7 1 2 3 5 6 - 7
1 2 3 4 5 6 - 7
7/28/2019 2. Cpm
18/21
Sift Marketing Pvt Ltd
18
Problem 8 (Practice)
Activity A B C D E F G H
Preceding activity - - A A B,C B,C D,E,F F
H
5
643
2
1
G
F
E
D
C
B
A
D0
1-2-5-6 1-2-3-5-6
1-2-3-4-6 1-2-3-4-5-6
1-3-5-6 1-3-4-6
1-3-4-5-6
Draw Network Diagram and identify different
paths
7/28/2019 2. Cpm
19/21
Sift Marketing Pvt Ltd
19
Critical Path
Critical Path is the path having longest duration
All the activities covered in critical path are called critical
activities
The duration to complete the critical path is called Project
Duration
Any delay in critical path will cause delay in the entire
project
7/28/2019 2. Cpm
20/21
Sift Marketing Pvt Ltd
20
Problem - 9
Activity 1-2 1-3 1-4 2-3 2-6 3-5 3-6 4-5 5-6 5-7 6-7Duration
7
6
4
3
2
1
5
7
68
3
12
6
8
40
8
6
1-2-6-7 = 8 + 8 + 8 = 24
1-2-3-6-7 = 8 + 6 + 4 + 8 = 26
1-2-3-5-7 = 8 + 6 + 6 + 6 = 26
1-2-3-5-6-7 = 8 + 6 + 6 + 0 + 8 = 28
1-3-6-7 = 7 + 4 + 8 = 19
1-3-5-7 = 7 + 6 + 6 = 19
1-3-5-6-7 = 7 + 6 + 0 + 8 = 21
1-4-5-7 = 3 + 12 + 6 = 21
1-4-5-6-7 = 3 + 12 + 0 + 8 = 23
Draw Network Diagram, find Critical
path & Project Duration
7/28/2019 2. Cpm
21/21
Sift Marketing Pvt Ltd
21
Problem 10 (Practice)
Activity A B C D E F G H J K L M N O
Preceding
Duration
Draw Network Diagram, find Critical path & Project Duration
5
4
3
2
1
O
N
M
L
K
J
H
G
F
E
D
C
B
A
1
1 2
3
3
45
1211
10
9
8
7
6
5
4
3
2
1
0
D0
66 D1
0
1-2-4-6-10-11-12 = 1+5+4+4+5+6 = 25
1-2-4-6-7-10-11-12 = 1+5+4+0+3+5+6 = 24
1-2-4-7-10-11-12 = 1+5+2+3+5+6 = 22
1-3-5-8-11-12 = 3+3+1+1+6 = 14
1-3-5-8-9-11-12 = 3+3+1+0+2+6 = 15
1-3-5-9-11-12 = 3+3+6+2+6 = 20