+ All Categories
Home > Documents > 2009 Work Product Review Group Orientation€¦ · 1980 ft tall, steel framed tower 3 leg mast guy...

2009 Work Product Review Group Orientation€¦ · 1980 ft tall, steel framed tower 3 leg mast guy...

Date post: 18-Jul-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
15
8/29/2010 1 CASE STUDY Structural Clay Tile Floor Failure Background “Sheffield” tile floor system Simple span of 31 ft - 6 in Constructed in 1961 Floor of grade school library/study area Background Cracking/popping noises heard by library occupants on normal day Library and classroom below vacated Floor cracks and sags became visible within next few hours Floor appeared to stabilize after several inches of deflection Site Observations Proprietary clay tile/concrete composite slab system No signs of pre-existing deterioration or distress in Library or other rooms Live loading appeared relatively light No signs of structurally significant modifications Site Observations Library 31.5 ft One-way slab span Typical load bearing walls Beam Plan view showing floor layout Site Observations Isometric view of typical Sheffield Tile installation
Transcript
Page 1: 2009 Work Product Review Group Orientation€¦ · 1980 ft tall, steel framed tower 3 leg mast guy cables at nine elevations on each leg Legs consist of 6” dia. solid rounds X-bracing

8/29/2010

1

CASE STUDYStructural Clay Tile Floor Failure

Background

“Sheffield” tile floor system

Simple span of 31 ft - 6 in

Constructed in 1961

Floor of grade school library/study area

Background

Cracking/popping noises heard by library occupants on normal day

Library and classroom below vacated

Floor cracks and sags became visible within next few hours

Floor appeared to stabilize after several inches of deflection

Site Observations

Proprietary clay tile/concrete composite slab system

No signs of pre-existing deterioration or distress in Library or other rooms

Live loading appeared relatively light

No signs of structurally significant modifications

Site Observations

Library

31.5 ft

One-wayslab span

Typicalloadbearingwalls

Beam

Plan viewshowingfloor layout

Site Observations

Isometric viewof typicalSheffield Tileinstallation

Page 2: 2009 Work Product Review Group Orientation€¦ · 1980 ft tall, steel framed tower 3 leg mast guy cables at nine elevations on each leg Legs consist of 6” dia. solid rounds X-bracing

8/29/2010

2

Site Observations

8” unit

4”

8”

Concrete topping

1.25” dia. bar

Cross sectionshowing typicalSheffield Tileunit, topping, andreinforcing bar

Site Observations

Damaged plaster andexposed underside of floor system

Site Observations

Bucket of backhoe was pressed onto floor to assess short term stability before removing important items from library

Site Observations

Lower portionof floor system collapsed about 3 weeks after load test!

Site Observations

Looking up into coredhole from room below(Intact slab)

Site Observations

Cores showing large planardiscontinuities in tiles

Topping

Topping

Joint

Plaster

Page 3: 2009 Work Product Review Group Orientation€¦ · 1980 ft tall, steel framed tower 3 leg mast guy cables at nine elevations on each leg Legs consist of 6” dia. solid rounds X-bracing

8/29/2010

3

Analysis

Identify critical stresses in tile units

Compare with test data

Typical Flexural Member

C

T

v

Solid web is primarily a shear element

Analysis

Portion of typical flexural member

shear flow=

reinf. steel

Shear flowmechanism intypical flexuralmember

Sheffield Flexural Member

C

T

v

Web is not solid. Discrete web elements sustain much more than shear.

ΔT

ΔT

mVertical tension and compression

ΔT

ΔT

Analysis

Shear flowmechanism intypical sectionof SheffieldTile beam

Analysis

TVsVs

Vc Vc

Tensile stress along top of tilewall due to the fact that:

T x d > 2 Vs x 6”

12” unit

d

Tile joints every 12”create significantbending tensilestresses acrosstile discontinuitiesthat exist in upperportions of walls

T

Page 4: 2009 Work Product Review Group Orientation€¦ · 1980 ft tall, steel framed tower 3 leg mast guy cables at nine elevations on each leg Legs consist of 6” dia. solid rounds X-bracing

8/29/2010

4

Site Testing

Core penetration

Pull up until failure aftercoring to depth shown

Lift off testing on intactfloor areas to estimatetensile strength of tilein critical area

Site Testing

Failure surface afterlift off test showingextent of core waterpenetration oneventual failure plane

Site Testing

In-situ tensile testing indicated average strength of about 120 psi, with standard deviation of about 40 psi

Several specimens were loose after coring (these were not included in the statistics shown above)

Analysis

Load-induced tile wall tensile stresses were estimated using floor system self weight only

Self weight stresses were estimated to be nearly 100 psi in highest shear areas

These stresses would increase over time due to clay tile swelling and concrete topping shrinkage

Volume Change Effects

Topping

Tile Tile

Concrete shrinks

Clay tile expands Clay tile expands

Volume Change Effects

Topping

Tile Tile

Initial compressive stress distribution

Comp. centroid

Page 5: 2009 Work Product Review Group Orientation€¦ · 1980 ft tall, steel framed tower 3 leg mast guy cables at nine elevations on each leg Legs consist of 6” dia. solid rounds X-bracing

8/29/2010

5

Volume Change Effects

Topping

Tile Tile

Long-term compressive stress distribution

Comp. centroid

Concrete shrinkage and tile expansion cause stresses to increase here Lower comp. centroid means

increased force needed for same moment. Larger force means more local (vertical) tension in tile

Conclusion

Floor system failed due to inadequate tensile strength in critical areas of tile units

Long term tile growth and accumulation of web failures caused situation to become critical almost 40 years after construction

Design/development of this system failed to recognize significance of closely spaced vertical joints in combination with inherent material weaknesses

etc.

Stamped writing reads:SHEFFIELD

LOAD BEARING TILE

etc.

CASE STUDYBillboard Shaft Failure

Background

Original structure completed in late 1988

Sign board extended about 5.5 ft shortly thereafter

Overall height about 150 ft

Sign board dim. (with apron) 48’ x 23’

Step-tapered steel pipe shaft; diameters ranging from 36” to 60”; wall thicknesses from 0.43” to 0.63”

Page 6: 2009 Work Product Review Group Orientation€¦ · 1980 ft tall, steel framed tower 3 leg mast guy cables at nine elevations on each leg Legs consist of 6” dia. solid rounds X-bracing

8/29/2010

6

Background

Elevation and typicalconnection detail fromoriginal design drawings

Background

Photo of recently completedsign, before extensionof sign board

Background

Steel shaft failed in late 1992 (less than four years in service)

Failure occurred on relatively calm day

Failure involved fracture of steel pipe shaft at splice location

Background

Photos of structure shortly afterfailure

Site Observations

Fracture surface clearly included substantial areas of fatigue cracking

Fatigue cracking located on opposite sides of pipe

Fatigue crack location consistent with sign displacements normal to faces of sign boards

Two other joints had cracked through entire wall thickness

Site Observations

Clear fatiguecracking in areasof fracture surfaceshown by arrows

Page 7: 2009 Work Product Review Group Orientation€¦ · 1980 ft tall, steel framed tower 3 leg mast guy cables at nine elevations on each leg Legs consist of 6” dia. solid rounds X-bracing

8/29/2010

7

Site Observations

Fatigue cracks justbelow fracturesurface, in weld ofring plate to lowerpipe

Site Observations

Through wall crackat joint above fracturelocation; seen frominside fallen sectionof shaft

Site Observations

Cracking at toe offillet weld in anothershaft joint

Analysis

Plan view

Oscillationcaused by vortex shedding

Vortex sheddingat ends of signs

Winddirection

Sign

Sign structure prone to oscillationdue to vortexshedding

Analysis

Plan view

Oscillationcaused by vortex shedding

Vortex sheddingat ends of signs

Winddirection

Sign

Direction of oscillationconsistent with fatiguecrack orientation

Area of fatigue cracking

Plan at fracture location

Analysis

Plan view

Oscillationcaused by vortex shedding

Vortex sheddingat ends of signs

Winddirection

Sign Fundamental periodof vibration about 2 sec

Wind speed causingresonance about 15 to20 mph

Page 8: 2009 Work Product Review Group Orientation€¦ · 1980 ft tall, steel framed tower 3 leg mast guy cables at nine elevations on each leg Legs consist of 6” dia. solid rounds X-bracing

8/29/2010

8

Analysis

Plan view

Oscillationcaused by vortex shedding

Vortex sheddingat ends of signs

Winddirection

Sign

Stress range associatedwith resonance estimatedto be between 10 and 20ksi

Analysis

Transverse weld on pipe sections similar to Category C detail

Recommended stress range limits for Category C details: 500,000 to 2,000,000 cycles: 13 ksi

Resonant conditions produce 500,000 cycles in 278 hours; which is less than one percent of structure’s lifespan

Conclusion

Shaft failed due to wind-induced fatigue that should have been anticipated

Additional Efforts

Microscopic examination of failure surface to quantify stress ranges that caused fatigue crack growth and number of cycles prior to failure

CASE STUDYRoof Failure

Background

Structure consisted of steel trusses supporting roof deck

Structure about 40 years old

Recently renovated, including truss modifications

Building expanded a few years before collapse

Page 9: 2009 Work Product Review Group Orientation€¦ · 1980 ft tall, steel framed tower 3 leg mast guy cables at nine elevations on each leg Legs consist of 6” dia. solid rounds X-bracing

8/29/2010

9

Background

Collapse occurred under accumulation of snow

Recent snow fall accompanied by westerly winds preceded event

Background

1980’s

Cross Section Through Building

1950’s

Collapse drift sourceOriginal drift source

Collapse area

Background

Typical framing athigh/low rooftransition

low roof truss

high roof truss

column

Background

high roof

low roof

Site Observations

20 ft

6 f

t 15 pcf

20 pcf

Typical drift conditions

Site Observations

First web compression element of many trussesbuckled as shown (element nearest high/low step)

Page 10: 2009 Work Product Review Group Orientation€¦ · 1980 ft tall, steel framed tower 3 leg mast guy cables at nine elevations on each leg Legs consist of 6” dia. solid rounds X-bracing

8/29/2010

10

Analysis

Compare capacity of endcompression element todemands associated withdrift measurements

Analysis

Eccentricallyloaded singleangle:

actual

modelMeasuring rotationalrestraint at ends oftypical angle

Analysis

Accounting for eccentricity of load, ultimate axial capacity was slightly less than 11 kips

Calculated load due to measured drift parameters was 11.1 kips

Calculated demand due to code specified service loads was about 14.4 kips

Other Observations

Top chord was reinforced as part of renovation (still deficient with respect to code required loading)

Single angle compression element had sufficient strength if loaded concentrically

Conclusions

Trusses failed well below required nominal strengths

Single angle compression element had sufficient strength if loaded concentrically

Structure survived for decades due to small snow drift source CASE STUDY

Guyed Tower

Page 11: 2009 Work Product Review Group Orientation€¦ · 1980 ft tall, steel framed tower 3 leg mast guy cables at nine elevations on each leg Legs consist of 6” dia. solid rounds X-bracing

8/29/2010

11

Background

1980 ft tall, steel framed tower

3 leg mast

guy cables at nine elevations on each leg

Legs consist of 6” dia. solid rounds

X-bracing consists of 0.75” dia. rounds being replaced with 0.875” dia. rounds

Background

Tower fell on very calm day

Brace replacement work was in progress

Background

Typical mast framing

Site Observations

All guy cables andtheir anchorageswere intact

Site Observations

Old bracing

New bracing

Site Observations

Temporarybracing frameused whenreplacingbrace rods

Page 12: 2009 Work Product Review Group Orientation€¦ · 1980 ft tall, steel framed tower 3 leg mast guy cables at nine elevations on each leg Legs consist of 6” dia. solid rounds X-bracing

8/29/2010

12

Site Observations

Partial elevation

Typical towersegment

Temporarybracing framebolted to legs

Temporary bracingframe allowed for saferemoval of brace rodswithin frame boundaries.

This work was underwaywhen tower fell.

Typicalbracerod

Site Observations

In bay abovetemporaryframe, bothconnectionplates lookedlike this for oneof the rods

No bolts, no hole distress

Analysis

15 ft bay above temporary frame had one brace disengaged

Evaluate stability of unbraced bay

Axial load due to gravity = 330 kips/leg at unbraced location (below lowermost guy point)

Analysis1

5 f

t

Leg segments above andbelow unbraced segmentsprovide rotational restraintat ends of buckling legs.

The extent to which such restraint is provided dependsupon whether or notintermediate horizontalmembers provide lateralrestraint at mid bay.

Rods run thruU-bolt

Which bowedshape right?

330 k/leg

Analysis

Assume initial misalignment of L/500 between ends of unbraced segments

Axial load causing yielding to begin in leg rods with mid bay horizontal fully effective = 320 kips

Axial load causing yielding to begin in leg with ineffective mid bay member = 290 kips

Conclusions

Ultimate capacities of unbraced legs in range of gravity load demands

Tower fell because brace was removed without other means of lateral bracing in place

Page 13: 2009 Work Product Review Group Orientation€¦ · 1980 ft tall, steel framed tower 3 leg mast guy cables at nine elevations on each leg Legs consist of 6” dia. solid rounds X-bracing

8/29/2010

13

CASE STUDYA Near Miss Analysis Breakdown

74

75

Rear legs

Front leg

Drive leg

Underbridge

76

Rear legs

Front leg

Underbridge

77

Front leg Drive leg

Underbridge

Rear legsFront leg

Drive leg

Underbridge

Page 14: 2009 Work Product Review Group Orientation€¦ · 1980 ft tall, steel framed tower 3 leg mast guy cables at nine elevations on each leg Legs consist of 6” dia. solid rounds X-bracing

8/29/2010

14

79

Fully extended,

suspended underbridge

Maximum load on extended front leg

Extended front leg

R

Initial pier check

method:Simply analyze pier as

a free standing column

with an axial load.

Substantially

overestimated

capacity.

Modified pier check

method:Apply gantry reaction via

rigid; pinned-pinned link.

Pier bracing required at

the taller piers would not

have been identified

otherwise

System Schematic

R

R

Underbridge weight

Gantry weight

Pier (not laterally braced)

R

Vertical and lateral support

on completed deck

Front leg; pinned at each end

82

83 84

Page 15: 2009 Work Product Review Group Orientation€¦ · 1980 ft tall, steel framed tower 3 leg mast guy cables at nine elevations on each leg Legs consist of 6” dia. solid rounds X-bracing

8/29/2010

15

85 86

87 88


Recommended