+ All Categories
Home > Documents > 2011-12 winter shutdown preparatory meeting A.Tauro 02-12-2011 2/12/11ALICE 2011-12 winter shutdown...

2011-12 winter shutdown preparatory meeting A.Tauro 02-12-2011 2/12/11ALICE 2011-12 winter shutdown...

Date post: 14-Dec-2015
Category:
Upload: edith-eaton
View: 216 times
Download: 0 times
Share this document with a friend
55
2011-12 winter shutdown preparatory meeting A.Tauro 02-12-2011 2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro 1
Transcript

ALICE 2011-12 winter shutdown schedule - A.Tauro

2011-12 winter shutdown preparatory meeting

A.Tauro02-12-2011

2/12/11 1

ALICE 2011-12 winter shutdown schedule - A.Tauro

  Dec   Jan Feb     Mar

Wk 49 50 51 52 1 2 3 4 5 6 7 8 9 10

Mo 5 12   19 26   2 9 16 23 30 6 13 20 27 5

Tu       

                      

We       

                      

Th       

                      

Fr       

                      

Sa     

                    

Su    Xmas

Day NY Day                    

2011-12 winter shutdown

2/12/11

ShieldingTRD EMC Shielding

CloseL3

OpenL3

V0.2

TRD infrastructure

EMCinfrastructure

Beam off: Dec 8th at 6:00 AMBeam on: Mar 7th at 18:00 PM

CERN closure: 22/12 to 4/1 included

2

Dec   Jan Feb Mar

Wk 49 50 51 52 1 2 3 4 5 6 7 8 9 10

Mo     5

After 17:00

  19 26  2 9 16 23 30 6

After 17:00

20     27     5

Tu                                            

We                                                    

ThAfter 17:00

                                             

Fr               AUG                                  

Sa                                     DSO            

Su           

Xmas Day

NY Day

                                   

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

UX25 access restrictions

Access restrictions:Removal/installation of shielding (restriction includes RB24 triplets)

• PX24 blocks: no access CR5 and UX25• PX24 beams (35t): no access CR1-5, Expo, and UX-25• All other blocks: no access to UX-25 (or 1-2 teams max, not on A-side)

TRD insertion: no access to MNF and L3AUG test (Arrêt Urgence General – General Emergency Stop) – no access UX25DSO test (Department Safety Officer) – no access UX25

No access SX2 during manipulation of blocks in SX2 (except ACR and WRs)

Close L3Open L3

Legend

No access (except transport)

Access possible

No access

After 17:00

To be scheduled (1 day in wk 51)

3

Dec   Jan Feb Mar

Wk 49 50 51 52 1 2 3 4 5 6 7 8 9 10

Mo     5

After 17:00

  19 26   2 9 16 23 30 No ventilation

After 17:00

20     27     5

Tu                                          

We                                                    

ThAfter 17:00

                                             

Fr No ventilation

        AUG                                  

Sa                               DSO            

Su             Xmas Day NY Day                                    

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

Wks 49-50 and 7: access in normal hours (e.g. TPC) to be coordinated with TC

Wks 1-2: no access inside L3 during TRD SMs insertionWhen moving from low-beta to insertion platform: no access to MNFWhen inserting the module: no access L3 and MNF

Watcher needed in wks 49-50 and from wk 6 onwards

L3 and MNF access restrictions

Close L3Open L3

4

EN-HE

• 8th Dec (9:30): reinstall crane (PR-774) electronics• 8th Dec (AM): load test cavern cranes (20t)• Wk 4: test UJ22 jig + annual maintenance P2 cranes

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

EN-HE-LM

• 14th Dec: maintenance lift CR1-4– Lift stopped whole day (7:00 – 16:00)

• Cavern lift has to be stopped as well for one day. Date tbc

5

TE-VSC

• 8th and 9th Dec: close MNF valve and venting central beampipe• Feb 1st – 23rd: pump down central beampipe

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

6

GS-ASE

• Week 52: evacuation test• Feb. 21st: maintenance PAD/MAD

– Guard will be provided by GS in order not to interfere with cavern access

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

7

EN-CV-OP – Dec

• 7th Dec at 18:00: adjustment chilled water flow in the cavern– Will affect all cooling plants– Keep as many detectors on till the 8th (DCS shutdown), in order to check

that regulation works (EN-CV-DC side)– Keep L3 and Dipole on till the 8th (DCS shutdown)

• Week 50: rinsing of mixed water in UX25 cavern (Philippe)– Refilling in parallel will not affect ALICE cooling

• End wk 50 (16th Dec): test of Dipole flooding alarm– Need access to Dipole (Philippe)

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

8

EN-CV-OP – Jan/Feb

• Thu 5th and Fri 6th Jan: maintenance PMD-MTG-MTK ventilation units• Fri 6th Jan: stop chilled water (SU2)

– Therefore stop mixed water (cavern, CRs)– Switch tap water into CRs

• Week 2:– Cleaning cooling towers (Mon to Thu)– Maintenance L3 injection and UX25 extraction/injection units. Test of alarms– Modification of chilled water pipe for L3 jacket (Mon)– Maintenance mixed water pumps PX24 (Mon-Wed) and UW25 (Wed-Thu)– Preparation services new ITS dehumidifier– Consolidation of automatic switchover to tap water into CRs

• Week 3:– Restart chilled & mixed water (around Wed, tbc)– Maintenance L3 extraction unit. Test of alarms– Maintenance ITS (old) ventilator in CR5– Maintenance ventilation unit SG2 (Mon-Tue)

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

9

EN-CV-OP – pending

• Repair leak FB pipe: 1 day (compensatory measures tbd)• Removal unused FB pipe (I-side). 1 day (need nacelle)

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

10

EN-EL 1/2

• 13/12: Test general secours: stop general services for 10’– Will affect all general services, also at P2. The UPSes for DAQ and DCS/HLT will bridge the

power cut (assuming they manage to repair the DCS/HLT one on 8.12...). Also rack power (CRs and UX) will not be affected.

– However all 'wall outlets', WR of the ACR, offices, meeting room, SXL2, coffee machine will be affected... Also the non ups part of the cooling plants as well as the gas system will be affected…

• 17/12: Test auto-transfert:– 1.5 days to configure + 1 day test– No impact on experiments

• Thu 12th Jan: maintenance power transformers:– Will cut EXD1/2X for 3h cut power to CRs (normal network)– Will cut ITS ventilator and HMPID rack in CR5

• Test AUG P2: Fri Jan 13th – No access UX25– Major electrical perturbation affecting P2 for whole day

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

11

EN-EL 2/2

• Consolidation 48V network (after incident 11th Jan 2011). Date tbc– 1 day no access to UX25

• Maintenance power transformer EMT306/2X. Date tbc (Feb. ?)– Scheduled the same day as 48V– Will stop UX25 air extraction and injection (4h) – impact on access to be seen (Fernando)

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

12

EN-CV-BE

• New ITS dehumidifier unit in SX2

– Ducts installation : ongoing (SPIE)– Air handling unit delivery : week 51– Electrical and control cubicle delivery : week 2– Cabling and mechanical connection : from week 2 to week 5– Start-up and commissioning : from week 6 to week 7

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

13

EN-CV-DC

• RP sampling: Dec 8th

• TOF-PHOS-EMC-SPD. Installation PHOS circulator + replacement flowmeter + periodic maintenance: plant stopped from 9th to 17th Jan

• SPD. Periodic maintenance + put entire plant on UPS: plant stopped 1 day on Jan 6th

• TRD. Periodic maintenance + replacement chilled water valve + preventive replacement pump + cleaning vacuum pump: plant stopped 2 days on Jan 5th and 6th

• TPC. Periodic maintenance + preventive replacement pump + include heaters in supervision + cleaning vacuum pump: pant stopped from 18th to 20th Jan

• HMPID. Periodic maintenance + preventive replacement pump: plant stopped 2 days on Jan 23rd and 24th

• TPC RR. Periodic maintenance + install new filters: plant stopped from Jan 25th to Feb 2nd

• SDD-SSD. Periodic maintenance + replacement pump: plant stopped from 3rd to 9th Feb

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

14

ALICE 2011-12 winter shutdown schedule - A.Tauro

BE-ABP-SU (survey)

• With L3 doors open, requiring two full days before Xmas (preferably on Sat-Sun w50):– Zero measurement (SF, TPC feet, MNF valve, MNF)– Low Beta network update– C-side photogrammetry (EMCal)

• After each TRD insertion, requiring 2h inside MNF :– MNF valve and MNF, requiring 2h inside MNF

• At the end of TRD and EMCal, requiring three full days with both doors open (wk 5):– TRD modules, CAL frame photogrammetry, MNF valve, MNF, SF

deformation, TPC feet• Muon ST2-3-4 and TRG surveys in February

2/12/11 15

DAQ

• DAQ shutdown 21st Dec mid-day• DAQ start after cooling and power interventions, end wk 3

– Arrangements for individual LDCs can be organized (send a mail to [email protected])

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

16

DCS

Week 49• Dec. 8 morning: shutdown all DCS for UPS repair; restart a.s.a.p. (afternoon)

– Profit from DCS stop to make backup !• Start (hardware) installation of new DCS cluster

Week 50• Dec. 12–14: Operating system and PVSS upgrade

– Reboots required, coordinated with detectors• Dec. 15: New framework available for detectors

– Detectors to validate functionality with new software

Week 51-52-01 • Preparation of new DCS cluster• DCS available during CERN End-of-Year closure

– with usual access limitations and best effort support

Week 02-03-04 • New DCS cluster available for detectors• Expect all detectors to run on new cluster by week 52/12/11 ALICE 2011-12 winter shutdown

schedule - A.Tauro17

TPC

• Take out capacitors on all A/C ROC

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

18

TPC heat screen

• Check the loops for the thermal screen in week 6 (there was a leak)

• We will need:– access to the TRD cooling plant– access to C side and A side of TPC– access to the miniframe and PP0

• Since the pipes are on the outside of the miniframe we would probably need a nacelle.

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

19

Removal of FMD2 box

ALICE 2011-12 winter shutdown schedule - A.Tauro

Present situation Situation without the box. The blue cable tray should stay in

place

Cable ends

2/12/11 20

Removal of FMD2 box

• Who: Borge

• What:

The cables from the detector are disconnected and secured. The box and the patch panels are unscrewed and dismounted. Then the patch-panel and the cables should be moved aside and secured. Uncertain where to put the cable bundle and patch panels – very stiff bundle.

• When: 8th December morning

ALICE 2011-12 winter shutdown schedule - A.Tauro

2/12/11 21

Removal of SSD-SPD boxes

ALICE 2011-12 winter shutdown schedule - A.Tauro

Present situation. The plate restricts the TPC access

SSD box

SPD box

Situation without the SSD box

Situation without the SSD and SPD boxes. Now the plate can be

easily removed

Plate

2/12/11 22

Removal of SSD-SPD boxes

• Who:– SSD: Ton– SPD: Michel Morel

• What:– The SPD box is removed from the MNF. The only risk is to damage the

fibers.– The SSD box is also removed from the MNF, and the cable trays from

PP1 should be opened. The box cannot be taken away, therefore the cable from the detector + box will be displaced and attached to the beampipe table for some days

– The plate is easily removable (4 screws), and this will be done by Yannick or Pieter

ALICE 2011-12 winter shutdown schedule - A.Tauro

2/12/11 23

Removal of V0-FMD1

• Who: Yannick, Pieter, Werner and Borge

• What: disconnection and displacement of V0-FMD1. The detector will be parked inside the MNF for some days. The removal is a complex but known operation. The main risks for the equipment are related to the beampipe and the naked silicon sensors of FMD1. Both will need temporary protection once the detector is moved out,

ALICE 2011-12 winter shutdown schedule - A.Tauro

2/12/11 24

Schedule

• Week 49:– Thu 8/12: displace FMD2 box. The box can be reinstalled anytime (at latest in week 5)– TPC A-14/15 (4 days anytime)

• Week 3: move PMD to parking position (see next slide)• Week 4:

– Mon 23/1 AM: disconnect and displace SPD box– Mon 23/1 PM: disconnect and displace SSD box– Tue-Fri: TPC A-11/12 (4 days)– Sat: put back and test SSD box

• Week 5:– Mon 30/1: put back and test SPD box– Tue: move V0-FMD1 to parking position (PMD already in parking position)– Wed-Fri: TPC A-13 (2 1/2 days)– Fri-Sat: move back and test V0-FMD1

• Week 6:– Mon 6/2: survey of V0-FMD1

ALICE 2011-12 winter shutdown schedule - A.Tauro

2/12/11 25

PMD

• Week 3 or 4: PMD moves to Parking Position• Week 4 - 6: PMD Maintenance

– Replacing some of the modules which are having problem– Replacing some of the FEE Chains– Need cooling for the DAQ (Crocus) so that we can check the health of

the modules and FEE chains.• Week 7 (after 17:00) and 8: Access to Crocus Crate for DAQ• Week 9 -10: PMD Moves back to Final Position

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

26

TPC laser

• Annual laser maintenance, 1-2 days. Needs normal power and cooling

• Open mirror box below TPC sector A13 (bottom below TPC endplate) and possibly replace camera or mirror. 1-2 days. I want to do this because a weak picture from this mirror/camera makes C-side alignment difficult. Best done with L3 doors open. I believe access between the TOF and TPC should be OK. I need to be able to run the laser, so we need to mount the long laser pipe temporarily after opening of L3 doors.

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

27

TRD

• 3 supermodules installation, cabling, commissioning (L3 access, A & C sides etc)– Arrival at CERN of Bernd & Co on 2nd Jan. around 12:00 AM– Insertion sequence: 6-2-3– Possible to have transport on Sun.8th Jan?

• C19 power installation -> we will ask DCS• C16-19 Netgear switch rearrangement• I08/O08 Netgear switch rearrangement• DAQ upgrade (discussion on going between Joerg and DAQ group)• Pretrigger backup PSU installation and LV cable rearrangements (I/O rack and C-side

in L3)• BKF LV protection panel replacement (C-side in L3)• Colling valves replacement for 10 sectors, C side (if necessary, ask Ana to judge) (C-

side in L3)• Moving back pressure sensors from TPC TS to TRD (C-side in L3)• GTU optical fiber installation (Stefan) (C16,17,18 racks)• CR4 HV rearrangement for new super-modules

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

28

EMC

• New rotator nose: installation and check end Dec/beginning Jan– Depending on delivery of nose to P2

• Arrival at CERN of Manoel & Co on 22nd Jan.

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

29

PHOS

• As from Dec 8th (PM):– Fix condensation problem on pipes and on top of detector– New redundant power supply for crystal cooling unit– Flowmeter crystal cooling unit (tbc)– 2 new T sensors inside L3– Replace RCU_0 in module_3

• Connect crystal plant and LVPS to FB water during cooling stoppage:– E.g. on Jan 5th

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

30

MTK

• Repair bus bars on slats: ST4, ST5 and ST3 (only limited to the ones accessible)– Week 50 (after 17:00);– Week 2 to week 9

• Change one quadrant in ST2 (3 Right Bottom);– Week 4 (Monday and/or Tuesday)

• Connection check in ST1 (without opening);– January: no day fixed yet…

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

31

MTG

• Maintenance Front-end Electronics, mostly spare installation:– 19th to 21st Dec. Nacelle needed and green fences must be dismantled

• Check on RPC (MTR21-OUT) for gas tightness, eventual dismounting and eventual changing– Week 3. Nacelle needed

• Survey of 2 half-planes (MT12-IN and MT12-OUT) including measurements with theodolite and photogrammetry, survey of the other 6 half-planes with only theodolite measurements– Week 5. Nacelle needed

• SAA3 Shielding - MTR in closed position– Week 6 (tbc) - can some concurrent activity in the MTR be carried out

(i.e. regional electronics)?• General global check

– One week (tbc)

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

32

ZDC

• Move detectors by 1.36m towards IP to solve the problem of collimator shadow

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

33

Status of gas systemsduring Christmas period

• MTR Ar backup• MCH CO2 backup 

• PMD Ar  backup • TOF C2H2F4 backup ? 

• TRD On. Will need about 40 m3 of CO2 for flushing 3 new TRD SMs

• TPC On • PHO N2 flushing

• HMP Ar backup inlet flushing

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

8/12: stop flammable gases i-C4H10, CH4 and H2

34

ALICE 2011-12 winter shutdown schedule - A.Tauro

Other activities

• TRD scaffolding: 22nd Dec.• SAA3 extension (February)• Release all TOF crates supports and Decoupling TPC-Space-Frame

– Yannick, week 51• Disconnect/reconnect SPD pipes• Pull cable DSS-SPD cooling plant• Modification BBF (EMCal access)• Install C-side ladder + trap• Picture ALICE (A.Saba)

– Week 5 (Wed-Fri. Tbc)• Replacement CR3 racks and removal air conditioning CR2-3-4

– From week 4• Installation accelerometers• Connect N2 line to SG2 dewar (Iniziative)• Test Dipole bus bars (2h, Pascal) with IR camera. Tbs in February

– Need to remove plexi protection2/12/11 35

DAY-BY-DAY SCHEDULEDECEMBER 2011

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

36

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

Activities in UX25 - Week 49 – 8/12 Thursday

Access after 17:00

ITECO

HAULOTTE

VA

C

RP samples

PX24 shielding:

blocks FM

D-2

box

Stop flammable gases i-C4H10, CH4 and H2

Borge (AM): removal FMD2

box

Reinstallation crane electronics (9:30) + load test cavern cranes (20t)

7/12 PM: adjustment chilled water flow in the cavern

Shutdown all DCS for UPS repair (AM)

PHOS

After 17:00

37

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

Activities in UX25 - Week 49 – 9/12 Friday

Access after 17:00

PX24 shielding:

beams (35t)

VA

C

TP

C C

apac

itors

TP

C C

apac

itors

PHOS

After 17:00

38

SP

D

Disconnect pipes (after 17:00)

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

Activities in UX25 - Week 49 – 10/12 Saturday

Access after 17:00

MNF shielding

Stabilizers

No access CR1-5 during lifting up of 5 big beams

Stabilizers

PHOS

After 17:00

39

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

Activities in UX25 - Week 49 – 11/12 Sunday

40

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

Activities in UX25 - Week 50– 12/12 Monday

Access after 17:00

LV156

MNF shielding TP

C C

apac

itors

TP

C C

apac

itors

Rinsing of mixed water in UX25 cavern (Philippe) (whole week)

Repair bus bars on slats: ST4, ST5 and ST3

MT

K

ITECO

41

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

Activities in UX25 - Week 50– 13/12 Tuesday

LV156

MNF shielding TP

C C

apac

itors

TP

C C

apac

itors

Access after 17:00

Test general secours: stop general services for 10’

MT

K

42

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

Activities in UX25 - Week 50– 14/12 Wednesday

LV156

MNF shielding

L3 ventilation

Access after 17:00

Maintenance lift CR1-4Lift stopped whole day (7:00 – 16:00)

MT

K

43

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

Activities in UX25 - Week 50– 15/12 Thursday

MNF shielding (green bridges)

Open I-side door

LV156

TP

C C

apac

itors

TP

C C

apac

itors

Access after 17:00

MT

K

44

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

Activities in UX25 - Week 50– 16/12 Friday

Open O-side door

LV156

TP

C C

apac

itors

TP

C C

apac

itors

Test of Dipole flooding alarm

MT

K

Gre

en f

ence

s

45

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

Activities in UX25 - Week 50– 17/12 Saturday

TP

C C

apac

itors

TP

C C

apac

itors

Test auto-transfert

Sur

vey

46

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

Activities in UX25 - Week 50– 18/12 Sunday

Sur

vey

47

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

Activities in UX25 - Week 51– 19/12 Monday

TRD infra.

TRD infra.

Access after 17:00 (tbc)

TP

C C

apac

itors

MT

G

Maintenance Front-end Electronics

TP

C C

apac

itors

HAULOTTE

Release all TOF crates

supports (Yannick-Samuel)

48

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

Activities in UX25 - Week 51– 20/12 Tuesday

TP

C C

apac

itors

MT

G

TP

C C

apac

itors Release all

TOF crates supports (Yannick-Samuel)

49

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

Activities in UX25 - Week 51– 21/12 Wednesday

DAQ shutdown (PM)

TP

C C

apac

itors

MT

G

TP

C C

apac

itors Decoupling

TPC-Space-Frame

(Yannick-Samuel)

50

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

Activities in UX25 - Week 51– 22/12 Thursday

TRDscaffolding

Decoupling TPC-

Space-Frame

(Yannick-Samuel)

CERN official holiday

51

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

Activities in UX25 - Week 51– 23/12 Friday

CERN official holiday

52

Transport TRD6 into cavern

Visits - Dec

• VIP: Stjepan Matin from 24Hours newspaper– 9th Dec. (possibly 11:45 – 12:30). Resp.: S.Tesauri

• 7 people– 17th Dec. (1t 17:00). Resp.: C.Bortolin

• 50 students from the University of Bologna Chemistry Department– 17th Dec. Resp.: R.Nania

• VIP: Kim Steele, New York Times Review– 21st Dec. Resp.: D.Hatzifotiadou

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

53

Visits – Jan-Feb

• TI operators– 11th Jan. (14:00). Resp.: A.Augustinus

• VIP: President of the French Centre national de la recherche scientifique (CNRS)– 16th Jan. Resp.: Y.Schutz

• Group of Italian students (42 students + 4 teachers)– 19th Jan (tbc). Resp.: C.Bortolin

• Group of 40 students + 4 teachers from Cagliari– 26th Jan. Resp.: C.Cicalo

• VIP: Members of the Comitato per il Progetto Culturale (IT)– 26th Jan. Resp.: L.Pedroso

• German School Geneva, 9th grade, i.e. 14-15 years old, 15 pupils plus teacher– 30th Jan. Resp.: R.Renfordt

• 50 students from university of Tübingen– 2nd Feb. Resp.: H-R.Schmidt

• Vice-Chancellor of Birmingham University and 7 senior figures from industry– 15th Feb. (12:00 to 13:00). Resp.: D.Evans

• Group of 38 students + 4 teachers from Cagliari– 21st Feb. Resp.: C.Cicalo

2/12/11 ALICE 2011-12 winter shutdown schedule - A.Tauro

54

ALICE 2011-12 winter shutdown schedule - A.Tauro

AOB

• As from now ADI replaced by IMPACT– Please do not submit anymore ADI requests– ADI no longer used– IMPACT is the new CERN wide tool– See Fernando’s tutorial

2/12/11 55


Recommended