of 35
7/27/2019 2001 Survey of Relaying Test Practices
1/35
7/27/2019 2001 Survey of Relaying Test Practices
2/35
This is a special report of the IEEE Power System Relay Committee.
Page i January 2002
Contents
1. Introduction.. 12. Personnel Requirements 1
2.1 Personnel who Calibrate, Test and Maintain Relays.. 12.2 Education Level Required.. 2
2.3 Training Requirements .. 23. Relay Test Procedures.. 4
3.1 Resources Used to Develop Relay Test Procedures.. 43.2 How Normal Relay Testing is Accomplished 5
4. Allowable Relay Calibration Tolerances... 84.1 Determination of Allowable Relay Tolerances.. 84.2 Relay Applications that Require Tighter Tolerances. 9
4.3 Relay Applications for which Looser than Normal Tolerances are Permitted. 104.4 Documentation of Allowable Tolerances by the Relay Users. 10
5. Factors that Influence Relay Test Schedules 115.1 Basis for Test Intervals for Relays in T&D Substations 115.2 Rationale for Shorter Test Intervals 135.3 Rationale for Longer Test Intervals 13
5.4 Basis for Test Intervals for In-Plant Relays (Generator, Switchgear, etc.) 145.5 Test Intervals Actually Met in Practice.. 14
6. Relay Test Intervals.. 156.1 Actual Relay Test Intervals Presently Used.. 156.2 Comparison of Relay Test Invervals with the 1991 Survey.. 20
7. Relay Test Equipment.. 25
7.1 Acquisition of Test Equipment.. 257.2 Passive vs. Solid State Relay Test Sets.. 257.3 Dynamic Relay Test Equipment. 257.4 Power Swing Test Equipment.267.5 Computer Controlled Test Sets.. 277.6 COMTRADE Compatibility and Usage. 27
7.7 Portability of Test Equipment. 28
8. Testing Protective Relays in a Particular Station.. 289. Protective Relaying Scheme Operational Test Conditions and Intervals..299.1 Operational Trip Testing. 299.2 Operational Trip Test Intervals.. 299.3 Personnel Who Perform Operational Trip Tests.30
10. Maintenance Program Effectiveness. 3010.1 Criteria Used3110.2 Correlation between Measurements and Failure Rates.. 3110.3 Satisfaction of the Utilities Maintenance Programs.. 32
11. Bibliography.. 33
7/27/2019 2001 Survey of Relaying Test Practices
3/35
This is a special report of the IEEE Power System Relay Committee.
Page 1 January 2002
1. Introduction
In 1971, the IEEE Power System Relaying Committee reported the results of A Survey of Relay Test Practices[1], which reflected the responses of 125 electric utilities with a total of 1,157 generating stations, 5,096
transmission substations, and 17,849 distribution substations.
In 1991, the IEEE Power System Relaying Committee reported the results of A Survey of Relay Test Practices[2], which reflected the responses of 146 electric utilities with a total of 1,229 generating stations, 9,814transmission substations and 26,680 distribution substations.
This present survey is based on 2001 data supplied by 79 electric utilities with an aggregate of 632 generatingstations, 8,461 transmission substations and 12,499 distribution substations. Results of these surveys are comparedto show significant changes in test practices and a trend toward longer test intervals.
The figures included in this report are named to identify with the Section of the survey from which the results arecompiled.
2. Personnel Requirements
2.1 Personnel who Calibrate, Test and Maintain Relays
As a rule, the number of relay personnel is proportional to the size of the service area of the utility. Exceptions to
this rule are those utilities having highly congested and heavily populated service areas which require significantlymore relay personnel than do those utilities with an equivalent size service area that is less congested and not asheavily populated.
82 % of the respondents use specialists to calibrate, test and maintain their protective relays and associatedequipment. 18 % of the respondents use non-dedicated personnel to perform relay testing in conjunction with other
work such as circuit breaker, transformer, or battery maintenance. None of the respondents used any type ofcontract personnel for relay testing or maintenance.
Figure 1: Personnel who Calibrate, Test and Maintain Relays
6%
82%
8%0% 4%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
PercentageofRespondents
Specialists whocalibrate and
test relays only
Specialists whoalso do
functional
testing of relay
circuits
Non-specialistswho also work
on breakers,
transformers,
etc.
Outsidecontracted relay
testers
Other
7/27/2019 2001 Survey of Relaying Test Practices
4/35
7/27/2019 2001 Survey of Relaying Test Practices
5/35
This is a special report of the IEEE Power System Relay Committee.
Page 3 January 2002
Figure 4: Training Hours per Test Personnel Each Year
Figure 5 shows that the working group foreman or test team group leader concept is widely used for trainingpurposes by most utilities. The idea behind this type of training is that groups of personnel are assigned to workunder the supervision of various knowledgeable senior relay foremen. Periodically, the various groups oftechnicians are rotated to work for another foreman until all the technicians have worked for all foremen. This typeof training has many advantages for management.
Figure 5: Utilities that Use a Working Relay Foreman or Test Team Group Leader to Train Relay TestPersonnel
Significantly, 97 % of respondents utilize the same personnel to maintain both electromechanical relays andelectronic relays, as indicated in Figure 6. Figure 7 indicates that most of the respondents require their personnel tohave specialized electronics training, which is normally provided as on the job training.
63%
37%
0%
10%
20%
30%
40%
50%
60%
70%
PercentageofRespondents
Use Do Not Use
16%
27%
31%
4%
35%
46%
36%
23%
16%16%
21%
27%
15%
6%
3%
12%
8%
3%3%
8%9%
3%1%
9%
0%0%
4%
14%
0%0%1%3%
0%
5%
10%
15%
20%
25%
30%
35%
40%
45%
50%
PercentageofRespondents
None 8 hours or
less
8-16 hours 16-24 hours 24-32 hours 32-40 hours More than 40
hours
Other
Relay Manufacturers
Test Equipment Manufacturers
Relay-Specific Independent
Relay-Specific In-House
7/27/2019 2001 Survey of Relaying Test Practices
6/35
This is a special report of the IEEE Power System Relay Committee.
Page 4 January 2002
Figure 6: Personnel who Calibrate and Maintain Non-Electromechanical Relays
Figure 7: Utilities that Require Specialized Electronics Training for Personnel who Calibrate and/or Test Non-Electromechanical Relays
3. Relay Test Procedures
3.1 Resources Used to Develop Relay Test Procedures
Figures 8 and 9 reflect the number of utilities who use In-House Procedures, Relay Manufacturers Data and/orEquipment Manufacturers Data for testing relays and their assessment of the value of each of these sources of datafor test procedures.
9 7 % 9 6 %
0 % 0 % 3 %4 %
0%
1 0 %
2 0 %
3 0 %
4 0 %
5 0 %
6 0 %
7 0 %
8 0 %
9 0 %
1 0 0 %
PercentageofRespon
dent
T h e s a m e p e r s o n n e l w h o
ca l i b ra te
e l e c t r o m e c h a n i c a l r e l a y s
P e r s o n n e l w h o d o n o t
ca l i b ra te
e l e c t r o m e c h a n i c a l r e l a y s
P e r s o n n e l w i t h s p e c i a l
t r a i n i ng to ca l i b ra te th i s
type o f r e l ay
M a i n t a i n N o n - E l e c t r o m e c h a n i c a l R e l a y s
T e s t & C a l i b r a t e N o n - E l e c t r o m e c h a n i c a l R e l a y s
84%
16%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
Percen
tageo
fRespon
den
ts
Required Not Required
7/27/2019 2001 Survey of Relaying Test Practices
7/35
This is a special report of the IEEE Power System Relay Committee.
Page 5 January 2002
Figure 8: Resources Used to Develop Relay Test Procedures
Figure 9: Value of In-House and Manufacturers Materials in Developing Relay Test Procedures
All of the respondents use the Relay Manufacturers materials as the basis for their testing, and many respondents
also use test equipment manufacturers materials to develop their test procedures.
3.2 How Normal Relay Testing is Accomplished
Figure 10 shows that 86 % of the respondents noted that they test relays using test plugs and secondary values, while10 % cleared the circuit and tested the relay circuit with secondary values. Only 1 respondent stated that his utility
tested relays using primary quantities.
99% 99%94%
1% 1%6%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
PercentageofRespondents
Used Not Used
In-House Procedures
Relay Manufacturers' Material
Test Equipment Manufacturers' Material
8%
1%
8%
48%
27%
48%44%
72%
44%
0%
10%
20%
30%
40%
50%
60%
70%
80%
Percentageo
fRespondents
Of little value Some value Very valuable
In-House
Relay Manufacturers
Test Equipment Manufacturers
7/27/2019 2001 Survey of Relaying Test Practices
8/35
This is a special report of the IEEE Power System Relay Committee.
Page 6 January 2002
Figure 10: How Normal Field Relay Testing is Accomplished
Figure 11 details the percentage of respondents who test other items during routine relay testing. It should be notedthat 28 % of those responding indicated that they perform all of the items shown in Figure 11 during the relaycalibration procedure.
Figure 11: Associated Items Also Tested During Routine Relay Testing
Figure 12 reflects that when field testing of electromechanical relays indicate that repairs are needed, 95 % of the
respondents rely on field personnel to do the repairs and only 5 % rely on the relay manufacturer. For non-
electromechanical relays, 25 % of the utilities rely on their field personnel, 3 % on trained lab technicians and 72 %on the manufacturer. This is a major shift from the 1991 survey where 62 % relied on their field personnel, 12 % ontrained lab technicians and only 26 % on the manufacturer.
1%
10%
86%
3%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
PercentageofResp
ondents
Applying primary
signals with the
primary circuit
cleared
Applying secondary
signals with the
primary circuit
cleared
Applying secondary
signals with test
plugs or drawout
relays
Other
42% 40%
88%
42%
29%
45%37% 38% 40%
16%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
PercentageofRespondents
Meters
Insulationof
wiring
Testtripping
CT/PT
Continuity
CT/PTRatio
VerifyCT
connections
Phasing
potentials
Fuseblocks
Control
circuits
Other
7/27/2019 2001 Survey of Relaying Test Practices
9/35
This is a special report of the IEEE Power System Relay Committee.
Page 7 January 2002
Figure 12: Personnel who Typically Repair Relays when Field Testing Determines that Repairs are Necessary
For use in testing non-electromechanical relays, Figure 13 indicates that 82 % of the respondents use test proceduresdeveloped especially for non-electromechanical relays.
Figure 13: How Field Testing is Accomplished for Non-Electromechanical Relays
Figure 14 shows that performance of relays in service is evaluated for relay operations during faults by analysis oftarget, event recorder and oscillographic data by 46 % of the respondents, while 40 % rely on periodic relay test
data. The 1991 survey revealed that 77 % evaluated performance of relays in service with operations during faultsby analysis of target, event recorder, and oscillographic data and only 22 % relied on periodic relay test data. Notethat the 1991 report stated that periodic relay testing seldom found problems with the relays.
25%
87%
3%
8%
72%
5%0% 0%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
PercentageofRespondents
Field testing
personnel
Trained lab
personnel
Manufacturer Other personnel
Non-Electromechanical
Electromechanical
14%
82%
0% 4%
0%
10 %
20 %
30 %
40 %
50 %
60 %
70 %
80 %
90 %
Percentag
eofRespondents
Using established
procedures for
electromechanical
relays
Using special
procedures
developed for non-
electromechanical
relays
Remote initiation of
self-diagnostic
features
Local initiation of
self-diagnostic
features
7/27/2019 2001 Survey of Relaying Test Practices
10/35
This is a special report of the IEEE Power System Relay Committee.
Page 8 January 2002
Figure 14: How In-Service Relay Performance is Determined
4. Allowable Relay Calibration Tolerances
4.1 Determination of Allowable Relay Tolerances
Figure 15 indicates that the majority of electric utilities surveyed use the protective relay Manufacturersrecommendations (65 %), while Knowledge and experience of the relay test personnel represents a significantnumber of electric utilities that rely on personnel within their respective organizations (27 %) for relay tolerances.
Figure 15: Determination of Allowable Relay Tolerances
The survey data indicates that a majority of relay manufacturers provide sufficient relay documentation that isacceptable to most engineers and technicians for maintenance and training purposes.
46%40%
0%
6% 8%
0%
5%
10%
15%
20%
25%30%
35%
40%
45%
50%
PercentageofRespondents
Analysis of
performance
after faults
(targets,
oscill., etc.)
Periodic relay
testing
Staged
primary faults
Self-checking
(internal relay
diagnostics)
Other
65%
27%
1% 1%6%
0%
10%
20%
30%
40%
50%
60%
70%
PercentageofRespondents
Manufacturers'recommendation
Knowledge andexperience of relay
test personnel
Regulationrequirement
No establishedtolerances
Other
7/27/2019 2001 Survey of Relaying Test Practices
11/35
This is a special report of the IEEE Power System Relay Committee.
Page 9 January 2002
The combined number of responses consisting of selections No established tolerance, Other means or practices,and No response to this question (12.8 %) indicates that the determination of acceptable tolerances is completed
by an internal or external organization and the survey may not have been transmitted to that group. This observation
is verified by the additional comments provided indicating that this function is either contracted out or accomplishedby engineering. Relaying engineers that responded to other means or practices provided information explainingthat relay tolerances were set by established company guidelines.
4.2 Relay Applications that Require Tighter Tolerances
The purpose of this question is to determine if utilities establish tighter tolerances based on the individual relaycharacteristic, user application, function in a particular protective scheme or some other defined criteria rather than
just the individual relay type or manufacturer involved.
Figure 16: Relay Applications Requiring Tolerances Tighter than Those Normally Required
Although in the majority of cases non-electromechanical relays may have a more precisely defined pickup and
dropout characteristic, only 19 % of the responses to the selection Non-electromechanical versuselectromechanical felt that there is sufficient justification to warrant closer setting tolerances when using non-electromechanical relays.
User responses shown under the selection Impedance versus overcurrent (10 %) illustrates the concern of possibleoverreaching and the additional complexities associated with this type of relay. In general, the simple overcurrent
relay has a larger allowable error setting tolerance due to its application.
The response under selection Type of equipment being protected by the relay (16 %) most likely denotes theconcerns regarding major damage to critical types of power system apparatus and facilities.
It should be noted, however, that no distinction was made within the survey for the variety of more complex relaysbelonging to the overcurrent family of relays, such as those based on directional, negative sequence, or other definedsupervising characteristics.
The survey responses shown under the selection Relay application or other instantaneous trips (17 %) regardingapplication such as Zone 1 or other instantaneous trip functions indicates that closer tolerances are used for theseapplication. Concerns regarding overreaching may be a major factor that directs testing philosophy for these
applications.
19%
10%
16%17%
0%
9%
30%
0%
5%
10%
15%
20%
25%
30%
PercentageofRespondents
Non-electro-
mechanical
vs electro-
mechanical
relays
Independent
and similar
vs over-
current and
equivalent
Type of
equipment
protected by
relay
Relay
application
such as
Zone 1 or
other inst.
trips
Over-
reaching vs
under-
reaching
Nuclear
power station
application
Other
7/27/2019 2001 Survey of Relaying Test Practices
12/35
This is a special report of the IEEE Power System Relay Committee.
Page 10 January 2002
Selection Overreaching versus underreaching (0 %) shows that an underreaching element is not more critical thanan overreaching element.
Utilities with nuclear facilities obviously have eminent concerns regarding certain regulatory procedures andperceived outage effects. Tolerances are more closely reviewed than for companies without nuclear installations, orthose having more rural type of distribution networks. This is reflected under selection Nuclear power stationapplication (9 %) of the utilities responding to this question.
A large number of responses (30 %) indicated other. This may indicate that all relays are calibrated with equal
tolerances.
4.3 Relay Applications for which Looser than Normal Tolerances are Permitted
The response to the survey question regarding the acceptability of looser tolerances for certain relay applicationswith respect to defined application is shown in Figure 17. Other than those responses under selection Non-tripping
relays, it appears that from the selection Other (38 %) that, although no additional information was provided,many utilities may calibrate relays with equal tolerances.
Figure 17: Relay Applications Requiring Tolerances Looser than Those Normally Required
A moderate percentage (11 %) of utilities indicated that Relays that trip after a time delay are not required to have
a precise setting or other exacting factors that affect tolerances. The question does arise regarding the accuracy ofthe relay before tripping occurs if looser than normal tolerances acceptable with respect to its characteristic andthose effects on the overall time delay.
The response under selection Non-tripping relays appears that a relative number of surveyed relay users (50 %)did agree that non-tripping relays are not required to have as tight a tolerance as those assigned to actual tripping
purposes. Relays used for alarm applications, auto test, or circuit breaker reclosing are most likely part of thiscategory.
4.4 Documentation of Allowable Tolerances by the Relay Users
The response to the question of the survey regarding whether allowable relay tolerances are documented is provided
in Figure 18 below.
11%
50%
2%
38%
0%
5%
10%
15%
20%
25%
30%
35%
40%
45%
50%
PercentageofRespondents
Relays that trip
after a time delay
Non-tripping relays Percentage
differential relays
Other
7/27/2019 2001 Survey of Relaying Test Practices
13/35
This is a special report of the IEEE Power System Relay Committee.
Page 11 January 2002
Figure 18: Documentation of Allowable Relay Tolerances
The combined selections Allowable relay tolerances are documented and Allowable relay tolerances are partiallydocumented (93.5 %) reflect that the majority of the polled users do indeed compile documentation on relaytolerances.
5. Factors that Influence Relay Test Schedules
There has been a lot of pressure to increase the time period between relay test intervals. Increasing the test intervals
obviously reduces direct testing costs. The probability that a failure will occur and exist undetected increases as theintervals go up. It is possible that relay crews will visit the less common relay systems so seldom that they willencounter delays while they have to relearn how to deal with them. This section of the survey was designed toinvestigate what are the most significant factors influencing selection of test intervals in the industry.
5.1 Basis for Test Intervals for Relays in T&D Substations
Figure 19 summarizes the respondents basis for selecting test intervals for relays protecting T&D substations.Nearly half of the respondents chose Analysis of past results and Voltage level of circuit. Manpowercapability or limitations and operations or misoperations were also selected by a large number of respondents. Itis interesting to note that all of the possible choices drew at least some selections, with More complex relay typesselected by only two of the respondents.
58.4%
35.1%
6.5%
0%
10%
20%
30%
40%
50%
60%
PercentageofRes
pondents
Allowable relay
tolerances are
documented
Allowable relay
tolerances are
partially documented
Allowable relay
tolerances are not
documented
7/27/2019 2001 Survey of Relaying Test Practices
14/35
This is a special report of the IEEE Power System Relay Committee.
Page 12 January 2002
Figure 19: Basis for Test Intervals for Relays in T&D Substations
Figure 20 summarizes the most important factors in selecting the test intervals for T&D substation relays. While theresults do not exactly correspond to those reflected in Figure 19, the two responses most frequently selected wereagain Analysis of past results and Voltage level of circuit.
Figure 20: Most Important Factors in Selecting Test Intervals for Relays in T&D Substations
45.6% 45.6%
32.9%
40.5%
30.4%
2.5%
19.0%
43.0%
13.9%
43.0%
36.7%
20.3%
31.6%29.1%
10.1%
0.0%
5.0%
10.0%
15.0%
20.0%
25.0%
30.0%
35.0%
40.0%
45.0%
50.0%
PercentageofRespondents
Anaysispastresults
Voltagelevel
Typeofrelay
Constructionofrelay
Importanceofloads
Complexrelays
Manufacturersrec.
Manpowerlim
its
Outagetim
e
Operationsorm
isops.
Maintenancesch.
Age,type,style
Selftest
Regionalcriteria
Other
19%
6%
10%
18%
8%
6%
3%
12%
5%
10%10%
10%
8%
13%
6%
0%
1%1%
4%4%4%
13%
6%
13%
3%
0%
1%
8%
12%
15%
3%
10%
9%
1%1%
4%3%
8%
3%
9%
6%
8%
0%
3%3%
0%
2%
4%
6%
8%
10%
12%
14%
16%
18%
20%
PercentageofRespondents
Anaysispastresults
Voltagelevel
Typeofrelay
Constructionofrelay
Importanceofload
s
Complexrelays
Manufacturersrec
.
Manpowerlim
its
Outagetim
e
Operationsorm
is
ops.
Maintenancesch.
Age,type,style
Selftest
Regionalcriteria
Other
Ranked 1 Ranked 2 Ranked 3
7/27/2019 2001 Survey of Relaying Test Practices
15/35
This is a special report of the IEEE Power System Relay Committee.
Page 13 January 2002
5.2 Rationale for Shorter Test Intervals
Figure 21 shows that shorter test intervals were selected for relays protecting higher (EHV) voltage systems by 56 %
of the respondents. The particular type of relay being tested was also frequently chosen to be a basis for usingshorter test intervals.
Figure 21: Reasons for Selection of Shorter Test Intervals for Relays in T&D Substations
5.3 Rationale for Longer Test Intervals
Figure 22 shows that 65 % of the respondents assign longer test intervals to T&D substation relays with self-checking algorithms. Again, as in the previous question, the particular type of relay was also a significant factor inchoosing longer test intervals.
Figure 22: Reasons for Selection of Longer Test Intervals for Relays in T&D Substations
21.3%
56.0%
16.0%
30.7%
2.7%
20.0%
0.0%
10.0%
20.0%
30.0%
40.0%
50.0%
60.0%
Percen
tageo
fRespon
den
ts
Non-EM vs. EM Higher Voltage
(EHV)
Type of load Relay Types Self-checking Other
24.7%
6.8%
13.7%
26.0%38.4%
24.7%
0 .0%
5.0%
10 .0%
15 .0%
20 .0%
25 .0%
30 .0%
35 .0%
40 .0%
PercentageofRespondents
N o n - E M v s . E M H i g he r V o l ta g e
(EHV)
Ty pe o f l oad Re lay typ es Sel f-checki ng O th er
7/27/2019 2001 Survey of Relaying Test Practices
16/35
This is a special report of the IEEE Power System Relay Committee.
Page 14 January 2002
5.4 Basis for Test Intervals for In-Plant Relays (Generator, Switchgear, etc.)
Figure 23 shows that a clear majority of respondents (almost 59 %) selected Maintenance schedule of protected
equipment as a factor. The next two most frequently selected choices were Operations and misoperations andAnalysis of past results. All of the possible choices drew at least some selections, with More complex relaytypes least frequently selected, consistent with the results collected for T&D substations.
Figure 23: Basis for Test Intervals for In-Plant Relays
Figure 24 summarizes the most important factors for selection of test intervals for in-plant relays. The most
frequently selected choice was Maintenance schedule of protected equipment. 12 % of the respondents ranked itas their most important factor.
Figure 24: Most Important Factors in Selecting Test Intervals for In-Plant Relays
5.5 Test Intervals Actually Met in Practice
A majority of respondents, 65 %, reported that their scheduled relay test intervals are actually met in practice.
3 1 . 4 %
1 4 . 3 % 1 4 . 3 %
2 2 . 9 %
1 5 . 7 %
2 . 9 %
2 2 . 9 %
2 7 . 1 %2 7 . 1 %
3 2 . 9 %
5 8 . 6 %
4 . 3 %
1 5 . 7 %
1 8 . 6 %
1 4 . 3 %
0 . 0 %
1 0 . 0 %
2 0 . 0 %
3 0 . 0 %
4 0 . 0 %
5 0 . 0 %
6 0 . 0 %
PercentageofRespondents
Anaysispastresults
Voltagelevel
Typeofrelay
Constructionofrelay
Importanceofloads
Complexrelays
Manufacturersrec.
Manpowerlim
its
Outagetime
Operationsormisops.
Maintenancesch.
Age,type,style
Selftest
Regionalcriteria
Other
1 2 %
3 %
1 2 %
4 %
1 %
3 %
3 %
6 %
4 %
6 %
3 %
6 %
1 0 %
4 %
3 %
0 %
1 %
0 %
3 %4 %4 %
3 %
1 3 %
1 5 %
7 %
1 0 %
6 %7 %
9 %
1 2 %
2 7 %
2 2 %
9 %
0 %1 %
4 %3 %
6 %
4 %4 %
6 %
4 %
9 %
1 %
0 %
0 %
5 %
1 0 %
1 5 %
2 0 %
2 5 %
3 0 %
Percen
tageo
fRespon
den
ts
Anaysispastresults
Voltagelevel
Typeofrelay
Constructionofrelay
Importanceofloa
ds
Complexrelays
Manufacturersr
ec.
Manpowerlim
its
Outagetime
Operationsorm
isops.
Maintenancesch
.
Age,type,style
Selftest
Regionalcriteria
Other
Ranked 1
Ranked 2
Ranked 3
7/27/2019 2001 Survey of Relaying Test Practices
17/35
This is a special report of the IEEE Power System Relay Committee.
Page 15 January 2002
6. Relay Test Intervals
6.1 Actual Relay Test Intervals Presently Used
The purpose of this section is to determine the relay test intervals for both electromechanical and non-electromechanical relays used in transmission, distribution, main generator, auxiliary bus, cogeneration and large
industrial substations.
The complete responses are given by the bar charts shown in Figures 25 through 36.
Figure 25: Time Intervals between Scheduled Relay Testing (years) - Electromechanical Relays onTRANSMISSION Circuits
Figure 26: Time Intervals between Scheduled Relay Testing (years) - Electromechanical Relays onSUBTRANSMISSION Circuits
4% 3%3%
4%
6%
13%
21 %
22%22%
23%
24%
25 %
26%
28%
26%27%
26 %
22%21 %
18%19%19%
17%
18 %
12 %
14%14%
12%11%11%
4%7%
7%
4% 4%
2%
0% 0%
3%1% 1%
0%
12%
8%8%
9%11%
9%
0%
5%
10 %
15 %
20 %
25 %
30 %
Perc
entageofRespondents
7
Years
Overcurrent Impedance Different ia l Pi lot Remote Tr ip Schemes Frequency
4%
1%
1%
3%3%
10% 10%
16%14 %
13%
13%
24%
21 %
23%
24%
32%
29%
22% 22 %
23%
22%
18%
16%17%
21%
15%
16%
15 % 15%
9%
8%8%
9%
5%
6%
3%
1%3%3%
3% 3%3%
13%
10%11%
11%
15%
10 %
0%
5%
10 %
15 %
20 %
25 %
30 %
35 %
PercentageofRespondents
7
Years
Overcurrent Impedance Differential Pilot Remote Tr ip Schemes Frequency
7/27/2019 2001 Survey of Relaying Test Practices
18/35
This is a special report of the IEEE Power System Relay Committee.
Page 16 January 2002
Figure 27: Time Intervals between Scheduled Relay Testing (years) - Electromechanical Relays on
DISTRIBUTION Circuits
Figure 28: Time Intervals between Scheduled Relay Testing (years) - Non-Electromechanical Relays onTRANSMISSION Circuits
3%
0%0%0%
3%
10%
4%
13%
10%
6%
8%
29%
12%13%
16%
12%
13%
12%
25%
23%
23%
27%
18%
19%
15%
18%
15%
21%
18%
12%
15%
10%
11%
9%
13%
3%
8%
5%
8%9%
8%
5%
18%
18%
16%
15%
21%
10%
0%
5%
10%
15%
20%
25%
30%
PercentageofRe
spondents
7
Years
Overcurrent Impedance Differential Pilot Remote Trip Schemes Frequency
1%
0%0%1%
4%
9%
21 %
22 %
23 %
27 %
27 %
26 %
18 %18 %18 %
21 %
23 %
22 %
19 %
21 %
22 %
15 %
11 %
19 %
13 %
14 %
11 %
11 %
12 %
9%
7%
5%
4%
6%
5%
2% 3%
4%
7%7%
7%
0%
18 %
16 %
16 %
11 %
10 %
13 %
0%
5%
10%
15%
20%
25%
30%
PercentageofRespondents
7
Years
Overcurrent Impedance Differential Pilot Remote Trip Schemes Frequency
7/27/2019 2001 Survey of Relaying Test Practices
19/35
This is a special report of the IEEE Power System Relay Committee.
Page 17 January 2002
Figure 29: Time Intervals between Scheduled Relay Testing (years) - Non-Electromechanical Relays on
SUBTRANSMISSION Circuits
Figure 30: Time Intervals between Scheduled Relay Testing (years) - Non-Electromechanical Relays onDISTRIBUTION Circuits
1%0%0%
2% 2%
9%
15 %
16 %
18 %
19 %
21 %
26 %
18 %
16 %
16 %
19 %
20 %
19 %
17 %
17 %
19 %
17 %
15 %
11 %
15 %
19 %
15 %
16 %16 %
13 %
7%
9%
7%7%
8%
6%
7%7% 7%7% 7%
2%
18 %
17 %
18 %
14 %
11 %
15 %
0%
5%
10%
15%
20%
25%
30%
PercentageofRespondents
7
Years
Overcurrent Impedance Differential Pilot Remote Trip Schemes Frequency
3%
0%0%0%
3%
10 %
1%
9%
7%
14 %
19 %
23 %
10 %
12 %
14 %
7%
5%
15 %
20 %
18 %
21 %
28 %
22 %
16% 16%
18 %
16 %17 %
16 %
15 %14 %
12 %
11 %
14%14%
3%
10 %
3%
7%
3%
5%
5%
25 %
29 %
25 %
17 %
16 %
13 %
0%
5%
10%
15%
20%
25%
30%
Percentageof
Respondents
7
Years
Overcurrent Impedance Differential Pilot Remote Trip Schemes Frequency
7/27/2019 2001 Survey of Relaying Test Practices
20/35
This is a special report of the IEEE Power System Relay Committee.
Page 18 January 2002
Figure 31: Time Intervals between Scheduled Relay Testing (years) - Electromechanical Relays for GENERATORApplications at Non-Nuclear Power Stations
Figure 32: Time Intervals between Scheduled Relay Testing (years) - Electromechanical Relays for AUXILIARYBUS Applications at Non-Nuclear Power Stations
8%
7%
7%
8%
11 %
22 %
25 %25 %
22 %
27 %
29 %
28 %
27 %
31 %
29 %
20 %
19 %
20%20%
16 %
12 %
12 %
12 %
10 %
9%
2% 2%2%2%
0% 0%0%0% 0% 0%
7% 7%7% 7% 7%
0%
5%
10%
15%
20%
25%
30%
35%
PercentageofRespondents
7
Years
Overcurrent Impedance Differential Voltage Frequency
10 %
5%5%
8%9%
16 %
23 %
20 %
15 %
23 %23 %
20 %
25 %
24 %25 %
23 %23 %
22 %22 %
18 %
13 %
11 %
14 %14 %
16 %
5%
7%
3%
5%
0%
2%
0%
2% 2%
0%
10 %
11 %
8%
10 %9%
0%
5%
10%
15%
20%
25%
30%
Percentag
eofRespondents
7
Years
Overcurrent Impedance Differential Voltage Frequency
7/27/2019 2001 Survey of Relaying Test Practices
21/35
This is a special report of the IEEE Power System Relay Committee.
Page 19 January 2002
Figure 33: Time Intervals between Scheduled Relay Testing (years) - Non-Electromechanical Relays forGENERATOR Applications at Non-Nuclear Power Stations
Figure 34: Time Intervals between Scheduled Relay Testing (years) - Non-Electromechanical Relays for
AUXILIARY BUS Applications at Non-Nuclear Power Stations
7%
4%6%
8%
12 %
18 %
23 %22 %
21 %
24 %
29 %28 %
25 %
29 %
24 %
24 %
19 %
22 %
21 %
22 %
13 %
15 %
14 %
12%12%
2%2% 2%2%
0% 0% 0% 0%0%0%
7%
9%
10 %
8% 8%
0%
5%
10%
15%
20%
25%
30%
PercentageofRespondents
7
Years
Overcurrent Impedance Differential Voltage Frequency
9%
6%6%
10%
11%
17%
21%
17%
15%
22%
22%
21%
23%
19%19%
22%
18%
26%
23%
19%
11%
15%
13%
13%
14%
7%6%
2%
8%
5%
2%
0%
2% 2%0%
9%
15%
11%
10%
11%
0%
5%
10%
15%
20%
25%
30%
Percentag
eofRespondents
7
Years
Overcurrent Impedance Differential Voltage Frequency
7/27/2019 2001 Survey of Relaying Test Practices
22/35
This is a special report of the IEEE Power System Relay Committee.
Page 20 January 2002
Figure 35: Time Intervals between Scheduled Relay Testing (years) - Electromechanical and Non-Electromechanical Relays for Substations Serving a LARGE INDUSTRIAL CUSTOMER
Figure 36: Time Intervals between Scheduled Relay Testing (years) - Electromechanical and Non-Electromechanical Relays for Substations Serving an INDEPENDENT POWER PRODUCER or Dispersed Source
of Generation
6.2 Comparison of Relay Test Invervals with the 1991 Survey
Charts comparing maintenance and calibration intervals compiled during the 2001 survey as compared to the resultsof the 1991 survey is included in Figures 37 through 44.
5%
2%2%
4%
6%
2%
5%
11 %8%
7%
18 %
4%
16 %
22 %
20 %
20 %
22 %
20 %
29 %
25 %
24 %
22 %
24 %
29 %
15 %
16 %
17 %16 %
12 %
16 %15 %
11 %
12 %
13 %
8%
12 %
3%2%
5%5%
0%
4%
13 %
11 %
12 %
13 %
10 %
14 %
0%
5%
10%
15%
20%
25%
30%
PercentageofRespondents
7
Years
Overcurrent Impedance Differential Voltage Frequency Reverse Power
4%
2%2%
4%
10 %
2% 2%
14 %
17%17%
15 %
21 %
15 %
18 %
18 %
22 %
24 %
22 %
19 %
20 %
18 %
27 %
20 %
17 %
20 %
19 %
24 %
20 %
12 %
15 %
15 %
15 %
17 %
15 %
18 %
8%
7%
7%
7%
2%
7% 7%
0%
2%2% 2%
0%
2%
0%
16 %
15 %
15 %
15 %12 %
15 %
16 %
0%
5%
10%
15%
20%
25%
30%
Percentag
eofRespondents
7
Years
Overcurrent Impedance Differential Voltage Frequency Reverse Power Synchronizing
7/27/2019 2001 Survey of Relaying Test Practices
23/35
This is a special report of the IEEE Power System Relay Committee.
Page 21 January 2002
Over the ten-year interval, 1991 to 2001, one can see a shift in longer test intervals. For example, electromechanicalimpedance relays used for protection of transmission facilities were tested every five or more years by 28.9 % of theelectric utilities responding in the 2001 survey, as compared to only 10.1 % in 1991. A similar shift in maintenance
test intervals is found in comparisons of the data compiled in the two surveys for other relay types as well asindicated in Figures 37 through 44.
Figure 37: 1991 Survey Electromechanical Relays - Transmission
Figure 38: 2001 Survey Electromechanical Relays - Transmission
11 %
14 %
12 %
13 %
32 %
46 %47 %
48 %
50 %
38 %
20 %
20 %
20 % 19 %19 %
11 %8%
7%6%
4%
13 %
10 %
13 %
12 %
7%
0%
5%
10%
15%
20%
25%
30%
35%
40%
45%
50%
PercentageofRespondents
5
Years
Overcurrent Impedance Differential Pilot Frequency
4%
3% 3%
4%
13 %
21 %
22 %
22 %
23 %
25 %26 %
28 %
26 %27 %
22% 21%
18 %
19 %19 %
18 %
29 % 29 %
31 %
27 %
22 %
0%
5%
10%
15%
20%
25%
30%
35%
PercentageofRespondents
5
Years
Overcurrent Impedance Differential Pilot Frequency
7/27/2019 2001 Survey of Relaying Test Practices
24/35
This is a special report of the IEEE Power System Relay Committee.
Page 22 January 2002
Figure 39: 1991 Survey Non-Electromechanical Relays - Transmission
Figure 40: 2001 Survey Non-Electromechanical Relays - Transmission
14 %
17 %
13 %
25 %
37 %
45 %
48 %
50 %
40 %
37 %
19 %
20 %
19 %
20 %
15 %
8%
6%6% 7%3%
14 %
9%
12 %
8% 9%
0%
5%
10%
15%
20%
25%
30%
35%
40%
45%
50%
PercentageofR
espondents
5
Years
Overcurrent Impedance Differential Pilot Frequency
1%
0% 0%
1%
9%
21 %
22 %
23 %
27 %
26 %
18 %
18 %
18 %
21 %
22 %
19 %
21 %22 %
15 %
19 %
40 %40 %
38 %
35 %
24 %
0%
5%
10%
15%
20%
25%
30%
35%
40%
45%
PercentageofRespondents
5
Years
Overcurrent Impedance Differential Pilot Frequency
7/27/2019 2001 Survey of Relaying Test Practices
25/35
This is a special report of the IEEE Power System Relay Committee.
Page 23 January 2002
Figure 41: 1991 Survey Electromechanical Relays - Distribution
Figure 42: 2001 Survey Electromechanical Relays - Distribution
3%
6%7% 8%
37 %
25 %
32% 32%
28% 28%
21 %21 %
22 %
22 %
15 %
22 %
23 %
18 %
23 %
8%
29 %
18 %
21 %
19 %
12 %
0%
5%
10%
15%
20%
25%
30%
35%
40%
PercentageofRespondents
5
Years
Overcurrent Impedance Differential Pilot Frequency
3%
0%0%0%
10 %
4%
13 %
10 %
6%
29 %
12 %13 %
16 %
12 % 12 %
25 %23 % 23 %
27 %
19 %
56 %51 %
51 %
55 %
31 %
0%
10%
20%
30%
40%
50%
60%
Percenta
geofRespondents
5
Years
Overcurrent Impedance Differential Pilot Frequency
7/27/2019 2001 Survey of Relaying Test Practices
26/35
This is a special report of the IEEE Power System Relay Committee.
Page 24 January 2002
Figure 43: 1991 Survey Non-Electromechanical Relays - Distribution
Figure 44: 2001 Survey Non-Electromechanical Relays - Distribution
7% 6%7%
10 %
36 %
24 %
30 %
33 %
27 % 27 %
19 %
23 %
19 %
23 %
15 %
23%23%
19 %
22 %
7%
27 %
18 %
23 %
19 %
16 %
0%
5%
10%
15%
20%
25%
30%
35%
40%
PercentageofR
espondents
5
Years
Overcurrent Impedance Differential Pilot Frequency
3%
0%0%0%
10 %
1%
9%
7%
14 %
23 %
10 %
12 %14 %
7%
15 %
20 %
18 %
21 %
28 %
16 %
65 %
62 %
58 %
52 %
36 %
0%
10%
20%
30%
40%
50%
60%
70%
PercentageofRespondents
5
Years
Overcurrent Impedance Differential Pilot Frequency
7/27/2019 2001 Survey of Relaying Test Practices
27/35
This is a special report of the IEEE Power System Relay Committee.
Page 25 January 2002
7. Relay Test Equipment
The purpose of this section is to compare what type of test equipment is being used, and for what type ofapplications. In addition, desired maximum weight is considered for transportability.
7.1 Acquisition of Test Equipment
According to the survey, fewer companies are building their own test sets. Over 97 % of those surveyed said thatthey procure commercially available relay test sets. Less than 3 % said that they build their own test sets.
7.2 Passive vs. Solid State Relay Test Sets
Passive relay test sets are defined as manually operated test sets comprised of resistive loads, mechanical phaseshifters, variable autotransformers, or phantom loads. Solid state relay test sets include electronically regulatedvoltage and current sources. The survey showed that over 98 % of the respondents have two or more solid staterelay test sets. As shown in Figure 45, almost half of the respondents, 49 %, use both passive and solid state relay
test sets, while another 49 % use solid state test sets only. Less than 2 % use passive test sets only.
Figure 45: Percentage of Utilities that Use Passive and Solid State Test Sets
The ratio of passive vs. solid state test sets has dropped significantly since the 1991 survey. In 1991, 50 % of thetest sets in use were passive loads. Today, of those surveyed, 29 % of the total number of units in use are passiveloads (861 passive test sets out of a total of 2,965 units). Therefore, it is concluded that as the older passive units areretired they are being replaced with modern solid state relay test sets.
7.3 Dynamic Relay Test Equipment
Dynamic test equipment is defined as test sets capable of providing pre-fault, fault, and post-fault outputs, with dcand harmonic components. As shown in Figure 46, 80 % of the respondents have equipment with this type ofcapability. This is a significant increase from the 1991 survey, when only 50 % of respondents said that they haddynamic test equipment.
2%
49% 49%
0%
5%
10%
15%
20%
25%
30%
35%
40%
45%
50%
PercentageofRespondents
Passive Only Passive and Sol id State Sol id State Only
7/27/2019 2001 Survey of Relaying Test Practices
28/35
This is a special report of the IEEE Power System Relay Committee.
Page 26 January 2002
Figure 46: Percentage of Utilities that Use Dynamic Test Sets
7.4 Power Swing Test Equipment
Utilities were asked if they have test sets capable of simulating power system disturbances such as power swings orfrequency excursions. As shown in Figure 47, 79 % of the respondents have at least 1 test set capable of performingthis type of test. This represents a 29 % increase from the 1991 survey.
Figure 47: Percentage of Utilities that Use Power Swing Capable Test Sets
50%
80%
0%
10%
20%
30%
40%
50%
60%
70%
80%
PercentageofRespondents
1991 Survey 2001 Survey
50%79%
0%
10%
20%
30%
40%
50%
60%
70%
80%
PercentageofRespondents
1991 Survey 2001 Survey
7/27/2019 2001 Survey of Relaying Test Practices
29/35
7/27/2019 2001 Survey of Relaying Test Practices
30/35
This is a special report of the IEEE Power System Relay Committee.
Page 28 January 2002
7.7 Portability of Test Equipment
Over 47 % of the respondents stated that they have relay test sets that require more than one person to carry. As
shown in Figure 50, 50 % of the respondents said that the maximum weight should be 50 pounds or less. Another47 % said that test sets that weighed from 50 to 80 pounds were acceptable, while 3 % said that test sets thatweighed 80 pounds or more were acceptable.
Figure 50: Desired Weights of Test Sets
8. Testing Protective Relays in a Particular Station
The purpose of this section is to determine how relay test crews are scheduled when relays are tested.
About 64 % of the respondents test all relays in a station with a single crew in one concentrated effort. Another27 % of the respondents test relays at different times by different crews according to voltage, criticality and relaycomplexity. The remaining 9 % use other methods to schedule relay testing. Utilities who use a single crew in oneeffort increased about 11 % since the 1991 survey, while utilities that use different crews at different timesdecreased about 6 % since the 1991 survey. This implies that relay testing at utilities is moving towardsperforming all relay testing in one effort. Figure 51 shows these results.
Figure 51: Utilities' Approach to Scheduling Relay Testing
5 0 %
4 7 %
3 %
0%
5%
1 0 %
1 5 %
2 0 %
2 5 %
3 0 %
3 5 %
4 0 %
4 5 %
5 0 %
PercentageofRespondents
U nd e r 5 0 L b s 5 0 t o 8 0 L b s 8 0 o r M o r e
W e i g h t
64.1%
3.8%
26.9%
5.1%
0%
10 %
20 %
30 %
40 %
50 %
60 %
70 %
Perce
ntageo
fRespon
den
ts
Al l re la ys , si ng le
crew, one effort.
Mul t ip le crews,
based on relay
criteria.
Di f ferent crews,
di f ferent t imes.
Other
7/27/2019 2001 Survey of Relaying Test Practices
31/35
This is a special report of the IEEE Power System Relay Committee.
Page 29 January 2002
9. Protective Relaying Scheme Operational Test Conditions and Intervals
The purpose of this section of the survey is to determine the conditions for which protective relaying schemes areoperationally tested and the intervals at which these tests are performed.
9.1 Operational Trip Testing
Most individuals responsible for power system protection consider operational trip testing necessary to verify that allrelays, power circuit breakers, station batteries and other equipment are performing correctly. This sectionaddresses when these operational checks are performed, how often are they performed and who performs theoperational check.
Power circuit breakers are trip tested with their protective relays during various routine maintenance tasks and whena malfunction or misoperation is suspected. If a misoperation is suspected, a majority of respondents said they
perform a trip check. For routine maintenance, operational trip checks of the power circuit breakers during bothrelay and breaker maintenance is a very common utility practice. The results are shown on Figure 52.
Figure 52: Other Testing Performed when Utilities Perform Operational Trip Testing
9.2 Operational Trip Test Intervals
The majority of relay schemes were operationally trip tested on a 1 to 3 year cycle. The results are shown on Figure53.
25.3%
11.4%74.7%
24.1%
22.8%
49.4%
0.0% 10.0% 20.0% 30.0% 40.0% 50.0% 60.0% 70.0% 80.0%
Percentage of Respondents
Other
Routine Interupting Device
Maintenance.
During SCADA Testing.
Af te r Mal fun cti on or
Misoperation.
Complete Maintenance
Shutdown of Facility.
Dedicated time, fixed
schedule.
7/27/2019 2001 Survey of Relaying Test Practices
32/35
This is a special report of the IEEE Power System Relay Committee.
Page 30 January 2002
Figure 53: Operational Testing Intervals
9.3 Personnel Who Perform Operational Trip Tests
As can be seen from Figure 54, maintenance and service personnel along with protection technicians are most likelyto be performing these trip tests.
Figure 54: Type of Personnel Who Perform Trip Testing
10. Maintenance Program Effectiveness
The purpose of this section was to determine how utilities decrease relay failures through their maintenanceprograms.
4.0%
21.3%21.3%
8.0%
12.0%
5.3%
0.0%
9.3%
18.7%
0%
5%
10%
15%
20%
25%
PercentageofResp
ondents
1 or
less
1-2 2-3 3-4 4-5 5-6 6-7 7+ NA
Years
3.8%
11.4%
77.2%
6.3%
1.3%
0% 10% 20% 30% 40% 50% 60% 70% 80%
Percentage of Respondents
Substation operators
Maintenance or service
personnel
Protection technicians
Protection engineers
Other
7/27/2019 2001 Survey of Relaying Test Practices
33/35
This is a special report of the IEEE Power System Relay Committee.
Page 31 January 2002
10.1 Criteria Used
As shown in Figure 55, Reliability was the chosen as the most common criteria used to measure maintenance
program effectiveness, while the second most common selection was Productivity and Performance.
Figure 55: Basis for Measurement Criteria to Determine Effectiveness of Maintenance Programs
10.2 Correlation between Measurements and Failure Rates
As shown in Figure 56, 25.3 % of the respondents said that there is a relationship between their measurements and areduction in failure rates. This is a 5.8 % increase from 1991 survey.
Figure 56: Percentage of Utilities Who Identify a Relationship Between Measurement and Failure Rate
6.3%
13.9%
25.3%
43.0%
7.6%
3.8%
0% 5% 10% 15% 20% 25% 30% 35% 40% 45%
Percentage of Respondents
Productivity
Performance
Productivity &
Performance
Reliability
None
Other
25.3%
74.7%
19.5%
80.5%
0% 10% 20% 30% 40% 50% 60% 70% 80% 90%
2001 Survey
1991 SurveyNo Relationship
Relationship
7/27/2019 2001 Survey of Relaying Test Practices
34/35
This is a special report of the IEEE Power System Relay Committee.
Page 32 January 2002
10.3 Satisfaction of the Utilities Maintenance Programs
In rating the effectiveness of their utilitys maintenance program, 25.3 % of the respondents were very satisfied,
58.2 % were satisfied, 13.9 % were unsatisfied and 2.5 % were very unsatisfied. The satisfaction level seems to beslightly lower then in the 1991 survey. Figure 57 shows the survey results.
Figure 57: Utility Opinions on Effectiveness of Maintenance Programs in Reducing Relay Failures
2.5%0.5%
13.9%4.5%
58.2%62.0%
25.3%
33.0%
0% 10% 20% 30% 40% 50% 60% 70%
Percentage of Respondents
Very Unsatisfactory
Unsatisfactory
Satisfactory
Very Satisfactory
2001 Survey 1991 Survey
7/27/2019 2001 Survey of Relaying Test Practices
35/35
11. Bibliography
[1] A Survey of Relay Test Practices, IEEE Power Systems Relaying Committee Report, IEEE TransactionsPower Apparatus and Systems, Vol. 91, pp. 1191-1196, May/June 1972.
[2] A Survey of Relay Test Practices, IEEE Power Systems Relaying Committee Report, IEEE TransactionsPower Delivery, Vol. 9, No. 3, pp. 1339-1351, July 1994.