+ All Categories
Home > Documents > 2009-09-18

2009-09-18

Date post: 10-Mar-2016
Category:
Upload: texas-am-agrilife
View: 213 times
Download: 0 times
Share this document with a friend
Description:
• Erected Crane for Elevated Work • Formed, reinforced, and poured shear wall at HQ • Poured the first floor deck over the crawlspace at VC on Tuesday • Poured West Side First Floor at HQ on Friday 9.18.09 • Began the remainder of the 30” Storm Sewer Run-out to Inlet Boxes • First floor termite protection sprayed on west half of HQ building • All pedestals on the cistern canopy pile caps are poured • Started backfill at the crawlspace walls at the VC North View
Popular Tags:
1
First floor termite protection sprayed on west half of HQ building Poured West Side First Floor at HQ on Friday 9.18.09 Began the remainder of the 30” Storm Sewer Run-out to Inlet Boxes Erected Crane for Elevated Work Approaches to John Kimbrough 100% complete Grade beams are 100% complete on the HQ Building All pedestals on the cistern canopy pile caps are poured Poured the first floor deck over the crawlspace at VC on Tuesday Started backfill at the crawlspace walls at the VC Formed, reinforced, and poured shear wall at HQ Storm lines to underground tank ongoing Texas A&M University Agriculture Headquarters Weekly Report: 9/14/09-9/18/09 North View Scaffold Training West Side First Floor Concrete Pour Crane Assembly Fire Extinguisher Training Shear Wall at HQ
Transcript

• First floor termite protection sprayed on west half of HQ building

• Poured West Side First Floor at HQ on Friday 9.18.09

• Began the remainder of the 30” Storm Sewer Run-out to Inlet Boxes

• Erected Crane for Elevated Work

• Approaches to John Kimbrough 100% complete

• Grade beams are 100% complete on the HQ Building

• All pedestals on the cistern canopy pile caps are poured

• Poured the first floor deck over the crawlspace at VC on Tuesday

• Started backfill at the crawlspace walls at the VC

• Formed, reinforced, and poured shear wall at HQ

• Storm lines to underground tank ongoing

Texas A&M University Agriculture Headquarters

Week ly Repo r t : 9 / 1 4 / 09 - 9 / 18 / 09

North View Scaffold Training

West Side First Floor Concrete Pour Crane Assembly Fire Extinguisher Training

Shear Wall at HQ

Recommended