Imagination at work. Davide Franceschi March 24 th , 2015 GE’s Operating Rhythm “GE proprietary and confidential”
Transcript
  • Imagination at work.

    Davide Franceschi March 24th, 2015

    GEs Operating Rhythm

    GE proprietary and confidential

  • Companys profile

  • GE Outlook

    3

    GE proprietary and confidential

  • Creating competitive advantage in the GE Store

    O&G Revenues $18,7B OP $2,6B OP @19%

    4

    GE proprietary and confidential

  • Purposeful portfolio moves

    5

    GE proprietary and confidential

  • 6

    GE proprietary and confidential

  • GE consolidated results

    7

    GE proprietary and confidential

  • 2014 General Electric Company - All rights reserved

    GE Oil & Gas today From extraction, to transportation, to end use

    8

    Subsea Systems

    $3.5B Subsea production

    systems

    Turbomachinery Solutions

    $5.4B LNG, on- and offshore,

    pipeline

    Downstream Technology

    Solutions

    $1.7B Refinery and gas

    distribution

    Drilling & Surface

    $4.9B BOPs and risers,

    onshore trees,

    Artificial lift

    ~45,000 employees ~$19B revenues 14

    Delivering customer solutions by applying systems-level engineering across the value chain

    Measurement & Control

    $3.8B Valves, controls, diagnostics

    8

    GE proprietary and confidential

  • Our technology solutions Subsea Systems Subsea trees & wellheads

    Subsea power & processing

    Controls

    Manifolds

    Flexible risers

    Flow lines

    Specialty connectors & pipes

    Measurement & Control Asset condition monitoring, control sensing

    & inspection solutions

    Optimization & diagnostic software

    Pipeline inspection and integrity services

    Control & safety relief valves

    Fuel dispensers & payment terminals

    Fuel control & retail systems

    Drilling & Surface Drilling risers

    Blow-out preventers

    Electric submersible pumps

    Logging while drilling & wire line tools

    Surface wellheads & flow control

    Logging services

    Well Performance Services

    Lufkin

    Artificial lift: rod lift, gas lift, plunger lift, progressive cavity pumps, hydraulic pumping units

    Service & repair

    Engineered industrial gears

    Fluid film bearings

    Turbomachinery Solutions Turbomachinery equipment and services for the upstream, midstream and LNG segments including:

    Gas turbines

    Axial & centrifugal compressors

    Electric motor driven compressors

    Turn-key industrial modular solutions

    Turboexpanders & heat exchangers

    Contractual & maintenance services

    Upgrades & industrial applications

    Monitoring & diagnostics

    ~45,000 employees

    ~$19B revenues 14

    Delivering customer solutions by applying systems-level engineering across the portfolio

    Downstream Technology Solutions Equipment & services for the refinery & petrochemical, distributed gas and industrial applications including:

    Steam turbines

    Reciprocating compressors

    Distributed gas solutions small LNG & CNG

    Pumps, valves & distribution systems

    Blowers & compressors

    Maintenance services & remote monitoring & diagnostics

    9

    GE proprietary and confidential

  • A Turbo Machinery company

    Well Support Pressure Control

    Electrical Submersible Pumps

    Logging Services

    Developed a Service

    model

    Expanded in Inspection

    Technologies

    Entered the Drilling &

    Production segment and

    Subsea

    Expanded to sensing and

    flow

    Ideal partner for new

    challenging O&G

    developments

    $1

    $2

    $4 2007

    $10

    ~$16

    ~$20

    1994 1997 2004 2008 2011 2013

    Where we are now growth of GE Oil & Gas Orders - $ in billions

    10

    GE proprietary and confidential

  • Our technology solutions 45,000 employees across the globe

    Subsea Systems

    Turbomachinery Solutions

    Drilling & Surface

    Downstream Technology

    Solutions

    Measurement & Control

    Aberdeen Houston Florence Houston Boston

    Advanced turbomachinery equipment and services for the upstream, midstream

    and LNG segments

    Drilling, completion & production solutions for

    unconventional resources, deepwater

    drilling & EOR applications

    Comprehensive systems & expertise

    for reliable subsea

    production, control and optimized life-of-field

    2014 General Electric Company

    Equipment & services for refinery, petrochemical,

    distributed gas & industrial

    applications

    Asset condition monitoring, control sensing & inspection solutions delivering healthcare for the industry

    11

    GE proprietary and confidential

  • Turbomachinery Solutions 6,000+ PEOPLE ACROSS 6 CONTINENTS

    Offshore

    Adjacent segments

    Pipeline

    Floating LNG

    AN INTEGRATED BUSINESS

    HIGH-TECH PRODUCTS &

    SERVICES

    PROJECT MANAGEMENT

    CONTRACTUAL & MAINTENANCE

    SERVICES & UPGRADES

    SERVING KEY SEGMENTS

    LNG Onshore

    DRIVERS

    Aeroderivative Gas Turbines

    Heavy Duty Gas Turbines

    Synchronous & Induction Electric Motors

    COMPRESSORS

    Centrifugal & Axial

    Integrated

    Direct Drive High Speed

    Subsea

    Turbo expanders

    TURN-KEY SOLUTIONS

    Industrial Modules Waste Heat Recovery

    OUR PORTFOLIO

    2014 General Electric Company

    COMPACT CONTROL

    SYSTEMS

    AIR COOLED HEAT

    EXCHANGERS

    12

    GE proprietary and confidential

  • Key Turbomachinery Solutions hubs

    2014 General Electric Company

    Where we are

    Headquarters

    Regional Hubs

    Manufacturing Facilities

    Service Shops

    Edmonton, Canada

    Houston, USA

    Rio de Janeiro, Brazil

    Florence, Italy Massa, Italy Avenza, Italy Vibo Valentia, Italy Talamona, Italy

    Aberdeen, UK

    Le Creusot, France

    Maracaibo, Venezuela

    Moscow, Russia

    Abu Dhabi, MENAT Doha, MENAT

    Beijing, China

    Jandakot, Australia

    Kuala Lumpur, Malaysia

    Gurgaon, India Port Harcourt, Nigeria

    Hassi R' Mel, Algeria

    Barcelona, Spain

    Port of Spain, Trinidad

    Fot, Hungary

    Recife, Brazil

    13

    GE proprietary and confidential

  • O&G Operational view

    14

    GE proprietary and confidential

  • O&G 2014 results

    15

    GE proprietary and confidential

  • GE Op Mechanism

  • Finance Competency Model

    17

    GE proprietary and confidential

  • Vision - CFO Agenda

    Finance Vision: Partners in Building Shareowner Value Through Integrity, Excellence, and Leadership

    Leadership Development Business Partners Drive Initiatives Services, Globalization, Simplification VCP, ROIC, Fastwork Digitization Providing Real Time Management Information and Solutions Controllership Fundamental

    18 GE proprietary and confidential

  • GEs Operating Rhythm

    Quarterly Earning Release to communicate externally the performance

    The annual drumbeat that keeps the Company moving

    Linkage of Processes and Meetings Form a Powerful Operating System to accelerate

    Business and Cultural Change.

    19

    GE proprietary and confidential

  • How we oversee risk

    20

    GE proprietary and confidential

  • GE Oil & Gas Op Mechanism

  • Executive summary

    2

    3

    4

    1

    Drive & influence behaviors

    Aligned with key O&G and GE HQ events

    Designed to be more action-oriented, topical, allow cross-functional engagement & best practices sharing

    Solid Predictability is not an option

    22

    GE proprietary and confidential

  • Organizational Structure GE Oil & Gas

    Latam MENAT Sub S Africa

    Russia & CIS

    China APac

    TMS DTS D&S

    Lufkin SubSea M&C

    ENG Quality Finance

    Communic. Marketing Global

    Supply C.

    IM HR

    Legal Biz Dev

    CEO

    Regions Business P&Ls

    Functions

    Project Management

    23

    GE proprietary and confidential

  • Project Mgmt

    Portfolio Analysis

    Planning

    Risk Management

    Stakeholders

    23/03/2015 24

    Biz Model

    Orders

    Revenues

    Op Profit, rate %

    CFOA

    Business Model

    Project Management

    Financial Plan & Analysis

    = +

    Dynamic loops between Project Directors & FP&A

    Opportunities

    Customers

    Projects

    Bids

    FEEDs

    Biz Objectives

    Orders

    Revenues

    Op Profit, rate %

    CFOA

    Project Directors

    Financial Planning

    Sales Force

    C- suite

    From tendering to execution

    24

    GE proprietary and confidential

  • Turbomachinery Project Organization

    TM - OTR

    PROJECT

    MANAGER

    PROJ. QUALITY

    MANAGER

    PROJECT

    ENGINEER

    MFG Fullfillment Cells

    SOU Fullfillment Cells

    DESIGN ENGINEERS *

    PROJECT

    PLANNER INSTALLATION

    MANAGER

    SITE TEAM *

    WARRANTY

    MANAGER

    TM - QUA ENG Supply

    Chain Global

    Service

    Operations Finance

    25

    GE proprietary and confidential

  • 26

    GE proprietary and confidential

  • Portfolio Orientation & Implementation

    Targets

    PM & Funct. Measured on Same Target

    Shared Team Accountability

    Operating rhythm

    Projects

    So

    urc

    ing

    TGT

    $/%

    Ma

    nu

    factu

    ring

    En

    gin

    ee

    ring

    $/% $/%

    Merge Project & Financial Rhythms to drive all functions on a common

    goal

    $/%

    Projects $/% $/% $/%

    23/03/2015 27 27

    GE proprietary and confidential

  • Project Execution Phases... Key Processes ITO/OTR Hand-off

    Project Contract Activation Project Plan Creation Project Budget Baseline Customer Kick Off Meeting Pre-inspection Meeting

    Engineering Project Design Reviews Project Documentation Mngt . (VDR)

    Sourcing Material Procurement Management Supplier Deviation Request Mngt .

    Manufacturing Manufacturing Plan Reviews NC Mngt . during production phase

    Shipping Meeting Packing & Shipment Transportation/Handling Process

    Events directly involving Customers 28

    GE proprietary and confidential

  • Installation & Warranty Phases... Key Processes

    Site Survey & Pre-Installation

    Meeting Warranty

    COD Site

    Start

    Warranty

    Expiration

    Planning and Monitoring Red Flag Review Technical Briefing Technical Package for Installation Management of NC detected at site

    Site Survey Pre-installation meeting

    Warranty Claim Mngt Hand-Off from TM to CSA

    Installation Contract

    Erection Pre-Commissioning

    & Commissioning Start-Up

    RFR

    Oil Flushing

    Mechanical

    Completion RFR

    Green Light RFR

    Loop Checks

    Events directly involving Customers

    29

    GE proprietary and confidential

  • Project Control & Risk Milestones Approach

    Launch Execution Shipment Installation Warranty

    Risk Reviews

    Customer Milestones

    Project Control Review

    Project Risk Reviews - @ Milestones

    Identify/Capture main Prj Risks for each milestone

    Risk Check-List, Risk Priority Number Action/Mitigation Plan & Risk Register Update

    Project Control Reviews Monthly

    Schedule, budget, quality and any other aspect related to project Issue & risk management

    Internal Reviews

    Pre-PO

    Impact

    Low High

    1 3 9

    High 9 9 27 81 Red Significant Risk

    3 3 9 27 Yellow Proceed with caution

    Low 1 1 3 9 Green No concern

    Gray Not yet evaluated / No risk

    Pro

    babili

    ty

    30

    GE proprietary and confidential

  • Project Budget unique baseline

    Keep As Bid cost estimation constantly aligned

    Freeze As Bid versions

    Order booking As Sold Budgetformally communicate

    As Sold Budget to Hand-Off (RAC) playersshare and analyze

    Input As Sold Budget into BOM structure

    As Sold true-up meeting with Finance/PM

    Support AE to update cost estimate

    Superviseupdate financial plan

    Analyze and check Order Plan consistency

    Attend Hand-Offcontribute!

    Provide dummy template for BOM costing recast

    Validate and upload in Oracle

    As Bid Budget

    As Sold Budget

    Hand-Off (RAC)

    Project Budget

    Commercial Ops Team Finance Team

    31

    GE proprietary and confidential

  • Month 1

    1 2 3 4 5

    8 9 10 11 12

    15 16 17 18 19

    22 23 24 25 26

    29 30 31 1 2

    Project finance rhythm

    Calendar

    QMI 1

    3

    KPIs weekly pacing ... Operations + Finance

    Month 2

    1 2 3 4 5

    8 9 10 11 12

    15 16 17 18 19

    22 23 24 25 26

    29 30 31 1 2

    Month 3

    1 2 3 4 5

    8 9 10 11 12

    15 16 17 18 19

    22 23 24 25 26

    29 30 31 1 2

    As Sold As Delivered

    Backlog review + B&B/ TO GO + Prodty

    BC

    E

    BC

    E

    BC

    E

    Project reviews

    BCE ( Project Margin review)

    2

    3

    1

    32

    GE proprietary and confidential

  • Rigorous process to track/ review project costs for long term contracts

    Drive productivity initiatives and project margin expansion

    Scalable and digitized process

    Formal reviews with key stakeholders Finance to lead

    Project margin review process

    Highlights

    33

    GE proprietary and confidential

  • Operations Finance

    B1) MATERIALS (EXTERNAL SUPPLY)

    Sez Item Sub-item Description Q.tyUnit Cost

    (Euros)

    Total Cost

    (Euros)

    100 0010 -

    100 0050 Outer casing -

    100 0100 Suction Head flange -

    100 0101 Discharge Head flange -

    100 0310 0010 Shaft 1 7,000.00 7,000.00

    100 0310 0020 Impeller 1 12,000.00 12,000.00

    100 0310 0030 Impeller 1 5,000.00 5,000.00

    100 0310 0040 Impeller 4 3,500.00 14,000.00

    100 0310 0050 Impeller -

    100 0310 0060 Impeller -

    100 0310 0070 Impeller -

    100 0310 0080 Impeller -

    100 0310 0090 Impeller -

    100 0310 OTH Completion parts 1 18,000.00 18,000.00

    100 0221 0010 Inner Casing 1 21,000.00 21,000.00

    100 0221 0020 Inner Casing -

    100 0221 0030 Inlet Diaphragm 1 4,000.00 4,000.00

    100 0221 0040 Inlet Diaphragm -

    100 0221 0050 Interph./Disch. Diaphragm -

    100 0221 0060 Models -

    100 0221 0070 Intermediate Diaphragm 1 5,000.00 5,000.00

    100 0221 0080 Intermediate Diaphragm 4 4,500.00 18,000.00

    100 0221 0090 Intermediate Diaphragm -

    100 0221 0100 Intermediate Diaphragm -

    100 0221 0110 Intermediate Diaphragm -

    100 0221 0120 Intermediate Diaphragm -

    100 0221 OTH Other 1 1,500.00 1,500.00

    100 0160 -

    100 0161 -

    COST CONTROL SEZ. 100

    Sez100

    0

    AL JUBAIL

    CUSTOMER :

    END USER :

    PROPOSAL # :

    PLANT :

    Rotor

    Rotor

    Rotor

    Rotor

    Diaphragms set

    Diaphragms set

    Diaphragms set

    Diaphragms set

    Suction end cover

    Discharge end cover

    Diaphragms set

    Rotor

    Diaphragms set

    Diaphragms set

    Diaphragms set

    Diaphragms set

    SCOPE of SUPPLY :

    Rotor

    Rotor

    Description

    Outer casing assembling accessories

    Rotor

    Rotor

    Diaphragms set

    Diaphragms set

    Diaphragms set

    Rotor

    Diaphragms set

    Project Budget

    Unique baseline for measurement Built on BOMcommon ITO/OTR language Shortened process available @ Hand-off

    Earlier visibility to protect/enhance margin Monthly rhythm calendar & dashboards Leakages RCA WF basedfunctions involvement

    Project Reviews

    OTR ITO

    Feedback to ITO

    Leverage on lessons learned Enable cost estimation improvementSource Books + Configuration Mgmt On Line & Oracle based tools

    0

    20

    40

    60

    Q1 '08 Q2 '08 Q3 '08 Q4 '08 Q1 '09

    0

    20

    40

    60

    Q1 '08 Q2 '08 Q3 '08 Q4 '08 Q1 '09

    0

    20

    40

    60

    Q1 '08 Q2 '08 Q3 '08 Q4 '08 Q1 '09

    Sourcebooks

    0

    20

    40

    60

    Q1 '08 Q2 '08 Q3 '08 Q4 '08 Q1 '09

    0

    20

    40

    60

    Q1 '08 Q2 '08 Q3 '08 Q4 '08 Q1 '09

    0

    20

    40

    60

    Q1 '08 Q2 '08 Q3 '08 Q4 '08 Q1 '09

    0

    20

    40

    60

    Q1 '08 Q2 '08 Q3 '08 Q4 '08 Q1 '09

    Sourcebooks

    Project budget loop back

    34

    GE proprietary and confidential

  • Simple Understandable

    Forward Looking

    Provide Operational Explanations

    Provide Accountability

    Focus Efforts In the Right Places

    Broadly applicable across businesses

    Accurate Timely

    Cost effective

    Difficult to manipulate

    Attributes of good performance metrics

    35

    GE proprietary and confidential

  • Q& A