+ All Categories
Home > Documents > 2 Volume-II

2 Volume-II

Date post: 26-Jan-2016
Category:
Upload: zankar-parikh
View: 255 times
Download: 21 times
Share this document with a friend
Description:
SSNNl tender Document
Popular Tags:
366
SARDAR SAROVAR NARMADA NIGAM LIMITED (SSNNL) (A WHOLLY OWNED GOVERNMENT OF GUJARAT UNDERTAKING) SARDAR SAROVAR (NARMADA) PROJECT BIDDING DOCUMENT FOR EPC CONTRACT FOR CONSTRUCTION OF KACHCHH BRANCH CANAL- PACKAGE-V BETWEEN CH. 45.00 KM TO 54.900 KM (EARTHWORK, LINING, STRUCTURES, SERVICE ROAD, C.R./ESCAPE/H.R. GATES, STOPLOG,CONTROL CABIN,TURFING), ETC. COMPLETE TOGATHER WITH OPERATION AND MAINTENANCE OF THE SAME FOR FIVE (5) YEARS. ESTIMATED COST – RS. 277.97 CRORES CONTRACT NO : SSNNL/KBC/EPC/PACKAGE-V/ OF 2010 VOLUME – II Description of Project Extent of work Design criteria SUPERINTENDING ENGINEER RADHANPUR CIRCLE (SSNNL) JUNE 2010
Transcript

SARDAR SAROVAR NARMADA NIGAM LIMITED

(SSNNL)

(A WHOLLY OWNED GOVERNMENT OF GUJARAT UNDERTAKING)

SARDAR SAROVAR (NARMADA) PROJECT

BIDDING DOCUMENT

FOR

EPC CONTRACT FOR CONSTRUCTION OF KACHCHH BRANCH CANAL-PACKAGE-V BETWEEN CH. 45.00 KM TO 54.900 KM (EARTHWORK, LINING, STRUCTURES, SERVICE ROAD, C.R./ESCAPE/H.R. GATES, STOPLOG,CONTROL CABIN,TURFING), ETC. COMPLETE TOGATHER WITH OPERATION AND MAINTENANCE OF THE SAME FOR FIVE (5) YEARS.

ESTIMATED COST – RS. 277.97 CRORES

CONTRACT NO : SSNNL/KBC/EPC/PACKAGE-V/ OF 2010

VOLUME – II

Description of Project Extent of work Design criteria

SUPERINTENDING ENGINEER

RADHANPUR CIRCLE

(SSNNL)

JUNE 2010

CONTENT

Paragraph No.

Particulars Page no.

1 2 3

Chapter – 1

Project Description

1 Project Background. 1

Chapter – 2

Scope & Extent of Work

1.0 General 5

2.0 Extent of Work 5

3.0 Scope of Work 5

4.0 Civil Work 8

5.0 Gates Including Hoisting Arrangement and Electro Mechanical Parts

8

6.0 Operation and maintenance. 9

Chapter – 3

Employer’s Particular Requirement

1.0 Description of Project 11

2.0 Hydraulic Section of Canal 13

3.0 Details of Structures 14

4.0 Canal syphon in the depression 15

5.0 Geo-Technical Data 17

6.0 Borrow Area (BA) 17

Chapter – 4

Employer’s requirements for designs and Drawings (General)

1.0 Employer’s requirements for designs and Drawings (General)

24

Chapter – 5

Employer’s requirements for DESIGN

1.0 Employer’s requirements for designs 31

Chapter – 6

Employer’s requirements for submittals by the Contractor

1.0 Employer’s requirements for submittals by the Contractor

44

Chapter – 7

Data for Canal Structures

STRUCTURE DATA FOR THE PROPOSED STRUCTURE ACROSS THE BRANCH CANAL.

1.0 Details of the structure 47

Part-I General Description 48

Part-II Canal Data 49

Part-III Drain Data 54

Part-IV Road Data 59

Part-V Soil Data 63

Part-VI Plans / Documents 69

Paragraph No.

Particulars Page no.

1 2 3

Chapter – 8

Guidelines for Soil Explorations

1.0 General 75

1.1 Hydrological Information 75

1.2 Topographical Information 77

1.3 Sub Soil Information 77

2.0 Methods of Soil Explorations 79

3.0 Investigation Record and Sampling 80

Table-1 Details of Investigation in various Stages. 82

Table-2 Sub Soil Exploration Methods 87

Annex-1 Certificate 94

Annex-2 Data required for Computation of Settlement 95

Annex-3 Laboratory Tests 97

Annex-4 Size of Sample required for test 99

Annex-5 List of Indian Standards followed for foundation investigation

100

Chapter – 9

Criteria for Soil Investigation for canal and canal structures

CANAL STRUCTURES

1.0 Preamble 103

2.0 Order 103

Chapter – 10

Employer’s requirement with reference to the details to be covered up in specific drawings for canal structures

1 List of Drawings of DSY 111

2 List of Drawings of CSY 112

3 List of Drawings of VRB/UVRB/MDRB/SHRB (Deck slab Type)

113

4 List of Drawings of VRB/UVRB/MDRB/SHRB (Box Culvert Type)

114

5 List of Drawings of HR (Single pipe) 115

6 List of Drawings of HR (Double pipe) 116

7 For Open Type Escape (Radial Gate) 117

8 For Open Type Escape (Vertical Gate) 118

9 List of Drawings of CR (Radial) 119

10 List of Drawings of CR (Vertical) 120

11 List of Drawings of CR/Fall (Radial) 121

12 List of Drawings of CR/Fall (Vertical) 122

13 List of Drawings of CR/CSY 123

14 List of Drawings of CR(Radial)/VRB 124

15 List of Drawings of CR(Vertical)/VRB 125

16 List of Drawings for Super Passage 126

Paragraph No.

Particulars Page no.

1 2 3

Chapter – 11

Employer’s guidelines for detailed designs

1 Guidelines for design of Canal sections of Narmada Main Canal

128

2 Guide lines for design of Head regulator on Branch canals

177

3 Guidelines for design of Escape on Branch canal 185

4 Guidelines for design of Canal syphon on Branch canal

190

5 Guidelines for design of Drainage syphon/Culvert on Branch canal

216

6 Guidelines for design of Road bridges on Branch canal

233

7 Guidelines for design of Super passages on Branch 255

canal

8 Guidelines for design of Cross regulator on Branch canal

274

9 Guidelines for design of Cross regulator/Fall on Branch canal

290

10 Guidelines for Gate design 318

CHAPTER 12

Indicative Quantity Schedules for guidance of the bidder

ISQ 1 Earthwork 331

ISQ 2 Lining 333

ISQ 3 Structures 335

ISQ 4 Service Road 341

ISQ 5 Gate Works 344

ISQ 6 Control Cabin 349

1

Chapter – 1

Project Description

1. PROJECT BACKGROUND

1.1. The Sardar Sarovar (Narmada) Project is a multipurpose river valley project on the

west flowing river Narmada in Gujarat State located along the west coast of India.

The project is expected to provide irrigation benefits to a gross area of about 3.43

million hectares generate a maximum of 1450 MW i.e. about 950 MW hydro powers

at 60 percent load factor and provide partial flood control. The project is estimated to

cost about Rs. 1,31,806 Million at 1991-92 price level.

1.2. The Project includes 1210 m long and 163 m high concrete gravity darn to store 0.95

M ham water in the reservoir at FRL 138.68 m of which 0.58 M ham will be live

storage. Majority of the Dam work is already completed along with the impounding

reservoir.

1.3. The project also includes two power houses, one river bed power house (6 units of

200 MW each) and the other canal head power house (5 units of 50 MW each)

1.4. Four ponds are created between the main reservoir (Sardar Sarovar) and the head

regulator of the Narmada Main Canal by constructing rock fill dams (dykes) with a

view to provide balancing reservoirs for absorbing i variation in the discharge released

from the canal head power house. These ponds are interconnected by link channels.

1.5. The head regulator for the Main Canal is located at the fringe of the fourth balancing

storage pond.

1.6. The Main canal is one of the largest lined canal in the world having a capacity of 1134

rn (40,000 cusecs) at head and a length of about 460 km up to its tail at Gujarat

Rajasthan border where its capacity will be 71 m (2500 cusecs).

There are 42 branches offtaking from the Main Canal to serve a Gross Command Area

ot 3.43 million hectares (8.472 million acres) and Culturable Command Area of 2.12

2

Million hectares (5.236 million acres). The distribution system will involve construction

of 2500 km of branch canals and about 76,000 km. of distributaries, minors and sub

minors.

1.7. The climate in the project area is tropical with temperature ranging between 9 degree

C. and 45 degree C. The seasons in this region can broadly be classified as:

(i) Rainy season from middle of June to September with total annual rainfall

ranging from 500 mm to 600 mm (about 90 percent of the annual rainfall

occurs in this season)

(ii) Dry season from October to middle of June covering winter and summer.

1.8. The Saurashtra Branch Canal passes through the Kadi Taluka of Mehsana District,

Viramgam taluka of Ahmedabad district and Lakhtar, Patdi andWadhwan taluka of

Surendranagar District. The area of the alignment is of saline one. The salinity exists

in sub-soil and sub-soil water.

1.9. DETAILS OF KBC.

1.9.1. General:

Off-takes from : NMC ch. 384.814 Km. Village – Salimgadh, Ta. – Kankrej,

District - Banaskantha

Length : 360 Km (Patan – 51 Km), (Banaskantha – 33 Km),

(Kachchh – 276 Km)

Discharge : Max: 220 Cumecs

Min: 60 Cumecs

Falls (Small Hydro

Power Station)

: Chainage in Km 20.67 40.30 82.30

Magnitude in

Mt.

11.25 9.25 10.27

Lifts (Pumping

Stations)

: Chainage in Km 100.97 111.75 189.97

Magnitude in

Mt.

18.21 18.21 18.72

1.9.2. Command Area:

Branch Canal will traverse initially in a length of 84 Km. through Banaskantha district and the

rest of the alignment passes through the Patan & Kachchh districts. It will irrigate 63,111 Ha.

of Cultivable Command Area (CCA) in Banaskantha & Patan and 1,12,778 Ha. CCA in

3

Kachchh District.

1.9.2.1. The details of the beneficiary area is as under:

Sr. No. District Taluka No. of villages

benefited CCA in Ha.

1 2 3 4 5

1 Banaskantha

Kankrej 2 2098.00

Bhabhar 26 18494.00

Deodar 1 225.00

Vav 9 7501.00

Sub Total 38 28318.00

2 Patan

Radhanpur 2 850.00

Santalpur 39 33943.00

Sub Total 41 34793.00

3 Kachchh

Rapar 47 38560.00

Bhachau 33 25935.00

Bhuj 6 1343.00

Gandhidham 8 4135.00

Anjar 24 13367.00

Mundra 34 18240.00

Mandvi 30 11198.00

Sub Total 182 112778.00

Grand Total 261 175889.00

4

1.9.3. Because of a very typical topography the canal has to traverse, it has a provision of

three falls and three lifts on it. Small hydro stations are considered at the fall sites

and Pumping stations are considered at the lift sites.

1.9.3.1. Details of Small Hydro Power Stations on KBC:

Three Power Stations

Preparation of DPR Entrusted to MECON — India Ltd., Ranchi. Under progress. Final

Report Expected Shortly

Power Generation

(Proposed Installed

Cap.) MW

SHPS – I

3 x 3.33 = 10

II

2 x 3.33 = 6.66

III

2 x 3.33 = 6.66

Expected Annual

Generation (MU)

39.9 28.6 26.7

Turbine S-type Kaplan

Preparation of DTP is entrusted of NHPC – Delhi

5

Chapter – 2

Scope & Extent of Work

1.0 GENERAL

The objective behind taking up this bidding process is to award a contract on

Engineering, Procurement, Construction & Commissioning (EPC) basis for design and

construction of Kachchh Branch Canal, Canal Lining, Canal Structures, Gates and

Hoists etc. for flow of 220 cumecs of water in the Canal from Ch. 45.00 to Ch. 54.90

km. The indicative drawing showing the canal alignment with topographical data for

guidance of the bidders is given in the Volume-V “Drawings”.

The scope of work is indicative and suggestive. The bidder can review and refine the

components so as to ensure flow of 220 cumecs of water in the Canal as shown

hereinabove.

2.0 EXTENT OF WORK –incorporated in Chapter 3

3.0 SCOPE OF WORK

3.1 The major components of works to be designed, constructed and maintained

by the contractor under the scope of this contract shall be as described herein

after. The scope shall include all designs, drawings and construction with

procurement and supply of materials including supply and installation of plants

and equipments as may be necessary, services and facilities to meet with the

objectives of the work.

3.2 Design of canal and structures.

3.2.1 The Contractor shall prepare and submit design of the branch canal,

structures, transitions, flow measuring devices and lining of canal in

conformity with the basic parameters, terms and conditions contained in this

bid as well as in total compliance to the relevant Bureau of Indian Standard,

codes and general engineering practices including the systems and procedures

that are adopted by the Employer.

6

3.2.2 Data and information, indicative designs and drawings related to the Project

that are provided as a part of this bid documents are for general guidance and

for reference. The contractor shall have to examine, modify and present the

final designs and drawings to meet with the objectives of the project for

approval of the Engineer-in-charge. The works shall have to be executed,

tested and commissioned based on the designs and drawings that are finally

approved and accepted by the Engineer-in-charge or his authorized

representative.

3.2.3 The contractor shall prepare a Design Memorandum indicating design criteria,

design parameters, design assumptions, method of analysis for all components

of the Work, (Civil, Canal System and Structure, Hydro-mechanical). This

Memorandum shall be submitted to the Engineer-in- Charge for approval

before carrying out detailed design and construction drawings. The Design

Memorandum shall be based on the codes of practices published by the

Bureau of Indian Standards, standard engineering practices and the design

manuals that are prepared and used by the Employer.

The contractor, while submitting the detailed engineering designs and

drawings for all the components of works under the scope of this contract,

shall make and provide design reports based on the approved Design

Memorandum for approval of the Engineer-in-Charge or his representative.

3.2.4 The contractor shall prepare detailed engineering designs for the Civil Works

i.e., Canal System including structures and formulate construction drawings for

the execution and the work. The detailed engineering designs along with the

design calculations and construction drawings shall be submitted to the

Engineer in charge for approval. The Engineer-in-charge or his representative

will check and vet the submissions and shall either approve the submissions or

make observations and suggestions for further improvements / modifications

in the detailed engineering designs and construction drawings. The contractor,

as a part of his scope of contract, shall have to correct, modify or reframe the

7

detailed engineering designs and construction drawings to the entire

satisfaction of the Engineer-in-Charge and only such designs and drawings

that are approved and signed by the Engineer-in-Charge or his representative

shall be accepted as the contract designs and contract drawings. No designs

and drawings other than the approved designs and drawings shall be

permitted for construction of the work under the scope of this contract.

3.2.5 The contractor shall carry out detailed engineering designs of gates, hoisting

arrangement and electro mechanical parts including construction drawings

required for the execution of the Works, supported by design calculations.

Such designs and drawings shall be submitted to the Engineer-in Charge for

his approval as has been provided under Para 3.2.4 hereinabove.

3.2.6 The contractor shall conceive, develop and design control arrangement

including drawings required for the execution of the work shall submit the

same to the Engineer-in-Charge for approval.

3.2.7 The contractor, as a part of his design function under the scope of this

contract shall also have to frame additional designs, modify the accepted

designs on a need basis as per site requirements during the course of

construction and performance of this contract.

3.2.8 The contractor shall also prepare as-built drawings for Canal System, its

structures, Gates & electro mechanical parts etc. for final approval of the

Engineer-in-Charge.

3.2.9 The contractor shall adopt modern methodology / State of art Techniques in

design of structures and canal lining.

3.2.10 The contractor shall also prepare and submit a detailed methodology to be

adopted by him for construction and commissioning of the entire project

system for approval of the Engineer-in-Charge.

3.3 Survey and Investigation:

All survey, leveling, geotechnical investigation, soil testing shall be carried out by the

contractor as a part of the scope of this contract including preparing and presenting

8

drawings like index plans, general area drawings, contour plans, longitudinal sections

etc. as per standard engineering practices. The contractor shall as a part of his scope

of work shall collect all data that may be required for the purpose of design and

drawings as a part of his scope under this contract.

4.0 CIVIL WORKS:

The scope of work under the category of civil works covers provision of all labour,

plant and materials for and execution of all civil works, complete in all respect, as

described in conditions of contract and Technical Specifications of this Bid Documents

including incidentals and all necessary works not shown or specified but reasonably

implied or necessary for the proper completion and functioning of the Works in

accordance with the contract including any amendments thereof.

Broadly the scope includes,

• Construction of Kachchh Branch Canal including lining and all structure like

cross drainage works, communication structures, control structures like Head

Regulators, Cross Regulators, escape, control cabins etc.

• Service roads, approach roads and inspection path on canal system.

• Trial run and Commissioning of system.

• The contractor has to connect the U/S and D/S adjoining canal reaches.

5.0 GATES INCLUDING HOISTING ARRANGEMENT AND ELECTRO

MECHANICAL PARTS:

The scope of work under this section covers provision of all labour, plant and

materials for supply and execution of all hydro-mechanical works i.e , Gates,

including electromechanical, embedded Parts and hoisting arrangements complete in

all respect, as per Technical Specifications of Bid Documents including incidentals and

all necessary works not shown or specified but reasonably implied or necessary for

the proper completion and functioning of the Works in accordance with the contract

including any amendments thereof. Broadly the scope includes,

9

5.1 Detailing, supply and manufacture, inspection, shop assembly, testing,

painting etc.

5.2 Delivery, transit insurance, collection of equipment and custom clearance (if

any), inland transportation to site.

5.3 Site storage, including insurance, transportation and handling. Site erection,

painting, testing and commissioning including provision of bour, plant material

etc, for the above.

5.4 Handing over to Employer. Supply and installation of all incidentals not

specified but are necessary for proper completion and satisfactory functioning

of the system.

6.0 OPERATION AND MAINTENANCE:

The scope under this section covers the operation and maintenance of the facilities

created under the scope of this bid for Five (5) years as per the terms and conditions

put forth in the bid documents. The contractor shall prepare operation and

maintenance Manuals and submit to the Engineer-in-Charge for approval. Broadly the

scope includes,

6.1 To maintain whole canal system including, its structures and maintenance of

all gates.

6.2 To provide all services necessary to maintain the project efficiently, maximize

the availability of the project; optimize the useful life of the project etc.

6.3 To provide requisite numbers of qualified (and if required licensed) personnel

to perform the services.

6.4 To carryout maintenance of the total canal system and carry out repair and

preventive maintenance in accordance with the recommendations of the

Engineer-in-Charge.

6.5 To carryout any maintenance or repairs or rectification work in case of any

problem or emergency that may arise while the system is in-operation during

the maintenance and defect liability period of five years.

10

6.6 To provide technical and other assistance to the Engineer-in-Charge, in solving

operational and maintenance problems.

6.7 Maintain all roads, yards, walkways, the colony, house keeping and security of

the project.

6.8 Suggest improvements in the operation and maintenance schedule for better

performance.

6.9 To prepare Annual Operation Plan and submit to the Engineer-in-Charge for

approval.

6.10 To prepare gate operation schedule of all regulation structures and get it

approved by the Engineer-in-Charge.

11

Chapter – 3

Employer’s Particular Requirement

The contractor, as a part of his scope of contract as defined in Chapter 2 of this

document shall design, construct, commission and operate and maintain the project

system in total compliance of the particular requirements contained herein below:

1.0 Description of the Project – Kachchh Branch Canal Ch. 45.00 to 54.90

Km.

The construction of Kachchh Branch Canal in upstream and down stream of the

above mentioned chainage is partially completed. The alignment of Kachchh Branch

Canal Ch. 45.00 Km to 54.90 Km is finalized to gather with C.R. planning. The

alignment plans L/S are given in the Volume 5 Drawings.

SSP Canal system is designed on controlled volume concept and is planned to be

operated by canal automation. The salient features of the reach under consideration

are as under:

Salient Features:

1 Name of Branch Canal Kachchh Branch Canal (KBC)

2 Total Length under the scope of this

contract From Ch. 82.300 Km to

112.500 Kms

9.9 Km.

3 Starting Point Ch. 45.00 Km.

4 FSL of KBC at Off-take 50.25 m.

5 Bed Gradient 1: 10000

6 Design Discharge 220 cumecs.

7 Velocity 1.362 m/s.

12

8 Canal Section 16.50x(5.8+0.9) m.

9 Total Nos. of Distributaries:

Ch. 45.00 to 54.90 Km

2 Nos.

10 Total Nos. of Structures 15 Nos.

Type of Structure Chainage Nos.

VRB 45300 1

DSY 45673 1

CRVRB/ESCAPE. 46570 1

CSY 47930 1

DSY 49780 1

VRB 50819 1

HR (L) 51180 1

HR (R) 51180 1

VRB 51756 1

VRB 52810 1

DSY 53402 1

VRB 53712 1

DSY 54098 1

ESCAPE 54830 1

DSY 54880 1

13

2.0 Hydraulic Section of the Canal

2.1 Design of Canal Section for KBC at Off-take point from Ch. 45.00 to 54.90 Km

Bed Width B = 16.50 m.

Full Supply Depth (FSD) (d) = 5.80 m.

Bed Width / FSD (B/d) = 2.84

Side Slope of the Canal Bank, H:V.

(Inner)

= 2:1

Coefficient of Rugosity (N) = 0.018

Bed Gradient - S = 1:10000

Free board = 0.90 m

Lining C.C. M-15 Bed

Slope (up to T.B.L)

=

=

10.0 cm thick

12.5 cm thick

Parapet Wall = As per drawing ( Vol. - V )

Details of Distributories

Sr.

No.

Name of Distributory Off taking

chainage in m

Discharge in

cumecs

Sill level

in m

FSL in m

1 Patanka 51180 (L) 0.845 21.405 23.582

2 Charanka 51180 (R) 0.989 21.405 23.582

14

The details of Apex Point, list of benchmarks, FSL statement, rise and fall details are

attached to this chapter as Annexure 1 to 4 enclosed.

2.2 Lining in the canal section shall be done upto top of bank level with parapet

on the key as per detailed drawing. Lining shall be done in C.C. M-15 and parapet

shall be done in C.C. M-15 also.

2.3 Turfing shall be done on the outer slope and cut slope of the canal.

3.0 Details of Structures

The alignment of this branch canal is generally passing on ridgeline, of the terrain

and hence it crosses some cart tracks, village Roads, district Roads, and state

highways. The statement of cross drainage (CD) works proposed is given in FSL

statement.

SSNNL has to done the design & drawings for the above mentioned structures. The

drawings are kept under relevant section of the drawing volume. Bidder is free to

adopted these drawings for the construction purpose. However, the formal approval

as laid down in bid document is necessary.

Sr. Chainage

in Meters

Type of

Structure

Remarks

1. 45300 VRB As per drawing volume

2. 45673 DSY As per drawing volume

3. 46570 CRVRB/ESCAPE. As per drawing volume

4. 47930 CSY C.SY .between Ch.46690 to 49990 m

5. 49780 DSY As per drawing volume

6. 50819 VRB As per drawing volume

7. 51180 HR (L) As per drawing volume

8. 51180 HR (R) As per drawing volume

15

9. 51756 VRB As per drawing volume

10. 52810 VRB As per drawing volume

11. 53402 DSY As per drawing volume

12. 53712 VRB As per drawing volume

13. 54098 DSY As per drawing volume

14. 54830 ESCAPE As per drawing volume

15. 54880 DSY As per drawing volume

4.0 CANAL SYPHON IN THE DEPRESSION: 4.1 There is a long depression between Ch.46690 to 49990 m. on the

canal alignment, requiring an embankment of maximum height of 17 m. in

case of open channel construction. S.S.N.N.L. has decided not to construct

earthen open channel with high banking in this reach, but to construct a Canal

Siphon or a combination of canal siphon in the central portion of the

depression flanked on either side by safe and suitable structural arrangement

instead.

4.2 The maximum embankment height in the remaining reach would be

about 10 to 12 m, which need rigorous stability analysis of slopes under

various conditions and specifically under drawdown conditions considering the

properties of soil to be used for embankment.

4.3 Detailed design of such a long siphon is very critical. Uneven settlement

of foundation or uplift effects should be examined in detail as the soil 1 to 1.5

m below the natural ground surface is CH or CI type with saturated conditions.

Adequate foundation investigation shall be carried out by the contractor.

4.4 It has been observed that canal siphons tend to get silted up

considerably during the canal operation. The design should therefore,

incorporate features which would minimize silting and facilitate easy removal of

the deposited silt.

4.5 The siphon shall be designed with at least three rows of barrels so that

16

if one row is closed and isolated for any purpose at least two-thirds of the

design discharge can continue to flow.

4.6 For facilitating repairing of barrels and removal of silt, arrangements of

radial gates and stop logs shall be made so that each row of siphon barrels

can be closed and isolated in turns. Sufficient level floor length shall be

provided between barrel openings and radial gates/stop logs, as the case may

be, so that silt/slush loaded tractors with trolley are able to work there. An

earthen envelop, 10 m. wide, at the junction of C.R. and Canal Syphon having

its top at a level equal to FSL+Free board at that junction shall be constructed

to facilitate operation and maintenance of Stop logs, Radial gates and removal

of silt, debris etc. It shall be extended up to 10 m. (Ten) beyond the farthest

stop logs to be serviced on either side. There after it shall be joined with the

service road and inspection path with a gradient not steeper then 1:50. It shall

have a bituminous top and the outer slope shall be turfed. Steel railing shall be

provided on the envelop and approach road in high banking. Similar

arrangement to be provided in the D/S of the canal siphon also, i.e. at the

junction of canal siphon and stop log portion.

4.6.1 Lean concrete shall be provided below the siphon barrels if its bottom is

out of the ground.

4.7 KBC is partially completed in the U/S and D/S of this reach (45 to 54.9

km.).The introduction of a canal siphon will require additional head loss over

the one considered in approved C.R. planning. The contractor shall

accommodate this head loss in the U/S of the canal siphon only, by raising the

CBL/FSL/TBL appropriately in the U/S. The contractor is supposed to get the

revised CR planning done based on his design and shall get it approved from

SSNNL. The maximum additional head loss that shall be allowed for the design of the canal siphon is 0.7 m. only.

4.8 A float well shall be constructed in the upstream of the Cross

Regulating structure to be constructed at the upstream end of the canal

siphon.

4.9 Plain cement concrete (PCC) (M-15 grade) Lining shall be extended up

17

to the top of the slope and a PCC parapet should be constructed on the key of

the lining as per the detailed drawing given in the Drawing volume. Spoil banks

should be located well away with proper slope protection and drainage.

5.0 Geo Technical Data:

SSNNL has carried out geotechnical investigation on canal alignment as well as for

majority of the structures listed above. The same are kept at Annex- 5 for

reference. These data is only for reference and the bidder is supposed to carry out all

kind of Geotechnical investigation required for the design of structures mentioned

above in line with the bid conditions and as per good engineering practices.

6.0 Borrow Area (BA):

Preliminary design of the canal section has revealed necessity of soil from borrow

area for its construction. Borrow area investigation has been carried out by Employer

in nearby villages namely Zazam, Fangali and Varnosari. The data are kept at

Annex-6 for reference. The village maps showing the tentative locations of the

Borrow area are kept in the drawing volume. These locations and data are for

reference purpose only and the bidder is supposed to finalise the locations based on

his own survey and investigation and assess the quantity of earth required from the

BA based on his own design of the canal section.

18

Annexure-1 Statement Showing Details of Appex Point of Kuchchh Branch Canal From Ch. 45000 m to 60000 m

Sl. Appex

No. Chainage Chainage For bearing Back

Bearing Include Angle

Deflection Angle

Chainage of

Radius of

Tangent Length

Length of Remarks

No.

in m in m as

per (FB) (BB) Tangent Point-1 Curve

T=R tan O/2

Curve Curvature (T-1)

1 2 3 4 5 6 7 8 9 10 11 12

1 13 43577.899 43573.845 263028'03" 044042'40" 141014'37" 038045'23" 43472.381 300 105.518 202.928

2 14 45200.517 45198.509 232037'24" 083028'03" 149009'21" 030050'39" 45117.759 300 82.758 161.500

3 15 49391.956 49391.933 225037'23" 052037'24" 172059'59" 007000'01" 49373.606 300 18.350 36.653

4 16 50946.018 50942.193 187035'14" 045037'23" 141057'51" 038002'09" 50842.615 300 103.403 199.155

5 17 52735.560 52734.917 208048'05" 007035'14" 158047'09" 021012'51" 52679.378 300 56.182 111.077

6 18 53592.778 53592.577 194021'50" 028048'05" 165033'45" 014026'15" 53554.779 300 37.999 75.595

7 19 55536.148 55534.137 225013'37" 014021'50" 149008'13" 030051'47" 55453.337 300 82.811 161.599

8 20 56868.153 56861.061 178051'11" 045013'3" 133037'34" 046022'26" 56739.654 300 128.499 242.813

9 21 58361.930 58346.688 237049'09" 358051'11" 121002'02" 058057'58" 58192.315 300 169.615 308.746

19

Annexure-2

List of Bench Marks for Kachchh Branch Canal from 45 Km. to 54.90 Km.

Sl. No. TBM/BM NO. DESCRIPTION R.L. in m

above msl

1 BM-92 Located on the pucca floor infront of Jai Mathadi Temple, Devapur village, 204m left side of center line of KBC, at Ch.40110m

19.860

2 STN-12 / BM On top of square stone pillar on the edge of cart track, 261m right side of center line of KBC at Ch.46408m.

22.108

3 BM-92A On top of square stone pillar on the field boundary corner, 22m right side of the center line of KBC at Ch. 46613m and right side edge of cart track to Jhejham village.

20.597

4 BM-93 Located on left abutment of pipe culvert Jhejham - Fangli road.

18.037

5 BM-94 Located on top of fifth concrete guard pillar of causeway towards Jhejham , right side of Jhejham to Fangli road.

8.886

6 STN-14 / BM-95 Located on left abutment of pipe culvert Jhejham - Fangli road.

11.694

7 STN-15 / BM On top of square stone pillar, 47m right side of center line of KBC at Ch.50222m.

20.011

8 BM-96 Located on ringwell concrete plateform under Khejada tree opposite to Radhaswami School on the outskirts of Fangli village.

23.844

9 STN-17 / BM-97 On top of sqaure stone pillar at high ground, 177m rightside of the center line of KBC at Ch. 52059m.

29.603

10 AP-17/ BM On top of square stone pillar of AP-17 of KBC. 21.938

11 BM-98 On top of square stone pillar at 12m left side of center line of KBC at Ch. 53267m.

21.763

12 STN-19 / BM On top of square stone pillar, 8.6m right side of center line of KBC at Ch. 54640m.

22.294

13 STN-20 / BM On top of square stone pillar located at field boundary corner, 102m right side of KBC at Ch.55692m and 8m left side of Fangli-Patanka road.

21.389

14 BM-99 On the pucca floor of the Hanuman temple near the front wall, one feet from the right side corner of the temple, Patanka village.

20.750

15 BM-100 Located on left abutment of pipe culvert WBM road Patanka to Babra at 35m towards Patanka from the T-junction of kacha road to Aluvas.

21.577

16 STN-22 / BM On top of square stone pillar at centrline of KBC at Ch.57230m.

22.795

20

Note:-The contractor shall take and connect the levels with double leveling from nearest Permanent Bench Mark (PBM) and verify the above values and get approved from the EIC before commencing the construction work .The contractor shall fix Temporary Bench Mark (TBM) along the length of the canal at a minimum centre to centre distance of one (10) km.

17 STN-23 / BM On top of square stone pillar, right edge of cart track Babar to Patanka 27m rightside of center line of KBC at Ch. 58225m.

22.389

18 STN-24 / BM On top of square stone pillar at centrline of KBC at Ch.59175m.

23.995

19 STN-25 / BM On top of square stone pillar, 97m left side of center line of KBC at Ch.59212m.

24.322

20 STN-26 / BM On top of square stone pillar, left side of center line of KBC, 115m from AP-22, near KBC Ch.60250m.

23.634

21

Note:- The FSL Statement will change in the U/S of the canal syphon depending upon the design of canal syphon and head loss allowed through it.

Annexure-3 Full Supply Level & Structure Detail statement of Kuchchh Branch Canal From Ch. 45000 m to 60000 m

Sl. Reach in Metres Ground

Name of Structure Struture Length Total Head Loss (in m) Total

Loss CBL FSL HWSL TOL TBL

No. From To Level Type in m Due to U/S D/S U/S D/S U/S D/S U/S D/S m Grade Structure Section m m m m m m m m m 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 45000 - 18.510 24.310 24.483 24.983 25.283

1 45000 45300 19.960 VRB V.R.B. 300 0.030 0.020 0.050 18.480 18.460 24.280 24.260 24.483 24.983 24.983 25.283 25.283

2 45300 45673 15.341 Drainage Syphon DS 373 0.037 0.037 18.423 18.423 24.223 24.223 24.483 24.983 24.983 25.283 25.283

3 45673 46570 21.002 CR/VRB/C. Escape

CR/V.R.B./ Esc. 897 0.090 0.070 0.160 18.333 18.263 24.133 24.063 24.483 24.983 24.663 25.283 24.963

4 46570 47930 7.371 Drainage Culvert DC 1360 0.136 0.136 18.127 18.127 23.927 23.927 - 24.527 24.527 24.827 24.827

5 47930 49780 14.577 Drainage Syphon DS 1850 0.185 0.185 17.942 17.942 23.742 23.742 - 24.342 24.342 24.642 24.642

6 49780 50819 23.639 VRB V.R.B. 1039 0.104 0.020 0.124 17.838 17.818 23.638 23.618 - 24.238 24.218 24.538 24.518

7 50819 51180 23.900

Off-take of Patanka & Charnka Distri.

HR 361 0.0361 0.0361 17.782 17.782 23.582 23.582 23.575 24.182 24.182 24.482 24.482

8 51180 51756 22.408 VRB V.R.B. 576 0.058 0.020 0.078 17.724 17.704 23.524 23.504 23.575 24.124 24.104 24.424 24.404

9 51756 52810 21.557 VRB V.R.B. 1054 0.105 0.020 0.125 17.599 17.579 23.399 23.379 23.575 24.075 24.075 24.375 24.375

10 52810 53402 20.368 Drainage Syphon DS 592 0.059 0.059 17.520 17.520 23.320 23.320

23.575 24.075 24.075 24.375 24.375

11 53402 53712 22.761 VRB V.R.B 310 0.031 0.020 0.051 17.489 17.469 23.289 23.269 23.575 24.075 24.075 24.375 24.375

12 53712 54098 19.066 Drainage Syphon DS 386 0.039 0.039 17.430 17.430 23.230 23.230

23.575 24.075 24.075 24.375 24.375

13 54098 54830 19.823 Canal Escape C. Escape 732 0.073 0.073 17.357 17.357 23.157 23.157

23.575 24.075 24.075 24.375 24.375

14 54830 54880 16.937 Drainage Syphon DS 50 0.005 0.005 17.352 17.352 23.152 23.152

23.575 24.075 24.075 24.375 24.375

15 54880 55720 19.450 CR/VRB CR/V.R.B 840 0.084 0.070 0.154 17.268 17.198 23.068 22.998 23.575 24.075 23.598 24.375 23.898

16 55720 55840 18.271 Drainage Syphon DS 120 0.012 0.012 17.186 17.186 22.986 22.986

- 23.586 23.586 23.886 23.886

22

Annexure-4 Rise & Fall details

Rising & Lowering for CR Planning

U/S CR/VRB @ Ch. 46570 m

L1 VRB@ Ch. 50819 m

L2 VRB@ Ch. 51756 m

L3 VRB@ Ch. 52810 m

L4 VRB @ Ch. 53712 m

L D/S CR/VRB @ Ch. 55720 m

L1 = 4249 M h1 = h2 = h3 = h4

L2 = 5186 M

= 0.02 L3 = 6240.0 M

L4 = 7142 M

h =

0.02

4 L = 9150 M = 0.080

Bed Gradient = 1 in 10000 Bed Gradient = 1 in 10000 B = 16.5 M

d = 5.8 M n = 2

hg = L = 9150 = 0.9150 10000 10000

hg/2 = 0.915 = 0.4575 2

h1 = L1 h1 (B+2xnxd-nxh1) BxL+2xnxdxL-2xnxL1xh1

= 3370.307 362915.08

= 0.00929

h2 = 4113.535

23

362840.12

= 0.01134

h3 = 4949.568 362755.80

= 0.01364

h3 = 5665.034 362683.64

= 0.01562

Total Rising = h h h h

hg/2

= 0.5074 < 0.650

Total Lowering = h + hg - Total Rising

= 0.4876 < 0.650

U/S CR

D/S CR D/S FSL

24.063 U/S FSL 0.4876 23.5754 23.5754 0.5074

23.068

CR/VRB @ 46570 m Chainage 51054 m CR/VRB @ 55720 m HWSL 23.5754

24

Chapter – 4

Employer’s requirements for designs and Drawings (General)

1) All the drawings shall be of A-1 size. The block size, notes, borders shall

be standardized & followed in all submission. The font size for note, title,

and subtitle shall be standardized & followed. The size other than above

mentioned shall be used in critical case only.

2) Measurement & allowances in variation shall be within the standard

tolerance limit accepted in India.

3) Nomenclature / abbreviation to be followed as per the standard

acceptable practice only.

4) There should not be any masonry, brick and pre stress concrete type

component of structure or structure as a whole permitted.

5) In any alteration or change in lay-out suggested for better performance

and least maintenance aspects shall be followed without any additional/

extra cost.

6) In N.H. category of bridge, the general lay out plan shall be prepared &

get approved with the design office. The work of such N.H. Bridge shall

be executed as deposited work such as design, construction, etc done by

N.H.A.I.

7) Similarly the structure of Railway crossing also shall be carried out as

deposited work by Railway Department.

8) Exposure condition shall be considered as “Moderate Exposure” for the

structure design, except otherwise required after conforming by testing

specified in IS: 456:2000. Suitable measures shall also be adopted in the

design accordingly.

9) For design of all the components of structure, only Working Stress

Method of Design shall be followed.

10) Any higher grade of steel or cement available in the market shall be used

considering its limited use with respect to the stress limitations ( As part

of produced and developed product) specified in IS : 456:2000 , IS

:7784: PART-I, IS:7784:PART-II (All section), IS:3370 (For water

25

retaining structures) considering performance durability, permeability,

crack width etc.

11) General Design Obligations shall be as under.

Canal Earth Work

Canal Lining

Control Gates and regulating devices

All Canal Siphons, Fall structure.

Canal bridges, SP Aqueduct.

Drainage Facilities, Drainage Culvert, D. Sy.

All Civil works

All Electro mechanical and hydraulic equipments as per

requirement.

The contractor shall submit the curriculum vitae of the design staff

deployed by the Contractor for the formulation of designs and drawings

under the scope of this contract to meet with the design obligations

specified in this document.

The Employer or his Chief Engineer (Design) will review the qualification,

expertise, experience and overall technical capability to formulate the

designs as per standard engineering practices as well as code of

practices/specification etc. and either approve the design staff deployed

staff by the contractor or ask the contractor to provide other capable

design engineers. On instructions from the Employer/or his Chief

Engineer(Designs), the contractor shall submit the CVs of such other

design engineers for its review and approval.

The Design engineer from agency part shall be continued from initial

stage of design to final stage of design as it will improve the set

procedure, if design, save time of submission and approval of design etc.

In case if the contractor desires to appoint a consultant for the design

function, such appointment shall be done only after prior approval of the

26

Employer or his Chief Engineer (Designs) on review of the technical

capabilities, qualifications, experience and expertise in design

engineering on the part of the consultant and his design staff. The

consultant once appointed, shall not be replaced by the contractor

without prior and express permission from the Employer and such

approval shall only be given provided the replaced consultant is found to

be capable, qualified, experienced and expert in design engineering.

The Employer, through the engineer-in-charge will provide the designs

and drawings that are prepared by the Employer, prior to the invitation

of the bids, by is consultant or its own design office, if available as the

preliminary and indicative designs to the contractor.

The Contractor's designer shall verify, modify or alter these designs, if

required as per the norms of design and technical conditions-provided

under Volume II of this contract as well as the applicable standard codes

and practices for the design and construction of irrigation canals, control

and regulating gates, civil structures, elector mechanical and hydraulic

equipments etc. and shall present the modified designs and drawings to

the engineer-in-charge for approval but if is accepted to the owner.

12) The employer shall not be responsible in any manner for mistakes,

shortcomings etc. in the preliminary and indicative designs provided by

the Employer to the Contractor.

13) Owner shall possess the right for giving ruling at C.E. ( Design ) or

higher level in case of differences, ambiguity, modifications in design and

type of structure, requirement of additional structure, proposing new

design concept or so among the design officers of contractors and

owner, after hearing the argument of both the parties.

14) The contractor shall be solely and fully responsible for the correctness

and soundness of all the engineering designs and drawings and shall

have no right to make a claim any time either during the performance of

the contract or thereafter on the grounds of defects/faults in the

preliminary and engineering designs provided by the Employer.

27

(a) Preparation of Commissioning and O & M Manuals

(b) Project Completion Report.

As built drawings for Canal System, its structures, Gates & EM Parts

of structures and a Detailed Project Completion Report shall be

prepared and got approved.

(c) Design liaison with the Employer.

Design liaison with the Chief Engineer, In charge of the Central

Design Office of the Sardar Sarovar Narmada Nigam Limited,

Gandhinagar and/or his authorized representative from the start of

the investigations and until commissioning of the project in full.

Preparation of Monthly Reports on the progress of the project work

as a whole for information of the Employer, in respect of:

Investigation & Surveys.

Design and engineering.

Civil Construction.

Gates & EM Parts

Control arrangement.

Technical status (Present status and future programme)

Project status (Time Schedule, achievement of mile-stone,

slippage in time schedule with specific reference to activities

and acceleration measures proposed).

15) The time frame program for design, drawings and scrutiny of the same

shall be prepared and got approved from C.E. (Design) to adhere the

progress of the work.

16) The typical design calculation and drawings for each type of structure

shall be referred to before planning stage.

17) The designs, drawings, calculations, reports that are prepared and

submitted shall be subject to approval from the Employer or a

Committee of Experts or a Consultant appointed by the Employer.

18) The Employer will ensure prompt approval of the designs and drawings

after due compliance of the observations made by the Employers'

28

Committee or his consultant, however the approval shall have to be

given and communicated to the contractor with a period as fixed by the

owner. In case if the employer or his committee or his consultant do not

approve the designs, drawings, calculation, report within a period of 14

days, as stated herein, the designs, drawings, calculations and reports

shall be deemed to be approved by the Employer and the Contractor

shall derive authority to proceed further with the work.

19) Construction shall not commence until the Contractor receives the

Employer's Representative's approval of the Construction Documents

which are relevant to the design and construction of such part.

20) Type of structures for which design guide lines, sample calculation &

drawings kept with are as follows for reference purpose only.

29

LIST OF STRUCTURES FOR EPC

Sr

No.

Nomenclature

Of Structure

Type Of

Structures Name of Files

1 A Drainage Syphon

A1 Guide Line

A2 Design & Drawing file

2 B Canal Syphon

B1 Guide Line

B2 Design & Drawing file

3 C

Bridge Structure C1 Guide Line

Road Bridge(Deck

slab) C2 Design & Drawing file

VRB C3 Design & Drawing file

Road Bridge(Box

Type) C4 Design & Drawing file

4 D Head Regulator

D1 Guide Line

D2 2 nos of Design File

D3 2 nos of Drawing File

5 E Escape

E1 Guide Line

E2 2 nos of Design File

E3 2 nos of Drawing File

6 F Cross Regulator

F1 Guide Line

F2 2 nos of Design File

F3 2 nos of Drawing File

7 G Cross Regulator /

Fall

G1 Guide Line

G2 Design File

G3 Drawing File

8 H CR-Syphon * Guide Line

30

H1 Design File

H2 Drawing File

9 I CR-Road Bridge

# Guide Line

I1 Design File

I2 Drawing File

10 J Canal Bank

Stability

J1 Guide Line

J2 Design & Drawing file

11 K Super Passage

K1 Guide Line

K2 Design & Drawing file

12 L Gates

L1 Guide Line

L2 4 nos of Design &

Drawing file

* Guide Lines for Structure of CR as well as for Canal Syphon.

# Guide Lines for Structure of CR as well as for Bridge

31

Chapter – 5

Employer’s requirements for DESIGN

1) Any new concept, if any, shall be discussed with reasons & followed, if

accepted by the Nigam.

2) In retaining structure normally the design shall be carried out without any

passive resistance, However if the passive resistance at all needs to be

considered in design. The same shall be followed as per the mutually

agreed condition only as special case.

3) Structure layout shall be planned in such a way that the purpose of

structure can fulfilled without any problems or other effects.

4) Design of structure layout shall be such that it would provide comfort in

operation/usability, least maintenance requirement.

5) Current Indian Standard Stipulations as well as up-dated standard

stipulations shall have to be followed. Any deviation as a special case shall

be accepted if mutually agreeable to both the party.

6) Rugosity of co-efficient as 0.018 shall be considered in design of

structures on canal.

7) The value of N – Rugosity of co-efficient – for drain shall be considered as

0.03. Higher or lower value shall be adopted considering the technical

justification thereto. (Dsy, D-culvert, superpassage, canal syphon or so).

8) The cantilever retaining wall (R.C.C.) shall be designed up to height of

7.0m. Beyond 7.0 m height the counter fort retaining (R.C.C.) wall shall be

designed. However for marginal increase in dimension / height, the

cantilever shall be accepted as a special case having height not more than

10% of 7.0 m. maximum height.

9) Deviation than to guide lines/Code/Circular shall be mutually discussed &

resolved in consultation of design organisation of Nigam.

10) Buoyancy concrete wherever needed shall not be less than 15 cm ,and

there after in multiple of 5.0 cm.

11) Top thickness of breast wall /R.C.C cantilever wall shall not be less than

23cm.

32

12) The height of barrel shall not be less than 1.80 m though mentioned as

1.50 m in Para 3.5.1 of guide line of Drainage syphon structure or any

other structure where barrel is to be provided.

13) Minimum concrete dimension of R.C.C barrels in branch canal structures

shall not less than 30 cm.

14) Leveling course shall not less than 150 mm.

15) The minimum temperature reinforcement for canal structures shall be 12

mm at 250 mm c/c or 10 mm at 200 mm c/c in all exposed faces (Para

7.8 also of DSY guide line ). 10 mm. Ø at 200 mm. c/c shall be preferable.

16) Minimum water way in any structure shall not be less than that provided in

u/s and/or d/s nearby structure on the water-course.

17) The lap length shall be worked as per codal stipulations. However ,in no

case it shall be less than 40 X Ø (dia of higher bar) except the bars in

direct tension. For direct tension codal provision shall be maintained.

18) Single layer & double layer reinforcement shall be provided wherever

required as per codal stipulation.

19) No weep holes shall be provided in the wing walls. The same shall be

taken care of in the design of wing walls.

20) The foundation of Bridge /pier/abutment shall be checked against the

condition of liquefaction. The probability of liquefaction shall be checked

& confirmed by vigorous testing and remedial measures shall be proposed

accordingly.

21) In combine structure viz. CR/CSY , the d/s Cistern shall not be considered

and proposed as it combines with the canal syphon ( i.e. u/s inclined

portion, horizontal portion and d/s inclined portion ) structure.

22) In case of canal in bed banking, the cut-off wall below structure, i.e.

intermediate stop-log, Gate-bay portion etc. shall be considered, so that it

shall be got embedded in natural ground by at-least 75 cm. or more based

on the type of soil. In any case, total depth of cut-off wall shall not be

less than 1.2 m. below foundation slab of structure in banking condition.

In case of High bed banking and pervious type soil, it shall be judiciously

33

decided or otherwise in consultation of design engineer of the Nigam. The

cut-off wall shall be continued in return wall as per the transition wall.

23) In case of computing uplift pressure, it shall be considered 60% in case of

rocky strata and up to 75 % In case of low permeable soil say

permeability of 10-6 cm/Sec or so.

24) Only abrupt transition wall (RCC cantilever) shall be provided in u/s and

d/s of the structure considering height mentioned in para. here above.

Other transition wall like gravity wall, and type of way warped wall,

straight transition etc. shall not be permitted.

25) The span of bridge/barrel in syphon in case of combined structure shall be

fixed based on the size of Gates proposed. i.e. center line of pier and

center line of wall shall be coincided.

26) The design of canal bank section shall be carried out as mentioned in the

guide line as well as respective codal stipulations.

27) The provision of surface drainage, transverse drain etc. shall be

considered while designing canal bank section and proposed accordingly.

28) The provision of suitable filter shall also be made based on the soil type to

be used in construction and saturation as per codal stipulations.

29) The type of embankment i.e. homogeneous zone section etc. shall be

proposed based on the availability of soil from canal excavation as well as

borrow area and techo-economical provision of stipulated in respective

Indian Standards.

30) The S.R. Width shall not be less than 4.27 m. excluding canal dowel and

canal bank gutter. The I.P. Width shall not be less than 2.50 m. excluding

canal dowel and canal bank gutter.

31) The aspect of canal bank, compaction and seepage shall be considered

and proposed accordingly in design section.

32) Stability analysis wherever required shall be carried out for all the

conditions along with earthquake with Importance Factor as 1.5 as

stipulated in respective IS stipulations.

33) In case of full cutting or more, the R.C.C. Box type bridge shall be

considered and design accordingly.

34

34) The design and construction of canal and canal structure shall be solemnly

called as designed and constructed by the EPC contractor and liable for

any damage, maintenance and repairs thereto.

35) The provision of approach slab and three rows of pipe railing shall be

considered in combined structure like CR-Bridge also. This shall also be

applied in Bridge structure.

36) The approach slab of 30 cm. thick with top and bottom reinforcement in

both directions shall be followed and provided as per the standard drawing

of MOST.

37) Placement of Intermediate Stop-log shall be considered from techno-

economic aspects as shown in reference drawing (CR/CSY).

38) In computing the depth of u/s or d/s cut-off, the equation given in para.

5.1.1 (b) shall be read as under.

The depth of u/s or d/s cut-off wall = 0.69 x sqrt(u/s or d/s water depth in

m.)

39) Water-way shall be generally provided as per the codal stipulations based

on existing nearby road-bridge structure/ railway bridge structure etc. It

shall be reduced to 60 to 80 % of Lacey’s water-way depending on site –

condition and as specified in IS Code. Mainly in case of flat topography

where the water flows like a sheet flow water-way shall be provided

without any reduction ( i.e. 60 to 80 percent of water-way in normal

condition) or say more than that of required be proposed from safety and

performance aspects.

40) The type of structure for HR/Escape etc. shall mainly depend on the canal

capacity. In case of very small discharge, barrel type or open-type

structure be replaced by pipe type structure.

41) Normally in pipe type of structures. Two rows of pipes be preferred but

can not be mandatory. The aspect of Two pipe versus One pipe shall be

put up on paper and final design shall be processed as per the

observations by the design office.

42) If hard rocky strata encountered at or higher than foundation level of

structure in full length and width of structure. The provision of cut-off

35

wall, Protection wall, design of structure etc. shall be considered and

carried out accordingly.

43) In design of each component of structure and canal bank ,the design shall

be checked with seismic condition as per IS Stipulations by adopting

suitable importance factor. The importance factor for canal bank and canal

structures shall be 1.5 and higher depending upon the importance of the

structure. The consideration of close to epi-center shall also be kept in

view while designing the canal structure as well as canal sections.

Canal Bank Design

Canal banks are designed as Earthen Dam section and the stability

of the banks is checked in full cutting, partial cutting banking and

full banking as per IS 7894 – 1975. The conditions normally

considered are

o Construction

o Steady seepage

o Sudden drawdown

Analysis is done, as if the section is unlined. Optimum utilization of

soil available from the excavated stuff shall be attempted and

accordingly either homogeneous or zoned section shall be provided

to meet the safety criteria.

Zoning -

As per the availability of soil from the canal excavation the zoning

of canal bank section is decided, which includes Central I.P. core

section, Upstream(I.P. core) trapezoidal zone, (SC, CL) cover in up

stream & Down stream etc.

Lining and Under-drainage Arrangements

Lining : The canal is lined with M-15 grade paver placed cement

concrete. The thickness of lining is kept 10 cm in bed & 12.5 cm on

slope. RCC lining, 20 cm thick in bed & 25 cm thick on slope shall

be provided in 15 m on either side of the structures.

36

Under Drainage Arrangement : The system comprising of

transverse and longitudinal drains and PRV shall be provided to

facilitate release of pressure to safeguard canal slopes and lining

during sudden drawdown.

In the reaches with high water table the system comprising of

stoneware pipe surrounded by inverted filter and PRVs shall be

provided.

Cross-drainage at bridge approaches

Depending upon the difference of formation level of bridge and

surrounding natural ground level, cross-drainage across the bridge

approaches may be necessary. Adequate provisions for such cross-

drainage arrangement shall be made to ensure that water does not

get impounded. This may be in the form of NP3 class Pipes or RCC

Box, number and size of which shall be based on the drainage

requirement as per the site conditions. However in no case pipe

diameter lesser than 900mm or box size lesser than 1.8m be

provided.

The Scope of services to be provided by the contractor under this

contract shall also include the following design engineering

activities:

Review and Assessment of Data Requirement.

Review of available survey and investigation data and identification

of additional survey and investigation requirement considered

necessary for design execution, commissioning and operation of the

project.

Review of technical and design parameters for Canals, branch

system, distributory system, its structure and Hydro-mechanical

Works.

Preparation and submission of Reports on the above for the

information to the Employer.

37

Preparation of work program for carrying out additional

investigations and studies for the information of the Employer.

The contractor shall submit a review report after carrying out the

above activities for acceptance of the Employer.

Additional Investigations and Observations and Studies

Carrying out additional surveys, geotechnical investigations and

laboratory tests, analysis and studies including collection of other

relevant data as necessary.

Evaluation of results of additional investigations, carrying out

studies and analysis for the design of the Project components.

Finalization of conceptual plan based upon the preliminary

design/planning of the Employer, the works to be executed for

Canal System of the scheme. The conceptual plan shall be on

whole to the part principle.

Preparation and submission of Reports on point as above for

reference, acceptance and record of the Employer.

Detailed Design

Preparation of design memorandum indicating design criteria,

design parameters, design assumptions, method of analysis on all

components of the project (Civil, Canal System and Structure

Hydro-mechanical). These design briefs shall be submitted to the

Employer for approval before carrying out detailed design and

construction drawings.

Detailed design for the Civil Works i. e, Canal System including

structures including drawings required for the execution of the

calculations performed and the construction drawings issued shall

be submitted to Employer for his approval.

Detailed design of gates, hoisting arrangement and EM Parts

including drawings required for the execution of the Works and all

calculations performed and the construction drawings issued shall

be submitted to Employer for his approval.

38

Detail of control arrangement including drawings required for the

execution of the Work shall be submitted to Employer for his

approval.

Additional design and modifications, as needed, during construction

shall be followed without asking any extra charge.

The contractor shall adopt modern methodology/State of art

Techniques in design of structures and canal lining like using HDPE

film,/Geo-membrane/Geo-textile etc, only after getting prior

approval based on performance report.

44) Prior to drafting drawings in AutoCAD, EPC Contractor shall ensure the

following from the concerned engineer(s) of NPDC.

Drawing Number of such Drawing.

Chainage of the Structure,Type of the Structure.

Details to be shown on the CAD Drawing / Content of the CAD

Drawing

Suitable Scale of such Drawing as applicable.

Details to be shown NOT TO SCALE (NTS).

Required Dimensions.

Missing Dimension(s) if any.

Readability of the Text, Font, Line Types, Spelling, Dimensions,

Arrows, Degree of angles etc.

Content of the Drawings to be kept on “HOLD” if required /

expressly directed by the designated engineer(s) of the respective

Design Unit.

Name and Designation of the concerned engineers / drawing

branch employees of the SSNNL to be inserted into the Drawing

Block as scrutiny by.

Any deviation from the CAD Standards decided by the

Superintending Engineer / Executive Engineer etc.

Title and Subtitles and Scale of such Details.

Graphical Symbols to be shown in the Drawing.

General Notes to be shown in the Drawing.

39

Reference Drawing Details / Numbers.

Revision Notes if any.

North Sign if required.

Adaptability Certificate if required to be shown in the Drawing.

Required date of submission of the Check Print(s).

Required date of submission of the Final Tracing and Soft Copy of

such Drawing in DVD in Read Only Format (in both AutoCAD 2000

and .pdf format).

45) EPC Contractor shall continuously interact with the designated engineer/s

of the SSNNL in connection with Services to understand the requirement

of the ‘Details’ to be shown on the Drawing/s.

46) EPC Contractor shall not sublet this work in part or whole to any third

party without written consent of the SSNNL.

47) EPC Contractor shall submit Final Drawings on 100 gsm Tracing Paper.

48) Virus infected Pen drives/Memory sticks etc. shall not be used while

transmitting the soft copy of the design or drawings to the SSNNL.

49) In the premises of the SSNNL. EPC Contractor shall use licensed version of

application software if it becomes necessary to do so.

50) The diameter of main reinforcing bar in structural member shall not be

less than 12 mm.

51) The spacing of bars shall be arranged in such a way that maximum main

bar spacing remains 150 mm. to 200 mm. c/c.

52) The selection of bar diameter shall be such that the variation may not be

next 2nd higher diameter or next 2nd lower diameter of bar.

53) The diameter below 10 mm. even in distribution reinforcement shall not

be permitted. In bridge structure, the standard drawing of MOST shall be

followed.

54) The hydrodynamic effect in design shall be considered over and above

dynamic forces on material itself.

40

55) The design of bridge structure shall be carried out as per the alignment of

road and canal system in case of unclassified Village Road Bridge and

Village Road Bridge.

56) Carriage way width shall be 3.65 m for Non Specified category of Road

bridge i.e. additional bridge as per Nigam’s norms.

57) For T -beam girder use NMC guide line.

58) SBC shall be initially assumed for designing the structure with 15 to 20

t/m2. SBC shall be confirmed during actual execution. If it is less than the

assumed one, the design of structure shall be re designed. The aspect of

liquefaction shall also be examined and the design shall be carried out

accordingly with all remedial considerations. In case of encroachment in

footing of abutment & pier, RCC box Type Bridge shall be considered.

59) The asphaltic concrete wearing coat having camber shall be provided in

additional UVRB structure (Preferable 1 : 30.42).

60) Adequate cross drainage arrangement shall be provided below approaches

of bridge with respect to flow quantum as per site condition. This may be

a Box or with pipes of larger diameter where number of pipes shall be met

with the site requirement. If the road side borrow pit not functions as

drain in monsoon, NP3 type RCC pipe may be used. For side gutters acting

as drain in monsoon with high discharge, RCC box shall be provided as per

site condition for continuity of either side of the gutters.

61) Pipe type H.R. shall be provided for available RCC pipe Size (from 450 mm

to 1800 mm or so), in accordance with the hydraulic requirement in the

guide line at clause 1.0. It shall be advisable to provide 2 rows of pipes. In

non feasible condition, only open type HR shall be designed.

62) In pipe type H.R., maximum diameter of pipe shall be 1800 mm.

63) Uplift pressure shall be considered 75 % of head in H.R. structure.

64) Hump height can be reduced to 0.0 in order to satisfy the condition of

pipe runs full in reference to operating level (FSL/HWSL) in unavoidable

condition having no other alternative in H.R. structure.

65) In H.R., for energy dissipation, minimum length of stilling basin (cistern)

shall be provided as 3.0 m or by using Blench Curves given in Varshney &

41

Gupta book, whichever is higher. If a bridge is provided, the cistern floor

length shall be in adjustment with the width of bridge.

66) While designing RCC cantilever retaining wall, top thickness shall not be

less than 23 cm.

67) Minimum thickness of end walls, piers and base slab shall be in conformity

with the requirement of stop-log groove & embedded parts of gates.

68) Top of D/s head wall shall be provided at 0.15 m above SR/IP level in case

of pipe length up to 7.5 m. However, for more lengths, suitable slopes

may be provided and top of head wall shall be kept at 0.15 m above D/s

TBL.

69) TMT bars equivalent to Fe-415 shall be used as reinforcement in R.C.C. or

P.C.C. concrete component. Higher grade can be used with following

stress reduction clause for water retaining structure i.e. 1500 Kg/cm2 to

the face in contact with water and 1900 Kg/cm2 for face away from water.

70) Foundation of HR shall not necessarily be laid 1.0m below GL. In case of

lower depths if suggested, it should be ensured that it is laid on well

compacted strata and prescribed factor of safety against sliding &

overturning duly checked.

71) Bedding below the pipes shall be as per relevant (I.S.) codal stipulations.

72) The provision of float well shall be considered as given in the guide line

given here with. It shall be necessary to provide Float Well in U/S and D/S

of regulating structure i.e. C.R. as isolated or combined with other

structure invariably.

73) U/s & D/s cut-offs shall be in RCC-M 25 in place of CC-M 15 grade.

74) Top of wing walls shall be kept at TOB+0.15 m

75) Factor of safety: For Normal condition in stability check, it shall be 1.5 in

place of 1.75 (in sliding). Checking the safety against uplift, it shall not be

less than 1.2.

76) Tail channel (TC) shall be planned, aligned and designed appropriately

with the topographical features in case of Escape structure. Type of Fall, if

required, may be selected to negotiate the magnitude of Fall suitable with

topographical features to arrive at a viable techno-economical option.

42

77) To safeguard the canal from overflow from and into the canal, open weir

type escape may be designed compromising with site specific necessity.

The guide line of CR and fall to be followed for structural design of the

components.

78) The notes given on the sample drawing shall be reproduced on the

drawings prepared for each structure. Additional note found essential shall

also be incorporated on the drawing under intimation to the design office.

79) The wall of canal syphon shall be constructed in one lift only.

For all canal i.e. Main Canal, Branch Canal, Sub Branch Canal structures having

discharge more than 8.5 cumecs i.e. to be operated under Control Volume

Concept as and when decided by Nigam, to be approved by C.E. (Design)

after recommendation of S.E. - NPDC - Gandhinagar.

80) For canals having discharge less than 8.5 cumecs, the design and drawing

of canal & canal structures are to be approved by concerned C.E. on the

recommendation of concerned field S.E.

81) Design of Canal bank section for KBC shall be carried out following the

Guide Lines prepared & enclosed for NMC.

82) In canal embankment where height of bank is more than 5 m and less

than 15 m, Pseudo-static stability analysis using seismic coefficient method

shall be considered as per I. S. Stipulation wherever applicable.

83) For canal embankment where height is more than 5 m and less than 15

m, if longer and continuous stretch is encountered, dynamic analysis by

Induced deformation analysis using Seed-Mekadisi Method shall be carried

out in addition to the analysis by seismic coefficient method, as stated in

the above point.

84) Following properties shall be required for dynamic analysis.

Soil shear strength parameters such as cohesion ( c ) and

friction angle ( Ø ) from consolidated un drained tri-axial

shear test with pore pressure measurement.

Shear modulus ( G ) and damping ration ( D ) variation with shear

strain ( ) and variation of shear modulus with mean stress from

Resonant Column test.

43

Dynamic un drained shear strength ( T ) of the soil from

Cyclic Tri axial shear test.

44

Chapter – 6

Employer’s requirements for submittals by the Contractor

1) The design note is to be submitted with the submission of detailed

drawings, for all the structures, alignment, stability calculation or so.

2) All submission shall be clean, neat and self-explanatory and with the

required format of submission.

Further more the Report shall include necessary photographs and sketches

showing the previous month's progress.

Supply of Drawings, Report etc.

The contractor shall furnish to the Employer's office the following number

of copies of drawings, reports and other technical documents;

Sr. Particulars Hard copies Soft

copies

Remarks

1 Drawings for

Information

2 (two) Sets 1(One) CDs Minimum two

version shall be

considered.

2 Drawing and

design for

approval

2 (Two) Sets

of Drawings

and 1(one)

set of Design

calculation.

2 (Two)

CDs

One hard copy

shall be

returned to the

contractor with

approval or

comments.

Minimum two

version shall be

considered.

3 Approved

Drawings

5 (five) sets 3

(Three)CDs

Submitted only

after getting

approval as in

45

(2) above.

4 As-built

document

One set 2

(Two)CDs

Shall be

submitted in

accordance with

contract.

5 Review

report/design

briefs/design

memo/design

reports(Draft)

2(Two)Sets 2

(Two)CDs

One hard copy

shall be

returned to the

contractor with

approval or

comments.

6 Review

Report/Desig

n

briefs/Design

Memo/Design

reports(Final)

4 sets 2

(Two)CDs

7 Commissionin

g and O &

Manuals

(Draft)

2(Two)Sets One hard copy

shall be

returned to the

contractor with

approval or

comments.

8 Commissionin

g and O &

Manuals

(Final)

10 (Ten)

Sets

2

(Two)CDs

9 Progress

Report

4 (Four) sets 1 CD

10 Final design

computations

2 (Two) sets 2

(Two)CDs

46

11 Detailed

Project

Completion

Report.

4 (Four) Sets 2 (Two)

CDs

3) All software used shall also be loaded in Employer's and Engineer-in

charge's Computers for design verification and Employer's subsequent use

at no additional cost. No separate payment shall be made for any of the

design and engineering works indicated above and needed for the

completion of the project and shall deemed to be included in the quoted

price.

4) The designs, drawings, calculations, reports that are prepared and

submitted shall be subject to approval from the Employer or a Committee

of Experts or a Consultant appointed by the Employer.

5) Any soft copy of submission shall be with self supported software or

compatible to the software available in design office.

6) The chronology as mentioned in above table shall be processed further

after getting approval stage-wise.

7) Any more delay in approval shall be narrowed down by consulting design

officers, resolving the reasons thereto, discussed with the C.E. (Design)

etc.

Considering the variety of design components involved in canals and canal

structures, it is practically impossible to list out all design criteria and specific

instructions. It shall therefore be noted that in case where no specific mention

has been made or there is a discrepancy in the design requirements spelt out in

the Bid Documents, its Annexures and Drawings etc., decision of the Employer

shall be final and binding to the contractor without any extra cost compensation.

47

Chapter – 7

Data for Canal Structures

STRUCTURE DATA FOR THE PROPOSED STRUCTURE ACROSS THE BRANCH CANAL.

DETAILS OF THE STRUCTURE.

1. Type of the proposed structure :

2. Location of the structure on the

canal i.e. at chainage :

3. Name of the Branch Canal/Distributaries:

DATA SOURCE OFFICES

1. Circle office.. Name :

Address :

H.Q :

Office Phones :

Controlling Officer :

2. Division Office. Name :

Address :

H.Q. :

Phones :

Concerned Officer :

3. Sub Dn. office. Name :

Address :

H.Q :

Phones :

Field Officer :

Site Officer :

4. Letter vide which the data is

furnished to the consultant by

concerned Superintending Engineer. :

48

SARDAR SAROVAR (NARMADA) PROJECT

FIELD DATA AND DESIGN DATA

Name of Branch/Distributary :

Name of proposed structure :

Chainage : ______________ m.

G E N E R A L

PART – I : General Description.

(NOTE: Brief description of the canal and proposed structure, its feasibility,

proposal, constraints at site whether road passes through a Govt. or

private land, land acquisition etc. shall be discussed here)

49

PART – II : CANAL DATA

Note: 1. All Units to be shown in Metric System.

2. For points 1 to 26 the values mentioned herein should tally with the L.S

and C.S of the Canal Section.

1. Name of the Canal :

2. R.D.(Chainage) of the canal for

the structure :___________ m.

(Important: The structure should

not be on the curve portion).

3. Canal Discharge

a. Designed (QD) :__________ cumecs

b. Required (QR) :__________ cumecs

4. Allowable Head loss (HL) :_______ m.

for the structure as per the C.R

Planning statement.

OR

Magnitude of fall (In case of fall)

5. Canal Bed width (B), u/s :_________ m.

d/s :_________ m.

6. Full Supply depth (D) u/s :_________ m.

d/s :_________ m.

7. Free board (FB) u/s :_________ m.

d/s :_________ m.

U/s D/S

a) Lining FB __________m. :_________ m.

b) Earthen FB __________m. :_________ m.

50

c) Total FB __________m. :_________ m.

8. Canal side slopes, u/s & d/s

a) Water side (H : V) : _____ in 1

b) Outer side (H : V) : _____ in 1

9. Top width of banks, u/s & d/s

a) Service Road (SR) side u/s :_______ m.

d/s :_______ m.

b) Inspection path (IP) side u/s :_______ m.

d/s :_______ m.

c) Mention, whether the SR is on

the right side or on the left

side of the canal flow : Left / Right

(While viewing the section

from u/s to d/s)

10. Average Ground level (GL) at

the crossing :RL __________ m.

11. Canal Bed Level (CBL) u/s :RL __________ m.

d/s :RL __________ m.

12. Full Supply Level (FSL), u/s :RL __________ m.

d/s :RL __________ m.

13. Top of Lining level (TOL), u/s :RL __________ m.

d/s :RL __________ m.

14. Top of Bank Level (TBL), u/s :RL __________ m.

d/s :RL __________ m.

15. Pool water level (HWSL) :RL __________ m.

16. Top of crust of SR/IP level

u/s :RL __________ m.

d/s :RL __________ m.

17. Top of Dowel Level (TOD)

51

u/s :RL __________ m.

d/s :RL __________ m.

18. Canal flow velocity (v)

u/s :_______ m/sec

d/s :_______ m/sec

19. Details of Canal lining

a) Lined or Unlined :Lined/Unlined

b) If lined, give details as

i) Type of lining :

ii) Material grade :

iii) Thickness of lining :________ m.

iv) Width of key : _______ m.

20. Coefficient of Rugosity (N) of

Canal surface :_______

21. Hydraulic gradient of the

canal (1 in S) : 1 in ______

22. Give sketch showing details of

the proposed structures between

the adjoining regulators : Yes / No

(If Yes give page no.) :_____

23. Whether distribution planning

is approved or not ? : Yes / NO

24. When Micro-Hydel Power Station

is provided and bridge structure

is nearer to CR/Fall structure,

CR/Fall shall be shifted 500 m

u/s or d/s of the bridge

structure.

25. Where Micro-Hydel Power station

52

is provided, HR shall be provided

500 m d/s otherwise it shall be

30 m, u/s of C.R.

26. Whether CR planning has been

approved by Competent Authority?: Yes / No

(If Yes then Mention letter No. :________________

_________________

Date :_________________

T.B.L. Line

T.O.L. Line

F.S.L. Line

H.W.S.L.

FLOW

1 in ___

1. Regulator at just U/S of the proposed structure

ch. __________ m.

2. Other proposed structure ch. ____________ m.

1 2

3

4 5

53

3. Proposed structure ch. ___________ m.

4. Other proposed structure ch. ___________ m.

5. Regulator at just D/S of the proposed structure

ch. __________ m.

T A B L E

Name of Branch Branch Canal

Name of Structure. Regulator Proposed Regulator

at u/s structures at d/s

in between

1. 2. 3. 4. 5.

Chainage (m)

Permissible

Head Loss (m)

Canal bed width(m)

F.S.D (m)

Free board (m)

Bed Gradient

(1: )

C.B.L (m) u/s

d/s

F.S.L (m) u/s

d/s

Top of lining (m)

Revised TBL (m)

Pool water level

(HWSL) (m)

Remarks

: Prepared by :

Dy.Ex.Engineer Executive Engineer

Sub Division Division

54

PART – III DRAIN DATA

Drain/Stream/Nalla crossing :

1) Hydraulic details

a) Catchment Area : _________ Sq.Km.

b) C.A. of diverted stream if any : _________ Sq.Km.

Note: i) For catchment area plan,

cover catchments for

adjoining streams.

c) Furnish, C.A. plan covering

all the information, such

as C.A. for the proposed

structure, overlapping

boundaries (in case of

diverted streams), flow

direction, marking of longest

stream , roads and railway

structures with sill level,

H.F.L of structure, road

formation levels etc.

d) (i) Attach L.S of drain as per

point No.4(b) of Part-VI and it

should show location.

(ii) Details of culvert/road/

railway on u/s & d/s of proposed

structure with rail formation level,

55

bottom of girder level etc. shall be

furnished by giving necessary sketch.

e) Latitude/Longitude at the

location of structure

f) Specify the seismic zone i.e. I,

II,III, IV, V :

g) Details of crossing

(a) Existing angle of crossing :

(b) Proposed angle of crossing :

Sketch

Angle to crossing – BFD or References for Sketch

Canal – AB

Drain - CD

Crossing point-F

Normal to Canal-EFG

Angle of crossing BFD or

Angle of skewness EFD or

Skew to right/left

2) Discharge:

I. a) Observed maximum flood : ________ cumecs.

b) Observed H.F.L : ________ m.

(Mention Source of inquiry) :

II. Year of this maximum

A B

G

F

C

D

E

CANAL

DRAIN

NORMAL

56

flood and :

III. Location of observed HFL :

IV. Calculated flood

(a) 100 year return flood. : ________ cumecs.

(b) 50 year return flood : ________ cumecs.

(c) 25 year return flood. : ________ cumecs.

V. Stream bed level at crossing : ________ m.

VI. Nature of catchment for suitable

run off coefficient.

Whether it is

i) Sandy soil/ sandy loam

/ arid areas. :

ii) Alluvium / silty loam /coastal

Areas. :

iii) Red soil / clayey loam / gray

Or brown alluvium / cultivated

Plains / tall crops / wooded

Areas. :

iv) Black cotton / clayey soil

/ lightly covered / lightly

wooded / plain and barren

/ sub mountain & plateau. :

v) Hilly soil / plateau &

Barren. :

(VII) Importance of land through which

the canal passes (whether barren

57

for agricultural etc.) :

(VIII) a) Give flood retention period :

b) Whether hazard accured due to

this flood. tentative ? give

details. :

(IX) Details of the influence of

the flood on the habitation

of the local people. :

(X) Rainfall intensity in mm/hr.

Of 100 / 50 / 25 year return

Period (furnished location

Of structure on Isopluvial

Map for sub zone – 3(a) also) :

(XI) Nature of topography :

(XII) Bed Gradient :

Note: i) Mark this in pencil

on L.S of Nalla.

ii) Mention in general

description how grade

is worked out from

L.S. of Nalla

iii) For the C.A. of

25 sq.km. or more

equivalent stream

slope shall be worked

out by taking 8 to 10

points.

58

(XIII) Cross section of the drain,

proposed by the field officer,

in d/s of the drainage structure :

: Prepared by :

Dy.Ex.Engineer Executive Engineer

Sub Division Division

: Checked by :

Dy.Ex.Engineer Executive Engineer

Sub Division Division

59

PART – IV : ROAD DATA

1. Category of Road :

a) Existing standard of the road :

b) As per the provision in the 20 year

Road planning (1981-2001) for the

District :

(IMPORTANT:- Produce the relevant certificate from the

concerned R & B Authority)

c) Latitude :

Longitude :

d) Seismic Zone :

2. Connecting villages/towns/

important Places etc. :

3. Details of Actual Road & crossing :

a) Type of crossing : Right/skew

b) If skew crossing Actual

skewness of road. :

Sketch for angle of crossing and skewness

Angle to crossing – BFD or References for Sketch

Canal – AB

Road - CD

Crossing point-F

Normal to Canal-EFG

Angle of crossing BFD or

Angle of skewness EFD or

Skew to right/left

A B

G

F

C

D

E

CANAL

ROAD

NORMAL

60

c) Mention, whether the road is skew to the

right or skew to the left :

4. Feasibility for combining with

adjacent structure :

5. Details of the proposed Bridge crossing :

(Important- Show revised proposal on relevant village maps/IMS

sheet and give reasons for that in brief e.g.

whether the road passes through a Govt. or Pvt.

land land acquisition required etc.)

a) If original is square :

i) Proposed as :Square/Skew crossing

ii) If proposed as skew :

i) Proposed angle of

skewness

(Limited to 60 Degree): _____ degree

b) If original is skew

i) Proposal is : Square/Skew

ii) If skew, angle is : Reduced/Increased

iii) Proposed Angle of

Skewness : ______ degree

6. Details of Road :

a) Road Surface

i) Existing :

ii)Proposed :

b) Number of lanes

i) Existing :

61

ii) Proposed :

c) Number of ways

i) Existing :

ii) Proposed :

d) Mention,whether there is

any level difference between

the two ways in case of multiple

lane divided bridges

and median width. : Yes/No

(If yes, Give details with drawing)

e) Carriage way width

i) Existing :

ii) Proposed :

f) Formation width

i) Existing :

ii) Proposed :

g) Land width

i) Existing :

ii) Proposed :

(Please furnish the sketch for full, cross section showing all details of proposed road).

Sketch

h) In case of VR or unclassified

62

VR (CT), mention whether the

road passes through the Govt.

land or private land. : Govt./Pvt.

i) Formation level of the road.

1. Existing :

2. Proposed :

7. Whether, the road or Borrow pit

functions as drains in monsoon? :

8. Availability of cohesive non

swelling soil (CNS) with its

detail like lead etc. :

9. Quote the Authority under which

SE/EE has approved the

proposed provision of Bridge

crossing in case of unclassified

road crossings only :

63

PART – V: SOIL DATA

To ascertain the characteristics of foundation soils, following field as well as

laboratory tests as per relevant I.S. codes shall be carried out.

(1) Field density & moisture content.

(2) Field permeability.

(3) Grain size analysis.

(4) Atterberg’s limit.

(5) Shear test (Different type for different characteristics of soil).

(6) Consolidation.

(7) Permeability.

(8) Relative density.

(9) Standard penetration test

NOTE:-

The soil test results of foundation soil, stating all necessary engineering

properties shall be furnished as listed bellow as undisturbed/disturbed soil sample for

various depths, by executing required nos. of trial bores, considering size and

importance of the structure, upto depth of 20 m. from ground level or for depth as

twice the width of foundation from foundation level.

(I) General soil details

1. Location of the bore hole.

2. Ground level R.L.

3. Depth below ground level

4. FDD and FMC

5. Specific gravity

6. Size and percentage of particles G,S,M,C etc.

7. Atterberg’s limit value LL, PL, PI.

8. C & phi (Shear parameters)

9. I.S. Classification of soil.

10. Coefficient of permeability (Kv) m/year.

11. Silt factor (f).

12. SPT value (N).

64

(II) In case of CI / CH / MI / MH etc. type

soils met with at foundation, allowable

bearing pressure (ABP) and settlement shall

be worked out on basis of following parameters.

1. Coefficient of consolidation (Cv) m2/year.

2. Compression index (Cc).

3. Swelling pressure (Sw) Kg/sq.m.

4. e – Log P curve.

5. Pre consolidation pressure (Pc) kg/sq.m.

6. Coefficient of volume change (mv) sq.cm./kg.

7. Coefficient of compressibility (av) sq.m./kg.

8. Initial void ratio (e0).

9. Unconfirmed compressive strength (Cu) kg/sq.cm.

10. Modulus of elasticity (E) kg/sq.cm.

11. Influence factor for immediate settlement (I) kg/sq.m.

12. Poisson’s ratio.

(III) If in case of SM / ML / SP etc. type soil met with at foundation, the

following values shall be furnished.

1. Particle size distribution curve i.e. S-curve.

2. Relative density.

3. Uniformity coefficient (Cu).

(IV) R O C K :

a) If the rock is met with mention

details with log sheet of bore hole

whethered or unwhethered :

1. Hard Rock or Soft Rock :

2. Weathered or Solid :

b) Safe Bearing Capacity (SBC) :

65

(V) S O I L :

(a) Safe bearing capacity of soil (SBC) : ________ t/sq.m.

Details of Trial Pit / bore hole No.____ at

Ch.________ m. On _______________ Branch canal.

SKETCH

Soil parameters as stated above for the structure shall be taken. SBC calculations in accordance

with the I.S. 6403 – 1981 or its latest version shall be furnished.

Note:-

1. In case of high banking, C, value of the earth fill material shall be given.

2. In case bore hole is taken, geological logging of bore hole should be furnished.

3. Position of pre monsoon and post monsoon Ground water table (GWT) RL and its depth below GL

(Mention the year and month when the data was taken).

: prepared by :

Dy.Ex.Engineer Executive Engineer

Sub Division Division

: Checked by :

Dy.Ex.Engineer Executive Engineer

Planning & Design Dn. Planning & Design Division

66

: C E R T I F I C A T E :

Certificate regarding verification of Ground profile for C.D. works at

Ch._________ m. of _______________ branch canal.

Certified that I have visited the site and inspected the strata of the trial pit

and compared it with trial pit register and found correct.

Dy.Ex.Engineer Executive Engine

67

: C E R T I F I C A T E :

Certificate regarding ground water table of nearby well for C.D. work of

Ch. ________ m. of ___________ branch canal.

Certified that I have inspected the nearby well and found ground water at

____________ m. below from G.L. on dated ____________.

Dy.Ex.Engineer. Executive Engineer

68

:CERTIFICATE:

This is to certify that, I have walked over the boundary of the catchment

area for structure at ch. _________ m. of _______________ Branch Canal and

visualised the specific inlets and outlets of nallas or small drains draining in the

catchment area. The same catchment area is marked on S.O.I. Map and verified

by me personally and found as _______ sq.km. and correct to the best of my

knowledge.

Deputy Executive Engineer

Counter signed

Executive Engineer

69

PART-VI : PLANS/DOCUMENTS

1) Index Plan (Scale 1 cm = 500 m.)showing

a) exact location of structure

i) Latitude :

ii) Longitude :

b) Important town/Taluka H.Q/village :

c) Existing roads & railways, in

different colours, 20 year road

planning of the surrounding region

category wise in different columns :

d) Proposed alignment of branch canal/

distributary, location,drainage

etc. :

e) Important rivers/streams :

f) G.T.S.Bench mark (with R.L) :

2) Village Plan (Scale 1 cm = 39.40 m.)

a) Alignment of proposed branch

canal, distributaries chainage

may be shown, location of

proposed structure, drain etc.

(in red colour) :

b) Mark (along with nomenclature)

70

river/drainage/reservoir/tanks

with blue colour, direction of

flow may be shown. :

c) Existing and proposed road

alignment (with 20 year planning,

lanes etc.) wearing surface and

status of road in standard R & B

notations. :

d) Angle of skew for drainage,if

provided. In case of skew

crossing, if proposed to be

made square, show proposed

layout of approaches. :

e) Contours in 1 m. interval

extending upto 1000 m. on either

side of the proposed structure :

f) Details of nearby road and railways

showing location of drainage

structure level crossing canals of

other project etc.

3) SOI Contour Plan (Scale 1 cm = 150 m.)

a) Alignment of proposed branch

canal/distributary with chainage

and location of the proposed

71

structure and details as for

village map.

b) HFL Line :

c) Direction of flow :

d) Angle of skew, if provided :

e) Contour beyond HFL and upto 200 m

on either side :

f) Catchment area boundary (With

Catchment boundaries of adjacent

Drainage structures in U/S and

D/S of the proposed structure. :

(g) Contour line at 0.5 m. interval.

4) Longitudinal Section (Scale 1 cm = 30 m. H)

(Scale 1 cm = 1 m. V)

a) Part L/S of Canal (1000 m. on

either side of structure) with

details of CBL,FSL, TBL etc. :

Note:-

Show on plan alignment of branch/dist. alignment of Drain/Road, Curve, distance

from the curve (Generally avoid structure falling within curve)

b) L/S of Nalla (Scale 1 cm = 30 m. H)

(Scale 1 cm = 1 m. V)

i) 300 m. on u/s side 500 m. on

d/s side of the structure :

72

ii) For flat topography 500 m. on

u/s side and 1000 m. on d/s side :

iii) 1000 m. either side for large

structure having C.A more

than 25 sq.km. :

iv) H.F.L Line

c) Details of trail pits upto 2.0 m.

below Nalla bed level with R.L.

and ground water level :

5) Cross Section (Br.Canal/Dist.) (Scale 1 cm = 100 cm.)

a) C/S of canal at structure

site showing canal section

service road, Inspection path,

plantation width spoil bank,

borrow pits, drain etc. :

b) C/S of existing river/Nalla

up to Ridge portion. (Scale 1 cm = 30 m. H)

(Scale 1 cm = 1 m. V)

i) At every 10 m. upto 150 m.

on u/s. :

ii) At every 10 m. upto 240 m.

on d/s :

6) C.R.Planning Statement :

7) S.B.C.calculation :

73

Note:-

1) Levels at sufficient points on the c/s shall be

taken to truly represent the shape of the

Nalla/drain/stream.

2) The c/s should not be drawn to distorted scale,

preferably 1:4 scale shall be adopted.

: Prepared by :

Dy.Ex.Engineer Executive Engineer

Sub Division Division

: Checked by :

Dy.Ex.Engineer Executive Engineer

Planning & Design Dn. Planning & Design Dn.

74

SKETCH SHOWING LOCATION OF TRIAL BORE / TRIAL PITS

Location of bore hole for structure ____________ m. at Ch.

_____________m.

River flow

U/S CANAL FLOW BH-L1 BH-C BH-R1

D/S

75

Chapter – 8

Guidelines for Soil Explorations

Guide lines on Investigation for structures on Branch Canals of Narmada Canal

System.

1.0 General

A detailed investigation of the site is essential to design a safe and economical

structure on realistic basis. The object of site investigation is to provide the

designer with informations about the existing conditions viz. Hydrological,

topographical and sub soil information as detailed below:-

1.1. Hydrological Information

1.1.1 Catchment Area:- Catchment area shall be marked on Toposheet as

well as on S.O.I. map covering catchments of adjoining streams with flow

direction, roads and railway structures with sill level, H.F.L. of structure, road

formation etc. It is desired that field officer should walk over the boundary of

catchment area and visualize the specific inlets and outlets of the nallas or small

drains draining in the catchment and it should be clearly shown on the map so

that correct discharge coming from the catchment can be derived. It shall also be

observed that back water or spill in water of any near by river is entering in the

catchment of the C.D. works under observation or not. Length of the longest

stream shall be carefully marked on the S.O.I. along the stream up to the

farthest point. For arriving at the correct slope of drain, levels shall be given for

atleast 3 to 5 points with corresponding length. A certificate regarding verification

of catchment area shall be given by field officer as per Annex.1.

1.1.2 Estimation of Design Flood:- For checking the overall safety of the

structure, from foundation, scour and free board considerations, the following

flood shall be adopted.

Sr.

No.

Catchment Area in

sq.km.

Method Remarks.

76

1 Less than 25.00 As per bridges and floods wing

report no.RBF-16 method.

2 25.00 to 518.00 Flood Estimation Reports of

various sub zones published

by the Director (Hydrology for

small catchment) C.W.C., New

Delhi

For Sub Zone

3(a), or 3(b) as

the case may be.

3 Above 518.00 Each case shall be taken up

specifically and decided after

detailed examination as

mentioned in IS 7784, Part-I,

1993

As per IS 7784 (Part-I), 1993 frequency of design flood for cross drainage

structures are tabulated as below:-

Design Flood Values.

Category

of

structure

Canal discharge in

m3/ sec.

(*) Estimated

drainage discharge in

m3/sec.

Frequency of Design

flood.

A 0.00 to 0.50 All discharges 1 in 25 years

B 0.5 to 15.00 0.00 to 150.00 1 in 50 years

C 15.00 to 30.00 Above 150.00 1 in 100 years

D Above 30.00 0.00 to 150.00

Above 150.00

1 in 100 years

As per Note-2

Notes:-1) The design flood to be adopted as mentioned in this table should in

no case be less than observed flood.

2) In case of very large cross drainage structures where estimated

drainage discharge is above 150.00 cumecs, the hydrology shall be

examined in detail and appropriate design flood adopted, which

77

should in no case be less than 1

in 100 years.

(*) This refers to the discharge estimated on the basis of river/ nalla

parameters corresponding to maximum observe flood level.

1.1.3 Determining the observed flood:- For determining observed flood, the

field officer should go to the site more than twice in a year immediately after the

floods occur and observe the levels carefully. The value of “N” (Co-efficient of

rougosity) shall be adopted carefully and the correct observed discharge may be

determined. Local inquiry is necessary to obtain the highest flood level and

thereby to calculate the maximum observed flood.

1.1.4. L.S and C/S of drain:- For large drains having C.F. more than 25 sq.km.

L.S. and C.S. of drain shall be given 1000 mt. on either side of the structure. For

small drain L.S. and C.S. may be given for 300 mt. on either side of structure.

But in case of drainage syphon for small drain L.S. of drain shall be given 500 mt.

in u/s and 1000 mt. in d/s of the structure.

1.2. Topographical Information:- Index map shall be given showing the

exact location of structure with latitude and longitude. Nature of the catchment

area i.e. whether it is plain, hilly or undulating etc. with type of catchment that

whether it is fan shaped, leaf shaped etc. shall be given. Flood retention period

and hazards occurred due to this flood retention shall be given. Details of the

influence of the flood on the sanitation of the local people shall also be given.

Type of average soil on surface in the catchment area shall be given, so

that correct flood calculation can be done.

1.3 Sub soil information:- The sub soil information is to provide safe and

secure foundation to take the estimated load without shear failure and undue

settlement. The foundation investigation shall be carried out below the

foundation grade. For shear failure the engineering properties of soil shall be

given.

78

In many cases the soil below the foundation level deep strata of “CH”, highly

plastic clay, with high moisture content meets with. The soil may consolidate

under the applied load resulting into settlement over a quite long time. This may

damage the structure. For such cases consolidation times has to be reduced by

taking suitable measures. It is therefore emphasized that for such cases

undisturbed samples may be collected and tested very scrupulously.

Where MH/MI/ML type of soil is met with in foundation, the liquefaction potential

shall be studied.

A list of data required for “CH” type of soil is given in Annex-II.

Due to the complexity of natural deposits the sub soil investigation is discussed in

the following paragraphs. The sub surface explorations are generally carried out

in stages namely, (1) Reconnaissance, (2) Preliminary and (3) Detailed as given

below:

1.3.1. Site Reconnaissance:- This helps to assess the need for preliminary for

detailed investigations It includes a study of local topography, excavations,

ravines, evidence of erosion or landslides, water level in streams, water courses

and walls, flood marks, drainage pattern, location of seeps etc. The information

on some of these may be obtained from topographical maps, geological maps,

soil survey maps and arial photographs.

1.3.2. Preliminary Exploration:- The scope of this exploration is restricted to

the determination of depth, thickness, extent and composition of each soil

stratum, location of rock and ground water and also to obtain approximate

information regarding strength and compressibility of the various strata.

1.3.3. Detailed Exploration:- The detailed investigation follow preliminary

investigation and should be planned on the basis of data obtained during

79

reconnaissance and preliminary investigation. The scope of this exploration is

restricted to the determination of engineering properties of sub soil viz. shear

strength, density, natural moisture content, permeability etc. The detailed

investigation includes boring and detailed sampling to determine these

properties. All in-situ tests are to be supplemented by laboratory investigations.

The guide lines for above stage investigation is given in Table-1, which shall be

followed in normal circumstances and shall be followed with caution and in the

spirit of the requirement of relevant I.S .Codes and technical publications.

2.0 Methods of Sub Soil Exploration:-

The methods of sub soil explorations are given in Table-2. However, the

foundation investigation procedure to be followed in general is give below for

guidance.

2.1. Soil Strata:- The soil below foundation level shall be tested with standard

penetration tests and/or by collecting undisturbed samples and test for

engineering properties. The water table shall also be recorded. In case of

cohesion less soil, where collecting undisturbed samples is not possible only S.P.

Tests shall be carried out. The S.P. Tests and collection of undisturbed samples

shall be done as below. Consolidation tests shall be carried out where highly

plastic clays viz.CH, CL, MH, MI is met with.

Sr.No. Item Depth.

1 Undisturbed samples 45 cm.

2 S.P. Tests scaling drive 15 cm.

3 S.P. Tests 15 cm.

4 S.P. Tests 15 cm.

To be continued to final depth in this order.

2.2. Rocky Strata:- In case the rocky strata is met with below the

foundations, the bore hole using rotary drilling machine and core bit having NX

80

size bit shall be drilled. During drilling care shall be taken to obtain maximum

core recovery. In case rock is highly weathered or rock is such that the

cementing material shall be removed during drilling and core recovery obtained is

less, double tube core barrel or triple tube core barrel shall be used.

The drilling at a stretch shall be done for maximum 1.5 m. depth or

change of strata whichever is earlier. The drilling time, wash water, water table

artesian condition met with if any, shall be recorded in drilling register.

The logging by Geologist shall be done and submitted along with report

and recommendation of Geologist to use the rock as foundation of particular

structure.

3.0 Investigation record and sampling:-

3.1 The soil strata can be examined in trial pits, the trial pits should therefore

be preferred to auger holes/bore holes. After the trial pit excavation is

completed or during the excavation logging of the pits should be done and field

classification of the soil should be carried out as outlined in IS 1498-1970.

3.2 In bore hole all the information viz. water table level, rate of drilling wash

water details, water loss during drilling and any other useful information shall be

recorded in drilling/investigation register.

3.3 The undisturbed samples shall be collected in the form of chunk samples

from trial pits and Shelby tube samples from bore holes. The samples shall be

protected properly during storing and their transportation to laboratory. The

testing shall be carried out as early as possible, to get reliable results.

3.4 In rock, the cores obtained shall be preserved in core boxes with proper

identification marks of location of hole and depth from which cores are

recovered. The cores shall be kept in core box as they are recovered from the

core barrel.

Testing:- Laboratory testing of all soils samples shall be carried out as detailed

81

in Para 1.3. For rock the bore hole log shall be prepared by the Geologist and

foundation grade and SBC shall be given.

Record of investigation data :- The results of laboratory test as per Para 1.3

and bore hold log as per Para 3.3. shall be furnished to the design office.

82

Table-1

Table-1 showing details of investigation in various stages (Please refer Para -5)

Sr.

No.

Stage Choice of Methods Spacing Location Depth of Exploration Remarks.

1. Reconnaissance

stage

Visual observation of

topography, cut-crops,

erosional features, quarries,

excavation, landslides,

water level in streams and

water courses, flood marks,

drainage pattern, location

seeps etc. Ground water

may be observed in existing

wells.

- - - 1) The investigation

should cover a

considerable

distance from the

structure based on

topography and

alternative sides.

2) The appraisal

should define major

advantages, defects

of the foundation

and material

deposits at

alternative sites with

reasonable

83

certainty.

3) The data for

overburden may be

obtained by visual

observation and

field identification

tests.

84

2. Preliminary

stage

Trial pits and boring 5-Trial pits/bores. At foundation

corners and one in

centre

Twice the width of

foundation below

foundation grade. In

weak soils the

exploration shall be

carried out to a

depth at which load

can be carried by the

stratum without

undesirable

settlement and shear

failure.

Spacing the number

of Trial pits/bore hole

shall depend on type

of structure and site

condition.

3. Detailed (Pre-

construction

investigation

stage)

Trial pits and boring. In grid widely

spaced for

uniform insitu

soils & closely

spaced for non

uniform soil in

foundation.

- Twice the width of

foundation below

foundation grade. In

weak soils the

exploration shall be

carried out to a

depth at which load

The spacing and

location shall be

taken depending

upon geological

complexity of site.

85

can be carried by the

stratum without

undesirable

settlement and shear

failure.

86

4. Construction

stage

As dictated by Geological

complexities.

- - - Construction stage

exploration should

aim at making

available duty for

(1) The evaluation

of specific

foundation

features and

(2) Preparation of

foundation

grade maps to

guide

foundation

preparation &

treatment.

NOTE:- The foundation investigation shall be carried out below foundation grade.

87

Table-2

Sub Soil Exploration Methods:-

Sr.

No.

Method Description Applicability.

1) Aerial

Photography

- For intensive investigation in

accessible area serial

photography is not essential

for soil exploration. For in

accessible and unfamiliar

areas air photography may be

adopted as an aid in planning

for detailed exploration work.

2) Geophysical

Methods

They are grouped as a)Seismic,

b) electrical, c) Magnetic, d)

Gravitational & e) Sonic.

a) Seismic Method Shock of seismic waves are

created by detonating small

charges or by striking a rod or

a plate near the surface. The

radiating waves are picked up

and time of travel from source

recorded by detectors known

as geophones or seismometers.

In seismic method, either

refracted or reflected waves

are detected.

i) Refraction

Method

In this method, time of arrival

of waves refracted at interfaces

between different strata are

recoded.

Used to determine depth to

rock or depths of significantly

differing soil strata. Can be

used only when velocity of

travel in lower layers is

88

significantly greater than the

upper ones. This method is

usually limited to depths up to

30 m. in a single stratum.

ii) Reflection

Method

Here seismometers record the

travel time of seismic waves

reflected from interface

between adjoining strata.

This method is usually adopted

to determine depth of deep

bed rocks. Generally applied

for depths exceeding 600 m.

At present this method is

mainly used in off-shore

investigation.

iii) Velocity

sounding

methods

In this method, seismic waves

are generated. Their travel

times & hence travel velocities

in travelling through soil along

the hole in down or up

direction or across the holes

are determined.

These method are used for

determining dynamic elastic &

shear modulus which enable

to estimate coefficient of

elastic uniform compression

etc.

b) Electrical

resistivity

method

In this method four metallic

spikes to serve as electrodes

are driven into the ground at

equal intervals along a line. A

known potential is then applied

between the outermost

electrodes and potential drop is

measured between the

innermost electrodes. Flow of

electric current is also

measured. This enables to

estimate resistivity of stratum.

From known resistivity of

Used to determine vertical as

well as horizontal extent of soil

strata at foundation site for

larger structures, such as

dams, Depth of exploration is

generally limited to about 30

m. Also used to obtain data for

designing electrical grounding

system.

89

different strata, prediction can

be made about the nature of

the stratum.

c) Magnetic

Method

- Rarely used in Civil

Engineering works.

d) Gravitational

Method

Rarely used in Civil

Engineering works

e) Sonic Method In this method time of travel of

sound was reflected from

certain boundaries between

different strata are measured.

From the knowledge of velocity

of sound wave a different

strata, depth to strata can be

obtained.

Used to determine position of

mud line and depth to hard

stratum underlying mud. Use

is currently limited to shallow

depths.

3) Test Pits,

Trenches and

Open Cuts.

Tests pits, trench or any other

type of open excavation an be

carried out manually or by

machines The sides of open

cut, need be provided with

lateral support with the help of

bracings whenever there is a

danger of cave-in.

Applicable in all soils provided

for visual examination of soil

strata in their natural

conditions. Disturbed or

undisturbed samples can be

conveniently obtained at

required depths. Use is usually

limited to shallow depth of 0

to 5 m. For greater depths

cost of open excavation and

necessary side bracing

becomes uneconomical

4 Borings Principal boring types are

auger boring, wash boring,

percussion drilling and rotary

drilling.

Refer respective type of

boring.

90

a) Auger boring Bore hole is advanced by hand

or power operated auger with

periodic removal of material. In

some cases continuous auger

may be used requiring only one

removal. Casing is generally

not used with auger boring.

Hand augers are used in soft

to stiff cohesive soils, in sandy

solty soils have water table

with hand auger, depth is

usually limited to 6 m. Power

driven augers can be used to

great depth, even to 30 m.

and used in almost all type of

soils above water table. This

method provides almost

continuous disturbed samples,

Undisturbed samples can be

obtained at required depths by

using proper samplers.

b) Wash promg. Bore hole is advanced by

chopping, twisting action of a

light chopping bit and jetting

action of a drilling fluid, usually

water, under pressure.

Changes in soil strata are

indicated by changes in the

rate of progress of boring

examination of outcoming

slurry and cuttings in the

slurry. Casings are used

whenever necessary to prevent

cave-ins.

Can be used in all types of

soils except those containing

bounders, can be used to

great depths, adopted easily at

inaccessible. Samples obtained

are in highly disturbed and

slurry form, undisturbed

samples whenever needed can

be obtained by use of proper

samplers.

c) Percussion

drilling

Bore hole is advanced by

chopping action of heavy bit

driven by power. Water is

added at the bottom of bore

hold during chopping action, if

Can be used in all soil types

including soils containing

boulders. Can be used for

great depths. Use is limited

because of difficulty in

91

the ground water is not already

struck. Slurry formed at bottom

of bore hole is removed by

bailer or sand pump. Casing is

generally required. Changes in

strata are predicted from the

rate of progress of boring and

examination of slurry bailed

out.

determining strata changes as

chopping action can cause

considerable disturbance and

because of high cost. May be

used in combination with

auger or wash borings when

boulders are encountered.

Undisturbed samples

whenever needed can be

obtained by use of proper

samples.

d) Rotary drilling Bore holes is advanced by

power rotation of drilling bit

and removal of cuttings by

circulating fluids which may be

water bentonite slurry or mud

slurry. Whenever rock or

boulders are encountered

suitable bits viz. diamond

studded bits or tun gesten

carbide bits or steel bits with

shots are to be used for

drilling. Casing may or may not

be needed during drilling.

Changes in strata are indicated

by change in rate of advancing

of bore hole ,action of drilling

tools, examination of cuttings

in drilling fluid.

Can be used in all types of

soils and rocks, can be used to

great depths, being

increasingly used because of

fast rate of progress in all soil

types, but difficult to use at

increasable locations because

of heavy machinery.

Undisturbed samples can be

obtained at desired depths by

using suitable samplers.

e) Drive tube

boring

Force open pipe or tube with

sharpened edge, without

rotation, into soils withdraw

Fine grained cohesive and

slightly cohesive soils, such as

loess firm to soft clays and

92

and remove soil. Thin or thick

wall tubing or pipe 50 mm. to

200 mm. dia.

silts.

5) Sounding and

probing

In this method some sounding

device like split spoon sampler,

a cone, or a rod is forced,

statically or dynamically, into

the soil. The energy consumed

in penetration into soil is an

indication of consistency of soil.

Standard penetration test

dynamic cone penetration test

& static cone penetration test

are commonly adopted

standard tests.

Can be used in any type of soil

and to any depth. Depth by

static cone penetration is

limited by the capacity of

equipment. Presently 3 tone

and 10 tone machines are in

use. Standard penetration test

is used in a bore hole.

6)

a)

Load Tests

Vertical plate

bearing test.

Vertical plate bearing test is

very common. In this method a

plate of 30 to 75 cm. square or

circular shape is loaded in

increments to obtain load

settlement curve.

Applicable in sandy soils,

murum, weathered rock. To

be used with caution in clayey

soil. Depth of influence is

limited by virtue of limited

plate size. In absence of

probing to greater depth by

other methods this test can be

misleading. Used in estimating

allowable bearing pressure,

coefficient of elastic uniform

compression (when the test is

cyclic) and modulus of sub-

grade reaction.

b) Pressure meter

test

Generally done in a bore hole.

Cylindrical probe is inserted in

Useful in all soils particularly in

bouldery strata, weathered

93

a bore and subject to

cylindrical pressure increments

and deformations noted.

rock etc. where it is difficult to

obtain undisturbed samples for

laboratory tests of difficult to

rely on in-situ tests, like

penetration tests.

94

ANNEX – 1.

C E R T I F I C A T E

This is to certify that, I walked over the boundary of catchment

area of cross drainage structure at ____________________m. of

_________________Branch Canal and visualize the specific inlets and outlets

of nallas or small drain, draining in the catchment area. The same catchment

is marked on the S.O.I. map and verified by me personally and found to be

_______________sq.km

Deputy

Executive Engineer

Countersigned.

Executive Engineer.

95

: ANNEX – 2 :

(I) DATA REQUIRED FOR COMPUTATION OF SETTLEMENT.

1. Poison’s ratio : U

2. Modulus of Elasticity : Es (with stress Vs strain curve)

3. Field dry density : rd

4. Water content : w

5. Preconsolidation Pressure : Pc

6. e log P curve :

7. Compression Index : Cc

8. Specific gravity : G

9. Coefficient of volume change : mv

10. Coefficient of compressibility : av

11. Initial void ratio : eo

12. Co-efficient of consolidation

-in vertical direction

-in radial direction

:

:

Cvz

Cvr

13. Coefficient of permeability : In horizontal dir. : kh

In vertical dir: kv

14. At curve for 90% consolidation: :

15. Liquid limit L.L. : Plastic limit – PL

Plasticity Index - IP

16. IS classification :

17. Grain size distribution : S Curve:

18. Ground Water level : WT

19. Degree of saturation : Str.

20. Saturated density : rsat

21. At least minimum five (5)

consolidation tests and two (2)

triaxial tests for each bore hole

96

below foundation level for clayey

strata.

22. Free swell at foundation level :

23. Swelling Pressure :

24. Water table variation in pre-

monsoon & post monsoon:

:

25. The depth of bore hole should be

the twice the width of structure

below foundation level.

26. Soil profile, Geological cross

section at centre line of canal

(showing above details).

II. DATA REQUIRED FOR COMPUTATION OF S.B.C.

1. Angle of internal friction : Ø By triaxial as well as Box shear

test.

2. Cohesion of soil : C

3. Dry density of soil : rd

4. Water content : w

5. Ground water level :

6. Specific gravity of soil :

7. ‘N’ value for 30 cms. penetration :

8. Unconfined compressive strength : cu

9. Relative density in case of sandy

stata

ID

97

ANNEX – 3

LABORATORY TEST

Sr.

No

Test Equipment Purpose of testing

1 2 3 4

1. Grain size analysis

IS 2720-IV

Coarse sieve (80 mm.

03,37.5, 25.8 20.00, 10.0,

6.3, 4.75 mm). Fine sieve (21

mm 600 micron, 425, 212, 75

micron), balance oven, stirrer,

hydrometer with jars.

For classification of soil

and thereby getting

indication of

2. Plasticity Index

IS 2720-V

Liquid limit device grooving

tools and sieves, oven,

Uppal’s cone penetrometer.

Indicates properties of

soils, Test not possible

for non plastic soils

which are used for

casing.

3. Standard compaction

IS: 2720-VII

Standard compaction mould

with base, collar, and

rammer, soil, extractor

balance 20 kg. oven 212.75

micron, balance oven, stirrer,

hydrometer with jars.

For determining the

maximum density which

can be attained on field

optimum moisture

content, with standard

energy.

4. Relative density

IS 2720-XIV

Relative density apparatus,

vibrator, balance 50 kg. oven.

Similar as above but for

coarse grained soil

5. Field density and

moisture

IS: 2778

XXVII -1974

XXXX-1975

XXXIII - 1971

Core cuter and replacement

kit and water replacement kit.

To determine the

placement density and

monitor compaction

effect. It also indicates

adequacy of moisture

content.

6. Permeability Permeability apparatus soil To decide drainage

98

IS: 2720- XVII-1966 extractor, oven. condition under which

the soil will behave in

field, anticipate probable

seepage and design

drains.

7. Field permeability

IS:5529-1969

Field permeability apparatus

like water storage drum,

shovels, augers etc.

To determine the

drainage condition of soil

insitu.

8. Direct shear

IS: 2720-IV

Direct shear apparatus soil

extractor, balance 5 kg.

To determine shear

strength of soil in

foundation or in

embankment.

9. Consolidation

IS:2720-XV- 1965

Consolidate test apparatus,

oven balance.

To determine settlement

rate and magnitude and

to assess whether soil is

normally consolidated or

preconsolidated.

10. Moisture content

IS: 2720- II - 1973

Balance oven or rapid

moisture meter.

To determine degree of

saturation, consistency

rate of a natural strata

or a compacted fill.

99

ANNEX -4

Size of Sample required for tests.

Sr.

No.

Test Quantity required for soil having maximum particle

size of

4.75 mm 10 mm 20 mm 40 mm 80 mm

1. Particle size analysis 0.40 kg 1.50 kg 6.5 kg 25 kg 60 kg

2. Liquid limit 270gm - - - -

3. Plastic limit

(Passing micron)

50 gm

425

-

425

- - -

4. Shear 3 kg 120 kg 120 kg 120 kg 120 kg

5. Consolidation (Undisturbed

sample)

75 mm

dia.

- - - -

6. Permeability 5 kg 15 kg 30 kg 120 kg 120 kg

7. Proctor

a) Light compaction

20 kg 20 kg 20 kg - -

b) Heavy compaction 20 kg 20 kg 20 kg - -

8. Relative density 12 kg 25 kg 50 kg 100 kg 120 kg

Total for all

Tests:

65 kg 200 kg 250 kg 365 kg 420 kg

100

ANNEX -5

List of Indian Standards Followed for Foundation Investigation.

Sr.

No.

Description IS Code No.

1. Classification and identification of soil for general engineering

purpose

1498 - 1970

2. Methods of tests for soil (Part-I) preparation of dry soil samples

for various tests.

2720 – 1983

(Part-I)

3. Method of tests for soils (Part-II) Determination of water

content.

2720 – 1973

(Part-II)

4. Method of test for soil (Part-IV) grain size analysis 2720 – 1975

(Part-IV)

5. Method of tests for soils (Part-V) Determination of liquid and

plastic limit

2720 – 1985

(Part-V)

6. Method of tests for soils (Part-VI)

Determination of shrinkage factors.

2720 – 1972

(Part-VI)

7. Method of tests for soils (Part-VII) Determination of water

content dry density relation usi9ng light compaction.

2720 – 1980

(Part-VII)

8. Method of tests for soils (Part-VIII) Determination of water

content dry density relation using having compaction

2720 – 1983

(Part – VIII)

9. Methods of tests for soils (Part-IX) Determination of dry density

moisture content relation by constant weight of soil method.

2720-1971

(Part-IX)

10. Methods of tests for soils (part-X) Determination of unconfined

compressive strength

2720 – 1973

(Part-X)

11. Methods of tests for soils (part-XI) Determination of shear

strength parameters of a specimen tested in unconsolidated

undrained triaxial compression without the measurement of

pore pressure.

2720-1971

(Part-XI)

12. Methods of tests for soils (Part-XII) determination of shear

strength parameters of soil from consolidated undrained triaxial

2720 -1981

(Part-XII)

101

compression tests with measurement of pore pressure.

13. Methods of tests for soils (Part-XIII) Direct Shear test. 2720 – 1986

(Part-XIII)

14. Method of tests for soil (part-XIV) Determination of density

Index relative density of cohesionless soils

2720-1983

(Part-XIV)

15. Method of test for soils (Part-XV) Determination of consolidation

properties.

2720-1986

(Part-XV)

16. Methods of tests for soils (Part-XVII) Laboratory determination

of soil permeability

2720-1986

(Part-XVII)

17. Method of tests for soils (Part-XX) Determination of linear

shrinkage

2720-1966

(Part-XXI)

18. Methods of tests for soils (Part-XXI) Determination for total

soluble solids

2720-1977

(Part-XXI)

19. Methods of test for soils (Part-XVIII) Determination of dry

density of soils in place, by the sand replacement method

2720 – 1974

(Part-XVIII)

20 Methods of tests for soils (Part-XXIX) Determination of dry

density of soil in place, by the core cutter method.

2720 – 1975

(Part-XXIX)

21 Methods of tests for soils (Part-XXI) Laboratory vane shear test. 2720 – 1980

(Part-XXI)

22. Methods of tests for soils (Part-XXL III) Determination of the

density implace by the ring and water replacement method.

2720 – 1971

(Part-XXL

III)

23. Methods of tests for soils (Part-XXXIV) Determination of density

of soils inplace, by rubble bullon method.

2720-1972

(Part-XXXLV)

24. Methods of tests for soil (Part-XXI VI) Laboratory determination

of permeability of granular soils.

2720-1987

(Part-XXLVI)

25. Part-XL Determination of free swell index of soil 2720 – 1966

(Part-XL)

26. Part-XLI measuring pressure of soil 2720 – 1977

(Part-XLI)

27. Standard penetration test 2131

102

28. Dynamic cone penetration test 4968 (Part I

& II)

29. Static cone penetration test 4968 (Part-

III)

30 In-situ vane shear test 4434

31 Plate bearing test 1888

32 Pile load test 2911 (Part-

IV)

33 Sand cone method 2720- (Part-

X (VIII)

34 Permeability Test 5529

35 California Bearing Ratio Test 2720 (Part-

XXXI)

36 Dynamic Tests for Dynamic properties of soils 5249

103

Chapter – 9

Criteria for Soil Investigation for canal and canal structures

CANAL STRUCTURES. 1.0 PREAMBLE :

Guide Lines on Investigation for Canal structures on Branch Canals of

Narmada Canal System has been issued by S.E., N.P.P.D.C., Gandhinagar

vide his letter No. NPPDC/H/Guide Lines/Investi-gations/2595 dt. 3.11.1998.

The Guidelines were for the purpose of determination of types of tests to be

carried out at various stages of investigations and were generalized for all

types of structures. Thereafter detailed guidelines incorporating various

aspects like no. of bore holes, their locations , types of tests, etc. keeping in

view the type of structures were published by S.E., N.P.P.D.C., Gandhinagar

vide letter No. NPPDC/B/Soil/Investigation/562 dt. 20.3.2003.

Despite many such efforts to guide the field offices as to how to conduct soil

investigation, lot many lacuna in the ground work have been encountered

which have not only made the design difficult but also led to serious financial

consequences. Such financial consequences impair the financial planning and

spawn serious doubts on working fashion of the officers involved.

With a close eye of auditing agencies and administrative transparency required

in the context of right to information, fair and transparent working at all levels

in the government has become imperative. Vigilance Commission has also

made emphasis on providing detailed provisions for all technical activities in

order to regular unforeseen expenditures and introduce financial discipline.

In view of this, an attempt has been made to spell out details of investigation

like no. of bore holes required for a specific type of structures, its exact

location, types of tests to be carried , etc.

2.0 ORDER

Methodology of investigation prescribed hereunder shall be applicable to all

canals and structures having designed discharge greater tan or equal to 3

cumecs. For location of Trial Pit/bore hole detailed sketches for various types

104

of structures are given . On the basis of results of soil investigation done in the

prescribed manner hereunder described, estimates shall be prepared. Design

office shall be furnished the same results and data for carrying out design

accordingly.

2.1 For Canal Alignment :

Every one km. one Trial Pit/bore hole at the centre of the canal up to 3 m.

depth below average ground level should normally be carried out. However,

if the canal is in cutting the depth should be taken up to 1.5 m below CBL.

In case of erratic soil strata, the adjacent Trial Pit/bore hole shall be reduced

up to 500 m.

2.2 For Bridge :

2.2.1 For UVRB/VRB one Trial Pit/bore hole up to 3 m depth below GL/CBL (

whichever is lower ) should be carried out at the crossing point of the road and

canal.

2.2.2 For ODRB, MDRB, SHRB or NHRB minimum one bore hole at the centre

of the central pier up to 5 m. depth from CBL/GL ( whichever is lower )

should be carried out and for any one abutment one Traial Pit/ bore hole in the

center of the abutment upto 5 m. depth from ground level shall be taken.

2.3 For Canal Siphon :

For Canal Siphon minimum three bore holes as shown in the Annexure-A up

to the depth equal to 1.5 B ( where B is the total width of the structure ) or 5

m. whichever is greater, below the deepest nala bed/River bed / GL whichever

is lower shall be taken.

2.4 For Drainage Siphon :

For Drainage Siphon one bore hole as shown in the Annexure- A up to the

depth equal to 1.5 B ( where B is the total width of structure ) or 5m.

whichever is greater . below deepest nala bed /River bed/ GL whichever is

lower shall be taken. Trial Pit of 2.5 m depth at 15 m. distance from start of

tail channel on centre line shall be done to ascertain type of soil in the tail

channel.

2.5 For HR/CR/CR Fall/Escape etc.:

For HR, CR, CR / Fall or Escape minimum one Trial Pit/ bore hole shall be

taken up to the 3 m. depth from GL or CBL whichever is lower. In escape tail

channel to ascertain the type of soil trial pit of 2.5 m depth at 15 m from start

105

of tail channel on the centre line shall be done.

2.6 General :

2.6.1 Normally following tests shall be carried out in all types of soil (i) Grain size

distribution (ii) Atterberg’s limit (iii) F.D.D. and F.M.C. (iv) specific Gravity

(v) Soil classification (vi) Direct box shear test (vii) Silt Factor and (viii) SPT

value.

2.6.2 During investigation if poor soil like ( CH, MH,OH,ML,MI,CI etc. is met

with, the safe bearing capacity ( SBC) shall be governed by the settlement

parameters and in such cases more depth than prescribed above for the Trial

Pit / bore hole shall be decided by the field officers so as to avoid problems of

settlement.

Consolidation tests as well as triaxial shear tests on undisturbed samples shall

be done to ascertain (i) Rate of consolidation of soil under normal load (ii)

Degree of consolidation (iii) Pressure – Void ratio relationship (iv)

Compression index (v) Co-efficient of compressibility (vi) Swelling pressure

(vii) Swelling index as per IS :2720 ( Part-XL)- 1977 recommendations. The

graph of sqrt (t) curve and e-log p curve shall be furnished. The tests shall be

carried out at 3 m. interval if stratum changes below foundation level. If

stratum remains unchanged, next test shall be carried out on next preceding

stratum.

Unconfirmed compressive strength test shall be done to ascertain the

compressive strength.

2.6.3. In case of soft rocks / weathered rock, minimum one bore hole up to hard rock

surface or 3 m. in depth from GL whichever is lower shall be taken.

2.6.4. If the soil such as SM, ML, SP etc. whose value of N < 30, certain tests to

ascertain liquefaction shall be carried out such as Cu (Uniformity coefficient ),

D60, RD ( Relative Density ), Grain size distribution curve, percentage fine

etc.

The above norms are general rules for easy and speedy working.

However, in abnormal situation design office shall be consulted.

106

ANNEXURE A LOCATION OF TP / BH FOR CANAL AND CANAL

STRUCTURES

2.1 CANAL ALIGNMENT :-

B

CANAL FLOW

1000 m. 1000 m.

WHERE :

DENOTES TP / BH

B = CANAL BED WIDTH TP = TRIAL PIT BH = BORE HOLE DENOTES CENTER LINE OF CANAL.

107

2.2 BRIDGES :- CENTER LINE OF CANAL

CENTER TP / BH TP / BH TP / BH LINE OF BRIDGE PLAN

GL CBL

TP /

BH

TP /

BH

TP /

BH

AL AR P ELEVATION WHERE :

DENOTES TP / BH TP = TRIAL PIT BH = BORE HOLE

AL = ABUTMENT LEFT

P = CENTRAL PIER

AR = ABUTMENT RIGHT

AR AL P

108

2.3 CANAL SYPHON :-

BH-L CANAL FLOW BH-C BH-R

DR

AIN

FL

OW

WHERE :

BH-L = BORE HOLE AT LEFT OF DRAIN. BH-C = BORE HOLE AT JUNCTION OF DRAIN AND CANAL CENTER. BH-R = BORE HOLE AT RIGHT OF DRAIN. DENOTES CENTER LINE OF CANAL

2.4

DRAINAGE SYPHON DRAIN FLOW BH-C

Trial pit of about 2.5 m depth at 15

m from start of tail channel

CA

NA

L FL

OW

WHERE :

BH-C = BORE HOLE AT JUNCTION OF DRAIN AND CANAL CENTER. DENOTES CENTER LINE OF DSY.

DENOTES CENTER LINE OF CANAL.

AL

109

2.5.1.1 HEAD REGULATOR :-

L CANAL FLOW OF OFF-TAKING CANAL

L /2

WHERE : = DENOTES TP / BH TP = TRIAL PIT BH = BORE HOLE

DENOTES CENTER LINE OF OFF-TAKING

CANAL 2.5.1.1 CROSS REGULATOR :-

U/S Return wall L

CANAL FLOW

L / 2

WHERE : = DENOTES TP / BH TP = TRIAL PIT BH = BORE HOLE DENOTES CENTER LINE OF CANAL

TP/ BH BH

TRANSITION PORTIONOGN

GATE BAY PORTIONA

BARREL/PIPE PORTION

TP BH

TRANSITION

GATEBAY

BARREL / PIPE

TP/ BH

TRANSITION PORTION

GATEBAYPORTIONION

CISTERN PORTION

TP /BHPP

110

2.5.1.2 CROSS REGULATOR / FALL :-

L

CANAL FLOW

L / 2 WHERE : = DENOTES TP / BH TP = TRIAL PIT BH = BORE HOLE

DENOTES CENTER LINE OF

CANAL 2.5.1.2 ESCAPE :-

2/3 L

TAIL CHANNEL

FLOW IN TAIL CHANNEL L Trial pit of

about 2.5 m depth at 15 m

from start of tail channel

WHERE : = DENOTES TP / BH TP = TRIAL PIT BH = BORE HOLE DENOTES CENTER LINE OF TAIL CHANNEL

TP BH

TRANSITION

GATEBAY

BARREL / PIPE

TP/ BH

TRASITION PORTIONTI

GATEBAY PORTIONORTIO

CISTERN PORTIONRTION

TTP/ BH

TRANSITION PORTIONPO

GATEBAYPORTION

111

Chapter – 10

Employer’s requirement with reference to the details to be covered

up in specific drawings for canal structures.

The contractor shall formulate drawings for construction based on the designs

containing the details as shown in the list of drawings contained here under:

LIST OF DRAWINGS OF DSY

Sr. No. Particulars of Drawings. Employer’s Requirement

1. Layout Plan & Sectional Elevation Detailed lay-out Plan

2. Reinforcement details of Barrel for Drainage Syphon

Cross Section of Barrel & Reinforcement Details with schedule

3. Reinforcement details of U/S & D/S Return Walls.(Section 1-1 & 6-6)

Section of u/s & d/s return wall & Reinforcement Details with schedule

4. Reinforcement details of U/S & D/S Return Walls.(Section 2-2 & 5-5)

Section of u/s & d/s return wall & Reinforcement Details with schedule

5. Reinforcement details of U/S & D/S Return Walls.(Section 3-3 & 4-4)

Section of u/s & d/s return wall & Reinforcement Details with schedule

6. Details of Joints & Railing

Details of PVC water stop, reinforcement details of Cutoff walls ,u/s & d/s protection work, collar details of barrels, details of key at junction of retaining wall & lining, details of sump & details of bituminous sealing compound with railing details.

112

LIST OF DRAWINGS OF CSY

Sr. No. Particulars of Drawings. Employer’s Requirement

1. Layout Plan & Sectional Elevation Detailed lay-out Plan

2. Reinforcement details of Barrels

Cross Section of Barrel & Reinforcement Details with schedule

3. Reinforcement details of U/S & D/S Stop logs

Cross Section of u/s & d/s stop-log & Reinforcement Details with schedule

4. Reinforcement details of U/S & D/S Return Walls.

Section of u/s & d/s return wall & Reinforcement Details with schedule

5. Details of Joints & Railing

Details of PVC water stop, reinforcement details of Cutoff walls ,u/s & d/s protection work, collar details of barrels, details of key at junction of retaining wall & lining, details of sump & details of bituminous sealing compound with railing details.

6. Details of Trash Rack Plan & Section of Trash RACK

7. Details of block outs and its 1stage embedded parts of U/S Stop log

Sectional Plan & Elevation with details of embedded parts

8. Details of block outs and its 1st stage embedded parts of D/S Stop log

Sectional Plan & Elevation with details of embedded parts

113

LIST OF DRAWINGS OF VRB/UVRB/MDRB/SHRB ( DECK SLAB TYPE )

Sr. No. Particulars of Drawings. Employer’s Requirement

1. Layout Plan General Layout Plan

2. Plan & Sectional Elevation Detailed lay-out Plan

3. Reinforcement details Deck Slab Cross Section of Deck Slab & Reinforcement Details with schedule

4. Reinforcement details of R.C.C. Abutment

Section of Abutment & Reinforcement Details with schedule

5. Reinforcement details of R.C.C. Pier Section of Pier & Reinforcement Details with schedule

6. Reinforcement details of Approach slab

Details of Section & Reinforcement Details

7. Reinforcement details of Parapet Details of Section & Reinforcement Details

8. Miscellaneous details of sections , joints railing etc

Details of PVC water stop, reinforcement details of Cut off walls , details of key at junction of retaining wall & lining & details of bituminous sealing compound with railing details.

9. General Note General Note

114

LIST OF DRAWINGS OF VRB/UVRB/MDRB/SHRB ( BOX-CULVERT- TYPE )

Sr. No. Particulars of Drawings. Employer’s Requirement

1. Layout Plan General Layout Plan

2. Plan & Sectional Elevation Detailed lay-out Plan

3. Reinforcement details of Box Culvert Cross Section of box culvert & Reinforcement Details with schedule

4. Reinforcement details of Approach slab

Details of Section & Reinforcement Details

5. Reinforcement details of Parapet Details of Section & Reinforcement Details

6. Miscellaneous details of sections , joints railing etc

Details of PVC water stop, reinforcement details of Cut off walls , details of key at junction of retaining wall & lining & details of bituminous sealing compound with railing details.

7. General Note General Note

115

List of Drawings of HR ( Single Pipe) Sr. no

Description of drawing

Employer’s Requirement

1

General Layout plan.

Detailed lay-out Plan

2 Reinforcement Details of Inlet Transition & Gate-bay Portion.

Cross Section of Inlet & Gate bay portion & Reinforcement Details with schedule

3

Details of Head Wall & Miscellaneous

Details of Section & details of miscellaneous

4 Details of Block-out and Ist stage embedded parts for Vertical Gate.

Sectional Plan & Elevation with details of embedded parts

116

List of Drawings of HR ( Double pipe ) Sr. no

Description of drawing

Employer’s Requirement

1

General Layout plan.

Detailed lay-out Plan

2 Reinforcement Details of &

U/S Head Wall.

Cross Section of Inlet & Head Wall & Reinforcement Details with schedule

3 Reinforcement Details of

Inlet & D/S stop-log.

Section of U/S barrel & cistern & Reinforcement Details with schedule

4 Details of Transition wall &

Miscellaneous

Section of Transition wall & miscellaneous details & Reinforcement Details with schedule

5

Details of Block-out and Ist stage embedded parts for Vertical Gate.

Sectional Plan & Elevation with details of embedded parts

117

For Open Type Escape (Radial Gate) Sr. no

Description of drawing Employer’s Requirement

1 Layout plan & Section.

Detailed lay-out Plan

2 Details of Inlet & Gate-bay.

Cross Section of Gate bay portion & Reinforcement Details with schedule

3 Reinforcement details of U/S Barrel, Cistern & D/S TR wall

Cross Section of barrel ,Section of u/s & d/s return wall and cistern & Reinforcement Details with schedule

4 Details of Railing and protection works.

Details of PVC water stop, reinforcement details of Cut off walls, details of key at junction of retaining wall & lining & details of bituminous sealing compound

5 Typical arrangement for Radial Gate.

Elevation, Section, Plan of block out.

6 Details of Ist stage embedded parts and Block outs for Radial gate.

Elevation, Section, Plan of block out.

7 Details of Block-out and Ist stage embedded parts for U/S stop log.

Sectional Plan & Elevation with details of embedded parts

8 Details of RCC Bracket for Abutment.

Plan, Sectional elevation Reinforcement Details

9 Details of RCC Bracket for Pier.

Plan, Sectional elevation Reinforcement Details

118

For Open Type Escape (Vertical Gate) Sr. no

Description of drawing Employer’s Requirement

1 Layout plan & Section.

Detailed lay-out Plan

2 Details of Inlet Transition & Gate-bay Portion.

Cross Section of Gate bay portion & Reinforcement Details with schedule

3 Details of Head wall & Miscellaneous details

Section of head wall,& Reinforcement Details with schedule Details of PVC water stop, reinforcement details of Cut off walls, details of key at junction of retaining wall & lining & details of bituminous sealing compound

4 Details of Block-out and Ist stage embedded parts for Vertical Gate for pipe

Sectional Plan & Elevation with details of embedded parts

119

LIST OF DRAWINGS OF CR (Radial)

Sr. No. Particulars of Drawings. Employer’s Requirement

1. Plan & Sectional Elevation Detailed lay-out Plan

2. Reinforcement details of Gate bay Section

Cross Section of Gate bay portion & Reinforcement Details with schedule

3. Details of combined section & U/S & D/S Retaining walls.

Section of u/s & d/s return wall & Reinforcement Details with schedule

4. Details of Railing & Protection works

Details of PVC water stop, reinforcement details of Cut off walls, details of key at junction of retaining wall & lining & details of bituminous sealing compound with railing details.

5. Typical arrangement for Radial Gate Elevation, Section, Plan of block out.

6. Details of 1st stage embedded parts & block out for radial gate.

Elevation, Section, Plan of block out.

7. Details of Trunnion Bracket for Abutment

Plan, Sectional elevation Reinforcement Details

8. Details of Trunnion Bracket for Pier. Plan, Sectional elevation Reinforcement Details

9. Details of Stop log groove. Detail of Section

120

LIST OF DRAWINGS OF CR (Vertical)

Sr. No. Particulars of Drawings. Employer’s Requirement

1. Layout Plan General Layout Plan

2. Plan & Sectional Elevation Detailed lay-out Plan

3. Reinforcement details of Gate bay Section

Cross Section of Gate bay portion & Reinforcement Details with schedule

4. Reinforcement details for Return Wall & combined section.

Section of u/s & d/s return wall , Combined win wall & Reinforcement Details with schedule

5. Details of Joints ,Sections & Railing

Details of PVC water stop, reinforcement details of Cut-off walls ,railing ,details of key at junction of retaining wall & lining, & details of bituminous sealing compound

6. General lay-out of vertical slide gate (open type) & stop logs.

Elevation, Section, Plan of block out.

121

LIST OF DRAWINGS OF CR/FALL (Radial)

Sr. No. Particulars of Drawings. Employer’s Requirement

1. Layout Plan General Layout Plan

2. Plan & Sectional Elevation Detailed lay-out Plan

3. Reinforcement details of Gate bay Section

Cross Section of Gate bay portion & Reinforcement Details with schedule

4. Reinforcement details of U/S & D/S Return Walls.

Section of u/s & d/s return wall & Reinforcement Details with schedule

5. Reinforcement details of Combined Wing wall/Open Trough

Section of wing wall/open trough & Reinforcement Details with schedule

6. Details of Joints & Railing

Details of PVC water stop, reinforcement details of Cut off walls, details of energy decipator, details of key at junction of retaining wall & lining & details of bituminous sealing compound

7.

Details of 1st stage embedded parts & block out for radial gate.

Elevation, Section, Plan of block out.

8. Details of Trunnion Bracket for Abutment

Plan, Sectional elevation & Reinforcement Details

9. Details of Trunnion Bracket for Pier.

Plan, Sectional elevation & Reinforcement Details

10.

Details of block outs and its 1st stage embedded parts of U/S Stop log

Sectional Plan & Elevation with details of embedded parts

11.

Details of block outs and its 1st stage embedded parts of D/S Stop log

Sectional Plan & Elevation with details of embedded parts

12. Details of float well Section, Plan & details of float well

122

LIST OF DRAWINGS OF CR/FALL (Vertical)

Sr. No. Particulars of Drawings. Employer’s Requirement

1. Layout Plan General Layout Plan

2. Plan & Sectional Elevation Detailed lay-out Plan

3. Reinforcement details of Gate bay Section

Cross Section of Gate bay portion & Reinforcement Details with schedule

4. Reinforcement details of Open Trough

Section of wing wall/open trough & Reinforcement Details with schedule

5. Reinforcement details of U/S & D/S Return Walls.

Section of u/s & d/s return wall & Reinforcement Details with schedule

6. Details of Railing & Joints

Details of PVC water stop, reinforcement details of Cut off walls, details of energy dissipater, details of key at junction of retaining wall & lining & details of bituminous sealing compound

7. General lay-out of vertical slide gate(open type) & stop logs. Elevation, Section, Plan of block out

123

LIST OF DRAWINGS OF CR/CSY

Sr. No. Particulars of Drawings. Employer’s Requirement

1. Layout Plan & Sectional Elevation Detailed lay-out Plan

2. Reinforcement details of Gate bay Section

Cross Section of Gate bay portion & Reinforcement Details with schedule

3. Reinforcement details of Barrels Cross Section of Barrel & Reinforcement Details with schedule

4. Reinforcement details of U/S & D/S Stop logs

Section of u/s & d/s stop-logs & Reinforcement Details with schedule

5. Reinforcement details of U/S & D/S Return Walls.

Section of u/s & d/s return wall,& Reinforcement Details with schedule

6. Details of Joints & Railing

Details of PVC water stop, reinforcement details of Cutoff walls ,u/s & d/s protection work, collar details of barrels, details of key at junction of retaining wall & lining, details of sump & details of bituminous sealing compound with railing details.

7. Details of Trash Rack Plan, Section of Trash Rack

8. Details of block outs and its 1st stage embedded parts of Radial gate

Elevation, Section, Plan of block out.

9. Details of Trunnion Bracket for Abutment

Plan, Sectional elevation Reinforcement Details

10. Details of Trunnion Bracket for Piers

Plan, Sectional elevation Reinforcement Details

11. Details of block outs and its 1stage embedded parts of U/S Stop log

Sectional Plan & Elevation with details of embedded parts

12. Details of block outs and its 1st stage embedded parts of D/S Stop log

Sectional Plan & Elevation with details of embedded parts

13. Details of block outs and its 1st stage embedded parts of Inter-mediate Stop log

Sectional Plan & Elevation with details of embedded parts

14. Float Well (Typical) Section, Plan & details of float well

124

LIST OF DRAWINGS OF CR(Radial)/VRB

Sr. No. Particulars of Drawings. Employer’s Requirement

1. Layout Plan General Layout Plan.

2. Plan & Sectional Elevation Detailed lay-out Plan

3. Reinforcement details of Gate bay Section

Cross Section of Gate bay portion & Reinforcement Details with schedule

4. Reinforcement details of R.C.C Box Culvert

Cross Section of Box culvert & Reinforcement Details with schedule

5. Reinforcement details of U/S & D/S Return Walls.

Section of u/s & d/s return wall,& Reinforcement Details with schedule

6. Details of Joints & Railing

Details of PVC water stop, reinforcement details of Cut off walls, details of key at junction of retaining wall & lining & details of bituminous sealing compound

7. Reinforcement details of Approach slab

Section of approach slab & Reinforcement Details with schedule

8. Reinforcement details of R.C.C. Parapet

Section, Plan & details of perforated parapet

9. Details of 1st stage embedded parts & block out for radial gate.

Elevation, Section, Plan of block out.

10. Details of Trunnion Bracket for Abutment

Plan, Sectional elevation Reinforcement Details

11. Details of Trunnion Bracket for Pier.

Plan, Sectional elevation Reinforcement Details

12. Details of block outs and its 1st stage embedded parts of U/S Stop log

Sectional Plan & Elevation with details of embedded parts

13. Details of block outs and its 1st stage embedded parts of D/S Stop log

Sectional Plan & Elevation with details of embedded parts

14. General Note General Note

125

LIST OF DRAWINGS OF CR(Vertical)/VRB

Sr. No. Particulars of Drawings. Employer’s Requirement

1. Layout Plan General Layout Plan.

2. Plan & Sectional Elevation Detailed lay-out Plan

3. Reinforcement details of Gate bay Section

Cross Section of Gate bay portion & Reinforcement Details with schedule

4. Reinforcement details of Box culvert

Cross Section of Box culvert & Reinforcement Details with schedule

5. Reinforcement details of U/S & D/S Return Walls.

Section of u/s & d/s return wall,& Reinforcement Details with schedule

6. Details of Railing & Joints

Details of PVC water stop, reinforcement details of Cut off walls, details of key at junction of retaining wall & lining &details of bituminoussealing compound

7. Reinforcement details of Approach slab

Section of approach slab & Reinforcement Details with schedule

8. Reinforcement details of Parapet wall

Section, Plan & details of perforated parapet

9. General lay-out of vertical slide gate(open type) & stop logs.

Elevation, Section, Plan of block out

10. General Note General Note

11 Float well Section, Plan & details of float well

126

LIST OF DRAWINGS FOR SUPERPASSAGE Sr.No. Details of Drawings Employer’s Requirement

1 General lay out plan Detailed lay-out Plan

2

Details of reinforcement for super structure

Section of Super structure & Reinforcement Details with schedule

3

Details (RCC / PCC ) for components

Details (RCC / PCC ) for components

4

General notes

General notes

127

Chapter – 11

Employer’s guidelines for detailed designs

The Employer has finalized detailed norms for designs and drawings relating

to canals and canal structures, which are being presently used for designs

and drawings. The contractor shall have to carry out the design function in

total compliance of these detailed norms listed herein below:

1) GUIDELINES FOR DESIGN OF CANAL SECTIONS OF NARMADA MAIN CANAL

2) GUIDE LINES FOR DESIGN OF HEAD REGULATOR ON BRANCH CANALS

3) GUIDE LINES FOR DESIGN OF ESCAPE ON BRANCH CANALS 4) GUIDE LINES FOR DESIGN OF CANAL SYPHON ON BRANCH CANALS 5) GUIDE LINES FOR DESIGN OF DRAINAGE SYPHON / CULVERT ON

BRANCH CANALS 6) GUIDE LINES FOR DESIGN OF ROAD BRIDGES ON BRANCH CANALS 7) GUIDE LINES FOR DESIGN OF SUPERPASSAGE ON BRANCH CANALS 8) GUIDE LINES FOR DESIGN OF CROSS REGULATOR GUIDE LINES FOR

DESIGN OF CROSS REGULATOR/FALL ON BRANCH CANALS 9) GUIDELINES FOR GATE DESIGN

Computer disks containing these guidelines are also available and can be

obtained from the Chief Engineer, designs, Sardar Sarovar Narmada Nigam

Limited Block No. 12, Gandhinagar.

The EPC contractor shall follow the relevant and applicable guidelines for his

design purposes and for any queries and clarifications he shall contact the

Chief Engineer (Designs) at the addressed mentioned hereinabove.

128

GUIDE LINES FOR DESIGN OF CANAL SECTIONS OF

NARMADA MAIN CANAL

1.0 Introduction

1.1 Sardar Sarovar (Narmada) Project envisages construction of a concrete gravity dam across the river Narmada,146.50 m. (480.60 ft.) high above mean sea level near village Navagam in Bharuch district to impound a reservoir with gross storage capacity of 0.95 m. ham (7.7 MAF) and a live storage capacity of 0.58 M ham (4.73 MAF) at FRL. The project is planned to provide an annual irrigation to an area of 1.8 million hectares (4.43 million acres) besides providing Municipal and Industrial uses to about 4720 villages and 131 urban centers located within as well as out side the command. A series of four ponds on right bank are created to act as a balancing reservoir between main reservoir and canal system that will take care of diurnal variations in discharges required for irrigation and canal head power house. The Narmada Main Canal (N.M.C) off takes from pond – 4.

1.2 The N.M.C. is aligned as a contour canal having its total length of 460 km. from its off-take near dam site to the Gujarat-Rajasthan border. The canal will serve an area of 75000 hectares (185325 acres) annually in Rajasthan. The discharging capacity of the main canal is 1133 cumecs (40000 cusecs) at the head and 71.10 cumecs (2500 cusecs) at the Gujarat-Rajasthan border. The section of the main canal in its head reach is 73.10 m x 7.6 m. and at tail is 10.10 m x 4.4 m. (FSD) with tentative side slope of 2 (H): 1(V). The slopes however are finalized based on the safety requirements considering the properties of soils encountered during execution. A free board of 1.5 m. (1.25 m. lined + 0.25 m. unlined) is provided. The entire canal is lined with machine placed concrete of thickness 12.5 cm. on slopes and 10.0 cm. in bed. The bed gradient of 1:12500 UP TO Mahi river crossing and 1:15500 beyond Mahi to Rajasthan border

129

is fixed for main canal. 1.3 The N.M.C passes through varying Geographical terrain

throughout its run to Rajasthan border. The advantage of past experience in planning, design and construction of canal with such a large capacity (1133 cumecs) is not available anywhere. The norms viz. (i) Requirement of data (ii) Design criteria i.e. stability analysis of Canal sections, internal drainage arrangements, slope protection on land side etc, are given for guidance in following paragraphs. The criteria evolved are based on available literature on the subject, criteria given in relevant Indian standards and practice followed elsewhere on large canals. This criteria is reviewed from time to time based on the experience gained during the course of investigation, design and construction on this project and other projects.

2.0 SALIENT FEATURES

Criteria and salient features, for NMC are annexed vide Annexure-I. It may be however, mentioned here that for embankment/depth of cutting greater than 6.0 m. stability analysis is carried out using Swedish slip circle method. Typical cross sections along with details of components are given vide plate ;No.1 & II.

3.0 INVESTIGATION AND DATA REQUIREMENTS

N.M.C passes through varying topographical terrain having wide variation in soil characteristics. Maximum banking as high as 17 m. and maximum cutting also of about 17 m. in some reaches have to be provided. The structure safety of such a large canal can not be ignored. As such design based on adequate soil testing is the prime requirement.

Guide lines for collection and furnishing of data for design of canal section are enumerated below.

3.1 GENERAL DATA:

a) Canal alignment and vicinity survey: The canal alignment shown on the village plan (scale

130

1:7920) indicating additional features viz. Contours, hills, local depressions, nallas, borrow areas, village site, roads etc.

b) Proposed cross-section of the canal showing the ground profile, CBL, FSL, zoning i.e. type of material proposed to be used in bank (with the help of flow chart) etc. for

i) Maximum banking ii) 5.0 m. banking and iii) Maximum cutting. c) Longitudinal section (scale 1:3000 (H) & 1:200 (v) )

along the C/L showing continuous chainage, GL, CBL, FSL, TBL, logging of strata (indicating Lab No. & strata R,L.), rock profile if any, location of structures, premonsoon and postmonsoon ground water table line (when the ground levels are likely to be near or above the CBL with the year in which the said levels were observed etc.). The ground levels at 30 m. c/c on the cross sections taken at about 150 m. along the canal alignment should be given on the plan.

d) Condensed LS on the centre line of the alignment showing the full details as stated in 3.1 (C).

(Scale: Hor. 1 :10000 Ver. 1; 200).

e) Flow chart indicating availability of materials from canal excavation based on soil classification in groups as shown in annexure II and the requirement of material with cross section adopted. The flow chart should also indicate the reach/borrow area from where the material is to be transported / borrowed in case of deficiency. Planning of surplus material should also be indicated. A note justifying the proposed zoning should be attached

f) For deciding strata/layer wise design constants for foundation material, the R.L. from which the soil samples have been taken may be given instead of giving only depth. Also the G.L. and lab. Nos. of trial pits/bore holes may be given on the L.S.

131

3.2 FOUNDATION AND CONSTRUCTION MATERIAL SURVEY:

3.2.1 Trial pits/bore/auger holes (i.e. along C/L may be taken at about 3000 m c/c to 5000 m c/c as per ground profile . The trial pit/bore hole may be taken down to about 4.0 m. below the C.B.L. However, in case where the canal is in high bed banking, trial pits about 2 m. deep below the ground surface are required to be taken.

The spacing of the trial pits may be reduced where the surface profile indicates rapidly changing strata. For every 2 km at least one bore hole should be drilled down to rock or other continuous impervious stratum in order to ascertain the infiltration characteristics of the strata in the vicinity of the canal. The visual logs of the trial pits and bore holes should be prepared and furnished to the design office.

In the case of the bore holes, details such as colour of wash

water, water loss at various depths, time rate of penetration etc. should be noted and recorded for proper appreciation of the sub soil conditions.

3.2. The samples may be collected as given below. Sr.No

Location of trial/bore holes

Nature of samples to be collected from trial pits/bore holes along C/L

A. Canal in cutting Between the stripped level and CBL

Undisturbed and disturbed (Alternatively at 1.5 m. interval with at least one undisturbed sample irrespective of the depth)

2. Below CBL Undisturbed (At 1.5 m. interval with a minimum of one sample)

B Canal in partial/full banking

1. Between stripped level and CBL

Undisturbed and disturbed (as in A-1)

2. Below CBL Undisturbed (As in A-2)

132

3. Borrow area (if required)

Disturbed (One sample for every 1.5 m. depth or change in stratum whichever is less)/

Sample should not be collected from top layer, which is required to be stripped. In case of the bore holes, details such as colour of wash water, water loss at various depths, time rate of penetration etc. should be noted and recorded for proper appreciation of the sub-soil condition.

3.2.3 For cohesive ( C –ø) material as well as fine grained soils, at least one sample for each stratum met with or at every 1.5 m. depth whichever is less should be tested as below.

Nature of sample Tested for

Disturbed samples MA, AL, Proctor and shear parameters on sample remolded at 95% MDD &

OMC. Undisturbed samples MA,AL,Field dry density, moisture

content and shear parameters at FDD, FMC.

Note:- Laboratory permeability test should be carried out at least for one undisturbed and one remolded sample of the representative soil in each trial pit.

3.2.4 Where material is cohesion less, the maximum and minimum density tests should be carried out on the disturbed sample. The tests for engineering properties and shear values for the material should be carried out on samples from various depths remolded at 65% relative density. If it is possible to collect undisturbed samples, the soil tests should be carried out on such samples at FDD and FMC. For the soil strata where the canal is in partial or full cutting, Vane shear tests (IS 2720 (Part – 30) 1980) at 1.5 m. intervals should invariably be carried out if undisturbed samples can not be collected.

133

3.2.5 BORROW AREA

i) The soil samples should be collected by excavating trial pits spaced suitably, based on the area, nature of soil, type of deposit etc. However initial spacing of about 400 m c/c is suggested for guidance. The spacing need not be closer than say 100 m c/c. The final spacing should however be decided by the concerned Executive Engineer in consultation with the Executive Engineer (Quality Control).

ii) The depth of borrow pit depends on: a) The types of excavating units and the quantities to

be borrowed with respect to the nature of the soil and the land area available,

b) The safety during borrowing of material. c) The ground water table d) The hard stratum horizon.

iii) During excavation of the trial pits the field engineer not below the rank of Deputy Executive Engineer (responsible for investigations, construction and testing) should keep close watch on the soil available from the borrow pits.

iv) If the soil available differs appreciably, based on visual observation from the type of soil required, it should be immediately reported to the Executive Engineer who inturn should take suitable action in consultation with the Executive Engineer (Quality Control).

v) If the soil properties marginally differ, based on the visual observation, the problem should be reported to the Executive Engineer with the representative results of MA & AL tests of the soil. Then the Executive Engineer should decide in consultation with the Executive Engineer Quality Control, whether the investigations with the same borrow area should be continued or otherwise.

134

3.3 LABORATORY TESTS.

The samples collected as per para 3.2 above may be tested as below. The relevant Indian Standard should be followed for the procedure for soil testing. The list of Indian Standards is given vide Annexure-IV.

3.3.1 MECHANICAL ANALYSIS AND ATTERBERG’S LIMIT TESTS

These tests may be conducted for undisturbed/disturbed samples from trial pits/bore holes along canal alignment and borrow area (as per Para 3.2.2). These tests should be carried out only after the permeability and shear tests are carried out in the case of undisturbed samples.

3.3.2 PROCTOR COMPACTIONS

The standard proctor tests may be carried out for disturbed samples (as per para 3.2.2.) representing the soils proposed to be used in the canal banks. When at least 20% material is coarser than 4.75 mm. size, gravel corrected densities and moisture content may be given. When the higher compacting efforts are applied in the field, to simulate this in the laboratory, modified proctor tests may be performed.

3.3.3 INSITU DENSITY

The insitu density test should be carried out on the undisturbed samples collected from the trial pits as per para 3.2.2. (The dry densities and void ratios, gradation analysis and index properties may also be given. These data will be helpful in assessing whether the foundation material is likely to collapse on saturation or during earth quake).

3.3.4 RELATIVE DENSITY

a) Disturbed samples for banking: The relative density test should be carried out insitu at

various depths in the trial pits in the case of purely

135

cohesion less soil using the result of maximum and minimum densities as mentioned in para 3.2.4. The samples for shear test may be prepared at 65% R.D.

b) Insitu properties for soil

3.3.5 SHEAR TEST: The procedure adopted for the test should simulate the field

conditions viz. (i) The normal load and / or confining pressure (only for triaxial test) to be applied on the sample in the direct shear test should simulate the over burden pressure likely to act at the end of the construction. (ii) The drainage conditions and the rate of shearing adopted for carrying out the tests should also match with field conditions. (a) Box Shear Test:

The consolidated undrained shear tests should be carried out on the disturbed and undisturbed samples. For disturbed samples the shear tests should be carried out on the samples remolded at OMC with 95% proctor MDD. For undisturbed samples the tests should be carried out at FDD, FMC. When at least 20% material is coarser than 4.75 mm. size, large size box shear tests should be carried out. The details of test procedure should invariably be given. For test procedure IS 2720-Part 13-1986 should be followed. (b) Triaxial Tests:

At least 10% of the (disturbed and undisturbed) samples should be tested in triaxial shear test apparatus for consolidated undrain shear tests with pore pressure measurements. The consolidated undrain shear tests in box shear apparatus should also be carried out for these samples. In the case of undisturbed samples, this requirement will necessitate collection of two similar sample from the same location. The values may be given for total stress and effective stress (considering pore pressure) separately for comparison. For test procedure IS 2720 (Part-12) 1981 should be followed.

136

3.3.6 PERMEABILITY TEST:

The permeability test should be carried out on representative samples. When at least 20% material is coarser than 4.75 mm. size, large size parameter should be used. Field permeability tests wherever required should be carried out in consultation with the Design Circle. Field test should always be preferred to the laboratory tests wherever possible. IS 5529 (Part-I) 1985 should be followed.

3.3.7 (a) CONSOLIDATION TESTS:

When the foundations of a structure or any of its components consist of more than 2.0 m. deep compressible soil, consolidation tests should be carried out. The undisturbed samples should be collected at mid depth of overburden below the structure. The values of coefficient of consolidation (Cv) compression index (Cc) and graph showing void ratio (on Y axis) V/S pressure on log scale (on X axis) may be given (e log P curve). In a continuous canal reach passing through compressible soils, consolidation tests on two or three representative samples should be carried out with loads and drainage simulating the field conditions. These tests will be helpful in assessing the likely settlement of foundations or the canal banks.

(b) TEST FOR SUDDEN COLLAPSE:

When foundation soils are fine grained uniform soils like salty sands, Sandy silts or non cohesive soils having R.D < 65%, sudden collapse tests under saturation and seismic loading should be carried out.

3.3.8 EROSION RESISTANCE TEST: The quality of soluble salts present and the equivalent sodium content in the soil and ground water may be given. For soils having PI less than 10%, the pin hole and crumb tests should be carried out to assess their erosion resistant characteristics.

137

3.3.9 SWELLING PROPERTIES. If high LL (> 55%) is accompanied with low shrinkage limit

(<10), Swelling pressure and free swell tests should be conducted as outlined in CWC Publications “Lining on expansive soils” June, 1987

3.4.0 RECORDING AND REPORTING THE DATA: 3.4.1 The trial pits/bore holes should be located on the L.S and the plan

showing the canal alignment. The trial pits/bore holes etc. should be numbered with suitable symbols.

3.4.2 The soil should be described in the logs and in the records according to IS No.1498 – 1970. The weak clayey layers, organic fills, loosely deposited sand lenses etc. should also be shown on the logs. The R.L. at the beginning of each stratum should be given.

3.4.3 The results of laboratory tests of all disturbed samples should be given. The suitability of the material for each zone should be based on the results of engineering properties of soils based on Appendix-A of I.S. No.12169-1987 (Annexure-II) An estimation of quantities of different types of soils viz. (i) CL, CI, CL-CI, (ii) SC, (iii) SM etc. available and required for bank should be given.

3.4.4 The borrow area plan and sections should be prepared indicating locations of trial pits and demarcating zones of different soils based on the engineering classification viz. (i) CL, CI, CL-CI, (ii) SC, (iii) SM etc.

4.0 COMPONENTS AND CANAL SECTION: A canal can either be in full cutting, partial banking or full

banking. A canal section in bank generally consists of following components. The zones however may be decided so as to accommodate practically all the excavated material. Only the balance quantity should be brought from the borrow area. i) core or impervious zone ii) casing or shell

138

iii) internal drainage system iv) surface drainage (seperately discussed in para -6) v) dowel. The functions and design requirements of these components are given below:

4.1 CORE:

The function of the core is to provide impermeable barrier in the body of the canal bank. Impervious soil with low to medium plasticity are suitable for core. Annexure-II shows the suitability of soils for construction of canal bank. Following guide lines are recommended for the design of the core. a)The core or impervious zone may be located either just

behind the lining or the centrally or inclined upstream, depending upon the stability requirement, availability of material etc. The impervious material having LL greater than 35 should not be placed behind lining.

b) The top of the core may be kept 0.50 meter above the FSL to prevent seepage by capillary siphoning.

c) Minimum top width of the core may be kept as 3.0 m. to facilitate proper compaction.

d) In case of bed banking the cores on both the banks should be connected with each other by an impervious layer covered with about 1.0 m. thick S.P. layers below the canal bed, if impervious material has LL greater than 35.

e) As far as possible the impervious zone of non expansive soil should be located just behind the lining. The top width of the zone can be 3.0 m. with slopes on u/s & d/s are as per provision of design requirement (Reference - IS code ). Adjacent to the impervious zone on the d/s side an inclined sand filter connected to the bottom horizontal filter should be provided if necessary . D/S of the inclined filter, all materials available from obligatory excavation should be suitably accommodated. If the availability of impervious material from the obligatory excavations is very substantial a thick central core should be attempted such that the width of the

139

u/s casing zone is sufficient to make the u/s bank slope stable under the sudden draw down condition. Filters may be provided as per requirement. If there is an u/s impervious zone and if the material for the casing zone is erodible, the outer portion of such an erodible zone can be covered suitably with erosion resistant impervious clayey material in case it is adequately available after meeting with the requirement of the u/s zone. A very thick u/s impervious zone should be avoided as otherwise the u/s outer slope probably become unstable in the sudden draw down condition.

4.2 CASING

The function of the casing is to impart stability and protect the core. Relatively pervious materials which are not subjected to cracking on direct exposure to atmosphere are suitable for casing. The top width of the canal bank should be provided as per canal bank section ( i.e 4.27 m on SR side & 2.50 m on IP side for branh canal ) . Beams may be provided about 6.0 m or as per design requirement . vertical interval. A beam width of 4.0 m.is desirable. The effective thickness perpendicular to the slope of the casing at the road level and at the beam level shall be 1.0 m. or more.

4.3 CANAL BANK

4.3.1 HOMOGENEOUS SECTION

An embankment of canal composed of single type of material.

4.3.2 RANDOM ZONE

The use of practically all the material available from the compulsory excavation may be planned in the appropriate zone. If this is not possible, the same may be used in a random zone which is generally located d/s of the inclined filter. Annexure-II may be referred for suitability of soils for construction.

140

4.4 INTERNAL DRAINAGE SYSTEM

The internal drainage system controls the seepage through the canal bank. The system generally consist of i) inclined filter, ii) horizontal filter, iii) rock toe cum toe drain, iv) pressure relief valves. The internal drainage should be provided for smaller bank height than the specified below, if required from safety considerations.

4.4.1 INCLINED FILTER:

The inclined filter is provided D/S of the impervious zone with or without transition zone in between, to collect seepage from the impervious zone and thereby keeps the d/s casing portion of the canal bank relatively dry. The inclined filter is to be provided in the cases where the canal section is in full banking or in bed banking. The filter material should be free draining having a permeability of 5 x 10-3 cm/sec or more. The inclined sand filter should be provided up to ¾ th height of FSD above CBL. It is preferable to provide inclined sand filter up to the FSL, where sufficient quantity of sand is available. The width of inclined sand filter should be kept 0.90 m.

4.4.2 HORIZONTAL FILTER:

The horizontal filter collects the seepage from the inclined filter and carries to the rock toe cum toe drain. It also collects seepage from the foundation and minimizes possibilities of piping of the canal seat. It is usually provided at ground level in the d/s of core or impervious zone. A d/s grade of about 1 IN 100 may be provided towards the rock toe for quick disposal of seepage water. i) The thickness of horizontal sand filter should be 30 cm.

(compacted) for partial banking (more than 5.0 m. height) and 60 cm. for the canal sections having full banking and bed banking.

141

ii) The horizontal sand filter of minimum thickness 30 cm. (compacted) may be provided where sufficient quantity of sand is not available.

iii) In a length of 15.0 m. adjoining cross drainage structure, the horizontal sand filter of minimum thickness of 60 cm. may be provided.

In case the upstream casing zone material has permeability less than 10-4 cm/sec. and high draw down pore pressures are apprehended, one or two intermediate horizontal sand filters might be considered in the zone. This should, however be avoided as far as possible by carefully selecting the upstream casing material. The design criteria for the filter material to be followed for horizontal/inclined filters is given in para 4.4.5

4.4.3 ROCK TOE CUM TOE DRAIN: The function of rock toe cum toe drain is to facilitate drainage of seepage water and to protect the lower part of d/s slope from accumulated surface water. The rock toe cum toe drain is provided at the d/s toe of canal banks to collect seepage water from the horizontal filter and to discharge it may from the bank. i) The design of rock toe should generally be provided

if the bank height exceeds 5.0 m. However the rock toe should be provided for smaller bank height for safety considerations. Where the horizontal filter is provided in the section. The design of rock toe should be adopted as given in Plate-II.

ii) In a length of 15 m. adjoining the cross drainage structures, the height of rock toe should be provided as h/6, where h is hydraulic head. The details of components are shown in Plate-II.

4.4.4 PRESSURE RELIEF VALVE

A lined canal crosses areas subject to seasonal high ground water or where the soil is sufficiently water tight to prevent the free draining of the seepage/leakage from the canal.

142

Pressure relief valves protected by surrounding graded filters are provided on the canal slopes and in the bed to relieve excess hydrostatic pressures behind the lining. These one way valves open out in the canal to drain the water from behind the lining. The PRVs should normally be provided where the permeability value of the sub grade either in cutting or in banking is between 10-4 cm/sec and 10-6 cm/sec. To reduce the pore pressures in the upstream casing zone, for stability requirement, the PRVs with 0.15 m. thick (minimum) horizontal filter blanket (preferably 0.30 m thick) can be provided irrespective of the permeability value of the sub grade. These horizontal filter blankets may extended in the portion (casing and/or core) in which the pore pressures are required to be lowered. In case these blankets extend in to the core, the effective thickness of the core beyond the toe of the horizontal filter blanket should not be less than one third the hydrostatic head acting at the point.

(I) Where the sub-soil water level is below CBL

Size of P.R.V.

Spacing along

Canal.

Location

150 mm dia. 50 mm dia.

16 m c/c 16 m c/c

Four in bed and two on slopes as shown in Plate –IV at lower elevation. Two at higher elevation on slopes (one on each slope)

(II) Where the sub soil water level is above CBL, following measures

could be considered. (i) Raised bed humps up to 1/3rd height of canal FSD can

be provided and kept filled with water to provide counter weight of uplift pressure. Till then some portions at suitable integrals can be left unlined to allow direct drainage and release of pressure.

143

(ii) Deep tube wells can be installed outside the banks. The water can be pumped in to canal to augment the supply

(iii) The pressure release valves may be provided in Narmada Main Canal (Refer Plate-IV) . The details of lining and under drainage arrangements are shown in Plate III & IV ( provided in Narmada Main Canal) .

(III) Where the sub soil water level is close to FSL. The under drainage arrangements may be provided as shown

in Plate V. If necessary, some additional measures like (i) & (ii) in (II) above could also be considered.

4.4.5 FILTER CRITERIA

The filter material should be well graded. It should not usually contain more than 5% material passing through 75 micron IS sieve and should not have size greater than 75 mm. So as to minimize segregation and bridging of large size particles. It should satisfy the following standard filter criteria between the adjoining zones. (a) D 15 (f)

------------ > 4 and < 20 D 15 (b)

(b) D 15 (f) ----------- < 5 D 85 (b)

(c) D 50 (f) --------- < 25 D 50 (b)

(d) The gradation curves of the filter material should be nearly parallel to the gradation curves of the base material. In (a), (b), (c) above, the suffix,

f = filter material b = base material

144

and 15,50,85% particles by weight respectively are finer than D15,D50, and D85 particle sizes.

4.5 DOWEL:

(I) We can have concrete parapet T shaped or L shaped dowels. The dowels edge may be 30 cm. away from the water side edges of the canal bank top.

(II) An earth dowel provided on the canal side edge of the bank provides an extra free board over and above the normal free board of 1.5 m. It prevents the surface water from entering in to the canal or behind the lining and prevents undermining of the soil below the lining. The top width, height, canal side & road side slopes of the dowel are proposed 1.0 m, 0.60 m, 2(H):1 (V) and 1.5 (H): 1 (V) respectively. Dowels may be replaced with parapet walls at the structures.

5.0 STABILITY ANALYSIS:

For the design of the canal bank, the alignment is divided in small reaches based on the following considerations. (a) The quantity of banking material required is obtained to

the maximum possible extent from the same slice from the cutting so that necessity to bring material from longer leads or from the borrow areas is minimized.

(b) As far as possible the transportation of materials remains within the major drainage crossings.

(c) There is not much variation in the properties of soils in the same slice so that the slopes as per the stability analysis remain identical for the whole reach.

5.1 SOIL PARAMETERS:

The suitability of material for each zone is decided based on results of engineering and index properties of soils and the criteria given in Annexure-II. For the foundation, the test results of undisturbed samples are required as mentioned in

145

Para 3.2 .A good number of consistent test results for each zone of the embankment and for the foundation material are necessary. 75% reliable values of MDD/FDD & Ø are obtained from the test results of disturbed and undisturbed samples and the corresponding values of OMC/FMC and ‘C’ respectively are adopted for the data and used as design constants. Lining, filters and rock toe cum toe drain are not considered in the stability analysis as they form a small portion of the canal bank.

5.2 PORE PRESSURE:

Pore pressures for various materials are assumed as under:

Sr.No

Material Construction condition

Sudden draw down condition.

Steady seepage condition.

a) b) c)

Impervious K< 10-6 cm/sec. Semi pervious 10-6 < K < 10-4

cm/sec. K > 10-4 cm/sec. Foundation K>10-6 Above C.B.L Below C.B.L.

50% X 25% X Nil Nil Nil

100% X 50% X Nil 50/100* 100*

100% 50% Nil 100* 100*

Remarks:- The figures are percentages of water columns equal to the height of the height of the embankment over the trial failure surface at various point.

X The pore pressures to be considered can be reduce to

half the values given above if horizontal filter mats are provided in the canal side casing of the bank. (Please. see Para 4.4.4.)

* For foundation strata of impervious type material.

The pore pressures are accounted in terms of heights of water columns. In operating and sudden draw down

146

conditions the buoyant weights are considered.

5.3 SAEISMIC-COEFFICIENT:

The horizontal component of seismic coefficient is worked out by seismic coefficient method given in the IS – 1893 – 1984 (Third Revision) on “Earth quake resistant design of structures”. The map of India showing seismic zones is referred for deciding the zone in which the canal bank is situated. The importance factor for NMC is however adopted as 2.0 against 3.0 for the dam. Only the horizontal component of seismic coefficient is considered in the analysis.

5.4 METHOD OF STABILITY ANALYSIS:

The stability analysis of canal bank is carried out by Swedish slip circle method of analysis. The effective stress method is adopted as recommended by IS 7894 – 1974” Code of practice for stability analysis of earthen dams”. In this method the factor of safety is worked out for a number of trial failure planes (Circular) which are adopted based on the geometry of section, zoning, properties of the material, boundaries of drawdown etc. The Canal side slope is checked for the construction and sudden drawdown conditions. Where as the land side slope is checked for the construction and steady seepage conditions. The operating condition or the steady seepage condition is also checked for earthquake effect. The factor of safety is worked out for each failure surface and the minimum value should not be less than the permissible value.

5.5 ACCEPTABLE FACTOR OF SAFETY :

The permissible value of factor of safety for each condition is given below.

Slope Condition Permissible value of factor of safety as adopted for NMC

As per I.S.

U/S i) End of construction 1.0 1.0

147

Slope *ii) Operating condition.

a) Without earth quake

b) With earth quake iii) Sudden

drawdown condition.

1.3

1.0

1.0

- - 1.3

D/S Slope

i) End of construction ii)Steady seepage

condition. a) Without earthquake b) With earthquake

1.0

1.5 1.0

1.0 1.5 1.0

Note:-(1)As decided during the 11th BOC Meeting checks for operating condition with and without earthquake may not be performed for the canal side slope.

(2)In the third Meeting of the Board of Consultants the minimum desired factor of safety under sudden draw down condition was reduced to 1.0 with controlled drawdown for U/S slope. This is being followed since then.

6.0 PROTECTION TO OUTER FACE: The Narmada Main Canal 460 km. long runs in partial

banking and full banking up to 17 m. height in considerably long reaches. The top width the of service road is 8.0 m. The outer slopes of the canal banks are 2(H): 1(V). The rain water may, therefore, run down the slopes at high velocity, eroding the canal banks. The erosion may be leading to finally deep rain cuts. These rain cuts shall have to be filled with compacted earth during maintenance, which is a very tedious work apart from being exceptionally costly and susceptible to serious damage.

In order to cut down the maintenance cost and minimize unforeseen problems due to erosion, the following measures (Broad guidelines) are proposed to protect the banks

6.1.1 SOIL CONSERVATION:

Rain water falling over the earthen bank and rolling down

148

the d/s slope of the bank will lead to sheet erosion. Sheet erosion strips the soil from unprotected surface of the earthen bank and moves down the slope with run off water. Sheet erosion leads to rill and then gully erosion. Vetiver grass is a useful plant to prevent soil erosion economically. The vetiver grass with its fibrous rooted shrubs and grasses planted as hedges along the contour can prevent the sheet erosion. They slow down the run-off water, spread it out, take erosive power out of it, filter out the soil it is carrying and let the filtered run off proceed down the slope gently without any further erosive effect. Vetiver grass is the ideal plant for this purpose. It has the following characteristics that make it ideal for soil conservation and stabilization. The details are given in Plate-II. (a)It is extremely cheap, because once the vetiver nursery is

established; the planting material can be received at no cost.

(b)It has a deep strong fibrous root system. (c)Planted at the correct distance it will quickly form a dense

hedge, under-lain by a dense curtain of roots binding the soil along contour.

(d)Once established, it is generally unpalatable to live stock. (e)It is perennial and will last as a hedge, not requiring

maintenance for years. (f)It can withstand fires, droughts, inundation and floods. (g)Its leaves and roots have demonstrated a resistance to

most pests and diseases. 6.1.2 Slope protection with vetiver grass along with surface drainage

arrangements as mentioned in Para 6.3 would help to arrest erosion of banks. However in acute cases the bank slopes can be protected with a cement stabilized or lime stabilized plating layer 25 to 30 cm. thick laid over the slopes and compacted with twin slope compactors. Pilot test strips of suitable lengths shall have to be laid before taking up such work on a large scale. The cement soil proportions, method of mixing, moisture content, lift thickness, number of passes of compactors etc. shall be decided based on such tests.

149

6.2. CATCH WATER DRAINS

The rain water falling over the top of bank and on the slopes moves down the slopes eroding the slopes. It is necessary to provide a system of drainage arrangement i.e. the catch water drains horizontally along the bank as well as inclined on the surface of the bank. These drains will collects rain water at every 6.0 m. vertical height and finally discharge the water beyond the toe of the bank. It is proposed to provide horizontal drains of 15 cm. dia half round pipes or brick/stone paved drains at tops of banks and at beam level i.e. at every 6.0 m height. The drains paved with brick/stone/ cc (0.30 m. x 0.15 m) are however preferred to the 15 cm. dia. Hale round pipes. The inclined drains of 15 cm. dia half round pipe or brick paved drains are proposed at 90 m. c/c along the canal banks. A brick masonry Kundi is proposed at every junction of the horizontal and the inclined drain. The details are given in Plate-II for ready reference.

6.3. OUTFALL HOLES IN TOE DRAIN:

The toe drain is provided at the d/s toe of the bank to collect seepage from the horizontal filter and to drain it safely away from the toe In order to avoid choking of rock toe it is proposed to fill the voids in exposed surface, with pointing with cement sand mortar, along the entire length of canal where toe drain is provided. It is necessary to provide the outfall holes in the toe drain from where the seepage water collected in the to drain can be drained out, otherwise there will be rise in water level in the d/s casting zone. The out fall holes in the toe drain shall he provided at every change of gradient at d/s toe or maximum 300 m. distance. The details are shown in Plate-II.

7.0 QUALITY CONTROL CRITERION:

The N.M.C 460 km. long, runs in partial banking and full banking in considerably long reaches. In order to obtain

150

uniform and proper quality control along the entire alignment, following guidelines related to earthwork in canal bank construction should be followed.

In order to carry out construction of canal banks and concurrent investigation on uniform lines the technical circulars issued are given in Annex-VI for guidelines.

7.1 The canal bank consists of zones having fill materials of

different characteristics. All zones should be raised simultaneously and to lines and levels as shown on the drawings. The properties of the bank material should be as specified in the design note and drawings. In case the material as specified in the design note is not available, the problem should be referred to Narmada Project Design Circle,, Gandhinagar for review of the design.

7.2 The roller should travel in the direction parallel to the

alignment of the canal. For rolling at the junction between two adjacent zones, the roller with low rolling pressure suitable for any of the two adjacent zones, should be used. The rolling at the junction should be done in such a way that the joint between the zones falls more or less in the middle of the roller width.

7.3 The dry density attained should be at least 95% of the MDD

(standard proctor) obtained in the laboratory for the material. If the field density achieved is less than the design density, the data should be furnished to the Narmada Project Design Circle, Gandhinagar to review the design.

7.4 For cohesion less material, the relative density of the compacted

material should not be less than 65% as determined by laboratory tests.

7.5 Field officers should be impressed upon about the importance of

drainage and protective filter arrangements within the body of the earth bank. Proper quality control regarding the type of

151

material, gradation and avoidance of contamination by the adjacent zone materials should be exercised by the field officers. The thickness of the filter and the continuity of the filters should be properly maintained in the whole length of the earthen bank during the execution. The horizontal filter should be completed and covered with suitable soil at the earliest so as to avoid contamination with foreign material. In the case of less cohesive soil or erodible hearting core soil, it is all the more necessary that the filter criteria in the direction of flow are strictly satisfied. If the filter criteria between any two zones is not satisfied the problem shall be referred to Narmada Project Design Circle, Gandhinagar to review the designed section.

7.6 For proper bond with the constructed canal bank, the new earth work should be carried out and finished as under.

7.6.1 In case the constructed bank is to be extended horizontally, the uncompacted soil from the end of the old bank should be removed and it should be cut to a slope not steeper than 1 in 3. The cut surface should be scarified properly just in advance of placing a new earth layer, to form benching steps of the height equal to the layer thickness and moistened. New earth layer should be laid with proper moisture content and compacted simultaneously with the adjacent old earth work so as to form homogeneous earthwork at joint.

7.6.2 If the existing bank is to be raised vertically, vegetation lose earth, organic material etc. should be cleared. Rain cuts, if any should be shaped so as to remove the loose soil. The rain cuts then should be filled up with compacted earth work. Surface should be made loose at least for a depth of 15 cm. necessary watering should be done and new material should be laid in layers and compacted.

7.7 Proud should be cut just prior to execution of lining. At the time of cutting the proud it should be ensured that the cut surface is well compacted earth.

7.8 If expansive soil is met with during excavation of the canal in partial or full cutting, the problem should be referred to

152

Narmada Project Design Circle, Gandhinagar along with necessary details viz. engineering properties, swelling pressure and free swell index of expansive soil and the engineering properties of the CNS material from canal excavation and/or borrow area etc, to evolve suitable treatment as may be necessary.

8.0 BOARD OF CONSULTANTS (BOC)

The design of the canal banks is prepared in house by the NPDC, Gandhinagar. As per suggestion of the World Bank, Sardar Sarovar (Narmada) Project Authority has set up the Board of Consultants (BOC) comprising independent experts to conduct periodic reviews of the design and the construction of N.M.C. The recommendations of the BOC for specifically identified problems (Agenda items as listed in Annexure-V) are incorporated in the design of the canal banks. In addition, for intricate problems related to the safety of the canal banks, the services of experts in the corresponding field are utilized.

9.0 SPECIAL PROBLEMS:

9.1 EXPANSIVE SOILS AND CNS MATERIAL

(Ref: 6th meeting of BOC held at Vadodara from January 19-21, 1988) Expansive soils contain Montmorillonite or combination of Montmorillonite and Elite clay minerals having expanding lattice in the clay fraction. It exhibits heave when moisture content increases. Cohesive non-swelling soils (CNS) possess cohesion but do not exhibit heave. Swelling soil behind the lining may exert a high pressure on the lining. It is therefore replaced with CNS soil of adequate thickness to counteract the swelling pressure.

The testing, design and construction of the CNS layer should be carried out as per Central Water Commission Publications “Lining of Canals in expansive soils” June, 1987. Slope

153

stability of the canals in cutting in expansive soils should be reviewed after carrying out triaxial shear tests simultaneously on samples taken out from the same location both in the project laboratory and in GERI for comparison and confirmation of test results.

9.2 MICA SCHIST:

(Ref: 6th meeting of BOC held at Vadodara from January 19-21,1988) The recommendations of BOC are as under: a) The weathered Mica-Schist may be used only in the outer

zone of the canal embankment. b) To see if 95% proctor density can be achieved in the field,

field trial should be conducted with smooth drum roller. If required density can not be achieved with reasonable efforts with smooth drum roller then only the density criteria may be relaxed.

c) The concrete lining should not be placed directly on top of Mica-Schist layer. The Mica-Schist layer. The Mica Schist layer should be over excavated by at least 1.0 m.(horizontally) on sides and 0.30 m. in bed and back filled with semi-pervious type of soil to a compactable width and compacted to achieve the 95% proctor density.

9.3 ML TYPE OF SOIL:

(Ref:- 7th meeting of BOC held at Vadodara from June 28- 30,1988). The recommendation of BOC are as under. a) The treatment of sub-grade as decided for Mica-Schist

strata during the 6th BOC meeting should be followed in this case also.

b) To take care of settlement problem, the bed should be soaked with water so that prior to laying lining over it, it gets settled to the maximum extent possible.

9.4 SM TYPE OF SOIL:

(Ref: Agenda item No.7,11th BOC held at Vadodara from 26-

154

28 February, 1991)

The canal traverses in reach where SM soils are predominant The canal section in this soil is not safe from stability consideration and from erosion of slope during monsoon.

The recommendation of BOC are as under:

(A) Stability i) As the canal supplies were to be regulated very

carefully and further for reasons explained in paras 3.1 and 3.3. the Nigam may not perform the checks for operating condition with and without earth quake.

ii) In respect of check of sudden draw down condition the safety factor of 1.0 as approved already would stand, although the Nigam might carry out the stability on the basis of revised values of C and Ø which would correspond to the values as would obtain in the field.

iii) In banking soil abutting the lining should be the best available.

(B) To protect the banks from erosion.

i) It would suffice to provide a small pucca drain on the outer side of banks, which should intercept rain water and carry to the drain to be provided at suitable intervals along the sloping portion of the bank. Suitable plants be grown on the slope to provide cover.

9.4.2 Though drainage combined with vegetative protection may suffice in many cases, special protection as mentioned in Para 6.2 might be required in certain cases.

9.5 Drainage arrangements where water table is high (reach from ch..124 to 144 km of Narmada Main Canal)

For above length of 20 km. where the depth of sub soil water level is in the range of 9 m. and above or close to full supply level, additional drainage arrangement need to be provided and in others, raised bed humps up to 1/3rd height of canal be

155

provided. Keep filled with water to provide counter weight of uplift pressure. Till then, some portions be left unlined to allow release of pressure (although not applicable in this case, deep tube wells could be installed out side the bank to keep water table low and to pump it in to the canal and augment the canal supplies). Drainage system need to be provided in the area served by Panam reservoir. It should have suitably placed cross drains from the higher land to the lower land in command.

As regard the design to be adopted, where additional drainage is to be provided the proposals made by the Nigam are modified as under.

In the bed, drains need to be only two longitudinal on the sides. There is also no need to have cross drains in the bed. However pressure release valves will be provided in the bed as in the past. On the slope cross drains proposed by the Nigam were approved. These longitudinal and cross drains will have perforated pipes embedded with filter around them and they will be suitably sloped along the canal bed.

Protection to outer face of canal bank by

Vetiver grass and toe drain arrangement.

156

Sardar Sarovar Narmada Nigam Ltd., Gandhinagar

Technical Circular No.NMC-1090-38-M Dated: 5th April, 1990

Circular The Narmada Main Canal 460 km. long runs in partial

banking and full banking in considerably long reaches. The rain

water running down the slopes at critically high velocity,

eroding the canal banks. The rain water carries earth particles in

the rock toe, thus chocking it and nullifying the very purpose of

the rock toe. During the inspection, the minor cuts were noticed

at some places on canal banks.

It is therefore directed to take following measures to prevent

soil erosion on outer face of canal banks and chocking of rock

toe.

1. Stabilization of slopes may be accomplished by the

establishment of vetiver grass. It is the ideal plant for this

purpose, so it should be planted as hedges along the contour

of bank, at very 3 m. vertival interval and along outer toe of

the top width and berms, as shown in sketch 1.

2. Horizontal and inclined surface water drains may be provided

to collect the rain water and finally discharge the water

beyond the toe of bank, as shown in sketch-1 and 2.

157

3. The voids in exposed surface of the rock toe should be filled

up with cement sand mortar to prevent the chocking of rock

toe. The out fall holes from rock toe should be provided as

shown in sketch-1 and 3 attached herewith.

It is further directed that careful and strict supervisions

should be arranged to see that the soil erosion is not taken place

on outer face of canal bank and the rock toe is prevented from

chocking by the loose earth rolling down from upper levels.

158

Sardar Sarovar Narmada Nigam Ltd., Gandhinagar.

Technical Circular No.NMC-1090-38-M

Dated 16th April, 1990.

Circular

Narmada Main Canal, 460 km. long, runs in partial banking

and full banking in considerably long reaches. In order to obtain

uniform and proper quality control along the entire alignment,

following guide lines related to earth-work in canal bank

construction should be followed.

1.0 The embankment consists of zones having fill materials of

different characteristics. All zones should be raised

simultaneously and to lines and levels as shown on the

drawings. The properties of the bank material should be as

specified in the design note. In case the material as

specified in design note is not available, the problem

should be referred to N.P.M.Canal Design Circle No.1, for

review of the design.

2.0 The roller should travel in a direction parallel to the

alignment of the canal. For rolling at junction between two

adjacent zones, the roller with low rolling pressure suitable

for any of the two adjacent zones, should be used.

3.0 The dry density attained should be at least 95k% of MDD

(Standard proctor) obtained in the laboratory for the

material. If the field density achieved is less than the

159

design density, the data should be furnished to

N.P.M.Canal Design Circle No.1, to review the design.

4.0 For cohesion less material, the relative density of the

compacted material should not be less than 65% as

determined by laboratory test.

5.0 Field officers should be impressed upon about the

importance of drainage and protective filter arrangements

within the body of the earth bank. Proper quality control

regarding the type of material, gradation and avoidance of

contamination by the adjacent zone materials, should be

exercised by the field officers. The thickness of the filters

and the continuity of the filters should be properly

maintained in the whole length of the earthen bank during

the execution. The horizontal filter should be completed

and covered at the earliest so as to avoid contamination

with the foreign materials.

6.0 For proper bond with the constructed embankment, the

new earth work should be carried out and finished as

under.

6.1 In case the constructed bank is to be extended horizontally,

the uncompacted soil from the end of old bank should be

removed and it should be cut to a slope not steeper than 1

in 3. The cut surface should be scarified properly just in

advance of placing the new earth layer, to form benching

steps of the height equal to the layer thickness and

moistened. New earth layer should be laid with proper

moisture content and compacted simultaneously with the

adjacent old earth-work so as to form homogeneous earth

work at joint.

160

6.2 If the existing bank is to be raised vertically, vegetation,

loose earth, organic material etc. should be cleared. Rain

cuts, if any should be shaped so as to remove the loose soil.

The rain cuts then should be filled up with compacted earth

work. Surface should be made loose at least for a depth of

15 cm. Necessary watering should be done and new

material should be laid inlayers and compacted.

7.0 Proud should be cut just prior to execution of lining. At the

time of cutting the proud it should be ensured that the cut

surface is well compacted earth.

8.0 If expansive soil is met with during excavations of canal in

partial or full cutting, the problem should be referred to

N.P.Main Canal Design Circle No.1, Gandhinagar along

with necessary details viz. Engineering properties, swelling

pressure and free swell index of expansive soil and the

engineering properties of CNS material from canal

excavation and / or borrow area etc. to evolve suitable

treatment as may be necessary.

9.0 The outer face of canal embankment on land side should be

protected against erosion as outlined in circular No.NMC-

1090-38-M dt: 5th April-1990 for “Protection to outer face

of canal bank by vetiver grass and toe drain arrangement”.

161

SARDAR SAROVAR NARMADA NIGAM LTD. GANDHINAGAR

TECHNICAL CIRCULAR NO.NMC-1090-38-M

Date: 17th April, 1990.

CIRCULAR

Preamble:

1.0 The canal banks are t present, being designed as an earth dam,

the internal drainage arrangement i.e. inclined and horizontal sand

filter and rock toe is provided to drain out seepage water safely away

from the canal banks.

The sand is required to be borrowed from the sand bed

available in local nala and / or the nearest river bed. This sand is also

required to be used in construction of masonary/concrete structures.

As such it is apprehended that adequate quality of sand may not be

available all along the length of the canal.

DECISION

2.0 In order to minimize the requirement of sand without

sacrificing the safety of the canal bank, it is directed that inclined sand

filter, horizontal sand filter and rock toe should be provided as below.

2.1 The inclined sand filter should be provided up to 3/4th height

of FSD above CBL. The width of inclined sand filter should be kept

0.9 m. The thickness of horizontal sand filter should be 30 cm.

(compacted) even for bank higher than 9.0 m. The thickness of

intermediate horizontal filter, (connected to PRV) provided to reduce

the pore pressure during construction and sudden draw down

162

condition, should be 0.15 m. thick (compacted).

2.2 The modified design of rock toe should be adopted, as shown in

figure-1.

2.3 It is also impressed upon about the importance of drainage and

protective filter arrangements within the body of the canal bank,

proper quality control regarding the type of material, gradations and

avoidance of contamination by the adjacent zone materials, should be

exercised during execution very scrupulously. Greater vigil should be

exercised particularly by the quality control staff in this respect. The

thickness of filters and their continuity should be properly maintained

as per design section. In case of less cohesive soils or erodible

hearting soils, it is all the more necessary that the filter criteria in the

direction of flow are strictly satisfied. If the filter criteria between any

two zones is not satisfied the problem shall be referred to N.P.Main

Canal Design Circle No.1, to review the designed sections.

Financial implications, if any due to above recommendations in

case of on going contracts should be got approved from the competent

authorities.

163

SARDAR SAROVAR NARMADA NIGAM LTD., GANDHINAGAR

NO.NMC-1090-38-m

TECHNICAL CIRCULAR Date: 21st May, 1990.

CIRCULAR

Preamble

1.0 It was brought to the notice of the undersigned that borrow area

investigation is carried out by testing large number of samples

collected from trial pits. The results of these samples indicated quite

different property of soil then the required one.

This results in to delay in design, unnecessary burden on testing

laboratories and infractituous expenditure.

DECISION

1.0 In view of this, all the field officers responsible for

investigation, testing and construction are instructed to clearly watch

the investigation work being done, so as to avoid recurrence of

incidents cited above in future. In order to stream line the procedure

the field engineers are instructed to follow the procedure laid down in

following paragraphs very scrupulously.

1.1 The soil samples should be collected by excavating trial pits

spaced suitably based on the area, nature of soil type of deposit etc.

However initial spacing of about 400 m. c/c is suggested for guidance

and close down to final spacing of say 100 m. c/c. The final spacing

should however be decided by the concerned Executive Engineer in

consultation with Executive Engineer (Quality Control).

1.2 The depth of the borrow pit should depend on the

1) Mode of excavating units.

2) Safety during borrowing of material

164

3) Ground water table

4) Hard strata etc.

1.3 During excavation of borrow pits the field engineers not

below the cadre of Deputy Executive Engineer (responsible for

investigations, construction and testing) should keep close watch on

the soil available from borrow pits.

1.4 If the soil available differs very appreciably based on visual

observation from the type of soil required, further work should be

immediately stopped and the problem reported to the Executive

Engineer should take suitable action in consultation with Executive

Engineer (Quality Control).

1.5 If the soil properties marginally differ based on the visual

observation the problem should be reported to Executive Engineer

with the representative results of MA and AL test of the soil.

In case of above the Executive Engineer should decide whether

the investigation in the same borrow area should be continued or

otherwise in consultation with Executive Engineer, Quality Control.

165

No.NPMCDC-1/D-14/2064. Office of the Superintending Engineer, N.P.Main Canal Design Circle-1, Narmada Block No.12,4th floor, New Sachivalaya Complex, Gandhinagar. Date: 12/6/1991.

To The Superintending Engineer, N.P.M.Canal Construction Circle.1, Vadodara.

Sub:- Protection to outer face of canal bank by vetiver grass and surface drainage arrangement. Ref:- SSNNL, Tech. Circular No.NMC-1090-38-M dt.5-4-90

1.0 The guide lines of measures to be adopted for the protection to outer face of canal bank from erosion of soil due to rain water, were issued vide technical circular referred to above. 2.0 The measures have been reviewed a fresh and approved by Engineer-in-Chief (Designs) recently. The principle modifications are given below. i) Vetiver hedges are provided at 2 m. vertical interval instead

of at 3 m. interval. ii) The horizontal and inclined surface drains are now proposed

to be paved with stone/brick instead of half round pipes. iii) The design of rock toe is modified as shown in plate attached. 3.0 A revised drawing showing all the details of components i.e. surface drainage arrangement and rock-toe arrangement dowel, etc. is furnished herewith. It is suggested to adopt the details of components for construction. The financial/contractual implications may however be got approved from the competent authority before execution.

166

ANNEX-I

SALIENT FEATURES OF NARMADA MAIN CANAL

(I) HEAD REGULATOR

(i) Location of H.R. On pond No.4

(ii) Nos. size and type 5 Nos. 12.20 m x 13.5 m.

of gates for H.R. Radial gates

(II) GENERAL DETAILS

(i) Length of main canal 460 km.

(ii) F.S.L.

a) At head 91.44 m. (300 ft.)

b) At tail 44.95 m. (147 ft.)

(iii) Capacity

a) At head 1133.05 cumecs

(40,000 cusecs)

b) At tail 71.10 cumecs

(2500 cusec)

(iv) Whether perennial seasonal or two Two seasonal seasonal (v) Whether contour or

Ridge canal. Contour Canal

(vi) Whether lined or Lined. Unlined

(III) CANAL SECTIONS

(i) Section a) At head 73.10 x 7.6 m.

b) At tail 10.10 x 4.4. m.

c) At tail 10.10 x 4.4 m.

(ii) B/D ratio

a) At head 9.618

b) At tail 2.30

(iii) Free board 1.5 m. (1.25 m. for Lining & 0.25 m. for Earthbanks.)

(iv) Bed Gradient 1 in 12,500 up to Mahi river crossing (Ch.km.0.0 to 144.50) and 1 in 15,500 beyond Mahi river crossing.

(v) Side slope 2 (H) : 1 (V)

(vi) Co-efficient of rugosity

0.018

(vii) Velocity

167

a) At head b) At tail

1.689 m/sec 0.8949 m/sec

(IV) CANAL BANKS

(i) Top width 8.0 m on both sides

(ii) Dowel

a) Top width 1.0 m

b) Height 0.55 m

c) Side slopes 2 (H) : 1 (V) on water side and 1.5 (H) : 1 (V) on

bank side.

(iii) Type of section Zoned section as per availability of soil and design

requirement.

(iv) Provision of i) No provision of filter up to 5.0 m bank height. Filter and rock However in certain specific cases filters as Required may be provided to ensure stability Of slopes or protection of soils. ii) Horizontal filter and rock toe for bank height between 5.0 to 9.0 m. Inclined filter may be necessary in certain specific cases.

iii) Inclined filter, horizontal filter & rock toe above 9.0 m height.

(V) LINING

i) Type of lining Machine placed M-16 c.c. lining. ii) Thickness of lining 12.5 cms. On slopes and 10 cms in bed. iii) Key at the top 0.35 m on both sides iv) Contraction joints At 4.0 m c/c v) Ladder rungs in lining Near the structure and at 1 km distance

stagered.

vi) Lining near structure 25 cms thick on slope & 20 cms thick in bed with nominal reinforcement. vii) Lining of expansive 1.0 m thick well compacted CNS layer Soil. to be provided. viii) Under drainage arrangement A network of longitudinal drain cross drains

168

& surface drainage continuous filter layer & pressure release arrangement. Valves are provided.

(VI) SPOIL BANK & BORROW PITS.

(A) Spoil banks

i) Height (i) 6.0 m if by machinery. (ii) 4.0 m if manualy. ii) Top width Minimum 1.5 m iii) Side slopes 1.5:1 iv) Gaps in continuous 10 m long at 150 m

spoil banks.

(B) BORROW PITS.

i) Depths Maximum 3.0 m ii) Width As per requirement. iii) Slopes. As per strata.

169

ANNEX - II (B)

APPENDIX - A. (Clauses 4.2.1, 4.3.1 and 4.7.2 )

SUITABILITY OF SOIL FOR CONSTRUCTION OF

DAMS.

Relative suitability

Homogeneous Dykes

ZONED DAM Impervious Blanket.

Impervious Core Previous casing Very suitable GC GC SW , GW GC Suitable CL , CI CL, CI GM CL, CI Fairly suitable SP, SM, CH GM-GC

SM-SC, CH SP, GP CH, SM

SC, GC

Poor - ML, MI, MH - - Not suitable - OL, OI , OG Pt. - - Note : Refer to IS : 1489 - 1970 classification and identification of soils for general Engineering purposes ( first revision ) '

170

ANNEX-IV

LIST OF INDIAN STADNARDS FOLLOWED TO STABILITY ANALYSIS AND DESIGN OF CANAL SECTIONS OF NARMADA MAIN CANAL (N.M.C.)

( Note : The list of IS code mentioned below are only for reference of IS code No, for design requirement latest version of IS Code shall be referred )

SR.NO.

DESCRIPTION I.S.CODE NO.

1. Classification and identification of soil for general engineering purposes.

1498-1970

2. Criteria for earthquake Resistant design of structures

1893-1984

3. Methods of tests for soils (Part-I) preparation of dry soil samples for various tests

2720-1983 (Part-I)

4. Method of tests for soils (Part-II) Determination of Water content. 2720-1973 (Part-II)

5. Method of test for soil (Part-IV) grain size analysis. 2720-1975 (Part-IV)

6. Method of tests for soils (Part-V)Determination of liquid and plastic limit 2720-1985 (Part-V)

7. Method of tests for soils (Part-VI) Determination of shrinkage factors. 2720-1972 (Part-VI)

8. Method of tests for soils (Part-VII) Determination of water content – dry density relation using light compaction.

2720-1980 (Part-VIII)

9. Method of tests for soils (Part-VIII) Determination of water content dry density relation using heavy compaction.

2720-1983 (Part-VIII)

10. Methods of tests for soils (Part-IX) Determination of dry density moisture content relation by constant weight of soil method

2720-1971 (Part-IX)

11. Methods of tests for soils (Part-X) Determination of unconfined compressive strength

2720-1973 (Part-X)

12. Methods of tests for soils (Part-XI) Determination of shear strength parameters of a specimen tested in unconsolidated undrained triaxial compression without the measurement of pore pressure.

2720-1971 (Part-XI)

13. Methods of tests for soils (Part-XII) Determination of shear strength parameters of soil from consolidated undrained triaxial compression tests with measurement of pore pressure.

2720-1981 (Part-XII)

14. Methods of tests for soils (Part-XIII) Direct shear test. 2720-1986 (Part-XIII)

171

15. Methods of tests for soils (Part-XIV) Determination of density index (relative

density) of cohesionless soils. 2720-1983 (Part-XIV)

16. Method of test for soils (Part-XV) Determination of consolidation properties.

2720-1986 (Part XV)

17. Methods of tests for soils (Part-XVII) Laboratory determination of permeability

2720- 1986 (Part-XVII)

18. Method of tests for soils (Part-XX) Determination of linier shrinkage 2720-1966 (Part-XX)

19. Methods of tests for soils (Part-XXI) Determination for total soluble solids. 2720-1977 (Part-XXI)

20. Methods of tests for soils (Part-XVIII) Determination of dry density of soils in place, by the sand replacement method.

2720-1974 (Part-XVIII)

21. Methods of tests for soils (Part-XXIX) Determination of dry density of soil in place, by the core cutter method

2720 – 1975 (Part-XXIX)

22. Methods of tests for soils (Part-XXL) Laboratory vane shear test.

2720-1980 (Part-XXL)

23. Methods of tests for soils (Part-XXLIII) Determination of the density in place by the ring and water replacement method.

2720-1971 (Part-XXLIII)

24. Methods of tests for soils (Part-XXXIV) Determination of density of soils in place by rubble balloon method.

2720-1972 (Part-XXXIV)

25. Method of tests for soils (Part-XXLVI) Laboratory determination of permeability of granular soils

2720-1987 (Part-XXVI)

26. Part XL Determination of free swell index of soil 2720-1966 (Part XL)

27. Part XLI Measuring pressure of soil. 2720-1977 (Part-XLI)

28. Laying in-situ cement concrete lining of canals 3873-1978

29. I.S.Code of practice for under-drainage of lined canals. 4558-1983

30. Code of practice for earthwork on canals 4701-1982

31. Code of practice for design of cross section of lined canals. 4745-1968

32. Criteria for design of cross section for unlined canal in alluvial soil.

7112-1973

33. Code of practice for design of drainage work part-II, Section-5 Syphon Aqueducts.

7784-1980 (Pt-II/Sec-5)

34. Code of practice for stability analysis of earth dams. 7894-1975

35. Code of practice for protection of slope for Reservoir embankment.

8237-1985

36. Guidelines for design of large earth and rock fill dams. 8826-1978

37. Code of practice for drainage system for earth and rock fill dams. 9429-1980

172

38. Guide for selection of method of measuring flow in open channels.

9922-1981

39. Criteria for design of lined canals and guidelines for selection of type of lining.

10430-1982

40. Code of practice for subsurface exploration for canals and cross drainage works.

11385-1985

41. Criteria for design of small embankment dams.

12169-1987

42. Code of practice for sealing joints in concrete lining on canals.

5256-1968

43 Code of practice for Maintenance of canals ( Part-III) for canal structures, Drains, Jungle clearance ,plantation & Regulation) .

4839 ( Part-III) -1969

44 Code of practice for Maintenance of canals ( Part-2 ) (Lined Canal ).

4839 ( Part-2) -1992

45 Guidelines for planning & design of surface drains

8835 -1978

46 Guidelines for Lining of canal in expansive soils

9451 -1994

47 Method of load test on soils

1888- 1982

48 Guidelines for planning & layout of canal system for irrigation

5968-1970

173

ANNEX-V

LIST OF AGENDA ITEMS PUT UP IN VARIOUS BOC MEETINGS.

Sr.No.

No. of meeting and Date.

Agenda Item No.

Description of Agenda Item Remarks.

1. First May 3.1986 (1) Stability of Narmada Main Canal slope. 2. Third March 13,1987 (1) Review of design of under drainage

arrangement behind canal lining (km.4 to 9)

-do- (3) Design of canal bank sections (Modified proposal)

3.. Fourth June 24/25,1987 (1) Review of design of under drainage arrangement behind canal lining.

4. Sixth (6) Provision of toe-drain in canal embankment of Narmada Main Canal.

-do- (8) Use of weathered mica-schist in the embankment of Narmada Main Canal.

-do- (9) Treatment of expansive soil layer in canal prism of Narmada Main Canal.

-do- Additional Agenda Item-1 & 2

Stability analysis of canal bank section.

5. Seventh June 28 to 30 1988

(4) To review under-drainage arrangements below lining.

-do- (5) To consider various alternative of zoning of canal embankment with special reference to BOC’s recommendation of providing impervious zone just below lining.

(7) To consider report on laying lining over ML type of soil.

6. Eleventh 26-28 February,1991

(7) To consider the review of the canal section in the reaches where SM type soil is predominant. Also, to suggest measures for control of erosion in such soil in canal cuts and embankments.

(9) To consider the drainage arrangement below lining in the reach of main canal where the water are high.

STATEMENT OF TEST RESULTS OF SOIL SAMPLE Annex-III

Name of work:

Sr. No

Lab No.

Sample Disturbed Or Undisturbed DS -------- UDS

Location Of sample

Grain size analysis Atterburgs Limits

IS Classi ficati ion

FDD/ MDD gm per Cu. m.

FMC ------- OMC %

Box shear

Perme- ability k @ 27 degree centi grade in cm/ sec

Remarks

Gravel % 4.75 mm & above.

Sand % 0.075 mm to 4.75 mm

Silt % 0.002 mm to 0.075 mm

Clay % less than 0.002 mm

L.L % WL

P.L % WP

P.I % IP

C Kg/sq. cm

Ø in degree

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

Notes: 1. Atterburg’s limit test is carried out on soil passing 75 micron sieve. 2. Box shear test is carried out on soil passing 75 micron sieve. 3. If a tri-axial test is carried out, values of C & Ø to be given in brackets. 4. The shear test is carried out on UDS sample/remolded sample/disturbed sample. 5. Unconsolidated; undrained/consolidated undrained consolidated drained type of sample Box shear test is carried out.

6. Permeability test is carried out on soil passing 75 micron sieve.

175

176

GUIDE LINES FOR DESIGN OF

HEAD REGULATOR ON BRANCH CANALS OF

SARDAR SAROVAR PROJECT

1.0 GENERAL: Head Regulator (H.R.) for distributaries off-taking from the branches act as

controlling devices for regulation of discharge. Pipe type H.R. shall be provided

upto and below discharge of 3.0 cumecs and R.C.C. open type H.R. are provided

above that. For discharge above 3.00 cumecs and below 8.50 cumecs, an open

type H.R. with vertical gate shall be provided, while for discharge above 8.50

cumecs an open type H.R. with radial gates shall be provided. The H.Rs. shall be

separately located at about 30m. U/S of the cross regulator and shall usually be

at right angle to the direction of flow of the branch canal and distance between

two consecutive H.Rs. should be 10m atleast.

2.0 LAYOUT: The layout shall include following components.

1. Inlet transition

2. Gate bay portion.

3. Water conveyance conduits across distributary bank in the form of pre-

cast R.C.C. pipe or open H.R. trough.

4. U/S and D/S head walls for pipe H.R.

5. Outlet transitions.

3.0 HYDRAULIC DESIGN: 3.1 Operating Water Level (H.W.S.L./F.S.L.)

On account of closure of D/S C.R. water level in the branch canal will Level up. It

will rise up to some extent higher than FSL in the lower half of water pool between

two consecutive CRs and the H.W.S.L. will be lower than F.S.L. in upper half of

the water pool. The operating water level will be F.S.L. in lower half of the pool

while H.W.S.L. will be the operating water level in the upper half of the pool.

3.2 Driving Head: For open type H.R. driving head shall be considered equivalent to the difference

between FSLs of branch canal and off-taking canal (i.e. distributory, minor, direct

outlet etc.) for pipe type H.R. the driving head is the difference between the F.S.Ls'

of the branch canal and the distributary in the lower half of the water pool and

between H.W.S.L. of branch canal and F.S.L. of the distributary in the upper half

of the water pool (as shown in Sketch at Annexure-I). The same should be 0.15m

but in no case shall be less than 0.10mt.

3.3 Waterway: For pipe type H.R.

Waterway shall be calculated using orifice formula which is

177

Q = A X V

where V = C 2gh ½

(Ref. Training Course on canals & canal structures Lecture Vol.III 1961

C.D.O.)

The values of co-efficient of discharge C depends on Land and D

Where L = Length of pipe

D = Diameter of pipe

h = driving head

L/D C

2 - 0.82

3 - 0.82

5 - 0.79

10 - 0.77

25 - 0.71

50 - 0.64

75 - 0.59

100 - 0.55

The diameter of pipe shall be between 0.45m and 1.2m

(a) For distributary Minimum diameter of pipe shall be 0.90m subject to that the

velocity in pipe shall not exceed 1.50 m/sec.

(b) For minor/direct outlet Minimum diameter of pipe shall be 0.45m subject to that the

velocity in pipe shall not exceed 1.50 m/sec.

( c) For open type H.R. For open type HRs. the waterway shall be calculated as under:

(Reference page 97) Irrigation Eng. Canals & barrage Vol. By

Serge Leliavsky-reprint edition 1983)

For free flow (Drowning ratio < 0.8)

Q = Cs Le H** 3/2

(As per IS 6531 – 1994)

For submerged flow

Q = C Le H 2gh

Where, C = Co-efficient of discharge which may be considered

as 0.72.

Le = Effective Length (As per Cl. 3.3.1 of I.S. 6531-1972)

H = D/S water depth

h = Difference between u/s & d/s water levels.

3.4 Exit Gradient: The length of structure shall be sufficient to provide adequate length of path for

178

seepage against piping action. This shall be computed by Khosla's exit gradient

theory. The value of safe exit gradient shall be adopted as per I.S. 6531, 1972 as

under:

Permissible exit gradient: Type of soil GE

1. Find Sand 1/6 to 1/7

2. Coarse Sand 1/5 to 1/6

3. Shingle 1/4 to 1/5

3.5 Uplift pressure For working out uplift pressure in the foundation, Khosla's theory shall be

adopted and 100% uplift pressure shall be taken into account. Following

conditions shall be checked up for uplift.

1. No water in the distributary and the branch canal pooled up at maximum

water level.

2. There is no water in the branch canal and distributary canal is pooled up at

F.S.L.

3.6 Head loss in pipe type H.R. For pipe H.R. it is considered essential to workout loss of head at the end of

conduit. For this, formula used is

H1 = (1 + f1 + f2L) x V2

R 2g

Where f1 = 0.505 for cylindrical entry and 0.08 for

Smooth transition

f2 = A(1 + B/R)

R = Hydraulic mean depth in m = D/4

L = Length of pipe in m.

V = Velocity in m/sec.

A = 0.00316 &

B = 0.0305 for R.C.C. pipes

3.6a Fixing soffit of pipe

To ensure that pipe will flow full in all condition, in case of pipe

H.R. it is necessary that its soffit level at entrance is kept lowest of following.

(a) Below the lowest u/s water level of parent canal ((i.e. F.S.L.

or H.W.S.L. whichever is lower) – head loss at the H.R.

(b) 15 cm below F.S.L. of distributary.

3.7 Cut-off walls Cut off walls are provided at u/s and d/s ends of floor.

u/s cut-off Depth of u/s cut-off wall shall be maximum of the following.

i) Depth of u/s cut-off = d 1/3 + 0.5m ……..(i)

(I.S. 6531-1972 Cl, 3.7.2.2) where d = U/S FSD in m.

179

ii) As per U.S.B.R. D/S cut-off depth = 0.69 d 1

(d 1 = d/s FSD in m.)

The thickness of cut-off wall shall be 0.30m. Fillets not provided.

Generally depth of cut-off on u/s & d/s sides shall be 1.50m &

2.00m below corresponding floor level respectively.

3.8 Other Hydraulic features Inlet For pipe type H.R. The inlet transition floor and gate bay floor shall be kept at same level

i.e. pipe shall be placed directly on floor.

Open type H.R.

Hump of minimum 0.15 mt. and maximum of 40% of U/S F.S.D. but not

exceeding 0.5 mt. shall be provided (above U/S or D/S C.B.L. whichever is

Higher).

(a) Stoplog grooves The stop log groove at size as listed below has to be provided in the U/S of

gate groove for the maintenance of structure whenever required.

Max. water depth (d) Size of stop log groove

d < 2 m. 200 mm x 200 mm

2m < d < 4m 550 mm x 250 mm

d ≥ 4 mt. 675 mm x 400 mm

4.0 ENERGY DISSIPATION: As the canal is to be operated on controlled volume concept, water will be stored

in the pool created between two consecutive cross regulators. Hence under all

operation conditions submerged hydraulic jump will be formed. However during

initial filling of the distributary (which is completely empty) from the branch canal

running at its design discharge, energy dissipation during low discharges @ 20%of

the designed discharge will be necessary for flows with very low Froude numbers.

To take care of this, nominal stilling basin of @ 3.0m or so length shall be

provided beyond exit of pipe or H.R. floor. The floor of stilling basin shall be kept

usually 30 cm. Lower than the CBL of off-taking distributary or invert of pipe

whichever is lower. The depressed floor shall be joined with the bed of the off-

taking canal in a bed slope of 5:1.

Open type H.R.: For energy dissipation length of stilling basin (cistern) shall be

provided by using blench curve and concern value of Ef2 shall be derived. Then

basin shall be kept having length equal to 5 times Ef2 value. The floor of stilling

basin shall be kept usually 30 cm. Lower than the CBL of off-taking canal or gate

bay floor level whichever is lower. The depressed floor shall be joined with the bed

at the off-taking canal in a bed slope of 5.1m.

5.0 STRUCTURAL DESIGN: 5.1 General: All R.C.C. components shall be provided with M-25 concrete.

180

5.2 Inlet transition: R.C.C. retaining walls integral with the base floor or

otherwise shall be provided. Inlet transition shall be designed as per the

loading conditions given in Annexure-2.

5.3 Gatebay portion: In the gated bay portion, the thickness of piers etc. shall

be provided as per requirement of stop log and gate embedded parts. The

working space between stop log & gate groove shall be minimum 1.20m.

5.4 Head wall for pipe H.R.: Head walls for pipe retain the earth above the

pipe barrels. Head walls shall be 0.30 thick at top, and as per structural

requirement at its base. The top of u/s head wall shall be kept at a level

worked out by considering opening of the gate along with clearance at the

top. It shall be monolithic with piers of gate bay portion. D/S head wall

shall be kept at T.B.L. of off-taking canal, or 1.2m above the soffit of pipes

at u/s head wall whichever is higher. Head walls shall be designed as per

loading conditions given in Annexure-3.

5.4.1 Foundation:

Foundation of U/S headwall shall be monolithic with inlet and gate bay

portion 550 mm below pipe bed level with R.C.C. M25 i.e. raft foundation.

While for D/S head wall foundation shall be 300 mm below pipe bed level

with R.C.C. M25. When the soil below the structure is expansive (CH

type), the soil upto 1.00 mt. depth shall be completely removed below the

structure and fill up with selected earth (Gritty type material) filling with

compaction achieved upto 9.5% proctor density. For other soil with very

low compressibility, entire structure shall be placed on foundation of

undisturbed earth on thoroughly compacted fill.

R.C.C. Open H.R.

For continuity of Service Road, the slab is provided at the top of bank level.

The open H.R. floor shall be laid in grade 1 in 62.5. Loading conditions

shall be used as per annexure-IVB.

5.4.2 Reinforcement: High yield strength deformed bar shall be used for

reinforcement R.C.C. design shall be carried out in accordance with the

criteria stipulated in I.S. 456-2000 & I.S. 3370 (Part I-II)

5.5 Outlet transition: 5.6 For pipe type H.R. the head walls shall be provided at the end of pipe. The

straight warped transition of C.C.M.15 (with nominal reinforcement 10 mm

@ 250 CC Both ways) monolithic with stilling basin floor and height upto

T.O.L. shall be provided. Transition shall be up to stilling basin/Cistern

and then full canal section shall start.

For open type H.R. straight warped transition of R.C.C. walls monolithic

with the floor shall be provided. The walls shall be checked with loading

conditions given in annexure-3. Height of walls shall be provided upto

TBL.

181

5.7 Stability analysis: The stability of entire individual component of

structure shall be checked against sliding, over turning etc. For factor of

safety against aforesaid conditions, please refer Annexure-4. The design of

open H.R. for stability includes among other consideration protection

against overturning, sliding & seepage.

Foundation: The foundation of the H.R. shall be at least one metre below

G.L.

6.0 GATES: (a) Pipe type H.R.

Hand operated vertical lift gates shall be adopted. The size of Gate

shall be the (outer dia of pipe + pipe thickness + 100 mm).

(b) Open type H.R.

Hand/mechanically operated vertical lift gate upto 8.50 cumecs

discharge and radial gate for discharge higher than 8.50 cumecs

shall be adopted as per standard size prescribed by mechanical

unit.

6.1 Operating Platform (Hoist Platform) Operating Platform: Operating platform shall be made of steel such that

required portions of the same can be dismantled whenever required for

maintenance and repair of gates.

Height: The height of platform shall depend upon the height of bank road

and gate operation requirements. It shall be so fixed that the platform has

an easy acess from bank or road. In any case the minimum height shall

never be less than 2.0 x gate height + .50 m.

Width: The width of platform for pipe type H.R. shall be 1.50 mt. while for

open H.R. it shall be as per Dist/FSD and prescribed by mechanical unit.

6.2 Radial gates: Radial gates shall be adopted for all open type H.Rs. having

discharge of more than 8.50 cumecs.

(a) Size of gates: The top of the gate is required to be fixed at height

= F.S.L. + raising of water level at d/s CRs + 0.40(for F.S.D. more

than 2.0 m) and FSD + raising of water level at d/s CR + 0.30 m

(for FSD less than 2.0m). The height of gate shall not exceed 1.5

times the width of the gate.

(b) Trunnion: The trunnion of Radial gate shall be kept at least

0.6m. above F.S.L. of the distributary canal for easy access for

maintenance. The trunnion height 'PH' shall satisfy the ratio

R/PH = 1.2 to 2.8.

Where R is Radius of gate and PH is trunnion height.

(As shown in Sketch at Annexure-3).

Radius: The Radius of gate shall be 1.40 to 1.50 times height of

gate. Size of block outs for sill of radial gates and wall plate shall

182

have to be determined from the size of radial gates. Spacing

between u/s stop log grooves and skin plates of gate shall be kept

at least 1.2m. The d/s stop log grooves shall be kept at least

0.75m away from the edge of road slab.

7.0 WATER STOPS: 225 mm. Long PVC water stops shall be provided in contraction

joints at the following locations.

i) In the inlet transition and its connection with branch Canal

lining.

ii) Junction of inlet transition and gate bay portion.

iii) Junction of D/S head wall or end of R.C.C. barrel and outlet

transition.

iv) Junction of outlet transition and distributary can Section.

8.0 R.C.C. PIPES:

R.C.C. non pressure pipes of NP3 class Conforming to I.S. 458-1988 shall

be used to carry the designed discharge. Pipes of minimum diameter 450

mm shall be provided and shall be laid to downward slope of 1 in 200. The

strength of pipe shall be checked as per I.S. 783-1985 considering Class-A

loading.

183

1. STABLITY ANALYSIS THE STRUCTURE SHALL BE SAFE AGAINST OVERTURING, SLIDING

AND UPLIFT, FACTOR OF SAFETY IS ADOPTED AS UNDER:

CONDITION MINIMUM FACTOR OF SAFETY

OVER TURNING

SLIDING

FLOATATION

1.5

1.5

1.0

REF: PAGE 380 OF FOUNDATION AND DESIGN BY JOSHEPH AND

BOWELS.

DESIGN CRITERIA FOR H.R.

184

Annexure-V Reference The following references are used in the design of Head Regulator.

1. I.S. 6531-1994 "Criteria for design of canal head regulators".

2. I.S. 456-2000 "Code of practice for plain and reinforced concrete".

3. I.SA. 3370 (Part-I) 1965 "Code of practice for concrete structures for the storage of

liquids (General requirements)".

4. I.S. 3370 (Part-II) 1965 "Code of practice for concrete structures for the storage of

liquids (reinforced concrete structures)".

5. I.S. 458-1985 I.S. "Code of practice for laying of concrete pipes".

6. I.S. 458-1988 "Specification for concrete pipes (with & without reinforcement)".

7. I.S. 1893-1984-Criteria for earthquake resistance.

8. Use IS 13920-1993 for monolithic reinforced concrete.

9. Training course on canals & canal structures – C.D.O. Lecture Vol. III-1961.

10. Irrigation Engineering Canals & Barrages Vol. I Serve-Leliavsky-1983.

11. Canal structures-Type design for head regulator for a distributary (Hume pipe

type).

12. United States Department of the interior Bureau of Reclamation.

Design standards No.3 Canals and related structures – 1967.

13. Guide lines for head regulator of main canal.

N.B. The above list is not comprehensive however the designer should

refer all the relevant codes necessary and pertaining to designs.

******

185

GUIDE LINES FOR DESIGN OF ESCAPE ON BRANCH CANAL OF SARDAR SAROVAR (NARMADA) PROJECT.

1.0 GENERAL 1.1 An escape is safety device usually located in the canal to release excess water into

major nalla or river during an emergency.

1.2 Narmada Canals are proposed to be operated by automatic control system based

on Controlled volume concept. Ideally speaking, there would be no need of any

escape. In such a system since the entire volume of water can be contained within

the canal pool itself. However considering that safety of such a large system of

canals would be of paramount importance to the state, a limited numbers of

escapes are proposed to be provided to serve as safety valves.

2.0 LOCATION The location of an escape should be such that it serves a group of about 5 to 10

CRS. Along this stretch of 5 to 10 CRs, the location should be governed on

availability of natural drain, depression or with their bed level below canal bed

level, proximity of a railway crossing or the canal running in high embankment

(banking), H.F.L. of drain etc. for disposing surplus water through the escape

directly or through an escape channel.

Escape may be necessary near important points where branches take off from a

main canal or several distributaries takes off from branches. In case of lift canals

escape may be necessary u/s of the pumping stations.

Escape may be located at a point downstream of the reach where the canal bank

is vulnerable to river flood damage to restrict the damage to the reach upstream of

the escape.

Escape may sometimes be provided economically in combination with canal

aqueduct.

The escape shall usually be laid at right angle to the flow of canal.

3.0 TYPE OF ESCAPE The escape may be classified into the following types:

a) Weir Or Surface Escapes: These are weirs or flush escapes constructed either in

masonry or concrete with or without crest shutters which are capable of disposing

surplus water from the canal.

b) Sluice Escape: Sluices are also used as surplusing escapes. They enable the

canal to be emptied quickly for repairs and maintenance and in some cases act as

scouring sluices also to facilitate removal of silt.

4.0 CHOICE OF THE TYPE OF ESCAPE:- a) Surface Escapes: Such structures may be conveniently used in case where

suitable. Site for sluice type escape is not available for want of adequate outfall

conditions. Surface escape also becomes useful u/s of railway crossing or in the

vicinity of high canal banks or at the tail end of the canal. When there is

186

fluctuation in the withdrawal from the canal, excess quantities of flow may be

conveniently diverted through the surface escape.

b) Sluice Escape: These escapes are necessary wherever the canal is required to

be emptied quickly. Sluice escapes become essential opposite an inlet when the

inlet can bring in considerable quantity of silt. Sluice escape in such cases would

serve the following purpose:-

i) Removal of surplus water.

ii) Exclusion of silt

5.0 LAYOUT: 5.1 The layout of the escape shall consist of

a) Inlet transitions section

b) Gate bay portions

c) Barrels/pipes under road

d) Energy dissipation arrangements

e) Outlet/transitions section

6.0 CAPACITY OF ESCAPE As per I.S. 6936 para 6.2 the capacity of escape is given as under:

6.1 It should seldom be greater than half the maximum discharge of the canal or not

less than the difference between the maximum discharge of the canal at the site of

work and maximum flow at the next lower escape.

(A) Where an escape is required mainly to empty the canal for maintenance, the

capacity should be fixed taking into consideration the time in which canal is to

be emptied.

6.2 Narmada branch canals are to be operated on control volume concept. Thus

unlike conventional operation, the escapes on Narmada Canals will need to be

rarely operated. It is therefore proposed to adopt percentage of discharge for

design of escape as under:

Discharge of parent Discharge to be considered parent canal in cumecs. for escape

(a) Above 150 20% of parent canal

(b) 30 to 150 25% "

( c) Less than 30 30% "

7.0 HYDRAULIC DESIGN:

7.1 General hydraulic design of an escape consists of design of tail channel, size of

with control gates, design of energy dissipation devices, exit gradient and uplift

etc.

7.2 For calculation of waterway & gate size etc. guide line for Design for CR/Fall &

H.R. as applicable may be generally followed.

7.3 The difference between the maximum water level of the canal and minimum water

level in the escapes channel should form the basis for determining the exit

187

gradient, uplift and sliding for designing the escape structure, if the structure is

found on permeable foundation.

7.4 The waterway required should be computed using appropriate discharge co-

efficient depending upon the condition of flow at the proposed structure.

7.5 In case of surface escapes, the sill is provided at FSL. The waterway shall

normally be fixed taking into consideration a depth of flow upto 0.0 to 0.5m over

the crest. This would limit undesirable rise in full supply level of the canal which

would involve additional cost of canal construction.

7.6 In case of sluice escapes, it is desirable to keep the sill as low as possible

depending upon the permissible bed level of the escape channel. This would

enable quick emptying in addition to providing an economical waterway.

7.7 Energy dissipation arrangements should be adequate to cater for all conditions of

flow and operation.

7.8 Adequate protection works should be provided on the D/S of the structure as in

the case of a regulating structure (See IS 6531)

7.9 Minimum 2 Nos. of gates of standard size shall be provided. For radial gates the

requirement of H/B<1.5 (where H is height of gate & B is width of gate) shall be

satisfied. Details of gate shall be adopted as per guide line given for C.R. cum fall

or H.R.

8.0 STRUCTURAL DESIGN 8.1 The structural and hydraulic design would be similar to that of regulators or

sluices.(See IS 6531-1972).

8.2 The structural and hydraulic design shall be done as per design criteria laid out

for H.R. or C.R. cum fall whichever is applicable. Suitable thickness of floor and

cut off depth shall be provided such that the structure is safe from consideration

of exit gradient and uplift.

9.0 DESIGN OF ESCAPE CHANNEL:

9.1 The section of escape channel shall be designed as per Manning's formula by

considering the value of "N" (Co-efficient of Rugosity), depending upon nature of

soil. Velocity for unlined channel shall be limited looking to the nature of soil as

per I.S. 7784(Part-II-see-3).

9.2 When the escape is located near the natural drain bed into which the water is

discharged, no escape channel may be required and the difference in elevation

may be negotiated through a fall. If the escape channel has to be specially

construction its bed level and fall must be fixed with reference to that of the

drainage into which it out falls. Where there is a substantial difference in the

water levels of the canal and escape channel proper energy dissipation

arrangements are necessary.

9.3 The escape channel will usually be an earthen channel. It is not advisable to if

found select such site where frequent channel bed falls are encountered. However

necessary, falls constructed to negotiate the difference in level between the F.S.L.

of the canal and the Water level in the natural drain.

188

9.4 The carrying capacity of the natural channel should be investigated, taking into

considerations, the possibility that it may be carrying the natural drainage water

at the same time when the escape is opened. If inadequate, the natural channel

must be enlarged to carry the required discharge. Necessary regarding & training

of nalla for protective measures wherever required must be provided in existing

drain.

189

ANNEXURE The following reference are used in the design of canal escape.

1. I.S. 6936 Guide for location selection and hydraulic design of canal escape.

2. I.S. 6531 Criteria for design of canal head regulator.

3. I.S. 7784 (Pt-II Sec.3) Code of practice for design of cross drainage works,

specific requirements canal siphons.

4. I.S. 456-2000 Code of practice for plain & reinforced concrete.

5. I.S. 3370-Part-I to IV, code of practice for concrete structure for the storage

of liquids.

6. I.S. 1893-1984-Criteria for earthquake resistance Design of structures.

190

Guide lines for design of Canal Syphon on Branch Canals and Distributaries. 1.0 General:-

1.1 Canal Syphons are used to convey canal discharges under natural drainage,

highways, railways, canals, oil/gas pipe lines etc. In case of natural drainage, they

are usually adopted when the canal flow is small compared to that of drainage or

when it is not desirable to change the regime of the natural drainage

1.2 The design of canal syphon shall be carried out keeping in view the relevant

recommendations and stipulations made in I.S. Codes and U.S.B.R manuals as

listed in Annex.I.

1.3 Based on the recommendations made in various I.S. Codes and U.S.B.R. manuals

as listed as Annex-I, guide lines for the design of canal syphon on Narmada

Branch Canal and distribution system have been evolved. The various aspects

accounted for in the guide lines are described below:-

2.0 Design Data :

The hydraulic data, the geological data and other general data required for a

particular crossing site for taking-up the design are to be as per DATA SHEET

FOR CSY prescribed by this office vide letter no.NPPDC/B/Str.data/1836 dated

12/10/2001.

2.2 Sub soil information for foundation

2.2.1 For safe and secure foundation of structure, foundation soil information with all

engineering properties at the location of structure are very essential for which

suitable trial bores at the location of structure, upto the depth of twice the width of

foundation from foundation level shall be taken. The number and spacing of bore

holes or trial pits will depend upon the extent of the site and the length of structures

coming on it. The soil information as disturbed and undisturbed sample for

ascertaining necessary soil properties shall be provided according to "Guide Lines

on Investigation for Structures on Branch Canals of Narmada Canal System"

issued by this office in September 1998.

2.2.2 As the ground water level play important role in deciding safe bearing capacity and

swelling pressure of soil, particularly for finer particles of cohesive soil and so

fluctuation of ground water table should be obtained during execution of trial bore.

2.2.3 Liquefaction:-

191

i) Soils having engineering classification such as SM/ML/SP /SM-SC etc. are

more susceptible to liquefaction. In general, silty soil, sandy soil or

combination of them having poor densities and high saturation are prone to

liquefaction

ii) To ascertain the possibility of liquefaction in case of the soils having

classification narrated under para 2.2.3 (I) above following criteria shall be

examined precisely.

a) Standard penetration test (SPT) shall be performed at foundation level as

per I.S. 2131. If the SPT value (N) is less than 20 soil is likely to liquefy

and detailed investigations shall be required to be performed. If this value

exceeds 20, risk of liquefaction is reduced.

b) Particle size analysis : - In general uniformly graded sand particles are

more susceptible to liquefaction than well graded particles. If soil exhibits

properties within the range as under than the soil is more likely to liquefy.

Sample should satisfied all the criteria stated below.

0.2 mm. < D60 < 1.0 mm.

Fineness content (Silt & Clay) < 15%

2.0 < Cu < 5.0

Void ratio (e) > 0.80

Plasticity Index (Ip) < 10.0

c) Relative density (Rd) :- In general cohesionless soils having relative

densities less than 75% liquefaction is possible.

2.3 In case rocky strata met with at foundation level the logging by the

geologist shall be done. The report and recommendation of Geologist

stating characteristics of rock is essential and shall be furnished

3.0 Layout:-

3.1 The Canal Syphon usually consists of horse shoe shaped, circular, rectangular or

square, single or multiple barrels or pipes depending upon the discharge in canal.

For discharge Type

Upto 3.0 cumecs - Usually pipe type or well type syphon

> 3.0 cumecs - Horse shoe shaped, circular,

Rectangular/square barrel.

Section of suitable type may be made judiciously based on guide lines and other

considerations such as cost, convenience of construction etc. However rectangular

or square barrels are generally preferred.

3.2 For a pipe type syphon standard pressure pipes of appropriate class P1, P2 and

192

P3 shall be used when the head of water is more than 7.0 m. Non pressure pipes

of appropriate class NP2, NP3 and NP4 shall be used when the head of water is

equal to or less than 7.0 m. However such pipes shall be invariably designed for

their hydraulic and structural integrity as per para 6.1.2

3.3 A Syphon barrel is kept parallel to the axis of the canal. The top level of barrel roof

is so fixed that about 300 to 750 mm of over-burden is maintained over the roof of

barrel upto the drainage bed level to safeguard it against abrasive damage. In

case, a road crossing is provided, a minimum over burden of of 900 mm shall be

allowed for. Sloped entry and exit approaches are provided on the upstream and

downstream sides to join the barrel to the bed of the canal.

3.3.1 The bed slope in the upstream and downstream inclined portions of barrels shall

not be steeper than 1 in 3 and 1 in 4 respectively. The length of the syphon

pipe/barrel may be curtailed by providing retaining walls to support the outer bank

in case of stream/drain and outer bank slopes in case of canals. Alternatively

extension of the barrels to cover the entire width of the bank (including outer

slopes) may be examined based on relative economics. The velocity allowed in the

barrel shall be in accordance with the head loss permissible in the structure.

Generally, the velocity in the barrel is limited to about 3 m/sec. Provided it does not

cause excessive head loss. However velocity induced in barrel shall always be

greater than that of canal velocity.

A water seal of 1.5 times the change in velocity head with a minimum of 200 mm is allowed

over the top of barrels at the entry

3.3.3 Cut-off walls at the entrance and exit ends of the barrel shall be provided in all

syphons and the same are to be continued under the wing walls. Cut-off walls shall

also be provided at the entry and exit of the transition.

3.3.4 The floor of the barrel should be extended to a depth below the anticipated scour.

In case the scour is very deep, the floor may be kept at a reasonable (higher) level

and protected against scour by provision of concrete cut-off walls extending upto

scour depth and suitable stone launching apron, pitching etc. as shown in the

enclosed sketch No.1 and 2.

For protecting the structure from any anticipated piping due to seepage in

the case where the scour depth is above the foundation level or the bottom level of

the floor, a longitudinal concrete cut-off shall be provided below the barrel as

detailed below in table – 1.

the construction of canal siphon shall have to be stopped at the end of

working season prior to monsoon. The cut-off across barrel at both the end of

horizontal barrel shall be provided as shown in Col.5 of table-1 given below to

protect against scouring of foundation due to flood water, only if the construction of

barrel remain incomplete at the end of working season prior to monsoon.

193

TABLE-1.

Sr. No

1.1.1.1.1.1.1.1.1 Particular Soil strata Depth of cut-

off in m. Section of cut-off

Along

barrel

Across

barrel

1 2 3 4 5 6

1 When the discharge of

drain / river is less than 100 cumecs

a) soil or

weathered rock

0.45 0.45 0.30x0.45

m.

b) Hard

rock

0.30 0.30 0.30x0.30

m.

2 When the discharge of

drain or river is between

101 to 1000 cumecs or CA is less than 50

sq.km.

a) soil or

weathered

rock

0.60 0.60 0.30x0.60

m.

b) Hard

rock

0.30 0.30 0.30x0.30

m.

3

When the discharge of drain/river is more than

1000 cumecs or C.A. is

more than 50 sq.km.

a) soil or weathered

rock

0.75 0.75 0.30x0.75 m.

b) Hard rock

0.30 0.30 0.30x0.30 m.

3.3.5 The invert level at the exit shall be kept lower than the invert level at the entrance

to the barrels by the amount of loss of head through the barrels.

3.4 Returns & Transitions:- The abrupt type RCC M-25 cantilever return wall shall

be provided for height upto 6.0 m at the beginning and at the end of U/S & D/S

stoplog respectively. The return wall (U/S & D/S) shall be provided adjoining to

stoplog and perpendicular to flow of canal. The length of return wall shall be

decided on the basis of width of canal at F.S.L. and shall extend for a minimum

length of 1 m. in banks.

The transition, i.e. starting of canal section upto required width up to

194

stoplog portion should be provided with a minimum splay of 3:1 & 4:1 on U/S & D/S

respectively. The floor and side slopes of transition shall be provided with nominal

temperature reinforcement 12 mm dia. @ 200 mm c/c bothways in R.C.C. M-15 as

double the thickness of canal lining proposed for normal section.

In general, cantilever type return wall shall be provided for a depth up

to 6m. while for depth more than 6m. counterfort type return wall shall be provided.

For pipe type canal syphon , where the velocity of water does not

exceed 1.0 m/sec. The canal cross section shall be carried right upto the structure

to abut upon the canal structure and no straight warped transition be provided as

shown in Sketch No.4.

Leveling course for the transition walls shall be in C.C. M-15 . Pipe

railing of 0.8 m. height as shown in Sketch No.5 shall be provided on the top of

wing wall.

4.0 Hydraulic aspects :-

4.1 Hydrological studies:-

4.1.a Design flood for drainage channel to be adopted for cross drainage works should

depend upon the size of canal, size of drainage channel and location of cross

drainage. A very long canal, crossing a drainage channel in the initial reach,

damage to which is likely to affect the canal supplies over a large area and for a

long period, should be given proper weightage.

4.1.b Methodology of Design Flood :- Methods to be adopted for determination of design

flood corresponding to the catchment area of the drainage/ nalla are as under.

Sr.No. Catchment

area in sq.km.

Method Remarks

1 Less than 25 Modified rational formula

2 25 to 518 Flood estimation reports of various

subzones published by the Director

(Hydrology for small catchment ) C.W.C. ,

New Delhi

For subzone 3(a)

or 3(b) as the

case may be.

3 Above 518 Each case shall be taken up specifically and

decided after detailed examination as

mentioned in I.S. 7784 (Part-I) 1993

Notes:

195

The cross drainage structure should be checked for a checked flood discharge of value

20% higher than the design flood given in the table in para 4.1c.

In case of very steep slopes, in case of catchment area less than 25.00 sq.km. results

arrived at by modified rational formula need to be care fully gone in to. If the modified rational

formula gives odd results it needs to be checked by alternative computation such as sub zone

report method (CWC). Same strategy should apply to C.A. exceeding 25.00 sq.kms.

For determining the observed flood, the field officer should go to the site more than two

times in a year immediately after the flood occur and observed the levels care fully. The value of “N”

( Coefficient of rugosity) shall be adopted care fully and the correct observed discharge may be

determine. This discharge should be further subjected to check by measuring through existing

structure U/S and D/S of the point of crossing.

4.1.c Frequency of Design Flood :- As per I.S. 7784 (Part-I) 1993, the design flood for

drainage channel as given para -7, cross drainage structures are divided in to four

categories depending upon the canal discharge and drainage discharge. Design

flood to be adopted for these four categories of cross drainage structure is given in

table-1 of the code of practice. Based on this table the B.O.C. as recommended the

following table for adoption.

196

TABLE FOR DESIGN FLOOD VALUES

Category of

structure

Canal

Discharge in

cumecs

(*) Estimated drainage

discharge in cumecs

Frequency of design

flood

A 0 to 0.50 All discharges 1 in 25 years

B

C

0.50 to 15.0

15.0 to 30.0 0 to 150 1 in 50 years

C 15.0 to 30.0 Above 150 1 in 100 years

D Above 30.0 0 to 150

Above 150

1 in 100 years

As per note.2

Notes: -

The design flood to be adopted as mentioned in this table should in no case, be less than

the observed flood.

2) In case of vary large cross drainage structures where estimated drainage discharge is above 150 cumecs, the hydrology shall, be examined in detail and appropriated design flood adopted, which should in no case be less than 1 in 100 years flood. (*) This refers to the discharge estimated on the basis of river/nalla parameters corresponding to maximum observed flood level.

4.1.d Basis for Design Flood Determination :- As per technical circular no. NPPDC/ A /

HYDROLOGY / 82 dated : 10/01/1995.

4.1.2 Afflux:-

When the area of obstruction is not very large compared to the original unrestricted

area, the following formula (Mole'sworth) shall be used

H = [ {( V2 / 17.85 ) + 0.0152} { ( A2 / a2) - 1}]

Where H = Afflux in meter.

V = Velocity in unobstructed stream in m/sec. Under the design

flood.

A = Unobstructed sectional area of stream/drain in m. under the

design flood.

a = section area of drainage channel provided in the

construction in m2.

4.1.3 Waterway for stream/drain discharge:-

The linear waterway of the stream/drain over the structure shall be restricted to

60% to 80% of Lacey's waterway as indicated below

Lacey's water way Pw = C Q

197

C = Co-efficient varying from 4.5 to 6.3 the usual value being 4.8

for regime channels.

Q = Design flood in cumecs.

In case of drain having rocky bed the linear water way may be selected such that

afflux is within reasonable limits to avoid high banks.

The following factors shall also be taken into account in deciding the waterway .

Actual width of drain

Permissible afflux

Construction and maintenance cost

4.1.4 Free Board:-

The free board above affluxed H.F.L under design flood shall be as per table below

for fixing the levels of canal bank, the guide bank and the bridge deck.

Discharge in cumecs of stream/drain Minimum vertical

clearance in mm.

0 to 30 600

30 to 300 900

300 to 3000 1200

Above 3000 1500

In no case the free board shall be less than the free board provided in the canal.

4.2 Watery way for barrels:-

4.2.1 Canal Fluming :- Fluming in the barrels shall not be lower than 75% . For this purpose, the fluming ratio is defined as the ratio of the clear water way in the barrels to the canal width at mid depth and shall be decided in accordance with the permissible head loss for the structure and other considerations such as length of transitions, floor thickness and protection and over all economy. 4.2.2 Loss of Head:- When water flows through any structure there are head

losses due to friction and change in the normal section of the flow. The total loss of

head occurring for a flow through a syphon is represented as the sum of the losses

occurring at different points of that syphon.

Thus if the total loss of head is denoted by H then

H = h1 + h2 + h3+ h4 +h5 + h6 +h7 + h8 .

Where h1 = losses due to skin friction in inlet transition .

h2 = losses at inlet transition .

h3 = losses at entry & exit .

h4 = head loss due to skin friction in barrels .

h5 = head loss due to bends .

h6 = head loss in outlet transition .

h7 = head loss due to skin friction in outlet transition .

198

h8 = head loss due to trashrack .

4.2.3 Losses due to skin friction in inlet transition (h1)

Sf1 = 1 / gradient

Sf2 = ( V22 X N2) / R2

(4/3)

h1 = {( Sf1 + Sf2 ) / 2 } X L1 Where L1 = Length of U/S inlet transition V2 = Velocity in inlet transition N = 0.018 for concrete

R2 = Hydraulic mean depth of outlet transition.

4.2.4 Head Loss at Inlet Transition (h2) h2 = 0.30 X ( Vc2 - V2

2) / 2 x g Where Vc = Canal velocity in m/sec

V2 = Velocity in inlet transition g = Acceleration due to gravity in m/sec2

4.2.5 Losses at entry & exit = (h3) h3 = ( 1 + f1) x V2 / 2g

Where h3 = loss of head at entrance and at exit in m.

F1 = a co-efficient which provide for the loss

of head on entry. It may be taken for all practical

design purposes as 0.08 for a bell mouth entrance and

0.505 for cylindrical entrance with sharp edges

(unsharp mouth of the same sectional area of the

barrel)

V = Velocity in syphon in m/sec.

g = Acceleration due to gravity in m/sec2

4.2.6 Loss of head due to skin friction in the barrel of syphon (h4)

h4 = f L / D x ( V2 / 2g )

Where h4 = loss of head due to friction in m.

f = friction factor to be derived as specified in

I.S 2951 Part-I-1965

L = Length of barrel in m.

V = Velocity in barrel in m/sec.

D = 4 Rn

Rn = Hydraulic mean depth

( Area of barrel / perimeter of barrel)

199

4.2.7 Head Loss due to bends (h5) h5 = K x ( V2 / 2g)

Where h5 = losses at bends

K = Resistance co-efficient to be derived from

graph as specified in I.S. 2951 Part II 1965

K = K1 + K2

Where K1 = Constant for U/S Bends

K2 = Constant for D/S Bends

V = Velocity in barrel in m/sec.

g = acceleration due to gravity in m/sec2

4.2.8 Head loss in outlet transition (h6)

h6 = 0.20 (Vc 2 - V42 ) / 2 X g

Where Vc = Canal velocity in m/sec

V4 = Velocity in inlet transition g = Acceleration due to gravity in m/sec2

4.2.9 Head loss due to skin friction in outlet transition (h7) H7 = ( Sf4 + Sf5 ) X L2 /2

Where Sf4 = Sf2 Sf5 = Sf1

L2 = Length of Outlet Transition

4.2.10 Head loss due to trashrack (h8)

H8 = 2.30 ( t / b ) X Sin(Theta) X V22 / 2 X g

Where t = Thickness of bar = 8 mm

b = spacing of Vertical bar = 200 mm Theta = Angle of inclination of Trash Rack = 90 Deg.

V2 = Velocity approaching Rack

The total head loss as computed above shall be increased by 10% (As specified in

I.S. 7784-Part-II-Section-3 1980)

4.3 Scour Depth:-

4.3.1 Mean depth of scour:- The mean depth of scour in meters below the check / high flood level may be calculated from the equation :

d sm = 1.34 x [ Di2 / Ksf ] 1/3

Where Di = The discharge in cumecs per meter width . The value of Di

should be the maximum of the following

I) The design flood divided by the effective linear water way between abutments or guide bunds, as

200

the case may be. ii) The value obtained should take into account

concentration of flow through a portion of the water way assessed from the study of the cross section of the drainage channel. Such modifications of the value may not be deemed applicable to minor cross drainage structures with over all water way less than 60 m.

iii) Actual observation, if any.

Ksf = The silt factor for representative sample of the bed

material obtained upto the level of the deepest

anticipated scour and given by the expression 1.76 x [

dm ]1/2 ' dm' being the weighted mean diameter in

millimeters.

NOTES :-

i) dsm may be taken as the grain size at 50% passing from

grain size distribution curve .

ii) The above method of estimated dsm is based on Lacey's

theory for regime condition in alluvial beds.

Maximum depth of scour for design of foundation:

The maximum depth of scour below the highest flood level (H.F.L) at obstructions

and configurations of the channel should be estimated from the value of 'dsm 'on the

following basis :

For the design of floor protection works , for raft foundations or shallow foundation ,

the following scour values should be adopted.

i) In a straight reach 1.27 dsm

ii) At a moderate bend 1.50 dsm

iii) At a severe bend 1.75 dsm

iv) At a right angled bend 2.00 dsm

NOTE:- The values of scour depth obtained as above may be suitably modified

where actual observed data is available . Where concrete or masonary floor is

provided under the works , scour condition is not applicable and the foundations

are usually taken to about 1.5 m below the floor levels with suitable cut-off for the

concrete or masonary floors . However where such a floor is not provided ,

foundations are taken to provide a margin below the anticipated scour level (

usually called grip length ) of about 0.33 times the maximum depth of scour . (I.S :

7784[PART-I] - 1993 )

4.4 Uplift:-

4.4.1 The barrels shall be checked for following conditions.

201

Self flotation condition i.e. when the flood occurs when there is part

completion or immediately after completion of structure. b) Drainage full and canal dry

c) Canal full and drainage dry

i) All barrels full

ii) One barrel empty and other barrels full in case of multi barrels.

4.4.2 In case a bridge is proposed monolithic with the syphon, the traffic load shall be

ignored, while checking the uplift.

4.4.3 A minimum factor of safety of 1.2 shall be allowed under the worst of the above

conditions, without considering the seismic force.

If the barrels are founded on sound rock strata the uplift may be resisted by

providing anchor bars. If they rest on soils the uplift shall be resisted by providing

buoyancy concrete on the top of barrels.

The uplift pressure for canal full / canal suddenly closed and river dry condition

would be vary from maximum at abutment and to minimum at the center of the river

section or at the point of tail water exit .Uplift forces should be estimated by

drawing flow nets / Lane's creep theory .

The Minimum factor of safety against buoyancy recommended in IS codes for

canal siphon is 1.2 where as that for drainage siphon is 1.0. Since syphon

aqueduct and canal syphon are structure of equal importance, the minimum factor

of safety for canal syphon can also be 1.0 instead of 1.20.

As per 13th B.O.C meeting, full head of water shall be considered for exit gradient

and the uplift pressure shall be worked out by Khosla's theory and arrived residual

head shall be multiply by 0.75 to achieve FOS against buoyancy.

5.0 Foundations :-

5.1. Foundation of horizontal portions of barrels shall be at the foundation level as

calculated in para 4.3.2. In case the scour depth is very deep suitable concrete cut-

off walls shall be provided upto depth with pitching and launching apron as shown

in sketch No.1 (Ref. para 3.3.4). Where hard rock is encountered at higher levels,

the foundations shall be so fixed that about 300 to 750 mm. of over burden is

maintained, over the roof of the barrel up to the bed level of the drainage for

providing a cushion against damage to the syphon.

5.1.1 Cut-Off:

a) Longitudinal direction: Cut-off walls in longitudinal direction shall be

provided at sides of barrel across the drain upto scour level or rock level

whichever is higher . In accordance with para. No. 3.3.4 (Sketch no. 1)

b) In transverse direction i.e. at entry and exit of transitions ( ( pucca floor

)and at entry and exit of pipe/barrel. Since the canal is lined, minimum

202

depth of cut-off walls required are as under:

U/S cut-off depth = d1/3 + 0.5 m.

Where d1 = u/s F.S.D of canal

d/s cut-off depth = d2/2 + 0.5

2. WHERE D2= D/S F.S.D OF CANAL (As per I.S 6531-1972 Cl.3.7.2.2)

depth of u/s or d/s cut-off = 0.69 u/s or d/s water depth

in m.

The depth of cut-off to be provided should be higher of the two conditions.

5.1.2 In case where wing walls/transitions wall fall in flood zone the foundations of these

walls shall be taken below safe scour level otherwise the same shall be taken at

least 1.5 m. below D.B.L / C.B.L. or ground lever whichever is lower. For pipe type

syphon, pipe shall rest on bedding of 250 mm. thick cement concrete of M-15,

which shall be increased to 550 mm. at joints. The end offsets and clear spacing

between adjacent pipes shall be a minimum of 250 mm. standard collar joints as

shown in Sketch-8 shall be used and these shall be properly grouted to make them

water tight. At bends, RCC joints shall be provided to receive ends of pipe (See

Sketch-9).

Bearing pressure on foundations shall be limited to permissible bearing pressure

depending upon nature of the foundation strata. The foundation shall be as far as

possible bear on homogeneous, undisturbed and uniform sub grade of fairly dense

type. Where the foundation has to be provided on sub grade of different types,

suitable joints shall be provided to avoid cracks due to differential behavior of the

foundation soil.

6.0 Structural design :-

6.1 Barrels:-

6.1. Loadings:- The various loadings assumed in the design of barrels shall consist of

the following.

a) Self weight of the structure

b) Super imposed loads

c) Surcharge loads

d) Full internal water pressure

e) Soil reaction and uplift pressure

f) Earth load on sides

g) Seismic force

The combination of loads which will result in maximum stress should be carefully

considered.

6.1.2 Structural Analysis:- The syphon shall be designed for the following conditions:

a) Portion under drainage bed: (Horizontal Barrel)

1) Canal full + nalla dry + Vehicular loading.

203

2) Canal full + nalla dry + No Vehicular loading.

3) Canal dry + nalla dry + Vehicular loading.

4) Canal dry + nalla full + No Vehicular loading.

5) Nalla dry + water passing through one barrel +

Vehicular loading. (For two barrels )

6) Nalla dry + water passing through end barrel +

Vehicular loading. (For three barrels )

7) Nalla dry + water passing through central barrel +

Vehicular loading. (For three barrels )

b) Portion under drainage bank (Inclined barrel)

1) Canal Full + nalla dry + Vehicular loading.

2) Canal dry + nalla dry + Vehicular loading.

3) Canal full + nalla dry + No Vehicular loading.

4) Nalla dry + water passing through one barrel +

Vehicular loading. (For two barrels )

5) Nalla dry + water passing through end barrel +

Vehicular loading. (For three barrels )

6) Nalla dry + water passing through central barrel

+ Vehicular loading. (For three barrels )

7) Canal dry + nalla full + No vehicular loading

( varying load for skew syphon)

8) Canal full + nalla dry + vehicular loading

( varying load for skew syphon)

9) Nalla dry + water passing through one barrel +

Vehicular loading. (For two barrels, varying load

for skew syphon)

10) Nalla dry + water passing through end barrel +

Vehicular loading. (For three barrels, varying

load for skew syphon)

11) Nalla dry + water passing through central barrel

+ Vehicular loading. (For three barrels, varying

load for skew syphon)

In case of multi channel barrel minimum thickness of intermediate wall shall be 200 mm.

Reinforcement in the intermediate walls shall be anchored in to top and bottom slabs. In

case of R.C.C barrel haunches with haunch reinforcement shall also be provided. In pipe

type canal syphon the standard pressure pipes or non pressure pipes of the requisite class

shall be used. These shall be invariably checked for their three edge bearing strength in

accordance with I.S. 783 -1985 and I.S. 458 - 1971.

However table 1 and 2 by V.V.S.Rao “Structural design of concrete pipes in accordance

with IS 783 - 1959” Volume-50, Institution of Engineers, Civil Engineering January-1970

204

give the safe height embankment for NP2 and NP3 class pipes with various types of

bedding as well as range of height of embankment under which the pipe can be safely laid

to with stand load transmitted by IRC Class AA wheel load of 6.25 ton for trench conditions

and positive projection condition as per IS 783 - 1959.

The mix of concrete for various R.C.C. / P.C.C components shall be adopted as under:-

Sr.N

o.

Grade of

Concrete

Where to be used

1 M-25 (RCC) RCC barrels, breast walls, launching ring, cut-off walls.

2 M-15 (PCC) Coping on masonry wing walls (if adopted), Pucca floor.

3 M-10 (PCC) Leveling course for foundation for RCC barrels, Buoyancy

concrete, foundation of masonry wing wall, if adopted.

The design of RCC components shall be done in accordance with I.S.456-2000 and I.S.

3370 (Part-I) 1965 to I.S.3370 (part-IV) 1967. Certain important clauses relevant to the design of

canal syphon structures extracted from I.S.456-2000 are reproduced here under for ready

reference.

205

Safe Depth of Earth cover on trench pipes in meters.

Inside

dia in

mm.

Trench

width in

mm.

Bedding conditions

Ordinary First class Concrete cradle Concrete cradle

NP2 NP3 NP2 NP3 NP2 NP3 NP2 NP3

Earth load at 1800 kg/m.

150 900 2.60 - 3.40 - 4.70 - 5.00 -

250 900 2.00 - 2.55 - 3.55 - 4.30 -

300 960 1.80 - 2.20 - 3.20 - 3.95 -

350 1100 1.30 3.40 1.70 5.00 2.50 10.00* 3.00 10.00*

400 1150 1.30 3.70 1.60 5.60 2.50 10.00* 3.00 10.00* 450 1200 1.30 4.00 1.70 6.00 2.50 10.00* 3.00 10.00* 500 1250 1.45 4.25 1.70 6.25 2.70 10.00* 3.50 10.00* 600 1360 1.40 4.00 1.70 6.20 2.80 10.00* 3.65 10.00* 700 2060 1.40 3.65 1.70 4.45 2.50 5.85 3.20 7.50

800 2180 1.30 3.40 1.60 4.30 2.40 6.15 3.00 8.00

900 2300 1.30 3.30 1.60 4.20 2.35 6.50 2.80 8.80

1000 2400 1.20 3.30 1.70 4.25 2.35 6.20 2.75 9.20

1200 2630 1.25 4.10 1.50 4.45 215 7.80 2.60 10.00

1400 2750 1.25 - 1.50 - 2.10 - 2.50 -

1600 2960 1.10 - 1.40 - 2.00 - 2.40 -

1800 3180 0.90 - 1.20 - 1.80 - 2.15 -

IRC Class AA Wheel Load of 6.25 ton

NP2 NP2 NP2 NP2 100

0.80 2.60 0.70 3.40 0.70 4.70 0.70 5.00

250 - - 1.20 2.55 1.00 3.55 1.00 4.30

300 - - 2.00 2.25 1.50 3.20 1.00 3.85

NP3 NP3 NP3 NP3 350

0.60 3.20 0.60 4.25 0.60 10.00* 0.60 10.00*

400 0.60 3.60 0.60 5.50 0.60 10.00* 0.50 10.00*

450 0.60 3.90 0.60 5.70 0.50 10.00* 0.50 10.00*

500 0.60 4.20 0.50 6.20 0.50 10.00* 0.50 10.00*

600 0.50 4.00 0.50 6.10 0.50 10.00* 0.50 10.00*

700 0.40 3.65 0.40 4.45 0.40 5.85 0.40 7.50

800 0.30 3.40 0.30 4.30 0.30 6.15 0.30 8.00

900 0.00 3.30 0.00 4.20 0.00 6.15 0.00 8.00

1000 0.00 3.30 0.00 4.30 0.00 6.20 0.00 8.00

1200 0.00 3.45 0.00 4.30 0.00 7.75 0.00 10.00

Actual values exceeds 10 meters. Sf = Strength factor.

NOTE :- Table provided gives the safe heights of embankment for NP2 & NP3 class pipes

which various type of bedding as well as the range of height of embankment

under which the pipe cab be safely laid to withstand the load transmitted by

IRC Class AA Wheel Load of 6.25 tons.

206

2.1.1.1 Safe depth of earth cover over culvert pipes in meters Inside

dia. of

pipe

Earth Load IRC Class AA Wheel Load 6.25

tons.

Ordinary

Bedding

Sf = 1.9

First class

Bedding

Sf = 2.3

Concrete

Bedding

Sf = 3.7

Ordinary

Bedding

Sf = 1.9

First class

Bedding

Sf = 2.3

Concrete

Bedding

Sf = 3.7

NP2 NP3 NP2 NP3 NP2 NP3 NP2 NP2 NP2

150 3.40 - 4.00 - 6.00 - 0.70 3.00 0.70 4.00 0.70 6.00

250 2.55 - 3.00 - 4.80 - 1.20 2.55 1.00 3.00 1.00 4.80

300 2.25 - 2.65 - 4.20 - 2.00 2.25 1.50 2.05 1.00 4.20

NP3 NP3 NP3

350 1.70 3.85 2.00 4.75 3.25 7.00 0.60 3.85 0.60 4.75 0.60 7.00

400 1.70 4.00 2.00 4.75 3.25 7.55 0.60 4.00 0.60 4.75 0.50 7.55

450 1.65 4.25 2.00 4.90 3.30 7.70 0.60 4.25 0.50 4.90 0.50 7.70

500 1.60 4.40 2.00 4.90 3.65 7.20 0.60 4.40 0.50 4.90 0.50 7.20

600 1.70 4.50 2.00 5.15 3.60 7.50 0.50 4.50 0.50 5.15 0.50 7.55

700 1.70 4.45 2.00 5.00 3.55 7.65 0.40 4.45 0.40 5.00 0.40 7.65

800 1.60 4.25 1.90 5.00 3.20 7.30 0.30 4.25 0.30 5.00 0.30 7.80

900 1.60 4.20 1.95 5.00 3.00 7.35 0.00 4.20 0.00 5.00 0.00 7.85

1000 1.70 4.25 2.00 5.15 2.95 8.25 0.00 4.25 0.00 5.15 0.00 8.25

1200 1.50 4.30 1.80 5.25 2.80 8.60 0.00 4.30 0.00 5.25 0.00 8.50

1400 1.50 - 1.50 - 2.70 -

Sf =Strength Factor 1600 1.40 - 1.65 - 2.40 -

1800 1.15 - 1.45 - 2.25 -

Weight of earth filling is 1.8 t/m3 , Impact factor for wheel load equal to 1.50 and factor of

safety equal to 1.50

6.1.5 Concrete (Table 21 of I.S 456-2000)

Sr.

No.

Permissible

stress

M-25 M-20 M-15

1 Bending 85 kg/cm2 70 kg/cm2 50 kg/cm2

2 Direct 60 kg/cm2 50 kg/cm22 40 kg/cm2

3 Bond 9 kg/cm2 for plain

bars in tension

8 kg/cm2 for plain

bars in tension

6 kg/cm2 for plain

bars in tension

207

Note : In case of deformed bars confirming to I.S. 1786 the bond stress given above

may be increased by 60% (Cl.no. B.2.1.2 I.S. 456-2000) for bars in tension and the

same shall be increased by 25% for bars in compression.

Shear: As per clause B-5 of I.S. 456-2000 as under:

Design shear strength of concrete without shear reinforcement. The permissible

shear stress (Tc) in concrete in beams without shear reinforcement.

100As/bd M-20 In kg/cm2 M-25 In kg/cm2

<= 0.15 1.80 1.90

0.25 2.20 2.30

0.50 3.00 3.10

0.75 3.50 3.60

1.00 3.90 4.00

1.25 4.20 4.40

1.50 4.50 4.60

1.75 4.70 4.90

2.00 4.90 5.10

2.25 5.10 5.30

2.50 5.10 5.50

2.75 5.10 5.60

3.00 and

above 5.10 5.70

Where ‘As’ is that area of longitudinal tension reinforcement which continues at least one

effective depth beyond the section being considered except at supports where the full area

of tension reinforcement may be used provided that detailing conforms to clause 26.2.2. i.e.

Anchoring of reinforcing bars and clause 26.2.3 i.e. curtailment of Tension reinforcement in

Flexural members, b is the breadth of beam and d is effective depth of beam.

For solid slabs, the permissible shear stress in concrete shall be K x Tc where k has the

value given below: (Clause no. B-5.2.1.1 I.S. 456-2000)

Tc = permissible shear stress in concrete in beams.

Overall depth of slab

in mm.

K

300 or more 1.00

275 1.05

250 1.10

225 1.15

200 1.20

175 1.25

208

150 or less 1.30

With shear Reinforcement:- When shear reinforcement is provided the nominal shear

stress Tc in beams shall not exceed Tcmax given below For slabs Tv shall not exceed half

the value of Tcmax given below:- ( I.S : 456 - 2000 Table -24 , page -85 )

Grade of Concrete M-15 M-20 M-25

Tcmax 16 kg/cm2 18 kg/cm2 19 kg/cm2

6.2 Reinforcement:- The main bars, distribution and temperature bars shall be high

yield strength deformed bars (H.Y.S.D) conforming to I.S.1139-1966 and I.S.1786-

1979. The stresses for above bars shall be adopted as per Table-2 of I.S. 3370

Part-II 1965.The detailing of reinforcement shall be done as per I.S : 13920 under

seismic condition .

Type of Stress 2.1.2 Permissible stresses

a) Direct Tension 1500 kg/cm2

b) Bending

i) On liquid retaining face of member

ii) On face away from liquid for members

less than 225 mm.

iii) On face away from liquid for members 225

mm. Or more in thickness

1500 kg/cm2

1500 kg/cm2

1900 kg/cm2

c) Shear

i) For members less than 225 mm. thickness

ii) For members 225 mm. Or more in

thickness

1500 kg/cm2

1750 kg/cm2

d) Compressive stresses. Compressive stress

in column subjected to direct load.

1750 kg/cm2

Note: Stress limitations for liquid retaining faces shall also apply to the

following.

a) Other faces within 225 mm. Of the liquid retaining face.

209

b) Outside or external faces of structures, away from the liquid but placed in water logged

soils upto the level of the highest sub soil water level.

6.3 Minimum Reinforcement:- (As per IS 3370 (Part-II)- 1965, For mild steel)

6.3.1 The minimum reinforcement in each of two directions at right shall have following

area in that direction.

a) For sections upto 100 mm. Thick. 0.3 percent of the Gross sectional area of

concrete.

b) For section between 100 mm. To

450 mm. Thickness.

Linearly varying from 0.3% for 100 mm.

Thick section to 0.2% for 450 mm. Thick

section.

c) * For sections greater than 450

mm. thickness 0.2% of cross sectional area.

* In concrete sections of thickness 225 mm. or greater two layers of reinforcing steel shall

be placed one near each face of the section to make up the minimum reinforcement

specified above.

Where the thickness of the section exceeds 450 mm. Thickness of 450 mm. shall be used

in determining the temperature or minimum reinforcement.

6.3.2 The minimum reinforcement specified above may be decreased by 20 percent in case

of high yield strength deformed bars conforming to I.S. 1786-1966 or I.S.1139-1966.

6.3.3 Where joints are provided in structures, the temperature or minimum reinforcement

shall be provided as under as per U.S. B.R. practice

A. The minimum reinforcement for canal structures shall be 12 mm. Dia @ 30 cm. In all

exposed faces and where reinforcement is placed in a single layer and 12 mm dia @ 30 cm. in

unexposed faces with two layer reinforcement.

B. Single layer reinforcement.

1) Reinforced concrete lining 10 cm. And less in thickness

with discontinuous wire fabric reinforcement and weakened

planes at 360 cm to 450 cm center.

0.10 percent.

2) Slabs and linings not exposed to freezing temperature or

direct sun with joints not exceeding 900 cm.

0.25 percent

3) Slabs and linings exposed to freezing temperature or direct

sun with joints not exceeding 900 cm.

0.30 percent

210

4) Slabs and linings exceeding 900 cm between joints.

Category (2) above

Category (3) above

0.35 percent

0.40 percent

5) Walls and other structural members. Total percentage of

horizontal reinforcement to be equal to the sum of those

required for both faces as determined below.

As per double layer

reinforcement

C. Double Layer reinforcement :-

1) Face adjacent to earth with joints not exceeding 900 cm. 0.10 percent

2) Face not adjacent to earth nor exposed to freezing

temperatures or direct sun and with joints not exceeding

900 cm.

0.15 percent

3) Face not adjacent to earth but exposed to freezing

temperatures or direct sun and with joints not exceeding

900 cm.

0.20 percent

4) If member exceeds 900 cm in any direction parallel to

reinforcement add to the reinforcement requirement in that

direction because of the increased length.

0.05 percent.

5) If a slab is fixed along any line, double the dimension from

line of fixity to free end to determine whether reinforcement

is within the less than 900 cm or more than 900 cm

percentages shown above (1),(2), (3) and (4) above

shown above

(1),(2), (3) and (4)

above

N.B . The percentages indicated are based on the gross cross sectional area not including fillets of the concrete to be reinforced. Where the thickness of the section exceeds 40 cm a thickness of 40 cm should be used in determining the temperature or minimum reinforcement.

6.3.4 Minimum shear reinforcement:- As per clause 26.5 1.6 of IS 456-2000 (P/48)

minimum shear reinforcement in the form of stirrups shall be provided such that

{Asv / (b x Sv) } {0.4 / (0.87 x fy)}

Where, Asv = total cross sectional area of stirrup legs effective in

shear

Sv = Stirrup spacing along the length of the member.

b = breadth of the beam or breadth of the web of

flanged beam.

fy = Characteristic strength of the stirrup reinforcement

in N/mm2 which shall not be taken

211

greater than 415 N/mm2.

6.4 Minimum cover to reinforcement:- (I.S : 456 - 2000 cl.no. 26.4 page - 46 )

6.4.1 Minimum cover at each end of reinforcing bar shall not be less than 30 mm. Nor

less than twice the diameter of such bar.

6.4.2 For faces not coming in contact with water, the minimum cover for reinforcement

shall not be less than 30 mm. Or less than the diameter of such bar.

6.4.3 For footing minimum cover shall be 50 mm.

6.4.4 In no case cover shall exceed 75 mm.

6.4.5 Cover to all type of reinforcement shall be 50 mm.

6.5 General requirement of reinforcement (Cl. No. 26 I.S. 456-2000)

6.5.1 Development length of bars. (Cl. No. 26.2.1 I.S. 456-2000)

The development length Ld is given by

Ld = ( x s) / (4 x Tbd )

Where , = Nominal diameter of bar s = Stress in bar at the section considered at design load. Tbd = design bond stress as per Cl.no. 26.2.1.1 I.S. 456-2000

6.5.2 Spacing of reinforcement:-

a) The horizontal distance between parallel main reinforcement bars shall not

be more than three times effective depth of a solid slab or 300 mm,

whichever is smaller.

b) The horizontal distance between parallel reinforcement bars provided

against shrinkage and temperature shall not be more than five times the

effective depth of a solid slab or 450 mm, whichever is smaller. (As per

clause 26.3.3 of I.S. 456-2000 Page 46)

c) The maximum spacing of shear reinforcement measured along the axis of

the member shall not exceed 0.75 d for vertical stirrups and d for inclined

stirrups at 45 Degree, where d is the effective depth of the section under

consideration. In no case shall spacing exceed 300 mm.(Clause 26.5.1.5

of I.S: 456 - 2000 P 47/48)

7.0 Miscellaneous:-

7.1 Joints:- In case of R.C.C. barrels, contraction joints with 225 mm wide P.V.C water

stop around the periphery shall be provided not more than 15 m. apart. As joints

are not to be located on bends the contraction joint shall be provided in the

horizontal limb of barrel at about 2.00 m away from the bend of inclined barrel. The

u/s and d/s inclined barrels shall be cast monolithic with this 2.00 m long horizontal

barrels as shown in sketch no. 6. When water flows through the syphon under high

pressure, two layers of water stops of PVC shall be provided. Normally a single

layer water stop may be adequate up to 6.0 m. head. If head is more than 6.0 m

two layer of PVC water stop shall be provided. In case of multi barrel syphons,

212

monolithic units of 3 or 4 barrels may be adopted and designed as a battery of

units in which the intermediate vertical walls are not designed for differential

hydrostatic pressure in the units. Water stops shall also be provided at the junction

of R.C.C. barrel with the transition walls.

7.2 Stop Logs:- Provision of u/s and d/s stoplog shall be made at either ends of

R.C.C. barrels to isolate any barrel for periodic inspection, maintenance and

repairs as and when required. The length of floor shall be decided on the basis of

FSD of canal.

7.3 Protection work:- The protection work are necessary in order to obviate the

possibilities of the scour due to travelling water close to C.C. floor of the structures.

The design of the apron as protective work depends upon the depth of scour,

velocity of flow and slope of launched apron. In other sense the protective work in

drain/river shall be provided with consideration of drain discharge and velocity of

flow in drain, as mentioned below.

7.3..1 For branch canal, the provision of protection of canal syphon , i.e. C.C. block pitching

and / or pitching on U/S and lonching apron on D/S should be provided as mention below as per

SSNNL circular no. SBC.1098-285-2-p dated 29/12/1998.

7.3.2 For protection of canal syphon across small rivers, Koters / nallas having design

discharge less than 1000 cumecs, the protection work is proposed as below (refer sketch no.1)

7.3.3 The thickness of pitching in U/S of structure and in the U/S and D/S side slope of the

drain / river shall be provided as per formula given in Para 8.5 of IS 8408-1976.

i.e. T = 0.06 x Q 1/3

Where ,T = Thickness of pitching in m.

Q = Discharge of drain/river in cumecs.

The thickness of pitching, weight and size of stone should be provided depending

upon the velocity of flow as per the sketch no.3. However, the minimum thickness

of pitching shall be kept equal to size of stone (as per fig 6 of IS-8408-1976) but not

less than 0.3 m. For velocities at which pitching stone of size greater than 0.4 m. is

needed (i.e. for velocity more than 3.5 m/sec) cement concrete blocks of 0.4 to

0.5 m. thickness can be used.

7.3.4 Length of pitching on U/S of structure

In U/S side of drain the length of pitching in bed as well as on slope shall be

provided as 1.5D where D is the maximum scour depth in m. from the lowest

ground level of river / nallas.

213

7.3.5 Launching apron on D/S of structure

Thickness: Thickness of launching apron shall be kept equal to 1.5T where T is the

thickness of pitching worked out as per Para 7.3.3 .

7.3.6 Length launching apron:- The length launching apron shall be kept as 2D ,

where D is the maximum scour depth in m. from the lowest ground level of river /

nallas.)

7.4 For all big rivers having discharge of 1000 cumecs and more , crossing the branch

canal the protection work is proposed as below (refer sketch no.2)

7.4.1 U/S protection :-

a) Block pitching 1.5 x 1.5 x 0.9 m. in a length of D (where D is scour depth in

m. from lowest ground level of river / drain).

b) Pitching in length of D (where D is scour depth in m. from the lowest

ground level of river of thickness T (T as per formula given below)

VA = 4.915 x d1/2

where. VA = Average velocity of flow in m/sec.

d = Mean depth of stone in m.

2.1.2.1.1.1 T = 2d

7.4.2 D/S protection :-

a) Block pitching 1.5 x 1.5 x 0.9 m. in a length of 1.5D (where D is scour

depth in m. from lowest ground level of river / drain).

b) Launching apron in a length of 1.5D of thickness 1.5T shall be provided

(Where T is calculated as above and D is scour depth from lowest ground

level of river / drain in m.)

For rivers where crossing site is near meander the block pitching shall be provided

1.5D and 2D for U/S and D/S of structure respectively.

7.6 For pitching on side slope of river, the pitching of thickness “T” shall be provided as

the case may be.

7.7 Pitching on the outer slopes of the canal bank shall be adequately protected

against flood up to HFL of the drain plus free board of minimum of 30 cm.

7.7.1 Local training works for large drainage:- Wherever a large drainage is flumed at

a canal crossing, suitable guide banks shall be constructed as per I.S.8408-1976.

7.7.2 Free board in the canal:- The free board for the canal bank u/s of the transition wall

214

shall be increased by 50% subject to a minimum of 0.3 m to prevent overtopping.

The increased free board shall be extended up to minimum length of 10 times the

canal bed width u/s of the syphon structure.

7.7.3 Service Road Bridge:- Suitable service road bridge shall be provided on service

road side of the canal.

7.7.4 Trash Racks:- Trash racks with adequate waterway shall be provided at the entrance

to the syphon structure where a large quantity of floating material is expected in the

channel water. To facilitate cleaning they are usually inclined at a slope of 1

horizontal to 4 vertical. If trash racks are provided head loss through trash rack

should be suitably taken.

7.8 Sump :- Sump shall be provided in the d/s of horizontal barrel for complete draining

out of water from the barrel as shown in sketch no. 7.

7.9 Collars :- The socket and spigot arrangement type R.C.C. M-25 collar shall be

provided(sketch no.10) at the joints in case of multi barrel syphon, where the

length of barrel exceeds 15 m. In case of barrels resting on compressible soils,

collars encircling the plain joint shall be provided. This will protect the water stop

from vertical shear due to excessive settlement. The cross section of the collar

shall be of size not less than 300mm x 300 mm. In case of syphons of multiple

barrels of more than one unit, the collar shall be designed to be flexible

(IS:7784(part-2/sect.3)-1996 clause no 8.2 page 6 ). Longitudinal analysis should

be done as per clause no 7.3.2 page-6 of above IS.

8.0 Model study :- For specific requirement of the structure, the model study shall be

carried out, if necessary. It shall be carried out at GERI, Vadodara for major

crossing to decide the adequacy of water way, river bank protection and other

protective measures required for the overall safety of the structure.

9.0 Overall all design shall be carried out in accordance with prevailing standard like I.S. / I.S.O / IRC, technical books, journals, guidelines of CSY etc. at where its found necessary. Over and above the best technical aspect and economy shall also be seen considering site conditions, importance of the structure etc. while designing of the structure.

***** Annex - I

REFERENCES The following references are used in the design of canal syphon.

1. IS:7784(part-I)-1993 " Code of practice for Design of Cross drainage works." 2. IS:7784(part-II)section3-1993 " Code of practice for Design of Cross drainage

works ,Specific requirements : Canal syphons" 3. IS:3370)part-I to IV)-1965/67 " Code of practice for Concrete structure for storage

of liquids ." 4. IS:456-2000 " Code of practice for Plain and Reinforced concrete. " 5. IS:1893-1984 " Criteria for earthquake resistance design of structures. " 6. IS:13920-1993 " Code of practice for Ductile detailing of RCC structures

215

subjected to seismic forces." 7. IS:6403-1971 " Code of practice for Determination of allowable bearing capacity." 8. IS:458-1983 " Code of practice for Concrete pipes ( with & without reinforcement

). " 9. IS:783-1985 " Code of practice for Laying of concrete pipes." 10. IS:8009 " Code of practice for Settlement. " 11. Design of small canal structures, 1978 - United states dept. Of the interior bureau

of Reclamation." 12.Design standard no. 3 ( Release no. DS 3.5 ) Canals and related structures

U.S.B.R. Note : The above list is not comprehensive, however the designer should refer all the relevant codes necessary and pertaining to designs.

*****

216

Guidelines for design of Drainage Syphon / Culvert on Branch Canals of Sardar Sarovar Project.

1.0 General:- When a canal crosses a stream or nalla a structure is required to carry canal

across it. This structure can be a drainage culvert or a canal syphon or an aqueduct

depending upon the relative levels of canal bed and drainage bed and also relative

discharge.

When the nalla bed is at a level lower than canal bed a drainage culvert is provided,

however in cases where HFL of nalla or stream is higher than the C.B.L it may be

necessary to provide drainage syphon.

In case where discharge of the stream is much larger than that of canal and also when

nalla is being used as road it will be advisable and economical to provide a canal syphon.

This note provides guide lines for design of Drainage Syphon or Drainage Culvert.

2.0 Design Data :

2.1 The hydraulic data, the geological data and other general data required for a particular

crossing site for taking-up the design are to be as per DATA SHEET FOR CSY prescribed

by this office vide letter no.NPPDC/B/Str.data/1836 dated 12/10/2001.

2.2 Sub soil information for foundation

2.2.1 For safe and secure foundation of structure, foundation soil information with all engineering

properties at the location of structure are very essential for which suitable trial bores at the

location of structure, upto the depth of twice the width of foundation from foundation level

shall be taken. The number and spacing of bore holes or trial pits will depend upon the

extent of the site and the length of the structure coming on it. The soil information as

disturbed and undisturbed samples for ascertaining necessary soil properties shall be

provided according to "Guide Lines on Investigation for Structures on Branch Canals of

Narmada Canal System" issued by this office in September 1998.

2.2.2 As the ground water level play important role in deciding safe bearing capacity and

swelling pressure of soil, particularly for finer particles of cohesive soil and so fluctuation of

ground water table should be obtained during execution of trial bore.

2.2.3 Liquefaction:-

i) Soils having engineering classification such as SM/ML/SP/SM-SC etc. are more

susceptible to liquefaction. In general, silty soil, sandy soil or combination of them

having poor densities and high saturation are prone to liquefaction

ii) To ascertain the possibility of liquefaction in case of the soils having classification

217

narrated under para 2.2.3 (I) above following criteria shall be examined precisely.

a) Standard penetration test (SPT) shall be performed at foundation level as per I.S.

2131. If the SPT value (N) is less than 20 soil is likely to liquefy and detail

investigations shall be required to be performed. If this value exceeds 20, risk of

liquefaction is reduced.

b) Particle size analysis : - In general uniformly graded sand particles are more

susceptible to liquefaction than well graded particles. If soil exhibits properties

within the range as under than the soil is more likely to liquefy. Sample should

satisfied all the criteria stated below.

i) 0.2 mm. < D60 < 1.0 mm.

ii) Fineness content (Silt & Clay) < 15%

iii) 2.0 < Cu < 5.0

iv) Void ratio (e) > 0.80

v) Plasticity Index (Ip) < 10.0

c) Relative density (Rd) :- In general cohesion less soils having relative densities

less than 75% liquefaction is possible.

2.3 In case rocky strata met with at foundation level the logging by the geologist shall

be done. The report and recommendation of Geologist stating characteristics of

rock is essential and shall be furnished

2.4 Layout:- As far as possib le a right angle crossing of drain shall be planned so that entry

and exit conditions are smooth and straight for about 30 m. or twice the width of the

structure whichever is more. Where a drain crosses a canal at an angle, entry and exit

conditions to satisfy the above requirements will have to be provided by redesigning/

regarding the drain. A skew crossing may be provided only where this is not possible.

2.5 Design of approach channel and tail channel:- Whenever regrading is required to be

resorted, such regraded level at downstream end of barrel shall be considered for

computing the bed gradient of the tail channel. Usually the water depth available (at or near

the starting point of approach channel and tail channel) above the nalla bed level for design

flood for the return period mentioned in para No.3.2.4 shall be considered in the design.

The ‘n’ value varying from 0.0225 to 0.03 depending upon the earth strata and 0.035 for

rocky strata may be adopted.

The main points regarding the design of the approach and tail channel are as

under:

218

i) Approach channel shall be designed with the average bed gradient of

nalla on upstream side of the structure.

ii) The depth of approach channel shall be considered equivalent to the

depth of water available in nalla on upstream side of the structure for

design flood.

iii) The tail channel shall be designed with depth of water in nalla on

downstream of the C.D work for design flood and average bed gradient

on downstream side of nalla where no regradation of nalla bed is

involved.

3 Hydrology:-

3.1 For checking the overall safety of the structure, from foundation scour and free board

considerations, the following shall be adopted

3.2 Hydraulic aspects :-

3.2.1 Hydrological studies:-

3.2.2 Design flood for drainage channel to be adopted for cross drainage works should depend

upon the size of canal, size of drainage channel and location of cross drainage. A very long

canal, crossing a drainage channel in the initial reach, damage to which is likely to affect

the canal supplies over a large area and for a long period, should be given proper

weightage.

3.2.3 Methodology of Design Flood :- Methods to be adopted for determination of design flood

corresponding to the catchment area of the drainage/ nalla are as under.

Sr.No. Catchment

area in sq.km.

Method Remarks

1 Less than 25 Modified rational formula

2 25 to 518 Flood estimation reports of various

subzones published by the Director

(Hydrology for small catchment ) C.W.C. ,

New Delhi

For subzone 3(a)

or 3(b) as the

case may be.

3 Above 518 Each case shall be taken up specifically and

decided after detailed examination as

mentioned in I.S. 7784 (Part-I) 1993

Notes:

219

1. The cross drainage structure should be checked for a checked flood discharge of value

20% higher than the design flood given in the table in para 3.2.4.

2. In case of very steep slopes, in case of catchment area less than 25.00 sq.km. results

arrived at by modified rational formula need to be care fully gone in to. If the modified

rational formula gives odd results it needs to be checked by alternative computation such

as sub zone report method (CWC). Same strategy should apply to C.A. exceeding 25.00

sq.kms.

3. For determining the observed flood, the field officer should go to the site more than two

times in a year immediately after the flood occurs and observe the levels care fully. The

value of “N” ( Coefficient of rugosity) shall be adopted care fully and the correct observed

discharge should be determined. This discharge should be further subjected to check by

measuring through existing structure U/S and D/S of the point of crossing if any.

3.2.4 Frequency of Design Flood :- As per I.S. 7784 (Part-I) 1993, the design flood for drainage

channel as given in para -7, cross drainage structures are divided in to four categories

depending upon the canal discharge and drainage discharge. Design flood to be adopted

for these four categories of cross drainage structure is given in table-1 of the code of

practice. Based on this table the B.O.C. has recommended the following table for adoption.

TABLE FOR DESIGN FLOOD VALUES

Category of

structure

Canal

Discharge in

cumecs

(*) Estimated drainage

discharge in cumecs

Frequency of design

flood

A 0 to 0.50 All discharges 1 in 25 years

B

C

0.50 to 15.0

15.0 to 30.0 0 to 150 1 in 50 years

C 15.0 to 30.0 Above 150 1 in 100 years

D Above 30.0 0 to 150

Above 150

1 in 100 years

As per note.2

Notes: -

1) The design flood to be adopted as mentioned in this table should in no case, be less than

the observed flood.

2) In case of vary large cross drainage structures where estimated drainage discharge is above 150 cumecs, the hydrology shall be examined in detail and appropriate design flood adopted, which should in no case be less than 1 in 100 years flood.

(*) This refers to the discharge estimated on the basis of river/nalla parameters corresponding to maximum observed flood level.

3.2.5 Basis for Design Flood Determination :- As per technical circular no. NPPDC/ A /

220

HYDROLOGY / 82 dated : 10/01/1995.

3.3 Wherever adjacent catchment areas are proposed to be diverted by means of a diversion

channel, the design flood discharge for the diverted areas shall be worked out considering

the total area for which the diversion is proposed to be made .

3.4 The H.F.L related to the design flood shall be completed at the center line of the canal and

then H.F.L at downstream end of the barrel shall be worked out as per bed gradient. The

upstream H.F.L shall be considered as the downstream H.F.L + loss of head through

drainage barrel. The loss of head through barrels is taken as hf = ( 1 + f1 + f2 L/R) V2/2g

(Unwins’ formula) value of ‘f1’ in working out loss of head shall be taken according to entry

condition as under:

f1 = 0.08 for bell mouth entrance and 0.505 for cylindrical entrance with sharp

edges ( unsharped mouth of the same sectional area of the barrel ).

f2 = a ( 1 + b/r)

Where the values of ‘a’ and ‘b’ are taken as 0.00316 and 0.030 for cement

plaster.

R = Hydraulic mean depth = A/P

Where, A = Cross sectional area of barrel in m2.

P = Wetted perimeter of barrel in m.

L = Length of barrel in m.

Hf= Head loss through barrel in m.

G = Acceleration due to gravity in m/sec.

For barrel / Pipe running partially the head loss shall be calculated as

HL = (sf x L)

Where Sf = V2 n2 / R4/3

L = Length of barrel in m.

3.5 Hydraulic Design :-

3.5.1 Square or rectangular R.C.C barrels or solid slab with abutments shall be adopted for

drainage syphon / culvert. RCC pipe may also be used depending upon discharge of drain

and economic considerations. Generally RCC pipes should be provided upto 3 cumecs

discharge and minimum diameter of pipe shall be 0.9 m. As a general guide line the size of

barrels may be adopted as required from drainage discharge consideration.

221

Variation in size of barrels shall be in multiple of 0.10 m.

3.5.2 The safety of barrels against uplift shall be checked for the following conditions.

a) Canal at FSL and drainage barrels empty.

b) Drainage at design flood level & Canal empty.

c) Construction condition i.e. ground water level at top of vertical wall and top slab is not

constructed.

d) Self floating conditions i.e. water table is above barrel including buoyancy concrete.

3.5.3 Additional resistance to uplift may be obtained by adding footing protruding beyond the

barrel and taking advantage of weight of earth lying above this footing.

Buoyancy concrete may be provided at the top of the barrel to resist uplift.

As per 13th B.O.C meeting full head of water shall be considered for exit gradient and the

uplift pressure shall be worked out by Khosla’s theory and arrived at head shall be

multiplied by 0.75 to achieve factor of safety against buoyancy.

3.5.6 The permissible velocity for the design flood shall be adopted as 4.0 m/sec. And for check

flood the velocity shall not exceed 5.0 m/sec. The check flood is considered as 30% more

than design flood. The velocity for 25 years return flood shall be checked and it shall be

ensured that the velocity is not less than 2.0m/sec.

3.5.7 For general, guide line the thickness of RCC member of the barrel for various sizes of

barrel may be assumed as given in statement No.1 the adequacy of thickness however

shall be checked for structural design requirement.

3.5.8 The crown of barrel/ pipe at the entrance shall be kept 0.5 m (water seal) below the

upstream HFL for the design flood (Refer sketch No.2. In case of small structures the water

seal may be taken 0.15 m or 0.20 m.

3.5.9 The inclination of the slopping barrels on the upstream shall not be kept steeper than 4

horizontal to 1 vertical and the downstream barrel slope shall be flatter than upstream

slope. The inclination of barrel shall start from 1.0 m away from the end of the canal bed

width near the junction of bed and slope of canal (Refer Sketch No.2)

3.5.10 The length of RCC barrels shall be fixed considering the height of breast

wall . The height of breast wall shall vary upto 5.0 m. as per requirement.

3.5.11 Scour Depth:-

3.5.11.1 Mean depth of scour:- The mean depth of scour in meters below the

222

check / high flood level may be calculated from the equation :

d sm = 1.34 x [ Di2 / Ksf ] 1/3

Where Di = The discharge in cumecs per meter width . The value of Di should be

the maximum of the following

I) The design flood divided by the effective linear water way between abutments or guide bunds, as the case may be.

ii) The value obtained should take into account

concentration of flow through a portion of the water way assessed from the study of the cross section of the drainage channel. Such modifications of the value may not be deemed

applicable to minor cross drainage structures with over all water way less than 60 m.

iii) Actual observation, if any.

Ksf = The silt factor for representative sample of the bed material

obtained upto the level of the deepest anticipated scour and

given by the expression 1.76 x [ dm ]1/2 ' dm' being the

weighted mean diameter in millimeters.

NOTES :- i) dsm may be taken as the grain size at 50% passing from grain size

distribution curve .

ii) The above method of estimated dsm is based on Lacey's theory for

regime condition in alluvial beds.

3.5.11.2 Maximum depth of scour for design of foundation:

The maximum depth of scour below the highest flood level (H.F.L) at obstructions and

configurations of the channel should be estimated from the value of 'dsm 'on the following

basis :

For the design of floor protection works , for raft foundations or shallow foundation , the

following scour values should be adopted.

i) In a straight reach 1.27 dsm

ii) At a moderate bend 1.50 dsm

iii) At a severe bend 1.75 dsm

iv) At a right angled bend 2.00 dsm

NOTE:- The values of scour depth obtained as above may be suitably modified where

actual observed data is available . Where concrete or masonary floor is provided under the

works , scour condition is not applicable and the foundations are usually taken to about 1.5

m below the floor levels with suitable cut-off for the concrete or masonary floors . However

223

where such a floor is not provided , foundations are taken to provide a margin below the

anticipated scour level ( usually called grip length ) of about 0.33 times the maximum depth

of scour . (I.S : 7784[PART-I] - 1993 )

3.5.12 The exit gradient shall be calculated with the cut off provision as above and it shall be

ensured that the value not less than as given below.

Clay 1 in 4

Single 1 in 4 to 5

Coarse sand 1 in 5 to 6

Fine sand 1 in 5 to 6

Fine sand 1 in 6 to 7

3.5.13 When slab culvert is provided, the minimum free board between the lowest point of super

structure and the HFL of drain shall be 60 cm (IS 7784 – Part-I, Page 1, Table No. 2)

4.0 Structural Design:-

4.1 Structural stability of the barrel shall be checked for the following condition:-

a) Canal at FSL & barrels dry.

b) Canal dry & drainage at design HFL (including afflux)

Due to difference in loading, the length of barrel is divided into two portions viz. Below

canal bed & below canal bank as per statement No.2

4.2 The mix of concrete of various RCC/PCC components shall be adopted as under:

Sr.N

o.

Grade of

Concrete

Where to be used

1 M-25 (RCC) RCC barrels, breast walls, staunching ring, cut-off walls.

2 M-15 (PCC) Coping on masonry wing walls (if adopted), Pucca floor.

Leveling course for foundation for RCC barrels.

3 M-10 (PCC) Buoyancy concrete, foundation of masonry wing wall, if

adopted.

4.3 The permissible stresses in concrete and steel shall be adopted as under.

Concrete (Table 21 of I.S 456-2000)

Sr.

No.

Permissible

stress

M-25 M-20 M-15

1 Bending 85 kg/cm2 70 kg/cm2 50 kg/cm2

2 Direct 60 kg/cm2 50 kg/cm22 40 kg/cm2

3 Bond 9 kg/cm2 for plain 8 kg/cm2 for plain 6 kg/cm2 for plain

224

bars in tension bars in tension bars in tension

Note : In case of deformed bars confirming to I.S. 1786 the bond stress given above

may be increased by 60% (Cl.no. B.2.1.2 I.S. 456-2000) for bars in tension and the

same shall be increased by 25% for bars in compression.

Shear: As per clause B-5 of I.S. 456-2000 as under:

Design shear strength of concrete without shear reinforcement. The permissible shear

stress (Tc) in concrete in beams without shear reinforcement.

100As/bd M-20 In kg/cm2 M-25 In kg/cm2

<= 0.15 1.80 1.90

0.25 2.20 2.30

0.50 3.00 3.10

0.75 3.50 3.60

1.00 3.90 4.00

1.25 4.20 4.40

1.50 4.50 4.60

1.75 4.70 4.90

2.00 4.90 5.10

2.25 5.10 5.30

2.50 5.10 5.50

2.75 5.10 5.60

3.00 and

above 5.10 5.70

Where ‘As’ is that area of longitudinal tension reinforcement which continues at least one effective

depth beyond the section being considered except at supports where the full area of tension

reinforcement may be used provided that detailing conforms to clause 26.2.2. i.e. Anchoring of

reinforcing bars and clause 26.2.3 i.e. curtailment of Tension reinforcement in Flexural members, b

is the breadth of beam and d is effective depth of beam.

For solid slabs, the permissible shear stress in concrete shall be K x Tc where k has the value

given below: (Clause no. B-5.2.1.1 I.S. 456-2000)

Tc = permissible shear stress in concrete in beams.

Overall depth of slab in mm.

K

300 or more 1.00 275 1.05 250 1.10 225 1.15 200 1.20 175 1.25

150 or less 1.30

225

With shear Reinforcement:- When shear reinforcement is provided the nominal shear stress Tc in

beams shall not exceed Tcmax given below For slabs Tv shall not exceed half the value of Tcmax

given below:- ( I.S : 456 - 2000 Table -24 , page -85 )

Grade of Concrete M-15 M-20 M-25

Tcmax 16 kg/cm2 18 kg/cm2 19 kg/cm2

4.4 Reinforcement:- The main bars, distribution and temperature bars shall be high yield

strength deformed bars (H.Y.S.D) conforming to I.S.1139-1966 and I.S.1786-1979. The

stresses for above bars shall be adopted as per Table-2 of I.S. 3370 Part-II 1965.The

detailing of reinforcement shall be done as per I.S : 13920 under seismic condition .

Type of Stress 2.1.3 Permissible stresses

a) Direct Tension 1500 kg/cm2

b) Bending

i) On liquid retaining face of member

ii) On face away from liquid for members

less than 225 mm.

iii) On face away from liquid for members 225

mm. Or more in thickness

1500 kg/cm2

1500 kg/cm2

1900 kg/cm2

c) Shear

i) For members less than 225 mm. Thickness

ii) For members 225 mm. Or more in

thickness

1500 kg/cm2

1750 kg/cm2

d) Compressive stresses. Compressive stress

in column subjected to direct load.

1750 kg/cm2

Note: Stress limitations for liquid retaining faces shall also apply to the

following.

a) Other faces within 225 mm. of the liquid retaining face.

b) Outside or external faces of structures, away from the liquid but placed in water logged

soils upto the level of the highest sub soil water level.

4.5 Minimum Reinforcement:- (As per IS 3370 (Part-II)- 1965, For mild steel)

226

4.5.1 The minimum reinforcement in each of two directions at right angle shall have following

area in that direction.

a) For sections upto 100 mm.

thickness.

0.3 percent of the Gross sectional area of

concrete.

b) For section between 100 mm. to

450 mm. Ttickness.

Linearly varying from 0.3% for 100 mm. thick

section to 0.2% for 450 mm. thick section.

c) * For sections greater than 450

mm. thickness 0.2% of cross sectional area.

* In concrete sections of thickness 225 mm. or greater two layers of reinforcing steel shall be placed

one near each face of the section to make up the minimum reinforcement specified above.

Where the thickness of the section exceeds 450 mm. thickness of 450 mm. shall be used in

determining the temperature or minimum reinforcement.

4.5.2 The minimum reinforcement specified above may be decreased by 20 percent in case of

high yield strength deformed bars conforming to I.S. 1786-1966 or I.S.1139-1966.

4.5.3 Where joints are provided in structures, the temperature or minimum reinforcement shall be

provided as under as per U.S. B.R. practice

A. The minimum reinforcement for canal structures shall be 12 mm. Dia @ 30 cm. In

all exposed faces and where reinforcement is placed in a single layer and 12 mm

dia @ 30 cm. in unexposed faces with two layer reinforcement.

B. Single layer reinforcement.

1) Reinforced concrete lining 10 cm. and less in thickness

with discontinuous wire fabric reinforcement and weakened

planes at 360 cm to 450 cm center.

0.10 percent.

2) Slab and lining not exposed to freezing temperature or

direct sun with joints not exceeding 900 cm.

0.25 percent

3) Slabs and linings exposed to freezing temperature or direct

sun with joints not exceeding 900 cm.

0.30 percent

4) Slabs and linings exceeding 900 cm between joints.

Category (2) above

Category (3) above

0.35 percent

0.40 percent

5) Walls and other structural members. Total percentage of

horizontal reinforcement to be equal to the sum of those

As per double layer

reinforcement

227

required for both faces as determined below.

C. Double Layer reinforcement :-

1) Face adjacent to earth with joints not exceeding 900 cm. 0.10 percent

2) Face not adjacent to earth nor exposed to freezing

temperatures or direct sun and with joints not exceeding

900 cm.

0.15 percent

3) Face not adjacent to earth but exposed to freezing

temperatures or direct sun and with joints not exceeding

900 cm.

0.20 percent

4) If member exceeds 900 cm in any direction parallel to

reinforcement add to the reinforcement requirement in that

direction because of the increased length.

0.05 percent.

5) If a slab is fixed along any line, double the dimension from

line of fixity to free end to determine whether reinforcement

is within the less than 900 cm or more than 900 cm

percentages shown above (1),(2), (3) and (4) above

shown above

(1),(2), (3) and (4)

above

N.B . The percentages indicated are based on the gross cross sectional area not including fillets of the concrete to be reinforced. Where the thickness of the section exceeds 40 cm a thickness of 40 cm should be used in determining the temperature or minimum reinforcement. 4.5.4 Minimum shear reinforcement:- As per clause 26.5 1.6 of IS 456-2000 (P/48) minimum

shear reinforcement in the form of stirrups shall be provided such that

{Asv / (b x Sv) } {0.4 / (0.87 x fy)}

Where, Asv = total cross sectional area of stirrup legs effective in shear

Sv = Stirrup spacing along the length of the member.

b = breadth of the beam or breadth of the web of

flanged beam.

fy = Characteristic strength of the stirrup reinforcement

in N/mm2 which shall not be taken

greater than 415 N/mm2.

4.6 Minimum cover to reinforcement:- (I.S : 456 - 2000 cl.no. 26.4 page - 46 )

4.6.1 Minimum cover at each end of reinforcing bar shall not be less than 30 mm. Nor less than

twice the diameter of such bar.

4.6.2 For faces not coming in contact with water, the minimum cover for reinforcement shall not

be less than 30 mm. Or less than the diameter of such bar.

4.6.3 For footing minimum cover shall be 50 mm.

228

4.6.4 In no case cover shall exceed 75 mm.

4.6.5 Cover to all type of reinforcement shall be 50 mm.

4.7 General requirement of reinforcement (Cl. No. 26 I.S. 456-2000)

4.7.1 Development length of bars. (Cl. No. 26.2.1 I.S. 456-2000)

The development length Ld is given by

Ld = ( x s) / (4 x Tbd )

Where , = Nominal diameter of bar s = Stress in bar at the section considered at design load. Tbd = design bond stress as per Cl.no. 26.2.1.1 I.S. 456-2000

4.7.2 Spacing of reinforcement:-

a) The horizontal distance between parallel main reinforcement bars shall not be

more than three times effective depth of a solid slab or 300 mm, whichever is

smaller.

b) The horizontal distance between parallel reinforcement bars provided against

shrinkage and temperature shall not be more than five times the effective depth of

a solid slab or 450 mm, whichever is smaller. (As per clause 26.3.3 of I.S. 456-

2000 Page 46)

c) The maximum spacing of shear reinforcement measured along the axis of the

member shall not exceed 0.75 d for vertical stirrups and d for inclined stirrups at 45

Degree, where d is the effective depth of the section under consideration. In no

case shall spacing exceed 300 mm.(Clause 26.5.1.5 of I.S: 456 - 2000 P 47/48)

5.0 Wing walls (RCC) M-25

5.1 The wing walls shall be provided straight with a splay of 2:1 on u/s & 3:1 on d/s side and

the slope of the wing wall shall match the outer slope of canal bank. The length of upstream

and downstream wing walls shall be provided as per requirements on the basis of width of

canal at the bank level. If necessary return wall may be provided thereafter. The top of the

wing walls shall be kept at minimum 0.30 m. above the HFL of the drain.

5.2 The top width shall be kept 0.30 m.

5.3 Weep holes in the wall shall be provided at spacing of 2.5 m c/c both ways in staggered

fashion with the bottom most row at 15 cm. above the nalla bed level. 10 cm asbestos

cement pipe shall be provided for weep holes with perforated jali both the ends of weep

holes.

229

5.4 The wing walls sections shall be checked for canal full and nalla dry condition, considering

back fill as saturated. No passive resistance shall be considered from the nalla side. Live

load and surcharge effected if any, shall be considered.

5.5 If the foundation of wing walls requires to be taken deeper for consideration of scour, the

minimum depth of foundation for wing wall shall be taken 1.5 m. from invert level of barrel

and for remaining depth up to scour RL a concrete key shall be provided along the

upstream face of the wing walls . The bottom width of key shall be kept 0.30 m.( Sketch-3).

6.0 Breast wall: (RCC M-25)

6.1 The top width of breast wall shall be kept 30 cm and the bottom width shall be provided as

per structural requirement.

6.2 The breast wall shall be designed for earth pressure and live load and seismic load effect if

any.

6.3 At the junction of breast walls with the barrel a haunch of 0.15 m x 0.15 m. shall be

provided.

7.0 Miscellaneous:-

7.1 Joints:- Joints shall be provided across and along the barrel length. The maximum spacing

of these joints, in either direction, shall be limited to 20 m. A gap of 12 mm. with water stops

at all the points across and along the barrel should be provided to accommodate the

movement.

7.2 In the case of drainage barrels resting on compressible soils, collars encircling the plain

joint should be provided (Sketch-4). In the case of multiple barrels having more than one

monolith, the collars may be designed to be flexible (Clause 6.6.1.1 I.S 7784 (Part-II

Section –5 1980)

7.3 At the junction of barrels with wing walls and barrels with breast walls and barrel with pucca

concrete floor P.V.C. water stops shall be provided.

7.4 Staunching Rings: When the exit gradient as specified in para 3.5.12 is not satisfied the

staunching ring of 30 cm. width and 90 cm. depth may be provided as per requirement on

SR and IP side. Nominal reinforcement shall be provided.

7.5 Pucca Floor:- The protection to be provided shall be as under:

30 cm. thick pucca concrete floor of M-15 grade shall be provided beyond the end of RCC

barrels upto the end of wing walls.

Beyond the end of wing walls 30 cm. thick rubble pitching in cm 1:5 shall be provided.

230

The pitching shall be bid upto a length L = 2(D) 1.5, where D = Depth of flow in the nalla at

design flood. (Refer sketch-5) or 5 m. whichever is more.

7.6 Pitching:- Rubble pitching of 30 cm. thickness shall be provided on the canal outer slope on

the upstream and downstream of the structure. The length of pitching, along the canal

banks shall be taken upto the ground level equal to afflux H.F.L. plus 0.5 m. or 30 m.

whichever is less.

7.7 Cut water and ease water:- The middle walls of the barrels shall be provided with semi

circular cut water and ease water at the entry and exit.

7.8 Canal Lining;- When barrel top is provided at CBL the thickness of canal lining near the

structure shall be increased to double the lining thickness in bed and sides upto a length of

15 m. on either side of CD work. Nominal reinforcement of 12 mm. at 30 cm c/c both ways

and both forces shall be provided (Sketch-6). High quality polysulphide sealants in the

lining joints should be provided commencing at a distance of 30 m. upstream of the

crossing and continuing 30 m. downstream.

7.9 Back filling behind end wall of barrel and wing wall.

For back filling behind end wall of barrel, more pervious material shall be placed at bottom

and less previous material at top (in 1.5 m. height). The back fill material shall be

compacted at OMC with pneumatic compactors. Minimum width of the trench shall be kept

0.45 m. Filling shall be done in a minimum slope of ½ :1 (Refer Sketch-7 )

For back filling behind wing walls more previous and free drainage material shall be

preferred. The back fill material shall be well compacted with pneumatic compressors.

Minimum width of the trench shall be 0.6 m. Filling shall be done in a minimum slope of ½:

1 in soil and ¼: 1 in rock.

231

Annex - I REFERENCES

The following references are used in the design of canal syphon. 1. IS:7784(part-I)-1993 " Code of practice for Design of Cross drainage works." 2. IS:7784(part-II)-1993 " Code of practice for Design of Cross drainage works

,Specific requirements :3. IS:3370)part-I to IV)-1965/67 " Code of practice for Concrete structure for storage of liquids ."

4. IS:456-2000 " Code of practice for Plain and Reinforced concrete. " 5. IS:1893-1984 " Criteria for earthquake resistance design of structures. " 6. IS:13920-1993 " Code of practice for Ductile detailing of RCC structures

subjected to seismic forces." 7. IS:6403-1971 " Code of practice for Determination of allowable bearing capacity." 8. IS:458-1983 " Code of practice for Concrete pipes ( with & without reinforcement

). " 9. IS:783-1985 " Code of practice for Laying of concrete pipes." 10. IS:8009 " Code of practice for Settlement. " 11. Design of small canal structures, 1978 - United states dept. Of the interior bureau

of Reclamation." 12.Design standard no. 3 ( Release no. DS 3.5 ) Canals and related structures

U.S.B.R. Note : The above list is not comprehensive, however the designer should refer all the relevant codes necessary and pertaining to designs.

232

Statement No.1

Statement showing the tentative thickness of members of the

barrels for various sizes of barrels.

Size No.

Size of Barrels in Mt.

Thickness of R.C.C. Members in Mt. Remarks.

Top slab

Bottom slab

End walls

Inter mediate walls

Walls Bet. Two monolith

Haunch sizie

1 2 3 4 5 6 7 8 9

1. 1.5 x 1.5 0.30 0.30 0.30 0.30 0.30 0.15

2. 2.0 x 2.0 0.30 0.30 0.30 0.30 0.30 0.15

3. 2.5 x 2.5 0.35 0.40 0.30 0.30 0.30 0.15

4. 3.0 x 3.0 0.35 0.45 0.30 0.30 0.30 0.15

5. 3.5 x 3.5 0.40 0.50 0.30 0.30 0.30 0.15

6. 4.0 x 4.0 0.45 0.55 0.35 0.30 0.35 0.15

7. 4.5 x 4.5 0.50 0.60 0.35 0.30 0.35 0.15

233

GUIDE LINES FOR DESIGN OF ROAD BRIDGES ON

NARMADA BRANCH CANAL

1.0. GENERAL

Usually the road bridges are planned to be provided at the crossing of the existing roads or cart

tracks. The average distance between the road bridges should be 1.60 km. If the existing roads or cart

tracks are nearer than the specified distance of 1.60 km. Location of the crossing on the canal shall be

decided in consultation with the District Panchayat Authorities.

1.2 As per the instructions contained in Govt. in R & B Deptt., Circular No.SSR-108-IB (19) C dated

30/5/1987 (in Gujarati) vide item (I) of Para 1, the location of the bridge structure shall be finalized

in consultation with the Superintending Engineer of State/Panchayat (R&B) Circle, as the case may

be. Moreover the category of the bridge shall be decided from the 20 years Road Development Plan

(Year 1981-2001).

1.3 For the sake of the economy, wherever possible, the bridge may be combined with irrigation

structures like falls, regulators, cross drainage works etc.

1.4 Clear carriage width for all categories of classified road bridges on Narmada Branch Canal shall be

kept as 7.50 m. as per B & C Deptt., G.R. No.VRR-1072-82(1) C dated 1.4.1981 and for unclassified

village road bridges it shall be kept 5.50 m. as per Government of Gujarat, NDD’s letter

No.NDS/1086/1523/17/I dated 17/10/88

1.5 Alignment:

As far as possible square crossing shall be provided. However the alignment of road crossing may

not be changed when the road crosses the branch canal at skew of less than 300. The skewness of

road crossing should not exceed 300 in any case.

1.6. Clearance:

The soffit level of the solid slab may be kept at the top of bank level (TBL) of the Canal. The

minimum vertical clearance shall be equal to the lined free board as given below.

Canal Discharge (Cumecs) Vertical Clearance (mm)

5 to 14.2 450

Above 14.2 600

2.0 Hydraulic Design

2.1. Length of Bridge:

Fluming of canal shall not be adopted at road crossing to avoid unnecessary head loss. Abutments

shall be so located behind the top of canal lining such that it does not intersect the horizontal key of

the lining. The total length of bridge shall be taken as the overall length measured along the center

line of bridge from end to end of the bridge deck.

2.2. Selection of span and type of bridge:

234

All the spans shall be usually kept equal and maximum span shall be generally not greater than 10

m. The most economical span length is that which satisfies the equation.

Cost of super structure = cost of the sub structure.

The number of spans shall be as low as possible, since piers obstruct the canal flow. For smaller

canals, piers may be avoided altogether as far as possible. Solid slab shall be provided for the road

crossing on branch canal up to 10 m. span. In small structure following approximate relationship

gives economical span for R.C.C. slab bridge.

S = 1.5 H

Where S = Clear span length (m)

H = Total height of abutment/pier from the bottom of its foundation to its top (m).

Solid slab shall be adopted as per type design of R&B Department.

For canals having discharge less than 3 cumecs pipe type crossing (PIPE CULVERT) may be

provided. For bridges having span greater than 10 m., T beam girder type bridges with cross girders

may be provided.

2.3. Loss of Head:

The head loss may be limited to 5 cm. for the branch canal. Typical head loss calculations are

attached at Annexure-2.

3.0 Design loading:

The live loads to be adopted for the design of various road bridges on Narmada Branch Canal are as

tabulated below:

TABLE-I

(Ref. Clause 207.4 of IRC-6-200)

Sr. No. Category of Road Design load to be adopted

1. National Highway (NH)

One lane of class 70 R for every two lanes with one lane of Class-A for the remaining lanes, if any, or one lane of Class A for each lane whichever gives worst effect.

2. State Highway (four lane) -do-

3. Stater Highway (S.H.)(Two lane)

One lane of Class 70 R or two lanes of Class-A.

4. Major District (M.D.R) Road -do-

5. Other district Road (O.D.R.) -do-

6. Village Road (V.R.) -do-

7. Unclassified Village Road (U.V.R) -do-

8. For additional single lane Village Road. One lane of Class-A considered to occupy 2.30 m. The remaining width of Carriageway shall be loaded with 500 kg/m2

4.0 Design of foundation :

The design of foundation shall be based on the engineering properties of foundation strata. Open

235

type footing may be provided as far as possible.

The safe allowable bearing values of rock strata shall be got tested as to its wet compressive

strength in actual practice, before finalizing the design of open foundation in rock.

The safe bearing capacity (SBC) values for hard rock or soft rock may be adopted from Indian

Roads Congress I.R.C.78-2000 Section VII as given below.

TABLE-II

Type of Rock/Condition Suggested allowable bearing values of average condition.

Hard Rocks 2.0 to 3.0 Mpa.

Soft Rocks 1.0 to 2.0 Mpa

Weathered Rocks, Conglomerates and latorites. Not more than 1.0 Mpa.

The safe bearing capacity (SBC) values shall be adopted as per data furnished by the field officer or

shall be worked out as per IS-1904-1978 Table-2 (Refer Annex-V) depending upon he type of soil.

The S.B.C., particularly in case of CH/CL/CI type of soils, shall be the minimum of that

obtained from shear failure criteria and that from allowable settlement point of view.

No tension shall be permitted under any combination of loads and forces for foundation resting

on any type of strata.

4.1.1. Pier Foundation :-

In case of ordinary soil strata, the minimum depth of foundation shall be 1.20 m. below CBL or GL,

whichever is lower. In case of black cotton soil, the foundation may at least be taken 1.80 m. into the

soil.

4.1.2. Abutment foundation :

In case of ordinary soil strata the minimum depth of foundation shall be 1.50 m. below GL or the

point of inter section, “P” of 2:1 line from toe of the canal side slope with the vertical face of

abutment as shown in the Sketch-1 below (i.e. 1.50 m. below G.L. or the intersection point “P”

whichever is lower).

4.1.3. Combined foundation:

In case when SBC of the soil is very low (less than 10 t/m2) combined foundation for pier &

abutment shall be designed.

236

ABUTMENT 2 : 1

F.S.

D.

SLOPEPCC M-15

SKETCH - 1

1.50

m

GL/ NBL

L1.

20 m

2:1

R=1.0m

CANAL LINING

C.B.L.

1.5 : 1

DECK SLAB OF BRIDGE

ROAD LEVEL

APPROACH SLAB

BACK FILLP

CAP

WEARING COAT

PIER

F.S.L.

4.1.4. In case of rocky strata, the minimum depth of foundation for abautment shall be 0.30 m. or so in to

hard rock and 0.60 m. or so in case of soft rock, below GL or point of intersection “P” whichever is

lower.

4.1.5. The slope between bottom edge of toe of abutment foundation and adjacent bottom of pier

foundation shall not be kept Steeper than 2:1. (Refer Sketch-1)

4.1.6. The distance (Refer Sketch-1) between the extreme edge of Toe of abutment foundation and canal

lining, measured Perpendicular to canal slope, shall be more than 1.20 m. (Refer Sketch-1).

4.2 Factor of safety for Pier and Abutment:

The different factors of safety shall be adopted as per the clause 706.2.2 of IRC:78-2000 as under:

i) Overturning (without seismic effect) = 2.00

ii) Overturning (with seismic effect) = 1.50

iii) Sliding (without seismic effect) = 1.50

iv) Sliding (with seismic effect) = 1.25

As per clause 222.5 of IRC-6-2000 the various seismic Coefficient are as below:

i) Horizontal seismic coefficient = As per respective zone

ii) Coefficient of soil, foundation = As per Table-6 of IRC-6-

2000

iii) Importance factor 1.00 1.50 For UVRB For VRB,ODRB,MDRB,SHRB& NHRB.

As per Clause 3.4.2.3 (a) of IS 1893-1984 the horizontal coefficient shall be worked out, for

calculating the horizontal seismic force.

5.0 Structural Design:

237

5.1 Concrete: For foundation, of abutment and pier 0.15 m. thick plain cement concrete (P.C.C.) of

M-15 grade shall be provided as a leveling course.

Pier and abutment shall be in R.C.C.M-25 grade.

The concrete for abutment and pier cap shall be in C.C.Grade M-25.

5.2 Sub Structure:

The piers and abutments are to be designed as per column theory. The design moments calculated for

pier caps and abutment cap are very small and hence minimum reinforcement shall be provided as

per IRC Codes. The cantilever pier caps for classified road square bridges and unclassified road

square bridges have been standardized. (Refer Annexure VII & VIII). The returns, pedestal shall

be designed as per relevant IRC codes of practice (refer Annexure-III & IV for the caps.)

5..3. Return Walls:

R.C.C. cantilever return wall may be provided as shown in the Sketch-2 below in case of high

abutment. Minimum depth of return wall at the end shall be 0.45 m. The length of cantilever return

wall shall not be more than 1.80 m.

SKETCH-2

5.3 Super structure and Ancillary Works:-

5.3.1. Solid Slab:-

Super structure is usually R.C.C. solid slab in M-25 grade for all categories of roads. Thickness and

reinforcement of the slab in C.C.M-25 grade for all categories of roads thickness and the

reinforcement of the slab shall be designed.

5.3.2. Reinforcement:

Only high yield strength deformed (H.Y.S.D.) bars conforming to IS-1786-1985 shall be used. The

allowable stresses in cold twisted deformed bars shall be 2000 kg/cm2 for tension in flexure, shear

or combined bending and 1700 kg/ cm2 for direct compression, as per Table – 10 of IRC-21-2000.

The maximum bar size is limited to 32 mm.

5.3.3. Parapet:-

Perforated R.C.C. grade M-25 parapets, 0.80 m. high above kerb and 0.15 m. for square bridge and

0.20 m. for skew bridge thick are provided on either side of the slab as per ;the type design of

238

Designs (R&B) Circle and shall not be cast monolithic with the solid slab of the bridge.

5.3.4. Water Spout:-

For drainage of rain water from the deck slab, water spouts of G.I. Pipe shall be provided as per

R&B standard at about 3 m. spacing.

5.3.5. Wearing Coat:-

The wearing coat of asphaltic concrete 80 mm. thick shall be provided as per M.O.T. standard in two

layers as shown in Sketch-3 as under.

CARRIAGE WAY=7.50 mCAMBERKERB

25 mm

1 IN 62.51 IN 62.5

SKETCH-3

DECK SLAB OF BRIDGE50 mm60 mm

25 mm

LC WEARING COAT OFASPHALTIC CONCRETEIN TWO LAYERS.

5.3.6 Camber:

The camber of Asphaltic concrete wearing coat shall be provided as 1:62.5 transversely on bridges

as well as on road up to 20 m. of approach for classified road abridges. For unclassified village road

bridges the camber for Asphaltic concrete wearing coat shall be provided as 1:48.

5.3.7 Expansion Joint:

Bitumen or premoulded asphalt joint filler of 20 mm. thickness shall be provided at

expansion joints in between two deck slabs as well as between the approach slab and the deck slab.

5.3.8 Joint:

The joint between canal lining and pier face shall be filled with sponge rubber filler at the bottom

and elastomer sealant at the top as shown in the sketch 4 below.

239

12mm

20 mm

SKETCH-4

CANAL LINING

SPONGE RUBBER FILLER

PIER FACE

ELASTOMER SEALANT COMPLETELY AROUND THE PIER

25 mm

5.3.9 Bearing

Tar paper bearings may be provided as per Ministry of Transport (MOT) specifications. The width

of bearing shall be considered as 0.37 m.

5.3.10 G.I. Pipe Railing

G.I.Pipe railing shall be provided as per standard design of R&B Department, Annexure-VI.

5.3.11 Dirt Wall:-

Dirt wall in R.C.C.M-25 grade shall be provided as per design (R&B) standards (refer Annexure-IV).

5.3.12. Walkway:

The walkways of 1.50 m. width shall be adopted on both sides of N.H.B. crossing. In case of

S.H.R.B/M.D.R.B., walkway of 1.50 m. width shall be provided on either side of the bridges which

are located near cities or any industrial area as per field officer’s proposal.

5.3.13 Approach Slab:

15 cm. Thick and 3.65 m. in length approach slab in R.C.C. M-25 grade shall be provided on either

side resting of 15 cm. thick bed concrete of P.C.C.M-15 grade as per standard drawing of R & B

Deptt., Type drawing for the approach slab is attached as Annexure IX.

5.3.14 The unit weights of R.C.C., plain concrete and compacted earth shall be taken as 2400, 2200 and

1800 kg/cm3 respectively as per Clause-205 of IRC 6-2000.

6.0 Approaches:

6.1 Ruling Gradient:

The standard for ruling gradient and ruling minimum radius for the curve for flat topography shall be

as follows.

240

TABLE-III

Sr.No. Type of Road Radius of the Curve Gradient

1. N.H. 300 1 in 50

2. S.H. 300 1 in 50

3. M.D.R. 240 1 in 50

4. O.D.R. 155 1 in 50

5. V.R. 90 1 in 50

6. U.V.R. 45 1 in 50

6.2 The approaches on either side of straight bridge shall have a minimum straight length of 15 meters

and shall be suitably increased, where necessary to provide for minimum sight distance of the design

speed. The approaches shall be provided from the end of bridge deck of the road way at the same

level as the top of the bridge deck as shown in Sketch-5 below:-

1 IN

30

SKETCH-5

SIDE ROAD

DECK SLABEND OF

1.5 : 1

1.5 : 1

SR / IP

20 m

1 IN 50

APPR-OACHROAD A

PPR

OA

CH

SLA

B

20 m

BER

M

1 IN

30

BER

M

OF BRIDGELC

CA

NA

L

FLO

W

In case where the bridge top level is higher then canal service road (SR)/Inspection Path (IP) top

level a grade of 1 in 30 shall be provided to join the SR/IP level and top of road bridge level.

241

The road approaches shall have a gradient of 1 in 50.

7.0 Miscellaneous:

7.1 Back filling:

The extent of backfilling behind the abutment shall be as shown in Sketch-6 below. It shall be

thoroughly compacted as per specifications. The backfill material shall be non swelling and non

shrinking type. The soil to be used for backfill should be non swelling/non shrinking type and shall

be compacted at optimum moisture content (O.M.C) to 95% Proctor Density.

NATURAL STRATAORAPPROACHEMBANKMENT

EXTENT OF FILL

SKETCH-6

EXCAVATION LINE

BACK FILL

CANAL SIDE

ABUTMENT

P.C.C. IN M-15

ROAD LEVELDECK SLAB

7.2 Bridges on Curves:

As far as possible bridges on curve shall be avoided. However when a road crosses the canal on

curves, special precaution is required to be taken while giving layout for the bridge construction and

its design. The road bridge shall remain right angle to the straight line joining points on center line of

the canal on outer edge of the bridge and each pier and abutment shall be aligned accordingly. (Refer

Sketch-7 below).

Additional forces due to curvature shall be considered as applicable.

242

OF CANAL

CUT WATER

EASE WATER

SKETCH-7FL

OW

90°

APEX PIER LINE

CL

OF BRIDGECL

7.3. Drain culverts in approaches:-

In case of contour alignment of canal whenever the bridge is away from the ridge line, suitable

arrangement in approach road to drain off the surface run off from the area on the ridge side of the

canal shall be provided.

The afflux due to the drain culverts in approaches shall be limited to 0.50 m. 8.0 PIPE ROAD CROSSING

8.1 Type of Pipe NP3 class pipe shall be used for road crossing. The minimum diameter of pipe may be kept as 0.90

m.

8.2 Cover:

Minimum earth cover over the pipe shall be 1.0 m. for classified roads and 0.60 m. for unclassified

road.

8.3. Velocity in Pipe

The maximum velocity of 2.50 m/sec. shall be allowed in the pipe

8.4 Head loss:

In case of pipe running full the head losses shall be calculated as under.

HL = 1.50 [V]2 + (Sf x L) 2g Where HL = Head loss ( in m.) V = Velocity in pipe ( in m/sec.) Sf = [V]**2[D]**2 (as per Manning’s formula) (R)** 4/3

R = D/4, where D is pipe diameter in m & L = Length of pipe in m. In case pipe is running partial,

the head loss shall be calculated as under, considering other losses at entry and exit insignificant.

243

HL = (Sf x L)

Where Sf = [V]**2 [n]**2 [R]** 4/3 L= Length of pipe ( in m.)

8.5 Strength of Pipe:-

The strength of pipe shall be checked to ensure that the requirements are met with as per IS 783 –

1985

8.6 Head walls shall be provided at u/s & d/s end of pipe and the canal section will about against the

head walls with suitable transition in bed width, if necessary. If transition in canal is required, it

shall be provided in a length of three times the diameter of pipe.

244

Annexure-1

REFERENCES

The following references are used in the Guide lines for design of road bridges.

1. I.S.1904-1998 structural safety of building: Shallow foundations, code of practice for

2. I.R.C.78-2000 “Standard Specifications and Code of Practice for Road Bridges Section-VII Foundation and Sub Structure”.

3. I.R.C. 6 – 2000 “Standard Specifications and Code of Practice for Road Bridges Section-II Loads and Stresses”.

4. I.S. 1893 – 1984 “Criteria for Earthquake resistant design of structures” (Fourth Revision)”

5. I.R.C. 21-2000 “Standard Specifications and Code of Practice for Road Bridges, Section-III Cement Concrete” (Plain and reinforced).

6. I.S.783 – 1985 “Code of Practice for laying of concrete Pipes”

7. IS 456-2000 “Plain and reinforced concrete Code of Practice” (Forth Revision)

8. I.S.1786-1985 “Specification for high strength deformed steel bars and wires for concrete reinforcement (Third Revision)

9. IRC-5 1998 Standard Specification and Code of Practice for Road Bridges Section-1 “General Features of Design”.

Note:- The above list is not comprehensive. However, the designer should refer all the relevant codes necessary and pertaining to designs.

Annexure-II

Typical Calculation for loss of Head of Canal Bridges at Ch.75270 m. on Vadodara Branch Canal

V.B.C.II

(A) Data:

1) R.D. of the structure 75270 m.

2) Design discharge of Canal QD 20.11 cumecs

245

3) Allowable Head Loss (HL) 0.05 m.

4) Ground Level (NBL) 0.05 m.

5) Canal Bed Level (CBL) U/S RL 19.402 m.

D/S RL 19.352 m.

6) Full Supply level (FSL) U/S RL 22.002 m.

D/S RL 21.952 m.

7) Bed width (B) 3.60 m.

8) Full Supply Depth (FSD) D 2.60 m.

9) Free Board (FB) 0.90 m.

10) Canal Velocity (VI) 1.03 m/sec.

11) Top width of Bank

a) Service Road (SR) side 4.88 m

b) Other side 4.88 m

12) Side slopes

a) Water side 1.5:1

b) Other side 2:1

13) Co-efficient of rugosity (n) 0.018

14) Type of crossing Right angle crossing

15) Proposed road width 7.50 m.

16) Shape of cutwater & ease water Semi Circular

(B) Head loss Calculation :-

Loss of head = h = h1 + h2 + h3

Where h1 = loss of head at entry

= h1 = loss of head at entry

= C1[ (V2)**2-(V1)**2 ] 2 x g h2 = loss of head due to rugosity though the bridge opening.

= (V2 x n)** 2 x L (R)** 4/3 And h3 = Loss of Head at exit = C2 [(V2)**2 – (V1)** 2] 2g Where V2 = Velocity in m/sec. through bridge opening

246

V1 = Canal velocity in m/sec. L = Length of Bridge opening in m. N = Co-efficient of rugosity = 0.017 for concrete or hume pipe = 0.010 for Brick masonary = 0.020 for stone masonary & concrete lined canal R = Hydraulic mean depth in m. Area (A) Perimeter (P) C1 = 0.5 for sharp concerned entrance = 0.25 for round concerned entrance = 0.10 for bell mouthed or warped entrance C2 = 0.5 for sharp concerned exit. = 0.2 for warped exit. A = {11.4 + 3.60 x 2.6} -2 {1.06 + 1.20 x 2} 2 2 = 14.98 m. V2 = 20.11 14.98 = 1.34 m/sec. H1 = C1 [(V2)2 – (V1)2] 2g = 0.25 x {(1.34) 2 - (1.03) 2} 2 x 9.81

= 0.0094 m = 0.009 m. N = 0.018 (given) R = A, where P = 3.60 + 2 x 4.7 = 13 m. P = 14.96 13 = 1.15 m. L = 0.02 m. H2 = (1.34 x 0.028) 2 x 9.02 (1.15) 4/3

247

= 0.0039 0.004 m. h3 = C2 [ (V2)2 – (V1)2 ) ] 2 x 9.81 = 0.50 x (1.34)2 – (1.03)2

2 x 9.81 = 0.019 m = 0.02 m. h = h1 + h2 + h3 = 0.009 + 0.004 + 0.02 - 0.033 < Allowable head loss of 0.05 m. However considered RL = 0.05 m.

SKETCH SHOWING DIMENSION OF BRIDGE COMPONENTS

TOP WIDTH OF PIER CAP

400TOP WIDTH OF

ABUT. CAP

400

370mm BEARING

185195

ABUTMENT

TOP WIDTH OF ABUT. STEM

10 10

150mm THICK APPROACH SLAB

20mm TH.EXPANSION

JOINT

NOTE:- ALL DIMENSIONS ARE IN mm

L clearL effective

(NOT TO SCALE)

20x20mm CHAMFERING

PROJECTIONOF ABT. CAP

20x20mm CHAMFERING

PROJECTIONOF PIER CAP

L c/c (SQUARE)

THICKNESS OF R.C.C SOLID SLAB IN M-25

80mm TH. (AVERAGE) WEARING COAT

Annexure -III

THICKNESS OF PIER CAP

TOP WIDTH OF PIER STEM

PIER

10370

10

20mm TH.EXPANSION JOINT

195185

249

ANNEXURE –IV (TABLE – IV)

DIMENSIONS OF ABUTMENT AND PIER COMPONENTS FOR DIFFERENT SPANS BASED ON MOST’S STANDARD PLAN FOR SOLID SLABS.

SPAN LENGTH (L) ABUTMENT COMPONENTS PIER COMPONENTS REMARKS L c/c (m)

L clear (m)

L eff (m)

Top width Of cap ( m.)

Thickness of Dirt wall (mm)

Thickness of Stem (mm)

Project ion of Cap (mm)

Top width of cap (mm)

Thickness of Stem (mm)

Project Of Cap (mm)

3.76 3.00 3.37 550 140 300 250 800 300 250 L clear = L c/c -2 [ 0.02 + 0.37] 2 L c/c = L clear + (0.37 + 0.02 ) x 2 2 L e f f = L clear + 0..37

4.76 4.00 4.37 600 190 400 200 800 400 200

5.76 5.00 5.37 650 240 500 150 800 500 150 Thickness of expansion Joint = 20 mm

Chamfering of 20 mm x 20 mm

Bearing = 370 mm thickness/depth of abutment/pier cap =

600 mm

Thickness of wearing coat= 80 mm (Av.)

Thickness of Approach slab 150 mm.

6.76 6.00 6.37 700 290 600 100 800 600 100 7.76 7.00 7.37 750 340 700 50 800 700 50 8.76 8.00 8.37 750 340 700 50 800 700 50 9.76 9.00 9.37 800 390 800 - 800 800 - 10.76 10.00 10.37 800 390 800 - 800 800 - NOTE:

1) THE DIMENSIONS SHOWING ARE TENTATIVE AND SHALL BE CHANGED AS PER DESIGN REQUIREMENTS.

2) THE TABLE HAS BEEN REVIEWED BASED ON MOST, NEW DELHI’S STANDARD PLANS FOR SOLID SLABS BY UNIT-E, NPP&DC, GANDHINAGAR

3) THE SKETCH ACKNOWLEDGED WITH THE TABLE MAY BE REFERRED FOR FURTHER DETAILS.

Annexure-V

S.B.C. I.S. 1904 – 1978

Sr.No. Cohesive Soils t/m2

1. Soft shale, hard or stiff clay in deep bed, dry 45

2. Medium clay [ indented with a thumb nail (impression)] 25

3. Moist clay & sandy clay mixture which can be indented with strong thumb pressure

15

4. Soft clay indented with moderate thumb pressure 10

5. Very soft clay 5

6. Black cotton soil or other shrinkable or expansive soil (50% saturation) -

Cohesion less soils

1. Gravel, sand & gravel, compact and offering high resistance to

penetration when excavated by tools 45

2. Coarsc sand compact & dry 45

3. Medium sand compact and dry 25

4. Fine sand silt (dry lumps easily pulverized by the finger) 15

5. Loose gravel or sand gravel mixture, loose course to Medium sand dry 25

6. Fine Sand 10

L= 3650-250-WIDTH OF DIRT WALL/23

L

L

3650

150 MM THICK FOUNDATION CONC.(P.C.C. M-15)

150 MM THICK APPROACH SLAB M-25

M.S.80X50X10 mmPLAN (NOT TO SCALE )

M.S. 80X50X10 mm

DETAILS OF G.I.PIPE RAILING

500PCC M-15BLOCK

ELEVATION (NOT TO SCALE)

500

250 L

300 MM RUBBLE SOLING

250

500

APPROACH SLAB

L

80 MM THICK WEARING COAT IN ASPHALTIC CONCRETE

SIDE VIEW (NOT TO SCALE)

ALL DIMENSIONS ARE IN mm.

WIDTH OF DIRT WALL /2

R.C.C. SLAB M-25

(M-25)ABUTMENT

(M-25)ABUTMENT CAP

L

EXPANSIVE JOINT20 mm THICK

BEARINGTAR PAPER

500

R.C.C. PARAPET

KERB M-25

(M-25)

300

150

15080

38 mm Ø G.I.PIPE.

38 mm Ø G.I.PIPE

3650L

PARAPET

ROAD LEVEL

KERB

SOLINGRUBBLE

300 THICK

150 THICK APPROACH

500 P.C.C.M-15FOUNDATIONP.C.C. M-15

SLAB IN M-25

AN

NE

XU

RE

-VI

M.S. 80X50X10 mm

ANNEXURE- VII

CANTILEVER PIER CAP For classified road square bridges (VRB, ODRB, MDRB & SHRB)

SECTION A-A

0.80m

0.075

SKETCHA

0.825m

0.750.

30m

0.30

m

A

Reinforcement details of cantilever Pier cap. Top : 10 Nos 16 mm Ø Bottom: 6 Nos 16 mm Ø Side: 2 Nos. 16 mm Ø on each side Stirrups: (i) For Torsion 12 mm Ø 2 legged stirrups @ 15 cm c/c ii) For Shear 12 mm Ø 4 legged stirrups @ 15 cm c/c Bond length = 125.0 + 10.0 = 135.0 cm. Grade of concrete : M-25 Type of steel : S 415

253

Annexure-VIII

CANTILEVER PIER CAP

For unclassified village road square bridge (U.V.R.B.)

0.80m

SKETCHA

0.60

0.675m

0.30

m0.

30m

0.075

A

SECTION A-A

Reinforcement details of cantilever pier cap. Top : 8 Nos 16 mm Ø Bottom: 6 Nos 16 mm Ø Side: 2 Nos. 16 mm Ø on each side Stirrups: (i) For Torsion 12 mm Ø 2 legged stirrups @ 20 cm c/c ii) For Shear 12 mm Ø 4 legged stirrups @ 20 cm c/c Bond length = 125.0 + 10.0 = 135.0 cm. Grade of concrete : M-25 Type of steel : S 415

3650

C1C1 C1C1

X

C3C4 C1

C1C4

C4

C1C3

C1

C3

C3C3

C1C3

C1

C3

C1C3

C1

C3

80 (AVG.) ACROSS THE ROAD WIDTH .

TAR PAPER BEARING

ABUTMENT CAP IN R.C.C M-25

20mm THICK EXPANSION JOINT FILLED WITH BITUMEN IMPREGNATED FELT

RCC SOLID SLAB M 25650

20x20 mm CHAMFERING

C2C2

150

C4

750

46 129

C3

150

340

RCC DIRT WALLM 25

B

C3 C2 C3 C2

1504C

129 150

A B C1 3C

C1C1C1C1 3590

C3C3

C1C3

C1

C3

C1C3

C1

C3

C3C3

C1C3

C1

C3

C1C3

C1

C3

C4

CARR

IAGE

WAY

=550

0

C4

C4

X

6 C 10 450

5 C 10 450

4 C 10 450

3 C 10 450

2 B 12 150

4

3

2

1

66

66

90

90

TRANSVERSE STEEL AT TOP AND BOTTOM

-DO-

-DO-

-DO-

ADDED 13Ø FOR EACH HOOK.

16166

33266

90

90186

3325440

553

724

626

772

5440

ALL DIMENSIONS ARE IN MILLIMETRE (mm) AND LEVELS AND CHAINAGES IN METRE (m) UNLESS OTHERWISE SPECIFIED.

THIS DRAWING SHALL NOT BE SCALED ONLY WRITTEN DIMENSIONS SHALL BE FOLLOWED.

GRADE OF CONCRETE FOR RCC COMPONENT IS M 25 HAVING COMPRESSIVE CUBE STRENGTH OF 250 kg/cm2 AT THE END OF 28 DAYS.

HIGH YIELD STRENGTH DEFORMED BARS (Fe 415 GRADE) CONFORMING TO IS:1786-1985 SHALL BE USED FOR REINFORCEMENT.

CLEAR COVER TO REINFORCEMENT SHOULD BE 30 mm. THIS DRAWING IS PREPARED IN ACCORDANCE WITH R & B DEPARTMENT DRAWING NO.T112/90 (iii) DATE 13/6/90.

BEFORE LAYING APPROACH SLAB, THE SUB GRADE SHOULD BE PROPERLY COMPACTED. THE SEISMIC FORCES HAVE NOT BEEN CONSIDERED IN THE DESIGN OF APPROACH SLAB.

REFER PLATE - 8/8, WHEN EVER SPLICING/LAPPING OF BARS IS TO BE DONE.

10. THE WORKING DRAWING SHALL BE FULLY EXAMINED WITH RESPECT TO CONDITIONS PREVAILING AT SITE BEFORE ADOPTING ON WORK AND IN CASE OF ANY DISCREPANCY OR SHORT FALL IS NOTICED, THE SAME MAY BE BROUGHT TO THE NOTICE OF DESIGN CIRCLE FOR CONSIDERATION AND MODIFICATION AS MAY BE NECESSARY.

SHAPE OF BAR WITH DIMENSIONS IN mm

(NOT TO SCALE)

129

300 THICK DRY RUBBLE SOLING

150 THICK LEVELLING COURSE PCC M 15

C3 C2

A

C3 C2 C3 C2 C3 C2

150 150

RCC M 25

WEARING COAT

150 1501.

2.

3.

4.

5. 6.

7.

8.

9.

150

150

150

154C4

46

129 46

300

150

1 A 12 150

DIA OF HYSD

BAR (mm)

TYPE OF BAR SR.

NO.

SPACING OF BAR

(mm)

80 (AVG.) ACROSS THE ROAD WIDTH .

4C AN

NEX

UR

E - IV

AT TOP AND BOTTOM

LENGTH OF BAR INCLUDING HOOKS (mm)

3590

REMARKS

Guidelines for design of Super passage on Branch Canals of Sardar Sarovar Project.

2.0 General:-

When a canal crosses a stream or nalla a structure is required to carry canal across it. This structure can be a drainage culvert or Super passage depending upon the relative levels of canal bed and drainage bed and also relative discharge. When the nalla bed is at a level higher than canal FSL/TBL a Super passage is provided. In case where discharge of the stream is much larger than that of canal and also when nalla is being used as road it will be advisable and economical to provide a canal syphon. This note provides guide lines for design of Super passage or Canal Culvert.

2.0 Design Data : 2.2 The hydraulic data, the geological data and other general data required for a

particular crossing site for taking-up the design are to be as per DATA SHEET FOR CSY / DSY.( Ref. guidelines of CSY / DSY )

2.2 Sub soil information for foundation 2.2.1 For safe and secure foundation of structure, foundation soil information with

all engineering properties at the location of structure are very essential for which suitable trial bores at the location of structure, upto the depth of twice the width of foundation from foundation level shall be taken. The number and spacing of bore holes or trial pits will depend upon the extent of the site and the length of the structure coming on it. The soil information as disturbed and undisturbed samples for ascertaining necessary soil properties shall be provided.

2.2.2 As the ground water level play important role in deciding safe bearing capacity and swelling pressure of soil, particularly for finer particles of cohesive soil and so fluctuation of ground water table should be obtained during execution of trial bore.

2.2.3 Liquefaction:- i) Soils having engineering classification such as SM/ML/SP/SM-SC

etc. are more susceptible to liquefaction. In general, silty soil, sandy soil or combination of them having poor densities and high saturation are prone to liquefaction

ii) To ascertain the possibility of liquefaction in case of the soils having classification narrated under para 2.2.3 (I) above following criteria shall be examined precisely.

a) Standard penetration test (SPT) shall be performed at foundation level as per I.S. 2131. If the SPT value (N) is less than 20 soil is likely to liquefy and detail investigations shall be required to be performed. If this value exceeds 20, risk of liquefaction is reduced.

b) Particle size analysis: - In general uniformly graded sand particles are more susceptible to liquefaction than well graded particles. If soil exhibits properties within the range as under than the soil is more likely to liquefy. Sample should satisfied all the criteria stated below.

vi) 0.2 mm. < D60 < 1.0 mm. vii) Fineness content (Silt & Clay) < 15% viii) 2.0 < Cu < 5.0 ix) Void ratio (e) > 0.80 x) Plasticity Index (Ip) < 10.0

c) Relative density (Rd) :- In general cohesion less soils having relative densities less than 70% liquefaction is possible.

2.3 In case rocky strata met with at foundation level the logging by the geologist shall be done. The report and recommendation of Geologist stating characteristics of rock is essential and shall be furnished

3.4 Layout: - As far as possible a right angle crossing of drain shall be planned so that entry and exit conditions are smooth and straight for about 30 m. or twice the width of the structure whichever is more. Where a drain crosses a canal at an angle, entry and exit conditions to satisfy the above requirements will have to be provided by redesigning/ regarding the drain. A skew crossing may be provided only where this is not possible.

3.5 Design of approach channel and tail channel:- Whenever regrading is required to be resorted, such regraded level at downstream end of trough shall be considered for computing the bed gradient of the tail channel. Usually the water depth available (at or near the starting point of approach channel and tail channel) above the nalla bed level for design flood for the return period mentioned in para No.3.2.4 shall be considered in the design. The ‘N’ value varying from 0.0225 to 0.03 depending upon the earth strata and 0.035 for rocky strata may be adopted. The main points regarding the design of the approach and tail channel are as under:

iv) Approach channel shall be designed with the average bed gradient of nalla on upstream side of the structure.

v) The depth of approach channel shall be considered equivalent to the depth of water available in nalla on upstream side of the structure for design flood.

vi) The tail channel shall be designed with depth of water in nalla on downstream of the C.D work for design flood and average bed gradient on downstream side of nalla where no regradation of nalla bed is involved.

4 Hydrology:- 3.2 For checking the overall safety of the structure, from foundation, scour and

free board considerations, the following shall be adopted 3.2 Hydraulic aspects:- 3.2.1 Hydrological studies:- 3.2.2 Design flood for drainage channel to be adopted for cross drainage works

should depend upon the size of canal, size of drainage channel and location of cross drainage. A very long canal, crossing a drainage channel in the initial reach, damage to which is likely to affect the canal supplies over a large area and for a long period, should be given proper weightage.

3.2.3 Methodology of Design Flood :- Methods to be adopted for determination of design flood corresponding to the catchment area of the drainage/ nalla are as under.

Sr.No. Catchment

area in sq.km. Method Remarks

1 Less than 25 Modified rational formula 2 25 to 518 Flood estimation reports of various

subzones published by the Director (Hydrology for small catchment) C.W.C. , New Delhi

For subzone 3(a) or 3(b) as the case may be.

Notes:

4. The cross drainage structure should be checked for a checked flood discharge of value 20% higher than the design flood given in the table in para 3.2.4.

5. In case of very steep slopes, in case of catchment area less than 25.00 sq.km. results arrived at by modified rational formula need to be care fully gone in to. If the modified rational formula gives odd results it needs to be checked by alternative computation such as sub zone report method (CWC). Same strategy should apply to C.A. exceeding 25.00 sq.kms.

6. For determining the observed flood, the field officer should go to the site more than two times in a year immediately after the flood occurs and observe the levels care fully. The value of “N” ( Coefficient of rugosity) shall

be adopted care fully and the correct observed discharge should be determined. This discharge should be further subjected to check by measuring through existing structure U/S and D/S of the point of crossing if any.

3.2.4 Frequency of Design Flood :- As per I.S. 7784 (Part-I) 1993, the design flood for drainage channel as given in para -7, cross drainage structures are divided in to four categories depending upon the canal discharge and drainage discharge. Design flood to be adopted for these four categories of cross drainage structure is given in table-1 of the code of practice.

TABLE FOR DESIGN FLOOD VALUES

Category of structure

Canal Discharge in

cumecs

(*) Estimated drainage discharge in cumecs

Frequency of design flood

A 0 to 0.50 All discharges 1 in 25 years B C

0.50 to 15.0 15.0 to 30.0 0 to 150 1 in 50 years

C 15.0 to 30.0 Above 150 1 in 100 years

D Above 30.0 0 to 150 Above 150

1 in 100 years As per note.2

Notes: -

2) The design flood to be adopted as mentioned in this table should in no case, be less than the observed flood.

2) In case of very large cross drainage structures where estimated drainage discharge is above 150 cumecs, the hydrology shall be examined in detail and appropriate design flood adopted, which should in no case be less than 1 in 100 years flood.

(*)This refers to the discharge estimated on the basis of river/nalla parameters corresponding to maximum observed flood level.

3.6 Wherever adjacent catchment areas are proposed to be diverted by means of a diversion channel, the design flood discharge for the diverted areas shall be worked out considering the total area for which the diversion is proposed to be made.

3.7 The H.F.L related to the design flood shall be completed at the center line of the canal and then H.F.L at downstream end of the trough shall be worked out as per bed gradient. The upstream H.F.L shall be considered as the downstream H.F.L + loss of head through drainage trough. The loss of head through trough (afflux) is taken as

h = { (V2 / 17.85) + 0.0152} { (A2/a2)-1} + hf Where, h = afflux in m.

V= Velocity in trough at entry. A = Unobstructed Sectional area of trough. a = Obstructed Sectional area of trough hf = Loss of head due to friction in transition portion (U/S & D/S) and in trough.

(a) For trough running partially the head loss shall be calculated as Hf = (Sf x L)

Where, Sf = V2 N2 / R4/3

R = Hydraulic mean depth = A/P A = Cross sectional area of trough in m2. P = Wetted perimeter of trough in m. L = Length of trough in m. Hf = Head loss through trough in m.

G = Acceleration due to gravity in m/sec. L = Length of trough in m. N = Coefficient of rugosity of trough

(b) Head loss in transition portion is calculated as per cl.8.6, IS: 7784 (part-1): 1993.

3.8 Hydraulic Design :- 3.8.1 Square or rectangular R.C.C trough or solid slab with abutments shall be

adopted for Super passage. RCC pipe may also be used depending upon discharge of drain and economic considerations. The section of trough should be determined by equating energies in the trough and the natural stream at maximum observed / calculated HFL. Generally RCC pipes should be provided upto 3 cumecs discharge and minimum diameter of pipe shall be 0.9 m. As a general guide line the size of trough may be adopted as required from drainage discharge consideration. Variation in size of trough shall be in multiple of 0.10 m.

3.5.2 The safety of trough against uplift shall be checked for the following conditions in case of submerged Super passage. However, this is not adopted. At this location canal siphon shall be proposed.

a) Canal at FSL and drainage troughs empty. b) Drainage at design flood level & Canal empty.

3.5.3 The permissible velocity for the design flood shall be adopted as 2 to 3 m/sec. And for check flood the velocity shall not exceed 3.5 m/sec. The check flood is considered as 20% more than design flood. The velocity for 25 years return flood shall be checked and it shall be ensured that the velocity is not less than 1.0m/sec.

3.5.4 For general, guide line the thickness of RCC member of the trough for various sizes of trough may be assumed as 0.30 m as minimum with top & bottom flange. The adequacy of thickness however shall be checked for structural design requirement and workability aspect.

3.5.5 Hydraulic design of canal. 3.5.5.1 Square / rectangular RCC barrel or trapezoidal section depending upon

discharge of canal or canal section and economic consideration. 3.5.5.2 Head loss in canal in super passage portion shall be calculated as per IS:

7784 Part-I, 1993. 3.5.6 Scour Depth:-

3.5.6.1 Mean depth of scour:- The mean depth of scour in meters below the check / high flood level may be calculated as per cl. 8.5 in IS : 7784 (Part-I)1993. 3.5.6.2 Maximum depth of scour for design of foundation:

The maximum depth of scour below the highest flood level (H.F.L) at obstructions and configurations of the channel should be estimated from the value of 'dsm 'on the following basis : For the design of floor protection works , for raft foundations or shallow foundation , the following scour values should be adopted. i) In a straight reach 1.27 dsm ii) At a moderate bend 1.50 dsm iii) At a severe bend 1.75 dsm iv) At a right angled bend 2.00 dsm NOTE:- The values of scour depth obtained as above may be suitably modified where actual observed data is available . Where concrete or masonry floor is provided under the works , scour condition is not applicable and the foundations are usually taken to about 1.5 m below the floor levels with suitable cut-off for the concrete or masonry floors . However where such a floor is not provided , foundations are taken to provide a margin below the anticipated scour level ( usually called grip length ) of about 0.33 times the maximum depth of scour . (I.S: 7784 [PART-I] - 1993)

3.5.7 The exit gradient shall be calculated with the cut off provision as above and it shall be ensured that the value not less than as given below. Clay 1 in 4 Single 1 in 4 to 5 Coarse sand 1 in 5 to 6 Fine sand 1 in 5 to 6 Fine sand 1 in 6 to 7

3.5.8 When slab culvert is provided, the minimum free board between the lowest point of super structure and the HFL of drain shall be 60 cm (IS 7784 – Part-I, Page 1, Table No. 2)

5.0 Structural Design:-

Structural design shall be carried out as per cl.6.2 of IS : 7784 ( part-2/sec-2): 2000 and IS : 456, 2000.

5.1 Structural stability of the trough shall be checked for the following condition:-

c) Canal at FSL & troughs dry. d) Canal dry & drainage at design HFL (including afflux) e) If super passage is used as road then loading due to vehicle (IRC)

shall also be adopted.

5.2 The mix of concrete of various RCC/PCC components shall be adopted as under:

Sr.N

o. Grade of Concrete

Where to be used

1 M-25 (RCC) RCC troughs, breast walls, staunching ring, cut-off walls. 2 M-15 (PCC) Coping on masonry wing walls (if adopted), Pucca floor.

Leveling course for foundation for RCC troughs. 3 M-10 (PCC) Buoyancy concrete, foundation of masonry wing wall, if

adopted. 5.3 The permissible stresses in concrete and steel shall be adopted as under. Concrete (Table 21 of IS: 456-2000)

Sr. No.

Permissible stress

M-25 M-20 M-15

1 Bending 85 kg/cm2 70 kg/cm2 50 kg/cm2 2 Direct 60 kg/cm2 50 kg/cm22 40 kg/cm2 3 Bond 9 kg/cm2 for plain

bars in tension 8 kg/cm2 for plain bars in tension

6 kg/cm2 for plain bars in tension

Note : In case of deformed bars confirming to I.S. 1786 the bond stress given above may be increased by 60% (Cl.no. B.2.1.2 I.S. 456-2000) for bars in tension and the same shall be increased by 25% for bars in compression.

Shear: As per clause B-5 of IS: 456-2000. With shear Reinforcement:- When shear reinforcement is provided the

nominal shear stress Tc in beams shall not exceed Tcmax given below For slabs Tv shall not exceed half the value of Tcmax given below:- ( I.S : 456 - 2000 Table -24 , page -85 )

4.4 Reinforcement:- The main bars, distribution and temperature bars shall be high yield strength deformed bars (H.Y.S.D / TMT) conforming to IS : 1786, 1985. The stresses for above bars shall be adopted as per Table-2 of IS: 3370 Part-II, 1965.The detailing of reinforcement shall be done as per IS: 13920 under seismic condition .

4.5 Minimum Reinforcement:- (As per IS 3370 (Part-II)- 1965, For mild steel) 4.5.4 The minimum reinforcement in each of two directions at right angle shall have

following area in that direction.

a) For sections upto 100 mm. thicknesses.

0.3 percent of the Gross sectional area of concrete.

b) For section between 100 mm. to 450 mm thickness.

Linearly varying from 0.3% for 100 mm. thick section to 0.2% for 450 mm. thick section.

c) * For sections greater than 450 mm. thickness 0.2% of cross sectional area.

* In concrete sections of thickness 225 mm. or greater two layers of reinforcing steel shall be placed one near each face of the section to make up the minimum reinforcement specified above. Where the thickness of the section exceeds 450 mm. thickness of 450 mm. shall

be used in determining the temperature or minimum reinforcement.

4.5.5 The minimum reinforcement specified above may be decreased by 20 percent in case of high yield strength deformed bars conforming to IS : 1786-1985.

4.5.6 Where joints are provided in structures, the temperature or minimum reinforcement shall be provided as per IS code.

C. The minimum reinforcement for canal structures shall be 12 mm. Dia @ 30 cm. in both ways in all exposed faces, where reinforcement is placed in a single layer and 12 mm dia @ 30 cm. in unexposed faces with two layer reinforcement in both ways.

D. Single layer reinforcement. 1) Reinforced concrete lining 10 cm. and less in thickness

with discontinuous wire fabric reinforcement and weakened planes at 360 cm to 450 cm center.

0.10 percent.

2) Slab and lining not exposed to freezing temperature or direct sun with joints not exceeding 900 cm.

0.25 percent

3) Slabs and linings exposed to freezing temperature or direct sun with joints not exceeding 900 cm.

0.30 percent

4) Slabs and linings exceeding 900 cm between joints. Category (2) above Category (3) above

0.35 percent 0.40 percent

5) Walls and other structural members. Total percentage of horizontal reinforcement to be equal to the sum of those required for both faces as determined below.

As per double layer reinforcement

C. Double Layer reinforcement:- 1) Face adjacent to earth with joints not exceeding 900 cm. 0.10 percent 2) Face not adjacent to earth nor exposed to freezing

temperatures or direct sun and with joints not exceeding 900 cm.

0.15 percent

3) Face not adjacent to earth but exposed to freezing temperatures or direct sun and with joints not exceeding 900 cm.

0.20 percent

4) If member exceeds 900 cm in any direction parallel to reinforcement add to the reinforcement requirement in that direction because of the increased length.

0.05 percent.

5) If a slab is fixed along any line, double the dimension from line of fixity to free end to determine whether reinforcement is within the less than 900 cm or more than 900 cm percentages shown above (1),(2), (3) and (4) above

shown above (1),(2), (3) and (4) above

N.B . The percentages indicated are based on the gross cross sectional area not including fillets of the concrete to be reinforced. Where the thickness of the section exceeds 40 cm a thickness of 40 cm should be used in determining the temperature or minimum reinforcement. 4.5.4 Minimum shear reinforcement:- As per clause 26.5 1.6 of IS 456-2000

(P.48) minimum shear reinforcement in the form of stirrups shall be provided such that {Asv / (b x Sv) } {0.4 / (0.87 x fy)} Where, Asv = total cross sectional area of stirrup legs effective in shear Sv = Stirrup spacing along the length of the member. b = breadth of the beam or breadth of the web of Flanged beam. fy = Characteristic strength of the stirrup reinforcement in N/mm2 which shall not be taken greater than 415 N/mm2.

4.6 Minimum cover to reinforcement shall be 50 mm for all faces of component of super passage.

4.7 General requirement of reinforcement (Cl. No. 26 IS: 456-2000) 4.7.1 Development length of bars. (Cl. No. 26.2.1 I.S. 456-2000)

The development length Ld is given by Ld = ( x s) / (4 x Tbd )

Where , = Nominal diameter of bar s = Stress in bar at the section considered at design load. Tbd = design bond stress as per Cl.no. 26.2.1.1 I.S. 456-2000

4.7.2 Spacing of reinforcement:- a) The horizontal distance between parallel main reinforcement bars

shall not be more than three times effective depth of a solid slab or 300 mm, whichever is smaller.

b) The horizontal distance between parallel reinforcement bars provided against shrinkage and temperature shall not be more than five times the effective depth of a solid slab or 450 mm, whichever is smaller. (As per clause 26.3.3 of I.S. 456-2000 Page 46)

c) The maximum spacing of shear reinforcement measured along the axis of the member shall not exceed 0.75d for vertical stirrups and d for inclined stirrups at 45 Degree, where d is the effective depth of the section under consideration. In no case shall spacing exceed 300 mm. (Clause 26.5.1.5 of IS: 456 – 2000 P 47/48)

5.6 Wing walls (RCC) M-25 :- 5.7 The wing walls shall be provided straight with a splay of 2:1 on u/s & 3:1 on

d/s side or as per site condition and the slope of the wing wall shall match the outer slope of canal bank. The length of upstream and downstream wing walls shall be provided as per requirements on the basis of width of canal at the bank level. If necessary return wall may be provided thereafter. The top of the wing walls shall be kept at minimum 0.30 m. above the AHFL / HFL of the drain.

5.8 The top width shall be kept 0.30 m. 5.9 Weep holes in the wall shall be provided at spacing of 2.5 m c/c both ways in

staggered fashion with the bottom most row at 15 cm. above the nalla bed

level. 10 cm asbestos cement pipe shall be provided for weep holes with perforated jali both the ends of weep holes.

5.10 The wing walls sections shall be checked for canal full and nalla dry condition, considering back fill as saturated. No passive resistance shall be considered from the nalla side. Live load and surcharge affected if any shall be considered.

5.5 If the foundation of wing walls requires to be taken deeper for consideration of scour, the minimum depth of foundation for wing wall shall be taken 1.5 m. from invert level of trough and for remaining depth up to scour RL a concrete key shall be provided along the upstream face of the wing walls. The bottom width of key shall be kept 0.30 m.

8.0 Miscellaneous:- 8.1 Joints:- Joints shall be provided across and along the trough length. The

maximum spacing of these joints, in either direction, shall be limited to 20 m. 300 mm PVC water stops should be provided all around the trough at all joints.

8.2 In the case of drainage troughs resting on compressible soils, collars encircling the plain joint should be provided.

8.3 At the junction of troughs with wing walls and trough with pucca concrete floor P.V.C. water stops shall be provided.

8.4 Staunching Rings: When the exit gradient as specified in para 3.5.7 is not satisfied the staunching ring of 30 cm. width and 90 cm. depth may be provided as per requirement on SR and IP side. Nominal reinforcement shall be provided.

8.5 Pucca Floor:- The protection to be provided shall be as under: 30 cm. thick pucca concrete floor of M-15 grade with minimum temperature reinforcement at top shall be provided beyond the end of RCC troughs up to the end of wing walls. Beyond the end of wing walls 30 cm. thick pucca rubble pitching in CM 1:5 shall be provided. The pitching shall be provided up to a length L = 2(D), where D = Depth of flow in the nalla at design flood or 5 m whichever is more. Weight of stone shall be as per IS:8408,1994.

8.6 Pitching:- Rubble pitching of 30 cm thickness shall be provided on the canal outer slope on the upstream and downstream of the structure. The length of pitching, along the canal banks shall be taken upto the ground level equal to afflux H.F.L. plus 0.5 m or 30 m whichever is less.

8.7 Cut water and ease water:- The middle walls of the troughs shall be provided with semi circular cut water and ease water at the entry and exit.

8.8 Canal Lining;- The thickness of canal lining near the structure shall be increased to double the lining thickness in bed and sides upto a length of 5 m on either side of CD work. Nominal reinforcement of 12 mm. at 30 cm c/c both ways and both faces shall be provided. High quality polysulphide sealants in the lining joints should be provided commencing at a distance of 30 m upstream of the crossing and continuing 30 m downstream.

8.9 Back filling behind end wall of trough and wing wall. For back filling behind end wall of trough, more pervious material shall be placed at bottom and less previous material at top (in 1.5 m. height). The back fill material shall be compacted at OMC with pneumatic compactors. Minimum width of the trench shall be kept 0.45 m. Filling shall be done in a minimum slope of 0.5 :1. For back filling behind wing walls more previous and free drainage material shall be preferred. The back fill material shall be well compacted with pneumatic compressors. Minimum width of the trench shall be 0.6 m. Filling shall be done in a minimum slope of 0.5 : 1 in soil and 0.25 : 1 in rock.

6.10 Box culvert (M-25) : Due to the requirement of continuity of SR & IP of the branch canal, to pass SR/IP over the Super Passage road over solid slab type / box culvert shall be proposed. The clear height between formation level of SP & soffit of top slab is kept as 4.0 m for traffic.

6.10.1 Parapet wall : RCC m-25 perforated parapet of 0.8m high & 0.15m thick having kerb of 0.225 m X 0.30 m is to be provided on top slab of box culvert.

6.10.2 Approach slab : RCC M-25 approach slab 5.0 m on either side of box culvert shall be provided on both the end wall of the box culvert. One end of approach slab rest on the wall of box culvert and other end on the approach embankment

. 7.0 Design Note

Typical design note of super passage is at Annex-II. Typical Drawings of Super Passage ( Annex-III )

(1) Typical drawing of super passage at ch. 75210 on Saurashtra Branch Canal.

(2) Typical drawing of super passage at ch. 76935 m on Limbdi Branch Canal.

(3) Typical drawing of super passage at ch. 6920 m on Jhinjuwada Branch Canal.

Annex - I REFERENCES

The following references are used in the design of canal syphon. 1. IS: 7784 (part-I)-1993 "Code of practice for Design of Cross drainage

works." 2. IS: 7784 (part-II)-2000 "Code of practice for Design of Cross drainage works,

Specific requirements: section-2, Super passages 3. IS: 3370 (part-I to IV)-1965/67 “Code of practice for Concrete structure for

storage of liquids.” 4. IS: 456-2000 “Code of practice for Plain and Reinforced concrete.” 5. IS: 1893-2002 “Criteria for earthquake resistance design of structures.” 6. IS: 13920-1993 “Code of practice for ductile detailing of RCC structures

subjected to seismic forces." 7. IS: 6403-1981 “Code of practice for Determination of allowable bearing

capacity." 8. IS: 458-1988 “Code of practice for Concrete pipes (with & without

reinforcement).” 9. IS: 783-1985 “Code of practice for Laying of concrete pipes." 10. IS: 8009-1976 “Code of practice for Settlement.”

*****

Annex-II DESIGN NOTE OF TYPICAL SUPER PASSAGE

AT CH. 75210 m ON SAURASHTRA BRANCH CANAL (22.00 m c/c span length )

1.0 INTRODUCTION (History of structure location etc.)

The Govt. of Gujarat has under taken the construction of Sardar Sarovar (Narmada) Project. The Saurashtra Branch Canal off take @ ch. 263.20 km. of Narmada Main Canal near Kadi. The design discharge of S.B.C. is 400.125 cumec with bed width of 35.5 m & full supply depth of 5.75 m. The bed gradient of S.B.C. is 1:10000. Canal data as well as Road / Drain data received from Superintending Engineer, Narmada Project Canal Circle No.7, Surendranagar. The Saurashtra Branch Canal travels from 0.0 to 104.406 km. During this, it crosses numbers of various categories of roads, rivers, kotar, Nalas etc. for which suitable type of structures are required to be provided. LOCATION OF STRUCTURE: -

The Saurashtra Branch Canal crosses Drain / Unclassified Village Road joining villages Adalsar to Kesaria at ch. 75.210 km. at an angle of 900. An additional Drain / road braidge is proposed by F.O. F.O has proposed square crossing.

2.0 DATA : -

A CANAL DATA

1. Chainage 75.210 km 2. Whether canal is flumed or unflumed Unflumed. 3. Enhanced discharge 400.125 Cumecs. 4. Canal bed level 24.656 m 5. Full supply level. 30.406 M. 6. Full supply depth 5.75 m 7. Canal bed width 35.50 m. 8. Velocity 1.481 m/s. 9. Canal bed gradient 1 in 10000 10. Canal side slopes 2:1 11. Whether canal is lined or unlined Lined. 12. Type of lining M-15 Grade RCC lining 20 cm thick On bed and on side slopes. 13. Coefficient of rugosity (Canal) 0.018 14. Head loss 1.0 cm 15 Top of lining 32.056 m. 16 Top of bank level 33.50.m. 17 Ground level (LHS) 35.356 m. B ROAD / DRAIN DATA 1. Type of crossing Square 2. Formation level of existing Drain / road 35.356 m. 3. Proposed formation level of Drain / bridge. 35.20 m. 4. Type of loading IRC class A. 5. Clear road width between kerbs. 7.50 m 6. Classification of road. UVRB 7. Catchments area 7.0 sq.km (FO furnished 1.41 sq.km) 8. Design flood discharge 20 cumec 9. Stream bed level (NBL) 35.20 m 10. Observed HFL 36.90 m 11. Source of information of HFL Marked on Rly. Culvert no 27

12. Bed gradient 1 in 1300 13 Seismic zone zone-III

3.0 HYDRAULIC DESIGN (IS: 7784,Part-I,1993, IS: 7784,Part-II, Sec-2, 2000,IRC:

codes)

3.1 WATER WAY :- The field office had furnished 1.41 sq.km catchment area. This office marked catchment area on S.O.I. sheet is about 7.0 sq.km. The 100 year return period flood is worked out as 108 cumec & check flood is 130 cumec as per Rational method RBF-16.But considering type of topography, capacity of the culvert no.27 constructed below Rly.line (for inflow of flood water),capacity of the culvert constructed below MDR(for outflow flood water),size & formation level of SP constructed @ ch 75855 on SBC etc the Unit leader had concluded & suggested that the proposed structure should be designed for passing 20 cumec flood discharge.Considering this discharge,OHFL & Formation level 7.95 m x 1.70 m + 0.30 m(free board) size trough section is adopted. Longitudinal slope of 1 in 1300 is provided from start point to end point of SP / UVRB by adjusting the thickness of wearing coat provided over the bottom slab of all components of SP / UVRB.

3.2 Length of bridge / span Unflumed SP/Bridge having a total length of 66.00 measured along the centre line of

bridge from end to end of bridge deck. However, the span of this SP/ UVRB is proposed as 22.00 m. c/c as per the in house type design. Three equal spans are proposed. The total length of bridge will be 66.00 m.

3.3 Head loss Permissible head loss of 10 mm is considered for design of this sp/bridge. The pier

and abutment are provided parallel to the direction of flow of S.B.C. 4.0 DESIGN LOADING

The Live load for design of super structure and sub structure ( as stipulated corresponds to IRC Class - A, Two lanes loading Irrigation Department letter No. NMD-1830-2712-298/51 (K-8) vide Govt. of Gujarat dated 7.8.1980) which ever produces the worst effect, has been considered.

RCC design is made for moderate exposure condition. However, the Grade of concrete should be used as per the environment and exposure conditions prevailing at the site and in accordance with IS: 456-2000. Good quality of Ordinary Portland Cement (OPC) of grade 43/53 is to be used. But if the environment or exposure conditions demands, then special type of cement shall be used.

5.0 DESIGN OF SUB-STRUCTURE 5.1 DESIGN OF FOUNDATIONS. The designs of foundation of piers, abutments and wing walls are based on the

engineering properties (at Ch. 75855m) of the foundations strata received from the Superintending Engineer, Narmada Project Canal Circle No.7, Surendranagar, vide his letters No. (1) NPCC-7/PB-1/Str.Data/75210-UVRB/2515 dated 13/07/2006. (2) NPCC-7/PB-4/Esti/75210/3089 dated 12/09/2006. (3) NPCC-7/PB-4/Str.data/75210/3657 dated 14/11/2006. Open type of foundations are proposed. The proposed F.L.s. & the maximum allowable pressure at F.Ls. adopted for design purpose are as under:

----------------------------------------------------------------------------------------------- Sr.No. Components Proposed Foundation Soil Strata Max. Stress level in m. adopted

(t/m²) -----------------------------------------------------------------------------------------------

1 Abutments 28.50 SP/CH 30 2 Piers 22.10 SP 27 3 Wing walls 30.65 SP/CH 25

5.2 ABUTMENTS

The fopundation level is kept at R.L. 28.50m for both L.H.S. and R.H.S. abutment which is 6.856 m below ground level for L.H.S. and R.H.S. abutment. The strata available at foundation levels are SP and CH type for L.H.S. and R.H.S. abutments. The CH type soil at foundation level shall be removed and replaced with gritty / CNS soil &thoroughly compacted to achieve 95% of the corresponding standard proctor maximum dry density. The maximum allowable stresses at F.Ls. has been kept limited to 30 T/Sq.m. The design is based on zero tension condition at foundation.

2.2 5.2.1 ABUTMENT SECTION

The abutment shall be of R.C.C. type with M25 concrete mix. The section of the abutment stem at base is designed by considering the active and passive earth pressure on abutment. To consider the effect of live load as backfill, the equivalent height of surcharge of earth is taken as equal to 1.20m according to clause 710.4.4 of IRC:78-2000. The design loads are taken as per IRC:6 (Section II-2000). The RCC design of abutment is carried out as per the Column Theory for combined axial and bending given under clause 306.5 or IRC:21-2000(SEC.III). The width of the abutment stem section are kept 0.80m at top of 1.00m at bottom for L.H.S. and R.H.S. abutment, giving a batter only on canal side, which the backfill face of the abutment is kept vertical. The length of the abutment is provided as 8.60 m with square ends

5.2.2 ABUTMENT CAP M-30

The abutment cap is provided 1.3m wide, 8.60 m long and 1.0m thick in M-30 concrete grade. The cantilever portion shall be 0.50 m on canal side only and the other end shall be flushed with the abutment face. The reinforcement is provided as per Corbel Theory.

5.2.3 DIRT WALL The dirt wall (M25) having a length of 8.60 m. height of 2.293 m and a thickness of

0.4m is provided to rest on abutment cap. It is provided monolithic with abutment.

5.3 PIER

The foundation level is kept at R.L. 22.10m for pier which is 2.556m below CBL. The strata available at F.L. is SP type. The maximum allowable stress at F.L. has been kept limited to 27.00 T/Sq.m. The design is based on zero tension condition at foundation. 5.3.1 PIER SECTION The pier shall be of RCC type with M25 concrete m,ix. The wdth of pier section are

kept 0.80m at top and 1.0m at CBL, with a uniform batter on both the faces of pier section. The straight length of the pier is kept to 5.60 m with semicircular ends of cut

& ease waters having a radius of 0.40m at top and 0.50 m at CBL. The design loads are considered as per IRC:6 (Section-II). The RCC design of pier section at base of the stem is carried out as per Column Theory for combined axial & bending given under clause 306.5 of IRC 21:2000, section-III.

5.3.2 PIER CAP

1.80m wide and 1.0m thick pier cap in M-30 concrete grade is provided at top and will follow the shape of pier. The cantilever portion is kept 0.50m uniformly around the whole pier section. The reinforcement is provided as per Corbel Theory.

5.4 R.C.C. WING WALLS ADJONING ABUTMENT

This wing walls is provided to protect the earth fill beneath the open trough & behind the abutment. This wing wall is designed as cantilever R.C.C. retaining wall in M-25 grade. The footing of the wing wall adjoining Abutment is kept at RL 30.65m for this additional super passage cum UVR bridge. The foundation is kept at 4.706 m & 1.406 m below G.L. & key lining R.L.respectively. The wing wall is kept horizontally level at R.L. 35.500m for a length of 1.50m in the direction of flow of canal & then kept sloping in 1.5:1 up to the R.L. 33.80m The width of footing is kept at 2.75 m. The top & bottom thickness of stem is 0.23m & 0.45m respectively, where as the bottom slab thickness is provided 0.45m. The maximum allowable stress at F.L. has been kept limited to 25.00 T/Sq.m. The back filling around abutment footing just beneath the part of wing wall foundation is to be filled with well compacted earth to achieve 95% of the corresponding standard proctor maximum dry density. This compacted earth is to be overlaid by 300 mm thick. M-15 plain cement concrete to be finally overlaid by the 150 mm leveling coarse of the footing as shown in the drawing. Proper compaction shall be done particularly near abutment stem in wing wall length before laying foundation. The safe bearing capacity of such made up soil shall be ascertained before laying the foundation of wing wall. The design is based on zero tension condition at foundation.

5.5 R.C.C. WING WALL ADJOINING THE BOX CULVERT (GUIDE WALL)

This wing wall is provided to guide the floodwater and to protect the earth of spoil

bank.This Wing Wall shall also be of cantilever type RCC retaining wall with M25 concrete grade. The length of wall is provided 6.00 m on u/s and d/s of additional super passage cum UVR bridge in continuation to the closed box with a 3:1 converging & diverging splay respectively. The wing wall is kept sloping from R.L. 39.78 to R.L. 37.500 in 4.00m length and kept horizontally leveled at R.L. 37.500 m for the next 2.0m length and then returned from there for 2.0m length in the direction of flow of canal. The thickness of wall section is kept to 0.30m at top. The bottom thickness of stem is kept varying from 0.7m near the closed box to 0.35m at the horizontally leveled section of wing wall. The vertical face is kept aligned whereas the earth face is kept at variation. The section of Wing wall at base of stem is designed by considering active and passive earth pressure with the relevant seismic forces to be considered for the Zone-III. The returned wall & horizontally leveled wall are kept uniform sectioned.

5.5.1 PUCCA FLOOR BETWEEN COMPLEMENTRY WING WALL

The 300mm thick pucca floor between complementary wing wall on U/s and D/s of proposed additional super passage cum UVR bridge is provided in 6.0m length. The pucca floor is provided with temperature reinforcement and is keyed into the cantilever wing wall. A 1.2m deep cut off cum toe wall is also provided at the entrance.

5.6 STOPPER BLOCK

Stopper block as anti sliding arrangement of super structure is provided to safeguard the deck slab super structure against earth quake forces. The stopper block of size 500 mm x 750mm and having 1200mm length for piers and 600mm length for abutments are introduced. It is provided on pier/abutment cap besides outer main girders on both the sides.

6.0 SUPER STRUCTURE

RCC M-25 grade solid slab type super structure having 22.0 m c/c span & 7.50 m carriage way width is provided. Super structure comprises of three main girders, eight cross girders and a deck slab. The type design is adopted for the effective span length of 21.40 m c/c between the bearings and an overall span length of 22.00 m c/c. 6.1 MAIN GIRDERS (M25)

Two main girders at 2.80m c/c are provided as main members of super structure, having depth of 1.80m including the thickness of deck slab. The thickness of the rib of main girder is 250 mm with 600 mm x 475 mm bulb at bottom.

6.2 CROSS GIRDERS (M25)

There are two end cross girders and four intermediate cross girders spaced at 1/5 th of the effective span. (c/c span length - 0.8m). The depth of the cross girders including thickness of deck slab is kept as 1.325m (to accommodate the thruston antisliding arrangement on pier/abutment caps). The rib thickness of cross girder is kept 250mm.

6.3 DECK SLB

RCC M25 deck slab is 240 mm thick for supported portion between the two outer girders and for cantilever portion it is 200 mm thick at parapet end and 350 m m thick at the outer face of the outer girders.

6.4 WEARING COAT ( RCC M15 )

Concrete wearing coat is provided with a camber of 1:48. The average thickness provided is 50 m m in two layers. The thickness of wearing coat is 100 mm and 50 mm respectively at the centre and at the kerb.

6.5 BEARINGS

The bearing shall be of elastomer (Neoprene) type. The size of 500mm x 360mm x 99mm is provided. A recess of 6mm shall be provided on the top of abutment/pier cap to accommodate the bearings firmly. It is provided below each main girder. 6.6 KERB AND PARAPETS

The R.C.C. M25 Kerb having a section of 0.225 m x 0.300m is provided continuously along the length of the bridge and at the both extreme ends of carriageway on the cantilevers of the deck slab. The Solid RCC M25 Parapet 1.70 m

high and 0.275m thick is to be provided to rest on top of the Kerb.

7.0 BOX CULVERT

Due to the requirements of continuity of SR / IP of the branch canal, to pass SR / IP over the SP / UVRB, road over solid slab type Box culvert having two barrels of size 3.75 m x 4.0 m are provided.The clear height between formation level & sofit of top slab of barrel is kept as 4.0 m for traffic of the UVRB. The SR/IP road level on the box culvert is 39.78 m having wearing coat of average 0.08 m thick.The clear road width for SR/IP is 7.50 m. The SR / IP are raised from TBL RL 33.50 m to top road level RL 39.78 m on Box culvert by 1 in 30 longitudinal slope & having 2 : 1 side slopes of compacted earth fill of embankment.

The Box culvert is designed for (i) Self weight (ii) Live Load from super structure (iii) Earth pressure (iv) Earth weight on cantilever projection (v) Earthquake effect. The section works out as 0.50 m top slab, 0.50 m end wall,0.45 m inner wal,0.55 m bottom slab,0.55 m cantilever slab length & 0.90 m cut-off wall.

7.1 APPROACH SLAB

RCC M-25 type approach slab, 5.0 m long, 8.25 m wide & 0.15 m thick is provided on both the ends of wall of box culvert. One end of approach slab rest on the wall of box culvert and other end on the approach embankment.

7.2 PARAPET WALL

RCC M-25 perforated parapet 0.8 m high and 0.15 m thick (As per R & B standard) having kerb of 0.225 m x 0.30 m is provided on solid slab of box culvert length as well as on approach slab length.

7.3 WATER SPOUTS

For the drainage of rain water from the wearing coat surface of the carriage way G.I.water spouts having 100 mm diameter are provided at 2.0 m interval on each side .i.e. 4 nos.in each span. 8.0 OPEN TROUGH

Due to the raising of SR / IP level from RL33.50 m to RL39.78 m having 2:1 side slopes of the embankment, the center line of SR / IP are shifted from its original alignment. Due to the shifting of alignment of SR / IP,A extended open trough having two barrel is provided between dirt wall of the abutment and Box culvert. Height of the walls of the open trough is provided 2.50 m from the formation level. One end of slab of the open trough is rest on Dowel Bracket of dirt wall & other on the compacted earth fill embankment.

The open trough is designed for (i) Self weight (ii) Water pressure & no earth pressure (iii) Earthquake effect etc. The section works out as 0.30 m inner wall,0.30 m end walls,0.35 m bottom slab, outer width of trough is 8.55 m. (3.825 x 2.0 + 0.30 x 3).

9.0 ANCILLIARY WORK

9.1 JOINTS

9.1.1 Joints between canal lining and piers

The joints between the canal lining and the piers at CBL shall be filled with P.V.C. (12 mm thick) sheet at bottom and elastomeric sealant at top around the whole pier to avoid leakage at C.B.L. 9.1.2 430 mm wide & 1.5 mm thick copper sheet is provided all-round the 20 mm

expansion joints provided at the junction of various components, to avoid leakage from joints.

9.1.3 Lining at the bridge crossing

At the bridge crossing. RCC lining having 20 cm thickness on canal bed and 25 cm thickness on side slopes with 12mm dia (HYSD) bars @ 30 cm c/c both ways on the top and bottom of the lining for a length of 15 m on either side of bridge shall be provided. 9.2 PROTECTION WORKS

0.30 m thick Pucca rubble pitching is provided on slopes(canal side) of embankment for raising the SR/IP level & Embankment on side of open trough. 0.30 m Dry rubble pitching is provided on Bed & Side slopes in u/s Launching apron & d/s Launching apron in the drain for a length of 10.0 m u/s & 10.0 m d/s.

10.0 DESIGN PARAMETERS

Design of all components i.e. Superstructure, Substructure u/s & d/s Open trough, Box culvert & Wing walls have been carried out in accordance with relevant provisions of IS 456-2000 with moderate exposure condition and as per seismic zone III of IS : 1893 –2002.

CONCRETE: M-25 grade concrete is to be used for RCC work while M-15 grade of concrete for PCC work below pier, abutments, open trough, box culvert & wing walls.

Allowable stresses in concrete are as under : Grade of concrete M-25 Bending compression 8.5 N / mm2

Direct compression 6.0 N / mm2 STEEL :-

High Yield strength deformed bars as per I.S 1786 –1985 (Fe- 415) Is to use for all works.

PERMISSIBLE STRESS: - (I) Direct tensile stress 150 N/mm2 (II) (a) Bending tensile stress 150 N/mm2 (Water face) (b) Bending tensile stress 190 N/mm2 (Earth face) (III) Tensile stress in shear 175 N/mm2 (Thickness of member > 225 mm.)

(IV) Compressive stress 175 N/mm2

The minimum reinforcement in walls / floors shall be as per I.S. 3370 Part –II. The minimum cover to reinforcement for parts of members in contact with water shall be 50 mm. Laps /Bends & size of bars shall be in accordance with relevant provision I.S. 456 – 2000, and IS-13920-1993.

11.0 BACKFIL

The soil to be used for the backfill shall be selected from the non expansive, preferably gritty type and shall be compacted at the optimum moisture content to achieve 95% of the corresponding Standard Proctor Maximum Dry Density.

Type of Structure: SUPER PASSAGE (SP) Design Steps

I. Verification of data: - Data received are to be as per standard data format

II. Validation of data: - 1. Parent and off taking canal data as per approved CR planning 2. Soil data shall be at the location of structure site

III. Determination of safe bearing capacity:- 1. As shear criteria as per IS: 6403 2. As per settlement criteria as per IS: 8009

IV. Type of structure:-

Reference as per guide line as for SP (clause 1.0 page no-1)

V. Hydrology :-

Refer guide line for SP cl.3.0-page -2

VI. Hydraulic Design:-

Refer guide line for SP cl.3.5-page -5

VII. Structural Design :-

Refer guide line for SP cl.4.0-page -6

VIII. Wing Walls :- Refer guide line for SP Cl.5.0 -page -10

IX. Miscellaneous :-

Joints, Staunching Ring, Pucca Floor, Pitching, cut water and ease water, Canal lining, back filling, Box culvert, Parapet wall, Approach wall etc.

Refer guide line for SP cl.6.0-page -10

Guide lines for design of cross regulators on branch canals of Sardar Sarovar ( Narmada )

Project.

1.0 GENERAL :

A cross regulator is a regulating structure located across a canal for regulating the depth of

water on u/s side and also for regulating the quantity of water passing through the cross regulator. It

shall be located as dictated by transient studies to control water elevation in the canal within set limit of

fluctuation during normal and emergency operation, to store water in the system to meet the

requirements of the off-takes during a shut down for a out flow discharge and to isolate any short

reaches or major works for facility of regulation particularly those having potential for significant

failure. In the even of breach in canal bank, cross regulators can be used to limit the volume of

escaping water to that confined between two cross regulators and prevent the entire canal from being

emptied.

2.0 LAYOUT ;

The layout will depend on the type of the cross regulator to be adopted and whether it is to be

combined with other structure viz. Fall, bridge etc. The main components are:-

i) Control structure with an operating platform for regulating the discharge.

ii) U/s & D/s transition walls for smooth entry and exit.

iii) Energy dissipation arrangements.

iv) U/s and D/s floor with cut-off walls to take care of uplift pressure and exit gradient

v) Float well.

3.0 Hydraulic Design :

3.1 Water way : Linear water-way of the cross regulator shall be so provided that the head loss

does not exceed 5 cms. which is usually provided in overall planning of the C.R. of Branch Canal.

Head loss shall be calculated as 0.5 times the difference in velocity head at cross regulator opening and

in the canal on the downstream. However where the gate size is standardized, the water –way should

be suitably adjusted.

3.2 Crest : 3.2.1 Crest level : A hump of minimum 0.15 m. and max. of 40% of u/s FSD but not exceeding

0.5 m shall be provided ( above u/s or d/s CBL whichever is higher ).

3.2.2 Hump : Hump shall be provided as follow :

1) Canal invert shall be kept horizontal between u/s nose of pier to its d/s end.

2) Canal bed shall be gradually raised between u/s CBL and hump level in the

length of u/s transition.

3) a) For discharges higher than 10 cumecs, the slope of d/s glacis shall be kept

2:1 ( Clause 3.2.1 of I.S. 7114 – 1973)

b) For discharges lower than 10 cumecs, the slope of d/s glacis shall be kept

2.5.:1 ( Clause 3.2.2. of I.S. 7114 – 1973)

3.3 Cistern & Cistern Level : Narmada Branch Canal is to be operated on volume control

concept, with a series of pools. Sufficient water depth will be available d/s of the gate. Hence

for various gate opening available tail water depth would be much more than required for a

perfect jump. Therefore only submerged jump will occur. However, during initial filling of

canal, when there is no water on d/s of gate, energy dissipation is required for a discharge up

to which submerged jump will occur. The jump would normally be weak and of less length.

There is no need to provide a stilling pool or other arrangement for energy dissipation.

However, a nominal stilling basin of 0.5 m depth below d/s CBL shall be provided. End of

cistern shall be joined with d/s CBL in a gradient of 1 in 5.

3.3.1 Cistern length : The cistern shall be provided up to the end of d/s transitions and checked

for exit gradient ( Para 3.5 ).

3.4 Cut-off walls :

3.4.1 U/s cut-off : U/s cut-off shall be provided at starting of u/s transition wall. Depth of u/s cut-

off wall shall be maximum of the following.

i) Depth of u/s cut-off = d1/3 + 0.5 m

Where d1 = u/s F.S.D. in m.

ii) As per U.S.B.R., U/s cut-off depth = 0.69 √ d1.

Minimum 0.6 m to be provided ( d1 = u/s FSD in m.)

The minimum thickness of cut-off shall be 0.3 m . Fillets of minimum 0.15 m x

0.15m size shall be provided at the junction of cut-off with the floor.

3.4.2. D/s cut-off : D/s cut-off shall be provided at end of D/s transition wall. Depth of d/s cut-off

wall shall be maximum , of the following.

i) Depth of d/s cut-off = d/2 + 0.5 m (1)

(I.S. 6531 – 1972 Cl. 3.7.2.2 ) where d = d/s FSD in m.

ii) As per U.S.B.R.D/s cut-off depth ( in MKS system )

= 0.69 √ d 1 ( d = d/s FSD in m).

Minimum thickness of cut-off shall be 0.3 m and fillets of minimum 0.15 m x 0.15 m

size shall be provided at the junction of cut-off with the floor.

3.4.3 Generally minimum depth of cut-off in u/s and d/s shall be 1.5 m and 2.0 respectively below

corresponding floor level.

3.4.4 Intermediate Cut-off :

3.4.4.1 U/s intermediate cut-off shall be provided at the U/s edge of u/s stoplog groove and

its depth shall be 1.5 m from hump level.

3.4.4.2 D/s intermediate cut-off shall be provided at the d/s end of piers and its depth shall

be same as d/s cut off depth.

3.5 Exit Gradient : As per clause 6.1 of I.S. 7114 – 1973, the structure should be checked for safe

exit gradient in accordance with accepted theories and adequate length of floor and d/s cut-off

wall should be provided for safe values of exit gradient. As exit gradient depending on type of

soil and importance of structure may be provided for ordinary condition. If the overall length of

impervious floor is inadequate, the d/s cut-off wall has to be deepened to the required extent

( Clause 6.1 of I.S. 7114 – 1973 ).

The Exit gradient ( GE) may be calculated from following formula ( Refer Plate No.3.)

GE = ( H / d ) ( 1 / π √ λ )

Where λ = ( 1 + √( 1 + a² ) ) / 2

Where a = b/d

b = length of impervious floor

d = depth of d/s cut-off wall

H = total head which is equal to difference

Between H.W.S.L. & d/s bed level.

The factor of safety for exit gradient for different types of soils shall be as under. ( Clause

3.7.1 of I.S. 6531-1972.

Shingle 1 in 4 to 1 in 5

Coarse sand 1 in 5 to 1 in 6

Fine sand 1 in 6 to 1 in 7.

3.6 Total impervious floor length :

3.6.1 Length : The total floor length can be taken from the starting of u/s transition wall to end of

d/s transition wall.

3.6.2 Uplift pressure : For permeable foundation, uplift pressure shall be worked out according to

Khosla’s theory and 100 % uplift pressure shall be allowed for working out the thickness of

impervious floor. If rock is available in foundation, creep length shall be worked out and

shall be safe as per Lane’s weighted creep theory. Where considerable amount of seepage is

probable, cross drains of selected graded gravel ( inverted filter ) with pressure relief valves

shall be provided in the concrete floor below the cistern. The benefit of release of uplift

pressure due to this may however be not availed of in design of floor thickness.

The following conditions shall be checked for uplift pressure.

i) Gate closed ( Canal full in u/s ) and no water on d/s.

ii) Gate closed ( Canal full in d/s) and no water on u/s

iii) Both u/s and d/s stop logs closed and gate bay portion in between stop logs

dewatered with differential head across C.R.

iv) Gate opening at partial discharge and corresponding to that discharge differential

head across the C.R. ( As a rough guide the unbalanced head may be assumed to be

½ (d2 – d1 ) where d1 & d2 are conjugate depths at the beginning and end of

hydraulic jump ( Ref. I.S. 6531-1972, Cl.3.6.3).

3.6.3 Floor Design :

1. Floor in the gate bay portion may be designed for the condition both u/s and d/s stop logs

closed, canal full on u/s and d/s and area between stop logs dewatered.

2. D/s floor may be designed for the condition gate closed. u/s full and d/s dry.

3. U/s floor may be designed for the condition u/s dry; gate closed and d/s full.

4. The floor shall be designed as R.C.C. slab spanning between abutments and piers or

between transitions.

5. In case transition floor width is more than 2 x FSD, the floor and transition will have to

be designed separately. Transition as retaining walls and floor gravity type.

6. The R.C.C. floor shall be of M-25 grade concrete. The gravity type floor shall be done in

concrete M-20 grade with temperature reinforcement of about 10 mm @ 25 cm. c/c both

ways on the top. If thickness of floor is more than 150 mm two layer reinforcement, one

at the top and other at the bottom shall be provided. The grade of concrete for cut-off

shall be same as that provided in floor.

7. The u/s and d/s cut- off 0.3m thick shall be laid in C.C.M. – 25 and u/s floor protection

in C.C.M.-15 shall be provided for the following length & thickness.

i) U/s floor protections length i. e. from end of u/s cut-off to u/s intermediate cut-

off = 2 x u/s F.S.D. subject to 5 m minimum.

ii) U/s floor protection thickness shall be 150 mm

iii) D/s floor protection length i.e. from end of d/s cut-off onwards = 3 x d/s F.S.D.

subject to minimum of 5 m.

iv) Thickness of d/s protection shall be provided twice the thickness of lining of

canal but minimum 150 mm & maximum 300 mm.

8. If the hard rock is met with below the floor, the anchor bars may be provided below the

floor, to resist the uplift pressure. In such case , minimum thickness of floor may be

provided as per design.

3.7 Transitions : Transitions are used to provide a connection with the canal section both u/s &

d/s of the structure. Straight Warped transition walls are provided with splay of 2 : 1 in u/s and

3:1 in d/s at FSL. Top of wing walls ( u/s and d/s ) shall be kept at respective T.O.B. level

R.C.C. type transition walls shall be in C.C. grade M-25.

The warped transition walls shall be designed as R.C.C. sections in a length from vertical

to1:1 u/s slope. Beyond 1 : 1 slope to canal side slope, the transition walls shall be in the

form of concrete lining of about 15 cm. thickness with nominal reinforcement of 10 mm at 25

cm. c/c both ways. When the length of warped transition wall is less that 5.0 m., only three

section viz. one at vertical face, other at centre and third at end of wall may be given.

Foundation concrete of the transition walls shall be in C.C.M-15.

0.8 m high pipe railing shall be provided on the top of transition walls.

4.0 Structural Design : (a) General : The size and shape of the C.R. structure shall be determined by consideration of

both the hydraulic and operational requirements and by structural economy. The concrete in

abutments designed in R.C.C. shall be of grade M-25. The minimum thickness of abutment

shall be provided from consideration of requirement of embedded parts for stop log gate and

C.R. gates.

The piers shall be monolithic with C.R. floor. Pier shall be designed considering one bay full

and adjoining bay empty. The floor shall be checked for punching shear due to the piers. The

piers shall be constructed in concrete M-25. The thickness of piers shall be provided from the

block out requirements of stop logs and C.R. gates and shall be checked from bending

consideration.

Grade of concrete permissible stresses for concrete and steel shall be taken as per Annex.-I.

5.0 Stability : 5.1 The design of C.R. for stability includes among other consideration, protection against

overturning, sliding and seepage. The transition walls and abutments shall be checked for

load combinations as under :

Load Condition Particulars.

No. 1 – A Canal full, No seismic load, earth fill eroded away from Back of Transition wall. No. I-B Canal full, with seismic load, earth fill eroded away from

back of Transition wall.

No.2-A Canal empty, saturated earth sides with vehicular surcharge on vertical wall, No seismic load. No.2 – B. Canal empty, saturated earth sides with vehicular

surcharge on vertical wall, with seismic load. Factor of Safety : against overturning and sliding shall be taken as under : Particulars Factor of Safety. A : Without seismic load : a) Against over – turning 2.0 ( without seismic loads ) As per I.S. 1904-1986 b) Against sliding ( without seismic loads ) 1.75 c) Against uplift 1 B : With seismic load : Particulars Factor of Safety. a) Against over turning 1.5 i) With seismic loads 1.2 b) Against sliding 1.5 as per IS-456-2000 i) With seismic loads 1.2 with the increase in value 6 to 25% c) Against uplift > 1.2 as per IS-3370 The sliding of the C.R. may be computed on the basis of total weight of structure and total

sliding force generated when all gates are closed with water at HWSL u/s of the gates and no

water on d/s.

The sliding factor, defined as the ratio of the horizontal force tending to cause sliding to the

total weight reduced by uplift, should not be lesser than the 0.3 for clay foundation, 0.4 for

sand and 0.5 for gravel. Cut-off walls extending down in to the foundation may be added to

further increase sliding resistance by increasing the total weight above the plane of sliding.

The weight of soil between cut-off may be taken as its natural weight less buoyancy due to

saturation.

5.2 The backfill behind the retaining wall sections and abutments shall of material excavated from

foundation. The angle of internal friction shall not be less than 30º and cohesiveness of soil

shall not be more than 0.05 kg/cm² for backfill material. Backfill soil shall be of non swelling

type. The backfill shall be well compacted in layers of 15cm. @ O.M.C.

6.0 Foundation :

The foundation investigation shall be carried out up to a depth equal to twice the width of

footing, until and otherwise specified. The investigation shall be carried out as per the

“Guidelines on investigation for structure on branch canal of Narmada Canal System”

Circulated by this office.

6.1 In no case the foundation shall rest on highly compressive liquefiable or weaker soil viz. CH,

CL, MH, MI, ML, OL, OH etc. if depth of such soil is up to 1.0 m the same shall be replaced

with gritty / CNS soil and thoroughly compacted to achieve 95% of the corresponding

standard proctor max. dry density.

6.2 If the depth of soil mentioned in para 4.1 is more than 1.0 m could not be removed the same

should be brought to the notice of this office for the review of foundation and / or

improvement treatment in such case it is necessary to furnish detailed soil testing results as

per note 14.0

6.3 If the structure rests on rocky strata, rocky strata has to be ascertained by the geologist with

geological mapping details shall be done prior to the construction and same shall be furnished

to the NPP & DC along with the report of the geologist regarding the suitability of the rock for

providing foundation of the structure on that rock.

6.4 If the foundation consists rock and soil in part areas, additional joint at the inter section of the

soil and foundation grade rock shall be provided to avoid unequal settlement.

7.0 Gates :

For controlled volume concept, all gates are to be operated simultaneously. Radial gates may

be provided where the canal capacity exceeds 8.5 cumecs. A minimum of two gates shall be

provided. Standardized size of gate shall be adopted.

a) Height of gate : For full supply more than 2 mt. top of the gate is required to be fixed

at height = FSL + raising of water level at d/s C.R. + 0.4 m.

For full supply depth less than 2 mt., the top of gate shall be kept at FSL + raising of

water level at d/s C.R. + 0.3 m.

The top of gate shall be kept lower than the top of lining.

As far as possible, the ratio of height (H) and width (W) of gate shall

not be greater than 1.5.

b) Radius ( R ) for the radial gate shall be calculated according to the following

equation, according to the following equation.

R = Radius of the gate = 1.5 H

Where H = height of the gate.

c) Trunnion level shall be fixed as under :

Trunnion level = d/s FSL + 0.6

However, it shall be ensured that ratio of R/PH shall have a range of about 1.2 to 1.8

Where R = Radius of gate and PH = Ht. of the trunnion pin above sill level.

d) Trunnion shall be fixed on the R.C.C. cantilever bracket provided from pier and

abutment.

e) Restricting Deflection : Especially in larger structure to ensure proper operation of

radial gates, the deflection on end walls and piers shall be restricted by providing

counter forts in case of R.C.C. Abutments.

f) Operating Platform : The C.R. structure shall be provided with an operating

platform

of 3.0 to 3.5 m width for providing the hoist mechanism for operation of gates.

Generally the platform shall consist of chequared plates supported on I-girders.

Suitable block outs shall be provided on top of pier and abutment for fixing girders of

hoist platform.

7.1 Stop logs.

Provision of stop logs shall be made in u/s and d/s of gate bay portion. These will help while

repairing of the gates and dewatering between u/s and d/s of gate bay portion. Stop logs shall

be of steel fabricated or wooden as per the requirement. Steel fabricated stop logs shall be

generally in 1.0 m tier.

Necessary block outs for gates and stop logs shall be left in abutment, piers and floor and

required embedded parts shall be provided in the block outs.

8.0 Miscellaneous details : 8.1A P.V.C. water stop 225 mm. wide shall be provided at the following locations ( wherever

applicable).

a) Junction of abutment with u/s and d/s transition walls.

b) Junction of C.R. floor with transition walls ( if there are not monolithic with floor).

c) Junction of end of transition walls with canal lining.

d) Junction of u/s and d/s transition floor with canal lining.

8.1 B Bituminous material shall be filled at the flowing locations where other than concrete

lining is provided.

a) Junction of C.R. floor with transition walls ( if these are not monolithic with floor ).

b) Junction of end of transition walls with canal lining.

c) Junction of u/s and d/s transition floor with canal lining.

8.2 Float well: Float wells shall be used as measuring devices where discharge of the canal is

more than 8.5 cumecs. These shall be provided at distance of 7.5 m. and 60 m. from the ends

of u/s and d/s transition walls respectively.

8.3 Control Cabin : A provision shall be made for control cabin located on the outer side of

service road. An earthen platform of 10 m x 15 m. ( 15 m dimension a along the canal ) shall

be provided at service road level for control cabin. Local control facilities and monitoring

equipments will be housed in the control cabin.

8.4 Lighting Arrangements : Provision shall be made for lighting posts on hoisting deck.

Annexure - I 1.0 Grade of Concrete, Permissible stress, Reinforcement etc.:- 1.1 The mix of concrete for various R.C.C ./ P.C.C. components shall be adopted as under : Sr.No. Grade of Concrete Where to be used. 1 M-25 ( RCC) R.C.C. barrels, Transition walls, cut-off walls.

2. M-20 (PCC) Gravity Floor.

3. M-15 (PCC) Copping on masonry wing walls ( if adopted)

Pucca floor.

4. M-15 (PCC) Leveling course for foundation for R.C.C.

Barrels.

5. M-10 (PCC) Buoyancy concrete, foundation of

Masonry wing wall, if adopted.

1.2 The design of R.C.C. components shall be done in accordance with I.S. 456-2000 and I.S.

3370 – ( Part –I to IV) relevant to the design or C.R. and C.R. /Fall structures as extracted

from I.S. 456-2000 are reproduced hereunder for ready reference.

1.1 Concrete ( Table – 21 of IS 456-2000 page No. 81)

Table 21 Permissible stresses in Concrete

(Clauses B-1.3, B-2.1, B-2.1.2, B-2.3 and B-4.2 )

All values in N/mm ²

Grade of Concrete

Permissible stress in bending Compression Direct Permissible stress Bond ( Average ) for Plain

bar in tension. Tbd

1 2 3 4

M-10 3.0 2.5 -

M-15 5.0 4.0 0.6

M-20 7.0 5.0 0.8

M-25 8.5 6.0 0.9

M-30 10.0 8.0 1.0

Note : 1. The values of permissible shear stress in concrete are given in Table-23

2. The bond stress given in col. 4 shall be increased by 25 percent for bars in

Compression.

………………………………………………………………………………………………………….

As per clause No. B 2.1.2 bond stress in case of deformed bar conforming I.S. 1786, the bond stress

given in the above table – 21 may be increased by 60 percent.

1.2 Design shear strength of concrete without shear reinforcement. The permissible shear stress

( Tc) in conc. Beams without shear reinforcement.

Table – 23 of I.S. 456-2000 page No. 84

Permissible shear Stress in Concrete ( Tc ) N/mm ²

100 As/bd M-15 M-20 M-25 M-30

1 2 3 4 5

<=0.15 0.18 0.18 0.19 0.20

0.25 0.22 0.22 0.23 0.23

0.50 0.29 0.30 0.31 0.31

0.75 0.34 0.35 0.36 0.37

1.00 0.37 0.39 0.40 0.41

1.25 0.40 0.42 0.44 0.45

1.50 0.42 0.45 0.46 0.48

1.75 0.44 0.47 0.49 0.50

2.00 0.44 0.49 0.51 0.53

2.25 0.44 0.51 0.53 0.55

2.5 0.44 0.51 0.55 0.57

2.75 0.44 0.51 0.56 0.58

3.00 and 0.44 0.51 0.57 0.60

Above

Where as is that area of longitudinal tension reinforcement which continues at least one effective depth

beyond the section being considered except at supports where the full area of tension reinforcement

may be used provided that detailing conforms to clause 26.2.2 i.e. Anchoring of reinforcing bars and

Clause 26.2.3 i.e. curtailment of Tension Reinforcement in Flexural members , b is the breath of beam

and d is effective depth of beam.

TC = Permissible shear stress in concrete.

For solid slabs, the permissible shear stress in concrete shall be Kx Tc where K has the value given

below as per clause No. B-5.2.1.1, IS-456-2000.

Overall dept of slab in mm. K

300 or more 1.00

275 1.05

225 1.15

250 1.10

200 1.20

175 1.25

150 or less 1.30

1.3 With shear Reinforcement, when shear Reinforcement is provided the nominal shear stress Tv in

beams shall not exceed Tc. Max. given below. For slabs Tv shall not exceed half of value of Tc

max. given below.

Table – 24 page No. 86 IS 456 – 2000.

Grade of Concrete M-15 M-20 M-25 M-30

Tc max. N/mm ² 1.6 1.8 1.9 2.2

As per clause No. B-2.3 ( IS 456-2000 ) where the stresses due to wind ( or earth quake ) the 33.33

stresses specified in table 21, 22 and 23 may be exceeded up to a limit of percent wind and seismic

forces need not be considered as acting simultaneously.

2.0 Steel : The main bars, distribution and temperature bars shall be high yield strength

deformed bars ( H.Y.S.D.) conforming to I.S. -1139-1966 and I.S. 1786-1979. The stresses for above

bars shall be adopted as per Table – 2 of I.S. 3370 Part-II 1965.

Type of stress Permissible stresses

a) Direct tension 1500 kg/cm²

b) Bending

i) on liquid retaining face of members 1500 kg/cm²

ii) On face away from liquid for members less 1500 kg/cm² than 225 mm. iii) On face away from liquid for members 1900 kg/cm² 225 mm. Or more in thickness

c) Shear

i) For members less than 225 mm thickness 1500 kg/cm²

ii) For members 225 mm or more in thickness 1750 kg/cm²

d) Compressive stresses

i) Compressive stress in column subjected to 1750 kg/cm² direct load.

Note : Stress limitations for liquid retaining faces shall also apply to the following.

a) Other faces within 225 mm. of the liquid retaining face.

b) Out side or external faces of structures away from the liquid but placed in water logged

soils upto the level of the highest sub soil water level.

2.1 Minimum Reinforcement : ( As per I.S. 3370 ) (Part-II-1965 )

2.1.1 The minimum reinforcement in each of two directions at right angles shall have following area in that direction. a) For sections upto 100 mm thick. 0.3 percent of the Gross sectional area of concrete. b) For section between 100 mm to Linearly varying from 0.3 % for 100 mm to 0.2 % for for 100 mm. 450 mm Thickness. 450 mm thick section. c) For sections greater than 450 mm. 0.2 % of cross sectional area. Thickness. 2.1.2 In concrete sections of thickness 225 mm or greater, two layers of reinforcing steel shall be

placed one near each face of the section to make up the minimum reinforcement specified

above.

2.1.3 The minimum reinforcement specified above may be decreased by 20 percent in case of high

yield strength deformed bars confirming to I.S.1786 – 1966 or I.S. 1139 – 1966.

2.1.4 Where joints are provided in structures, the temperature or minimum reinforcement shall be

provided as under as per U.S.B.R. practice.

A. The minimum reinforcement for canal structures shall be 10 mm Dia at 30 cms.

B. Single layer reinforcement :

i) Reinforced concrete lining 10 cms. and less in thickness

with discontinuous wire-fabric reinforcement and weakened

planes at 360 cm. to 450 cm. Centres. …..0.10 %

ii) Slab and linings not exposed to freezing temperature

or direct sun with joints not exceeding 900 cm. …..0.25 %

iii) Slabs and linings exposed to freezing temperature

Or direct sun with joints not exceeding 900 cm. ….0.30%

iv) Slabs and linings exceeding 900 cm. between joints ….0.35 %

Category (ii ) above.

Category (iii) above ….0.40%

v) Walls and other structural members total percentage of

Horizontal reinforcement to be equal to the sum of those

Required for both faces as determined below :

c) Double Layer reinforcement

i) Face adjacent to earth with joints not exceeding 900 cm …0.10 %

ii) Face not adjacent to earth nor exposed to freezing temperatures

or direct sun and with joints not exceeding 900 cm. …0.15%

iii) If member exceeds 900 cm. in any direction parallel

to reinforcement add to the reinforcement requirement

in that direction because of the increased length …0.05 %

iv) If a slab is fixed along any line, double the dimension from line

of fixing to free end to determine whether reinforcement is within

the less than 900 cm. or more than 900 cm. Percentages shown

above (i), (ii), (iii) & (iv) above.

Note : The percentage indicated are based on the gross cross sectional area not including Fillets of

the concrete to be reinforced where the thickness of the section exceeds 40 cm. A thickness of

40 cm. should be used in determining the temperature or minimum reinforcement.

2.1.5 Minimum shear reinforcement : ( As per Clause 26.5.1.6 of I.S. 456-2000).

Minimum shear reinforcement in the form of stirrups shall be provided such that

Asv / bsv > = 0.4/0.87 fy

Where Asv = Total cross sectional area of stirrup legs effective in shear.

Sv = Stirrup spacing along the length of the member

B = Breadth of the beam or breadth of the web of flanged beam.

Fy = Characteristic strength of the stirrup reinforcement in N/mm² which shall not be

greater than 415 N/mm² .

2.2 Minimum Cover to reinforcement :-

2.2.1 Minimum cover at each end of reinforcing bar shall not be less than 50 mm. Nor less than

the diameter of such bar which ever is higher.

2.2.2 For faces not coming in contact with water, the minimum cover for reinforcement shall not be

les than 15 mm. or less than the diameter of such bar.

2.2.3 In no case cover shall exceed 75 mm.

2.3 General requirement of reinforcement

2.3.1 Development length of bars : The development length Ld is given by

Ld = Φ σs / 4 Tbd

Where Φ = Nominal diameter of bar

σs = Stress in bar at the section considered at design load.

Tbd = Design bond stress as per Cl. B-2.1 or Table 21 of I.S. 456 – 2000.

2.3.2 Spacing of reinforcement :

i) The horizontal distance between parallel main reinforcement bars shall not be more than

three times effective depth of a solid slab or 300 mm. whichever is smaller.

ii) The horizontal distance between parallel reinforcement bars provided against shrinkage

and temperature shall not be more than five times the effective depth of a solid slab or

450 mm whichever is smaller ( As per Clause 26.3.3 of I.S. 456 – 2000).

iii) The maximum spacing of shear reinforcement measured along the axis of the member

shall not exceed 0.75 d for vertical stirrups and d for inclined stirrup at 45 º , where d is

the effective depth of the section under consideration. In no case shall spacing exceed

300 mm. ( Clause 26.5.1.5 of I.S. 456 – 2000 ).

N. B. : The above IS Codes are not comprehensive, however the designer should refer all the

relevant Codes etc. OF LATEST REVISION necessary and pertaining to designs.

Annexure - II

References.

The following references are used for preparing the guide lines.

1. I.S. 7114 – 1973 – ‘ Criteria for hydraulic design of cross regulators for canals’.

2 I.S. 6531 – 1972 – “ Criteria for design of canal head regulators ‘.

3. I.S. 3370 ( Part-I) – 1965 ‘ Code of practice for concrete structures for the storage of liquids’ ( General requirements ).

4. I.S. 3370 ( Part-II) 1965 ‘ Code of practice for concrete structures for the storage of liquids’

( Reinforcement concrete structures.) 5. I.S. 3370 ( Part-III) – 1967 – ‘Code of practice for concrete structures for the storage of

liquids’ ( Prestressed concrete structures.) 6. I.S. 3370 (Part-V)-‘ Code of practice for concrete structures for the storage of liquids ‘

( Design tables ) 7. I.S.456-2000-‘ Code of practice for plain and reinforced concrete ‘ ( Forth Revision). 8. I.S. 1904 – 1986 – I.S. for structural safety of building shallow foundation.’ 9. Draft manual on fall – Central water & power commission ( water wing ) 1960. 10. Seminar lecture IV – Design for canal structures for minor irrigation – M.I.P. 11. C.D.O. lecture volume – 1 August, 1961. 12. Narmada Planning Group, Gandhinagar April, 88. Guide lines for operational requirement for

planning & design of conveyance system to be operated on controlled volume concept. 13. United States Deptt. Of the Interior Bureau of Reclamation Dec. 1967 ‘ Design standards

No.3, Canals and related structures.’ 14. I.S. 1893 – latest revision criteria for earthquake resistant design of structure. 15. United States Department of the Interior – 1978 – ‘ Design of small canal structure. 16. Irrigation Engineering – S.K. Garg. 17. Theory and design of irrigation structures volume – II Varshney & Gupta. 18. Guide lines on Investigation for structures on Branch Canal of Narmada Canal System

prepared by N. P. Planning & Design Circle, Gandhinagar, 1998. N.B. : The above list is not comprehensive, however the designer should refer all the relevant Code

/ Books etc. OF LATEST REVISION necessary and pertaining to designs.

Guidelines for Design of Cross – Regulator / Fall on Branch Canals of Sardar Sarovar (Narmada) Project.

1.0. General:-

1.1. Necessity of Falls:- Where the natural slope of the land on which the

canal passes is greater than the grade of the canal, it is necessary to

transfer the canal safely from higher level to a lower level by providing

a suitable structure namely fall or drop.

1.2 C.R. with Fall:- Narmada Main Canal, Branch Canals and Dstributories

are to be operated on controlled volume concept. In Controlled Volume

operated canal, a fall is invariably provided with a cross regulator.

2.0 Layout:

2.1 Components:- The layout will depend upon the type of C.R. and its

combination with a fall or a bridge etc. The main components shall be

a) Inlet transition

b) Control structures with operation platform and regulating

device.

d) Outlet transition

e) U/S, D/S & Intermediate Cut-off Wall

f) Abutment, Piers and Road Bridge, where provided

g) Float well.

3.0 Selection of Type of Fall: (See Sketch-1)

3.1. Well type Fall:- For discharge less than 1.5 cumecs and drop more than

1.0 m.

3.2 Vertical drop type Fall:- For discharge upto 15 cumecs and drop upto

1.0 m.

3.3. Straight glacis Fall (without Baffle Wall and Platform):- For discharge

from 15 cumecs to 60 cumecs and drop upto 1.0 m.

3.4 Glacis fall with baffle wall and baffle platform:- For all discharges

and drop more than 1.0 m.

Note:- If the drop is more than 5.0 m. the feasibility of chute fall may be

examined.

4.0 Hydraulic Design

4.1. Water Way:-

4.1.1. For submerged fall the drawing ratio that is (the ratio of tail water over

crest to head water over crest) should be greater than 0.80 (Cl.2.1.3. of

I.S.7114-1973).

4.1.2. For submerged fall, waterway is found out from the following

equation. (Irrigation Engineering by S.K. Garg).

Q = 2/3 Cd1 √ 2g x (B ( h +ha) 3/2 – ha 3/2))

+ Cd2 x B x h1 √ 2g (h+ha)

Where Cd1 = 0.577, Cd2 = 0.80

B = Clear waterway required

h = Difference of water level u/s and d/s

h1 = Depth of d/s water level above crest.

ha = Velocity head = v2/2g

4.1.3 For free fall, the discharge per unit length over the crest should be

equal to or greater than that required for the available loss of head and

the required value of the full supply depth d/s. (Cl.2.1.3 of I.S. 7114-

1973).

4.1.4. When the gate size is standardized for the branch canal the waterway

should be adjusted accordingly.

4.2.0 Crest:-

4.2.1. Crest level:- Crest level should be worked out as per following

equation (Cl.3.1.1. of I.S.7114-1973)

Q = C x Bt x H 3/2

Where Q = Full supply discharge D/S in m3/sec.

C = Co-efficient of discharge

= 1.84 (The width of Crest at top, b < 2/3 H) for sharp crest weir.

C = 1.705 For broad crested weir

(Where b > 2.5 H)

(Ref. Theory and design of irrigation structure Vol .II of Varshaney and

Gupta).

H = Head over crest. H = U/S T.E.L – Crest R.L.

Bt = Effective Waterway

= Clear Waterway – 2 (Ka + nkp) H

Where n = number of Pier

Kp = Pier contraction coefficient = 0.01 (For rounded nose).

Ka = Abutment contraction co-efficient.

= 0.1 (For rounded abutment with head wall at 900)

(Ref. The value of Ka and Kp as per Cl.3.4.1. of I.S. 6531 – 1972)

4.2.2 In a lined Canal, setting of the crest above bed (upstream or

downstream whichever is higher) should not be less than 15 cms nor

higher than 40% of normal depth of the canal u/s (Cl.3.1.2. of I.S.7114 –

1973).

4.2.3. Crest Width:- The Crest width shall be fixed from operational

consideration subject to a minimum of 2/3 H , where H is the head

over the crest (Cl.3.2.1. of I.S.7114 – 1973) or just downstream of gate

up to nose of pier / abutment whichever is higher for the smooth

operation.

4.3.0. Glacis:-

4.3.1 U/S and D/S glacis Slope:-

a) Generally for total discharge higher than 10 cumecs, the u/s and

d/s

glacis should have a slope of two horizontals to one vertical

(Cl.3.2.1. of

7114 – 1973).

b) For total discharge lower than 10 cumecs, the slope of d/s glacis

shall

be kept at 2.5:1 (Cl.3.2.2. of I.S.7114 – 1973)

c) If however baffle platform with a baffle wall is provided then

the slope

of d/s glacis may be kept at 2/3:1 (As per draft manual on fall).

4.3.2. U/S & D/S Glacis Radius:-

a) For discharge higher than 10 cumecs the radius joining the crest

with u/s glacis should be kept equal to H and the radius joining

the crest with d/s glacis should be kept equal to 1.5 H where H

is the head over the crest (Cl.3.2.1. of I.S.711-4 1973).

b) In case the criteria indicated in (4.3.2.1.) above the radius of u/s

glacis and d/s glacis shall be worked out as under:-

i) Upstream Glacis:-

Radius R = T/Tan θ1/2

Where R = Radius for u/s glacis

T = Tangent length

√ X12 + H12

Where X1 = 2 H1 for 2:1 slope

H1 = Crest R.L. – U/S C.B.L.

and θ1 = tan -1 (H1 / X1)

ii) For D/S Glacis

Radius R = T1/Tan θ2/2

T1 = Crest width – T

Where T is as worked out in 4.3.2. b (i) above u/s glacis radius.

Where θ2 = tan -1 (H2 / X2)

Where H2 = Crest RL – D/S Cistern RL

X2 = 2 H2 (For 2:1 Slope)

iii) For baffle platform with a baffle wall the crest is jointed the

baffle platform by curve of radius is equal to H (Ref. Draft

manual on falls). (H= Head over crest)

c) For discharge lower than 10 cumecs, the u/s glacis should be

entirely of a circular curve without any straight portion. The

radius of the circular curve is obtained from the following

formula.

Ra = (3 H3 – X2) / 200 x

Where Ra = Radius of curvature of u/s glacis in m.

H = Head over crest in m.

X = Height of crest above u/s bed in m.

The curve joining the crest with the d/s glacis should have a

radius of 0.60 m. (Clause 3.2.2. of I.S. 7114 – 1973).

5.0 Energy Dissipation Devices:-

5.1.0 Well Type Fall:

5.1.1. For higher magnitude of fall more than 1.0 m. this type of fall

can be adopted. It is suitable for small discharges with

comparatively high drops.

5.1.2. Dia. of Pipe D = 2 √( Q / ¶X V)

Where V = Velocity in m/sec.

Q = Discharge in cumecs.

5.1.3. Length of Pipe: - Minimum length of the pipe should be

decided to the requirement of slopes of cutting.

5.1.4 Wall of Well:- circular C.C.M-15 or R.C.C.M-25 should be

provided.

5.1.5. Water level in the Well:- After deciding the length & dia. of the

pipe the loss of head should be calculated as per the formula

given below:-

H= (1 + f1 + f2 x L/r) V2/2g.

Where f1 = 0.505 and f2 = A ( 1+ B/r)

A = 0.00316

B = 0.03

r = Hydraulic mean depth

V =Velocity of flow in m/sec.

L= Length of Pipe

Water level in the Well = D/S F.S.L. + Loss of Head

5.1.6 Dia of well (D)

(a) Minimum 3 ft.

(b) D = X + (4/9 x F.S.D.)

Where X = V x √ 2Y/g

V = Velocity in notch

Q / (B x F.S.D. (U/S)

B = Notch width

Y = U/S C.B.L. + (U/S F.S.D/3) – Water level in the well

5.1.7 Water cushion:- Depth of cushion in Well

X = (Magnitude of fall + U/S F.S.D.)/3

5.1.8 Sill of the well shall be laid with 3” (75 mm) of C.C.M-15 (Ref.

Seminar lecture IV Design for Canal structures for minor

irrigation).

5.2.0. Vertical Drop Fall:-

5.2.1. Cushion:-

In case of a vertical drop fall there is no glacis or sloping floor

downstream of the crest, the deep cushion of water is dependent

upon for dissipation of energy due to falling water. The energy

is dissipated by means of impact; and deflection of velocity,

suddenly from the vertical to the horizontal direction.

The water cushion is formed by depressing the floor below the

d/s bed of the channel.

Cistern Length Lc = 5 (HL x D )1/2

Cistern depth X= ¼ (HL X D) 2/3

Where Lc = Length of cistern

X = Depression below the d/s bed

HL = Drop in meter

D = Depth of crest below u/s. T.E.L. in m.

(Ref. Theory & Design of Irrigation St. Vol.II by Varshney &

Gupta)

5.2.2. Friction Blocks:-

For discharge exceeding 3 cumecs two rows of friction blocks

staggered in plan may be provided in cistern so that d/s edge of

d/s row is at a distance of L/3 from the end of cistern floor.

Length of friction Block = Height of friction block.

= hfr = d3 / 8, width at top = 1/4 of height = hfr/4

Spacing between two rows may be kept equal to height of block.

Where Lf = Length of floor (Ref. Draft manual on falls of C.W.

and P.C.) d3 = d/s F.S.D.

5.3.0. Straight Glacis Fall: (Without Baffle Wall and Platform)

5.3.1. Cistern:-

a) Cistern R.L. = D/S TEL – (1.25 Ef2)

D/S T.E.L. = D/S F.S.D. + V2/2g

Where V = D/S Velocity in canal

Knowing Q and HL, value of Ef2 is read from flow energy

curve

(Blench Curve Sketch-2)

b) Length of Cistern: - 5 Ef2

c) D/S end of cistern is kept slopping upward to meet d/s CBL

at slope

of 5:1

5.3.2 Deflector wall:-

a) The deflector wall is provided at the D/S end of glacis

which helps in the formation of horizontal positive

vortices.

b) Height of Deflector Wall:- d3/10, Where d3= D/S FSD

c) Top R.L. of deflector Wall = D/S CBL + height of wall.

d) Thickness of Deflector Wall = 0.30 m.

5.3.3. Friction Blocks:-

a) Fur unflumed Fall:- No friction Blocks is provided

b) For flumed fall:- Four rows of friction blocks in staggered

arrangements are provided.

a) First row at a distance of 5d3/8 from the toe of glacis

b) Distance between each row = hfr = d3 / 8

c) Top width of each block = 2/3 hfr

d) Distance between blocks = 3 hfr

e) Length of each block = 3 hfr

Where d3 = D/S F.S.D.

5.3.4. Glacis Blocks:- Are not provided.

5.4.0 Glacis fall with Baffle wall and Baffle Platform:-

5.4.1. Baffle Platform and Baffle Wall:-

a) Depth of baffle platform:-

The dimensions of baffle platform shall be determined from

the

following equation.

dx = 0.98 q 0.52 x Hx 0.21

Where q = Design discharge per meter width

Hx= Head loss due to unflumed fall

dx= Sub Critical depth.

b) R.L. of baffle platform = D/S F.S.L. - dx

c) Length of baffle platform = 5.25 x Height of Wall ( Hb)

d) Height of baffle Wall (Hb)

Hb = dc – d2

Where dc = Critical depth = (q2/g)1/3

d2 = 0.183 x q 0.89 x Hx -0.35

e) Thickness of baffle wall = 2/3 x Height of Wall (Hb)

5.4.2. Cistern:-

a) R.L. of Cistern = D/S CBL – 0.1 d3

Where d3 = D/S F.S.D.

b) Length of Cistern = 5dx

Where dx = Sub critical depth

c) The cistern is provided horizontal for whole length.

5.4.3. Deflector Wall:- As per Para 5.3.2.

5.4.4. Friction Blocks:

a) Friction blocks are provided where magnitude of fall is greater

than

1.80 m.

b) Two rows of friction blocks are provided one at Lf/3 from d/s

end of

cistern and other row at distance of hfr u/s from it.

Where Lf = Length of cistern.

Hfr = 2/9 x 0.85-1 x dx

Where dx = Sub Critical depth

a) Length of friction blocks = hfr

b) Width of friction blocks = 2/3 hfr

c) Distance between blocks = hfr

5.4.5. Glacis Blocks:- For fall more than 1.8 m. glacis blocks of same

height as friction blocks to be provided. The effect of these blocks

is to reduce the turbulence in flow which in turn reduces wave

wash. Thus ensuring uniform flow.

6.0 Cut-off Walls:- Cut-off walls shall be provided in case of straight

glacis with baffle wall and straight glacis with baffle wall & baffle

platform.

6.1 U/S Cut-off:

6.1.1. U/S Cut-off wall shall be provided at starting of u/s transition

wall.

a) Depth of u/s cut-off wall shall be determined from the following

whichever is higher. However minimum depth of cut-off shall be

provided 1.5 m. from top of the floor.

i) Depth of u/s cut-off = d1/3 + 0.5 m. (1)

Where d1 = U/S FSD in m.

ii) As per U.S.B.R. u/s cut-off depth in metric system

iii) U/S Cut-off depth =0.69√ d1

Where d1 = u/s water depth in m.

The minimum thickness of cut-off shall be 0.3 m. Fillets of

minimum 0.15 m x 0.15 m. size shall be provided at the junction of

cut-off with the floor. The maximum depth of the u/s cut off wall

shall be restricted to 2.5 m. from the top of the floor except it is

absolutely necessary to increase beyond 2.5 m.

6.2 D/S Cut-off:

6.2.1. D/S Cut-off wall shall be provided at D/S end of cistern length

depth of d/s cut-off wall shall be maximum of the following

criteria. However min. depth of cut-off shall be provided 2.0 m

from top of the defector wall or d/s floor. However in no case

bottom of the d/s cut off should be higher than bottom of the u/s

cut-off.

a) Depth of d/s cut-off wall is found out according to the following

criteria.

i) Depth of d/s cut-off = d/2 + 0.5m. ………….(1)

(IS.6531 – 1972 Cl.3.7.2.2.)

Where d=d/s FSD

ii) As per U.S.B.R. D/S cut-off depth in metric system d/s cut-off

depth =0.69 √ d1

d1= D/S water depth in m.

Minimum thickness of cut-off shall be 0.3 m and fillets of

minimum 0.15 m x 0.15 m size shall be provided at the junction of

cut-off with the floor.

Maximum depth of d/s cut off shall be 3.0 m except it is

absolutely necessary to increase for control of exit gradient.

6.3 Intermediate Cut-off:

6.3.1. U/S intermediate cut-off wall be provided at the u/s edge of u/s

stoplog groove and where depth shall be 1.5 m from top of hump

level.

6.3.2. D/S intermediate cut-off shall be provided at the d/s end of baffle

wall and its depth shall be 1.5 m. from the top of baffle platform

level.

7.0 Exit Gradient:

7.1 Design:- The structure should be checked for safe exit gradient in

accordance with accepted theories and adequate length of floor

and d/s cut-off walls should be provided for safe values of exit

gradients. An exit gradient depending on type of soil and

importance of structure may be provided for ordinary conditions.

If the overall length of impervious floor is inadequate, the d/s

cut-off wall has to be depend to the required extent (Clause 6.1 of

I.S.7114 – 1973).

7.2 The exit gradient (GE) may be calculated from following formula.

GE = (H/d) (1 / √ ¶XY )

Where Y = (1 + √ 1 + a2 ) /2

Where a = b/d

Where b = length of impervious floor

d= depth of d/s cut-off wall

H = Total head which is equal to difference between u/s

FSL/HWSL and d/s bed level.

7.3 The factors of safety for exit gradient for different types of soils

shall be as under (Clause 3.7.1. of I.S. 6531 – 1972)

Shingle 1 in 4 to 1 in 5

Coarse Sand 1 in 5 to 1 in 6

Fine Sand 1 in 6 to 1 in 7

Note:- 1. In case where rock is met with the exit gradient criteria

will not

be governing.

2. Grain size analysis of soil shall be taken in to account

before

finalization of the type of soil for the purpose of deciding

factor

of safety for exit gradient.

8.0 Total impervious floor length:-

8.1 Length:- The total floor length can be taken from the starting of

u/s transition wall to end of d/s transition wall. The length of

impervious floor is related to the depth of d/s cut-off wall. The

total floor length can be decreased by increasing the depth of d/s

cut-off wall or vice versa. However any increase in the depth of

d/s cut-off wall shall result in higher uplift pressures, specially in

d/s half of the floor. A balance design should there be achieved

by trial and error and economic study.

8.1.1. Minimum of total floor length required shall be the sum of :-

a) D/S transition wall length

b) Horizontal floor on the d/s side from surface flow consideration.

c) Length required to accommodate the sloping glacis crest, and

starting of the abutment.

d) Length required for energy dissipation devices.

e) U/S transition wall length.

9.0 Uplift Pressure:-

9.1 For permeable foundation:- The uplift pressure shall be worked

out according to Khosla’s theory and 75% uplift pressure shall be

allowed for working out the thickness of impervious floor.

9.2 If rock is available in foundation creep length shall be worked out

and shall be safe as per lane’s weighed creep theory where

considerable amount of seepage is probable, cross drains of

selected gravel with pressure release valves shall be provided in

the concrete floor below the cistern.

9.3 The following conditions shall be checked for uplift pressure.

9.3.1. Gate closed (canal full in u/s and no water on d/s)

9.3.2. Gate closed (Canal full in d/s and no water on u/s)

9.3.3. Both U/S and D/S stoplogs closed and gated bay portion in

between stoplogs dewatered with differential head across C.R.

9.3.4. Gate opening at partial discharge and corresponding to that

discharge, differential head across the C.R. (As a rough guide the

unbalance head may be assumed to be ½ (d2 – d1) where, d1 & d2

are conjugate depths at the beginning and end of hydraulic jump.

(Ref. I.S.6531 – 1972 Cl.3.6.3.)

10.0 Floor Design:-

10.1 Floor in the gated bay portion may be designed for the condition

both u/s and d/s stoplog closed, canals full on u/s and d/s and

area between stoplogs dewatered.

10.1.1. D/S floor may be designed for the condition gate closed, u/s full

and d/s dry.

10.1.2. U/S floor may be designed for the condition u/s dry, gate closed

and d/s full.

10.1.3 The floor width shall be designed as RCC slab spanning between

abutments and pier or between transition.

10.1.4 The RCC floor shall be of M-25 grade concrete. The gravity type

floor shall be done in concrete M-20 grade with temperature

reinforcement of about 10 mm θ @ 25 cm c/c both ways. If

thickness of floor is more than 150 mm two layer reinforcement,

one at the top and other at the bottom shall be provided. The

grade of concrete for cut-off shall be same as that provided in

floor.

10.2 The concrete for RCC floor, baffle wall, friction blocks and glacis

blocks shall be of M-25 grade.

10.3 The u/s and d/s cut-off 0.3 m thick shall be laid in C.C.M-25 and

u/s floor protection in C.C.M-15 shall be provided for the

following length & thickness.

i) U/S floor protections length i.e. from end of u/s cut-off to u/s

intermediate cut-off = 2 x u/s FSD subject to 4 m minimum.

ii) U/S floor protection thickness shall be 150 mm.

iii) D/S floor protection length i.e. from end of d/s cut-off onwards =

3 x d/s F.S.D. subject to minimum of 5 m.

iv) Thickness of d/s protection shall be provided twice the thickness

of lining of canal but minimum 150 mm & maximum 300 mm

10.4. If the hard rock is met with below the floor, the anchor bars

maybe provided below the floor, to resist the uplift pressure. In

such case minimum thickness of floor may be provided as per

design.

11.0 Transition:-

Transition are used to provide a connection with the canal section

both u/s & d/s of the structure.

11.1. U/S transition:-

11.1.1. Straight warped transition walls at u/s are provided with splay of

1:1 as there is no consideration of loss of head due to provision of

fall.

11.1.2. Where the velocity of water does not exceed 1.0 m/sec. The canal

cross section shall be carried out right up to the structure to abut

upon the canal structure and no straight warped transition be

provided.

11.2 D/S Transition:-

11.2.1. The d/s transition wall beyond the toe of the glacis shall be kept

vertical up to deflector wall and beyond that suitable slope shall

be provided. A splay of 3:1 at F.S.L. straight warped transition

wall to d/s transition shall be given or alternatively the end of the

d/s straight wall near deflector wall may be returned at right

angle and keyed in to the canal slope with suitable protection in

bed and sides on d/s side based on the economic consideration.

Top of Wing Walls (U/S and D/S) shall usually be kept at the

respective bank level. R.C.C type transition wall shall be in

R.C.C.M-25 grade of concrete.

11.2.2. The warped transition walls shall be designed as R.C.C. sections

in the length from vertical section to 1:1 u/s slope. Beyond 1:1

slope to canal side slope the transition walls shall be in the form of

concrete lining of about 150 mm. Thickness with nominal

reinforcement of 10 mm θ @ 25 cm. C/C each way. When the

length of warped transition wall is less than 5.0 m. The wall shall

be designed as R.C.C. section and three section viz. One at vertical

face, other at center and third at end of wall may be given.

11.3 Foundation concrete of the transition walls shall be constructed in

C.C.M-15

11.4 0.8 m high pipe railing shall be provided on the top of wing wall

and railing shall usually be provided on water face side.

12.0 Structural Design:-

12.1 General:- The size and shape of the CR/FALL structure shall be

determined by consideration of both the hydraulic and

operational requirements and by structural economy. When the

concrete in abutment when designed is in R.C.C these shall be in

M-25.

12.2. The minimum thickness of abutment shall be provided for

requirement of embedded parts for stop log gate and C.R. gates.

The piers shall be monolithic with C.R floor, pier shall be

designed considering one bay full and adjoining bay empty. The

floor slab shall be checked for punching shear due to the piers.

12.3. The piers shall be constructed in Concrete M-25. The thickness of

piers shall be provided from the requirement of stoplogs and C.R.

gates.

12.4 Permissible stresses for concrete and steel shall be taken as per the

relevant I.S. Codes, Reinforcement shall be provided on the basis

of design subject to minimum steel requirement.

12.5 Seismic forces considering the zone in which location of the

structure falls, shall be considered as per IS 1893-1984 and IS 456-

2000 in design calculation.

13.0 Stability:-

13.1 The design of C.R./Fall for stability includes among other

consideration, protection against overturning, sliding and

seepage. The transition walls and abutment shall be checked for

load combinations as under:

Load Condition Particulars

No.1 Canal full, with seismic load and

earth loose

Contract from back of transition

walls.

No.2 Canal empty sat. Earth sides with

vehicular

surcharge on vertical wall, and

seismic load.

13.2. The backfill behind the retaining wall and abutment shall be of

material excavated from foundation having the angle of internal

friction shall not be less than 200 and cohesion of soil shall not be

more than 0.05 kg/cm2. Back fill soil be of non-swelling type. The

backfill shall be well compacted in layers of 15 cm. @ O.M.C. to

achieve 95% of corresponding standard protactor max. dry

density.

Particulars Factor of Safety

a) Against over turning 1.5

i) With seismic loads 1.2

b) Against sliding 1.5 as per IS-456-2000

i) With seismic loads 1.2

c) Against uplift > 1.2 as per IS - 3370

13.3. The sliding of the C.R. may be computed on the basis of total

weight of structure and total sliding force generated when all

gated are closed with water at HWSL u/s of the gates and no

water on d/s. The sliding factor defined as the ratio of the

horizontal forces tending to cause sliding to the total weight

reduced by uplift should not be lesser than the 0.30 for clay

foundation. 0.40 for sand and 0.50 for gravel cut-off walls

extending down in to the foundation may be added to further

increase sliding resistance by increasing the total weight above the

plane of sliding. The weight of soil between cut-off may be taken

as its natural weight less buoyancy due to saturation.

14.0 Foundation:- The foundation investigation shall be carried out up

to a depth equal to twice the width of footing, until and otherwise

specified. The investigation shall be carried out as per the

“Guideline on investigation for structure on branch canal of

Narmada Canal System” circulated by this office.

14.1 In no case the foundation shall rest on highly compressive

liquefiable or weaker soil viz. CH, CL, MH, MI, ML, OL, OH etc.

if depth of such soil up to 1.0 m. the same shall be replaced with

gritty/ CNS soil and thoroughly compacted to achieve 95% of the

corresponding standard proctor max. dry density.

14.2 If the depth of soil mentioned in Para 4.1. is more than 1.0 m.

could not be removed the same should be brought to the notice of

this office for the review of foundation and / or improvement

treatment in such case it is necessary to furnish detailed soil

testing results as per note no.14.0.

14.3 If the structure rests on rocky strata, rocky strata has to be

ascertained by the geologist with geological mapping details shall

be furnished to the NPP& DC along with the report of the

geologist regarding the suitability of the rock for providing

foundation of the structure on that rock.

14.4. If the foundation consists rock and soil in part areas, additional

joint at the inter section of the soil and foundation grade rock shall

be provided to avoid unequal settlement

15.0 Gates:-

15.1. For Controlled Volume Concept of regulation of all gates are to be

operated simultaneously. Radial gates may be provided where the

canal capacity exceeds 8.5. cumecs. A minimum of two gates shall

be provided. Standardized size of gates shall be adopted, stoplogs

shall be provided both on u/s and d/s side of the gate as per

standardized details.

15.2 Height of Gates:-

15.2.1. For full supply depth equal or more than 2 m. top of the gate is

required to be fixed at height = FSL + rise of water level at d/s

C.R. + 0.4 m. i.e. 0.1 m. less than the lining to avoid over topping

of lining during emergency shut-down.

15.2.2. For full supply depth less than 2 Mt. The top of gate shall be kept

at FSL + rise or water level at d/s CR + 0.3 m.

As far as possible the ratio of height (H) and width (W) shall not

be greater than 1.5

15.3 Radius:- R of the radial gate shall be calculated according to the

following equation. However radius shall be considered in design

and drawing as per given standardization of gate size.

R = Radius of the gate = 1.5 H

Where, H = Height of the gate.

15.4. Trunnion Level:- Trunnion level shall be fixed as per the

following criteria.

15.4.1. Trunnion level = Head over crest (He + 0.6 m (minimum)and max.

1.2 m..

15.4.2. Trunnion level = Crest level + 0.5 H to 0.75 H

Where, H = Height of the gate.

Out of (1) and (2) the one which gives higher value shall be

adopted as trunnion level. However, it shall be ensured that ratio

of R / PH shall have range of about 1.2 to 1.8 where R = Radius of

gate and PH= Height of the trunnion pin above sill level.

15.5. Trunnion shall be fixed on the R.C.C. cantilever bracket provided

from pier and abutment.

15.6 Restricting Deflection:- Especially in larger structures to ensure

proper operation of radial gates, the deflection of walls and pier

shall be restricted by providing counter forts in case of RCC

abutments and walls.

15.7 Operating Platform:- The C.R. structure shall be provided with

an operating platform of 3.0 to 3.5 m. width for providing the

hoist mechanism for operation of gates. Generally the platform

shall consists of chequrred plats supported on I-girders. Suitable

block outs shall be provided on top of pier and abutment for

fixing girders of hoist platform

15.8. Stop-logs:- Provision of stop-logs grooves shall be made in u/s

and d/s of gate bay portion. These will help while repairing of

gate and dewater between u/s and d/s of gate bay portion

stoplog shall be of steel fabricated or wooden as finalized by NPP

& Design Circle, Gandhinagar. Steel fabricated stoplogs shall be in

1.0 m. tier. D/S stoplog may not be provided where d/s FSL is 0.6

m. below the crest level.

16.0 Miscellaneous Details:-

16.1 PVC water stop 225 mm wide shall be provided at the following

locations (wherever applicable)

16.1.1. Junction of abutment with u/s and d/s wing walls.

16.1.2. Junction of d/s protection (concrete floor) with canal lining.

16.1.3. Junction of C.R. floor with abutments, Piers and Wing Walls (if

these are not monolithic with floor)

16.1.4. Junction of end of wing walls with canal lining

16.1.5. Junction of u/s and d/s cut-off walls with u/s canal lining and

d/s protective floor.

16.2 Float Well:- Float wells shall be used as measuring devices. These

shall be provided at distance of 7.5. m. and 60 m. from the ends of

u/s and d/s transition walls respectively.

16.3. Control Cabin:- A provision shall be made for control cabin

located on the outer side of the service road. An earthen platform

of 10 m x 15 m. (15 m. dimension along the canal) shall be

provided at service road level for control cabin. Local control

facilities and monitoring equipments will be housed in the control

cabin.

ANNEXURE-1

1.0. Grade of Concrete, Permissible stress, reinforcement etc.:-

1.1. The mix of concrete for various RCC/PCC components shall be

adopted as under:-

Sr.No. Grade of Concrete Where to be used. 1. M-25 (RCC) RCC barrels, Transition walls, cut-

off walls. 2. M-15 (PCC) Copping on Masonry wing walls

(if adopted) Pucca floor 3. M-15 (PCC) Leveling course for foundation for

RCC barrels. 4. M-10 (PCC) Buoyancy concrete, foundation of

masonry wing wall, if adopted.

1.2. The design of RCC components shall be done in accordance with

I.S. 456-2000 and I.S. 3370 – (Part I to IV) relevant to the design of

C.R. and C.R/Fall structures as extracted from I.S.456-2000 are

reproduced hereunder for ready reference.

1.3. Concrete (Table-21 of IS 456-2000 Page No.81)

Table 21 Permissible le stresses in Concrete (Clauses B-1.3, B-2.1, B-2.1.2, B-2.3 and B-4.2

All values in N/mm2

Grade of Concrete

Permissible Stresses in Bending cbc

Compression Direct cc

Permissible stress Bond (Average) for Plain bar in tension. Tbd

1 2 3 4 M-10 3.0 2.5 - M-15 5.0 4.0 0.6 M-20 7.0 5.0 0.8 M-25 8.5 6.0 0.9 M-30 10.0 8.0 1.0

Notes:-1. The values of permissible shear stress in concrete are given in

Table-23.

2. The bond stress given in col.4 shall be increased by 25 percent for

bars in compression.

As per Clause No. B 2.1.2 bond stress in case of deformed bar conforming

I.S. 1786, the bond stress given in the above table-21 may be increased by

60%.

1.4 Design shear strength of concrete without shear reinforcement. The

permissible shear stress (Tc) in conc. Beams without shear

reinforcement.

Table-23 of I.S. 456-2000 Page No.84

Permissible shear Stress in Concrete (Tc ) N/mm2

100 As/bd M-15 M-20 M-25 M-30 (1) (2) (3) (4) (5) <=0.15 0.18 0.18 0.19 0.20 0.25 0.22 0.22 0.23 0.23 0.50 0.29 0.30 0.31 0.31 0.75 0.34 0.35 0.36 0.37 1.00 0.37 0.39 0.40 0.41 1.25 0.40 0.42 0.44 0.45 1.50 0.42 0.45 0.46 0.48 1.75 0.44 0.47 0.49 0.50 2.00 0.44 0.49 0.51 0.53 2.25 0.44 0.51 0.53 0.55 2.5 0.44 0.51 0.55 0.57 2.75 0.44 0.51 0.56 0.58 3.00 and above

0.44 0.51 0.57 0.60

Where As is that area of longitudinal tension reinforcement

which continues at least one effective depth beyond the section

being considered except at supports where the full area of

tension reinforcement may be used provided that detailing

conforms to Clause 26.2.2. i.e. Anchoring of reinforcing bars and

Clause 26.2.3. i.e. curtailment of Tension Reinforcement in

Flexural members, b is the breath of beam and d is effective

depth of beam.

Tc = Permissible shear stress in concrete

For solid slabs, the permissible shear stress in concrete shall be K

x TC Where K has the value given below as per Clause No.B-

5.2.1.1., I.S. 456 – 2000

Overall depth of slab in m.

K

300 or more 1.00 275 1.05 250 1.10 225 1.15 200 1.20 175 1.25 150 or less 1.30

1.5 With shear Reinforcement, when shear Reinforcement is

provided the nominal shear stress Tv in beams shall not exceed

Tc max. given below. For slabs Tv shall not exceed half of value

of Tc max. given below.

Table-24 Page No.86 IS 456 -2000

Grade of Concrete M-15 M-20 M-25 M-30

Tc max. N/mm2 1.6 1.8 1.9 2.2

As per Clause No.B-2.3 (IS 456-2000) Where the stresses due to

wind (or earth quake) the 33.33 stresses specified in Table 21,22

and 23 may be exceeded up to a limit of percent wind and

seismic forces need to be considered as acting simultaneously.

2.0 Steel:- The main bars, distributions and temperature bars shall

be high yield strength deformed bars (H.Y.S.D.) conforming to

I.S. 1139-1966 and I.S. 1786-1979. The stresses for above bars

shall be adopted as per Table -2 of I.S.3370 Part-II 1965

Types Permissible stresses a) Direct tension 1500 kg/cm2 b) Bending

i) On liquid retaining face of members

1500 kg/cm2

ii) On face away from 1500 kg/cm2

liquid for members less than 225 mm.

iii) On face away from liquid for members 225 mm. or more in thickness.

1900kg/cm2

c) Shear i) For members less

than 225 mm thickness.

1500 kg/cm2

ii) For members 225 mm or more in thickness

1750 kg/cm2

d) Compressive stress i) Compressive stress in column subjected to direct load

1750 kg/cm2

Note: Stress limitations for liquid retaining faces shall also apply

to the following.

a) Other faces within 225 mm. of the liquid retaining face.

b) Outside or external faces of structures away from the liquid

but placed in water logged soils up to the level of the highest

sub soil water level.

2.1. Minimum Reinforcement:- (As per I.S. 3370) (Part-II-1965)

2.1.1 The minimum reinforcement in each of two directions at right

angles shall have following area in that direction.

a) For section up to 100 mm. thick

0.3 percent of the Gross Sectional Area of concrete

b) For Section between 100 mm. to 450 mm. Thickness

Linearly varying from 0.3% for 100 mm. thick section to 0.2% for450 mm. thickness

c) For sections greater than 450 mm. thickness.

0.2% of cross sectional area

2.1.2. In concrete sections of thickness 225 mm. or greater, two layers

of reinforcing steel shall be placed one near each face of the

section to make up the minimum reinforcement specified above.

2.1.3. The minimum reinforcement specified above may be decreased

by 20 percent in case of high yield strength deformed bars

confirming to I.S. 1786 – 1966 or I.S. 1139 – 1966.

2.1.4. Where joints are provided in structures, the temperature or

minimum reinforcement shall be provided as under as per

U.S.B.R practice.

A. The minimum reinforcement for canal structures shall be 10

mm. Dia. at 30 cms.

B. Single layer reinforcement:

i) Reinforced concrete lining 10 cms. and less in thickness

With discontinuous wire-fabric reinforcement and weakened.

Planes at 360 cm to 450 cm. Centres. …………….

0.10%

ii) Slab and linings not exposed to freezing temperature

or direct sun with joints not exceeding 900 cm.

………………0.25%

iii) Slabs and linings exposed to freezing temperature

or direct sun with joints not exceeding 900 cm.

…………….0.30%

iv) slabs and linings exceeding 900 cm. Between joints

Category (ii) above.

…………….0.35%

Category (iii) above.

……………..0.40%

v) Walls and other structural members total percentage of

horizontal reinforcement to be equal to the sum of those

required for both faces as determined below:-

C. Double Layer reinforcement

i) Face adjacent to earth with joints not exceeding 900 cm. …

………0.10%

ii) Face not adjacent to earth nor exposed to freezing

temperatures or direct sun and with joints not exceeding

900 cm.

……………0.15%

iii) Face not adjacent to earth but exposed to freezing

temperatures or direct sun and with joints not exceeding

900 cm.

……………0.20%

iv) If member exceeds 900 cm in any direction parallel

to reinforcement add to the reinforcement requirement

in that direction because of the increased length

……………..0.05%

v) If a slab is fixed along any line, double the dimension

from line of fixity to free end to determine whether

reinforcement is within the less than 900 cm. or more

than 900 cm. Percentages shown above (i), (ii), (iii)

& (iv) above.

Note: The percentage indicated are based on the gross cross

sectional area not including Fillets of the concrete to be

reinforced where the thickness of the section exceeds 40 cm. A

thickness of 40 cm. should be used in determining the

temperature or minimum reinforcement

2.1.5. Minimum shear reinforcement: (As per Clause 26.5.1.6 of

I.S.456-2000) Minimum shear reinforcement in the form of

stirrups shall be provided such that

Asv/bsv >=0.4/0.87 fy

Where Asv = Total cross sectional area of stirrup legs effective in

shear.

Sv= Stirrup spacing along the length of the member

B= Breadth of the beam or breadth of the web of flanged beam.

Fy= Characteristic strength of the stirrup reinforcement in

N/mm2 which shall not be greater than 415/N/mm2

2.2 Minimum Cover to reinforcement:

2.2.1. Minimum cover at each end of reinforcing bar shall not be less

than 50 mm. Nor less than the diameter of such bar whichever is

higher.

2.2.2. For faces not coming in contact with water, the minimum cover

for reinforcement shall not be less than 15 mm. or less than the

diameter of such bar.

2.2.3 In no case cover shall exceed 75 mm.

2.3 General requirement of reinforcement

2.3.1. Develo0ment length of bars :- The development length Ld is

given by

Ld = Φ s/ 4 Tbd

Where Φ = Nominal diameter of bar

s = Stress in bar at the section considered at design load.

Tbd = Design bond stress as per Cl.B-2.1 or Table 21 of I.S. 456 –

2000.

2.3.2 Spacing of reinforcement:-

i) The horizontal distance between parallel main reinforcement

bars shall not be more than three times effective depth of a solid

slab or 300 mm. whichever is smaller.

ii) The horizontal distance between parallel reinforcement bars

provided against shrinkage and temperature shall not be more

than five times the effective depth of a solid slab or 450 mm.

Whichever is smaller. (As per Clause 26.3.3. of I.S. 456 – 2000).

iii) The maximum spacing of shear reinforcement measured along

the axis of the member shall not exceed 0.75’d’ for vertical

stirrups and ‘d’ for inclined stirrups at 450, where ‘d’ is the

effective depth of the section under consideration. In no case

shall spacing exceed 300 mm. (Clause 26.5.1.5 of I.S. 456 – 2000).

Annexure-II References

The following references are used for preparing the guide lines.

1. I.S.7114-1973 – ‘Criteria for hydraulic design of cross regulators for canals’

2. I.S.6531-1972 – ‘Criteria for design of canal head regulators’ 3. I.S.3370 (Part-I) -1965 -‘Code of practice for concrete structures for

the storage of liquids’ (General requirements). 4. I.S.3370 (Part-II)- 1965 -“Code of practice for concrete structures for

the storage of liquids’ (Reinforced concrete structures). 5. I.S.3370 (Part-III) – 1967 – ‘Code of practice for concrete structures

for the storage of liquids’ (Prestressed concrete structures). 6. I.S.3370 (Part-IV) – ‘Code of practice for concrete structures for the

storage of liquids’(Design Tables) 7. I.S. 456 – 2000 –‘Code of practice for plain and reinforced concrete’

(Forth Revision). 8. I.S.1904 – 1986 – I.S. for structural safety of building shallow

foundation 9. Draft manual on fall – Central Water & Power commission (Water

Wing) 1960 10. Seminar Lecture IV – Design for canal structures for minor

irrigation – M.I.P. 11. C.D.O. Lecture Volume – I, August, 1961. 12. Narmada Planning Group, Gandhinagar April, 88 Guide lines for

Operational Requirement for Planning & Design of Conveyance System to be operated on Controlled Volume Concept.

13 United States Deptt. of the Interior Bureau of Reclamation Dec., 1967 ‘design Standards No.3, Canals and related Structures’

14. I.S. 1893 – Latest Revision Criteria for Earthquake resistant design of structure.

15. United States Department of the Interior – 1978 –‘Design of small canal structure’

16. Irrigation Engineering – S.K.Garg. 17. Theory and design of irrigation structures volume-II Varshne &

Gupta. 18. Guide lines on Investigation for structures on Branch Canal of

Narmada Canal System – prepared by N.P.Planning & Design Circle, Gandhinagar 1998.

N.B.:- The above list is not comprehensive, however the designer should

refer all the relevant Code/Books etc. OF LATEST REVISION

necessary and pertaining to designs.

Guidelines for Gate Design:

EPC contract for Gate works of Narmada Branch Canals. (I) Introduction : 1.0 The Sardar Sarovar (Narmada) Project envisages the construction of a

concrete gravity dam ( including River Bed Power House ( RBPH) and Canal

Head Power House (CHPH) across the Narmada River near village Navagam

in Bharuch District with a large network of canal system. The Narmada

Main Canal is about 458 km. long up to Gujarat – Rajasthan boarder and

further 74 km in Rajasthan. Its capacity at the head is @ 1133 cumecs and

at the Gujarat – Rajasthan boarder is 71 cumecs. The cross section at its

head is 73.1 m x 7.60 m. where B = bed width and D = Full

( B x D )

supply depth. There are 42 Branch Canals off taking from the Main Canal.

Water for Irrigation will be conveyed to 8 ha. Blocks through a @ 66000 km.

Network of conveyance and distribution system consisting of Branch canals,

distributaries, minors and sub minors. The branch canals and the

distributory system network up to 8 ha. Block are to be lined. To regulate

the flow in canal, Cross Regulators have been proposed at about 13 to 15

km. on Narmada Main Canal and at about 5 to 7 km. on Narmada Branch

Canals.

2.0 Selection of type of Gate : i) Radial gates are to be proposed at the Regulating structures having

discharge ( Q ) greater than 8.5 cumecs, i.e. for Q ≥ 8.5 cumecs, - Radial

gates.

ii) Vertical slide gates (open type) are to be proposed at the Regulating

structures having discharge ( Q ) less than 8.5 cumecs & greater than

3.0 cumecs. (i.e. 8.5 cumecs > Q ≥ 3.0 cumecs. )

iii) Vertical slide gates (pipe type) are to be proposed at the Regulating

structures having discharge (Q) less than 3.0 cumecs (i.e. Q < 3.0 Cumecs.)

3.0 Size of Gate : Gate sizes for

(A) Radial gates

(B) Vertical slide gates ( open type )

(C) Vertical slide gates ( pipe type ) ;

have been standardized for the Regulating structures of Narmada Branch

Canals ( Phase-II ) which are attached herewith as per Annexure – I. These

standardized gate sizes are to be adopted while designing the Regulating

structures such as C.R., H.R., Escape etc.

4.0 Block – out details : Drawings showing the details of Block-outs and their 1st and

2nd stage embedded parts for:

i) Radial gates

ii) Vertical slide gates ( open type )

iii) Vertical slide gates ( pipe type ) &

iv) Stop logs.;

have been standardized for the Regulating structures of Narmada Branch

Canals ( Phase – II) .These standardized Block-out drawings are to be

adopted while designing the Regulating structures such as C.R., H.R.

Escape etc. as attached herewith as a sample design & drawings

v) Water supply out let.

a) Gate design for block-out shall be carried out as per hydraulic data

and accordingly Block-out shall be provided as per Drg. for

wheel type / when the head of water is exceeding 5m just to reduce

hoist capacity at vertical gate with wheel type is preferred. The

sample design & drawing is attached herewith . The sealing

& wheel shall be same side @ skin plate . The provision of u/s slop

log shall also be made. For lower head less than 5 m slide type

vertical gate with U/s stop-log provision shall be made.

b) The Block-out for water supply pipe ( M.S. pipe ) if adopted ,separate

detailing, sizing of block-out etc. shall be made as per typical

drawing attached herewith.

5.0 Indian Standard Codes : List of IS codes to be used for the reference for the design of i) Radial gates

ii) Vertical slide gates ( open type )

iii) Vertical slide gates ( pipe type )

iv) Stop logs

v) Rope drum type hoist.

vi) Screw type hoist &

vii) Other Gate related features etc.;

is attached herewith as per Annexure-II.

6.0 General Guide lines for planning and Design of Gates.

i) Radial gates are to be supported on cantilever R.C.C. brackets which

are to be constructed monolithically with pier / abutments up to total

horizontal thrust 110 t . If horizontal thrust more than 110 t,

trunnion girder type anchorage system shall be provided.

The trunnion bracket detailing shall be adopted as per typical

drawings .

Design of Cantilever R.C.C. bracket (having b/d < 0.5, where b =

distance between C/L of load application and pier / abutment face, d

= Depth of R.C.C. bracket). has to be done as per the corbel theory

considering shear – friction method.

ii) When Radial gate is to be provided, a hump of 0.5 m. is to be

proposed in the invert of concerned CR/ HR such that canal invert

through CR/HR is flat and nearly horizontal from the U/s pier nose

to the end of the pier d/s.

iii) When vertical gate is to be provided, a hump of 0.15 m. is to be

proposed in the invert of concerned CR/HR.

iv) In case of Radial gates, Radius for each Radial gate is to be provided

as mentioned against each standardized Radial gate size (Reference

Annexure-I). It is to mention that in case of CR / Fall, where gate-bay

portion is to be provided as per CR (i.e. Horizontal floor in gate-bay

portion) than in that case radius of gate will be as per CR.

v) In case of Radial gates, trunnion pins are to be located as under

a) Trunnion pin R.L. = D.S. F.S.L. + 0.6 to

1.20 m OR

(b) Trunnion pin R.L. = Sill elevation of gate +

0.5 to 0.75H of gate

where H = height of gate.

From above (a) & (b), higher value is to be adopted as trunnion R.L.

However, it is to ensure that R/PH shall have a range of @ 1.2

to 1.8 and accordingly, the trunnion pin R.L. shall have to be

finalized. The gate shall be self closing type.

(where, R = Radius of gate.

PH = Pinion height i.e. Trunnion pin R.L. – Sill

elevation of gate ).

The minimum height of piers above gate crest shall be 1.5 times

height of radial gates for allowing the gate to be remains in groove for

1/3 ht. of gate.

The provision free board of radial gates shall be made such that

necessary additional tolerance is included when the regulated

structure is designed take care of total permissible settlement when

structure is rested on settable soil as per I.S. provisions.

(vii) Where vertical slide gates are to be provided, they are to be supported on

grooves kept in pier / abutments.

(viii) Radial gates and vertical gates are to be designed for the following

conditions.

a) U.S. full and D.S. empty.

b) U.S. empty and D.S. full.

(ix) All the Radial gates are to be stiffened by Horizontal stiffeners, supported

on vertical girders and jointed with the arms ( parallel to pier /

abutment ) so as to form a rigid frame. All members of gate which are

to be submerged ,shall have minimum 8 mm thickness.

(x) Size of arm shall be 150x150 mm to accommodate with vertical girder as

its flange width is kept 150 mm. Suitable provision of guard railing

shall be made on top of arm.

(xi) Thickness of seal seat shall not be less than 6 mm after machining in any

case and seal seat base plate shall be of minimum 10 mm thick.

It is to note that this system differs than that shown in IS: 4623

“Recommendations for structural design of Radial gates” in which

Radial gates are to be stiffened by vertical stiffeners supported on

Horizontal girders and jointed with the arms.

(xii) All the vertical gates are to be stiffened by Horizontal stiffeners supported

on vertical girders.

(xiii) Radial gates are to be operated by Electrically operated Rope-drum type

hoist comprising of Induction motor, EMG brake, worm reducer,

spur gear reduction units, Rope drums etc.

This Rope drum type hoist is to be provided on U.S. side of Radial gate

on M.S. steel hoist platform.

Provision for manual operation has also to be made in accordance

to I.S.:6938.

(xiv) For central drive unit of Rope drum type hoist worm gear ratio up to

8.0 MT capacity shall be of 500:1 & above 8 MT this gear ratio should

be of 60:1 only.

(xv) For hoist capacity up to 8 MT , single stage reduction and above

8 MT capacity three stage reduction spur gear box for end

reduction unit with oil lubrication shall be preferred.

(xvi) Design of wire rope & rope drum, motor, worm reducer,

Electromagnetic brake ,gear pinion shaft, key etc. should be as per

IS 6938 of latest version.

(xvii) The various permissible design stresses for various component of

rope drum hoist like gear, pinion, shaft, key etc shall be

in accordance with IS : 6938 of latest version.

(xviii) The minimum wall thickness of spur gear box (i.e. End reduction unit) of

rope drum hoist shall be of at least 8 mm for small size.

(xix) The design hoisting speed shall be maximum 50 cm/min. with ratio for

speed range 10:1.

(xx) The induction motor of 1000 rpm shall be provided with limit

switch(torque switch if required ) for operation of radial gates The same

shall be replaced with induction motor clubbed with eddy current drive

only at the time of automation and shall be operated to match with rpm

of worm reducer which are to be designed at 1000 rpm. The relevant

specifications shall be as finalized by C.E.(E& M) vadodara and EQDC ,

Gandhinagar respectively.

(xxi) The hoist capacity as well as the H.P. etc. shall be adopted as per the

methodology of design unit of Nigam which is under review.

( xxi ) After meeting with Gate consultant, CE (E&M) etc. worm reducer shall be

designed to compatible with 1000 rpm induction motor.

Removalable hand railing shall be provided on all four sides of hoist

in platform with provision of entry gate & fabricated access ladder.

(xiv) Vertical gates are to be operated by electrically operated screw type

worm geared hoist comprising of geared motor, worm, worm shaft,

Nut and stem rod, electromagnetic brake, flexible coupling, dog clutch

with manual operation system.

Provision for manual operation has also to be made in accordance

with Indian Standard. The material for each components at all type of

gates and hoists etc. shall be as per IS for the relevant components

of gate design & drawings as furnished in sampled.

This screw type hoist is to be provided on M.S. steel hoist

platform.

The thread of screw stem shall be trapezoidal.

For stem rod, slenderness ratio (l/r) shall be kept within 120 to

140 & accordingly one or two stem bracket shall be provided.

Maximum hoisting speed shall be 10 cm/minute.

(xv) Following IS codes are to be followed for the

design of gates and hoists as well as materials

to be used for fabrication of various gate

components.

a) Design of Radial gates IS : 4623

b) Design of vertical slide gates IS : 5620

c) Design of Rope drum type hoist IS : 6938

d) Design of screw type hoist IS : 11228

e) Design of stoplogs. IS : 5620

IS : 4622

(xiv) For the operation of Branch Canals having

discharge Q > 8.5 cumecs, a controlled

volume concept has to be adopted. For this

purpose, the Canal system is to be proposed

to be divided into a series of storage pools

separated by Cross Regulators. The canal will

be operated by automatic operation system,

using remote monitoring and control by means

of Real time computers.

One Control room ( cabin ) is to be provided on

Canal bank for the operation of gates by

remote control system. Remote

terminal unit for automatic gate operation is to

be provided in control room.

(xv) For the maintenance of gates ( i.e.Radial &

Vertical ) , stoplogs are to be provided at U.S. &

D.S. of gates.

Stoplogs are to be designed in balanced water

head condition.

(xvi) Stoplogs are to be operated by Mobile Cranes

through lifting beams.

(xvii) Size of stoplog : Height of each stoplog tier is

to be kept 1.0 m.

Hence size of stop-log tier = B x 1.0

Where, B = clear opening.

(xviii) one pair ( i.e. U.S. & D.S.) of stoplog will be

required for the maintenance of one gate. This

pair of stoplog can be used at other structures

having same size of gate. Hence, clubbing of

structures is to be determined for one pair of

stop-log in view of economy.

(xxv) Stoplogs are to be stacked in stack yard.

Hence, planning of stack yard is to be made

with the provision of “ Stand ” to hold the stop- logs.

(xxvi) For protection against weathering to the gate control cabinet suitable

removable shade shall be provided on the hoisting platform of

relevant gate after making suitable arrangement in the civil

structure which shall not be an obstacle for stoplog inclusion during

closure of canal at time of repairs of gates & stop-log operations etc.

(xxvii) The provision of panel board, for electrical operation

gates, wiring diagram etc. shall be included as per the guideline

finalized by electrical wing of Nigam/ CE ( E & M ), SSNNL, Vadodara

/Gate consultant. Sample drawing is attached herewith .

STANDARD SIZE OF GATES FOR Branch Canal gates ( Phase-II).

(A) Radial gates.

Sr. No.

Size of gate Radius for CR

in. Hoist capacity

B X H mt. R=1.5H (Rope drum

type) m x m in MT

1 3.00 X 2.40 3.6 2 2 3.00 X 3.20 4.8 4 3 4.10 X 4.00 6 8 4 4.80 X 4.80 7.2 10 5 5.20 X 5.60 8.4 18 6 5.50 X 6.20 9.3 18 7 2.15 X 2.10 3.2 2 8 2.30 X 2.60 4 2 9 2.70 X 3.00 4.5 4 10 2.90 X 3.40 5 4 11 3.40 X 3.80 5.8 8 12 3.60 X 4.20 6.3 8 13 3.90 X 4.60 7 8 14 4.20 X 5.00 7.5 10 15 4.50 X 5.40 8.1 10 16 4.60 X 5.80 8.7 18 17 4.90 X 6.20 9.3 18

B=clear opening of gate.

H= Height of gate.

R=Radius of

gate.

B) Vertical slide gates (open type). Sr. No. Gate size Hoist capacity

B m X H m (screw type) in MT.

1 0.75 X 1.25 1.4 2 0.75 X 1.65 1.4 3 1.00 X 1.20 1.4 4 1.00 X 1.60 1.4 5 1.00 X 2.65 3 6 1.20 X 1.90 3 7 1.30 X 1.50 1.4 8 1.40 X 1.85 3 9 1.50 X 1.25 1.4 10 1.60 X 1.10 1.4 11 1.60 X 2.30 4.5 12 1.75 X 1.80 3 13 1.90 X 2.45 4.5 14 1.90 X 3.35 8 15 2.00 X 2.35 4.5 16 1.00 X 1.85 1.4 17 1.00 X 2.40 3 18 1.10 X 2.50 3 19 1.15 X 2.50 3 20 1.20 X 2.30 3 21 1.20 X 3.10 6 22 1.50 X 1.75 3 23 1.75 X 2.35 4.5 24 1.00 X 2.00 3 25 1.20 X 2.60 4.5

B=Clear opening of gate. H=Height of gate.

Vertical slide gates (pipe type) Sr. No. pipe dia

Barrel Wall/pipe Gate size proposed Design head Hoist capacity

in mm. thickness ( D+ 2t+100) in m (screw type) D t in mm mm X mm in MT.

1 300 40 500 X 500 3 1.4 2(a) 450 75 700 X 700 3 1.4 (b) 600 85 870 X 870 3 1.4

3 900 100 1200 X 1200 3.6 4.5 4 1000 115 1330 X 1330 5 6 5 1100 115 1430 X 1430 4 6 6 1200 120 1540 X 1540 5 8

7 1400 135 1770 X 1770 5 10 8 1600 140 1980 X 1980 5 13 9 1800 150 2200 X 2200 5 13

List of IS Codes to be used for the reference for design of Radial and Vertical gates & Rope drum and screw lift hoist.

Sr.No. IS Code No. Description.

1 IS : 4623 Recommendations for structural design of Radial

gates. 2 IS : 1030 Carbon steel castings for general engineering

purposes. 3 IS : 318 Specification for Leaded Tin Bronze Ingots and

castings. 4 IS : 1570

(Part-II) Schedule for wrought steels. Part-II carbon steels (unalloyed steels).

5 IS : 210 Specification for grey iron castings. 6 IS :1570

(Part-V) Schedules for wrought steels Part - V - stainless and Heat resisting steels.

7 IS : 325 Specification for three phase induction motors. 8 IS : 7718

Recommendations for inspection, testing and maintenance of fixed wheel and slide gates.

9 IS : 813 Scheme of symbols for welding. 10 IS : 4622 Recommendations for Structural Design of Fixed

wheel gates. 11 IS : 800 Code of practice for use of structural steel in general

building construction. 12 IS : 6938 Design of rope drum and chain hoists for Hydraulic

gates - Code of practice. 13 IS : 11855 Guidelines for Design and use of different types of

rubber seats for hydraulic gates. 14 IS : 1182 Recommended practice for the radiographic

examination of fusion welded butt joints in steel plates.

15 IS : 4218 (Part-II)

ISO General Purpose Metric Screw Threads - Part II General Plan.

16 IS : 4218 (Part-IV)

ISO General Purpose Metric Screw Threads - Part-IV -Selected sizes of screw Bolts & Nuts.

17 IS : 2062 Steel for General Structural Purposes - Specification. 18 IS : 2266 Specification for steel wire ropes for general

engineering purpose. 19 IS : 10210 Design criteria for Hydraulic hoists for gates. 20 IS : 2485 Specification for Drop Forged Sockets for Wire

Ropes for General Engineering Purposes. 21 IS : 10096

(Part- I & II) Recommendations for Inspection, testing & maintenance of Radial gates & their hoists.

22 IS : 304 Specification for high tensile brass ingots and casting ( Revised).

23 IS : 11228 Recommendations for design of screw hoists for Hydraulic gates.

24 IS : 3177 Code of practice for Electric Overhead Travelling Cranes and Gantry Cranes other than Steel Work Cranes.

25 IS : 807 Code of practice for Design, Erection and testing ( structural portion ) of Cranes and Hoists.

26 IS : 808 Dimensions for Hot Rolled Steel beams, Channels & Angle sections.

27 IS : 3444 Corrosion Resistant High Alloy Steel And Nickel Base Castings for General Applications - Specification.

28 IS : 1079 Hot Rolled Carbon Steel Sheet & Strips-Specification.

29 IS : 3961 Part-3

Recommended currant ratings for cables - Part-3. Rubber insulated cables.

30 IS : 822 Code of procedure of inspection of welds. 31 IS : 1387 General requirements for the supply of

metallurgical materials. 32 IS : 2048 Specification for Parallel keys & keyways. 33 IS : 2074 Specification for Ready Mixed Paint, Air Drying,

Red Oxide Zinc chrome, Priming. 34 IS : 2075 Ready Mixed Paint, Stoving, Red Oxide Zinc

chrome, Priming - Specification. 35 IS : 2291 Tangential keys and keyways. 36 IS : 2693 Power Transmission - Bush Type flexible coupling. 37 IS : 694 PVC Insulated Cable for working voltages up to and

including 1100 V.

38 IS : 900 Code of Practice for Installation and Maintenance of Induction Motor.

39 IS : 1248 Direct Acting Indicating Analogue Electrical Measuring Instruments and their Accessories (Part - 1 to 9).

40 IS : 1271 Thermal evaluation and classification of electrical insulation.

41 IS : 1777 Industrial Luminaries with metal reflectors.

42 IS : 2419 Dimensions for Panel mounted indicating and recording electrical instrument.

43 IS : 2551 Danger Notice Plates. 44 IS : 2705 Current Transformers ( Part- 1 to 4) 45 IS : 3043 Code of Practice for earthing. 46 IS : 3156 Voltage Transformer 47 IS : 3231 Electrical Relays for power System Protections 48 IS : 4029 Guide for testing three phase induction motors. 49 IS : 4722 Rotating Electrical Machines - Specification. 50 IS : 4889 Method of determination of Efficiency of Rotating

Electrical Machines. 51 IS : 5216 Recommendations on Safety Procedures and

Practices in Electrical work. ( Part-I & II) 52 IS : 5578 Guide for Marking of Insulated Conductors. 53 IS : 6236 Direct Recording Electrical Measuring Instruments. 54 IS : 8130 Conductors for Insulated electrical cables and

flexible cords. 55 IS : 8828 Electrical Accessories - Circuit Breakers for Over

Current Protection for Household and Similar Installations.

56 IS : 9385 H. V. fuses. ( Part 1 to 5 ) 57 IS : 9974 High Pressure Sodium Vapor Lamps. ( Part-1 & 2) 58 IS : 10118 Code of practice for selection, installation and

maintenance of switchgear and control gear. (Part-1 to 4)

59 IS : 5620 Recommendations for Structural Design Criteria for Low Head Slide Gates.

CHAPTER 12

Indicative Quantity Schedules for guidance of the bidder

The indicative quantities for different items of work for the various

components of the works as assessed on preliminary basis by the SSNNL are

enclosed with this chapter as Schedules IQS – 1 to IQS 6 as detailed below.

The quantities mentioned in the items are also indicative and the bidder shall

have to make his own assessment while bidding. These quantities will not

form a part of contract and the price bid.

ISQ No. Particulars of work

1 Earthwork

2 Lining

3 Structures

4 Service Road

5 Gate Works

6 Control Cabin

ISQ No. 1 – EARTH WORK

Quantity Description Unit

76.00 Item No. E-1 Clearing the canal land width including removing the trees up to 0.50 m. bushes etc. including depositing the materials outside the canal land width as directed etc. complete (SOR It.No E-1)year 2008-09 P. 2)

ha

148818.51 Item No.E-2 Stripping the canal construction width and borrow areas in all sorts of soil, soft and hard mudroom including depositing the stripped material as and where directed within a lead unto 200m. (SOR It.No E-3)year 2008-09 P. 2)

m3

427168.00 Item no E-3 Excavation of canal in all sorts of soil including soft and hard murrum including depositing the excavated stuff in uniform layers in canal banks or as and where directed etc complete in varying lead upto 1 km and with all lifts. (SOR It.No E-4(C)(a)year 2008-09 P. 3)

m3

106792.00

Item no E-4 Excavation of canal in soft rock including depositing the excavated stuff in uniform layers in canal banks or as and where directed including dressing the section etc. complete in varying lead up to 1 km & all lifts. (SOR It.No E-5(c)(a)) year 2008-09 P. 3

m3

1463426.00

Item no.E-5 Earth work in embankment using selected soil, soft & hard murrum excavated from approved borrow area / village tanks etc. Including royalty charges, conveying, spreading in uniform layers, breaking clods and dressing to the designed canal section etc. with lead upto 1 km and all lift .(For canals having capacity beyond 8.5 cumecs) (SOR It.No E-11 & E-10 year 2008-09 P. 5)

m3

1590386.00 Item no E-6 Compaction of earth work in embankment in uniform layers at optimum moisture content to required dry density including watering, rolling with suitable type of roller of specified capacity etc. complete.(SOR It.No E-12)year 2008-09 P. 5

m3

4431.00 Item no.E-7 Providing and constructing rock toe as per drawing including transporting, placing, laying, handling and hand packing of stones, pointing with cement mortar 1:5 proportion, finishing

m3

& curing with all leads and lifts etc. complete. (Rate as per RA No.1)

106060.00 Item no. E-8 Providing and laying sand filter layer of specified gradation in uniform layers of specified thickness in horizontal, inclined and inverted filter zone in canal banks as per drawing including watering upto saturation and compaction as directed. (Rate as per RA No.2)

m3

20930.40 Item no E-9 Excavation of canal side gutter in all sorts of soil incl. soft & hard murrum including depositing the excavated stuff in uniform layers in canal banks or as and where directed including dressing the section etc. complete in varying lead up to 500 m & all lifts. (SOR It.No E-25(a)year 2008-09 P. 6

m3

Item no E-10 Providing 7.5 cm thick paved drain in M-10 concrete as per drawing for proper drainage arrangement including disposing off the excavated materials as directed. (Rate as per RA No.3)

6980.00 (a)Size 0.40 m x 0.30 m m 96.00 Item no.E-11

Providing and constructing kundi in B.B. masonry in CM 1:6 including plastering in CM 1:3, M-10 concrete base and laying 300 mm dia pipe for draining out water from berm, rubble filling, excavation and refilling as per drawing etc. complete. (SOR It.No E-24)year 2008-09 P. 6

No.

198.00 Item No.E-12 Providing and constructing kundi in B.B. masonary in CM 1:6 including plastering in CM 1:3, M-10 concrete base for draining out water from berm, rubble filling, excavation and refilling as per drawing etc. complete.

No.

135215.00 Item no.E-13 Furnishing and laying of the live sods of perennial turf forming grass on embankment slope, verges or other locations shown on the drawing or as directed by the engineer including preparation, of ground, fetching of sods and watering. (As per RA)

m2

ISQ No. 2 – LINING

Quantity Description Unit

335003.00 Item No.L-1 Mechanized trimming of the canal section for preparing sub grade for laying cement concrete lining in all sort of soils and murrum and backfilling the over excavated rock sections, if any, with lean concrete including watering and compacting bed and side slopes using slope compactors, including backfillling and dewatering where required. m2

Item No.L-2 Providing and laying plain / reinforced cement concrete lining of M-15 grade in bed, side slopes and curvature including batching, mixing, transporting, placing, vibrating, smooth finishing, curing including dewatering where required.

204890.00 (a) 12.5 cm thick lining in slopes and curvatures m2

108323.00 (b) 10 cm thick lining in bed m2

16258.00 (c) 25 mm thick R.C.C. lining in slope in bed. m2

41245.00 (d) 20 mm thick R.C.C. lining in slope in bed. m2

159460.00 Item No.L-3 Providing and fixing PVC strips in the concrete lining including inserting in crack inducing joints of dimension as per drawing etc. complete. m

1196.00 Item No.L-4 Providing and laying M-15 grade plain concrete of cement, sand and crushed metal for 1 m wide step on the canal slope with 0.20 m wide side wall including dressing the sub grade to correct profile, mixing, placing, vibrating, form work, finishing and curing the concrete etc. complete as per drawing will all leads and lift. No.

Item No.L-5 Providing and laying vertical non metalic pressure release valve including excavation of pits and refilling the same

with filter materials as per design and drawing at required intervals etc complete as directed.

848.00 (a) 63 mm outer dia No. 1696.00 (b) 160 mm outer dia No.

Item No.L-6Providing &placing in position reinforcment bars including cutting, bending, welding joints where necessary hooking etc complete as per drawing for all leads and lifts.

346.00 HYSD MT

Item No.L-7 Providing M-15 grade plain cement concrete for including providing washing ghat, 1.20 m high G.I. Pipe railing as per design and drawing etc. complete.

5.00 (a) 5 m wide washing ghat for branch canals No.

ISQ No. 3- Structures

Quantity Description Unit

Item no S-1 Excavation for foundation in all sorts of soil including yellow sandy gravelly soil, soft & hard murrum etc. including depositing the excavated stuff in uniform layers in banks or as and where directed etc. complete for lead upto 1 km and all lift. (By machinery)

62920.96 (a)Above water table m3 548496.00 (b)Below water table m3

Item no S-2 Excavation for foundation in SOFT ROCK including depositing the excavated stuff as and where directed etc. complete for lead upto 1 km and all lift

7240.00 (b)Below water table m3

255754.22

Item no S-3 Back filling the foundation trenches around the structures etc with selected excavated stuff including watering, ramming, compacting etc. complete m3

1424.00

Item no S-4 Providing and filling in foundation with gritty material in foundation of structure wherever CH type soil metwith including watering, compacting etc complete. m3

Item no S-5 Providing &laying plain / reinforced ordinary portland cement concrete of M-15 grade with cement, sand, and coarse aggregates including centering, shuttering, batching, mixing, transporting, placing, vibrating, smooth finishing, curing etc. complate. ( MACHINARY BASED ) (EXCLUDING DEWATERING)

11916.94 (a) Raft, Bottom slab of barrel, bottom slab of sump, approach slab and chute floor slab, etc m3

2899.00 (b)Footing of columns of piers & abutments, Piers, abutments, pier cap, abutmemt cap, wingwalls, headwalls, returnnwall, etc m3

Item no S-6 Providing & laying plain / reinforced ordinary portland cement concrete of M-25 grade with cement, sand, and coarse aggregates including centering, shuttering, batching, mixing, transporting, placing, vibrating, smooth

finishing, curing etc. complate. ( MACHINARY BASED INCLUDING DEWATERING)

50855.55 (a) Raft, Bottom slab of barrel, bottom slab of sump, approach slab and chute floor slab, etc m3

71830.34 (b) Footing of columns of piers & abutments, Piers, abutments, pier cap, abutmemt cap, wingwalls, headwalls, returnnwall, etc.

m3

31243.47 (c) Walls of barrels, breastwall, staunching rings, pedestals of bearing, stoplog piers, well staining, transitionwall, etc

m3

31692.42 (d) Roadway slab, kerb, hoisting platform, top slab of barrel, etc m3

1706.58 (e) Top slab of bridge with main and cross girder of bridge, etc.

m3

Item no S-7 Providing & laying plain / reinforced ordinary portland cement concrete of M-30 grade with cement, sand, and coarse aggregates including centering, shuttering, batching, mixing, transporting, placing, vibrating, smooth finishing, curing etc. complate (MACHINERY BASED )

5.82 Top slab of bridge with main and cross girder of bridge, etc m3

Item no S-8Providing & laying plain / reinforced ordinary portland cement concrete of M-35 grade with cement, sand, and coarse aggregates including centering, shuttering, batching, mixing, transporting, placing, vibrating, smooth finishing, curing etc. complate. ( MACHINERY BASED )

11.75 Top slab of bridge with main and cross girder of bridge, etc m3

Item no S-9 Providing & Placing in position rainforcement bars including cutting, bending, welding joints where necessary, hooking etc. complete as per drawing for all lead and lifts

28052.50 (a) HYSD t 0.00 (b) TMT t 0.00 (c) TMT-CRS t

Item no S-10 Providing and fixing in position P.V.C. heavy duty water stops in barrels, troughs and wing walls,etc. with expansion joints as shown in the drawing including filling the joints with asphalt pad or bitumen cork board of approved quality.(Asphalt pad payable seperately)

1049.90 (a)225 mm WIDE P.V.C. WATER STOP m

3415.74 (b) 300 mm WIDE P.V.C. WATER STOP m

2928.92

Item no S-11 Providing and fixing in position pre moulded asphalt or bitumen cork board of approved quality and specifications as per design and drawing and as directed.

(a) 12 mm thickness m2 0.00 (b) 20 mm thickness m2 0.00 (c) 25 mm thickness m2

509.00

Item no S-12Providing cast in citu R C C parapet wall including kerb with controlled cement concrete of M-25 grade as per detailed drawing including batching, mixing, placing, centering, shuttering, rodding, vibrating, smooth finishing, curing, including providing and laying reinforcement as per design and drawings including applying three coats of white or colour wash etc. complete. (i) Square crossing (0.15 m thick) Rmt

Item no S-13 providing & fixing in position 0.75 m long G.I. water spouts of specified dia.

136.00 ( a ) G.I. Pipe 100 mm dia. No.

2032.90

Item no S-14 Providing and laying wearing coat 100mm. thick at center and 50mm thick at ends of compacted asphaltic concrete with tack coat of 0.50 Kg/m2 using stone aggregates as per gradation and asphalt at 6.5% (which will vary as per design of mix in laboratory) to have the required specific gravity of the compacted final mix by weight of total mix per binder by hot mix hot laid process including consolidation and providing required plant and machinery, cost of fuel, oil, lubricant, labour charges etc. complete. (a) Machinery based m2

242.50

Item no S-15 Providing and laying 75 mm thick wearing coat of ordinary portland cement concerete M-15 grade including laying in proper camber, tamping,screening, finishing, brooming or grooving etc. complete for all leads and lifts. Machinery based m2

662.40

Item no S-16 Providing and laying rubble for launching apron including hand packing and filling the voids with quarry spauls as directed m3

127.16

Item no S-18Providing panel pitching having panels of 3.0 m x 3.0 m.with M-15 grade concrete walls, 0.3 m wide and 1.0 m deep around pannels including filling pannels with 15 cm thick sand layers, 15 cm thick gravel m2

layer and 35 cm thick rubbel filling as shown in the drawing and filling the voids with earth as directed

Item no S-19 Providing and laying dry rubble pitching of various thickness to required grade including trimming of earth work, hand packing the interstices with spauls, filling earth in interstices pannelling complete for all leads and lifts.

328.80 (a) 300 MM THICK m2

Item no S-20 Providing and fixing post and 38 mm dia pipe railing as per detailed drawing including angle iron post of size 80mm x 50mm x 10mm fixed in C.C. block (1:3:6) of size 0.30 m x 0.30 m x 0.30 m etc. as per specifications including 3 coats of oil painting to steel work and as directed etc. complete.

1195.76 ( a ) Three rows m

5120.00

Item no S-22 Providing and fixing removable hand railing 1.10 m height using double angle iron post of size 80mm x 80 mm x 10 mm M.S.angle and two rows of 38 mm dia G.I. pipe and block out 10 mm thick M.S.plate 150 mm x 150 mm x 10 mm size with M.S.angle with 12 mm dia bolts, nuts including 3 coats of oil painting to steel work and as directed etc. comlete m

129.40

Item no S-23 Providing and laying in position 100 mm dia A.C. Pipe for weep holes with non corroding jali in abutments, wing walls, retaining walls etc. complete m

772.53

Item no S-24 Providing filter layer of sand and gravel of specified size as shown in the drawing in even specified thickness, compacting, dressing etc. complete. m3

Item no S-25Providing and fixing in position ( different diameter ) I.S.,NP-3 class reinforced pipe with caulking the joints with cement mortar 1:1 proportion,using jute string soaked in cement slurry, finishing joints and laying pipes to the designed grade and levels, curing etc. complete for all leads and lifts.

320.00 (a) 900 mm dia m 75.00 (b) 1000 mm dia m

459.10

Item no S-26 Providing and placing 150 mm PVC pipe in the kerb (both side of bridge) including cutting, fixing, laying and keeping in position etc. completed. m

32.00 Item no S-27 No.

Providing and fixing in position sign boards of standard size 0.45 m x 0.30m with M.S. angle 40mm x 40mm x 6mm with 3mm thick iron plate,3 m height in 1:5:10 proportion concrete block size 40cm x 40cm x 75 cm including radium paint on both side etc. complete.

30.00

Item no S-28 Providing and fixing in position canal data boards of standard size 1.20 m x 0.90 m with M.S. angle 40mm x 40mm x 6mm with 3mm thick iron plate, 3 m height in 1:5:10 proportion concrete block size 40cm x 40cm x 75 cm including painting existing data on the board etc. complete as directed. No.

139.10

Item no S-29 Providing and laying 12 mm thick PVC sheet at bottom and polysulphid sealent at top(in two parts) all around the pier as per drawing. m

167.04

Item no S-30 Providing and fixing metal expansion joints for road bridge, including filling the joints with asphalt joint filler as per drawing. m

Item no S-31Providing and fixing in position, true in Iine and level, POT-PTFE beaing for the following type and capacity as per the drawing and technical specification as directed by Engineer in charge etc. complete (A) Sliding POT-PTFE bearing

(a) Free bearing 27.00 (i) 81 t No.

(b) Logiuinally guided 18.00 (i) 74 t No. 24.00 (c ) T.G. No.

0.00 (d ) Fix Pot bearing 21.00 (i) 74 t No.

273668.40

Item no S-32 Providing and fixing in position fully moulded elastomeric bearing pads as per drawing.(SOR It no S-39 Year 2008-09 P.18) cm3

0.00 Item no S-33 Providing and fixing 150 mm dia C.I. Pipe as per drawing and as directed m

2.00

Item no S-34 Providing and laying float well with R.C.C. NP4 (non pressure) pipe of 900 mm dia as per drawing with spigot and socket end with filling joints in cement mortar 1:1 using 'O' rubber ring finishing joint and laying pipe as shown in the drawing including supplying and laying 150 no.

mm dia A.C. pipe with completing and fitting with 900 mm dia pipe (excluding the cost of excavation and refilling with embankment).

Item no S-35 Excavation of canal (Approach and Tail channel) in all sorts of soil including soft and hard murrum including depositing the excavated stuff in uniform layers in canal banks or as and where directed etc.complete in varying lead up to 500 m and with all lifts.

9185.00 (a) Above water table m3

6.08

Item no S-36Suppying and instaling anchor bolts for embeded parts for radial gates, stop logs and hoists of cross regulators, escapes etc. as per drawing and as directed t

Item no S-37 Providing & laying plain / reinforced ordinary portland cement concrete of various grade with cement, sand, and coarse aggregates including centering, shuttering, batching, mixing, transporting, placing, vibrating, smooth finishing, curing etc. complate. (MACHINARY BASED ) (EXCLUDING DEWATERING)

0.00 Foundation 18088.00 (ii) M 10 grade.(Cement level-220 kg) m3

ISQ No. 4 -Service Road

Quantity Description of Item Unit

593985.00 Item No. R-1 Earth work in embankment using selected soil, soft & hard murrum excavated from approved borrow area / village tanks etc. Including royalty charges, conveying, spreading in uniform layers, breaking clods and dressing to the designed canal section etc. with lead upto 1 km and all lift . (For canals having capacity beyond 8.5 cumecs) m3

21632.01 Item No. R-2 Excavation of canal in all sorts of soil including soft and hard murrum including depositing the excavated stuff in uniform layer in canal banks or as and where directed etc complete in varying lead upto 500 m and with all lifts. m3

593985.00 Item No. R-3 Compaction of earth work in embankment in uniform layers at optimum moisture content to required dry density including watering, rolling with suitable type of roller specified capacity etc. complete.) m3

24989.088 Item No. R-4 Collecting, carting and stacking 40 mm to 63 mm size metal (on road side) including filling the standard size boxes as directed. m3

24989.088 Item No. R-5 Labour charges for spreading 40 mm to 63 mm size material to the required grade and camber including barreling etc complete. m3

8100.00 Item No. R-6Collecting, carting and stacking soft murrum ( on road side ) including filling the standard size boxes as directed. m3

8100.00 Item No. R-7 Labour charges for spreading soft murrum as directed. m3

142720.00 Item No. R-8 Consolidation WBM surface with roller including watering etc. complete as directed.

m2

1562.63 Item No. R-9 Providing and laying bituminous 75 mm thick lean bound mecadam (LBM) in two layers considering 0.66 m3 per MT mix material with machiner crushed stone aggregate and asphalt for tack coat @ of 10 kg / m2 (on existing metal surface) using 2.5 kg per 10 m2 on existing bituminous surface using 30 kg of bitumenous per MT of total mix including mixing the aggregate, heating the asphalt including mixing by continuous batching from hot mix plant and spreading the same by paver finisher and consolidation with power roller including providing all equipment by the contractor and flushing sand @ 0.30 cum per 100 m2. MT

403.20 Item No. R-10 Providing and laying 20mm premix asphalt carpet with 4.20 tonne material per 100 m2 with machine crushed aggregate and asphalt for tack coat 10 Kg/ 10m2 including 35 kg of Bitumen per ton (3.5%) for mixing aggreagate, heating the asphalt including mixing by continuous batching hot mix plant, spreading the same by paver finisher and consolidation with power roller including providing all equipments by contractor etc. complete. MT

359.41 Item No. R-11Providing and laying bitumen mix seal surfacing using 2.80 tonne material per 100 m2 with machine crushed aggregate and using 44 Kg. Of bitumen per ton of mix aggregate (4.4%) for mixing aggregate, heating the asphalt including mixing by continuous batching hot mix plant, spreading the same by paver finisher and consolidation with power roller including providing all equipments by contractor etc. complete. MT

10.00 Item No. R-12 Providing and fixing C.C. 1:2:4 km stone of standard size 0.75 m x 0.20 m x 0.15 m along the canal in C.C. 1:4:8 block of size 35cm x 25cm x 60 cm including curbing and painting, lettering etc complete. No.

100.00 Item No. R-13 Providing and fixing indicator stone of size 20 cm x 20 cm x 75 cm including white washing in two coats. No.

2118.00 Item No. R-14 Providing and fixing guard stone of size 20 cm x 20 cm x 75 cm including white washing in two coats (Dhrangadhra stone)

No.

ISQ No.5- Gates

Radial Gate

Qty. Description of Item Unit

1 2 3 Manufacture, supply of radial gates components including performance

test.

Embeded and stationery parts of radials gates consisting of wall plats, sill plates, trunnion boalts, nuts for anchor rod and hoist anchor bolts for gate having steel platform, trunion brackets and other relevant components and accessories as per drawing including painting with primer coat and colour including second stage concreting etc. complete as per drawing and specifications.

4 (a) CR at KBC Ch 46570 m Set

Gate leaf for each radial gate consisting of skin plate assembly including rubber seals , guide rollers , horizontal stiffeners , vertical girders , arms , bracings , trunion assembly i.e hub , pin , plates, bushing and other relevant components and accessories with erection cleats and splicing arrangement, painting with primer coat and colour as per drawing and specification .

4 (a) CR at KBC Ch 46570 m Set

Manufacture and supply of various capacity electrically operated rope drum hoist components and equipments as under including performance test .

Hoist motor cabin, including motors with adjustable (variable) speed device and drum unit, starters, contactors, brakes, worms reducers and manual drive mechanism and other relevant component.

Gear reduction units, including gears, drums, wireropes, shafts, gear cases, covers, pedestal blocks, bearings, lines shafts, couplings and other relevant components as per drawing and specification.

Manufacture,supply and fixing of Hoist Plate form consisting of Beams,cross members,chequered plates,railing angles,access ladder,railing etc.complete including painting with primer coat and colour as per drawing and specifications.

4 (a) CR at KBC Ch 46570 m Set

Erection of gate leaves, vertical girders, arms, trunnion and embeded parts and stationary parts which includes second stage concreting, joining and fixing them in true line and level and welding and fitting rubber seal etc.

Erection of gate hoist equipment and components including lifting and lowering, stopping , closing of gate so as to ensure smooth and water tight operation . This item also includes supply and laying of cables from control room equipment to the individual gate hoist motor, measuring instruments including, limit switches etc. as per drawings and specification etc complete.

4 (a) CR at KBC Ch 46570 m Set

GATE CONTROL ROOM EQUIPMENTS

Manufacture, supplying and erection of gate control cabinet, power distribution panel, gate position indicator limiting alarms etc. including wiring in control room provide by SSNNL on site as per drawing and specifications including performance test.

4 ( Four ) Gate control panel

1 (a) CR at KBC Ch 46570 m Set

Vertical GATES (HR)

2 4 3

Supplying ie. Manufacturing, transportation and erecting of vertical gates components including performance test.

Manufacture, supplying, and erection of vertical gates consisting of gate leaf, stiffeners, rubber seals, embeded parts as shown in drawing including cost of materials, fabrication, painting, erection in position with all accessories, second stage concreting etc complete and performance test as per drawings and specifications.

2 (a) HR at Ch. 51180-L Set

2 (a) HR at Ch. 51180-R Set

Manufacture, supply and erection of 8 tonne electrically operated screw hoist and hoist platform for operating the vertical gate consisting of capstan, having worm and worm wheel, stem, motor, throst bearing, electromagnetic brake, clutch, limit switches, gate opening measurement device, hand operation device with all accessories and equipment, painting .Supplying and installing the gate control cabinet with interface terminal block in control room, supplying and laying cables from control / monitoring room to the individual gate so as to enable the lifting, stopping and lowering the gate to ensure smooth and watertight operation etc. complete as per drawings and specifications. (Control room provided by SSNNL on site)

Vertical GATES (Escape)

Supplying ie. Manufacturing, transportation and erecting of vertical gates components including performance test.

Manufacture, supply and erecting of vertical gate consisting of gate leaf, stiffeners, rubber seals, embeded parts as shown in drawing including cost of materials, fabrication, painting, erection in position with all accessories, second stage concreting

2 (a)Escape at Ch. 46570-L Set

2 (b)Escape at Ch. 54830-L Set

Manufacture, supply and erection of 8 tonne electrically operated screw hoist and hoist platform for operating the vertical gate consisting of capstan, having worm and worm wheel, stem, motor, throst bearing, electromagnetic brake, clutch, limit switches, gate opening measurement device, hand operation device with all accessories and equipment, painting .Supplying and installing the gate control cabinet with interface terminal block in control room, supplying and laying cables from control / monitoring room to the individual gate so as to enable the lifting, stopping and lowering the gate to ensure smooth and watertight operation etc. complete as per drawings and specifications. (Control room provided by SSNNL on site)

2 (a)Escape at Ch. 46570-L Set

2 (b)Escape at Ch. 54830-L Set

Stoplog Gates (CR)

4

Manufacturing, Supplying of Radial gates components including performance test. Manufacturing, Supply and erection of embedded and stationary parts of stoplog gate at U/S of CR consisting side seal plates, sill plates and other parts as shown in the drawing in all the groove left for stplogs including painting coat and colour including second stage concreting including cost of material and labour, scaffolding and to give performance test etc. as per drawing and specification.

Set

2 (a) HR at Ch. 51180-L Set

2 (a) HR at Ch. 51180-R Set

4

Manufacturing, Supply and erection of embedded and stationary parts of stoplog gate at D/S of CR consisting side seal plates, sill plates and other parts as shown in the drawing in all the groove left for stplogs including painting coat and colour including second stage concreting including cost of material and labour, scaffolding and to give performance test etc. as per drawing and specification. [As per Rate Analysisi-1 (1.2)]

Set

2

Manufacturing, Supply and assembling the required number of tiers of the stoplog gates in to stoplog groove with the help of lifting beam of appropriate capacity and disassembling the same and stacking in stock yard on canal bank or near by appropriate place including painting with primer coat and colour and to give performance test etc. complete as per drawing and specifications.

Set

Stoplog Gates (HR)

1

Manufacturing, Supplying of Radial gates components including performance test. Manufacturing, Supply and erection of embedded and stationary parts of stoplog gate at U/S of HR consisting side seal plates, sill plates and other parts as shown in the drawing in all the groove left for stplogs including painting coat and colour including second stage concreting including cost of material and labour, scaffolding and to give performance test etc. as per drawing and specification.

Set

1

Manufacturing, Supply and assembling the required number of tiers of the stoplog gates in to stoplog groove with the help of lifting beam of appropriate capacity and disassembling the same and stacking in stock yard on canal bank or near by appropriate place including painting with primer coat and colour and to give performance test etc. complete as per drawing and specifications.

Set

Stoplog Gates (HR)

4

Manufacturing, Supplying of Radial gates components including performance test. Manufacturing, Supply and erection of embedded and stationary parts of stoplog gate at U/S of Escape consisting side seal plates, sill plates and other parts as shown in the drawing in all the groove left for stplogs including painting coat and colour including second stage concreting including cost of material and labour, scaffolding and to give performance test etc. as per drawing and specification.

Set

4

Manufacturing, Supply and erection of embedded and stationary parts of stoplog gate at D/S ofEscapeR consisting side seal plates, sill plates and other parts as shown in the drawing in all the groove left for stplogs including painting coat and colour including second stage concreting including cost of material and labour, scaffolding and to give performance test etc. as per drawing and specification.

2

Manufacturing, Supply and assembling the required number of tiers of the stoplog gates in to stoplog groove with the help of lifting beam of appropriate capacity and disassembling the same and stacking in stock yard on canal bank or near by appropriate place including painting with primer coat and colour and to give performance test etc. complete as per drawing and specifications.

Set

ISQ No. 6 – Control Cabin

1 2 3 108.81 Item No.- 1 Excavation for foundation of structures in all

sorts of soils including sandy and gravelly soil, soft and hard murrum including dewatering where required including depositing the excavated stuff as and where directed including backfilling the trenches with suitable excavated stuff etc. complete for lead upto 50 m and for depth of cutting as under.

Cum 18.01 Item No.- 2 Providing and laying cement concrete

1:5:10 (1 cement, 5 sand, 10 graded Brick aggregates 40mm nominal size)and curing complete excluding cost of for mworin (a)Foundation and plinth

Cum 34.46 Item No.- 3 (a) Brick work using common Burnt clay

building bricks having crushing strength not less then 35 kg/cm2 in foundation and plinth in cement mortar 1:5 (1cement:5finesand) (b) Conventional

Cum 27.20 Item No.- 3 (b) Extra for brick work in super structure

above plinth level upto (b) Conventional

cum 6.50 Item No.- 4 Half brick masonary in common burnt clay

building brick having crushing strength not less than 35 kg/cm2 in cement mortar 1:4(1 cement, 4 coarse sand ) jn foundation and plinth including Extra for brick work in super structure above plinth level up to floor two level.

Sqm

1.70 Item No.- 5 Providing and laying plain or reinforced cement concrete of 1:3:6 nominal mix (1 cement, 3 sand, 6 coarse aggregate) including centering, shuttering, batching, mixing, transforting, placing, vibrating, smooth finishing, curing etc. complete.

cum 3.00 Item No.- 6 Providing and laying plain cement concrete

of 1:2:4 nominal mix (1 cement, 2 sand, 4 coarse aggregate) including centering, shuttering, batching, mixing, transporting, placing, vibrating, smooth finishing curing etc. complete.

Cum 31.00 Item No.- 7 Providing and laying reinforced cement

concrete of 1:1.5:3 nominal mix (1 cement, 1.5 sand, 3 coarse aggregate) including centering, shuttering, batching, mixing, transporting, placing, vibrating, smooth finishing curing etc. complete

Cum 28.36 Item No.- 8 Back filling the foundation trenches around

the structures etc. with selected excavated stuff including watering, ramming, compacting etc. complete.

Cum. 2.73 Item No.- 9 Providing and placing in position mild steel or

high yield strength deformed (HYSD) reinforcement bars including cuffing, bending, binding, hooking, etc. as per drawing.

M.T. 233.50 Item No.- 10 Providing 15 mm. thick cement plaster in

single coat on fair side brick/ concrete wall, ceiling for for interior plastering upto floor two level finished even and smooth in cement mortar 1 : 3 (1 cement : 3 sand) finishing with a floating coat of neat cement slurry including scaffolding, curing etc. complete.

Sqm.

148.00 Item No.- 11 20 mm. thick sand faced cement plaster on walls up to height 10 m. above GL consisting of 12 mm. thick backing coat of cement mortar 1:3 (1 cement :3 sand) and 8 mm thick finishing coat of cement mortar 1:1 (1 cement, 1 sand) etc. comp.

Sqm 34.00 Item No.- 12 Providing and laying kota stone slab

flooring over 20 mm. (average) base of cement mortar 1:6 (1 cement : 6 coarse sand) or L. M. 1 : 1.5 and laid over and jointed with grey cement slurry including rubbing and polishing completed. (A) 25 mm thick

Sqm 2.30 Item No.- 13 Providing and laying white glazed tiles 6mm

thick in flooring having mat finish treads of steps, and landing laid on bed of 12mm thick cement mortar 1:3 (1 cement, 3 coarse sand) finished with flush pointing in whitecement)

sqm. 6.75 Item No.-14 Providing and laying kota stone slab 25 mm

thick in risers of steps, Dado & pillars laid on 10mm thick cement mortar 1:3 (1 cement : 3 coaese sand ) and jointed with grey slurry, rubbing and polishing etc. complete.

Sqm. 12.00 Item No.- 15 Providing and laying white glazed tiles 6 mm

thick in skirting, risers of steps, and dedo on 10 mm. thick cement mortar 1:3 (1 cement, 3 coarse sand ) pointing in white cement slurry.

sqm.

4.20 Item No.-16 Providing and fixing 3.5 m wide rolling shutter of approved make made of 30 mm wide MS laths interlocked together through their entire length and joined together at the end locks mounted on specially designed pipe shaft with bracket plates, guide channels and arrangement for inside outside locking with push and pull operation including the cost of hood cover and spring etc. completed.

sqm. 7.60 Item No.-17 Providing and fixing steel shutter door of

pressed steel panel of 18 gauge MS sheet having ISA 40 × 40 × 4 mm angle frame with fixtures, fastning with primer etc as per drawing.

sqm. 7.55 Item No.-18 Providing and fixing window having ISA 40x

40x 4 mm angle frame having 5 mm thick glass shutter and 12 mm rods fixed within frame including fixtures, fastening including applying one coat of primer etc, as per drawing.

sqm. 0.30 Item No.- 19 Providing and fixing Ventilators having ISA

40 x 40 x 4 mm angle frame with stainless steel jali of 12 gauge wire fixed within frame including applying one coat of primer etc. as per drawing.

sqm 10.50 Item No.- 20 Providing and fixing 40 mm square & 4 mm

thick M.S. gate with 25 x 4 mm M.S. flats at required spacing including brackets, outside and inside locking with push/pull operation with primer coat etc. complete as directed.

sqm 234.00 Item No.- 21 White washing with lime on wall surfaces,

ceiling ( two coats ) to give an even shade including thoroughly brooming the surface to remove all dirt, dust, mortar drops and other foreign matter.

sqm.

148.00 Item No.- 22 Finishing wall with water proofing cement paint of approved brand and manufacture on wall surface three coats to give an even shade including thoroughly brooming the surface to remove all dirt, dust, and remains of loose powdered materials

sqm 61.00 Item No.- 23 Applying priming coat over new steel and

other metal surface including preparing the surface by thoroughly cleaning oil, grease, dirt and other foreign matter and scoured with brushes fine steel wool, scrapers and sand paper with ready mixed priming paint brushing red lead

sqm. 61.00 Item No.- 24 Painting two coats (excluding priming coat)

on previously painted steel and other metal surface with enamel paint to give an even shade including cleaning of all dirt, dust and other foreign matter.

sqm Item No.- 25 Providing and laying in trenches, galvanized

mild steel tubes (medium grade) of the following nominal bore & tube fittings and clamps including making good thewall, ceiling and floor.

9.00 (A) 15 mm dia m 3.00 (C) 25 mm dia m 8.00 Item No.- 26 Providing and fixing cast iron spigot and

socket, soil waste venulating pipes of the following nominalsize (B)75mmdia

m 1.00 Item No.- 27 Providing and fixing in position cowl vent to

pipes (i)75mmdia

No.

Item No.- 28 Providing and fixing (to level or slopes ) and jointing with stiff mixture of cement mortar in proportion 1:1 salt glazed stoneware pipes following nominal internal diameter including testing of pipes and joints etc. complete.

14.00 (A) 100 mm dia m 15.00 (B) 150 mm dia m 2.00 Item No.- 29 Providing and fixing cast iron (spun) nahni

trap of the following nominal dia of self cleaning design with CI screwed down or hinged grating including cost of cutting and making good the hole in walls and floors 100 mm inlet and 50 mm outlet

No. 1.00 Item No.- 30 Providing and fixing water closet squatting

pan( Indian type W /C pan ) size 580 mm with providing and fixing in cement mortar 1: 3 ( 1 cement : 3 coarse sand ) A pair of white vitreous china 250mm x 120 mm x 30 mm foot rest for long pattern squatting pan water closet.( Earthwork, bed concrete and trap to be measured and paid for separately). (A) vitreouschina (i)long pattern of white colour.

No. 1.00 Item No.- 31 Providing and fixing 100mm size “ P “ or “

S “ trap for water closet squatting pan including jointing the trap with the pan in cement mortar 1: 1( 1 cement : 1 fine sand ).

Pair Item No.- 32 Providing and fixing chromium plated

brass half turn flush cock of approved quality including fixing in pipeline etc. complete.

1.00 (I) 25mm dia. No. 1.00 Item No.- 33 Providing and fixing wash basin with single

hole for piller tap with C.I. or M.S. brackets painted white including cutting holes and making good the same but excluding fittings.

No.

(A) Vitreous china (i) Flat back wash basin of size 500 mm x 400 mm (ii) In white colour

Item No.- 34 Providing and fixing C.P. brass waste for wash basin or sink.

1.00 (A) 32 mm dia No.

Item No.- 35 Providing and fixing screw down bib taps of following size. (B) Brass cromium plated screw down bib tape.

1.00 (i) 15 mm dia. No. 2.00 Item No.- 36 Providing and fixing 600 mm x 450 mm

leveled edge mirror of superior glass, mounted on 6 mm thick A.C. sheet or plywood sheet and fixed to wooden plugs with C.P. brass screws and washers.

No. Item No.-37 Providing and fixing piller tap, capstan head,

screw down high pressure with screws, shanks and back nuts.

1.00 (A) 15 mm dia No.

Item No.- 38 Providing and fixing gun metal check or non return full way wheel valve.(S.O.R. R & B Dn. Patan. It. No. 23.99.(C) P. No. 92 Year 2008-2009)

1.00 (A) 25mm dia No.

Item No.- 39 Providing and fixing brass screw down stop tap.

1.00 (A) 15mm dia No.

1.00 Item No.- 40 Constructing brick masonary road gully chamber 500 mm x 450 mm x 600 mm including 500 mm x 450 mm C.I. Horizontal grating with frame complete.

No. 1.00 Item No.- 41 Constructing brick masonary chamber for

under ground C.I. inspection chamber and bends with bricks having crushing strength not less than 35 Kg/cm2 in CM 1:5 Cl. cover with frame (light duty) 455 mm x 610 mm internal dimension, total weight of cover with frame to be not less than 38 kgs. (weight of cover 23 kg and weight of frame 15 Kg.) RCC top slab with 1:2:4 mix ( 1 cement, 2 coarse sand : 4 graded stone aggregates 20 mm size ) foundation concrete 1:5:10 inside plaster 15 mm thick with cement mortar 1: 3 finished smooth with a floating coat of neat cement on walls and bed concrete etc.complete. (i) Inside dimensions, 500mm x700mm and 450 mm deep for pipe line with one or two inlets.

No. 1.00 Item No.- 42 Providing and Constructing under ground

septic tank including 1.00 m. excavation of size 1.80 m x 1.20 m x 1.20 m (inside dimension) with 0.23 m. thick outer wall and half brick partition wall with brick masonary in CM 1:5 (1 cement, 5 sand) including applying single coat of water proofing plaster 20 mm. thick in cement mortar 1:3 (1 cement, 3 sand) with cement vata at all corner of size 10 cm. x 10 cm. including B.B.C.C. 1:5:10 for base and plain cement concrete (10 cm. thick) 1:2:4 at bottom including covering the top with stone including providing vatas in cement mortar 1:3 (1 cement, 3 sand) with finishing curing etc. complete as directed.)

No.

1.00 Item No.- 43 Providing soak pit of 5.0 CM volume including excavating and filling brick bats with dry masonary work at top for 45 cm. height including covering the top with stone including providing vatas in cement mortar 1:3 (1 cement, 3 sand) with finishing curing etc. completed as directed.

No. 97.00 Item No.- 44 Applying general insecticide paste control

treatment to floors, cupboards etc. including labours, materials etc complete.

Sqm. Item No.- 45 Providing and installing PVC ready made

water tank as directed etc. complete.

1.00 (i) 500 Litres capacity (At ground level) No. 1.00 (ii) 250 Litres capacity( Over head ) No. 47.26 Item No. - 46 Providing and laying pre cast terrazzo tiles

20mm. thick with white, black (or white and black or of the colour specified in tender item ) marble chips of size up to 6mm laid in floor, treads of steps and landings on a bed of 25mm. average thickness of lime mortar 1:1.5 ( 1 lime putty : 1.5 sand ) or C.M. 1 : 6 jointed with neat cement slurry mixed with pigment to match the shade of tiles including rubbing and polishing complete with pre cast tiles of ( A ) Light shade pigment with white cement ( in top layer only )

Sqm. 4.00 Item No.- 47 Providing and Fixing on wall face 110mm

dia. PVC ( 6.0 kg. F / sq.cm. ) rain water pipe with PVC bend including jointing with PVC adhesive etc. complete.

No.

105.00 Item No.- 48 Providing and fixing 1.20 m. high fencing with two metre long M.S.angle post 40mm x 40mm x 6mm and oil painting 3 coats, fixed at 2.5m.c/c with 5 horizontal lines and two diagonals of galvanized steel barbed wire weighting 9.38 kg per 100m., strained and fixed to posts with G.I. staples including fixing posts in ground with 0.5m.x 0.5m. 0.5 m.block in c.c.1:5:10 etc. complete.

m. 2065.00 Item No.- 49 Earthwork in embankment using selected

soil, soft and hard murrum excavated from approved borrow area / village tanks etc. including conveying, spreading in uniform layers, breaking clods and dressing etc. with lead up to 1.0 km. and all lifts

cum. 2065.00 Item No.- 50 Compaction of earthwork in embankment in

uniform layers at optimum moisture content to attain 95 % maximum dry density including watering, rolling with suitable type of roller etc. complete.

cum 18.00 Item No.- 51 Providing and fixing lightning arrester as

directed by Engineer in charge

Kg. 77.00 Item No.-52 Providing and erecting 20 mm dia and 1.5

mm. thick rigid PVC pipe confirming to ISS complete, erected with necessary fittings, fixed with adhesive solution with 16G GI fish wire for concealed in wall/slab with necessary cementation .

m.


Recommended