Page 1 of 128
Moyne Shire
2016 – 2017 BUDGET PAPERS
Prepared for Council meeting on 26 April 2016
Contents Page
Mayor’s introduction 2
Executive summary 6
Budget reports
1. Link to the Council Plan 9
2. Services and service performance indicators 12
3. Financial statements 38
4. Financial performance indicators 45
5. Other budget information 47
6. Detailed list of capital works 50
7. Rates and charges 59
Budget analysis
8. Summary of financial position 64
9. Budget influences 68
10. Analysis of operating budget 71
11. Analysis of budgeted cash position 76
12. Analysis of capital budget 79
13. Analysis of budgeted financial position 83
Long term strategies
14. Strategic resource plan and key financial indicators 87
15. Rating information 89
16. Borrowings 92
Appendices
A Fees and charges schedule 93
B Budget process 119
C Glossary 120
2 Moyne Shire Budget 2016-17
Mayor’s Introduction It is with great pleasure that we present the Draft Budget for the 2016-17 year for Council’s consideration. In April 2015 Council reviewed its Long Term Financial Plan to address the freeze on indexation to the Financial Assistance Grants, the loss of Country Roads and Bridges funding and the State Government’s impending rate capping to commence in 2016-17. The review identified the need to reduce recurrent operational expenditure by $600,000 and reduce $2,000,000 from capital expenditure over the next ten years to remain financially sustainable. Subsequent to this a number of service reviews have been undertaken over the past 12 months. As a result, Council has identified ongoing operational savings and efficiencies of $614,000, and reprioritised its capital works program, saving a further $220,000 for the 2016-17 budget year. The 2016-17 draft budget proposes a 2.5 per cent rate increase. This is in line with the new Fair Go Rates System (FGRS) which has capped rates increases by Victorian Councils to the forecast movement of 2.5 per cent in the Consumer Price Index (CPI). This proposed budget continues to provide for a comprehensive range of services, programs and capital works that balance community demands with the financial capacity of Council to fund such demands while maintaining a responsible financial position. Council will, with the introduction of rate capping in 2016, continue to focus on identifying sustainable cost savings that will enable it to deliver high quality, responsive and accessible services to the community to help shape the Shire as a safe, vibrant, liveable and prosperous community. The budget has been developed through a rigorous process of consultation and review including input from community township priorities and a review of Council’s Rating Strategy. Continuing Services
Kindergartens
Provision of a universal early childhood program, for children in the year prior to commencing primary school. Children attending kindergarten receive a planned, developmentally appropriate program delivered by a qualified early childhood educator.
Aged Care Services Provide aged care services including domestic assistance, personal care,
respite, garden and property maintenance, and meals on wheels.
3 Moyne Shire Budget 2016-17
Recreation and Community Development Continue to develop township community plans across the shire. Provide Community Assistance Grants ($232,500) to support community
groups for program delivery, facility upgrade and equipment purchases. Provide support to Recreation Reserve Committees, and Public Hall
Committees.
Childcare
Provision of child care services to Moyne Shire residents as follows:
Location Type of service Operating Hours
Port Fairy Community Services Centre Long Day Care Monday – Friday
7.30 am – 6.00 pm
Hawkesdale & District Family Services Centre Long Day Care Mon, Tues &Thursday
8.30 am – 5.00 pm
Chatsworth Occasional Child Care
Tues & Thursday
9.00 am – 4.30 pm
Road Maintenance
Maintenance of approximately 1,700 km local sealed network. Maintenance of approximately 1,100 km unsealed road network.
Parks and Amenities
Lawn, garden and tree maintenance of 28 township sites, maintenance of
19 playgrounds, BBQ maintenance, public toilets maintenance, street
cleaning, and festival support.
Asset Management
Management of Council assets including maintenance, renewal and
project management. Includes maintenance of Council’s 280 buildings.
Regulatory Services Provide emergency services, including fire prevention and emergency
management support. Education and enforcement of Council’s local laws and animal control
measures. Continue monitoring of food premises, approval of septic tanks and
broader health initiatives across the shire.
4 Moyne Shire Budget 2016-17
Town Planning Planning permit applications processing and enforcement of the Moyne
Planning Scheme. Major projects liaison with proponents, government agencies and local
communities. Strategic plans for various settlements such as Koroit, Hawkesdale and
others.
Waste Service Provision of waste collection and disposal services across the shire,
including management of Council’s kerbside collection service, and management of Council’s waste facilities.
Council has made changes to the operation of waste facilities to commence 1 July 2016, including the closure of Bessiebelle and Port Fairy transfer stations and change to operating hours of 7 waste facilities.
Promote and educate Council and the community on sustainable waste management practices.
New Initiatives The Draft 2016-17 Operating Budget provides the following new initiatives including
Port of Port Fairy Wharf Redevelopment ($2,850,000)1
Mortlake Heritage Planning Scheme Amendment C61 ($28,000);
Roadside Conservation and Weed Management Plan ($30,000);
Rural Housing Strategy Planning Scheme Amendment ($20,000).
A full list of operating programs is listed in section 2. Capital Council’s commitment to capital works will reach $18.3 million including $11.9 million on Council’s road network. Other capital works projects include:
Hawkesdale: Swimming pool refurbishment ($51,300);
Koroit: Skate park and facilities ($170,000), Victoria Park sealing works
($20,000);
Macarthur: Hall works ($20,000);
Mortlake: Mortlake library and information centre upgrade ($750,000),
accessible toilets for the bowls club ($60,000); swimming pool refurbishment
($250,000); sprinkler system Market Square ($36,000); DC Farran Oval sealing
works ($20,000);
Peterborough: Foreshore bollards ($10,500);
Port Fairy: Surf Lifesaving Club extension ($512,000), Reardon Theatre
ventilation works ($25,000), Powling Street footpath ($110,000);
Yambuk: Public toilet upgrade ($35,000), Playground renewal at Yambuk Lake
($25,000);
1 Fully funded (State Government: $1.43 million and the Port of Port Fairy Reserve: $1.43million).
5 Moyne Shire Budget 2016-17
Wangoom: Recreation Reserve accessibility upgrade ($115,000);
Woolsthorpe: Transfer station upgrade ($50,000)
Woorndoo: Recreation Reserve Toilets upgrade ($120,000);
Mailors Flat: Mailors Flat Hall refurbishment ($16,000);
Cudgee: Footpath to link new estate area with existing footpath ($70,000);
Hexham: BBQ Shelter ($20,000);
Cr Colin Ryan Mayor
6 Moyne Shire Budget 2016-17
Executive summary Council has prepared a Budget for 2016-17 which is aligned to the vision in the Council Plan 2013-17. It seeks to maintain and improve services and infrastructure as well as deliver projects and services that are valued by our community, and do this within the rate increase mandated by the State Government. This Budget projects a surplus of $4.89 million for 2016-17 and an adjusted underlying surplus of $3.30 million. An adjusted underlying result is net operating result after excluding capital grants and contributions revenue (refer Sections 5 and 10.1).
1. Key things we are funding
1) Ongoing delivery of services to the Moyne Shire community funded by a budget of $49.42 million. These services are summarised in Section 2.1.
2) Continued investment in Infrastructure assets ($14.47m) primarily for renewal
works. This includes roads ($11.93m); bridges ($1.11m); footpaths ($0.41m); drainage ($0.37m); recreational and leisure ($0.59m); and waste facilities ($0.06m). The Statement of Capital Works can be found in Section 3 and further details on the capital works budget can be found in Sections 6 and 12.
2. The Rate Rise
a. The average rate will rise by 2.5% in line with the order by the Minister for Local Government on 14 December 2015 under the Fair Go Rates System.
b. Key drivers
i. To fund ongoing service delivery – business as usual (balanced with greater service demands from residents)
ii. To fund renewal of infrastructure and community assets
iii. To cope with the cost shifting from the State Government
iv. To cope with a reduction in funding from the Commonwealth Government via the Victoria Grants Commission caused by their freezing of indexation of the grant
c. This will be a revaluation year. Valuations will be as per the General Revaluation dated 1 January 2016 (as amended by supplementary valuations).
d. The kerbside collection charge will increase by 2.4% per property and the waste facility service charge will increase 2.5% for developed properties and 3.2% for undeveloped properties.
e. Note that for every $100 in taxes paid by Victorian residents, rates make up approximately $3.50. The other $96.50 goes to the State and Federal Governments.
f. Refer Section 7 for further Rates and Charges details.
7 Moyne Shire Budget 2016-17
3. Key Statistics
1) Total Revenue: $49.4 2) Total Expenditure: $44.5M 3) Accounting Result: $4.9M Surplus2 4) Underlying operating result: $3.3M Surplus 5) Cash and Investments: $6.3M 6) Total Capital Works Program of $18.3M
4. Budget Influences
External / Internal Influences In preparing the 2016-17 budget, a number of external and internal influences have been taken into consideration because they are likely to impact significantly on the services delivered by Council in the budget period. These include:
Rate Capping
This is the first year of the Fair Go Rates System and Council proposes a
rate increase that is in line with the 2.5 per cent cap.
Grants
Commonwealth’s decision to pause indexation of the national pool of
financial assistance grants for the three years to the end of 2016-17.
Additional Roads to Recovery funding.
A number of grants are anticipated for capital works, and new initiatives.
Borrowings
Nil new borrowing for 2016-17.
Fees and Charges
Non statutory fees will increase by approximately 4% in accordance with the Strategic Resource Plan (SRP) adopted in 2015-16.
Employee Costs
No increase in unfunded positions over the 4 years of the SRP.
2 Includes increase in income from the Roads to Recovery program of $4.2 million. The matching expenditure is included in the capital works program.
8 Moyne Shire Budget 2016-17
Budget Reports
The following reports include all statutory disclosures of information and are supported by the analysis contained in sections 8 to 13 of this report. This section includes the following reports and statements in accordance with the Local Government Act 1989 and the Local Government Model Financial Report.
1 Links to Council Plan
2 Services and service indicators
3 Financial statements
4 Financial performance indicators
5 Grants and borrowings
6 Detailed list of capital works
7 Rates and charges
9 Moyne Shire Budget 2016-17
1 Link to the Council Plan 1.1 Strategic planning framework
The Strategic Resource Plan, included in the Council Plan, summarises the financial and non-financial objectives and strategies of the Council and determines the sustainability of these objectives and strategies over the next four years. The Annual Budget is then framed within the Strategic Resource Plan, including the activities and initiatives which contribute to achieving the Council’s strategic objectives. The strategic planning framework of Council is set out below.
10 Moyne Shire Budget 2016-17
In summary: Long term planning Long Term Financial Plan 10 Year Financial Plan
Medium term planning & sustainability
Council Plan Strategic Resources Plan Strategic Plans Community Plans
Strategic objectives Strategies Strategic indicators Strategic Resources Plan
Short term planning Budget Activities and initiatives Key strategic activities Other information
Accountability Audited statements Annual report
Financial statements Performance statements
The timing of each component of the planning framework is critical to the successful achievements of the planned outcomes. The Council Plan, including the Strategic Resources Plan, is reviewed in time for officers to develop their activities and initiatives and key strategic activities to be contributed to the annual budget process. It also allows time for targets to be established during the Strategic Resources Plan process to guide the preparation of the annual budget from February onwards. 1.2 Our purpose
Our vision - Moyne – a safe, vibrant, liveable, and prosperous community We are made up of many local communities, hamlets and small towns. We respect and grow the diversity of our people. We care for one another and ensure the services we need are provided to the benefit of all to remain healthy, active and mobile. We protect our spectacular natural and built landscape, providing links between landscapes to ensure their long-term integrity and allow development balanced with sustainability. We thrive on our sustainable agricultural base, enhanced with competitive industries and growing tourism. Our community is highly skilled, with a willingness to share knowledge and learn, being adaptive and responsive to change. Moyne seeks to support and foster its strong communities through investing in our youth; improving health and allowing our residents to enjoy their lifestyle and actively participate in the community. Moyne is a place where culture and creativity are highly valued and opportunities for participation in a wide range of leisure activities abounds. We seek to provide residents and visitors with a safe road network. We build on our natural resource strengths, promoting innovation and enterprise to develop a healthy and diverse economy.
11 Moyne Shire Budget 2016-17
Our values 1. Providing Community Leadership We will provide leadership for the community
and advocate on behalf of the community
2. Teamwork We will work together for the whole Shire and recognise our accountability
3. Being Involved We will engage with the community and fellow councillors and communicate effectively
4. Practising Fairness & Balance We will act with fairness in all decision
making 5. Striving for Quality We will seek to improve service quality and
access 6. Respecting Views We will respect alternative views both within
the Council and the community 7. Recognising Diversity We acknowledge the diversity of the Shire
and the varied needs of its different communities
1.3 Strategic objectives
The Council undertakes activities and initiatives through 35 major service categories which are grouped into four key result areas. The following table lists the strategic objectives as described in the Council Plan. Key Result Area Strategic Objective
1. Governance To achieve “best practice” in governance and administration in Moyne.
2. Physical Services To ensure that the shire continues to be an attractive and desirable place in which to live, work and visit.
To continuously improve our roads to ensure they are safe and trafficable.
To protect, preserve and improve required assets.
3. Sustainable Development and Planning
To preserve and enhance our natural and built environment.
To encourage and promote development which is sensitive to its location and environment and which protects our cultural, heritage and indigenous assets.
To provide assurance that the community is adhering to federal, state and local laws.
To facilitate sustainable economic growth. To ensure the health and well-being of our communities.
4. Community and Corporate Support
Enhance the quality of resident’s lives by facilitating and encouraging healthy lifestyles, a community in which it is safe to live and an environment that is diverse and sustainable.
12 Moyne Shire Budget 2016-17
2 Services, Initiatives and service performance indicators This section provides a description of the services and initiatives to be funded in the Budget for the 2016-17 year and how these will contribute to achieving the strategic objectives specified in the Council Plan as set out in Section 1. It also includes a number of performance targets and measures in relation to these. The relationship between these components of the Budget and the Council Plan is shown below.
Budget
Activities Initiatives
Key
Strategic
Activities
Council Plan
Strategic Objective
Strategic Objective
Strategic Objective
Strategic Objective
Performance
Measures/
Targets
Performance
Statement
Medium term planning
(4 Years)
Short term planning(12 Months)
Activities
Activities
Activities
Initiatives
Initiatives
Initiatives
Budget
Activities Initiatives
Key
Strategic
Activities
Council Plan
Strategic Objective
Strategic Objective
Strategic Objective
Strategic Objective
Performance
Measures/
Targets
Performance
Statement
Medium term planning
(4 Years)
Medium term planning
(4 Years)
Short term planning(12 Months)
Short term planning(12 Months)
Activities
Activities
Activities
Initiatives
Initiatives
Initiatives
13 Moyne Shire Budget 2016-17
Key Result Area 1 - Governance Strategic Objective
To achieve “best practice” in governance and administration in Moyne
To achieve our objective of best practice in governance and administration, we will continue to plan, deliver and improve high quality, cost effective, accessible and responsive services which adhere to best value principles.
Services The services, activities, initiatives, major initiatives and service performance indicators for each service category are described below.
Program: Governance
Program Description
Administration of Executive services, Council, Councillor support and monitoring Council activities to ensure legislative compliance.
Expenditure: $1,289,961
Income: - Net Surplus/(Deficit): ($1,289,961)
Key Program Activities
Statutory and corporate support services to Council
Mayoral and Councillor allowances, expenses, training, professional development and membership
Administration of Council meetings and workshops
Supervision of all Council activities to ensure accountability, probity and legislative compliance
Collaboration with other agencies in regional projects
Subscriptions to municipal affiliations and public liability insurance cover
Maintain an understanding of issues of local importance and provide leadership in tackling them
Where appropriate, advocate on behalf of our community and ensure that our community is represented in debates which affect us
Strategic planning activities such as Council Plan review and studies on future directions and initiatives, including contributions to regional planning and projects.
14 Moyne Shire Budget 2016-17
Program: Communications
Program Description
This service is responsible for the management and provision of external communication through various media, in consultation with relevant stakeholders, on behalf of Council.
Expenditure: $263,610
Income: $190,536
Net Surplus/(Deficit): ($73,074)
Key Program Activities
Publishing of quarterly Country to Coast newsletters
Publishing of fortnightly electronic news updates to subscribers
Liaison with local media outlets and co-ordination of responses to media inquiries (approximately three to four times a week)
Coordination of all statutory and discretionary public weekly advertising
Maintenance of internet and intranet content (as required)
Media releases (distribute as required, approximately 130 a year)
Coordinate information, design and production of Annual report
Daily monitoring of press clippings
Coordinate monthly Mayors message that appears The Warrnambool Standard
Coordinate weekly Mayors radio interview
Coordinate commercial printing such as letterhead, business cards etc.
Prepare the Moyne Shire Council Welcome Kit for new residents
Program: Organisational Development
Program Description
This service provides Council with strategic and operational organisation development support. The service develops and implements strategies, policies and procedures through the provision of performance management, benchmarking human resource management and risk management.
Expenditure: $830,182
Income: $585,809
Net Surplus/(Deficit): ($244,373)
Key Program Activities
Co-ordination of advertising, short listing, interview and selection for positions vacant
Induction of all new employees (Inc. caravan park & road construction summer crews)
Delivery of training and professional development program
Administration of employee performance appraisal system for all employees
Industrial Relations management including enterprise bargaining
Development and review of Human Resources policies and procedures
Staff Health & Wellbeing Program
Memberships to Meekin Apel (Industrial Relations Services)
Fortnightly payroll service
Implementation and maintenance of specific risk management & reduction policies & programs.
Work with Internal Audit on the Risk Assessment program. JMAPP, LMI and Fidelity Audits
Administration of the Council’s insurance including Asset, Public Liability, Professional Indemnity and the WorkCover premium
Management of Work-cover claims and return to work obligations
Development of policies, systems and documentation to ensure safe work environments for employees, volunteers, contractors and the community
15 Moyne Shire Budget 2016-17
Program: Financial Services
Program Description
This service predominately provides financial based services to both internal and external customers. This includes reporting, investment of surplus funds and accounts payable and receivable functions.
Expenditure: $1,100,441
Income: $4,419,471
Net Surplus/(Deficit): $3,319,030
Key Program Activities
Adequate internal control mechanisms are maintained at all times so as to record and control all Council’s receipts and payments
Preparation and auditing of financial statements
Preparation of annual budget including capital works budget
Completion of statutory returns including Victorian Grants Commission and Fringe Benefits Tax return
Prepare reports to Council and Managers on a monthly basis highlighting budget variations in respect of Council’s operations
Compile financial models to assist in financial planning including the preparation of long term financial and capital works plans
Accounts payable and receivable functions
Maximise investment income on surplus Council funds for both the short and intermediate term
Manage Council’s loan portfolio and ensure funds are raised in accordance with Council’s approved program.
Provide administrative support to the Audit and Risk Management Committee
Program: Information Technology Services
Program Description
This service provides, supports and maintains reliable and cost effective communications and computing systems to Council staff enabling them to deliver services in a smart, productive and efficient way.
Expenditure: $855,770
Income: $660,612
Net Surplus/(Deficit): ($195,158)
Key Program Activities
Implement the ICT strategy and manage the Council’s ICT system
Monitor and review the ICT strategy and activities
Recommend new capital purchases and hardware and software acquisitions
Ensure the integrity and confidentiality of data and manage information in accordance with established principles including relevant privacy principles and guidelines
Development and delivery of appropriate information technology tools to enable Council departments to meet the needs of their internal and external customers
Development and implementation of policies, standards, guidelines and operating instructions for information systems and operating procedures for all users of computer facilities
16 Moyne Shire Budget 2016-17
Program: Property and Rating
Program Description
Management of Council’s rating system, including levying rates and charges, outstanding interest and valuations of rateable properties
Expenditure: $325,814
Income: $166,502
Net Surplus/(Deficit): ($159,312)
Key Program Activities
Production of approximately 12,000 rate assessment notices per year
Management of bi-annual revaluation process
Management of supplementary rate process
Supervision and maintenance of approximately 12,400 property files
Issuing of approximately 800 Land Information Certificates per year
Compilation of statistical data for rate management and reporting purposes Processing of pensioner and farm municipal exemption forms
Calculation and reconciliation of Fire Services Levy on behalf of State Government Production and maintenance of non-resident voters roll
Program: Administrative Service
Program Description
This service provides office accommodation for Port Fairy and Mortlake including customer service centres, as well as, document and information management support services to Council. This includes compliance with statutory obligations under freedom of information, public records and information privacy legislation
Expenditure: $1,061,842
Income: $685,885
Net Surplus/(Deficit): ($375,957)
Key Program Activities
Office accommodation at Port Fairy, Mortlake and Macarthur
Provision of customer service function
Maintenance of the Council’s Electronic Records Management System
Provision of records management policies and procedures
Training of employees in document management and retrieval
Maintenance of the Corporate Library
Compliance with Public Records Office Victoria standards in records management
Delivery and receipt of all physical correspondence – average of 50 documents scanned daily
Freedom of Information requests
Privacy inquiries
17 Moyne Shire Budget 2016-17
Major Initiatives
Implement Work Cover Self Insurance including safety maps accreditation across all Council ($Nil net cost).
Initiatives
Development of an ICT Strategy ($30,000 net cost).
Electronic Performance Management System implementation ($40,000 net cost).
Set up of Mayoral Blog which incorporates Moyne Matters and allows for comments ($Nil net cost).
Service Performance Outcome Indicators
Service Indicator Performance Measure Computation
Governance
Satisfaction Satisfaction with Council decisions (Community satisfaction rating out of 100 with how Council has performed in making decisions in the interests of the community)
Community satisfaction rating out of 100 with how Council has performed in making decisions in the interests of the community
18 Moyne Shire Budget 2016-17
Key Result Area 2 – Physical Services Strategic Objectives
To ensure that the Shire continues to be an attractive and desirable place in which to live, work and visit
To continuously improve our roads to ensure they are safe and more trafficable
To protect, preserve and improve required assets
To achieve our objectives in the key result area of infrastructure and assets, we will continue to plan, deliver and improve high quality, cost effective, accessible and responsive infrastructure, assets and services.
Services The services, activities, initiatives, major initiatives and service performance indicators for each service category are described below.
Program: Physical Services Directorate
Program Description
Management and operation of Infrastructure and Assets Directorate at the Mortlake office.
Expenditure: $515,540
Income: $485,690
Net Surplus/(Deficit): ($29,850)
Key Program Activities
Directing Engineering and Design Unit, Assets Unit and Construction & Maintenance Unit
Managing Mount Shadwell Quarry
Provision of reports to CEO and Council meetings
Provision of VicRoads agency at Mortlake Office
Liaison with various Government departments, proposed energy project, dairy industry and timber industry personnel
Responding to infrastructure requests and complaints
Memberships include Timber Towns Victoria
Program: Engineering Design & Contract Management
Program Description
This service undertakes design and planning for various works within Council’s capital works program including roads, footpaths, bridges, drainage and waterways infrastructure This service also undertakes contract management and supervision of various works within Council’s programs and provides specialist advice to other Council service units who are letting contracts.
Expenditure: $888,877
Income: - Net Surplus/(Deficit): ($888,877)
Key Program Activities
Project management including programming of roads, road seals, bridges and footpaths
Management of the contract and quotation system for the entire organisation
Contract management including preparation of service specifications for majority of infrastructure projects and for other areas of Council as required
Management of the quarry including the ongoing implementation of all recommendations of the
19 Moyne Shire Budget 2016-17
quarry business plan
Grant application and administration for various projects, including Roads to Recovery, Flood Recovery as they become available
Work with proponents associated with Windfarm development to ensure appropriate road design/construction issues
Assist all departments across the organisation with all engineering and infrastructure related works
Deal with enquiries, issue permits and advice on Vehicle Crossovers, B-Double Higher Mass, Works in Road Reserve, Cattle Underpasses, Legal Point of Discharge, Utility Requests, Signage, Street Lighting, Bus Routes, Dial Before You Dig, Traffic Counts and Miscellaneous Customer Requests
Program: Parks and Amenities
Program Description
This service involves the management of parkland areas, including other areas of environmental significance, and also provides management of all parks and gardens and infrastructure maintenance. Ensures the Shire’s public toilets are kept clean to agreed standards and usable at all times. Undertakes maintenance of Council’s footpath assets in an integrated and prioritised manner in order to optimise their strategic value and service potential.
Expenditure: $2,899,884
Income: - Net Surplus/(Deficit): ($2,899,884)
Key Program Activities
Lawn, gardens and tree maintenance at 28 township sites
Site preparation/maintenance prior to local festivals/activities
Cleaning and maintenance of 20 public toilets
Cleaning and maintenance of 19 BBQ’s
Maintenance of 9 Playgrounds
Clearing of street bins in 15 townships
Port Fairy Folk Festival, provision and placing of bins, barriers, toilet cleaning, bin clearing and street/footpath sweeping
Operation of Street Lights
Program: Quarry Operations
Program Description
This is one of Council’s business enterprises and manages the operations of the Mount Shadwell Quarry at Mortlake providing a range of scoria materials to customers. The enterprise returns a 29% of gross sales dividend to Council’s general revenue.
Expenditure: $1,481,731
Income: $1,700,000
Net Surplus/(Deficit): $218,269
20 Moyne Shire Budget 2016-17
Key Program Activities
Winning and screening of scoria
Feeding and operating crusher making scoria limestone mix and aggregates
Stockpiling – moving products to stockpiles away from production area
Loading trucks from stockpiles
Delivery to clients of small quantities of material
Pit maintenance to ensure weed free and tidy quarry
Quarry Management and supervision
Crusher maintenance
Plant maintenance
Quarry dividend to Council of $485,690
Truck, Water Truck and Ute maintenance
Weighbridge maintenance
Program: Asset Management
Program Description
This service prepares long term asset management programs for Council’s property assets in an integrated and prioritised manner in order to optimise their strategic value and service potential. These are all non-road related assets and include municipal buildings, pavilions and other community buildings. The service ensures that buildings are to a standard specified by Council with advice from the functional manager of the facility. In addition the service is responsible for the coordination, management and strategic planning for Council’s building, land and property leases and licenses as well as maintains the GIS service.
Expenditure: $1,402,360
Income: $50,000
Net Surplus/(Deficit): ($1,352,360)
Key Program Activities
Maintain and populate asset registers and Asset Management System, including condition and compliance audits, and risk and maintenance inspections for non- roads assets.
Program and coordinate works for maintenance, renewal and upgrades for assets including playgrounds, buildings, structures and streetscapes, including maintenance on 280 buildings.
Project Management including design input, tender documentation, supervision and contract management for construction of annual capital works program for playgrounds, buildings, streetscapes, and special projects.
Formulate, make application for, administer and report on funding grants for projects under RDV and similar.
Manage GIS including creating, updating, improving, linking to asset management system, of all councils spatial datasets. All dealings with Geographic Place Names.
Manage all Land and dealings including, leases, licences, sales, purchases, adverse possession claims, and road status queries.
Dealing with infrastructure planning referrals including assessment, conditions, certification, and statement of compliance.
21 Moyne Shire Budget 2016-17
Program: Local Roads & Streets
Program Description
This service undertakes maintenance programs for Council’s civil infrastructure assets in an integrated and prioritised manner in order to optimise their strategic value and service potential, minimising risk to the community and meeting their expectations. These include roads, laneways, car parks and foot/bike paths, bridges, culverts, stormwater drainage. This service also competes for external works in the marketplace. Also included are works supervision and management and provision of works depots and stores. As well as, purchases and maintenance of Council vehicles, plant and equipment to meet functionality and safety needs and to maximise the performance and minimise operational cost of the fleet.
Expenditure: $13,307,814
Income: $10,525,182
Net Surplus/(Deficit): ($2,782,632)
Key Program Activities
Maintenance of approx. 1700km local sealed network, including pothole patching, shoulder sheeting, culvert maintenance, vegetation removal, major patching, bridge maintenance and verge slashing
Maintenance of approx. 1100km unsealed road network including pavement grading, pavement sheeting, drain cleaning, verge slashing, bridge maintenance, vegetation clearing
Maintenance of approximately 240 Bridges and Culverts
Bid for and carry out private works
Provision and maintenance of 4 works depots.
Supervision and administrative functions for 74 (EFT) staff plus temporary employees as required.
Determine and cost 10 year forward plant replacement program.
Ensure full cost recovery via plant hire rates.
Maintain major plant, minor plant and sedan/utility holding.
Program: Main Road Maintenance
Program Description
This service prepares & conducts maintenance under contract for VicRoads to maintain their arterial road network to specified standards.
Expenditure: $446,967
Income: $504,187
Net Surplus/(Deficit): $57,220
Key Program Activities
Contract for VicRoads maintenance to maintain arterial roads within Moyne Shire
22 Moyne Shire Budget 2016-17
Program: Youth Services
Program Description
Facilitating the connection of young people of the Shire to their own local community by initiating and implementing projects and/or events that are of benefit to the whole community. This service encourages the participation of young people in all facets of community life thus promoting young people as integral members of the community.
Expenditure: $187,964
Income: $59,500
Net Surplus/(Deficit): ($128,464)
Key Program Activities
Increased participation of young people in the life of their local communities
Development of responsive and supportive partnerships in order to build community; local service clubs, Vic Police, township progress associations, local government, schools and regional service providers are key stakeholders in the program
Moyne Youth Council activities: leadership training, project planning and delivery
Youth-lead facilitation of major community activities and events, such as the Youth Forum, FReeZA Events and music festivals
Our PlaYce Youth Leadership training program, delivering initiatives that add value to community heritage, recreation and commemoration
Local Youth Action Groups, which facilitate projects like Mortlake Rainbow Run and the landscape design for the Tee Tree Lake skate park.
Program: Arts, Culture & Library Services
Program Description
This service provides support of the Shire’s varied program of arts and cultural events and activities; plans and develops arts and cultural facilities and infrastructure in conjunction with community groups and develops policies and strategies to facilitate art practice through support of the Regional Arts Development Officer and the Arts & Culture Advisory Committee of Council. This service also provides public library services at Port Fairy, Koroit and Mortlake branches, outreach van service to Peterborough and Nullawarre and community libraries at Hawkesdale and Macarthur.
Expenditure: $534,570
Income: $2,000
Net Surplus/(Deficit): ($532,570)
Key Program Activities
Contribution to Regional Library
Provision of operations to isolated sites Macarthur and Hawkesdale.
Building operations to Moyne Shire Branch libraries
Contribution to Regional Arts Development Officer (RADO) position
Support for Arts and Culture Strategy
Support community’s artists, not-for-profit groups and organisations to utilise the arts as a way of cultivating connection and wellbeing in the community
Assist the community to source and achieve funding for Arts projects
23 Moyne Shire Budget 2016-17
Program: Recreation & Community Development
Program Description
This service is Council’s liaison with groups who operate from Council’s sporting reserves and oversees maintenance of gardens oval and Victoria Park Reserve as well as operation of the Southcombe Park Sporting Complex. Works with sporting groups to manage reserves and negotiates License Agreements. Provides community assistance fund, contributions to minor recreation reserves (based on the number of clubs – football, cricket, tennis, netball) and contributions to public halls. This service manages the operation of the Mortlake and Macarthur pools and contributes to the operation of the Hawkesdale pool and the Belfast Aquatic Centre (Port Fairy pool).
Expenditure: $2,003,333
Income: $137,198
Net Surplus/(Deficit): ($1,866,135)
Key Program Activities
Community Assistance Fund
Contribution to minor recreation reserves (based on number of clubs – football, cricket, tennis and netball)
Contribution to public halls
Support for Sport and Recreation Committees
Maintenance of Gardens Oval and Victoria Park Reserves
Operation of DC Farren Oval Mortlake (Sec 86 committee)
Operation of Southcombe Park Sporting Complex (Sec 86 committee)
Operation of the Mortlake and Macarthur swimming pool
Contribution to the operation of the Hawkesdale and Port Fairy swimming pool
Provision of community planning support
Provision of rural access program
24 Moyne Shire Budget 2016-17
Major Initiatives
Review of gravel roads condition for the entire Shire. ($70,000 net cost)
Initiatives
Review of drainage strategy. ($Nil net cost)
Road Focus Group Projects. ($50,000 net cost)
Anchor tenant agreement for Reardon Theatre. ($Nil net cost)
Regional projects: Arts Atlas and social enterprise art project
Youth Council and FreeZa youth leadership and planning camp to develop 12 months’ program.
Further encourage and assist communities to adopt a self-help approach through community planning processes focusing on Wangoom, Minhamite, Woorndoo, Hexham, Gravoc, Broadwater, The Sisters and Koroit communities.
Service Performance Outcome Indicators
Service Indicator Performance Measure Computation
Roads
Satisfaction
Satisfaction with sealed local roads (Community satisfaction rating out of 100 with how Council has performed on the condition of sealed local roads)
Community satisfaction rating out of 100 with how Council has performed on the condition of sealed local roads.
Libraries Participation Active library members (Percentage of the municipal population that are active library members)
[Number of active library members / municipal population] x100
Aquatic Facilities
Utilisation
Utilisation of aquatic facilities (The number of visits to aquatic facilities per head of municipal population)
Number of visits to aquatic facilities / Municipal population
25 Moyne Shire Budget 2016-17
Key Result Area 3 – Sustainable Development and Planning Strategic Objectives
To preserve and enhance our natural and built environment
To encourage and promote development which is sensitive to its location and environment and which protects our cultural, heritage and indigenous assets
To provide assurance that the community is adhering to federal, state and local laws
To facilitate sustainable economic growth
To ensure the health and well-being of our communities
To achieve our objectives in the key result area of Sustainable Development and Planning, we will continue to plan, deliver and improve high quality, cost effective, accessible and responsive services.
Services The services, activities, initiatives, major initiatives and service performance indicators for each service category are described below.
Program: Sustainable Development Directorate
Program Description
This service provides for the Director and Personal Assistant who are responsible for overall coordination and direction of Directorate involving 12 various services.
Expenditure: $642,014
Income: - Net Surplus/(Deficit): ($642,014)
Key Program Activities
Provision of Management and administrative support to the Sustainable Development Department
Oversee provision of Environment and Sustainability, Waste Management, Health, Building, Local Laws, Fire Management, Emergency Management, Animal Control, Statutory Planning, Strategic Planning and School Crossings.
Provision of Administrative staff to support services provided by the Directorate
Provides for legal advice and specialist consultant advice.
26 Moyne Shire Budget 2016-17
Program: Building Services
Program Description
This service provides statutory building services to the Council community including processing of building permits, emergency management responsibilities, fire safety inspections, audits of swimming pool barriers and investigations of complaints and illegal works.
Expenditure: $226,716
Income: $33,050
Net Surplus/(Deficit): ($193,666)
Key Program Activities
Building inspections at progress stages including stump hole, footing, slab, frame and final stage
Pool inspections
Essential safety measure inspections
Temporary structure inspections
Notice inspections (illegal work)
Program: Health Services
Program Description
This service protects the community’s health and well-being by coordinating food safety support programs, Tobacco Act activities and infectious diseases control. The service also works to rectify any public health concerns relating to unreasonable noise emissions, housing standards and pest controls. The unit undertakes some health education initiatives as well as supervises and advises on septic tank systems.
Expenditure: $286,507
Income: $93,500
Net Surplus/(Deficit): ($193,007)
Key Program Activities
Registration of food and health premises, caravan parks and accommodation houses
Issue permits for installation and use of septic tanks
Implementation of the waste water management plan
Infectious disease control
Environmental health nuisance control
Respond to complaint and enquires on public health issues
Food surveillance and sampling
Monitoring Food Safety Plan
Tobacco legislation requirements
27 Moyne Shire Budget 2016-17
Program: Local Laws and Animal Control
Program Description
This service facilitates the smooth flow of traffic and parking in Port Fairy through the provision of safe, orderly and equitable parking enforcement and education. It also provides education, regulation and enforcement of the General Local Law and relevant State legislation and administers Council local laws including the issue of permits for grazing, droving and stock crossings. This service also provides services including a cat trapping program, a dog and cat collection service, a pound service, a registration and administration service, an after-hours service and an emergency service. Also implements the provisions of the Domestic Animals Act.
Expenditure: $637,056
Income: $160,000
Net Surplus/(Deficit): ($477,056)
Key Program Activities
Administrating Council Local Laws
Issuing and enforcement of permits for grazing, droving stock crossings and activities on Council land.
Management of infringement notices including court proceedings
Responding to complaints related to animals including dogs and wandering stock
Implement provisions of the Domestic Animals Act
Issuing of animal registrations ( 4,500 per annum)
Supervision of safe school crossing points at Koroit, Mortlake and Port Fairy.
Program: Emergency Management
Program Description
This service meets Council’s obligations under the Emergency Management Act and develops and maintains the Municipal Emergency management Plan and Emergency Management Committee and works with other agencies to prepare for, respond to, and recover from emergencies. This service also manages fire prevention services and State Emergency Services contributions, including support for fire brigades, fire spotting services at Mt Rouse and Mt Warrnambool and maintenance of emergency fire equipment.
Expenditure: $311,100
Income: $88,500
Net Surplus/(Deficit): ($222,600)
Key Program Activities
Emergency Management Act obligations
Municipal Emergency Management Plan
Fire prevention services and State Emergency Contributions
Support of fire brigades
Fire spotting services at Mt Rouse and Mt Warrnambool
Maintenance of emergency fire equipment
28 Moyne Shire Budget 2016-17
Program: Environmental Management
Program Description
This service promotes environmentally sustainable development principles, coordinates and implements environmental projects and works with other services to improve Council’s environmental performance.
Expenditure: $534,015
Income: $63,347
Net Surplus/(Deficit): ($470,668)
Key Program Activities
Council reserves - management and maintenance
Weed management on Council managed land (including roadsides)
East Beach coastal engineering studies and associated works
Sustainability initiatives
Policy and strategy development
Referral responses to internal and external information requests
Provision of advice and support to the public and community groups
Lobbying, advocacy, promotion and education regarding sustainable practices
Program: Waste Management
Program Description
This service provides kerbside rubbish, recyclable materials and green waste from residential and commercial properties in the designated collection districts. The service also manages the waste transfer stations and landfills throughout the Shire.
Expenditure: $2,610,086
Income: $3,044,800
Net Surplus/(Deficit): $434,714
Key Program Activities
Manage the shire’s residential and commercial kerbside collections
Manage the shires waste transfer stations and landfill.
Oversee a range of waste resource recovery services
Partner with Regional Waste Reduction Group to implement regional waste reduction programs.
Maintain and monitor the Shire’s closed landfills.
Promotion and education on sustainable waste management practices
Program: Statutory & Strategic Planning
Program Description
This service maintains Councils role under the Planning and Environment Act 1987 as a Responsible Authority, including dealing with planning permit applications and enforcement of the Shire Planning Scheme. Provides advisory service to residents and developers in regards to heritage matters in the built environment. This service also provides strategic planning and economic development functions including policy and scheme development and review, as well as liaison with major project developers
Expenditure: $1,418,993
Income: $178,000
Net Surplus/(Deficit):
($1,240,993)
29 Moyne Shire Budget 2016-17
Key Program Activities
Development Approvals, permit application decisions, planning applications and subdivision applications.
Enforcement of planning scheme
Developer and community education.
Advise Council in relation to its role as Responsible Authority
Forward planning policies and programs,
VCAT Hearings
Provision of Heritage Advisory Service Forward planning policies and programs,
Major development proposals
Amendments to the planning scheme
Developing and implementing sustainable economic development programs for the Moyne Shire Council that supports local enterprise and employment
Major Initiatives
Port Fairy Coastal and Structure Planning Project – ($580,000 net cost)
Initiatives
Roll-out of new regulatory signs e.g. dogs on leashes. ($Nil net cost)
C61 – Amendment to Moyne Planning Scheme Mortlake Heritage Amendment – ($28,000 net cost)
C48 – Amendment to Moyne Planning Scheme – Rural Housing and Settlement Strategy and Land Capability and Biodiversity Strategy ($20,000 net cost)
Review of Roadside Conservation and Weed Management Plan. ($30,000 net cost)
Kerbside waste collection review and new contract. ($Nil net cost)
Implementation of new transfer station arrangements. ($Nil net cost)
Service Performance Outcome Indicators
Service Indicator Performance Measure Computation
Statutory planning
Decision making
Council planning decisions upheld at VCAT (Percentage of planning application decisions subject to review by VCAT and that were not set aside)
[Number of VCAT decisions that upheld Council’s decision in relation to a planning application / Number of decisions in relation to planning applications subject to review by VCAT] x100
Waste collection
Waste diversion
Kerbside collection waste diverted from landfill (Percentage of garbage, recyclables and green organics collected from kerbside bins that is diverted from landfill)
[Weight of recyclables and green organics collected from kerbside bins / Weight of garbage, recyclables and green organics collected from kerbside bins] x100
Animal Management
Health and safety
Animal management prosecutions (Number of successful animal management prosecutions)
Number of successful animal management prosecutions
30 Moyne Shire Budget 2016-17
Service Indicator Performance Measure Computation
Food safety
Health and safety
Critical and major non-compliance notifications (Percentage of critical and major non-compliance notifications that are followed up by Council)
[Number of critical non-compliance notifications and major non-compliance notifications about a food premises followed up / Number of critical non-compliance notifications and major non-compliance notifications about food premises] x100
31 Moyne Shire Budget 2016-17
Key Result Area 4 – Community and Corporate Support Strategic Objective
Enhance the quality of resident’s lives by facilitating and encouraging healthy lifestyles, a community in which it is safe to live and an environment that is diverse and sustainable.
To achieve our objective of strengthening the health and social well-being of the residents of the Shire, we will continue to plan, deliver and improve high quality, cost effective, accessible and responsive services.
Services The services, activities, initiatives, major initiatives and service performance indicators for each service category are described below.
Program: Community Support
Program Description
This service combines a wide range of programs and services, which provide the opportunity for the community to participate in a variety of cultural, health, education, and leisure activities, which contribute to the general well-being towards the community.
Expenditure: $710,368
Income: $269,500
Net Surplus/(Deficit): ($440,868)
Key Program Activities
Compliance with statutory obligations
Preparation of Council reports
Policy review
Oversee financial management
Administrative operation of Directorate
Delivery on Council Plan
Management of people & culture
Project delivery
Continuous Improvement
Scholarship coordination
Provision of Australia Day ceremonial activities
Coordination of citizenship ceremonies
Delivery of actions associated with Health and Wellbeing
Promotion of healthy lifestyle and well-being activities
32 Moyne Shire Budget 2016-17
Program: Child Care Services
Program Description
Provide occasional care through Hawkesdale and District Family Services Centre and long day care services at Port Fairy.
Expenditure: $1,308,685
Income: $1,069,476
Net Surplus/(Deficit): ($239,209)
Key Program Activities
Provision of Long day care at the Port Fairy Community Services Centre
Provision of occasional child care at Hawkesdale on Mondays, Tuesdays and Thursdays
Provision of occasional child care at Chatsworth on Tuesdays and Thursdays
Program: Kindergartens & Preschools
Program Description
Group employer for kindergarten centres at Koroit, Merri, Macarthur, Hawkesdale, Port Fairy and Nullawarre and provides support for the pre-school at Mortlake. Support is also provided for pre-school and kinder committees. Council is the cluster manager.
Expenditure: $1,246,226
Income: $1,035,979
Net Surplus/(Deficit): ($210,247)
Key Program Activities
A universal early childhood program, funded by the State Government on a per capita basis, for children in the year prior to commencing primary school. Children attending kindergarten receive a planned, developmentally appropriate program delivered by a qualified early childhood educator.
Moyne Shire Council is Cluster Manager of the following services: Koroit, Merri, Nullawarre, Macarthur, Hawkesdale
Provision of Kindergarten in Port Fairy at the Port Fairy Community Services Centre.
Program: Maternal and Child Health
Program Description
This service conducts sessions at Port Fairy, Koroit, Hawkesdale, Macarthur, Younger Ross Centre, Yambuk and Mortlake providing immunisation advice, guidance and promotion and health care for infants as well as education for their parents.
Expenditure: $467,860
Income: $184,050
Net Surplus/(Deficit): ($283,810)
Key Program Activities
The universal MCH Service delivers a free, universally accessible service for all families with children from birth to school age. Through the provision of ten “Key Age and Stage” visits, the Service supports families and their children with an emphasis on parenting, prevention and health promotion, developmental assessment, early detection and referral and social support.
The MCH Service also provides support to children and families in the provision of additional consultations, telephone support and parenting support groups.
The Enhanced MCH Service responds assertively to the needs of children and families at risk of poor outcomes, in particular where there are multiple risk factors. It provides a more intensive level of support in a variety of settings, such as the family’s home, MCH centre or
33 Moyne Shire Budget 2016-17
another location within the community.
Immunisation Services.
Program: Aged and Disability Services
Program Description
Provide aged care services including domestic assistance, personal care, respite, garden & property maintenance, meals on wheels, some transport and social support.
Expenditure: $2,041,865
Income: $1,592,296
Net Surplus/(Deficit): ($449,569)
Key Program Activities
Home and Community Care (HACC) is a service that is funded primarily by the State Government under the banner of Department of Health, It provides services to maintain residents of the Moyne Shire in their homes for as long as possible. Council provides
13,712 hours of homecare,
7,236 hours of personal care,
3,832 hours of respite,
2,420 hours of home & garden maintenance.
Community transport and social support.
Deliver approximately 12,200 meals across the whole of the shire. In delivering all these services we cover in excess of 165,000 kilometres.
Program: Aged Support Services
Program Description
This service provides a range of support for senior citizen clubs. Each conducts a program involving recreation, fitness, centre-based meals and social support. This service also provides planned activity groups (PAGs) and respite care for those frail ages or for those with a disability.
Expenditure: $145,166
Income: $71,492
Net Surplus/(Deficit): ($73,674)
Key Program Activities
High needs clients 6 every Tuesday from 9.30 – 1.30pm
Core (lower needs) clients 15 every Thursday from 10.00am – 3.00pm
Men’s group every second Wednesday from 10.00 – 2.00pm
Operation of four Senior Citizen facilities
Annual Senior Citizens week activity
34 Moyne Shire Budget 2016-17
Program: Corporate Business
Program Description
Provides management and administrative support service for the Shire Caravan parks, Port of Port Fairy, Festivals and Tourism.
Expenditure: $309,007
Income: $962,611
Net Surplus/(Deficit): $653,604
Key Program Activities
Management of Council Business Enterprise staff and contractors
Finance control of unit activities
Preparation of Council reports
Policy review
Prepare funding applications & acquittals
Project management
Port Fairy Aerodrome - maintenance
Shire Marquee – bookings
Customer enquiries
Event application coordination
Business & Tourism Committee meetings
Program: Caravan Parks
Program Description
Operation and management of caravan parks at Port Fairy Gardens, Southcombe Park, Killarney, Koroit, Mortlake, Peterborough and Yambuk. Also includes operation of Southcombe Lodge. Major caravan parks return a dividend of 33% to general revenue.
Expenditure: $3,144,519
Income: $3,212,660
Net Surplus/(Deficit): $68,141
Key Program Activities
GCP & SCP accommodating approx. 135,000 persons, per annum.
Management of site and cabin bookings – customer service
Park conditions of entry – enforce compliance
Maintain surrounds (mowing, gardens)
Cleaning of facilities (amenities and camp kitchens)
Project management of park improvements
Minor maintenance of facilities
Management of contracts for the operation of Killarney Beach Camping Reserve, Koroit / Tower Hill Caravan Park, Mortlake Caravan Park, Yambuk Caravan Park and Lease of the Great Ocean Road Tourist Park – Peterborough
35 Moyne Shire Budget 2016-17
Program: Tourism
Program Description
This service operates the Port Fairy Visitor Information Centre and also undertakes event promotion, souvenir sales and support for local tourism. Also Provides support for festivals and administration of the Festivals Support Fund.
Expenditure: $524,389
Income: $43,550
Net Surplus/(Deficit): ($480,839)
Key Program Activities
Festivals & Events
Support provided to local community Festivals & Events ($110,000 festival funding and officer advice and support)
Summer Cinema Program - provision of movies at Reardon Theatre / Village Green from Boxing Day to Australia Day
Tourism Services
Operation of the Port Fairy & Region Visitor Information Centre – local tourism advisory service. (30 volunteers)
Visitor Information Centre services approx. 70,000 + visitors per annum.
Provision of visitor information
Promoting events
Souvenir sales
Promotion & Marketing
Support for the tourism industry in Moyne ( Regional Tourism Board, Victorian Industry Council and in-house tourism marketing services – website promotion & maintenance, tourism newsletters and general tourism promotion of townships and events across the Shire)
Program: Port of Port Fairy
Program Description
This service includes the management of operations and maintenance of the Port of Port Fairy who manage administration, navigation, vessel berthing, slipways and leisure activities around the port. The Port Board provides direction for the development and operation of the Port.
Expenditure: $3,013,374
Income: $2,137,252
Net Surplus/(Deficit): ($876,122)
Key Program Activities
Port administration
Navigation aides maintenance
Management of berths allocations (14 commercial & 56 recreational)
Visiting itinerant boat – berth and amenities facilities
Maintain public boat ramp
Slipway services
Wharf and marina maintenance
Training walls maintenance
Dredging of the river channel
Diesel refuelling facility
Department of Transport Management Agreement reporting
Port Board meetings
Lifeboat committee meetings
36 Moyne Shire Budget 2016-17
Major Initiatives
Redevelopment of wharf-side building for new restaurant and fish-sales premises. ($925,000 million net cost).
Initiatives
Economic Development Small Business Workshop events ($12,000 net cost).
Service Performance Outcome Indicators
Service Indicator Performance Measure Computation
Home and Community Care
Participation
Participation in HACC service (Percentage of the municipal target population that receive a HACC service)
[Number of people that received a HACC service / Municipal target population for HACC services] x100
Participation in HACC service by CALD people (Percentage of the municipal target population in relation to CALD people that receive a HACC service)
[Number of CALD people who receive a HACC service / Municipal target population in relation to CALD people for HACC services] x100
Maternal and Child Health
Participation Participation in MCH key ages and stages visits (Percentage of children attending the MCH key ages and stages visits)
[Number of actual MCH visits / Number of expected MCH visits] x100
Participation in MCH key ages and stages visits by Aboriginal children (Percentage of Aboriginal children attending the MCH key ages and stages visits)
[Number of actual MCH visits for Aboriginal children / Number of expected MCH visits for Aboriginal children] x100
37 Moyne Shire Budget 2016-17
Performance Statement The service performance indicators detailed in the preceding pages will be reported on within the Performance Statement which is prepared at the end of the year as required by section 132 of the Act and included in the 2016-17 Annual Report. The Performance Statement will also include reporting on prescribed indicators of financial performance (outlined in section 8) and sustainable capacity, which are not included in this budget report. The full set of prescribed performance indicators are audited each year by the Victorian Auditor General who issues an audit opinion on the Performance Statement. The major initiatives detailed in the preceding pages will be reported in the Annual Report in the form of a statement of progress in the report of operations. Reconciliation of the Key Result Areas with budgeted operating result
Key Result Area Net Surplus/(Deficit) $
Expenditure $
Income $
Governance 981,195 5,727,620 6,708,815
Physical Services (10,205,283) 23,669,040 13,463,757
Sustainable Development and Planning (3,005,290) 6,666,487 3,661,197
Community and Corporate Support (2,332,593) 12,911,459 10,578,866
(14,561,971) 48,974,606 34,412,635
Rates 17,888,068
Capital Grants and Contributions 1,560,000
Total Funding Sources 19,448,068
Surplus for the year 4,886,097
Note: The income and expenditure in this section are based on the Activity Based Costing (ABC) model and include inter-unit transfers.
38 Moyne Shire Budget 2016-17
3 Financial Statements
This section presents information in regard to the Budgeted Financial Statements and Statement of Human Resources. The budget information for the years 2016-17 to 2019-20 has been extracted from the Strategic Resource Plan. The section includes the following budgeted information:
Comprehensive Income Statement
Balance Sheet
Statement of Changes in Equity
Statement of Cash Flows
Statement of Capital Works
Statement of Human Resources.
39 Moyne Shire Budget 2016-17
Moyne Shire Council Comprehensive Income Statement
For the four years ending 30 June 2020
Forecast Strategic Resource Plan
Actual Budget Projections
2015/16 2016/17 2017/18 2018/19 2019/20
$'000 $'000 $'000 $'000 $'000
Income
Rates and charges 20,069 20,690 20,570 20,872 21,197
User fees and fines 9,934 8,644 8,863 8,889 9,112
Grants - operating 11,759 17,914 12,289 12,245 12,245
Grants - capital 2,283 1,090 2,186 1,871 2,108
Contributions - operating 212 148 148 148 148 Contributions - capital 565 470 Net gain/(loss) on disposal of property, infrastructure, plant and equipment (78) - - - -
Other income 460 460 456 500 500
Total income 45,204 49,416 44,512 44,525 45,310
Expenses
Employee benefits 16,370 16,094 16,261 16,430 16,600
Materials and services 16,472 15,653 13,647 13,375 13,719
Depreciation and amortisation 12,387 12,662 13,050 13,092 13,125
Borrowing costs 152 121 92 64 35
Total expenses 45,381 44,530 43,050 42,961 43,479
Surplus (deficit) for the year (177) 4,886 1,462 1,564 1,831
40 Moyne Shire Budget 2016-17
Moyne Shire Council
Balance Sheet
For the four years ending 30 June 2020
Forecast Strategic Resource Plan
Actual Budget Projections
2015/16 2016/17 2017/18 2018/19 2019/20
$'000 $'000 $'000 $'000 $'000
Current assets
Cash and cash equivalents 7,222 6,407 6,045 5,796 5,776
Trade and other receivables 2,607 2,620 2,617 2,626 2,636
Inventories 488 488 488 488 488
Other assets 195 195 194 203 203
Total current assets 10,512 9,710 9,344 9,113 9,103
Non-current assets
Trade and other receivables 3 3 3 3 3
Investment in associates 215 215 215 215 215 Property, infrastructure, plant & equipment 443,451 448,726 450,237 451,692 452,819
Total non-current assets 443,669 448,944 450,455 451,910 453,037
Total assets 454,181 458,654 459,799 461,023 462,140
Current liabilities
Trade and other payables 2,433 2,434 2,434 2,434 2,434
Trust funds and deposits 352 352 352 352 352
Provisions 5,279 5,424 5,573 5,726 5,884 Interest bearing loans and borrowings 571 479 506 536 245
Total current liabilities 8,635 8,689 8,865 9,048 8,915
Non-current liabilities
Provisions 873 885 898 911 575 Interest bearing loans and borrowings 1,766 1,287 781 245 -
Total non-current liabilities 2,639 2,172 1,679 1,156 575
Total liabilities 11,274 10,861 10,544 10,204 9,490
Net assets 442,907 447,793 449,255 450,819 452,650
Equity
Accumulated surplus 209,365 214,192 215,204 216,215 217,353
Reserves 233,542 233,601 234,051 234,604 235,297
Total equity 442,907 447,793 449,255 450,819 452,650
41 Moyne Shire Budget 2016-17
Statement of Changes in Equity
For the four years ending 30 June 2020
Total
Accumulated Surplus
Revaluation Reserve
Other Reserves
$’000 $’000 $’000 $’000
2017
Balance at beginning of the financial year 442,907 209,365 230,120 3,422
Surplus/(deficit) for the year 4,886 4,886 0 0
Transfer to reserves 0 (59) 0 59
Balance at end of the financial year 447,793 214,192 230,120 3,481
2018
Balance at beginning of the financial year 447,793 214,192 230,120 3,481
Comprehensive result 1,462 1,462 0 0
Transfer to reserves 0 (450) 0 450
Balance at end of the financial year 449,255 215,204 230,120 3,931
2019
Balance at beginning of the financial year 449,255 215,204 230,120 3,931
Comprehensive result 1,564 1,564 0 0
Transfer to reserves 0 (553) 0 553
Balance at end of the financial year 450,819 216,215 230,120 4,484
2020
Balance at beginning of the financial year 450,819 216,215 230,120 4,484
Comprehensive result 1,831 1,831 0 0
Transfer to reserves 0 (694) 0 694
Balance at end of the financial year 452,650 217,352 230,120 5,178
42 Moyne Shire Budget 2016-17
Moyne Shire Council
Statement of Cash Flows For the four years ending 30 June 2020
2015/16 2016/17 2017/18 2018/19 2019/20
$'000 $'000 $'000 $'000 $'000
Inflows Inflows Inflows Inflows Inflows
(Outflows
) (Outflows
) (Outflows
) (Outflows
) (Outflows
)
Cash flows from operating activities
Receipts
General rates and charges 20,469 20,671 20,574 20,863 21,188
User fees & fines 9,770 8,644 8,863 8,889 9,112
Operating grants 11,759 17,914 12,289 12,245 12,245
Capital grants 2,283 1,090 2,186 1,871 2,108
Contributions 777 618 148 148 148
Interest 433 460 456 491 500
45,491 49,397 44,516 44,507 45,301
Payments
Employee costs (16,097) (15,936) (16,099) (16,264) (16,429)
Materials and contracts (16,912) (15,653) (13,647) (13,375) (14,069)
(33,009) (31,589) (29,746) (29,639) (30,498)
Net cash provided by operating activities 12,482 17,808 14,770 14,868 14,803
Cash flows from investing activities Payments for property, plant and equipment (20,896) (18,261) (14,957) (14,919) (14,586) Proceeds from sale of property, plant and equipment 1,187 324 396 372 334
Repayment of loans and advances 138 6 0 0 0
Net cash used in investing activities (19,571) (17,931) (14,561) (14,547) (14,252)
Cash flows from financing activities
Finance costs (153) (121) (92) (64) (35)
Proceeds from borrowings 0 0 0 0 0
Repayment of borrowings (560) (571) (479) (506) (536)
Net cash provided by (used in) financing activities (713) (692) (571) (570) (571)
Net increase (decrease) in cash & cash equivalents (7,802) (815) (362) (249) (20) Cash & cash equivalents at the beginning of the year 15,024 7,222 6,407 6,045 5,796
Cash & cash equivalents at end of year 7,222 6,407 6,045 5,796 5,776
43 Moyne Shire Budget 2016-17
Moyne Shire Council Statement of Capital Works
For the four years ending 30 June 2020
Forecast Strategic Resource Plan Actual Budget Projections
2015/16 2016/17 2017/18 2018/19 2019/20 $'000 $'000 $'000 $'000 $'000
Capital works areas
Property
Buildings 3,170 2,125 1,982 2,513 2,681
Land & Natural Assets 610 113 440 155 575
Total Property 3,780 2,238 2,422 2,668 3,256
Plant and Equipment
IT Equipment & Furniture 207 131 145 255 155
Plant 1,852 1,422 1,841 1,459 1,571
Total Plant and Equipment 2,059 1,553 1,986 1,714 1,726
Infrastructure
Bridges 1,145 1,110 1,100 560 576
Drainage 498 372 374 382 378
Footpaths 372 410 250 250 250
Recreation 626 585 896 1,057 285
Roads 12,070 11,929 7,748 7,773 7,648
Waste Facilities 346 65 181 516 467
Total Infrastructure 15,057 14,471 10,549 10,538 9,604
Total capital works 20,896 18,262 14,957 14,920 14,586
Represented by:
New Asset Expenditure 2,076 439
Asset Renewal Expenditure 14,881 13,835 12,319 12,290 12,149
Asset Upgrade/Expansion Expenditure
3,939 3,988 2,638 2,630 2,437
Total capital works 20,896 18,262 14,957 14,920 14,586
44 Moyne Shire Budget 2016-17
Moyne Shire Council
Statement of Human Resources
For the four years ending 30 June 2020
Forecast Actual Budget Strategic Resource Plan
Projections
2015/16 2016/17 2017/18 2018/19 2019/20
$’000 $’000 $’000 $’000 $’000
Staff expenditure
Employee costs - operating 16,370 16,094 16,261 16,430 16,600
Total staff expenditure 16,370 16,094 16,261 16,430 16,600
EFT EFT EFT EFT EFT
Staff numbers
Employees 242.5 233.6 233.6 233.6 233.6
Total staff numbers 242.5 233.6 233.6 233.6 233.6
A summary of the number of full time equivalent (FTE) Council staff by directorate is provided below.
Directorate
Budget 2016-17
FTE
Permanent Full Time
Permanent Part Time
Community & Corporate Services 85.84 43.00 42.84 Governance & Leadership 2.52 2.00 0.52 Sustainable Development 28.16 19.00 9.16 Infrastructure & Assets 108.16 99.00 9.16 Total permanent staff 224.67 163.00 61.67 Casuals and other 8.93 Total staff 233.60
Casual staff are employed at several work sites including caravan parks, fire spotting towers and customer service.
45 Moyne Shire Budget 2016-17
4 Financial Performance Indicators
The following table highlights Council’s current and projected performance across a range of key financial performance indicators. These indicators provide a useful analysis of Council’s financial position and performance and should be used in the context of the organisation’s objectives.
Forecast Strategic Resource Plan
Projections
Indicator Measure Actual Budget Projections Trend
2015/16 2016/17 2017/18 2018/19 2019/20 +/o/-
Operating position
Adjusted underlying result
Adjusted underlying surplus (deficit) / Adjusted underlying revenue
-7.1% 7.0% -1.7% -0.7% -0.6% +
Liquidity
Working Capital Current assets / current liabilities
122% 112% 105% 101% 102% -
Unrestricted cash
Unrestricted cash / current liabilities
44.0% 33.7% 23.8% 14.5% 6.7% -
Obligations
Loans and borrowings
Interest bearing loans and borrowings / rate revenue
11.6% 8.5% 6.3% 3.7% 1.2% +
Loans and borrowings
Interest and principal repayments / rate revenue
3.6% 3.3% 2.8% 2.7% 2.7% +
Indebtedness Non-current liabilities / own source revenue
8.7% 7.3% 5.6% 3.8% 1.9% +
Asset renewal Asset renewal expenditure / depreciation
120.1% 109.3% 94.4% 93.9% 92.6% -
Stability
Rates concentration
Rate revenue / adjusted underlying revenue
47.3% 43.2% 48.6% 48.9% 49.1% o
Rates effort Rate revenue / property values (CIV)
0.3% 0.3% 0.3% 0.3% 0.3% o
Efficiency
Expenditure level
Total expenditure / no. of assessments
$3,812 $3,709 $3,556 $3,520 $3,533 o
Revenue level Residential rate revenue / No. of residential assessments
829 839 851 868 886 +
Workforce turnover
No. of resignations & terminations / average no. of staff
10.0% 10.0% 10.0% 10.0% 10.0% o
Key to Forecast Trend: + Forecasts improvement in Council's financial performance/financial position indicator o Forecasts that Council's financial performance/financial position indicator will be steady - Forecasts deterioration in Council's financial performance/financial position indicator
46 Moyne Shire Budget 2016-17
Notes to Indicators
1 Underlying result – An indicator of the sustainable operating result required to enable Council to continue to provide core services and meet its objectives. Improvement in financial performance expected over the three-year period ending 2019-2020, although continued losses means reliance on Council's cash reserves or increased debt to maintain services. 2 Working Capital – The ratio expresses the level of current assets the Council has available to meet its current liabilities. Working capital is forecast to decrease to 102% by 2019-2020. This will be closely monitored to ensure liquidity does not fall below 100%. It is essential that Council has sufficient liquid funds in order to meet its day to day obligations. 3 Debt compared to rates - Trend indicates Council's reducing reliance on debt against its annual rate revenue through redemption of long term debt. 4 Asset renewal - This percentage indicates the extent of Council's renewals against its depreciation charge (an indication of the decline in value of its existing capital assets). A percentage greater than 100 indicates Council is maintaining its existing assets, while a percentage less than 100 means its assets are deteriorating faster than they are being renewed and future capital expenditure will be required to renew assets. 5 Rates concentration - Reflects extent of reliance on rate revenues to fund Council's on-going services. Trend indicates Council will become more reliant on rate revenue compared to all other revenue sources
47 Moyne Shire Budget 2016-17
5 Other budget information This section presents other budget related information required by the Regulations This section includes the following statements and reports: 5.1.1 Grants operating 5.1.2 Grants capital 5.2 Statement of borrowings
48 Moyne Shire Budget 2016-17
5.1.1 Grants - operating ($6.1 million increase) Operating grants include all monies received from State and Federal sources for the purposes of funding the delivery of Council’s services. Overall, the level of grants has increased compared with 2015-16 primarily due to the timing in receipt of the Victorian Grants Commission allocation ($3.6 million). Other significant increases include the additional Roads to Recovery funding of $0.8 million and a non-recurrent grant for the Port of Port Fairy wharf development of $1.4 million. A list of operating grants by type, classified into recurrent and non-recurrent, is included below.
Forecast Actual Budget Variance Grant Funding Types 2015/16 2016/17 $'000 $'000 $'000 Recurrent Victorian Grants Commission > General Purposes 1,836 3,697 1,861 > Local Roads 1,904 3,720 1,816 Federal Roads to Recovery 5,202 6,007 805
Home and Community Care (Dept. Human Services) 988 1,000 12 Kindergartens (Education and Early Childhood Development) 790 962 172 Maternal & Child Health 173 174 1 Port of Port Fairy 408 408 0 Emergency Management 60 60 - Other 306 460 154 Non-recurrent Environmental Management 32 - (32) Recreation & Leisure 60 - (60) Port of Port Fairy - 1,425 1,425 Total Operating Grants 11,759 17,914 6,155
5.1.2 Capital grants ($1.2 million decrease) Capital grants include all monies to be received from State and Federal governments and community sources for the purposes of funding the capital works program. Overall the level of grants has decreased by $1.2 million compared to 2015-16 due mainly to specific funding for some significant building capital works projects in 2015-16. A list of capital grants by type is included below.
Forecast Actual Budget Variance Grant Funding Types 2015/16 2016/17 $'000 $'000 $'000 Non-recurrent Buildings 1,487 500 (987) Bridges 500 500 - Streetscapes 140 - (140) Other 156 90 (66) Total Capital Grants 2,283 1,090 (1,193)
49 Moyne Shire Budget 2016-17
5.2 Statement of Borrowings This table below shows information on borrowings specifically required by the regulations Statement of Borrowings 2015/16 2016/17
$ $
Total amount borrowed as at 30 June of the prior year 2,896,921 2,336,670
Total amount to be borrowed - -
Total amount projected to be redeemed 560,251 570,531
Total amount outstanding as at 30 June 2,336,670 1,766,139
50 Moyne Shire Budget 2016-17
6 Detailed list of capital works
This section lists the new programs for 2016-17:
Capital Works and Non-recurrent Projects
Building Renewal Program
51 Moyne Shire Budget 2016-17
Capital Works Area/Non-recurrent operating projects
Project cost
$
New $
Expansion $
Renewal $
Upgrade $
Grants $
Contributions $
Asset Sales
$
Net Cost to
Council $
Bridges
Capital and Periodic works on bridges 1,110,000
777,000 333,000 (500,000)
610,000
Bridges Total 1,110,000
777,000 333,000 (500,000)
610,000
Buildings
Accessible toilets for the Mortlake Bowls Club 60,000
30,000 30,000
60,000
Buildings Renewal 269,000
269,000
269,000
Extension of office area at Koroit depot for works manager and support staff 85,000
85,000
85,000
Installation of ventilation in Reardon Theatre 25,000
25,000
25,000
Plans for Hall Cluster 4 projects 30,000
30,000
30,000
Rebuilding of the Mortlake Library and Information Centre as one facility 750,000
600,000 150,000 (500,000)
250,000
Recladding and painting of exterior of Mailors Flat Hall 16,000
16,000
16,000
Renewal and upgrade works at the Woorndoo Rec Reserve Toilets 120,000
50,000 70,000
120,000
Repairs to the wall at Macarthur hall that is exposed to weather 20,000
20,000
20,000
Water tanks for Killarney and Yambuk Caravan Parks 20,000
20,000
20,000
Renewal works at entrance, toilets and changerooms at Hawkesdale Swimming Pool 51,300
51,300
51,300
Port Fairy Surf Lifesaving Club Extension-training room and administration area 512,000
512,000
(412,000)
100,000
Provide accessible toilet and disabled access to the Wangoom Rec Reserve 115,000
115,000
(28,000)
87,000
Yambuk Public Toilet Upgrade 35,000
20,000 15,000
35,000
Buildings Total 2,108,300
597,000 1,106,300 405,000 (500,000) (440,000)
1,168,300
52 Moyne Shire Budget 2016-17
Capital Works Area/Non-recurrent operating projects
Project cost
$
New $
Expansion $
Renewal $
Upgrade $
Grants $
Contributions $
Asset Sales
$
Net Cost to
Council $
Drainage
Drainage works including planned and reactive works 372,000
186,000 186,000
372,000 Drainage Total
372,000
186,000 186,000
372,000
Footpaths
Footpath along Powling Street from Polding St to Ocean Dve 110,000 110,000
110,000
Renewal of Footpaths identified for renewal 230,000
230,000
230,000
Footpath to link new estate area with existing footpath in Cudgee 70,000 70,000
70,000 Footpaths Total
410,000 180,000
230,000
410,000
IT Equipment
Replace Furniture and Fittings - Council Offices and Depots 15,000
15,000
15,000
VMWare Software Licencing, UPS and Switch renewal and replacement of IT equipment as required. 116,000
116,000
116,000 IT Equipment Total
131,000
131,000
131,000
Land & Natural Assets
Renewal of bollards along the Peterborough Foreshore area 10,500
10,500
10,500
Port Fairy Community House boundary Fence Renewal 6,500
6,500
6,500
Automatic sprinkler system for Mortlake Market Square 36,000 36,000
36,000 Land & Natural Assets Total
53,000 36,000
17,000
53,000
Other Structures
Street and Park Furniture Replacement 25,000
25,000
25,000
Renewal of Township entrance signage 20,000
20,000
20,000
53 Moyne Shire Budget 2016-17
Capital Works Area/Non-recurrent operating projects
Project cost
$
New $
Expansion $
Renewal $
Upgrade $
Grants $
Contributions $
Asset Sales
$
Net Cost to
Council $
BBQ shelter at Rest stop on Hamilton Hwy, Hexham 20,000 20,000
(10,000)
10,000 Other Structures Total
65,000 20,000
45,000
(10,000)
55,000
Plant
Major Plant purchases 721,000
721,000
(93,000)
628,000
Minor Plant purchases 65,000
65,000
(5,000)
60,000
Purchase of motor vehicles and utes 600,000
600,000
(226,000)
374,000
Plant Total 1,386,000
1,386,000
(324,000)
1,062,000 Playgrounds
Renewal of Playground at Yambuk Lake 25,000
25,000
25,000
Shade structure to cover 1/2 of Mortlake Playground at Market Square 20,000
20,000
20,000
Koroit Skate Park and facilities ($60k from Subdivision Reserve) 170,000 170,000
(80,000) (30,000)
60,000
Renewal of the Playground in Elizabeth Street Port Fairy ($50k from Subdivision Reserve) 50,000
50,000
50,000 Playgrounds Total
265,000 170,000
75,000 20,000 (80,000) (30,000)
155,000
Recreation
Renewal of supply and return lines and gutters at Mortlake Swimming Pool 250,000
250,000
250,000
Sealing of the area in front of the changerooms at Victoria Park 20,000
20,000
20,000
Sealing of the road and car park area at DC Farran Oval 20,000
20,000
20,000 Recreation Total
290,000
250,000 40,000
290,000
Roads
Drainage works on sealed and unsealed roads 100,000
100,000
100,000
Gravel Road re-sheets 780,000
780,000
780,000
54 Moyne Shire Budget 2016-17
Capital Works Area/Non-recurrent operating projects
Project cost
$
New $
Expansion $
Renewal $
Upgrade $
Grants $
Contributions $
Asset Sales
$
Net Cost to
Council $
Improvement works to identified intersections 277,000
138,500 138,500
277,000
Replacement of statutory and information signage 50,000
50,000
50,000
Reseal Program 1,662,590
1,662,590
1,662,590
Road Rehabilitation program 8,967,150
6,727,150 2,240,000
8,967,150
Roads Total 11,836,740
9,458,240 2,378,500
11,836,740
Waste
Mobile Bin Replacement 15,000
15,000
15,000
Upgrade to ramp and fencing at Woolsthorpe Transfer Station 50,000
25,000 25,000
50,000 Waste Total
65,000
40,000 25,000
65,000
Caravan Parks
GCP - Additional light poles and lights 18,000 18,000
18,000
GCP - Bourne Ave boom gate 6,000
6,000
6,000
GCP - Creative carving of old cypress pine stumps 10,000 10,000
10,000
GCP - General repairs to cabins 10,000
10,000
10,000
GCP - Powerhead replacement 10,000
10,000
10,000
GCP - Repairs to road network 5,000
5,000
5,000
GCP - Replace switchboard at Bourne Ave entrance 25,000
25,000
25,000
GCP - Tree maintenance 5,000
5,000
5,000
SCL - Replace safety switches at the Lodge 2,000
2,000
2,000
SCP - Additional lighting to make the park safer at night. 5,000 5,000
5,000
SCP - Boom gate motor 5,000
5,000
5,000
55 Moyne Shire Budget 2016-17
Capital Works Area/Non-recurrent operating projects
Project cost
$
New $
Expansion $
Renewal $
Upgrade $
Grants $
Contributions $
Asset Sales
$
Net Cost to
Council $
SCP - Maintenance of trees and shrubs throughout the park to mitigate damage from falling limbs 25,000
25,000
25,000
SCP - Re-seal part of road network within caravan park 3,500
3,500
3,500
SCP - Upgrade and renew play equipment 30,000
30,000
30,000
Caravan Parks Total 159,500 33,000
123,000 3,500
159,500
Quarry
Quarry Face Restoration/Trees 5,000
5,000
5,000
Weighbridge/Signage Improvements 5,000
5,000
5,000
Quarry Total 10,000
10,000
10,000
Total capital works 18,261,540 439,000 597,000 13,834,540 3,391,000 (1,090,000) (470,000) (324,000)
16,377,540
Non-Recurrent operating projects
Victoria Park Masterplan 15,000
15,000
A review of the current Tea Tree Lake Masterplan to update actions and identify future priorities 5,000
5,000
To implement the findings of the Moyne Heritage Study into the Moyne Planning Scheme for Mortlake. 28,000
28,000
Workshops, industrial land prospectus, venue expenses for 6 Small Business Victoria events, Business Development program in conjunction with AGL (Macarthur and Hawkesdale region) 12,000
12,000
56 Moyne Shire Budget 2016-17
Capital Works Area/Non-recurrent operating projects
Project cost
$
New $
Expansion $
Renewal $
Upgrade $
Grants $
Contributions $
Asset Sales
$
Net Cost to
Council $
Planning Scheme Amendment C48 is to implement findings of the Rural Housing and Settlement Strategy and Land Capability and Biodiversity Strategy and the 2015 Addendum Report. 20,000
20,000
Comprehensive review and redevelopment of Roadside Conservation Plan to incorporate roadside weed management. 30,000
30,000
Contribution to address Mobile Blackspot in Hawkesdale as requested by local federal member 25,000
25,000
A plan for infrastructure and land use in Nullawarre 15,000
15,000
ICT Strategy 30,000
30,000
Subscription to Remplan for economic and community data and analysis 15,000
15,000
Peterborough Coastal Wattle Planning Scheme Amendment 15,000
15,000
Non-Recurrent Project Total 210,000
210,000
57 Moyne Shire Budget 2016-17
Building Renewal Works 2016-17 Budget
Service Plan initiatives - Public Toilets
Caramut Public Toilets- Renew 100m fence 4,000
Hawkesdale Swimming Pool Public Toilets- Exter Paint 7,000
Macarthur Public Toilets - Internal & External Paint 5,000
Mortlake Market Square Toilets - External repaint 4,000
Mortlake Market Square Toilets - Internal paint 8,000
Nullawarre BBQ Shelter & Public Toilets - External paint 5,000
Peterborough Foreshore Reserve Toilets - External & Int Paint 6,000
Port Fairy East Beach Toilets Ext Int Paint 4,000
Port Fairy East Beach Toilets Roof Renewal 12,000
Port Fairy East Beach Toilets - Epoxy floor coating 10,000
Municipal Offices
Mortlake Municipal Offices - Chamber/Presidents Room dividing door 20,000
Port Fairy Municipal Offices - Offices internal repaint 10,000
Hawkesdale Municipal Offices - External paint 4,000
Libraries
Port Fairy Library - Façade Paint 4,000
Family and Children Services
Macarthur Preschool - Fence replacement 5,000
Mortlake Preschool - Roof Renewal East side 6,000
Community Theatre Facilities
Koroit Theatre - Paint Ext 10,000
Koroit Theatre - Verandah Asbestos Removal and Paint 10,000
Koroit Theatre - Window Renewal 20,000
Port Fairy Reardon Theatre - Kitchen Roof renewal 6,000
Senior Citizens Service
Koroit Senior Citizens Clubrooms - External Paint 4,000
Public Meeting Places
Port Fairy Lecture Hall - Paint Façade 4,000
Recreation Buildings Tennis/ Netball
Macarthur Tennis Clubrooms - Partial reroof 5,000
Willatook Tennis Club/Recreation Reserve Toilets - Fit out 7,000
Recreation Buildings Bowls/Croquet
58 Moyne Shire Budget 2016-17
Building Renewal Works 2016-17 Budget
Macarthur Bowls Clubrooms - Main roof reroof 11,000
Mortlake Bowls Clubrooms - External Paint 5,000
Recreation Buildings- Ovals
Killarney Camping Ground Public Toilets - repaint 4,000
Port Fairy Gardens Oval - Scoreboard - patch & paint 5,000
Port Fairy Gardens Oval - Scoreboard - repair handrail & ballustrade 5,000
Port Fairy Gardens Oval - Netball Fence 10,000
Wangoom Rec Reserve Clubrooms - Reroof 15,000
Recreation - Pools
Macarthur Swimming Pool Filtration Shed - Electrical Storage Area 4,000
Mortlake Swimming Pool - Renew fencing (partial) 5,000
Miscellaneous Community Support - Buildings
Koroit Jacaranda House Clinic - replace two external windows 10,000
Koroit Vic Park Heritage School - External Paint 15,000
Total 269,000
59 Moyne Shire Budget 2016-17
7 Rates and Charges
This section presents information about rates and charges which the Act and the Regulations required to be disclosed in the Council’s annual budget.
60 Moyne Shire Budget 2016-17
7.1 The rate in the dollar to be levied as general rates under Section 158 of the Act for each type or class of land compared with the previous financial year
Type or class of land 2015/16 2016/17
cents/$CIV cents/$CIV Change
General rate for rateable residential properties 0.23108 0.23146 0.16%
General rate for rateable rural properties 0.23108 0.23146 0.16%
General rate for rateable rural lifestyle properties 0.23108 0.23146 0.16%
General rate for rateable commercial properties 0.23108 0.23146 0.16%
General rate for rateable industrial properties 0.23108 0.23146 0.16%
7.2 The estimated total amount to be raised by general rates in relation to each type or class
of land, and the estimated total amount to be raised by general rates, compared with the previous financial year
Type or class of land 2015/16 2016/17
$ $ Change
Residential 3,543,608 3,598,575 1.6%
Rural 7,511,456 7,811,718 4.0%
Rural Lifestyle 1,885,354 1,925,391 2.1%
Commercial 180,278 192,012 6.5%
Industrial 484,931 490,312 1.1%
Total amount to be raised by general rates 13,605,627 14,018,008 3.0%
7.3 The number of assessments in relation to each type or class of land, and the total number of assessments, compared with the previous financial year
Type or class of land 2015/16 2016/17
Number Number Change
Residential 4,172 4,220 1.2% Rural 4,829 4,852 0.5% Rural Lifestyle 2,482 2,508 1.0% Commercial 244 243 -0.4% Industrial 83 83 0.0% Total number of assessments 11,810 11,906 0.8%
7.4 The basis of valuation to be used is the Capital Improved Value (CIV)
7.5 The estimated total value of each type or class of land, and the estimated total value of land, compared with the previous financial year
61 Moyne Shire Budget 2016-17
Type or class of land 2015/16 2016/17 Change
$ $
Residential 1,533,498,560 1,554,728,500 1.4%
Rural 3,250,586,780 3,374,975,500 3.8%
Rural Lifestyle 815,888,140 831,846,000 2.0%
Commercial 78,015,500 82,957,000 6.3%
Industrial 209,854,000 211,834,500 0.9%
Total value of land 5,887,842,980 6,056,341,500 2.9%
7.6 The municipal charge under Section 159 of the Act compared with the previous financial year
Per Rateable
Property Per Rateable
Property
Type of Charge 2015/16 2016/17 Change
$ $
Municipal 243 250 2.9%
7.7 The estimated total amount to be raised by municipal charges compared with the
previous financial year
Type of Charge 2015/16 2016/17 Change
$ $
Municipal 2,287,116 2,382,500 4.2%
7.8 The rate or unit amount to be levied for each type of service rate or charge under Section 162 of the Act compared with the previous financial year
Per Rateable
Property Per Rateable
Property
Type of Charge 2015/16 2016/17 Change
$ $
Kerbside collection service 319.9 327.6 2.4%
State government landfill levy 12.1 12.4 2.5%
Waste facility service charge
- Improved 121 124 2.5%
- Unimproved 31 32 3.2%
62 Moyne Shire Budget 2016-17
7.9 The estimated total amount to be raised by each type of service rate or charge, and the estimated total amount to be raised by service rates and charges, compared with the previous financial year
Type of Charge 2015/16 2016/17 Change
$ $
Kerbside collection service 1,620,933 1,706,468 5.3%
State government landfill levy 61,311 64,592 5.4%
Waste facility service charge 996,818 1,031,410 3.5%
Total 2,679,062 2,802,470 4.6%
7.10 The estimated total amount to be raised by all rates and charges compared with the
previous financial year
2015/16 2016/17 Change
$ $
General rates 13,605,627 14,018,008 3.0%
Municipal charge 2,287,116 2,382,500 4.2%
Service Charges 2,679,062 2,802,470 4.6%
Payments in lieu of rates 1,435,312 1,457,322 1.5%
Rates and charges 20,007,117 20,660,300 3.3%
7.11 Any significant changes that may affect the estimated amounts to be raised by rates and charges
There are no known significant changes which may affect the estimated amounts to be raised by rates and charges. However, the total amount to be raised by rates and charges may be affected by:
The making of supplementary valuations (2016/17: estimated $30,000)
The variation of returned levels of value (e.g. valuation appeals)
Changes in use of land such that rateable land becomes non-rateable land and vice versa
Changes in use of land such that residential land becomes business land and vice versa.
63 Moyne Shire Budget 2016-17
Budget Analysis The following reports provide detailed analysis to support and explain the budget reports in the previous section. This section includes the following analysis and information:
1 Summary of financial position 2 Budget influences 3 Analysis of operating budget 4 Analysis of budgeted cash position 5 Analysis of capital budget 6 Analysis of budgeted financial position 7 Strategic resource plan 8 Summary of other strategies 9 Rating strategy
64 Moyne Shire Budget 2016-17
8 Summary of financial position The executive summary provides key information about the operating result, rate increase, cash and investments, capital works and financial position of Council. The following graphs include 2014-15 Actual (A), 2015-16 Forecast Actual (F), 2016-17 Budget (B) and the next three years as set out in the Strategic Resource Plan (SRP). 1. Operating Result
The expected operating result for the 2016-17 year is a surplus of $4.89 million, which is a increase of $5.06 million from 2015-16. The increase operating result is due mainly to the timing in the Victorian Grants Commission funding ($3.7million) and additional $0.8 million from the Roads to Recovery program. The adjusted underlying result, which excludes items such as non-recurrent capital grants and non-cash contributions is a surplus of $3.3 million.
$12.31 M
-$0.17 M
$4.89 M
$1.46 M $1.56 M $1.83 M
-$1 M$0 M$1 M$2 M$3 M$4 M$5 M$6 M$7 M$8 M$9 M
$10 M$11 M$12 M$13 M
A2014/15 F2015/16 B2016/17 SRP2017/18
SRP2018/19
SRP2019/20
su
rplu
s/d
efi
cit
$M
65 Moyne Shire Budget 2016-17
2. Rates
It is proposed that the average rate increase by 2.5% for the 2016-17 year, raising total rates and charges to $20.69 million, including $1.46 million raised from energy generators. The rates will go toward maintaining service levels and delivering on capital works programs. The rate increase is in line with the rate cap set by the Minister for Local Government. 3. Cash and Investments
Cash and investments are expected to decrease by $0.81 million during the year to $6.41 million as at 30 June 2017. The decrease in cash and investments is in line with Council's Strategic Resource Plan. (Cash and investments are forecast to be $7.22 million as at 30 June 2016).
4.9%
5.8%
2.5% 2.5% 2.5% 2.5%
0%
2%
4%
6%
8%
10%
A2014/15 F2015/16 B2016/17 SRP2017/18
SRP2018/19
SRP2019/20
% R
ate
In
cre
ase
$15.02 M
$7.22 M$6.41 M $6.04 M $5.80 M $5.78 M
$0 M
$2 M
$4 M
$6 M
$8 M
$10 M
$12 M
$14 M
$16 M
A2014/15 F2015/16 B2016/17 SRP2017/18
SRP2018/19
SRP2019/20
cash
on
han
d $
'M
66 Moyne Shire Budget 2016-17
4. Capital Works
The capital works program for the 2016-17 year is budgeted to be $18.26 million. This year's program continues Council’s commitment to renewal works including road infrastructure, building and footpath renewal and ongoing improvements to Council drainage network. The capital works program has been developed according to an extensive selection and prioritisation process. 5. Financial Position
Working Capital Ratio is comparing Current Assets to Current Liabilities and is a measure of Councils’ short term ability to meet its liquidity requirements within the current financial year. The working capital ratio will decrease to 112% as at 30 June 2017. (Working capital is forecast to be 122% as at 30 June 2016).
$16.50 M
$20.90 M
$18.26 M
$14.96 M $14.92 M $14.59 M
$0 M
$4 M
$8 M
$12 M
$16 M
$20 M
$24 M
A2014/15 F2015/16 B2016/17 SRP2017/18
SRP2018/19
SRP2019/20
cap
ital
wo
rks $
M
187%
122%112% 105% 101% 102%
0%
100%
200%
A2014/15 F2015/16 B2016/17 SRP2017/18
SRP2018/19
SRP2019/20
wo
rkin
g c
ap
ital
Rati
o
67 Moyne Shire Budget 2016-17
6. Financial Sustainability
A high level Strategic Resource Plan for the years 2016/17 to 2019/20 has been developed to assist Council in adopting a budget within a longer prudential framework. The key objective of the Plan is financial sustainability in the medium to long term, while still achieving the Council’s strategic objectives as specified in the Council Plan. The adjusted underlying result shows an adjusted underlying surplus of $3.33 million for 2016-17, this includes additional Roads to Recovery program funding in 2016-17. Council is forecasting a reducing underlying deficit for the three-year period ending from 2017-18 to 2019-20.
-$3.02 M
$3.33 M
-$0.72 M -$0.31 M -$0.28 M
-$4 M
-$3 M
-$2 M
-$1 M
$0 M
$1 M
$2 M
$3 M
$4 M
F2015/16 B2016/17 SRP 2017/18 SRP 2018/19 SRP 2019/20
Ad
juste
d u
nd
erl
yin
gsu
rplu
s/-
defi
cit
$M
68 Moyne Shire Budget 2016-17
9 Budget Influences This section sets out the key budget influences arising from the external and internal environment in which the Council operates. 9.1 Snapshot of Moyne Shire
Moyne Shire covers approximately 5,500 sq km of south west Victoria. Some 16,060 people live here. The Shire is characterised by its beautiful coastal and rural landscape, significant agricultural production, a growing tourism industry and an infrastructure of towns connected by an extensive road system. There are nearly 3,300 km of roads and streets. It is home to a wide range of industry including dairy products, fresh fish, pharmaceuticals, manufactured foods, seafood processing, quarrying, transport, health services and education centres. Over 1,000 commercial businesses operate within the Shire. The main townships are Port Fairy, Koroit, Mortlake, Hawkesdale, Macarthur and Peterborough.
69 Moyne Shire Budget 2016-17
Quick Facts:
There are three people per square km
Moyne’s population has increased by 921 since 2001(estimated Resident Population)
Population is 98.5% Anglo Celtic in origin
Unemployment in the district is low – Census data from 2011 indicated an unemployment rate of 3.7%
There are currently just over 5,600 households in the Shire
31% of the workforce are in the agriculture, forestry and fishing industry sector. Tourism, retail, manufacturing, education, construction and health and community services are also significant
Moyne has a strong sense of community
Moyne rates high on the values of feeling safe, feeling valued, opportunity to contribute, inclusiveness, community participation, and local action
Population in Moyne is forecast to grow to almost 17,452 by 2021
Population is expected to continue ageing, around 28% over 60 by 2021, compared to 22% in 2006
Land use
milk accounts for 50% of the value of all agricultural commodities produced
0.8% of land in the Shire is used for timber plantations
Median house prices are expected to continue to rise 9.2 External influences
In preparing the 2016-17 budget, a number of external influences have been taken into consideration, because they are likely to impact significantly on the services delivered by Council in the budget period. These include: Grants
Commonwealth’s decision to pause indexation of the national pool of financial assistance
grants for the three years to the end of 2016-17.
Completion of the Country Roads and bridges funding program of $1 million per annum in
2014-15.
A number of grants are anticipated for capital works, and new initiatives.
Rate Capping
This is the first year of the Fair Go Rates System and Council proposes a rate increase that
is in line with the 2.5 per cent cap.
9.3 Internal influences
Fees and Charges
Non statutory fees will increase by approximately 4% in accordance with the Strategic Resource Plan
Borrowings No new borrowing for 2015-16 and 2016-17.
70 Moyne Shire Budget 2016-17
9.4 Budget principles
Guidelines were prepared and distributed to Council officers with budget responsibilities. These principles included:
Service levels maintained at 2015-16 levels with the emphasis on continuous improvement, productivity, innovation and efficiency.
All discretionary user fees and charges to be increased by 4% or market levels.
New revenue sources to be identified where possible.
Real savings in expenditure and increases in revenue identified during 2015-16 to be preserved.
Service reviews undertaken in 2015-16 to be implemented in 2016-17.
71 Moyne Shire Budget 2016-17
10 Analysis of operating budget This section analyses the operating budget including expected income and expenses of the Council for the 2016-17 year. 10.1 Budgeted Income Statement
Forecast
Actual Budget Variance
2015/16 2016/17
$'000 $'000 $'000 Total revenue
45,204 49,416 4,212
Total expenses
(45,381) (44,530) 851 Surplus (deficit) for the year
(177) 4,886 5,063
Grants - capital
(2,283) (1,090) 1,193 Contributions - capital
(565) (470) 95
Contributions - non-monetary assets
- - - Adjusted underlying surplus(deficit) (3,025) 3,326 6,351
10.1.1 Adjusted underlying surplus The underlying result is the net surplus or deficit for the year adjusted for capital grants, contributions of non-monetary assets and other once-off adjustments. It is a measure of financial sustainability as it is not impacted by non-recurring or once-off items of income and expenses which can often mask the operating result. The underlying result for the 2016-17 year is a surplus of $3.32 million compared to a $3.02 million underlying deficit in the 2015-16 year. The significant variance is due to the timing in the Victorian Grants commission payments, where $3.7 million of the 2015-16 allocation was received in 2014-15, and additional Roads to recovery funding of $0.8 million in 2016-17.
10.2 Income
Income types Ref Forecast
Actual Budget Variance
2015/16 2016/17
$'000 $'000 $'000 Revenues from ordinary activities
Rates & charges 10.2.1 20,069 20,690 621 User fees and fines 10.2.2 9,934 8,644 (1,290) Grants - operating 5.1.1 11,759 17,914 6,155 Grants - capital 5.1.2 2,283 1,090 (1,193) Contributions - operating 10.2.3 212 148 (64) Contributions - capital 10.2.4 565 470 (95) Net gain on sale of assets
(78) - 78
Other revenue 10.2.5 460 460 - Total operating revenue 45,204 49,416 4,212
72 Moyne Shire Budget 2016-17
Source: Appendix A 10.2.1 Rates and charges ($0.62 million increase) It is proposed that the total to be derived from rates and charges will increase from $20.07 million in 2015-16 to $20.69 million in 2016-17. Council is retaining a uniform general rate tariff which will be 0.23146 cents in the dollar of a property’s Capital Improved Valuation (CIV). The Municipal Charge will rise from $243 in 2015-16 to $250 in 2016-17 per assessment, in accordance with the Rating Strategy, which requires the Municipal Charge to be 15% of the total rates revenue raised.
Type of Rate/Charge 2015/2016 2016/2017
$ $
General rate (cents in the $CIV) 0.23108 0.23146
Municipal charge 243 250
The rates budget also includes $1.46 million to be derived from energy generators operating within the Shire. Section 9, the Rating Strategy, includes a more detailed analysis of the rates and charges to be levied for 2016-17.
Rates & charges, $621
User fees and fines, ($1,290)
Grants - operating, $6,155
Grants - capital, ($1,193)
Contributions -operating, ($64)
Contributions -capital, ($95)
Net gain on sale of assets, $78
Other revenue, $0
(2,000)
(1,000)
-
1,000
2,000
3,000
4,000
5,000
6,000
7,000
$'000 Income Variances Report 2015-16 to 2016-17
73 Moyne Shire Budget 2016-17
10.2.2 User fees and fines ($1.29 million decrease) Council generates significant revenue through user fees primarily due to caravan parks, quarry operations and external works. Other user fees relate to the recovery of service delivery costs such as planning fees, provision of human services such as aged care and family day care services, waste disposal fees and regulatory services such as animal registrations and food premises. Total user fees are predicted to decrease by $1.29 million compared to 2015-16 primarily due to a reduction in external works undertaken by Council. In general, Council plans to increase user charges for all areas by 4% to maintain parity between user charges and the costs of service delivery. A detailed listing of all fees and charges is set out in Appendix D and is also available on Council’s website. 10.2.3 Contributions Operating ($0.06 million decrease) Contributions relate to monies paid for specific programs of Council and includes public open space developer contributions. Contributions operating are projected to decrease by $0.06 million compared to 2015-16. 10.2.4 Contributions Capital ($0.09 million decrease) Contributions capital relate to monies paid towards projects or services from other stakeholders towards capital projects. Contributions capital are projected to decrease by $0.09 million compared to 2015-16. 10.2.5 Other revenue (No change) Other revenue includes interest on investments and rate arrears.
74 Moyne Shire Budget 2016-17
10.3 Operating expenditure
Expenditure types Ref Forecast
Actual Budget Variance
2015/16 2016/17
$'000 $'000 $'000
Expenses from ordinary activities
Employee costs 10.3.1 16,370 16,094 (276)
Materials and services 10.3.2 16,472 15,653 (819)
Depreciation and amortisation 10.3.3 12,387 12,662 275
Finance costs 10.3.4 152 121 (31)
Total operating expenditure 45,381 44,530 (851)
10.3.1 Employee benefits ($0.28 million decrease) This category includes wages and salaries and the direct overheads of superannuation, annual leave, long service provision, work-cover premiums and training costs. Employee costs are forecast to decrease $0.28 million compared to 2015-16.
This is primarily due to a reduction in the amount of external works that Council employees will deliver in 2016-17 and a reduction in the opening hours of Council’s waste facilities.
Various funded programs will also impact on the level of staff and staff costs from year to year.
10.3.2 Materials and services ($0.82 million decrease) Materials and services include the purchases of consumables, payments to contractors for the provision of services and utility costs. Materials and services are forecast to decrease by $0.82
Employee costs, ($276)
Materials and services, ($819)
Depreciation and amortisation, $275
Finance costs, ($31)
(1,000)
(800)
(600)
(400)
(200)
-
200
400
$'000 Expenditure Variances Report 2015-16 to 2016-17
75 Moyne Shire Budget 2016-17
million compared to 2015-16 primarily due to the reduction in external works undertaken by Council. 10.3.3 Depreciation and amortisation ($0.27 million increase) Depreciation is an accounting measure which relates to the usage of Council’s property, plant and equipment including infrastructure assets such as roads and drains. As capital works increase each year the value of assets increases; consequently these assigned costs rise. This also takes into account any revaluation impacts from the previous year and the subsequent impact on the depreciation expense. 10.3.4 Finance costs ($0.03 million decrease) Borrowing costs relate to interest charged by financial institutions on funds borrowed.
76 Moyne Shire Budget 2016-17
11 Analysis of budgeted cash position 11.1 Budgeted cash flow statement
Ref Forecast
Actual Budget Variance
2015/16 2016/17
$'000 $'000 $'000
Cash flows from operating activities 11.1.1
Receipts
General rates and charges
20,469 20,671 202
User fees and fines
9,770 8,644 (1,126)
Operating grants
11,759 17,914 6,155
Capital grants
2,283 1,090 (1,193)
Contributions
777 618 (159)
Interest
433 460 27
45,491 49,397 3,906
Payments
Employee costs
(16,097) (15,936) 161
Materials and contracts
(16,912) (15,653) 1,259
(33,009) (31,589) 1,420
Net cash provided by operating activities
12,482 17,808 5,326
Cash flows from investing activities 11.1.2
Payments for property, plant and equipment
(20,896) (18,261) 2,635
Proceeds from sale of property, plant and equipment
1,187 324 (863)
Repayment of loans and advances
138 6 (132)
Net cash used in investing activities
(19,571) (17,931) 1,640
Cash flows from financing activities 11.1.3
Finance costs
(153) (121) 32
Proceeds from borrowings
- - -
Repayment of borrowings
(560) (571) (11)
Net cash provided by (used in) financing activities
(713) (692) 21
Net increase (decrease) in cash & cash equivalents
(7,802) (815) 6,987
Cash & cash equivalents at the beginning of the year
15,024 7,222 (7,802)
Cash & cash equivalents at end of year 11.1.4 7,222 6,407 (815)
77 Moyne Shire Budget 2016-17
This section of the report analyses the expected cash flows from the operating, investing and financing activities of Council for the 2016-17 year, i.e. the budgeted cash flow position. Budgeting cash flows for Council is a key factor in setting the level of rates and providing a guide to the level of capital expenditure that can be sustained with or without using existing cash reserves. 11.1.1 Operating activities ($5.3 million increase) The net cash flows from operating activities does not equal the operating result for the year as the expected revenues and expenses of the Council include non-cash items which have been excluded from the Cash Flow Statement. The budgeted operating result is reconciled to budgeted cash flows available from operating activities as set out in the following table.
Forecast
Actual Budget Variance
2015/16 2016/17
$'000 $'000 $'000
Surplus (deficit) for the year (177) 4,886 5,063
Depreciation
12,387 12,662 275
Finance Costs
152 121 (31)
Loss (gain) on sale of assets
78 - (78)
Net movement in current assets and liabilities 42
139 97
Cash flows available from operating activities 12,482 17,808 5,326
11.1.2 Investing activities ($1.6) million decrease) Investing activities refer to cash generated or used in the enhancement or creation of infrastructure and other assets. These activities also include the acquisition and sale of other assets such as vehicles, property, equipment, etc. The decrease in cash outflows is mainly due to the decrease in capital expenditure compared to 2015-16. 11.1.3 Financing activities ($0.02 million decrease) Financing activities refer to cash generated or used in the financing of Council functions and include borrowings from financial institutions. These activities also include repayment of the principal component of loan repayments for the year. 11.1.4 Cash and cash equivalents at end of the year ($0.81 million decrease) Overall, total cash and investments is forecast to be $6.4 million as at 30 June 2017.
78 Moyne Shire Budget 2016-17
11.2 Restricted funds, and discretionary funds
The cash flow statement above indicates that Council is estimating at 30 June, 2017 it will have cash and investments of $6.4 million which are committed as follows:
Forecast
Actual Budget Variance
2015/16 2016/17
$'000 $'000 $'000 Total cash and investments
7,222 6,407 (815)
Restricted cash and investments
- - Restricted reserves
(545) (461) 84
- Discretionary reserves
(2,877) (3,020) (143) Unrestricted cash and investments 3,800 2,926 (874)
Restricted reserves ($0.46 million) These funds must be applied for specified statutory purposes in accordance with various legislative and contractual requirements. Whilst these funds earn interest revenues for Council, they are not available for other purposes. Discretionary reserves ($3.02 million) These funds are available for whatever purpose Council decides is their best use. In this case Council has made decisions regarding the future use of these funds and unless there is a Council resolution these funds will be used for those earmarked purposes. The decisions about future use of these funds has been reflected in Council’s Strategic Resource Plan and any changes in future use of the funds will be made in the context of the future funding requirements set out in the Plan. These funds are generated by business enterprise profits and also include the Waste Reserve to fund future waste disposal costs. Unrestricted cash and investments ($2.93 million) These funds are free of all specific Council commitments and represent funds available to meet daily cash flow requirements and unexpected short term needs. Council regards these funds as necessary to ensure that it can meet its commitments as and when they fall due without borrowing further funds.
79 Moyne Shire Budget 2016-17
12 Analysis of capital budget This section analyses the planned capital expenditure budget for the 2016-17 year and the sources of funding for the capital budget. 12.1 Capital Works
Forecast
Actual Budget Variance
Capital Works Areas 2015/16 2016/17
$'000 $'000 $'000
Capital works areas
Property 12.1.1
Buildings
3,170 2,125 (1,045)
Land & Natural Assets
610 113 (497)
Total Property
3,780 2,238 (1,542)
Plant and Equipment 12.1.2
IT Equipment & Furniture
207 131 (76)
Plant
1,852 1,422 (430)
Total Plant and Equipment
2,059 1,553 (506)
Infrastructure 12.1.3
Bridges
1,145 1,110 (35)
Drainage
498 372 (126)
Footpaths
372 410 38
Recreation
626 585 (41)
Roads
12,070 11,929 (141)
Waste Facilities
346 65 (281)
Total Infrastructure
15,057 14,471 (586)
Total capital works 20,896 18,262 (2,634)
Represented by:
New Asset Expenditure 12.1.4 2,076 439 (1,637)
Asset Renewal Expenditure 12.1.4 14,881 13,835 (1,046)
Asset Upgrade/Expansion Expenditure 12.1.4 3,939 3,988 49
Total capital works 20,896 18,262 (2,634)
80 Moyne Shire Budget 2016-17
8%
2%
2%
88%
Budgeted total funding sources 2016-17
Grants and contributions -Capital
Proceeds on sale of assets
Reserves
Operations
2%
76%
22%
Budgeted Capital Works 2016-17
New Asset Expenditure
Asset RenewalExpenditure
Asset Upgrade/ExpansionExpenditure
81 Moyne Shire Budget 2016-17
12.1.1 Property ($2.24 million) The property class comprises buildings and building improvements including community facilities, municipal offices, sports facilities and pavilions. For the 2016-17 year, $2.12 million will be expended on building projects. Significant projects include the upgrade to the Mortlake library and Information Centre ($0.75 million), and the Extension of the Port Fairy Surf Lifesaving Club ($0.5 million). 12.1.2 Plant and equipment ($1.55 million) Plant and equipment includes information technology, motor vehicles and plant purchases. For the 2016-17 year, $1.55 million will be expended on plant and equipment and other projects. The more significant projects include ongoing cyclical replacement of the plant and vehicle fleet ($1.39 million), and the upgrade and replacement of information technology ($0.12 million). 12.1.3 Infrastructure ($14.47 million) Infrastructure includes local roads, car parks, footpaths, drainage, bridges and culverts, recreation facilities and waste facilities. For the 2016-17 year, $11.9 million will be expended on road projects. The more significant projects include local road rehabilitation ($8.97 million) including Federally funded Roads to Recovery projects, road resheeting ($0.78 million), and road sealing ($1.66 million). Other infrastructure expenditure includes $1.11 million on bridges, $0.37 million on drainage, $0.41 million on footpaths, $0.58 million on recreation projects and $0.06 million on waste facilities. 12.1.4 Asset renewal ($13.83 million), new assets ($0.44 million) and upgrade/expansion
($3.99 million) A distinction is made between expenditure on the construction or purchase of new assets, the expansion/upgrade of assets and expenditure on asset renewal. Expenditure on asset renewal is expenditure on an existing asset, which improves the service potential or the life of the asset. Expenditure on new assets does not have any element of expansion/upgrade of existing assets but will result in an additional burden for future operation, maintenance and capital renewal. The major projects included in the above categories, which constitute expenditure on new assets, are the construction the Koroit Skate Park and facilities ($0.17 million) and new footpaths ($0.18 million). The remaining capital expenditure represents renewal and upgrade of existing assets.
82 Moyne Shire Budget 2016-17
12.2 Funding sources
Forecast Actual Budget Variance Sources of Funding Ref. 2015/16 2016/17 $'000 $'000 $'000
External
Grants and contributions - Capital 12.2.1 2,848 1,560 (1,288)
Proceeds on sale of assets 12.2.2 1,187 324 (863)
4,035 1,884 (2,151)
Internal
Reserves 12.2.3 444 344 (100)
Operations 12.2.4 16,417 16,034 (383)
16,861 16,378 (483)
Total funding sources 20,896 18,262 (2,634)
12.2.1 Capital grants and contributions ($1.56 million) Capital grants and contributions include all monies to be received from State and Federal governments and community sources for the purposes of funding the capital works program. Significant items include bridge to recovery $0.5 million, Mortlake Library $0.5 million, and $0.4 million capital contributions towards the Port Fairy Surf Life Saving Club extension. 12.2.2 Proceeds from sale of assets ($0.32 million) Proceeds from the sale of Council assets will raise $0.32 million in 2016-17 and relates to the cyclical replacement of the plant and vehicle fleet. 12.2.3 Reserves ($0.34 million) The Council has reserves set aside to fund its annual capital works program. The reserves include monies set aside for specific purposes such as Waste Disposal, Caravan Parks, and Mount Shadwell Quarry. For 2016-17 the reserve will be used to fund, Caravan Park works ($0.15 million), Quarry plant and equipment ($0.01 million) and waste facility improvements ($0.06 million). 12.2.4 Operations ($16.03 million) Council generates cash from its operating activities, which is used as a funding source for the capital works program. For 2016-17, $16.03 million will be required from operations to fund the balance of the capital works program.
83 Moyne Shire Budget 2016-17
13 Analysis of budgeted financial position This section analyses the movement in assets, liabilities and equity between 2015-16 and 2016-17. It also considers a number of key performance indicators. 13.1 Budgeted balance sheet
Ref Forecast
Actual Budget Variance
2015/16 2016/17
$'000 $'000 $'000
Current assets 13.1.1
Cash and cash equivalents
7,222 6,407 (815)
Trade and other receivables
2,607 2,620 13
Other assets
683 683 -
Total current assets
10,512 9,710 (802)
Non-current assets 13.1.1
Trade and other receivables
3 3 -
Investment in associates
215 215 -
Property, infrastructure, plant & equipment
443,451 448,726 5,275
Total non-current assets
443,669 448,944 5,275
Total assets
454,181 458,654 4,473
Current liabilities 13.1.2
Trade and other payables
2,785 2,786 (1)
Provisions
5,279 5,424 (145)
Interest bearing loans and borrowings
571 479 92
Total current liabilities
8,635 8,689 (54)
Non-current liabilities 13.1.2
Provisions
873 885 (12)
Interest bearing loans and borrowings
1,766 1,287 479
Total non-current liabilities
2,639 2,172 467
Total liabilities
11,274 10,861 413
Net assets
442,907 447,793 4,886
Equity 13.1.3
Accumulated surplus
209,365 214,192 4,827
Reserve
233,542 233,601 59
Total equity 442,907 447,793 4,886
84 Moyne Shire Budget 2016-17
13.1.1 Current assets ($0.80 million decrease) and Non-current assets ($4.5 million increase)
Current Cash and cash equivalents include cash and investments such as cash held in the bank and in petty cash and the value of investments in deposits or other highly liquid investments with short term maturities of three months or less. These balances are projected to decrease by $0.81 million during the year. Trade and other receivables are monies owed to Council by ratepayers and others. Short term debtors are not expected to change significantly in the budget. Other assets (current) includes items such as prepayments for expenses that Council has paid in advance of service delivery, inventories or stocks held for sale or consumption in Council’s services and other revenues due to be received in the next 12 months. Non-Current Property, infrastructure, plant and equipment is the largest component of Council’s worth and represents the value of all the land, buildings, roads, vehicles, equipment, etc. which has been built up by the Council over many years. The increase in this balance is attributable to the net result of the capital works program ($18.2 million of new assets), depreciation of assets ($12.7 million) and the sale through sale of property, plant and equipment ($0.3 million). 13.1.2 Current liabilities ($0.54 increase) and Non-current liabilities ($0.41 million
decrease) Current Trade and other payables are those to whom Council owes money as at 30 June. These liabilities are budgeted to remain consistent with 2015-16 levels. Provisions current include accrued long service leave, annual leave and rostered days off owing to employees. These employee entitlements are expected to increase marginally due to increased wage cost associated with the Enterprise Bargain Agreement outcomes. Non-Current Provisions noncurrent include accrued long service leave and the waste rehabilitation provision. The Council is budgeting to repay loan principal of $0.57 million over the year.
85 Moyne Shire Budget 2016-17
13.1.3 Equity ($4.89 million increase) Total equity always equals net assets and is made up of the following components:
Accumulated surplus which is the value of all net assets less Reserves that have accumulated over time. The $4.89 million increase in equity results directly from the surplus for the year. An amount of $0.06 million is budget to be transferred to reserve. This is a transfer between equity balances only.
Asset revaluation reserve which represents the difference between the previously recorded value of assets and their current valuations
Other reserves are funds that Council wishes to separately identify as being set aside to meet a specific purpose in the future and to which there is no existing liability. These amounts are transferred from the Accumulated Surplus of the Council to be separately disclosed
13.2 Key assumptions
In preparing the Budgeted Balance Sheet for the year ended 30 June 2017 it was necessary to make a number of assumptions about assets, liabilities and equity balances. The key assumptions are as follows:
A total of 97% of total rates and charges raised will be collected in the 2016-17 year
Other debtors and creditors to remain consistent with 2015-16 levels
Repayment of loan principal to be $0.57 million
Total capital expenditure to be $18.3 million.
86 Moyne Shire Budget 2016-17
LONG TERM STRATEGIES This section includes the following analysis and information 14 Strategic resource plan 15 Rating information 16 Other long term strategies
87 Moyne Shire Budget 2016-17
14 Strategic Resource Plan and Key Financial Indicators This section provides information on the long term financial projections of the Council. 14.1 Plan development
The Act requires a Strategic Resource Plan to be prepared covering both financial and non-financial resources, and including key financial indicators for at least the next four financial years to support the Council Plan. Council has prepared a Strategic Resource Plan (SRP) for the four years 2016-17 to 2019-20 as part of its ongoing financial planning to assist in adopting a budget within a longer term framework. The SRP takes the strategic objectives and strategies as specified in the Council Plan and expresses them in financial terms for the next four years. The key objective, which underlines the development of the SRP, is financial sustainability in the medium to long term, while still achieving Council’s strategic objectives as specified in the Council Plan. The key financial objectives, which underpin the SRP, are:
Maintain the existing range and level of service provision and develop the capacity to respond to community service needs
Services provided with an emphasis on continuous improvement, productivity, innovation, and efficiency
Maintain a strong cash position
Achieve operating statement surpluses with the exclusion of all non-operational items such as granted assets and capital income
Maintain debt levels below prudential guidelines
Continue to pursue recurrent grant funding and strategic capital funding aligned with Council plan objectives
Rate increases that provide the level of funding;
For a sustainability index to exceed 95 per cent, that is meeting the infrastructure renewal demand
To increase funding for asset upgrade, expansion and new assets
Provide user fees and charges based on Best Value Principles. In preparing the SRP, Council has also been mindful of the need to comply with the following Principles of Sound Financial Management as contained in the Act:
Prudently manage financial risks relating to debt, assets and liabilities
Provide reasonable stability in the level of rate burden
Consider the financial effects of Council decisions on future generations
Provide full, accurate and timely disclosure of financial information. The SRP is updated annually through a rigorous process of consultation with Council service providers followed by a detailed sensitivity analysis to achieve the key financial objectives.
88 Moyne Shire Budget 2016-17
14.2 Financial resources
The following table summarises the key financial results for the next four years as set out in the SRP for years 2016-17 to 2019-20. Appendix A includes a more detailed analysis of the financial resources to be used over the four year period.
Forecast Strategic Resource Plan
Indicator
No
tes
Actual Budget Projections
2015/16 2016/17 2017/18 2018/19 2019/20
$’000 $’000 $’000 $’000 $’000
Surplus/ (deficit) for the year -177 4,886 1,462 1,564 1,831
Adjusted underlying result 1 -3,025 3,326 -724 -307 -277
Cash and investments 2 7,222 6,407 6,045 5,796 5,776
Cash flows from operations 12,482 17,809 14,770 14,869 14,803
Current assets/Current liabilities 2 122% 112% 105% 101% 102%
Capital works 3 20,896 18,262 14,957 14,919 14,586
Net capital expenditure (Net of capital grants and contributions and asset sales) 3 16,860 16,378 12,375 12,677 12,144
Debt servicing/Total revenue 4 0.34% 0.25% 0.21% 0.14% 0.08%
Borrowings outstanding 4 2,337
1,766
1,287 781 245
Notes to Indicators 1 Adjusted underlying result: An indicator of the sustainable operating result. Council
aims to achieve positive underlying results in the long term.
2 Cash and Liquidity: Working capital is forecast to decrease to 102% by 2019-20, and cash will decrease over the term of the Strategic Resource Plan to $5.8 million.
3 Capital works: Total capital expenditure forecast for 2016-17 includes additional Roads to Recovery program funding of $4.2 million, the remaining three year capital program is based on the standard Roads to Recovery funding program of $1.8 million.
4 Debt Levels: Council’s debt levels are well within the local government prudential guidelines that set limits for levels of debt and debt commitment costs. Total borrowing outstanding will be reduced to $0.2 million by 2019-20.
14.3 Non-financial resources
In addition to the financial resources to be consumed over the planning period, Council will also consume non-financial resources, in particular human resources. The following table summarises the non-financial resources for the next four years.
Indicator
Actual Budget Projections
2015/16 2016/17 2017/18 2018/19 2019/20
Employee costs – operating $ 16,370 16,094 16,261 16,430 16,600
Full time equivalent employees 242.5 233.6 233.6 233.6 233.6
89 Moyne Shire Budget 2016-17
15 Rating Information 15.1 Rating strategy
The Rating Strategy adopted by the Council is:
a Continue with a general rating structure comprised of two (2) elements:
Property values (Capital Improved Value- CIV) – multiplied by a uniform shire-wide tariff;
Standard municipal charge – to cover the administrative costs of the Council.
b Municipal charge set to contribute 15% of the income derived from total rate revenue. The position paper, used as a basis for formulation of the Strategy noted that any review of the rating structure needed to produce a revenue neutral outcome. The quantum of rates raised by the Council is a process properly associated with the preparation of the annual Budget. Council has reviewed its Rating Strategy in 2015-16 for 2016-17 (subject to adoption by the Council) that contains expanded information on Council’s rating structure and the reasons behind its choice in applying the rating mechanisms it has used. The proposed Rating Strategy 2016-17 will be put on public exhibition for a period of 28 days prior to adoption by the Council. 15.2 Rating comparisons
Deciding on the amount to be raised by rates irrespective of the validity of any comparative analysis, is always a major challenge to the Council. Notwithstanding, it is reasonable that the Council and the community are aware of these comparisons so as to better appreciate Moyne’s rating position. An inter-Council comparison, for the large rural councils group, shows a favorable comparative outcome for Moyne on the average rates per assessment for 2014-2015.
* 2014-15 is the latest comparable data available
Moyne1,604
1,772
Moyne1,686
Moyne1,723
$1,500
$1,550
$1,600
$1,650
$1,700
$1,750
$1,800
2014/15 Actual 2014/15 AverageLarge Rural
2015/16 Forecast 2016/17 Budget
Rates per assessment
90 Moyne Shire Budget 2016-17
A comparison of rates as a percentage of total revenue for 2014-15 shows Moyne having one of the smallest percent in the large shires group. Moyne has a greater reliance on non-rate revenue to fund its activities and its ability to source external funds for projects and capital works allows for a wider scope of services and amenities to be provided with rates a lesser impost on the community. The Council must, in order to deliver all of the activities outlined in the current strategies, be prepared to follow through with raising sufficient revenue. This, of course, has to be balanced against the community expectation of reasonable cost increases. Rate revenue is the most significant ‘discretionary’ funding directly controlled by the Council. The following table highlights the rate and charges increases for the years 2013-14 to 2016-17:
Year Rate and Charges Increase Total Rates Raised
% $'000
2013-14 5.00 17,996
2014-15 4.90 18,972
2015-16 5.75 20,069
2016-17 2.50 20,690
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
Rate Revenue/Total Adjusted Revenue - 2015 - Large Rural Group Average
91 Moyne Shire Budget 2016-17
15.3 Rating tariffs
CHARGE BASIS
General Rate Uniform rate, no differentials.
Payments in lieu of rates Energy generation companies enter into a rating agreement in lieu of the normal rating methodology.
Municipal Charge On single enterprises only.
Cover administrative costs.
Raise 15% of the income derived from total rate revenue.
Kerbside Collection Service Kerbside collection service costs
State Government Landfill Levy State Government Landfill Levy
Waste Facilities Service Charge Waste disposal costs
Waste facility development costs
Rehabilitation and post-closure maintenance costs
RATES AND CHARGES STRUCTURE
Rate/Charge
Amount to be raised
$
General Rate (cents in the dollar CIV) 0.23146 14,018,008
Payments in lieu of rates 1,457,322
Municipal Charge $250 2,382,500
Kerbside Collection Service Charge $327.60 1,706,468
State Government Landfill Levy $12.40 64,592
Waste Facilities Service Charge
Developed (residence) per property $124
Undeveloped/Vacant per property $32
1,031,410
Total 20,660,300
92 Moyne Shire Budget 2016-17
16 Borrowings 16.1 Prudential ratios
In assessing Council’s borrowing strategy, reference has been made to the prudential ratios used by the State Government to assess the loan capacity of local governments. The table below shows the Council borrowings and debt servicing ratios compared to the prudential thresholds. It shows that Council is well within these prudential thresholds.
Year Borrowings Outstanding
Debt Mgt Debt Commitment
Debt servicing Costs/Total
Revenue
Debt servicing and redemtion costs /rates
revenue
30-Jun $,000 %
2015 2,897 0.34% 4.28%
2016 2,337 0.34% 3.55%
2017 1,766 0.25% 3.34%
2018 1,287 0.21% 2.77%
2019 781 0.14% 2.73%
2020 245 0.08% 2.69%
Threshold (prudential ratios) <5.0% <10.0%
16.2 Current year borrowings
For the 2016-17 year, no new borrowings are required. The following table below sets out the Council’s loan indebtedness, principal and interest payments based on the forecast financial position of Council as at 30 June 2016. Outstanding borrowings are projected to decrease to $0.2 million by 30 June 2020.
Year New Borrowings Loan Principal Loan Interest Balance 30 June
2015 - 629 182 2,897
2016 - 560 152 2,337
2017 - 571 121 1,766
2018 - 479 92 1,287
2019 - 506 64 781
2020 - 536 35 245
Council has maintained a low level of debt so as to retain financial flexibility. However, as the cash reserves run down and major capital expenditures remain a priority, additional borrowings may become a future financing option for major projects.
93 Moyne Shire Budget 2016-17
Appendix A: Fees and Charges
This appendix lists the various fees and charges for Council services that will apply for 2016-17.
94 Moyne Shire Budget 2016-17
Each fee or charge is classified under the following categories:
(Z) Zero Cost Recovery This good/service is provided at no cost. The costs are met entirely from rates and general purpose income. Generally, where there is no fee or charge, the service provided is not mentioned in the fees and charges list.
(P) Partial Cost Recovery The price for this good/service is set to make a significant (more than 50%) contribution towards the operating costs, both direct and indirect, of providing the good/service. The remainder of the costs are met from rate and general purpose income.
(F) Full Cost Recovery The price for this good/service is set to recover the total operating costs, both direct and indirect, of providing this good/service. Indirect costs are to include taxation equivalent payments, where applicable, in accordance with the principles of National Competition Policy.
(R) Regulatory The price for this good/service is a statutory charge set by government regulation.
(M) Market Price The price for this good/service is set by reference to prices charged for similar goods/services by like Councils or competitors.
95 Moyne Shire Budget 2016-17
FEES AND CHARGES DESCRIPTION
2015/16 GST
Inclusive$
2016/17 GST
Inclusive $
Pricing Policy
FINANCE AND ADMINISTRATION
Freedom of Information 25.70 27.20 R
Land Information Certificate 20.00 24.80 R
Photo-copying - General Public per copy - A4 0.40 0.50 F
'Photo-copying - General Public per cop y - A3 0.50 0.60 F
Colour photo-copying - General Public per copy - A4 0.70 0.80 F
Colour photo-copying - General Public per copy - A3 1.60 1.70 F
Plan Printing Black & White- A1 paper & printing provided by shire 6.40 6.70 F
Plan Printing Black & White- A1 printer provided by shire 3.70 3.80 F
Plan Printing Colour - A4 2.10 2.20 F
Plan Printing Colour - A3 3.50 3.60 F
Plan Printing Colour - A2 7.90 8.20 F
Plan Printing Colour - A1 15.80 16.40 F
Plan Printing Colour - A0 30.40 31.60 F
Document Search General Per Hour- Minimum Charge one hour 64.00 67.00 F
Replacement Rate Notice 8.90 9.30 P
Replacement Cheque Fee 22.50 23.40 P
Taping of Council Meeting Fee 23.40 24.30 P
BUILDING PERMIT FEES
Item Class Description
1
1B & 2-9
Residential & Commercial works other than Class 1A
6.5(value/2000+
√value)+ GST
Minimum Fee:
$1,320.00
6.5(value/2000+ √value)+ GST Minimum Fee: $1,320.00
F
2 1A All Dwellings – Single Detached Houses or attached Multi-Units Development
Up to $150,000 2,640.00 2,750.00 F
$150,001-$200,000 3,515.00 3,660.00 F
$200,001-$250,000 4,540.00 4,720.00 F
$250,001 -$300,000 5,830.00 6,060.00 F
>$300,000
large projects
negotiable
large projects negotiable
F
3 1A Dwellings - Extension Alterations (including Demolitions)
Up to $10,000 975.00 1,010.00 F
$10,001-$20,000 1,195.00 1,240.00 F
$20,001-$50,000 1,640.00 1,710.00 F
96 Moyne Shire Budget 2016-17
FEES AND CHARGES DESCRIPTION
2015/16 GST
Inclusive$
2016/17 GST
Inclusive $
Pricing Policy
$50,001-$100,000 2,310.00 2,400.00 F
$100,001-$150,000 2,970.00 3,090.00 F
>$150,000 Value/50 Value/50 F
4 1A Dwellings - Internal Alterations / Minor Works
Up to $10,000 710.00 740.00 F
$10,001-$20,000 975.00 1,010.00 F
$20,001-$50,000 1425.00 1,480.00 F
$50,001-$100,000 1805.00 1,880.00 F
>$100,000 Value/55 Value/45 F
5 10A/10B Minor Works - Garages, carports, pools, fences etc.
Up to $5,000 710.00 740.00 F
Up to $10,000 975.00 1,010.00 F
$10,001-$20,000 1,195.00 1,240.00 F
$20,001-$50,000 1,425.00 1,480.00 F
$50,001-$100,000 1,805.00 1,880.00 F
>$100,000 Value/55 Value/45 F
6 10B Pool fence (without pool) 302.00 314.00 F
7 Sundry Any Additional Inspection
Domestic 330.00 343.00 F
Commercial 520.00 540.00 F
8 Regulation 326(1) 326(2) 326(3) or 326(4) Advise (Property Information)
49.90 49.90 R
9 Amendment and/or Extension of Building Permits, Amendment of Approved Plans
330.00 343.00 F
10 Dispensation for Siting of Single Dwellings
250.00 250.00 R
11 Application for Demolition Consents (Section29A) (GST Not Applicable)
62.60 62.60 R
12 Building Notice 924.00 960.00 F
13 Building Order 652.00 680.00 F
14 Temporary Structure Siting Approval
652.00 680.00 F
15 Places of Public Entertainment Occupancy Permit
940.00 980.00 F
16 Subdivision Statements for Buildings - Regulation 503(2)
250.00 250.00 R
17 Pool Safety Fence Inspection 198.00 206.00 F
19 Provide copy of Building Permit or Occupancy Permit (with owners consent)
74.00 77.00 F
20 Provide copy of Building Permit including plans (with owners consent)
132.00 137.00 F
97 Moyne Shire Budget 2016-17
FEES AND CHARGES DESCRIPTION
2015/16 GST
Inclusive$
2016/17 GST
Inclusive $
Pricing Policy
NOTE: THE FOLLOWING COSTS APPLY IN ADDITION TO THE BASIC FEE SCALE
1 A State Government levy of $1.28 per $1,000 construction value must be paid before the permit can be issued. This applies to all building works exceeding a construction value of $10,000 (GST exempt).
2 A lodgement fee of $37.40 must be paid before the permit can be issued for all works with a project cost >$5,000 (GST Exempt).
3 The fee schedule is based on structural design certification being provided where applicable in accordance with BCC Practice Note 3.
4 Checking of specialist system designs (structural, mechanical, electrical and hydraulic) where necessary and/or where an appropriate design compliance certificate is not provided is charged on a cost recovery basis.
5 Statutory fees incurred relating to property requisitions, lodgement of permit documents, etc are charged on a cost recovery basis.
6 Domestic Special performance based assessments, applications for reporting authority consents (Councils and heritage approvals), modification applications, preparation or protection works notices or any other necessary Building Notices or Order are at an hourly rate of $88 (inc GST) per hour - minimum payable - $110 (inc GST).
7 Commercial Special assessments, applications for reporting authority consents (Council and Fire Brigade), modification applications, preparation of protection works notices or any other necessary Building Notices or Orders are at an hourly rate of $132.00 (inc GST) per hour - minimum payable of $198 (inc GST)
ENVIRONMENTAL HEALTH
Food Premises Registrations
Non Compliance or Late Fee 120.00 125.00 F
Transfer of Registration 50% of scheduled
fee
50% of scheduled
fee
F
Inspection and report fee 158.00 165.00 F
Premises Class
Food Premises
Class 1
Renewal Fee 350.00 365.00 F
New Registration 525.00 548.00 F
Class 2 L1
Renewal Fee 350.00 365.00 F
New Registration 525.00 548.00 F
Class 2 L2 Community organisations with paid employees
Renewal Fee 234.00 240.00 F
New Registration 351.00 360.00 F
Class 2 L3 Community organisations with volunteers
Renewal Fee Nil Nil Z
New Registration Nil Nil Z
Class 3 L1
Renewal Fee 105.00 110.00 F
New Registration 158.00 165.00 F
Class 3 L2 Community organisations with paid employees
Renewal Fee 78.00 80.00 F
New Registration 117.00 120.00 F
98 Moyne Shire Budget 2016-17
FEES AND CHARGES DESCRIPTION
2015/16 GST
Inclusive$
2016/17 GST
Inclusive $
Pricing Policy
Class 3 L3 Community organisations with volunteers
Renewal Fee Nil Nil Z
New Registration Nil Nil Z
Premises Class
Food Premises with Accommodation
Class 2 L1
Renewal Fee 460.00 480.00 F
New Registration 690.00 720.00 F
Class 2 L2 Community organisations with paid employees
Renewal Fee 341.00 355.00 F
New Registration 512.00 532.00 F
Class 2 L3 Community organisations with volunteers
Renewal Fee Nil Nil Z
New Registration Nil Nil Z
Class 3 L1
Renewal Fee 211.00 220.00 F
New Registration 317.00 330.00 F
Class 3 L2 Community organisations with paid employees
Renewal Fee 184.00 190.00 F
New Registration 276.00 285.00 F
Class 3 L3 Community organisations with volunteers
Renewal Fee Nil Nil Z
New Registration Nil Nil Z
Health Premises
Renewal Fee 78.00 80.00 F
New Registration 117.00 120.00 F
Non Compliance or Late Fee
120.00 125.00 F
PRESCRIBED ACCOMMODATION
Prescribed Accommodation - without pool
Renewal Fee 125.00 130.00 F
New Registration 188.00 195.00 F
Non Compliance or Late Fee 120.00 125.00 F
Prescribed Accommodation - with pool
Renewal Fee 156.00 160.00 F
New Registration 234.00 240.00 F
Non Compliance or Late Fee 120.00 125.00 F
Caravan Park Registration
99 Moyne Shire Budget 2016-17
FEES AND CHARGES DESCRIPTION
2015/16 GST
Inclusive$
2016/17 GST
Inclusive $
Pricing Policy
Caravan Park Registration as per Residential Tenancies Regulation 17 Schedule of fees. Fee units
13.00 13.60 R
Transfer of Caravan Park Registration 61.00 61.00 R
Immunisations
Immunisation (Adult hep B, Chicken Pox + OTHERS)
At cost per dose plus
30%
At cost per dose plus
30%
F
Environment Protection Act
Septic Tanks (excl-gst)
Septic Tank Application Fee - Install 572.00 600.00 P
Septic Tank Application Fee - Minor Alter New 300.00 F
Septic Tank Application Fee - Major Alter New 600.00 F
Sharps Containers Nil Nil Z
Domestic Animal Registration
Dogs
Dogs(which fit into category of reduced fee as prescribed by Act) 36.00 37.00 P
Dogs full fee 108.00 111.00 P
Pension and State Concession Holders (50% reduction)
Dogs(which fit into category of reduced fee as prescribed by Act) 18.00 18.50 P
Dogs full fee 54.00 55.50 P
Cats
Cats(which fit into category of reduced fee as prescribed by Act) 28.50 30.00 P
Cats full fee 85.50 90.00 P
Pension and State Concession Holders (50% reduction)
Cats(which fit into category of reduced fee as prescribed by Act) 14.25 15.00 P
Cats full fee 42.75 45.00 P
Domestic Animal Business 109.00 114.00 P
Transfer of Domestic Animal Business 55.00 57.00 P
Inspection of Domestic Animal Business 55.00 57.00 P
Permit Fees
Advertising signs per sign
46.00
48.00 P
Street displays per display (table/rack etc.) 46.00 48.00 P
Confiscated Goods/Signs release fee 138.00 144.00 P
Itinerant Traders Annual 645.00 671.00 P
Itinerant Traders Monthly Permit
258.00 268.00 P
100 Moyne Shire Budget 2016-17
FEES AND CHARGES DESCRIPTION
2015/16 GST
Inclusive$
2016/17 GST
Inclusive $
Pricing Policy
Itinerant Traders Daily Permit 129.00 134.00 P
Itinerant Traders Eligible Non Profit Nil Nil P
Temporary dwelling permit $69/ month $70/ month P
General Local Laws Busking Permit 61.00 63.00 P
Temporary placement of trade waste skip on Council property 23.00 24.00 P
Eligible Not for Profit groups sale of raffle tickets/street stalls Nil Nil Z
Sporting clubs, churches and community group sale of raffle tickets/street stalls Nil Nil Z
Outdoor eating facilities
Table and 4 chairs (Outside of Port Fairy) $46.00 per table & 4
chairs
$48.00 per table & 4
chairs
P
Table and 4 chairs (Port Fairy) $46.00 per table & 4
chairs
$96.00 per table & 4
chairs
P
Placement of removable wind breaks (per item) 46.00 48.00 P
Placement of umbrella (per umbrella) 46.00 48.00 P
Grazing Permit Sites $63 plus $31/hectar
e
$65 plus $32/hectare
F
Hay cropping existing sites only - no new sites to be permitted $63 plus $31/hectar
e
$65 plus $32/hectare
P
Stock Crossing Inspection Fee for siting of signs 134.00 139.00 P
Stock crossing fee for installation of signs Cost of sign plus
$312 installation
Cost of sign plus $324 installation
F
Fire Clearance Fee - non-standard Contractors cost plus
$120 admin fee
Contractors cost plus
$150 admin fee
F
Standpipe Fees - < 5,000 litres 26.40 27.00 F
- > 5,000 litres $26.40 plus $1.92/1,00
0lts
$27.00 plus $2.00/1,000lt
s
F
Works in Road Reserves Consent Applications
Consent Application - Minor Works 78.00 85.00 P
Consent Application - Works in a Road Pavement 166.00 175.00 P
Reinstatement Fees - indicative charges. Invoices are at cost
Roads - sprayed seal on crushed rock base per sq. metre 90.00 94.00 F
- asphalt on crushed rock base per sq. metre 116.00 121.00 F
- unsealed per sq. metre 53.00 55.00 F
Footpaths - sprayed seal on crushed rock base per sq. metre 65.00 68.00 F
- asphalt or 75mm concrete per sq. metre 90.00 94.00 F
- unsealed per sq. metre 40.00 42.00 F
Channel / Kerb - concrete / bluestone pitchers per lineal metre 116.00 121.00 F
Dressed bluestone kerb and channel
- new sawn bluestone per lineal metre 422.00 439.00 F
- existing sawn bluestone per lineal metre 126.00 131.00 F
101 Moyne Shire Budget 2016-17
FEES AND CHARGES DESCRIPTION
2015/16 GST
Inclusive$
2016/17 GST
Inclusive $
Pricing Policy
Services Site Location Fee
Services location for Authority Reciprocal Fee
Reciprocal Fee
F
WASTE FACILITIES
Domestic & Commercial Waste
Putrescible Waste - Minimum Charge
5.00 6.00 P
Putrescible Waste - Small Wheelie Bin - 120 litre 6.00 6.50 P
Putrescible Waste - Large Wheelie Bin - 240 litre 12.00 13.00 P
General Waste - Car boot 12.00 13.00 P
General Waste -Loads per M3
48.00 52.00 P
Commingled Recyclables (glass, plastic, paper, cardboard, aluminium) - Minimum Charge
2.00 4.00 P
Commingled Recyclables (glass, plastic, paper, cardboard, aluminium) - per M3 2.00 4.00 P
Approved Green Waste per M3 15.00 16.00 P
Tyres no rims
Car
8.00 9.00 P
Light Truck 11.00 12.00 P
Large Truck 16.00 17.00 P
Super Single 31.00 32.00 P
Tractor - Small 68.00 71.00 P
Tractor - Large 135.00 140.00 P
Tyre containing Wheel Rim (additional to tyre disposal cost) 6.00 7.00 P
Other
Annual Out of Hours Access - key card 487.00 500.00 P
Batteries 1.00 1.00 P
Oil (per deposit) 1.00 1.00 P
e-waste per small item 4.00 4.00 P
e-waste per medium item 8.00 9.00 P
e-waste per large item 18.00 19.00 P
silage wrap per bag 1.00 1.00 P
Fridges and Freezers not degassed 11.00 12.00 F
Mattress - single 22.00 24.00 F
Mattress - double 33.00 36.00 F
Scrap metal
Gas Bottles - Small 3.00 4.00 P
Gas Bottles - Large 6.00 7.00 P
Wheelie Bin Repair - Service Fee 12.00 13.00 F
Wheelie Bin Repair - Replacement Fee 36.00 55.00 F
PORT OF PORT FAIRY
102 Moyne Shire Budget 2016-17
FEES AND CHARGES DESCRIPTION
2015/16 GST
Inclusive$
2016/17 GST
Inclusive $
Pricing Policy
Mooring Fees- Quarterly (incl. extra 1 metre)
- single 36/mtr 37/mtr M
- double (75% of single) 28/mtr 29/mtr M
- Marina Pens (Small Berth) 285.00 296.00 M
- Marina Pens (Large Berth) 335.00 348.00 M
NB. Vessels over 60 feet are charged at 125% of normal fees
Itinerant Moorings
- commercial 37.00 38.00 M
- yachts 30.00 31.00 M
Slipway Fees
Large Slipway - 10 tonnes or under Slip fee (including first day) 144.00 150.00 M
Large Slipway - 10 tonnes or under day fee 73.00 76.00 M
Large Slipway - over 10 tonnes Slip fee (including first day) 16/GT 17/GT M
Large Slipway - over 10 tonnes day fee (min. of $70 per day) 4.5/GT 5.0/GT M
Large Slipway - large yacht Slip fee (including first day) 240.00 250.00 M
Large Slipway - large yacht day fee 74.00 77.00 M
Small Slipway - 4 tonnes or under Slip fee (including first day) 83.00 86.00 M
Small Slipway - 4 tonnes or under day fee 34.00 35.00 M
Small Slipway - over 4 tonnes Slip fee (including first day) 118.00 123.00 M
Small Slipway - over 4 tonnes day fee 49.00 51.00 M
Small Slipway - yacht Slip fee (including first day) 150.00 156.00 M
Small Slipway - yacht day fee 55.00 57.00 M
Crane Hire Per Hour (includes Licensed Crane Operator)
Within Port Fairy Township (Mon - Fri 8.00am to 4.30pm ) 160.00 166.00 M
All other occasions 215.00 224.00 M
With spotter 60.00 62.00 M
MOUNT SHADWELL QUARRY
Quarry Products
All prices are per cubic metre
10mm minus Dust 25.20 26.00 M
7mm minus Dust 25.20 26.00 M
Crushed 40mm Minus 15.50 16.00 M
Crushed 20mm Minus 15.50 16.00 M
Screened 20mm Minus 15.50 16.00 M
Screened 30mm Minus Blend (Dirty) - Dairy Tracks 15.50 16.00 M
Screened 40mm Minus 15.50 16.00 M
Screened 75-150mm Rubble 15.00 16.00 M
Screened 40 to 75mm Rubble 15.00 16.00 M
Screened 25mm - 40mm Aggregate 25.20 26.00 M
Screened 10 to 20mm Aggregate 19.80 21.00 M
Screened 10 to 15mm Aggregate 19.80 21.00 M
Crushed 20mm minus Scoria/Limestone Mix 23.50 24.00 M
103 Moyne Shire Budget 2016-17
FEES AND CHARGES DESCRIPTION
2015/16 GST
Inclusive$
2016/17 GST
Inclusive $
Pricing Policy
Other Scoria products made to Client's Specification
All the above prices include loading at Quarry during normal working hours
Mortlake Weighbridge
Certified Weigh 7.30am to 4.30pm 35.00 36.00 P
CARAVAN PARK FEES
Port Fairy Gardens Caravan Park
Cabin - Standard
Peak 155.00 161.00 M
Off-peak 120.00 120.00 M
Cabin - Deluxe
Peak 185.00 192.00 M
Off-peak 135.00 135.00 M
Extra Persons
Adult 17.00 18.00 M
Child 11.00 12.00 M
Powered Site
Peak 48.00 50.00 M
Off-peak 41.00 43.00 M
Extra Persons
Adult 15.00 16.00 M
Child 8.00 10.00 M
Unpowered
Peak 43.00 45.00 M
Off-peak 37.00 38.00 M
Extra Persons
Adult 15.00 16.00 M
Child 8.00 10.00 M
Extra Vehicles (above 2)
(e.g. any registrable vehicle, caravan, boat trailer etc.)
Daily
11.00 11.00 M
Linen Hire $17.00 per set
$20.00 per set
M
Annual Site with Van
2 Adults, Children in Family and 2 vehicles 3,245.00 3375.00 M
104 Moyne Shire Budget 2016-17
FEES AND CHARGES DESCRIPTION
2015/16 GST
Inclusive$
2016/17 GST
Inclusive $
Pricing Policy
Extra Person
Adult 241.00 251.00 M
Child 160.00 166.00 M
Adult (Daily Fee) 15.00 16.00 M
Child (Daily Fee) 8.00 8.00 M
Extra Vehicles 103.00 107.00 M
Folk Festival (includes Fri, Sat, Sun)
Adults 111.00 114.00 M
Children 60.00 63.00 M
Extra Vehicle 20.00 21.00 M
Southcombe Caravan Park
Powered Site
Peak 48.00 50.00 M
Off-peak 41.00 43.00 M
Extra Persons
Adult 15.00 16.00 M
Child 8.00 10.00 M
Unpowered
Peak 43.00 45.00 M
Off-peak 37.00 38.00 M
Extra Persons
Adult 15.00 16.00 M
Child 8.00 10.00 M
Extra Vehicles
(e.g.. any registrable vehicle, caravan, boat trailer, etc.)
Daily 11.00 11.00 M
Casual Storage
Daily (not available Folk Festival Weekend) 10.00 10.00 M
Folk Festival (includes Fri, Sat, Sun)
Adults 111.00 114.00 M
Children 60.00 63.00 M
Motor Vehicle (for weekend) 45.00 48.00 M
Additional Vehicle Security Parking (Per Car) 25.00 26.00 M
Powered Site booking fee for weekend 49.00 51.00 M
Pre Folk Festival Powered Site Fee (Vacant) 20.00 21.00 M
Pre Folk Festival Unpowered Site Fee (Vacant) 20.00 21.00 M
105 Moyne Shire Budget 2016-17
FEES AND CHARGES DESCRIPTION
2015/16 GST
Inclusive$
2016/17 GST
Inclusive $
Pricing Policy
Note: Southcombe Caravan Park & Gardens Caravan Park
* Peak - All Victorian School holidays, Public holidays & other designated holidays
* Off-peak - All other times .
* All bookings will receive a discount under the 'Loyalty' discount program . Minimum
stay to be eligible for loyalty discount is seven nights
* 10% Senior Card/FPA discount non peak periods
* Child under 3yrs of age is free
* Child classifies as under 18yrs of age
* Refund Policy
December and January bookings not paid in full by 6pm on the 31st of October will be cancelled incurring forfeiture of
deposit. Cancellation of a December or January booking after the 31st of October incurs a loss of deposit and fees.
No refunds or balance transfers for early departure or changes for any reason during December or January.
Cancellation of a booking 14 or more days prior to arrival incurs a $30 fee. Cancellation of a booking 13 days or less
prior to arrival date incurs the forfeiture of the deposit. No Show incurs forfeiture of deposit and fees paid.
Folk festival No refund once the application has been processed
GCP Management reserve the right to discount cabin fees in periods of low demand.
Southcombe Lodge
Non School Groups
Group Booking of 20 or more, the basic costs for the total facility are ;-
* A one night stay (per person) 35.00 36.00 M
* Two nights stay (per person) 32.00 33.00 M
* Three or more nights (per person) 31.00 32.00 M
Less than 20 people minimum charge for total facility 630.00 655.00 M
* Per night (per person) 36.00 37.00 M
Casual hire of ensuite rooms per night (minimum fee) 112.00 116.00 M
Casual hire of double bed rooms per night (minimum fee) 92.00 96.00 M
School Groups
Group Booking of 20 or more, the basic costs for the total facility are ;-
* A one night stay (per person) 34.00 35.00 M
* Two nights stay (per person) 31.00 32.00 M
* Three or more nights (per person) 30.00 31.00 M
Less than 20 people minimum charge for total facility 630.00
655.00 M
* Per night (per person) 35.00 36.00 M
Casual hire of ensuite rooms per night (minimum fee) 112.00 116.00 M
Casual hire of double bed rooms per night (minimum fee) 92.00 96.00 M
106 Moyne Shire Budget 2016-17
FEES AND CHARGES DESCRIPTION
2015/16 GST
Inclusive$
2016/17 GST
Inclusive $
Pricing Policy
Note:
Southcombe Lodge - Children aged 3 & 4 years are half price, no charge if under 3 years
Other Caravan Parks (Killarney, Koroit, Mortlake and Yambuk )
Powered sites 25.00 26.00 M
Unpowered sites 20.00 21.00 M
Extra Persons
Adult 6.00 6.00 M
Child 3.00 3.00 M
Note:
10% Senior Card Holder discount applies
All pre-paid weekly booking receive the 7th day free
Other Fees
Washing machines - Gardens Caravan Park 4.00 4.00 M
Washing machines - Southcombe Caravan Park 4.00 4.00 M
Dryers 2.00 2.00 M
SWIMMING POOLS
Mortlake Swimming Pool
Season Memberships
Family (including under 16 years) 160.20 167.00 M
Adults
86.30 90.00 M
Concession 77.00 80.00 M
Children (under 16) 71.80 75.00 M
Daily Admission Charges
Adults
3.80 4.00 M
Children (under 16) 3.00 3.20 M
Spectator
0.70 1.00 M
School Group (per child) 1.20 1.30 M
Macarthur Swimming Pool
Season Memberships
Family (including under 16 years) 92.60 96.00 M
107 Moyne Shire Budget 2016-17
FEES AND CHARGES DESCRIPTION
2015/16 GST
Inclusive$
2016/17 GST
Inclusive $
Pricing Policy
Single season pass 47.80 50.00 M
Daily Admission Charges
Adults 3.80 4.00 M
Children (under 16) 3.00 3.20 M
Reardon Theatre Venue Hire
Community Hire Rates (Not for Profit Activities)
Summer Rate: 1 November - 31 March (No heating usage permissible)
1 hour minimum hire Period 19.10 20.00 P
24 hour period 192.00 200.00 P
Set Up Fee for Long Hire: One full day fee at applicable rate for a maximum of three days unless bookings clash
192.00 200.00 P
Winter Rate: 1 April - 31 October (Heating usage permissible)
1 hour minimum hire Period 25.30 26.00 P
24 hour period 256.00 266.00 P
Set Up Fee for Long Hire: One full day fee at applicable rate for a maximum of three days unless bookings clash
256.00 266.00 P
Commercial Hire Rates (All activities held for profit)
Summer Rate: 1 November - 31 March (No heating usage permissible)
1 hour minimum hire Period 25.30 26.00 P
24 hour period 256.00 266.00 P
Set Up Fee for Long Hire: One full day fee at applicable rate for a maximum of three days unless bookings clash
256.00 266.00 P
Winter Rate: 1 April - 31 October (Heating usage permissible)
1 hour minimum hire Period 31.40 33.00 P
24 hour period 315.00 328.00 P
Set Up Fee for Long Hire: One full day fee at applicable rate for a maximum of three days unless bookings clash
315.00 328.00 P
Bond - Minimal Risk 292.00 304.00 P
Bond - High Risk 1170.00 1217.00 P
Public Liability through Moyne Shire Council - (GST not applicable) 15.60 16.00 P
AGED AND DISABILITY SERVICES FEES
Disabled Parking Permits 5.60 5.80 F
Adult Day Care
Client per day 8.80 9.20 P
108 Moyne Shire Budget 2016-17
FEES AND CHARGES DESCRIPTION
2015/16 GST
Inclusive$
2016/17 GST
Inclusive $
Pricing Policy
HACC Services
Home Care
Single 6.90 7.20 P
Low Income Families(Health Care Card/Additional Family Payment)
Single 6.90 7.20 P
Other (No Health Care Card or benefit recipients)
Single 18.90 45.00 P
Respite (greater than 4 hrs per week)
General Rate 3.20 5.00 P
Personal Care
Single 6.90 7.20 P
Full Cost Care
Post Acute Care
Home Care 50.60 60.50 F
Personal Care 50.60 60.50 F
Home Maintenance 75.00 78.00 F
Community Aged Care Packages
Homecare 39.90 50.00 F
Personal Care 39.90 50.00 F
Respite 39.90 50.00 F
Maintenance of effort 9.80 12.25 P
Home Maintenance 75.00 78.00 P
Home Maintenance
Client per hour 16.20 17.50 P
Meals on Wheels (per meal)
Port Fairy 8.30 8.60 P
Mortlake 8.30 8.60 P
Koroit 8.30 8.60 P
Macarthur 8.30 8.60 P
Post Acute Care 14.50 17.00 F
Community Aged Care Packages 12.40 17.00 F
Child Care Services
Occasional Child Care - Hawkesdale - Commencing 1 January 2017
Child per short 1/2 day 31.00 32.00 P
Child per short 1/2 day - casual 37.00 P
Child per long 1/2 day 52.00 54.00 P
Child per long 1/2 day - casual 59.00 P
109 Moyne Shire Budget 2016-17
FEES AND CHARGES DESCRIPTION
2015/16 GST
Inclusive$
2016/17 GST
Inclusive $
Pricing Policy
Child per day Session 73.00 76.00 P
Child per day Session - casual 81.00 P
Long Day Child Care - Port Fairy - Commencing 1 January 2017
Weekly 421.00 438.00 P
Daily 92.00 96.00 P
Half Daily 47.00 49.00 P
Sessional Kindergarten - Port Fairy - Commencing 1 January 2017
4 year old per term 15 hours per Week 214.00 223.00 P
Chatsworth Occasional Child Care - Commencing 1 January 2017
Full Day 64.50 67.00 P
Hire Fees
Mortlake Community Bus
Community Group Hire $1.00/klm $1.00/klm P
Community Room Hire - Non Profit Community Groups
Hawkesdale Family Services Centre per room
Consulting Room (per day) 48.90 51.00 P
Consulting room (per hour) 12.30 13.00 P
Port Fairy Community Services Centre
Hourly rates
Meeting room 1 Large (per hour) 23.50 24.00 P
Meeting room 2 Medium (per hour) 17.50 18.00 P
Consulting Room (per hour) 11.60 12.00 P
Daily Rates
Meeting room 1 Large (per day) 93.50 97.00 P
Meeting room 2 Medium (per day) 71.00 74.00 P
Consulting Room (per day) 46.00 48.00 P
Meeting Set-Up/Clean Up Costs 54.00 56.00 P
Community Room Hire - Commercial Use
Hawkesdale Family Services Centre per room
Consulting room (per hour) 17.50 18.00 F
Port Fairy Community Services Centre
Meeting room 1 Large (per hour) 29.20 30.00 F
110 Moyne Shire Budget 2016-17
FEES AND CHARGES DESCRIPTION
2015/16 GST
Inclusive$
2016/17 GST
Inclusive $
Pricing Policy
Meeting room 2 Medium (per hour) 23.40 24.00 F
Consulting Room (per hour) 17.50 18.00 F
Meeting Set-Up/Clean Up Costs 54.00 56.00 P
Video Conferencing Hire
Non-profit community groups - charge per half hour (min half hour block) 46.00 48.00 F
Commercial Use - charge per half hour (min half hour block) 70.00 73.00 F
Airstrip Hire
Commercial use of Port Fairy Airstrip Hire/per day 108.00 112.00 F
111 Moyne Shire Budget 2016-17
PLANNING & ENVIRONMENT (FEES & CHARGES) REGULATIONS 2000
All fees listed below are statutory fees (R) set by government regulation. Applications for permits under section 47 The fee for an application for a permit under section 47, other than an application under section 96(1), is the fee set out for an application of that particular class as follows:
Class of application Fee
Class 1 An application for use only. $502
Class 2 An application (other than an application to subdivide land) to develop land or to use and develop land for a single dwelling per lot or to undertake development ancillary to the use of the land for a single dwelling per lot if the estimated cost of development included in the application is more than $10,000 and not more than $100,000. $239
Class 3 An application (other than an application to subdivide land) to develop land or to use and develop land for a single dwelling per lot or to undertake development ancillary to the use of the land for a single dwelling per lot if the estimated cost of development included in the application is more than $100,000. $490
Class 4 An application, other than— (a) an application to undertake development ancillary to the use of the land for a single dwelling per lot; or (b) an application to subdivide land— to develop land if the estimated cost of development included in the application is $10,000 or less. $102
Class 5 An application, other than— (a) a Class 2 application; or (b) a Class 3 application; or (c) an application to subdivide land— to develop land if the estimated cost of development included in the application is more than $10,000 and not more than $250,000. $604
Class 6 An application, other than— (a) a Class 3 application; or (b) an application to subdivide land— to develop land if the estimated cost of development included in the application is more than $250,000 and not more than $500,000. $707
Class 7 An application, other than— (a) a Class 3 application; or (b) an application to subdivide land— to develop land if the estimated cost of development included in the application is more than $500,000 and not more than $1,000,000. $815
112 Moyne Shire Budget 2016-17
Class 8 An application, other than— (a) a Class 3 application; or (b) an application to subdivide land— to develop land if the estimated cost of development included in the application is more than $1,000,000 and not more than $7,000,000. $1,153
Class 9 An application, other than— (a) a Class 3 application; or (b) an application to subdivide land— to develop land if the estimated cost of development included in the application is more than $7,000,000 and not more than $10,000,000. $4,837
Class 10 An application, other than— (a) a Class 3 application; or (b) an application to subdivide land— to develop land if the estimated cost of development included in the application is more than $10,000,000 and not more than $50,000,000. $8,064
Class 11 An application, other than— (a) a Class 3 application; or (b) an application to subdivide land— to develop land if the estimated cost of development included in the application is more than $50,000,000. $16,130
Class 12 An application to subdivide an existing building. $386
Class 13 An application, other than a Class 12 application, to subdivide land into two lots. $386
Class 14 An application to effect a realignment of a common boundary between lots or to consolidate two or more lots. $386
Class 15 An application, other than— (a) a Class 12 application; or (b) a Class 13 application; or (c) a Class 14 application— to subdivide land. $781
Class 16 An application to remove a restriction (within the meaning of the Subdivision Act 1988) over land if the land has been used or developed for more than 2 years before the date of the applications in a manner which would have been lawful under the Planning and Environment Act 1987 but for the existence of the restriction. $249
Class 17 An application (other than a Class 16 application) to— (a) create, vary or remove a restriction within the meaning of the Subdivision Act 1988 (b) create or remove a right of way. $541
113 Moyne Shire Budget 2016-17
Class 18 An application (other than a Class 16 application) to— (a) create, vary or remove an easement other than a right of way; or (b) vary or remove a condition in the nature of an easement other than a right of way in a Crown grant. $404
Combined permit applications The fee for an application for any combination of use, development other than subdivision, subdivision and any matter referred to in classes of application 16, 17 or 18 set out in the table in regulation 7 is the sum arrived at by adding the highest of the fees which would have applied if separate applications had been made plus 50% of each of the other fees which would have applied if separate applications had been made. Fees to amend applications (1) For the purposes of Section 57A(3)(a), the fee for a request to amend an
application for a permit after notice of the application has been given under section 52 is $102 or every class of application (other than a class 4 application) set out in the table in regulation 7.
(2) For the purposes of Section 57A(3)(a), the fee for a request to amend an application to amend a permit after notice of the application has been given under Section 52 is $102 or every class of application (other than a class 5 application) set out in the table in regulation 8B.
114 Moyne Shire Budget 2016-17
Applications for amendments to permits under section 72 The fee for an application to amend a permit under section 72 is the fee set out for an application of that particular class in the following table—
Class of application Fee
Class 1 An application to amend a permit to use land if that amendment is to change the use for which the land may be used. $502
Class 2 An application to amend a permit (other than a permit to develop land or to use and develop land for a single dwelling per lot or to undertake development ancillary to the use of the land for a single dwelling per lot)— (a) to change the statement of what the permit allows; or (b) to change any or all of the conditions which apply to the permit; or (c) in any way not otherwise provided for in this regulation. $502
Class 3 An application to amend a permit (other than a permit to Subdivide land) to develop land or to use and develop land for a single dwelling per lot or to undertake development ancillary to the use of the land for a single dwelling per lot if the estimated cost of any additional development to be permitted by the amendment is more than $10,000 and not more than $100,000. $239
Class 4 An application to amend a permit (other than a permit to Subdivide land) to develop land or to use and develop land for a single dwelling per lot or to undertake development ancillary to the use of the land for a single dwelling per lot if the estimated cost of any additional development to be permitted by the amendment is more than $100,000. $490 Class 5 An application to amend a permit to develop land, other than— (a) a permit to undertake development ancillary to the use of the land for a single dwelling per lot where the total estimated cost of the development originally permitted and the additional development to be permitted by the amendment is not more than $10,000; or (b) a permit to subdivide land— if the estimated cost of any additional development to be permitted by the amendment is $10,000 or less. $102
Class 6 An application (other than a Class 3 application or a Class 4 application) to amend a permit if the estimated cost of any additional development to be permitted by the amendment is more than $10,000 and not more than $250,000. $604
115 Moyne Shire Budget 2016-17
Class 7 An application (other than a Class 4 application) to amend a permit if the estimated cost of any additional development to be permitted by the amendment is more than $250,000 and not more than $500,000. $707
Class 8 An application (other than a Class 4 application) to amend a permit if the estimated cost of any additional development to be permitted by the amendment is more than $500,000. $815
Class 9 An application to amend a permit to— (a) subdivide an existing building; or (b) subdivide land into two lots; or (c) effect a realignment of a common boundary between lots or to consolidate two or more lots. $386
Combined application to amend permit The fee for an application (involving any combination of use, development other than subdivision, subdivision and any matter referred to in class 2 set out in the table in regulation 8B) to amend a permit is the sum arrived at by adding the highest of the fees which would have applied if separate applications to amend the permit had been made plus 50% of each of the other fees which would have applied if separate applications to amend the permit had been made. Combined permit application and planning scheme amendment (1) The fee for an application for a planning permit combined with a request for
amendment of a planning scheme, made in accordance with section 96A, is the sum arrived at by adding the higher of the fees plus 50% of the lower of the fees which would have applied if separate applications had been made.
(2) If the application for a planning permit referred to in sub-regulation (1) is for any combination of use, development other than subdivision, subdivision and any matter referred to in classes of application 16, 17 or 18 set out in the table in regulation 7, the fee for the planning permit for the purposes of the calculation under sub-regulation (1) is the higher of the fees which would have applied if separate applications for planning permits had been made.
Certificates of Compliance The fee for an application for a certificate of compliance under section 97N is $147. Fees to accompany applications for planning certificates under section 198 The fee for an application for a planning certificate under section 198 is $18.20. Determining whether anything has been done to the satisfaction of a responsible authority, Minister, public authority, municipal council or a referral authority If a planning scheme specifies that a matter must be done to the satisfaction of a responsible authority or a referral authority, the fee for determining that matter is $102. Power to waive or rebate the payment of a fee (1) A responsible authority or the Minister may waive or rebate the payment of a fee,
in connection with matters other than an amendment to a planning scheme, in the following circumstances— (a) if an application is withdrawn and a new application is submitted; or (b) if in the opinion of the authority or the Minister the payment of the
prescribed fee is not warranted because— (i) of the minor nature of the consideration of the matter decided; or
116 Moyne Shire Budget 2016-17
(ii) in the opinion of the authority the application or determination imposes on the authority no appreciable burden; or
(iii) in the opinion of the authority the application or determination imposes on the authority a lesser burden than usual; or
(c) if in the opinion of the authority or the Minister the application or determination assists— (i) the proper development of the State, region or municipal district; or (ii) the proper development of part of the State, region or municipal
district; or (iii) the preservation of buildings or places in the State, region or municipal
district which are of historical or environmental interest; or (iv) an application is for land used exclusively for charitable purposes.
(2) A planning authority or the Minister may waive or rebate the payment of a fee for an application for amendment to a planning scheme in the following circumstances— (a) if the application is intended to implement State, regional or local policy; (b) if the application is intended to remove errors or anomalies in the planning
scheme; (c) if the application imposes on the authority or Minister no appreciable burden
or a lesser burden than usual for supplying that service; (d) if an application to amend a planning scheme, to consider submissions, or
to approve an amendment has been withdrawn and a new application submitted;
(e) if the application rewrites and restructures the scheme so that it may be more readily understood, without changing the planning policy;
(f) if the application implements a general review of the planning scheme, is to implement a new use or development strategy, or is otherwise designed to upgrade and improve the scheme in the public interest;
(g) if the application combines more than one separate item into one amendment;
(h) if the application has been made by a person or group of persons standing to gain no financial benefit from the amendment, or is not intended to benefit financially an owner or group of owners or is otherwise in the public interest.
(3) If a planning authority, responsible authority or Minister waives or rebates the
payment of a fee in accordance with this regulation the matters taken into account and which formed the basis of the decision to waive or rebate the fee must be recorded in writing.
117 Moyne Shire Budget 2016-17
Fees for amendments to planning schemes
(1) The fee for— (a) considering a request to amend a planning scheme; and (b) taking action required by Division 1 of Part 3 of the Planning and Environment Act 1987; and (c) considering any submissions which do not seek a change to the amendment; and (d) if applicable, abandoning the amendment in accordance with section 28— is $798
(2) The additional fee for— (a) considering submissions which seek a change to an amendment, and where necessary referring the submissions to a panel; and (b) providing assistance to a panel in accordance with section 158; and (c) making a submission in accordance with section 24(b); and (d) considering the report in accordance with section 27; and (e) after considering submissions and the report in accordance with section 27, if applicable, abandoning the amendment in accordance with section 28— is $798
(3) The additional fee for— (a) adopting an amendment or a part of an amendment in accordance with section 29; and (b) submitting the amendment for approval in accordance with section 31— is $524
(4) The additional fee for— (a) considering a request to approve an amendment in accordance with section 35; and (b) giving notice of approval of an amendment in accordance with section 36— is $798
(5) The fee prescribed in sub-regulation (1) is to be paid to the planning authority by
the person who requested the amendment, at the time of making the request. (6) The fee prescribed in sub-regulation (2) is to be paid to the planning authority by
the person who requested the amendment, before the authority considers the submissions.
(7) The fee prescribed in sub-regulation (3) is to be paid to the planning authority by
the person who requested the amendment, before the authority adopts the amendment.
118 Moyne Shire Budget 2016-17
MOYNE SHIRE COUNCIL FEES & CHARGES
PLANNING FEES Fee Inc GST
Search for old permit documentation per hour $56.20
Extension of Planning Permit $102.00
Secondary Consent $102.00
**When State Government Review of Planning Permit fees is completed, these fees will be increased in line with the same level fee on which this is based.
SUBDIVISION FEE
Subdivision certification fee $100 per application $ 20 per lot
Planning Advertising
Newspaper advertising per advertisement full cost to be passed on to applicant
Letters – in cases of 11 or more letters $ 3.75 per letter
Sign on site if Council is to erect sign $120.00
Section 173 Agreements
Amend or end a Section 173 agreement $570
119 Moyne Shire Budget 2016-17
Appendix B: Budget Processes This section lists the budget processes to be undertaken in order to adopt the Budget in accordance with the Local Government Act 1989 (the Act) and Local Government (Planning and Reporting) Regulations 2014 (the Regulations). Under the Act, Council is required to prepare and adopt an annual budget for each financial year. The budget is required to include certain information about the rates and charges that Council intends to levy as well as a range of other information required by the Regulations which support the Act. The 2016-17 budget, which is included in this report, is for the year 1 July 2016 to 30 June 2017 and is prepared in accordance with the Act and Regulations. The budget includes financial statements being a Comprehensive Income Statement, Balance Sheet, Statement of Changes in Equity, Statement of Cash Flows and Statement of Capital Works. These statements have been prepared for the year ended 30 June 2017 in accordance with the Act and Regulations, and consistent with the annual financial statements which are prepared in accordance with Australian Accounting Standards. The budget also includes information about the rates and charges to be levied, the capital works program to be undertaken, the human resources required, and other financial information Council requires in order to make an informed decision about the adoption of the budget. In advance of preparing the budget, Officers firstly review and update Council's long term financial projections. Financial projections for at least four years are ultimately included in Council's Strategic Resource Plan, which is the key medium-term financial plan produced by Council on a rolling basis. The preparation of the budget, within this broader context, begins with Officers preparing the operating and capital components of the annual budget during January and February. A draft consolidated budget is then prepared and various iterations are considered by Council at briefings during early April. A ‘proposed’ budget is prepared in accordance with the Act and submitted to Council in April for approval ’in principle’. Council is then required to give ’public notice’ that it intends to ’adopt’ the budget. It must give 28 days’ notice of its intention to adopt the proposed budget and make the budget available for inspection at its offices and on its internet web site. A person has a right to make a submission on any proposal contained in the budget and any submission must be considered before adoption of the budget by Council. The final step is for Council to adopt the budget after receiving and considering any submissions from interested parties. The budget is required to be adopted by 30 June and a copy submitted to the Minister within 28 days after adoption. The key dates for the budget process are summarised below:
Budget process Timing
1. Proposed budget submitted to Council for approval 26 April 2016
2. Public notice advising intention to adopt budget 28 April 2016
3. Budget available for public inspection and comment 28 April 2016
4. Submissions period closes 26 May 2016
5. Special Council meeting to receive and hear budget submissions 7 June 2016
6. Ordinary Council meeting to adopt budget 28 June 2016
120 Moyne Shire Budget 2016-17
Appendix C: Glossary
Glossary Act Adjusted underlying surplus (or deficit)
Local Government Act 1989 The adjusted underlying surplus or (deficit) means adjusted underlying revenue less expenditure. It is a measure of financial sustainability of the Council which can be masked by non-recurring items.
Annual budget This document is framed within the Council’s Strategic Resource Plan and sets out the
short term goals and objectives as part of the overall strategic planning framework
Annual operating budget (Budgeted income statement)
The budgeted income statement shows the expected operating result in the forthcoming year with a distinction made between revenue received for operating purposes and revenue received for capital purposes.
Annual report The annual report prepared by a Council under section 131 of the Act
Annual reporting requirements
Annual reporting requirements include the financial reporting requirements of the Act, Accounting Standards and other mandatory professional reporting requirements.
Australian Accounting Standards
Accounting standards are issued from time to by the professional accounting bodies and are applicable to the preparation of general purpose financial reports.
Australian Accounting Standard AAS 27 - Financial Reporting by Local Governments is applicable to all general purpose financial reports prepared by Councils. AAS27 is currently the subject of review by the AASB with the release of Exposure Draft ED 125 - Financial Reporting by Local Governments.
Activity Based Costing
Activity-based costing (ABC) is a costing methodology that identifies activities in an organization and assigns the cost of each activity with resources to all products and services according to the actual consumption by each.
Borrowing strategy
A borrowing strategy is the process by which the Council’s current external funding requirements can be identified, existing funding arrangements managed and future requirements monitored.
Financial Statements
Prepared under section(s) 126(2)(a), 127(2)(a) and / or 131(1)(b) of the Act, standard statements are required in the:
- Strategic resource plan - Budget - Annual report The budgeted financial statements are the: - Comprehensive Income Statement - Balance Sheet - Statement of Changes in Equity - Statement of Cash Flows - Statement of Capital Work
121 Moyne Shire Budget 2016-17
Glossary Budgeted cash position (Budgeted cash flow statement)
The budgeted cash flow statement shows the expected net cash inflows and outflows in the forthcoming year in the form of reconciliation between opening and closing balances of total cash and investments for the year. Comparison is made to the current year’s expected inflows and outflows. The budgeted cash flow statement should be prepared in accordance with the requirements of AASB 107 Cash Flow Statements.
Budget preparation requirement
Under the Act, a Council is required to prepare and adopt an annual budget by 30 June each year.
Capital expenditure
Capital expenditure is relatively large (material) expenditure that produces economic benefits expected to last for more than 12 months. A pre determined ‘threshold’ may be used which indicates the level of expenditure deemed to be material in accordance with Council’s policy. Capital expenditure includes renewal, expansion and upgrade. Where capital projects involve a combination of renewal, expansion and upgrade expenditures, the total project cost needs to be allocated accordingly. Capital expenditure is recorded in the balance sheet as additions to the value of the asset (that is, it is capitalised). This accounting treatment reflects the fact that this expenditure has resulted in the creation of additional value in an asset of discernable magnitude (materiality) which will benefit the community over several years and which has not been ‘used up’ in the year. The asset value is then progressively ’expensed’ or written off to the income statement (operating statement), as its life (or service potential) is used up through the depreciation charge. In this way the total cost/value of the asset is spread over the period in which it is used, the operating result in each period reflecting the consumption of assets and service potential during that period. This best practice guide recommends that capital expenditure be distinguished between new assets (upgrade, expansion, new assets) and asset renewal.
Capital performance statement)
This statement shows the internal and external funds for the budget year and forecast which will be used to fund capital works projects and the total capital works expected to be completed in comparison to the budget.
Capital renewal
Capital renewal expenditure is expenditure on an existing asset, which returns the service potential or the life of the asset, up to, that which it had originally. It is periodically required expenditure, relatively large (material) in value compared with the value of the components of the asset being renewed. As capital renewal expenditure reinstates existing service potential, it has no impact on revenue, but may reduce future operating and maintenance expenditure if completed at the optimum time.
Capital works budget (Budgeted capital works statement)
The capital works budget shows the expected internal and external funding for capital works program and the total proposed capital works program for the forthcoming year with a comparison with forecast actual for the current year.
Capital works program
Capital works projects that will be undertaken during the budget year.
122 Moyne Shire Budget 2016-17
Glossary Council Plan This document sets out the medium term goals and objectives as part of the overall
strategic planning framework and strategic resource plan and is prepared under section 125 of the Act. The resources required to achieve the Council plan are detailed in the Strategic Resource Plan. As a minimum, a Council plan must include: -the strategic objectives of the Council -strategies for achieving those objectives for at least the next four years -strategic indicators for monitoring the achievement of those objectives -strategic resource plan
Community satisfaction survey
A survey conducted on an annual basis by every Council.
Current year rate increase (Rating strategy)
A statement included in the budget quantifying the amount of the rate change for the forthcoming year and disclosing any significant factors influencing the rate change.
Discretionary reserves
Discretionary reserves are funds earmarked by Council for various purposes. Councils can by resolution change the purpose of these reserves.
External funding sources (Analysis of capital budget)
External funding sources relate to capital grants or contributions, which will be received from parties external to the Council. It also includes the proceeds of assets sold to fund the capital works program.
External influences in the preparation of a budget
Matters arising from third party actions over which Council has little or no control e.g. change in legislation
Financial sustainability
A key outcome of the strategic resource plan. Longer term planning is essential in ensuring that a Council remains financially sustainable in the long term.
Financing activities
Financing activities means those activities which relate to changing the size and composition of the financial structure of the entity, including equity, and borrowings not falling within the definition of cash.
Infrastructure Physical assets of the entity or of another entity that contribute to meeting the public’s
need for access to major economic and social facilities and services.
Infrastructure strategy
An infrastructure strategy is the process by which the Council’s current infrastructure and ongoing maintenance requirements can be identified, budgeted capital works implemented and future developments monitored.
123 Moyne Shire Budget 2016-17
Glossary The key objective of an infrastructure strategy is to maintain or preserve Council’s existing assets at desired condition levels. If sufficient funds are not allocated to asset preservation then Council’s investment in those assets will reduce, along with the capacity to deliver services to the community.
Internal funding sources (Analysis of capital budget)
Internal sources relate to cash and investments held in reserves or which are uncommitted and cash that will be generated from the operations of Council during the budget year. The latter should equate to the cash inflows from operating activities less capital revenue.
Internal influences in the preparation of a budget
Matters arising from Council actions over which there is some element of control (e.g. approval of unbudgeted capital expenditure).
Investing activities
Investing activities means those activities which relate to acquisition and disposal of non-current assets, including property, plant and equipment and other productive assets, and investments not falling within the definition of cash.
Key assumptions
When preparing a budgeted balance sheet of financial position, key assumptions upon which the statement has been based should be disclosed in the budget to assist the reader when comparing movements in assets, liabilities and equity between budget years.
Key budget outcomes
The key activities and initiatives that will be achieved in line with the Council plan.
Key financial indicators
A range of ratios and comparisons of critical financial data over a period of years allowing a reader to gain a better understanding of key measures, such as indebtedness and liquidity which are often undisclosed when financial information is presented in standard statement format.
Operating expenses / Assessment
This ratio measures the average operational spending (as drawn from the income statement) on a per assessment basis. It should be noted that for this ratio to be meaningful, operational expenditure should be adjusted to remove non-operational items such as granted assets from developers any budgeted revaluation income.
Rate revenue/ Total revenue
This ratio measures Council’s reliance on rate revenue as its principal source of funding. Increasing trends in this ratio will highlight that growth in rate revenue is frequently higher than what is able to be achieved in Fees and Grant revenue.
Rate revenue / Assessment
This ratio provides an illustration of the average rates paid on a per assessment basis across the municipality. It should be noted that this measure does not differentiate between residential and commercial ratepayers and does not represent either an average residential or commercial rate.
Debt servicing / Total revenue
This ratio contrasts the amount of interest expense that Council is incurring on its interest bearing liabilities as a percentage of the total revenue base. The Department of Victorian Communities (DVC) has established a prudential maximum of 5% in this indicator.
Grants/ Total revenue
124 Moyne Shire Budget 2016-17
Glossary This ratio provides an indication of the percentage of total revenue that is comprised of grant income. Falling percentages will indicate that grant revenue is not keeping pace with growth in total revenue and will most probably link to increasing reliance on rate revenue.
Fees and charges / Total revenue
This ratio provides an indication of the percentage of total revenue that is comprised of fees and charges income. Falling percentages will indicate that fees and charges revenue is not keeping pace with growth in total revenue and will most probably link to increasing reliance on rate revenue.
Indebtedness / Rate revenue
This ratio measures the total amount of interest bearing liabilities compared to the annual rates levy. This debt indicator is one of the three debt measures used by DVC when considering applications for loan borrowings. The prudential limit is 80%.
Key financial indicators continued
Underlying surplus / Total assets This ratio indicates the contribution the underlying operational position makes to the net asset base of Council. Deficit ratios will highlight the percentage of total assets that is being eroded on annual basis by the operational activities of Council. Surplus ratios will highlight the additional contribution that is made to net asset base. Underlying surplus refers to the operational outcome as assessed in the income statement, adjusted for non-operational items such as; revaluation income and expenses, asset write offs and the net gain/loss on sale of assets.
Total assets / Assessment This ratio expresses the total assets that Council holds on a per assessment basis.
Current assets / Current liabilities Otherwise known as the working capital ratio, this indicator expresses Council’s short-term ability to meet its liquidity requirements within the current financial year. Ratio’s below or nearing 100% indicate that Council may not be able to meet short-term liabilities.
Total liabilities / Assessment This ratio expresses the sum total of current liabilities and non current liabilities expressed on a per assessment basis.
Capital outlays / Total cash outflows This ratio draws the amount of projected cash outflows from the cash flow statement to be expended on the acquisition of property, plant and equipment (inclusive of infrastructure expenditure) as a percentage of all cash outflows. Declining trends may indicate that Council is not or will not in the future be able to adequately fund asset renewal as required or deliver required new facilities.
Capital outlays / Rate revenue This ratio represents the capital outlays as a percentage of rate revenue and therefore Council’s relative ability to convert rate revenue into capital works. The outcomes in this ratio will be influenced by capital grants.
Capital renewal expenditure / Total depreciation As distinct from other capital ratios, this indicator looks solely at capital renewal
125 Moyne Shire Budget 2016-17
Glossary expenditure and excludes capital spending on new assets. By contrasting this ratio against total depreciation, the outcome provides a broad level overview on whether Council is able to achieve a result in excess of 100%. This is a useful indicator but given depreciation may not always represent asset consumption on an annual basis; care should be used in its interpretation.
Legislative framework
The Act, Regulations and other laws and statutes which set a Council’s governance and reporting requirements.
Local Government (Planning and Reporting) Regulations 2014
The objective of these Regulations, made under section 243 of the local Government Act 1989 and which come into operation on 18 April 2014, is to prescribe: (a) the content an preparation of the financial statements of a Council (b) the performance indicators and measures to be included in a budget, revised budget and annual report of a Council (c) the information to be included in a Council Plan, Strategic Resource Plan, budget, revised budget and annual report (d) other matters required to be prescribed under Parts 6 and 7 of the Act.
New assets New assets or capital expenditure does not have any element of expansion or upgrade
of existing assets. New capital expenditure may or may not result in additional revenue for Council and will result in an additional burden for future operation, maintenance and capital renewal.
Non financial resources
Resources of a non financial nature (such as human resources, information systems and processes, asset management systems) which are consumed by a Council in the achievement of its strategic resource plan goals
Operating activities
Operating activities means those activities that relate to the provision of goods and services.
Operating budgeted income statement
The budgeted income statement shows the expected operating result in the forthcoming year compared to the forecast actual result in the current year. The budgeted statement income statement should be prepared in accordance with the requirements of AASB 101 - Presentation of Financial Statements in accordance in the new International Financial Reporting Standard.
Operating expenditure
Operating expenditure is defined as consumptions or losses of future economic benefits, in the form of reductions in assets or increases in liabilities; and that result in a decrease in equity during the reporting period.
Operating revenue
Operating revenue is defined as inflows or other enhancements, or savings in outflows of future economic benefits, in the form of increases in assets or reductions in liabilities; and that result in an increase in equity during the reporting period.
Performance Statement
Performance statement prepared by a Council under section 131 of the Act. A performance statement must be included in the annual report of a Council and include the results of the prescribed service outcome indicators, financial performance indicators and sustainable capacity indicators for the financial year.
126 Moyne Shire Budget 2016-17
Glossary Prudential ratios and thresholds (Borrowing strategy)
Used by the Department for Victorian Communities in assessing a Council’s borrowing capacity as part of the annual Australian Loan Council borrowing allocation. Working Capital Ratio (to assess Council's ability to meet current commitments) The ratio expresses the level of current assets the Council has available to meet its current liabilities.
Debt management servicing costs/Revenue (to identify the capacity of Council to service its outstanding debt)
Debt servicing costs refer to the payment of interest on loan borrowings, finance lease, and bank overdraft.
The ratio expresses the amount of interest paid as a percentage of Council's total revenue.
Debt expense liabilities/Realisable assets (to identify Council's exposure to debt)
For the purposes of the calculation of financial ratios, realisable assets are those assets which can be sold and which are not subject to any restriction on realisation or use. The following assets are excluded from total assets when calculating Council's realisable assets:
land and buildings on Crown land; restricted assets; heritage assets; total infrastructure assets; and Council's investment in associate.
This ratio enables assessment of Council's solvency and exposure to debt. Total indebtedness refers to the total liabilities of Council. Total liabilities are compared to total realisable assets which are all Council assets not subject to any restriction and are able to be realised. The ratio expresses the multiple of total liabilities for each dollar of realisable assets.
Rate structure (Rating strategy)
Site value (SV), capital improved value (CIV) or net annual value (NAV) are the main bases upon which rates will be levied. These should be detailed in the budget statement.
Rating strategy
A rating strategy is the process by which the Council’s rate structure is established and how the quanta of rate change has been determined, taking into consideration longer term philosophy issues and framework.
Regulations Local Government (Finance and Reporting) Regulations 2004.
Restricted funds and discretionary reserves
Monies set aside for statutory and discretionary purposes.
Revised budget
Section 128 of the Act permits a Council to prepare a revised budget if circumstances arise which cause a material change in the budget and which affects the financial operations and position of the Council.
127 Moyne Shire Budget 2016-17
Glossary Road Management Act
The purpose of this Act which came into operation from 1 July 2004 is to reform the law relating to road management in Victoria and to make relating amendments to certain Acts, including the local Government Act 1989.
Service delivery (in Strategic Resource Plan))
A key outcome of a strategic resource plan, service delivery must be linked with performance strategies in order to assess the adequacy of service delivery and the impact on long term budget preparation.
Statutory reserves
Statutory reserves are funds set aside for specified statutory purposes in accordance with various legislative and contractual requirements. These reserves are not available for other purposes.
Strategic planning framework
A “community owned” document or process which identifies the long term needs and aspirations of the Council, and the medium and short term goals and objectives which are framed within the long term plan.
Strategic resource plan (SRP)
The Act requires that a Council plan should include a strategic resource plan that includes financial and non-financial resources including human resources.
The strategic resource plan outlines the resources required to achieve the Council
plan. As a minimum a strategic resource plan must include in respect of at least the next four years:
-standard statements describing the required financial resources, -statements describing the required non-financial resources – including human
resources. Such planning is essential in ensuring that an organisation remains financially
sustainable in the long term. The annual budget should be consistent with the first projected year of a strategic resource plan.
Sustainability index (Infrastructure strategy)
The sustainability index is a means of measuring a Council’s performance in the area of infrastructure preservation. This is the proportion of the total asset value consumed compared to the amount spent in preserving the asset on an annual basis.
Valuations of Land Act 1960
The Valuations of Land Act 1960 requires a Council to revalue all rateable properties every two years.
Working capital
Working capital represents funds that are free of all specific Council commitments and are available to meet daily cash flow requirements and unexpected short term needs.