01.08.2008 BUILDING MAGAZINE E C O N O M I C S analysis / facts / forecast COST MODEL AIRPORT TERMINALS UK airport operators need to make substantial investments in infrastructure to prepare for continuing long-term demand for domestic and international flights. Simon Rawlinson of Davis Langdon reports 01 / INTRODUCTION Air travel has become increasingly segmented, with budget airlines introducing new sets of re q u i rements for fast terminal turnaround and minimal service. The types of flights and airlines served will determine many of the principal design fe a t u res of a terminal, including airport- wide services, baggage handling, apron (area designed for loading and unloading passengers and cargo) and gate design, and retail. The main re q u i rements of the different service types are as follows: Full-service airlines. These typically require pier/gate service and dedicated facilities for premium passengers. Full-service flights have longer turn-around periods and often run an “open gate” boarding policy, which reduces the need for holding space at the gate. The quantity and size of baggage is likely to be high and the security profile of some destinations may result in more bags progressing to higher l evels of screening Budget airlines. These work on a model of maximum throughput and minimal operating cost. Passengers are held at gates prior to boarding but few gate services are required. Minimising turnaround time is vital. Discouraging hold baggage simplifies apron o p e rations but places more pressure on passenger and hand-luggage screening. To simplify landside operations, budget carriers encourage e-ticketing and remote check-in Charter flights. These have a profile of high baggage loads, longer turnarounds and limited passenger service. Passengers also require extensive, off-airport long-term parking. Within the terminal, the key issue related to charter flights is their contribution to peak flows at holiday times – determining the sizing of many aspects of airport equipment. Air traffic has grown exponentially over the past decade. UK passenger numbers totalled 189 million in 2002 and are forecast to grow to at least 350 million by 2020, and possibly as high as 480 million. In response to forecast growth and with government support, airport operators are planning and implementing substantial investment in additional capacity. The most dynamic sector has been budget airlines, in which passenger numbers grew 300% in the five years to 2005. In addition to expansion, existing facilities such as security need to be upgraded to meet new requirements and counter obsolescence. However, the combination of an economic downturn and high oil prices will undoubtedly challenge the business model of many airlines and the airports they serve. For airport operators, there will be greater pressure on landing charges and operating costs. In providing a high-quality service for passengers, any new terminal investment will need to balance the scale of initial capital investment, provision for future expansion and operational efficiency, together with the imperative to maximise revenues from all available income streams. The economic case for further expansion is described in the 2003 white paper, The Future of Air Transport. Air travel underpins the UK’s exports and its general business performance, as well as making a significant contribution to tourism. Air transport has also had an important social role in reducing the cost and time of long-distance travel. The white paper acknowledges that continued investment should be balanced against the environmental effects of expanded air travel, an issue that, clearly, has not been resolved. In the meantime, BAA is well advanced in the implementation of a £6bn investment programme to follow on from Terminal 5, and other operators in the private, public and PPP sectors are preparing major programmes for regional facilities in locations such as Manchester, Birmingham, Liverpool and Leeds Bradford. 02 / TYPES OF AIRPORT TERMINAL Airport facilities are developed to respond both to existing levels of demand and future growth in traffic. Investment is targeted at attracting two key clients – passengers and the airlines that serve them. Passengers typically choose their preferred airport on the basis of the availability of routes, services and pricing, so being successful in attracting the right airlines and routes is critical to commercial success. Important factors for passengers also include: location; ease of access; and the range of services provided. However, if the right flights are not on offer, passengers will not come. Key considerations in attracting airlines include: accessibility; the size of the local market; the availability of runway capacity; the presence of competing airports and airlines; the levels of landing charges; the speed of turnaround at the stand; and the services available to passengers. In response to the twin requirements of passengers and airlines, developers will seek to address and balance the following brief requirements: Passenger requirements Stress-free experience, including avoidance of queues Ease of access, with good parking, public transport and hotel infrastructure Quick processing times fo r security 03 / CLIENT REQUIREMENTS FOR TERMINAL FACILITIES
Transcript
  • 01.08.2008 BUILDING MAGAZINE

    E C O N O M I C Sanalysis / facts / forecast

    COST MODEL AIRPORT TERMINALSUK airport opera t o rs need to make substantial investments in inf ra s t r u c t u re to pre p a re fo r c o n t i n u i n glong-term demand fo r domestic and international flights. Simon Raw l i n s o n of D avis La n g d o n re p o r t s

    01 / INTRODUCTION

    A i r t ravel has become increasingly segmented,with budget airlines introducing new sets ofre q u i rements fo r fast terminal turnaround andminimal service. The types of flights and airliness e r ved will determine many of the principaldesign fe a t u res of a terminal, including airport-wide services, baggage handling, apron (are adesigned fo r loading and unloading passengersand cargo) and gate design, and retail.

    The main re q u i rements of the diffe rent servicetypes are as fo l l ows : Full-service airlines. These typically re q u i repier/gate service and dedicated facilities fo r

    p remium passengers. Full-service flights havel o n g e r t u r n - a round periods and often run anopen gate boarding policy, which reduces theneed fo r holding space at the gate. T h equantity and size of baggage is likely to behigh and the security profile of somedestinations may result in more bagsp ro g ressing to higher l evels of scre e n i n g Budget airlines. These work on a model ofmaximum throughput and minimal opera t i n gcost. Pa s s e n g e rs are held at gates prior t ob o a rding but few gate services are re q u i re d .Minimising turnaround time is v i t a l .

    D i s c o u raging hold baggage simplifies apro no p e rations but places more pre s s u re onp a s s e n g e r and hand-luggage screening. Tosimplify landside operations, budget carrierse n c o u rage e-ticketing and remote check-in C h a r t e r flights. These have a profile of highbaggage loads, longer t u r n a rounds and limitedp a s s e n g e r service. Pa s s e n g e rs also re q u i ree x t e n s i ve, off-airport long-term parking.Within the terminal, the key issue related toc h a r t e r flights is their contribution to peakf l ows at holiday times determining the sizingof many aspects of airport equipment.

    Air traffic has grown exponentially over thepast decade. UK passenger numbers totalled189 million in 2002 and are forecast to growto at least 350 million by 2020, and possiblyas high as 480 million.

    In response to forecast growth and withg overnment support, airport operators areplanning and implementing substantiali nvestment in additional capacity. The mostdynamic sector has been budget airlines, i nw h i ch passenger numbers grew 300% in thef ive years to 2005.

    In addition to expansion, existing fa c i l i t i e ss u ch as security need to be upgraded tomeet new requirements and countero b s o l e s c e n c e .

    H oweve r, the combination of an economic

    d ownturn and high oil prices willu n d o u b t e d ly challenge the business model ofm a ny airlines and the airports they serve . Fo rairport operat o r s , there will be great e rpressure on landing charges and operat i n gc o s t s . In providing a high-quality service fo rp a s s e n g e r s , a ny new terminal investment willneed to balance the scale of initial capitali nve s t m e n t , p r ovision for future expansionand operational efficiency, together with thei m p e r at ive to maximise revenues from allavailable income streams.

    The economic case for further expansion isdescribed in the 2003 white paper, The Futureof Air Tr a n s p o r t . Air travel underpins the UKsexports and its general bu s i n e s sp e r fo r m a n c e , as well as making a significant

    c o n t r i bution to tourism. Air transporthas also had an important social role inreducing the cost and time of long-distancet r ave l .

    The white paper ack n owledges thatcontinued investment should be balancedagainst the environmental effects ofexpanded air trave l , an issue that , c l e a r ly, h a snot been resolve d .

    In the meantime, BAA is well advanced inthe implementation of a 6bn inve s t m e n tprogramme to fo l l ow on from Terminal 5, a n dother operators in the privat e , public and PPPsectors are preparing major programmes fo rregional facilities in locations such asM a n ch e s t e r, B i r m i n g h a m , L iverpool andLeeds Bradfo r d .

    02 / TYPES OF AIRPORT TERMINAL

    Airport facilities are developed torespond both to existing levels ofdemand and future growth in traf f i c .I nvestment is targeted at attra c t i n gt wo key clients passengers and theairlines that serve them.

    Pa s s e n g e rs typically choose theirp refe r red airport on the basis of theavailability of routes, services and

    pricing, so being successful ina t t racting the right airlines and ro u t e sis critical to commercial success.

    Important fa c t o rs fo r p a s s e n g e rsalso include: location; ease of access;and the range of services prov i d e d .H oweve r, if the right flights are not onof fe r, passengers will not come.

    Key considerations in attra c t i n g

    airlines include: accessibility; the sizeof the local market; the availability ofr u nway capacity; the presence ofcompeting airports and airlines; thel evels of landing charges; the speed oft u r n a round at the stand; and theservices available to passengers .

    In response to the twin re q u i re m e n t sof passengers and airlines, deve l o p e rs

    will seek to address and balance thefo l l owing brief re q u i re m e n t s :Pa s s e n g e r re q u i re m e n t s St re s s - f ree experience, includingavoidance of queues Ease of access, with good parking,public transport and hoteli nf ra s t r u c t u re Quick processing times fo r s e c u r i t y

    03 / CLIENT REQUIREMENTS FOR TERMINAL FACILITIES

  • BUILDING MAGAZINE 01.08.2008

    Terminal 4 at Barajas airport in Madrid, designed by Rich a rd Rogers

    P a r t n e r s h i p, won the Stirling prize in 2006

    and baggage collectionShort travel distances and dire c t ,s i n g l e - l evel access to departure gatesUp-to-date flight information andc l e a r way - f i n d i n gTa rgeted retail and catering thatmeet the needs of diffe rent groups Facilities and information fo rm e e t e rs and gre e t e rs .

    Airline re q u i re m e n t sCapacity to respond to changingflight schedules and fleet Fa i l s afe operation of sys t e m s Flexibility to respond to changingbusiness needs C o s t - ef fe c t i ve design solutions tominimise landing charg e sC l e a r p rocess routes thro u g h

    d e p a r t u re and arrivals to preve n td e p a r t u re delaysWe l l - o rganised apron services tominimise turnaround time.

    The airport opera t o r will also haveits own development priorities. T h e s einclude: the optimisation of reve n u eg e n e ra t o rs such as retail; securityp rovision; and the achievement of

    va l u e - fo r - m o n ey investment thro u g hphasing the delivery of capacity inf i xed assets such as security andbaggage systems.

    T h i rd-party re q u i rements associatedwith security, airport services,p a s s e n g e r services and b a c k - of-house provision must also beaccommodated.

  • The key elements of a baggage handling sys t e mdesign are : A 100% secure env i ronment baggage flowf rom check-in to airc raft loading has to becompletely secure . Capacity and flow rates the time of check-inc l o s u re is determined by the wo rst-case pro c e s s i n gtime fo r bags through all levels of security. T h etypical time fo r a bag to pass directly thro u g hs c reening and straight onto the airc raft is about 12minutes. Meeting target times depends on capacityof the first stage of hold baggage screening thro u g hwhich all bags pass the latest machines typicallyh ave a capacity of 1,800 bags per h o u r The adopted baggage screening protocol thisvaries between countries and in the UK invo l ves af i ve-stage sequence of increasingly sophisticatedscanning techniques, including X- ray and CT

    scanning processes. Many of these processes areautomated, but input from specialist opera t o rs isre q u i red at defined stages in the pro c e s s .

    The main drive rs fo r sizing a baggage system are : The peak busy hour p a s s e n g e r f l ow A i rc raft size Flight type diffe rent types of flight haved i f fe rent load chara c t e r i s t i c s Bag profile based on destination, flight type ando t h e r fa c t o rs, the risk profile of baggage and thep rofile of scanning operations can be determined.

    O t h e r cost drive rs fo r baggage systems include: Redundancy and fa i l s afe provision particularlyfo r e x p l o s i ves detection systems and baggagesortation machines, which have high costs Load-sharing systems these enable baggage tobe directed evenly across all scanning lines so thatall elements of the system are utilised, maintenance

    can be carried out without disruption, andmechanical systems we a r at the same ra t e Management information systems covering bagt racking, processing times and other o p e ra t i o n a lkey performance indicators

    I n d i c a t i ve costs of baggage sys t e m s

    / sys t e m

    X- ray MVTHR scanner 2 0 0 , 0 0 0CT e xa m i n e r 6 0 0 , 0 0 0N e t work interfa c e 5 0 , 0 0 0X- ray scanner (hand baggage) 7 0 , 0 0 0Tilt tray sorter c o m p l e t e 1 0 , 0 0 0 / mM a ke-up caro u s e l 7 5 , 0 0 0Reclaim caro u s e l 9 0 , 0 0 0All costs are net of builders work, preliminaries andp rofessional fe e s .

    01.08.2008 BUILDING MAGAZINE

    4 2 / economics / cost model

    Capacity Terminals are being designed toaccommodate sustained expansion,which may invo l ve a phasedd evelopment of baggage handling,gates and stands.

    Capacity is determined by twomain variables: total annualp a s s e n g e r f l ow and peak passengerf l ow. Total flow is used to calculated e p a r t u re and airside spacea l l owances, while peak flow is usedto size elements linked w i t hp a s s e n g e r p rocessing such ass e c u r i t y, check-in and baggagehandling. In the UK, the designs t a n d a rd adopted is the 30th peakb u sy hour.

    Level of service International bodies including theInternational Civil Av i a t i o nO rg a n i zation and the InternationalA i r Transport Association assess

    p e r formance fo r check-in, security,queuing times and so on. These areused to justify landing charges, anda re a key element of competitionb e t ween hubs.

    Pa s s e n g e r experience Important aspects to managei n c l u d e : Rapid completion of check-in ands e c u r i t y. Clearing security is a majors o u rce of stress, so an ef f i c i e n tp rocess will make a majorcontribution to the passengerse x p e r i e n c e . C l e a r way-finding and orientation.Terminal buildings have becomel a rg e r and more complex, w i t hmultiple piers and gates. Ease ofn avigation, direct routes to gatesand information on travel times togates also reduce stress and help tog i ve more time fo r p a s s e n g e rs touse airside facilities.

    Humanising the scale Terminal buildings are necessarilyl a rge, but a clear l ayo u t ,well-signalled navigation fe a t u re sand high-quality signage all help tomitigate the scale. Re p e a t e delements of structure or c o l o u rb reak up very large spaces intos m a l l e r, more easily unders t o o dunits, as do repeated designfe a t u res at a variety of scales.

    Security Baggage-handling and holdbaggage screening are the principalelements of the security sys t e m ,but other elements includep e rsonnel screening, phys i c a lsecurity elements such as barriers ,the rationalisation of circ u l a t i o nroutes, the provision of clear lines of sight and the consideration of blast resistance in the s t r u c t u ral design.

    Transit systems Fo r l a rg e r terminals and piers ,t ransit systems become necessarywhen distances exceed 300m. Inaddition to the cost of the trave l a t o rsystem itself, the impact ofi n c reased circulation re q u i re m e n t son the footprint of the building alsoneeds to be taken into account

    Retail of fe rAirport retail diffe rs from highs t reet shopping in that customersa re captive and are passing thro u g ha process. Some terminals aredesigned to direct passenger f l owt h rough the retail of fe r. Optimisingfo o t fall and retail frontage isimportant, as is avoiding cold spotsin the flow of passengers around theterminal. In some terminals, the fo o dand drink of fe r is treated as thea n c h o r destination and retail isplanned around it.

    04 / DESIGN ISSUES

    05 / BAGGAGE HANDLING

    The large scale of terminals means that in public areas there are fewsignificant sources of heat load other than the building occupants. T h i ss o u rce fluctuates considerably in response to peak travel hours, so are s p o n s i ve ventilation system is essential. Low - l evel displacementventilation has become common, as comfort conditions need to bemaintained only in the passenger zone, and systems can take advantage ofl a rge building volumes fo r h i g h - l evel extraction of exhaust air.

    System capacity has to be designed to cope not only with anticipatedt raffic levels but also with the consequences of flight disruption and the

    l i ke. Design of air m ovement in public areas also needs to take account ofs m o ke extraction and contro l .

    S h a red airport systems such as common user terminal equipment (CUTE)and flight information are increasingly run across a common fibre-optic ITbackbone using internet protocols. While the distribution installation issimplified and more scalable, the actual on-site addressing of systems ishighly complex and needs an extended installation and commissioningp ro g ramme. Use of the common backbone also permits easier i n t e g ra t i o nand re c o nf i g u ration as the building adapts to new re q u i re m e n t s .

    06 / BUILDING SERVICES INSTALLATIONS

  • BUILDING MAGAZINE 01.08.2008

    The cost model fe atures the new - bu i l dconstruction of a regional-scale airportterminal handling both domestic andi n t e r n ational flights, with a gross internalfloor area of 25,000m2. The costs in theb r e a k d own exclude piers, air bridges andbaggage-handling systems, as well as allcosts of site preparat i o n , external wo r k s ,drainage and external services. The costs ofCUTE are also excluded.

    Costs are current in Ju ly 2008, based on al o c ation in south-east England.The level ofpricing assumes procurement on the basis ofa two-stage competitive tender, with designresponsibility for elements such as thecurtain walling and engineering servicesbeing taken by specialists as part of a pre-contract services agreement. A d j u s t m e n tshould be made to the costs detailed in themodel to account for va r i ations in phasing,s p e c i f i c at i o n , site conditions, p r o c u r e m e n tr o u t e , programme and market conditions.

    Location fa c t o rsThe cost breakdown is based on price leve l scurrent in the South-east and should beadjusted by the fo l l owing location fa c t o r s :South-east England 1 . 0 0S o u t h - west England 0 . 9 6East Midlands 0 . 9 3West Midlands 0 . 9 2East A n g l i a 0 . 9 6Yo r ks h i re and Humbers i d e 0 . 9 6N o r t h - west England 0 . 9 2Northern England 0 . 9 7S c o t l a n d 0 . 9 9Wa l e s 0 . 9 6Northern Ire l a n d 0.75

    The complex operations found particularly w h e nworking in restricted airside zones create a w i d erange of additional cost drive rs.

    Security clearance is a key issue,particularly with airside working, and makes thep rocessing of personnel and d e l i veries potentiallysubject to long delays. Contra c t o rs tend to useestablished supply chains, which already havesecurity clearance and trained opera t i ves, althoughthis may reduce competitive pre s s u re inp ro c u rement.

    As airside working adds significantly to pro j e c tcosts, sites should be conf i g u red w h e reve r p o s s i b l eso that they can be managed as landside pro j e c t swith conventional pro c e d u res.

    Re q u i rements and restrictions associated w i t ha i rside working include: H i g h e r costs of third-party legal liability insura n c e Cost of training associated with driving andwo r ks permits Maintenance of restricted zone boundary C o n t rol of airborne dust and debris to avo i dingestion by airc raft engines V i b ration limits when working in proximity tos e n s i t i ve buildings Remote facilities, including we l fa re ,a d m i n i s t ration, storage and parking, owing top re s s u re on airside space.

    O t h e r airport-specific constraints thatcan af fect terminal design and constructioni n c l u d e : Re q u i rement of stake h o l d e rs, including theDepartment of Transport, customs special bra n c hand so on Civil Aviation Authority (CAA) restrictions onpermanent building heights within safety glides l o p e s Enhanced acoustic control and monitoring

    m e a s u re s P revention of electromagnetic interfe rence andthe minimisation of ra d a r s i g n a t u re s CAA restrictions on crane heights within s afety glide slopes and restrictions on the use of ra d i o s O u t - of - h o u rs working and phased development to minimise disruption to passengers and a i rc raf t C o n t rols on delivery and construction traffic top revent airport road congestion.

    P ro c u rement of specialist equipment is anotherkey consideration. Airport opera t o rs are adopting arange of alternative pro c u rement routes in acontinuing search fo r the optimum balance of riskand competitive pricing.

    H oweve r, terminal development invo l ve sm a ny specialist systems such as baggagehandling, air bridges and shared info r m a t i o nsystems and these re q u i re specialist designto be completed alongside the initial designd evelopment. Two-stage approaches to thea g reement of package contract sums enable designinput and co-ordination to be secured during earlystages of the pro j e c t .

    T h e re are a large number of stake h o l d e rs invo l ve din a terminal project, with interests ranging fro ms e c u r i t y, passport and customs control, to theo p e rational and commercial interests of multipleairlines. In a global industry, the securityre q u i rements of destinations such as the US mayalso need to be taken into account.

    With so many interests to be re c o n c i l e d ,finalising and adhering to project briefs andsecuring strong decision-making is a challenge.St a ke h o l d e r management should be a key clientresponsibility but also needs to be facilitated by thep roject team.

    07 / PROJECT MANAGEMENT AND PROCUREMENT 08 / COST BREAKDOWN

    Kohn Pedersen Fox s Midfield Terminal at A bu Dhabi

    a i rport will process more than 50 million passengers a ye a r

  • 01.08.2008 BUILDING MAGAZINE

    4 4 / economics / cost model

    / m2 G I FA %

    S u b s t r u c t u re 4 , 3 0 7 , 0 0 0 1 7 2 . 2 8 6 . 0 2

    U n d e rc roft construction; re d u c e d - l evel exc avation, 200mm-thick re i nfo rced con-c rete ground slab, hard c o re, damp-pro of membrane: 8,550m2 @ 300G round slab; 200mm-thick re i nfo rced insitu concrete bed, hard c o re, damp-pro ofm e m b rane: 1,050m2 @ 120E x t ra fo r retaining walls, l inings etc: item @ 320,000E x t ra fo r foundations; isolated pad and raft foundations: 9,600m2 @ 105A l l owance fo r b e l ow - g round drainage and incoming services: 9,600m2 @ 30

    F ra m e 3 , 5 8 5 , 8 0 0 1 4 3 . 4 3 5 . 0 1

    A l l owance fo r s t r u c t u ral steel framing based on 80kg / m2 ( ave rage rate fo r u n i ve rs a land hollow sections): 1,330t @ 2,300A l l owance fo r s t r u c t u ral steelwork to office mezzanine, based on 35kg / m2: 25t @ 1 , 9 5 0A l l owance fo r additional framing/trimming to service risers and openings fo r b a g-gage conveyo rs: item @ 160,000C o l d - rolled galvanised steel ro of purlins; 1.6m centres, 4.5kg/m ave rage we i g h t :9,300m @ 10Intumescent 1hr f i re - resistant paint finish: 15,000m2 @ 15

    U p p e r f l o o rs 1 , 5 7 0 , 0 0 0 6 2 . 8 0 2 . 2 0

    P re s t ressed, precast concrete structural suspended floor units; 50mm-thick struc-t u ral topping: 14,800m2 @ 95E x t ra fo r 7 . 5 k N / m2 f l o o r loading to plant room areas: 500m2 @ 8E x t ra fo r formation of openings, l ift and escalator pits etc: item @ 160,000

    Ro of 5 , 5 5 1 , 5 0 0 2 2 2 . 0 6 7 . 7 6

    Ro of cladding, including perfo rated fe a t u re cladding, raised-seam aluminium ro of i n g ,s t r u c t u ral deck, insulation, va p o u r b a r r i e r and liner: 9,200m2 @ 285E x t ra fo r ro oflights, with sealed double-glazed units, powder-coated aluminiumf raming and secondary steelwork including perfo rated panel sunscreens: 900m2 @ 9 5 0A l l owance fo r work to boundaries, gutters, ro oflights, openings etc: 7,500m @ 80P recast concrete ro of slabs; 7.5kN/m2 f l o o r loading, fo r ro of - l evel plant, with wa t e r-p ro of membrane, plinths and bases: 450m2 @ 250Full-length entra n c e / s e t - d own canopy, complete with hollow-section framing, curve daluminium raised-seam ro ofing, ro oflights: 1,300m2 @ 900A l l owance fo r ro of safety system: 1,200m @ 160

    St a i rs 8 0 7 , 0 0 0 3 2 . 2 8 1 . 1 3

    Steel fe a t u re stair and half-landings, ove rall rise 5.50m, with toughened, laminatedglass balustrade, stainless steel handrails, finishes: 2 nr @ 40,000Steel fe a t u re stair, ove rall rise 3.00m, with toughened, laminated glass balustra d e ,stainless steel handrails, finishes: 2 nr @ 32,000P recast concrete stairs and half-landings, ove rall rise 5.50m, with stainless steelh a n d rails, finishes: 2 nr @ 26,000P recast concrete stairs and half-landings, ove rall rise 5.50m, with polye s t e r p ow-der-coated steel handrails, finishes: 16 nr @ 20,000B a l u s t rade and handrail to mezzanine and first floor with toughened laminated glassb a l u s t rade and stainless steel handrail: 190m @ 900A l l owance fo r access platforms and stairs to plant rooms: item @ 100,000A l l owance fo r ro of access, stairs and hatches: item @ 20,000

    External walls, w i n d ows and doors6 , 8 4 0 , 2 0 0 2 7 3 . 6 1 9 . 5 7

    Wall cladding; aluminium-faced composite panels with 25% glazing in aluminium-f ramed sealed double-glazed units, flashings and accessories: internal lining,including 140mm-thick blockwork backing wall: 7,000m2 @ 650Curtain walling; silicone-sealed double-glazed units, colour-coated aluminium fra m-ing, flashings and accessories: 1,750m2 @ 900

    E x t ra fo r s h o pf ront fe a t u re curtain walling to entrance areas: 100m2 @ 400E x t ra fo r triple-glazing and increased depth of framing to airside curtain wa l l i n g :4 8 0 m2 @ 240Lo u v re panels to plant areas, of powder-coated aluminium: 250m2 @ 400Principal entrance double doorsets (2 nr) and wind lobby, fully glazed with iro n m o n-gery and accessories: 6 nr @ 50,000A l u m i n i u m - faced powder-coated vision-panel double doors and frames, with iro n-mongery: 10 nr @ 10,000High-speed sectional doors to baggage handling, electrically operated, includingc o n t rols: 4 nr @ 15,000

    Internal walls and partitions 2 , 0 9 9 , 0 0 0 8 3 . 9 6 2 . 9 4

    Insitu concrete shear walls to stair c o res and service risers, 250mm ave rage thick-ness: 2,500m2 @ 140B l o c k work partitions, 140mm ave rage thickness, with head re s t raint: 7,700m2 @ 6 0Metal stud partitions; 5.0m high, single-laye r i m p a c t - resistant board, single-laye rwa l l b o a rd, each side, to public areas: 2,500m2 @ 80Metal stud partitions; double-laye r wa l l b o a rd, each side, to office areas: 1,050m2 @ 6 0Metal stud partitions; shaf t wall construction, double-laye r f i reline board, single-l aye r c o re board, one side only: 2,000m2 @ 100Fascia panel to ticket sales desks: 40m @ 800Fully glazed shopf ronts; fascia panel: 160m @ 3,200Toilet cubicle partitions: 50 nr @ 1,600M e l a m i n e - faced solid-laminate access panelling to WCs etc: 150 nr @ 800A l l owance fo r additional screens and partitions: item @ 80,000

    Internal doors 3 7 1 , 1 0 0 1 4 . 8 4 0 . 5 2

    Flush doors to public areas, solid-core laminate/ve n e e r - faced with hard wood fra m e sand ironmongery: 100 nr @ 1,450Flush doors to administration areas, solid-core laminate/ve n e e r - faced with hard-wood frames and ironmongery: 72 nr @ 1,300Duct access doors: 100 nr @ 1,125A l l owance fo r additional services access panels: item @ 20,000

    Wall finishes 1 , 2 2 4 , 6 0 0 4 8 . 9 8 1 . 7 1

    Independent wall lining; plasterboard lining to inner face of external walls: 4,600m2

    @ 50E x t ra ove r p l a s t e r b o a rd linings fo r laminate-finish wall panelling: 2,500m2 @ 15Laminate-finish wall panelling to blockwork: 3,700m2 @ 65C e ramic tiles with sand cement backing to concrete or b l o c k work: 300m2 @ 6513mm double-coat lightweight plaster and two coats emulsion paint tob l o c k wo r k / c o n c rete: 10,900m2 @ 20Two coats emulsion paint to blockwork: 6,650m2 @ 5Skim coat and two coats emulsion paint to plasterboard: 5,900m2 @ 12Wall pro t e c t o rs, stainless steel pro t e c t i ve rails: 1,500m @ 250

    F l o o r f i n i s h e s 1 , 7 2 0 , 5 0 0 6 8 . 8 2 2 . 4 1

    Sand cement screed, ave rage 40mm thick: 10,040m2 @ 24G ranite terra z zo floor tiles, 300 x 300mm, including allowance fo r skirtings, move-ment joints and brass division strips: 6,540m2 @ 130Vitrified ceramic tiles, 400 x 400mm, including allowance fo r skirtings and move-ment joints: 1,100m2 @ 95Raised access floor, carpet tile, to office areas: 800m2 @ 65H e avy-duty carpet tiles, including allowance fo r skirtings: 2,400m2 @ 45V i nyl floor tiles and levelling screed, including allowance fo r skirtings, to core are a s :2 , 5 5 0 m2 @ 40E x t ra fo r finish to WCs: 400m2 @ 76C o n c rete hard e n e r to concession shells, plant rooms and baggage handling, andskirtings: 10,300m2 @ 8A l l owance fo r additional floor finishes: item @ 100,000

    A / COST BREAKDOWN

  • BUILDING MAGAZINE 01.08.2008

    economics / cost model / 4 5

    A l l owance fo r mats and matwells: item @ 50,000

    Ceiling finishes 1 , 1 4 8 , 9 0 0 4 5 . 9 6 1 . 6 1

    Suspended ceilings, open-grid ceiling, generally: 3,400m2 @ 120Finish to ro of soffit generally: 8,300m2 @ 30Suspended ceilings, including metal pan tiles and lay-in grid: 1,650m2 @ 65Suspended ceilings, including minera l - f i b re tiles to core areas: 440m2 @ 40E x t ra ove r ceiling finishes generally fo r acoustic treatment: 6,000m2 @ 35E x t ra fo r m o i s t u re - resistant ceiling tiles to WC areas: 400m2 @ 10C o n c rete sealant to concession shells, plant rooms and baggage handling:1 0 , 3 0 0 m2 @ 10E x t ra fo r 4 h r f i re protection to areas of underc roft plant room soffit: 500m2 @ 1 0 0

    F u r n i t u re and fittings 1 , 7 7 0 , 0 0 0 7 0 . 8 0 2 . 4 8

    Check-in desks: 64 nr @ 5,000O u t - of-gauge baggage counter: item @ 40,000I nformation and security desks: item @ 80,000T i c ket desks: 20 nr @ 10,000Statutory and directional signage: item @ 240,000Seating to check-in and departure lounge areas: 400 nr @ 250A l l owance fo r f i x t u res and fittings generally to public areas: item @ 320,000A l l owance fo r f u r n i t u re and equipment to check-in and ticket sales areas (exc l u d i n gI T installations): item @ 320,000A l l owance fo r fittings to back-of-house areas: item @ 150,000

    Sanitary fittings 1 1 4 , 5 0 0 4 . 5 8 0 . 1 6

    WCs, urinals, hand basins generally: 150 nr @ 650A l l owance fo r fittings fo r disabled WCs: item @ 8,100C l e a n e rs sinks: 6 nr @ 650A l l owance fo r d r i n k i n g - wa t e r fountains: item @ 5,000

    Disposal installations 4 4 5 , 0 0 0 1 7 . 8 0 0 . 6 2

    Ra i nwa t e r disposal, including cast-iron downpipes and fittings: 25,000m2 @ 6Waste, soil and vent installation: 25,000m2 @ 8A l l owance fo r pumped disposal from underc roft: item @ 95,000

    B o i l e r p l a n t s 4 5 0 , 0 0 0 1 8 . 0 0 0 . 6 3

    Hot and cold wa t e r service, including calorifiers, hot and cold wa t e r s t o rage and dis-tribution: 25,000m2 @ 18

    Space heating and air t re a t m e n t 9 , 6 1 0 , 9 0 0 3 8 4 . 4 4 1 3 . 4 4

    Gas installation: item @ 32,000Low - t e m p e ra t u re hot wa t e r heating (boiler plant), including stainless steel flues,pumps and va l ves, distribution within plant rooms, insulation: 25,000m2 @ 24 Low - t e m p e ra t u re hot wa t e r heating (perimeter heating), including LT H W e l e m e n t sand distribution: 25,000m2 @ 38Chilled wa t e r installation, including chillers and cooling towe rs (total load 2,500kW),p ressurisation unit, pumps and va l ves, distribution pipework, insulation and tra c eheating: 25,000m2 @ 64Supply and extract ventilation: air-handling unit with heating and cooling batteries;d u c t work in risers and plant rooms: 25,000m2 @ 32Supply and extract ventilation: displacement system; ductwork, grilles and dif-f u s e rs, insulation; to public areas: 13,500m2 @ 290Air-conditioning: four-pipe fan-coil installation to office areas, check-in etc; LT H Wand chilled wa t e r distribution, condensate drainage, fan-coil units, ductwork, insula-tion, grilles and diffusers: 1,650m2 @ 250A l l owance fo r services to comms rooms: item @ 240,000Mechanical ventilation to baggage handling and plant rooms: 7,400m2 @ 80Toilet extract installation: 25,000m2 @ 8A l l owance fo r s m o ke extract to public areas, ro of - l evel extract: 13,500m2 @ 10

    E x t ra fo r s m o ke extract to baggage handling: 4,200m2 @ 32

    Electrical installations 6 , 9 1 3 , 8 0 0 2 7 6 . 5 5 9 . 6 7

    H V sw i t c h g e a r, 5mVA, tra n sfo r m e rs, HV cable, LV switchgear: item @ 1,600,000St a n d by generation (1,750kVA) fo r essential services only: item @ 800,000Mains and sub-mains installation: 25,000m2 @ 46Small powe r distribution: 25,000m2 @ 16Lighting and luminaires to public areas: 13,500m2 @ 120Lighting and luminaires to check-in, ticket sales and offices: 1,650m2 @ 90Lighting and luminaires to core, plant and baggage handling: 9,850m2 @ 65E m e rgency lighting installation: 25,000m2 @ 15Powe r to mechanical services: item @ 180,000

    Lift installations 1 , 5 6 0 , 0 0 0 6 2 . 4 0 2 . 1 8

    2 6 - p e rson, 0.6m/s electro - hyd raulic lift serving 2 floors: 4 nr @ 150,0002 , 0 0 0 kg goods lift serving 3 floors: 2 nr @ 160,000E s c a l a t o r, 0.5m/s, 1m step-width, 5.2m rise, glass balustrade: 4 nr @ 160,000

    P ro t e c t i ve installations 1 , 2 1 0 , 0 0 0 4 8 . 4 0 1 . 6 9

    Lightning protection: 25,000m2 @ 3Earthing and bonding: 25,000m2 @ 5S p r i n k l e r installation, with storage tank, pumps and pipework: 25,000m2 @ 32A l l owance fo r d r y - r i s e r and hose-reel installations: item @ 160,000F i re - s u p p ression installation to comms room: item @ 50,000

    Communications installations 4 , 0 7 5 , 0 0 0 1 6 3 . 0 0 5 . 7 0

    Fully addressable fire and smoke detection and alarm system: 25,000m2 @ 30Voice/public address system with interfaces to flight information, fire and securitysystems: 25,000m2 @ 16I n t r u d e r detection: 25,000m2 @ 10A l l owance fo r s e c u r i t y, CCT V and access control: 25,000m2 @ 32W i reways fo r telephones, data and structured cable: 25,000m2 @ 13St r u c t u red cable installation, linking check-in, ticket desks and security contro lpoints: 25,000m2 @ 30A l l owance fo r flight information display system; 100 LED displays, 150 monitors :item @ 800,000

    Special installations 1 , 3 5 0 , 0 0 0 5 4 . 0 0 1 . 8 9

    Building management system: 25,000m2 @ 54(Baggage-handling installation exc l u d e d )

    B u i l d e r s work in connection 7 7 0 , 0 0 0 3 0 . 8 0 1 . 0 8

    A l l owance fo r forming holes, chases etc @ 3%: item @ 770,000

    P reliminaries and contingencies1 4 , 0 5 0 , 2 0 0 5 6 0 . 2 1 1 9 . 5 9

    A l l owance fo r c o n t ra c t o r s overheads, site establishment and site supervision @18%: item @ 10,387,000A l l owance fo r commissioning management: item @ 250,000A l l owance fo r design re s e r ve @ 5%: item @ 3,368,200

    Total construction cost (building only)7 1 , 5 0 0 , 0 0 02 8 6 0 . 0 0 1 0 0 . 0 0