• First floor termite protection sprayed on west half of HQ building
• Poured West Side First Floor at HQ on Friday 9.18.09
• Began the remainder of the 30” Storm Sewer Run-out to Inlet Boxes
• Erected Crane for Elevated Work
• Approaches to John Kimbrough 100% complete
• Grade beams are 100% complete on the HQ Building
• All pedestals on the cistern canopy pile caps are poured
• Poured the first floor deck over the crawlspace at VC on Tuesday
• Started backfill at the crawlspace walls at the VC
• Formed, reinforced, and poured shear wall at HQ
• Storm lines to underground tank ongoing
Texas A&M University Agriculture Headquarters
Week ly Repo r t : 9 / 1 4 / 09 - 9 / 18 / 09
North View Scaffold Training
West Side First Floor Concrete Pour Crane Assembly Fire Extinguisher Training
Shear Wall at HQ