7/15/2012 1 Civil Engineering Construction Chapter 3 Formwork System Dr Mohamad Syazli Fathi Department of Civil Engineering UTM Razak School of Engineering &Advanced Technology UTM International Campus July 15, 2012 Choosing the RIGHT Formwork System! 7/15/2012 28
Transcript
Page 1: 2011 DDA2132 - Chp 4 - Formwork (Lecture file)...Civil Engineering Construction Chapter 3 Formwork System Dr Mohamad Syazli Fathi Department of Civil Engineering UTM Razak School of

7/15/2012

1

Civil Engineering ConstructionChapter 3

Formwork System

Dr Mohamad Syazli Fathi

Department of Civil EngineeringUTM Razak School of Engineering &Advanced Technology

UTM International Campus

July 15, 2012

Choosing the RIGHTgFormwork System!

7/15/2012 28

Page 2: 2011 DDA2132 - Chp 4 - Formwork (Lecture file)...Civil Engineering Construction Chapter 3 Formwork System Dr Mohamad Syazli Fathi Department of Civil Engineering UTM Razak School of

7/15/2012

2

Why worry about the Choice of

Forming System?

7/15/2012 29Chek Lap Kok Airport (Hong Kong)

Concrete Frame Costs

Formwork: 50 - 70%

Concrete: 15Concrete: 15 25%25%

7/15/2012 30Petronas Tower

Rebar: 15 Rebar: 15 -- 25%25%

Concrete: 15 Concrete: 15 -- 25%25%

Page 3: 2011 DDA2132 - Chp 4 - Formwork (Lecture file)...Civil Engineering Construction Chapter 3 Formwork System Dr Mohamad Syazli Fathi Department of Civil Engineering UTM Razak School of

7/15/2012

3

Formwork Cost

Other: 10Other: 10 -- 15%15%

Labor: 50 - 70%

Material: 15 Material: 15 -- 20%20%Other: 10 Other: 10 15%15%

7/15/2012 31

What Choices Do I Have?

Let’s focus on:

7/15/2012 32

• Walls• Slabs• Columns

Page 4: 2011 DDA2132 - Chp 4 - Formwork (Lecture file)...Civil Engineering Construction Chapter 3 Formwork System Dr Mohamad Syazli Fathi Department of Civil Engineering UTM Razak School of

7/15/2012

4

Wall Forming

WallsWalls

7/15/2012 33

WallsWalls–– Loose FramingLoose Framing–– Prefabricated PanelsPrefabricated Panels–– Crane Set GangsCrane Set Gangs

Wall Systems (Loose Framing)

7/15/2012 34

Page 5: 2011 DDA2132 - Chp 4 - Formwork (Lecture file)...Civil Engineering Construction Chapter 3 Formwork System Dr Mohamad Syazli Fathi Department of Civil Engineering UTM Razak School of

7/15/2012

5

Wall Systems (Prefabricated Panels)

7/15/2012 35

Prefab Steel Panel Prefab Alum. PanelPrefab Alum. Panel

Prefabricated Panels

• are durable for many reusesare durable for many reuses• simplify and reduce the labor required• studs and sheathing are preassembled in units

small enough to be handled• panels are set into position and tied together• wales, ties, and braces are then attached

7/15/2012 36

wales, ties, and braces are then attached• made of wood, metal, plywood with metal

bracing, or glass fiber and plastic over wood

Page 6: 2011 DDA2132 - Chp 4 - Formwork (Lecture file)...Civil Engineering Construction Chapter 3 Formwork System Dr Mohamad Syazli Fathi Department of Civil Engineering UTM Razak School of

7/15/2012

6

Prefabricated Panels

7/15/2012 37

Aluminum Panel

Wall Systems (Ganged Panel Forms)

7/15/2012 38

Page 7: 2011 DDA2132 - Chp 4 - Formwork (Lecture file)...Civil Engineering Construction Chapter 3 Formwork System Dr Mohamad Syazli Fathi Department of Civil Engineering UTM Razak School of

7/15/2012

7

Ganged Panel Forms

• ranging up to 30x50 ft• ranging up to 30x50 ft• large panels can be assembled flat on the

ground where it is easier to work• stripping is easier (stripped as a unit)• extra bracing is required to withstand the

h dli t

7/15/2012 39

handling stresses• are frequently used as “climbing” forms in

high wall construction• small panels can be ganged together to form

larger units

7/15/2012 40Aluminum Beam Gang Systems

Page 8: 2011 DDA2132 - Chp 4 - Formwork (Lecture file)...Civil Engineering Construction Chapter 3 Formwork System Dr Mohamad Syazli Fathi Department of Civil Engineering UTM Razak School of

7/15/2012

8

Wall Systems

7/15/2012 41Steel Panel Gang Systems

7/15/2012 42Steel Crane Set Gangs

Page 9: 2011 DDA2132 - Chp 4 - Formwork (Lecture file)...Civil Engineering Construction Chapter 3 Formwork System Dr Mohamad Syazli Fathi Department of Civil Engineering UTM Razak School of

7/15/2012

9

7/15/2012 43Shearwall Roll Back System

Shear Wall Roll Back System

7/15/2012 44

Page 10: 2011 DDA2132 - Chp 4 - Formwork (Lecture file)...Civil Engineering Construction Chapter 3 Formwork System Dr Mohamad Syazli Fathi Department of Civil Engineering UTM Razak School of

7/15/2012

10

Slipform Construction• vertical slipforms are moved upward by jacks• can be used for structures such as silos and forcan be used for structures such as silos, and for

high rise elevator and stairway cores• working decks and finisher’s scaffolds are

attached to and carried up with the forms• has shorter construction time

i t f t t t ll th 40 ft

7/15/2012 45

• appropriate for structures taller than 40 ft• not efficient where there are many projections to

the direction of slide

7/15/2012 46

Page 11: 2011 DDA2132 - Chp 4 - Formwork (Lecture file)...Civil Engineering Construction Chapter 3 Formwork System Dr Mohamad Syazli Fathi Department of Civil Engineering UTM Razak School of

7/15/2012

11

7/15/2012 47

Vertical SlipformsVertical Slipforms

7/15/2012 48

Page 12: 2011 DDA2132 - Chp 4 - Formwork (Lecture file)...Civil Engineering Construction Chapter 3 Formwork System Dr Mohamad Syazli Fathi Department of Civil Engineering UTM Razak School of

7/15/2012

12

One-sided Wall Form

7/15/2012 49

7/15/2012 50Slab Shoring• Loose Wood Framing• Steel or Aluminum Shoring• Flying Forms

Page 13: 2011 DDA2132 - Chp 4 - Formwork (Lecture file)...Civil Engineering Construction Chapter 3 Formwork System Dr Mohamad Syazli Fathi Department of Civil Engineering UTM Razak School of

7/15/2012

13

Hand-set Wood Shoring

7/15/2012 51

Steel shoring with aluminum beams

7/15/2012 52

Page 14: 2011 DDA2132 - Chp 4 - Formwork (Lecture file)...Civil Engineering Construction Chapter 3 Formwork System Dr Mohamad Syazli Fathi Department of Civil Engineering UTM Razak School of

7/15/2012

14

Aluminum shoring with aluminum beams

7/15/2012 53

Flying Forms (truss-supported)

7/15/2012 54

Page 15: 2011 DDA2132 - Chp 4 - Formwork (Lecture file)...Civil Engineering Construction Chapter 3 Formwork System Dr Mohamad Syazli Fathi Department of Civil Engineering UTM Razak School of

7/15/2012

15

Flying Form (column-mounted)

7/15/2012 55

Flying Form (column-mounted)

7/15/2012 56

Page 16: 2011 DDA2132 - Chp 4 - Formwork (Lecture file)...Civil Engineering Construction Chapter 3 Formwork System Dr Mohamad Syazli Fathi Department of Civil Engineering UTM Razak School of

7/15/2012

16

Tunnel Forms

7/15/2012 57

Forms wall and slab together

Garage Beam Forms

7/15/2012 58

Panelized system for garage beams and slabs

Page 17: 2011 DDA2132 - Chp 4 - Formwork (Lecture file)...Civil Engineering Construction Chapter 3 Formwork System Dr Mohamad Syazli Fathi Department of Civil Engineering UTM Razak School of

7/15/2012

17

Column Forming

7/15/2012 59

• Columns– Loose Framing– Hand-set Panels– Crane Set Gangs

Column Forms

7/15/2012 60

Hand-set Steel Panel HandHand--set Aluminum set Aluminum PanelPanel

Page 18: 2011 DDA2132 - Chp 4 - Formwork (Lecture file)...Civil Engineering Construction Chapter 3 Formwork System Dr Mohamad Syazli Fathi Department of Civil Engineering UTM Razak School of

7/15/2012

18

Column Forms

7/15/2012 61

Round FiberglassRound FiberglassColumn Forms Column Forms

Column Forms

7/15/2012 62Steel Column Forms Steel Column Forms

Page 19: 2011 DDA2132 - Chp 4 - Formwork (Lecture file)...Civil Engineering Construction Chapter 3 Formwork System Dr Mohamad Syazli Fathi Department of Civil Engineering UTM Razak School of

7/15/2012

19

Column Forms

7/15/2012 63

Aluma Beam Column Forms Aluma Beam Column Forms

Custom Forms

7/15/2012 64

Page 20: 2011 DDA2132 - Chp 4 - Formwork (Lecture file)...Civil Engineering Construction Chapter 3 Formwork System Dr Mohamad Syazli Fathi Department of Civil Engineering UTM Razak School of

7/15/2012

20

Custom Forms

7/15/2012 65

Choices

7/15/2012 66

Nothing else withstanding, the choice is always….

GANG PANELS!

Page 21: 2011 DDA2132 - Chp 4 - Formwork (Lecture file)...Civil Engineering Construction Chapter 3 Formwork System Dr Mohamad Syazli Fathi Department of Civil Engineering UTM Razak School of

7/15/2012

21

Factors in the Choice

• What you own• Availability• Initial price• Total cost

7/15/2012 67

• Total cost

Factors in the Choice

• Experience of workers• Experience of workers• What will produce the desired results

with the least amount of cost?

7/15/2012 68

Page 22: 2011 DDA2132 - Chp 4 - Formwork (Lecture file)...Civil Engineering Construction Chapter 3 Formwork System Dr Mohamad Syazli Fathi Department of Civil Engineering UTM Razak School of

7/15/2012

22

Factors in the Choice• Number of uses• Desired finish• Site conditions

7/15/2012 69

Factors in the Choice• Crane• Schedule• Building design

7/15/2012 70

Page 23: 2011 DDA2132 - Chp 4 - Formwork (Lecture file)...Civil Engineering Construction Chapter 3 Formwork System Dr Mohamad Syazli Fathi Department of Civil Engineering UTM Razak School of

7/15/2012

23

Factors in the ChoiceFactors in the Choice

The Supplier:The Supplier:History with similar projectsHistory with similar projectsEngineering expertiseEngineering expertiseSupport servicesSupport servicesKnowledge of support personnelKnowledge of support personnel

pppp

7/15/2012 71

g pp pg pp pLocationLocation

Buy vs. Rent

• Duration of project• Future usage• Cash flow• Return on investment

7/15/2012 72

Steel radius wall forms

Page 24: 2011 DDA2132 - Chp 4 - Formwork (Lecture file)...Civil Engineering Construction Chapter 3 Formwork System Dr Mohamad Syazli Fathi Department of Civil Engineering UTM Razak School of

7/15/2012

24

TheThe

7/15/2012 73

TheThe

EndEnd