+ All Categories
Home > Documents > 2015 03 Ak and Cn PoD · c2k-c 1k 0 1 c19k c 1 8 7 c16k-1 b2k-1 b2 1k-b0-b9k-b18 k-1 a 2k-a20k-1...

2015 03 Ak and Cn PoD · c2k-c 1k 0 1 c19k c 1 8 7 c16k-1 b2k-1 b2 1k-b0-b9k-b18 k-1 a 2k-a20k-1...

Date post: 05-Jul-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
7
PoD, Oct 2014 Page 1 EarthScope Transportable Array Plan of Development Project Summary From 2003 to 2013 the EarthScope Transportable Array (TA) installed over 1,700 seismometer stations across the continental United States and southern Canada in a dense semipermanent array at a 70 km (42 mile) grid spacing. The TA is one segment of EarthScope, an extensive earth science research project funded by the National Science Foundation. The TA is operated by the Incorporated Research Institutions for Seismology (IRIS), a nonprofit 503C founded in 1984 that is a consortium of over 100 US universities dedicated to the operation of science facilities for the acquisition, management, and distribution of seismological data. Figure 1: Proposed sites for the Transportable Array in Alaska, based on 2013 and 2014 reconnaissance efforts. Note that actual station locations are subject to permit approval.
Transcript
Page 1: 2015 03 Ak and Cn PoD · c2k-c 1k 0 1 c19k c 1 8 7 c16k-1 b2k-1 b2 1k-b0-b9k-b18 k-1 a 2k-a20k-1 i23k -4 l2 6k- 3 6g 2 7k- 3 g 5k g 24 k-g3k g2 1k- 3 9 4g 20-g 1 8k-2 g 16k-g5k 3

PoD,  Oct  2014   Page  1    

   EarthScope  Transportable  Array  Plan  of  Development  

   Project  Summary      From  2003  to  2013  the  EarthScope  Transportable  Array  (TA)  installed  over  1,700  seismometer  stations  across  the  continental  United  States  and  southern  Canada  in  a  dense  semi-­‐permanent  array  at  a  70  km  (42  mile)  grid  spacing.      The  TA  is  one  segment  of  EarthScope,  an  extensive  earth  science  research  project  funded  by  the  National  Science  Foundation.    The  TA  is  operated  by  the  Incorporated  Research  Institutions  for  Seismology  (IRIS),  a  nonprofit  503C  founded  in  1984  that  is  a  consortium  of  over  100  US  universities  dedicated  to  the  operation  of  science  facilities  for  the  acquisition,  management,  and  distribution  of  seismological  data.        

 Figure  1:  Proposed  sites  for  the  Transportable  Array  in  Alaska,  based  on  2013  and  2014  reconnaissance  efforts.    Note  that  actual  station  locations  are  subject  to  permit  approval.  

Page 2: 2015 03 Ak and Cn PoD · c2k-c 1k 0 1 c19k c 1 8 7 c16k-1 b2k-1 b2 1k-b0-b9k-b18 k-1 a 2k-a20k-1 i23k -4 l2 6k- 3 6g 2 7k- 3 g 5k g 24 k-g3k g2 1k- 3 9 4g 20-g 1 8k-2 g 16k-g5k 3

PoD,  Oct  2014   Page  2    

Following   the   completion   of   the   seismic   installations   in   the   lower   48   states,   the  EarthScope  Transportable  Array  project  is  beginning  work  in  Alaska  and  Western  Canada.    This  project  consists  of  a  large  deployment  (approximately  270)  of  ground  motion  sensors  (seismometers)   at   a   nominal   spacing   of   85   km   (51  miles)   over   the   next   4   years.       See  www.usarray.org/alaska  and  Figure  1.    Each  station  will  remain  in  place  for  up  to  5  years,  at   which   time   the   equipment   will   be   recovered   and   the   site   restored   to   its   original  condition.          Purpose  and  Need    One  of  the  main  objectives  of  the  project   is  to   improve  our  understanding  of  the  active  tectonics  and  geologic  history  of  the  North  American  continent.    The  Transportable  Array  will  create  images  of  the  deep  structure  of  the  earth,  from  depths  of  about  5  km  to  the  core  of  the  earth.    The  instruments  are  spread  too  far  apart  to  provide  detailed  imaging  commonly   used   for   exploration   for   oil   and   gas   (whose   drills   go   less   than   4   km   deep).    Further   science   objectives   and   rationale   for   the   deployment   of   this   large   array   are  explained  in  a  63-­‐page  report  found  at      http://www.iris.edu/hq/Alaska_Workshop_2011/report.phph    The  seismometers  record  earthquakes  that  occur   locally,  regionally,  and  throughout  the  world.     The   unique   value   of   data   produced   from   this   array   is   due   to   the   large   area  covered,   and   to   the   dense,   regular   spacing   of   hundreds   of   high-­‐quality   seismometers.  Data  from  these  stations  are  open  and  freely  available  and  are  forwarded  immediately  to  USGS  National  Earthquake  Information  Center  in  Golden  CO,  Alaska  Earthquake  Center  at  UAF,   the   Canadian   Hazard   Information   Service   in   Ottawa   (NRCan),   the   Alaska   Volcano  Observatory,   and   NOAA’s   Tsunami   Warning   Center   and   distributed   to   hundreds   of  researchers   worldwide.   The   data   help   scientists   gain   new   insights   into   earthquake  processes   and   source   characteristics,   expand   our   understanding   of   earthquakes   and  lower   crustal   processes,   and   improve   earthquake   and   tsunami   warning   systems   for  hazard  mitigation.    The   locations   proposed   in   Alaska   will   supplement   or   enhance   existing   seismic   stations  currently  operated  by   the  Alaska  Earthquake  Center   (AEC),  Alaska  Volcano  Observatory  (AVO),   Tsunami   Warning   Center   (TWC),   Canadian   Hazards   Information   Service   (CHIS),  Yukon  Geological  Survey  (YGS),  and  Pacific  Geoscience  Center  of   the  Geologic  Survey  of  Canada.   About   a   dozen   seismic   stations   will   be   co-­‐located   with   existing   GPS   stations  constructed   by   the   EarthScope   Plate   Boundary   Observatory   (PBO).   As   the   stations  become  operational,  some  of  the  partnering  networks  may  seek  to  retain  certain  stations  to  be  left  in  place  and  become  part  of  the  permanent  seismic  monitoring  networks.    It  is  difficult   to   predict   the   number   and   location   of   these   selections   and  we  will   work  with  agencies   to  adapt  permits  where  possible   to  accommodate  the  enhanced  observational  capability.    

Page 3: 2015 03 Ak and Cn PoD · c2k-c 1k 0 1 c19k c 1 8 7 c16k-1 b2k-1 b2 1k-b0-b9k-b18 k-1 a 2k-a20k-1 i23k -4 l2 6k- 3 6g 2 7k- 3 g 5k g 24 k-g3k g2 1k- 3 9 4g 20-g 1 8k-2 g 16k-g5k 3

PoD,  Oct  2014   Page  3    

   Description  of  Proposed  Work    The   general   design   and   construction   of   the   TA   stations   will   be   uniform   for   all   site  locations  across  the  state.    Slight  variations  may  be  required  for  individual  sites  based  on  local  and  environmental  conditions.      The  typical  Transportable  Array  station  will  occupy  a  footprint  not  to  exceed  20  x  20  feet  (6  x  6  meters),  with  a  low  physical  profile.  The  equipment  does  not  produce  any  noise  or  motion.   To   protect   the   sensor   and   reduce   interference   from   surface   noise,   the  seismometer  will  be  placed  in  a  PVC  or  steel  cased  hole  3  to  15  feet  (1  to  5  meters)  below  the  surface  of  the  ground.  The  holes  will  either  be  augured  or  downhole  hammered,  and  will   be   approximately   6   inches   (15   cm)   in   diameter.   Ground   conditions   at   the   site  will  dictate  the  hole  depth  and  creation  technique.      At  most  TA  stations,  the  electronics  and  power  system  will  be  housed  in  an  above  ground-­‐insulated  enclosure.    The  most  common  enclosure  is  a  grey  hut,  measuring  approximately  5’x5’x7’H  (1.5x1.5x2H  meters)  and  made  of  fiberglass  that  can  be  painted  to  blend  in  with  the   form,   line,   and   color   of   the   surrounding   landscape   (Figure   2   and   Figure   3).   Solar  panels   are  mounted   directly   to   the   hut.   The   alternate   station   configuration   consists   of  boxes/containers,  which  are  secured  to  a  frame,  and  anchored  to  the  ground;  this  frame  will  also  serve  as  the  mount  for  the  solar  panel.    In  either  case,  the  enclosure  will  house  a  power  system  comprising  rechargeable  lithium  ion   and   lead-­‐acid   AGM   batteries   charged   by   solar   panels.    The   solar   panels   will   be  mounted  on  the  outside  of  the  hut  or  on  a  vertical  bracket  attached  to  the  base  frame.  The  batteries  inside  the  enclosure  will  power  a  Quanterra  Q330  datalogger  connected  to  a   three-­‐component   broadband   seismometer   (STS-­‐4B,   STS-­‐5A,   T120PH,   or   CMG-­‐3T)  residing   in   the  augured  or  downhole  hammered  hole.    Ground  motion  data   is   recorded  continuously  at  40  samples  per  second.    Average  power  of  the  entire  system  is  about  7  watts.    A   standard  TA  atmospheric   sensor  package  containing  a  MEMS  barometer,   a  Hyperion  IFS-­‐4232   infrasound   sensor   (hyperiontg.com),   and   a   Setra   278   microbarograph  (setra.com)  will  be  included  in  each  station.    When  present,  weather  station  sensors  will  be  mounted  on  top  of  the  hut  or  on  the  enclosure  support  frame.    Additional  sensors  that  could   be   deployed   at   some   stations   as   part   of   collaborative   projects   include   a   strong-­‐motion   accelerometer,   and/or   soil   temperature   profiler.    Weather   and   pressure   data   is  recorded   at   1   sample   every   second,   with   infrasound   also   recorded   at   40   samples   per  second.    The  UTC  accuracy  of  time  labels,  which  is  required  for  seismology,  is  unusual  in  weather  monitoring.    

Page 4: 2015 03 Ak and Cn PoD · c2k-c 1k 0 1 c19k c 1 8 7 c16k-1 b2k-1 b2 1k-b0-b9k-b18 k-1 a 2k-a20k-1 i23k -4 l2 6k- 3 6g 2 7k- 3 g 5k g 24 k-g3k g2 1k- 3 9 4g 20-g 1 8k-2 g 16k-g5k 3

PoD,  Oct  2014   Page  4    

Power   and   data   cables   from   the   seismometer   to   the   enclosure   will   be   run   through  conduit   placed   in   trenches,   or   anchored   to   rock   surface,   leading   to   the   enclosure.   The  trenches  will  be  backfilled  after  all  cables  have  been  secured  and  tested.      

 Figure  2:  Illustration  of  a  TA  Seismic  Installation.  Dimensions  in  feet.  

Page 5: 2015 03 Ak and Cn PoD · c2k-c 1k 0 1 c19k c 1 8 7 c16k-1 b2k-1 b2 1k-b0-b9k-b18 k-1 a 2k-a20k-1 i23k -4 l2 6k- 3 6g 2 7k- 3 g 5k g 24 k-g3k g2 1k- 3 9 4g 20-g 1 8k-2 g 16k-g5k 3

PoD,  Oct  2014   Page  5    

       

 Figure  3  Photo  of  station  N25K  being  installed  near  Chitina,  Alaska,  in  the  fall  of  2014.  

 Data  from  the  stations  will  be  transmitted  to  the  Internet  via  cell  modem,  radio  links  or  through  a  satellite  link  and  received  at  the  Array  Network  Facility  at  UC  San  Diego  Super  Computing  Center   for  processing,  and  archived  at   the   IRIS  Data  Management  Center   in  Seattle,   Washington.     All   data   are   freely   available   to   the   public   and   to   scientific  researchers.        General  Construction/Installation  Procedure    A  lightweight  portable  drill  rig  with  the  ability  to  both  auger  and  downhole  hammer  the  boreholes  will  be  transported  via  fixed  wing  or  helicopter  to  sites  that  cannot  be  accessed  by  road.  A  team  of  two  to  three  field  engineers  will  construct  the  borehole  (~6  in/15cm  diameter  and  3-­‐15  feet/1-­‐5  meters  deep)  and  install  6  in  (15cm)  PVC  or  steel  casing.    The  PVC   or   steel   casing   will   be   secured   in   place   by   grout.   Care   will   be   taken   to   minimize  ground   disturbance   at   the   site.     Construction   and   installation   of   a   station   will   take  approximately  8-­‐10  hours.    Installation  of  the  electronics  may  proceed  immediately  but  is  often  performed  on  a  separate  day  within  a  week  of  construction  and  subject  to  weather  conditions.   Stations   will   typically   be   installed   between   mid-­‐May   and   mid-­‐October,   as  weather  permits.      EarthScope  is  seeking  participation  from  private  landowners,  state  and  federal  agencies,  First  Nations,   and  Native  Corporations   to   help   accomplish   this   unprecedented   research  and  public   education  project.     EarthScope   recognizes   their   responsibility   to   respect   the  property   and   privacy   of   landowners,   the   obligation   to   operate   all   stations   safely   and  securely,   while   assuming   full   liability   if   the   equipment   is   damaged   or   stolen.   The  landowner   will   be   held   harmless   for   any   loss   or   injury   involved   with   the   EarthScope  project.  

Page 6: 2015 03 Ak and Cn PoD · c2k-c 1k 0 1 c19k c 1 8 7 c16k-1 b2k-1 b2 1k-b0-b9k-b18 k-1 a 2k-a20k-1 i23k -4 l2 6k- 3 6g 2 7k- 3 g 5k g 24 k-g3k g2 1k- 3 9 4g 20-g 1 8k-2 g 16k-g5k 3

PoD,  Oct  2014   Page  6    

         Project  schedule:      In  2011,  roughly  294  initial  sites  were  identified  within  predetermined  20km  areas.  2013  and  2014   field   reconnaissance  efforts   refined   these   locations   to  within  a   few  meters  of  the  actual  site  location,  and  in  some  cases  provided  several  alternate  locations.  With  the  actual  sites  located,  efforts  have  moved  to  permitting  and  install  logistics.  As  of  fall  2014,  25   stations   have   been   installed   and/or   incorporated   into   the   array.   The   proposed  schedule  for  future  station  installations  over  the  next  few  years  is  depicted  in  Figure  4.    

 Figure   4   Location   of   sites   based   on   2013   and   2014   field   reconnaissance  work.     Sites   in   red   are   installed   seismic  stations.    Sites  with  square  symbols  are  existing  seismic  stations  that  we  anticipate  being  incorporated  into  the  array.  All  other  sites  follow  the  installation  plan.  

     

#*

#*

#*

#*

#*

#*

#*

#*

#*

!(

!(

!(

")

!(

!(

!(

!(

")

")

")

")!(

!(

")!(

!(

!(

!(

!(

!(")

!(

")

!(

!(

!(!(

")

") ")!( !( ")

!(

!( ")

!( ") ")

")")

")!(

")

!( !( !(

!(

")")

") ")

!(

!(!(

!( !(") !(

!(

")

!(!( !(

!(")

")

")")

!( ")

")")

!(

")

!( !(!(

")!(

")")

") ")

")") ")

")

!(

!(!(

!( ")

") !( ")")

") ")

!(

!(

")")

!(

!(

!(

!( ")

")

")

")

")

")!(

")

")

")

")

!(

!(

!(

!(

!(

!( !(

!(

")

")

!(

!(

!(

!(

")

!(

")

")

!(!(

!(!(

!( !(

!(!(

!(

!( !(

!(!( !( !(

!(!(

!( !(

!(!( !(

!(

")

!(

!(

!(

!(

!(

")

!(

!(

!(

!(

!(

!(!( !(

!(

!( !(

!( !( !(

!( !(!(

!(!(

!( !(!(

!(!(

!(!(

!(!( !(

!(

!(!( !(

!(!( !(

!(

!(

!(

!(

!(!(

!(

!(

!(

!( !( !(

!(!(

!(!(

!( !(!( !(

!(

!(

!(!( !( !( !(

!(!(

!(

!(!(

!(

!(

!(

!(

")

!(

!(

!(!(

!(

!(

!( !(

!( !(

!(

!(!( !(

!(!(

!(!(

!(!(

!(

!(

!(

!(

!(!(

!(

!( !(

!(

!(

!(

!(

!(

!(

!(

!(

!(

")

!(

!(

!(

!(!(

!(

!(

!(

!(!(

!(!(

!(

!(

!(

!(

!(

K24K

L27K

EPYK

C36M

A21K

Q23K

P08K

O22K

M24K

K27K

K07K

POKR

G13K

TOLK

A36M

O19K-1

H26K-1

AK.PNL

V35K-1

U35K-2

U34K-1U33K-1

S33K-1

S32K-2

S31K-1

R31K-1

R18K-1

M29M-1

L29M-1

L28M-1

J30M-1

J28M-1

I30M-1I28M-2

H31M-2H29M-1H28M-1

G31M-1

G29M-1G28M-1

F30M-2F29M-2

F28M-2

E30M-2

E29M-2E28M-2

D27M-1

AT.PMR

M25K-2

N27K-2

E22K-1

E21K-1

E20K-1

D25K-2

D24K-2

D23K-1D22K-2D21K-1

D20K-2

D19K-2

D17K-2

C27K-1

C26K-1C25K-1

C24K-1C23K-1

C22K-2

C21K-1

C20K-1

C19K-2

C18K-1C17K-1

C16K-1

B22K-1

B21K-1

B20K-1

B19K-1

B18K-1

A22K-2

A20K-1

I23K-4

L26K-3

G27K-3G26K-2

G25K-2G24K-2

G23K-1

G22K-1

G21K-3

G20K-1G19K-4

G18K-2

G16K-1

G15K-3

F27K-1

F26K-2

F25K-2

F24K-1F22K-2

F21K-2F20K-2

F19K-1

F18K-1F17K-1

F16K-2F15K-1F14K-2

E27K-1E26K-1

E24K-1

E19K-2E18K-1

E17K-1

E16K-1

P16K-1

R17K-2

M14K-1

N14K-1

O14K-1

N15K-1

O15K-2

N16K-1

O16K-1

AK.SAW

J15K-1

M16K-2M15K-1

M13K-1

L16K-1L15K-1

L14K-1L13K-1

K16K-1K15K-1K14K-2K13K-1

J17K-1J16K-2

J14K-1

I20K-2

I18K-2

H20K-1H19K-2

H18K-1H17K-1

G17K-3H23K-5

AK.CUT

H27K-9

M27K-5

E23K-3

K17K-2

J19K-2

A19K-1

AK.HOMO17K-1

N25K-3M22K-1

M20K-3M19K-1

M18K-5M17K-2

L20K-2

L19K-1L18K-4L17K-3

AK.MCK

K18K-6

AK.HDA

J20K-2

J18K-4

I27K-5

AK.MLYI21K-1

AK.TNA

D31M-1

D28M-1

I26K-2

F31M-T1

G30M-T4

I29M-T1

J29M-T3

L30M-T1

M30M-T1 M31M-T1

N31M-T2 N32M-T1

O28M-T1

P29M-T1

P30M-T1

P31M-T1

P33M-T1

O29M-T3

IU.COLA

Q32M-T2

R33M-T1

S34M-T1

T35M-T2

P32M-T1

AT.SDPT

H24K-3a

CN.YUK6

AK.CAPN

AK.RC01

AK.SCRK

K20K-4b

AK.NEA2

H21K-4a

AK.COLD

AK.RDOG

K29M-T3

M26K-3-2

H22K-3-1

P17K-4-1

O18K-5-1

N30M-7-2

N18K-3-1N17K-3.5

J26K-3-1J25K-6-1

H25K-1-2

N19K-6-HCL6

Q20K-PB.AC39

S18K-2-AK.SII

U13K-1-AK.CHN

T32K-1-AT.SIT

T17K-2-AK.CHI

T09K-2-AK.UNV

P28K-1-AK.PIN

P25K-1-AK.KAIP22K-1-AK.SWD

P19K-1-AV.OPT

P18K-1-AV.BGM

O31M-1-CN.WHY

O30M-2-CN.HYT

O27K-1-AK.CTG

O26K-1-AK.CRQO25K-1-AK.BMR

O23K-2-AK.GLI

N24K-1-AK.KLU

N23K-1-AK.KNKN21K-1-AK.SSN

M21K-1-AK.SKN

L25K-1-AK.PAXL24K-1-AK.DHY

K22K-2-AK.TRF

K19K-2-AT.TTA

I25K-1-AK.PPD

G14K-1-AK.ANM

E31M-1-CN.INK

P21K-6-AK.BRSE

M23K-6-AK.WAT6

R19K-3-II.KDAK

Q17K-2-AV.CNTC

Q29K-2-AK.DCPH

Q18K-3-AV.KAHC

V34K-4-AT.CRAG

U06K-3-AK.NIKH

T34K-2-US.WRAK

T33K-1-PB.AB51

T10K-2-AK.FALS

S19K-3-AT.OHAK

S15K-2-AT.CHGNS14K-1-AV.VNFG

S12K-1-AV.BLHA

R32K-1-PB.AB50

R16K-1-PB.AC52

Q31K-1-AT.SKAGQ30M-1-CN.PLBC

Q19K-1-PB.AC08

P27K-1-AK.MESAP26K-1-AK.BGLC

P23K-1-PB.AC79

O24K-1-AK.EYAK

O20K-1-PB.AC47

O08K-1-AK.SPIA

N29M-2-CN.YUK4N28M-2-CN.YUK3

N26K-1-AK.MCAR

N20K-1-AV.SPCR

M28M-2-CN.BVCY

M11K-1-PB.AB08

L23K-1-AK.WAT2L21K-1-AK.PPLA

K28M-2-CN.DAWY

K25K-1-AK.RIDG

K21K-2-AK.CAST

J27K-1-US.EGAK

J22K-1-AK.BPAW

J21K-1-AK.CHUM

I19K-2-AK.GCSA

I17K-1-PB.AB17

H16K-1-PB.AC31

G10K-1-PB.AB04

G09K-1-AK.GAMB

E25K-1-PB.AB46

Faro, YT

Mayo, YT

Wrigley, NT

Fort Liard, NT

Watson Lake, YT

Hyland Airport, YT

Twin Creeks Airport, YT

NOWN - Norman Wells, NT

CLVN - Colville Lake, NT

Proposed Alaska TA Installation Plan

C:\Data\GIS-data\AllStates\Alaska\InstallPlan\AK_InstallPlan_D.mxd 11/24/2014

!( 2014 (New) - 15

") 2014 (Existing) - 10

!( 2015 (New) - 38

") 2015 (Existing) - 45

!( 2016 (New) - 84

") 2016 (Existing) - 14

!( 2017 (New) - 90

#* YNSN

Page 7: 2015 03 Ak and Cn PoD · c2k-c 1k 0 1 c19k c 1 8 7 c16k-1 b2k-1 b2 1k-b0-b9k-b18 k-1 a 2k-a20k-1 i23k -4 l2 6k- 3 6g 2 7k- 3 g 5k g 24 k-g3k g2 1k- 3 9 4g 20-g 1 8k-2 g 16k-g5k 3

PoD,  Oct  2014   Page  7    

Operation  and  Maintenance    The   seismometer   and   other   equipment   will   operate   continuously.    Whenever   possible  maintenance  will   be  performed   remotely.     If   the  equipment  malfunctions,   the  problem  can  be   identified  at   the  data  processing   center.  On  occasion  maintenance   trips  may  be  necessary  and  will  be  limited  to  roughly  a  few  hours  on  one  day  about  once  a  year.  Most  often  maintenance  issues  are  related  to  data  communications.    Additional  Information  A   significant   portion   of   the   funding   for   this   project   is   dedicated   to   public   outreach.    EarthScope   and   its   partners   have   developed   activities,   lesson   plans,   map   tools,  visualizations   -­‐   and  much  more   -­‐   to   help   students   and   teachers  work  with   EarthScope  data   and   scientific   results.   EarthScope   materials   include   teachable   moments,   research  summaries,   links   to   research   projects,   and   interactions   with   EarthScope   scientists   and  staff.    For  more  information  on  the  EarthScope  project,  please  review  the  links  below:    http://www.usarray.org/researchers/obs/transportable    http://www.nature.com/news/us-­‐seismic-­‐array-­‐eyes-­‐its-­‐final-­‐frontier-­‐1.14099    www.popsci.com/science/gallery/2011-­‐07/big-­‐science-­‐universes-­‐ten-­‐most-­‐epic-­‐projects?image=9    www.earthscope.org    http://www.earthscope.org/science/observatories    http://www.earthscope.org/resources    www.nature.nps.gov/geology/earthscope        


Recommended