  • 7/29/2019 201205 Presentation

    1/21

    A Case Study: Updating a Refinery Boiler

    Controls utilizing ISA 84 Standard for

    Safety Instrumented Systems

    Permission granted for ISA Houston Section Website

  • 7/29/2019 201205 Presentation

    2/21

    Presenters

    Alan Sharkey Audubon

    Chuck Laughter Audubon

    Matt Hufford Wilson Mohr

    Steve Papp - Wilson Mohr

    Permission granted for ISA Houston Section Website

  • 7/29/2019 201205 Presentation

    3/21

    Agenda

    Functional Safety Life Cycle Overview

    Case Study of Boiler in Refinery

    HAZOP

    LOPA PFD/SIL Determination

    SRS Development

    SIS Implementation Phase

    Operation & Maintenance Phase

    Q&A

    Permission granted for ISA Houston Section Website

  • 7/29/2019 201205 Presentation

    4/21

    Process Safety Management

    ISA 84

    IEC 61508/11

    NFPA

    API

    Permission granted for ISA Houston Section Website

  • 7/29/2019 201205 Presentation

    5/21

    Safety Life Cycle Flow-Chart

    Permission granted for ISA Houston Section Website

  • 7/29/2019 201205 Presentation

    6/21

    Hazard ID and Risk Assessment

    Permission granted for ISA Houston Section Website

  • 7/29/2019 201205 Presentation

    7/21

    HAZID/HAZOP Objectives

    Identify Hazards and Hazardous events of the process and

    associated equipment

    Task Required For each hazard identified , determine the consequence /severity

    level, the deviation, the initiating cause(s), and the safeguards(s)

    Note: Safe design should be developed as far as reasonably

    practical before reliance is placed on the SIS to reduce risk

    Permission granted for ISA Houston Section Website

  • 7/29/2019 201205 Presentation

    8/21

    LOPA

    Objectives Identify required mechanical, operational & safety instrumented

    functions (SIF) protection layers for each consequence carried intoLOPA

    For each SIF determine the associated SIL & and risk reduction

    target

    Tasks required

    Review hazard identification, for each hazard assign risk reductioncredits

    Assign target PFD (SIL x) to each SIF

    Note: Client will most likely have own risk graph and acceptablelevels of risk

    Permission granted for ISA Houston Section Website

  • 7/29/2019 201205 Presentation

    9/21

    SRSDefinition of SRS: Function design requirements of the SIS

    Minimum Requirements

    SIS System architecture (sensor, logic solver & end control elements

    System hardware standards

    Spare capacity, loading & expansion

    Specify testing interval(s)

    I/O requirements

    I/O signal types and field interfaces

    System communications

    Equipment and field termination/marshalling cabinet design

    requirements Operator MOS Override requirements (HSW/KSW/Status Panel)

    Optional Items

    Preliminary SIL verification calculations

    Permission granted for ISA Houston Section Website

  • 7/29/2019 201205 Presentation

    10/21

    Det ai l Designing of SIS Objectives To design, procure and test the SIS equipment to meet the SRS

    Detailed specification of hardware; data sheets, etc

    Provide SIS detailed design drawings; loop diagrams, etc.

    Application software functional logic design and development. Construct SIS following approved procedures designed to reduce

    systematic faults.

    Verify compliance to SRS; confirm testing intervals are satisfied.

    Provide procedures to operate and maintain the SIS. To validate, through inspection and testing, that the designed,

    built & configured SIS logic solver, application software (SIFs) &

    associated hardware meets in all respects the requirements as

    stated in the SRS (FAT).

    Permission granted for ISA Houston Section Website

  • 7/29/2019 201205 Presentation

    11/21

    Ins ta l la t ion & Comm iss ion ing Objectives Install and commission the SIS according to design

    documentation so that it is ready for final system validation.

    Commission and check calibration of the SIS components

    To integrate and test the SIS (SAT)

    To validate, through inspection and testing, that theinstalled & commissioned SIS & its associated SIFs meets

    in all respects the requirements as stated in the SRS.

    Permission granted for ISA Houston Section Website

  • 7/29/2019 201205 Presentation

    12/21

    Operat ion & Main tenanc e Objectives To ensure that the functional safety of the SIS is maintained

    during operation and maintenance

    SIS documentation is maintained

    To control maintenance and testing activities, so that the

    design intent of SIS is retained over the asset life

    Permission granted for ISA Houston Section Website

  • 7/29/2019 201205 Presentation

    13/21

    Management o f Change Objectives To control all SIS modifications, so that safety integrity of

    the SIS is maintained over the asset life.

    To ensure that any SIS changes are properly planned,designed reviewed, approved and tested prior to

    implementation.

    Permission granted for ISA Houston Section Website

  • 7/29/2019 201205 Presentation

    14/21

    Case Study of Refinery SRU

    HAZOP

    LOPA

    SRS

    SIS

    Operations & Maintenance

    Permission granted for ISA Houston Section Website

  • 7/29/2019 201205 Presentation

    15/21

    SIS Implementation

    -Customer Timing

    -Plant Control

    Infrastructure

    -CorporateSpecifications

    -S84 vs NFPA 85

    -CustomerAwareness

    -MaintenanceRestrictions

    Practical Considerations

    -Concurrent

    Development Cycle

    -Vendor

    Restrictions

    -Conflicting

    Requirements

    -Needs dont match

    capabilities

    Impact on Cycle

    QualificationsResulting

    Complications

    Permission granted for ISA Houston Section Website

  • 7/29/2019 201205 Presentation

    16/21

    SIS Implementation

    - Customer Timing:

    - 2 Year Turnaround Schedule

    - Confecting Requirements

    - Corporate Spec for S84

    - Plant Spec for NFPA 85

    - Concurrent design cycle required

    - Forced SIL Target

    - Commitment to Amend Mechanical design

    - Preselected Control Vendor

    Permission granted for ISA Houston Section Website

  • 7/29/2019 201205 Presentation

    17/21

    SIS Implementation

    - RedundantProcessors UtilizingIndependent Tasks

    - Shared Power &Comm Backbone

    - DedicatedRedundant Analog &Digital Inputs on SISI/O

    - SIS & BMS OperateTotally independently

    - SIS Processes SIF

    and Controls SafetyRelay Only

    - MFT Circuit is theInterlockingMechanism Betweenthe Two Systems

    Permission granted for ISA Houston Section Website

  • 7/29/2019 201205 Presentation

    18/21

    SIS Implementation

    DCS Controlled

    Combustion Circuit

    with BMS Dump

    Vale on IP

    Backup Nitrogen

    System on IA

    Single Block with

    Vent on Headers

    Low Fire Light off on

    Individual Burner Trains

    2of3 Voting on all

    NFPA Recommended

    SignalsDouble Block and

    Bleed on all

    Individual Trains

    Permission granted for ISA Houston Section Website

  • 7/29/2019 201205 Presentation

    19/21

    SIS Implementation

    Permission granted for ISA Houston Section Website

  • 7/29/2019 201205 Presentation

    20/21

    SIS Implementation

    Permission granted for ISA Houston Section Website

  • 7/29/2019 201205 Presentation

    21/21

    Quest ions?