+ All Categories
Home > Documents > 2019 - 2023 Five Year Plan

2019 - 2023 Five Year Plan

Date post: 05-Oct-2021
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
36
Rev. 5/1/2019 Page 1 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202 5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLAN DISTRICT WIDE 2019 - 2023 Tort Operations and Maintenance Site Improvement (paid by construction accounts) School/Principal Grant Funded Plainfield Academy New HVAC System - complete facility 2015 - 2016 C 2,029,250.00 $ Surveillance system outdoors & indoor halls and gym 2015 - 2016 A 60 41,500.00 $ Rusted entryway doors C 2015 - 2016 A 60 15,000.00 $ Lighting upgrade outside LED (PSD 202 maintenance) 2016 - 2017 A 60 6,100.00 $ Painting work 2016 - 2017 A O&M 1,500.00 $ 1,500.00 $ 1,500.00 $ 1,500.00 $ 1,500.00 $ Asphalt work 2016 -2017 C 50,000.00 $ Gymnasium ceiling replacement 2017 - 2018 C 100,000.00 $ Gymnasium & offices window replacement 2017 - 2018 B 49,500.00 $ Classroom door replacement 2017 - 2018 B 145,000.00 $ (4) Washroom & basement window replacement 2017 - 2018 A 60 18,200.00 $ 10 year Life Safety 2017 - 2018 C 12,000.00 $ Mill gym floor refinish lines/refinish floor 2017 - 2018 B 25,000.00 $ Clean and refinish gym floor 2017 - 2018 C 1,500.00 $ Asbestos three year compliance 2017 - 2018 C 750.00 $ Concrete work 2017 - 2018 A 60 6,500.00 $ Paint Gym Ceiling 2018 - 2019 B 18,000.00 $ Flashing LED lights exterior 2018 - 2019 B 15,600.00 $ Scoreboard LED wireless 2018 - 2019 B 12,000.00 $ Gym lighting LED 2018 - 2019 B 9,000.00 $ 2023 SCHOOL PROJECT DESCRIPTION, LOCALE INITIAL REPORTING YEAR STATUS C - Completed PRIORITY LEVEL A - High B - Medium C - Low FUND ALLOCATION FUTURE ESTIMATED 2019 2020 2021 2022
Transcript
Page 1: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 1 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

Plainfield AcademyNew HVAC System - complete facility 2015 - 2016 C 2,029,250.00$ Surveillance system outdoors & indoor halls and gym 2015 - 2016 A 60 41,500.00$ Rusted entryway doors C 2015 - 2016 A 60 15,000.00$ Lighting upgrade outside LED (PSD 202 maintenance) 2016 - 2017 A 60 6,100.00$ Painting work 2016 - 2017 A O&M 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ Asphalt work 2016 -2017 C 50,000.00$ Gymnasium ceiling replacement 2017 - 2018 C 100,000.00$ Gymnasium & offices window replacement 2017 - 2018 B 49,500.00$ Classroom door replacement 2017 - 2018 B 145,000.00$ (4) Washroom & basement window replacement 2017 - 2018 A 60 18,200.00$ 10 year Life Safety 2017 - 2018 C 12,000.00$ Mill gym floor refinish lines/refinish floor 2017 - 2018 B 25,000.00$ Clean and refinish gym floor 2017 - 2018 C 1,500.00$ Asbestos three year compliance 2017 - 2018 C 750.00$ Concrete work 2017 - 2018 A 60 6,500.00$ Paint Gym Ceiling 2018 - 2019 B 18,000.00$ Flashing LED lights exterior 2018 - 2019 B 15,600.00$ Scoreboard LED wireless 2018 - 2019 B 12,000.00$ Gym lighting LED 2018 - 2019 B 9,000.00$

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

Page 2: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 2 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

Plainfield CentralReplace 5 rooms of carpeting - 7 rooms per yr. 2010 - 2011 C 20,000.00$ Repair/replace curtain in main gym and fieldhouse (patched 12 and 13) 2011 - 2012 C 25,000.00$ Move dumpster and provide pavement for two trucks. Provide door to hall 2011 - 2012 A 60 30,000.00$ Create an outdoor locker/storage area 2011 - 2012 B 1,000,000.00$ Repair drainage on freshmen baseball fields 2012 - 2013 C 75,000.00$ Replace tablet arms in auditorium (removed) 2013 - 2014 B 130,000.00$ Concrete work 2013 - 2014 A 60 8,000.00$ 8,000.00$ 8,000.00$ 8,000.00$ Locker electrostatic P.E. girls 2013 - 2014 A 60 20,000.00$ 20,000.00$ Install bottom and mid rail to tennis fence 2014 - 2015 A 60 8,500.00$ Stage lighting to LED 2016 - 2017 A 60 75,000.00$ Auditorium lighting to LED 2016 - 2017 C 155,000.00$ Asphalt work 2016 - 2017 C 150,000.00$ Painting 2016 - 2017 A O&M 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 2,000.00$ Repairs to outdoor bleachers (portable) 2016 - 2017 A 60 28,000.00$ Lighting upgrade outside LED (PSD 202 maintenance) 2016 - 2017 A O&M 168,500.00$ 87,102.00$ Media center doors to courtyard 2017 - 2018 C 18,000.00$ Media Center paver patio with tables and sitting wall 2017 - 2018 C 25,000.00$ Thermostat replacement 2017 - 2018 A 60 10,000.00$ Replace freshman center chiller 2017 - 2018 A 60 240,000.00$ Clean and refinish main gym 2017 - 2018 C 2,500.00$ 2,500.00$ Clean and refinish freshman center gym 2017 - 2018 A O&M 2,000.00$ 2,000.00$ Paint gym all 2017 - 2018 B 18,000.00$ Paint fieldhouse all 2017 - 2018 C 30,000.00$ Repaint press box 2017 - 2018 C 3,000.00$ Staff bathroom partition replace 2017 - 2018 B $ ?Replacement aluminum door & frames "G" & "H" 2017 - 2018 B $Computer Equipment Video Score Board 2017 - 2018 C 85,000.00$ Paint Freshman Gym 2018 - 2019 B O&M 18,000.00$ Auditorium Rigging inspection 2018 - 2019 A 60 10,000.00$ Flashing LED lights exterior 2018 - 2019 B 15,600.00$ Surveillance System (new number) 2018 - 2019 B 180,000.00$ Turf Replacement 2018 - 2019 C(2031) 800,000.00$ Replace counter tops 2018 - 2019 C $Band Pathway 2018 - 2019 A 60 24,999.00$ Window Screens 2018 - 2019 A O&M 10,000.00$ Clean and fire treatment auditorium curtain 2018 - 2019 C 20,000.00$ HVAC remodel 4 phase project 2018 - 2019 C 4,000,000.00$ 4,000,000.00$ 10 year life safety survey Freshman Center 2018 - 2019 C 20,000.00$ 10 year life safety survey HS 2018 - 2019 C 46,000.00$

Page 3: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 3 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

Plainfield EastImprovements to practice field 2011 - 2012 B 70,000.00$ Replace carpet - 7 rooms per year 2012 - 2013 C 25,000.00$ Curb removal - FH garage door 2014 - 2015 A 60 15,500.00$ Damper covers - FH, main gym 2014 - 2015 B 2,500.00$ Scoreboard - FH - move court 2 to Court 3 2014 - 2015 B 1,000.00$ Lightning alert and warning system 2015 - 2016 B 6,668.00$ Fieldhouse overhead doors 2015 - 2016 B 30,000.00$ Lighting upgrade outside LED (PSD 202 maintenance) 2016 - 2017 B O&M 314,350.00$ 170,142.00$ Paint classrooms 2016 - 2017 A O&M 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 2,000.00$ Concrete work 2016 - 2017 A 60 8,000.00$ 8,000.00$ Asphalt work 2016 - 2017 C Tort 180,000.00$ Auditorium entrance 2017 - 2018 B 3,500.00$ 10 Year Life Safety Survey 2017 - 2018 C(2028) O&M 68,000.00$ Stage lighting to LED 2017 - 2018 A 60 75,149.00$ Auditorium house lighting to LED 2017 - 2018 B 155,000.00$ Paint gym all the way-up 2017 - 2018 A O&M 24,999.00$ Mill gym floor repaint/refinish floor 2017 - 2018 C 25,000.00$ Clean and refinish main gym floor 2017 - 2018 C 2,500.00$ 2,500.00$ New VCT main hall/lobby 2017 - 2018 C 25,000.00$ 25,000.00$ Attendance office replace carpet 2017 - 2018 C 28,000.00$ Main office replace carpet 2017 - 2018 C 10,000.00$ Student services office replace carpet 2017 - 2018 C 26,000.00$ Attendance office replace carpet with Optima tile 2017 - 2018 C 42,000.00$ Main office replace carpet with Optima tile 2017 - 2018 C 16,000.00$ Student services office replace carpet with Optima tile 2017 - 2018 C 39,000.00$ Create outdoor storage area 2017 - 2018 C 1,000,000.00$ New signs & posts for traffic signs 2017 - 2018 C 10,000.00$ Auditorium Rigging inspection 2018 - 2019 A 60 10,000.00$ Flashing LED lights exterior 2018 - 2019 B 15,600.00$ Surveillance System (new number) 2018 - 2019 B 142,000.00$ Turf Replacement 2018 - 2019 C(2032) 800,000.00$ Clean fire treat auditorium curtain 2018 - 2019 C 20,000.00$ Computer Equipment Video Score Board 2018 - 2019 C 85,000.00$ Clean and restripe indoor fieldhouse track area 2018 - 2019 A 60 12,500.00$

Page 4: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 4 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

Plainfield NorthMove scoreboard in fieldhouse 2011 - 2014 A O&M 1,000.00$ Install auto handicap door opener - entrance I (STARS Program) 2014 - 2015 C 8,000.00$ Carpet replacement- 7 rooms 2014 - 2015 B 25,000.00$ Alt replace additional 50' by 20' of sidewalk at entrance "N" concrete work 2014 - 2015 B 13,000.00$ Resurface tennis courts 2015 - 2016 C 80,000.00$ Lightning alert and warning system 2015 - 2016 B 6,668.00$ Lighting upgrade fieldhouse/gym/MPR 2016 - 2017 A 60 50,000.00$ Repair main gym bleachers 2016 - 2017 A 60 9,100.00$ Concrete work 2016 - 2017 A 60 10,000.00$ 8,000.00$ 8,000.00$ Lighting upgrade outside LED (PSD 202 maintenance) 2016 - 2017 A O&M 314,350.00$ 163,522.00$ Painting classrooms 2016 - 2017 A O&M 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 2,000.00$ Pathway student parking 2017 - 2018 C 100,000.00$ Pathways to baseball/softball subdivision 2017 - 2018 A 60 75,000.00$ 75,000.00$ Stage lighting to LED 2017 - 2018 A 60 75,000.00$ 100,000.00$ Auditorium lighting to LED 2017 - 2018 B 155,000.00$ Clean and refinish main gym floor 2017 - 2018 C O&M 2,500.00$ 2,500.00$ Create outdoor storage area 2017 - 2018 C 1,000,000.00$ New signs & posts for traffic signs 2017 - 2018 A O&M 10,000.00$ Room PE office & Athletic office to Lv+tile 2017 - 2018 A 60 16,000.00$ Auditorium Rigging inspection 2018 -2019 A 60 10,000.00$ Flashing LED lights exterior 2018 -2019 B 15,600.00$ Asphalt work 2018 - 2019 C Tort 180,000.00$ Surveillance System (new number) 2018 -2019 B 14,200.00$ Parking Lot Extension 2018 -2019 C 112,000.00$ Turf Replacement 2018 -2019 C(2032) 800,000.00$ Principal Sidewalk 2018 -2019 A Principal 6,000.00$ Door N street at entrance paint 2018 -2019 A O&M 1,500.00$ Clean and fire treat auditorium curtain 2018 -2019 C 20,000.00$ Epdm roof replacement 2 phases 2018 -2019 C 3,000,000.00$ Computer Equipment Video Score Board 2018 -2019 C 85,000.00$ Clean and restripe indoor fieldhouse track area 2018 - 2019 A 60 12,500.00$ 10 year life safety survey 2018 - 2019 C(2025) 66,000.00$

Page 5: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 5 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

Plainfield SouthImprovements to softball varsity field, needs to be regraded 2011 - 2012 B $ 30,000.00 Electrostatic paint PE lockers 2011 - 2012 C $ 20,000.00 Repair drainage on freshman baseball field 2012 - 2013 B $ 25,000.00 Storage racks for book room 2013 - 2014 C $ 15,000.00 Carpet replacement - 7 rooms per year 2013 - 2014 C $ 25,000.00 Resurface/repair tennis courts (safety) 2014 - 2015 C 80,000.00$ Address issue of curbs, road repairs - drive North of soccer fields, drive along tennis courts 2014 - 2015 C 3,000,000.00$ New discuss cage (Fenced like East) 2014 - 2015 B 11,000.00$ Lightning alert and warning system 2015 - 2016 C 6,668.00$ Paint classrooms 2016 - 2017 A O&M 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 2,000.00$ Repair main gym bleachers 2016 - 2017 A 60 9,500.00$ Asphalt work 2016 - 2017 C Tort 180,000.00$ 10 Year Life Safety 2017 - 2018 C 62,900.00$ Roof work EPDM flat roof area 2017 - 2018 B 2,000,000.00$ 2,000,000.00$ Pathways to softball fields from south lot 2017 - 2018 A Tort 72,000.00$ Stage lighting to LED 2017 - 2018 A 60 75,000.00$ Auditorium lighting to LED 2017 - 2018 B 150,000.00$ Clean and refinish main gym floor 2017 - 2018 C O&M 2,500.00$ 2,500.00$ Recondition cooling towers 2017 - 2018 A 60 24,999.00$ Replace (3) net posts Tennis 2017 - 2018 A 60 12,000.00$ Computer Equipment Video Score Board 2017 - 2018 C 85,000.00$ Concrete work 2017 - 2018 C 8,000.00$ 8,000.00$ 8,000.00$ Create an outdoor storage area 2017 - 2018 C 1,000,000.00$ Replace stair treds on staircases at entrances C, H & I 2018 - 2019 A 60 21,000.00$ Auditorium Rigging inspection 2018 - 2019 A 60 10,000.00$ Flashing LED lights exterior 2018 - 2019 B 15,600.00$ Surveillance System (new number) 2018 - 2019 B 142,000.00$ Turf Replacement 2018 - 2019 C(2031) 800,000.00$ West Stadium building lockers electrostatic 2018 - 2019 B $Fieldhouse lighting LED 2018 - 2019 A 50,000.00$ Rubber to washrooms 4x4 (16) 2018 - 2019 C $Clean and fire treat auditorium curtain 2018 - 2019 C 20,000.00$ Wall packs replaced LED exterior 2018 - 2019 A 60 10,000.00$ Clean and restripe indoor fieldhouse track area 2018 - 2019 A 60 12,500.00$

Page 6: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 6 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

Aux SableReplace/repair bus drop-off doors - rusted door frames I & J 2013 - 2014 A 60 20,000.00$ Glycol to 2 pipe HVAC system 2014 - 2015 B 16,500.00$ Lightning alert and warning system 2015 - 2016 B 6,668.00$ Lighting upgrade outside LED (PSD 202 maintenance) 2016 - 2017 A 60 81,600.00$ 35,182.00$ Paint classrooms 2016 - 2017 A O&M 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ Asphalt work road 2016 - 2017 A Tort 11,980.00$ 10,000.00$ 10,000.00$ Asphalt work 2017 - 2018 A Tort 57,000.00$ 90,000.00$ Carpet replacement 2nd floor 1/2 2017 - 2018 A 60 15,000.00$ Storage in front by band room 2017 - 2018 C 425,000.00$ Clean refinish gym floor 2017 - 2018 A O&M 1,750.00$ 1,750.00$ 1,750.00$ Concrete work 2017 -2018 CFlashing LED lights exterior 2018 - 2019 B 8,600.00$ Surveillance System (new number) 2018 - 2019 B 71,000.00$ Replace rusted doors and frame H&G 2018 - 2019 B 20,000.00$ Sound system gym 2018 - 2019 C 22,000.00$ 10 year life safety survey 2018 - 2019 C(2028)Roof work shingle 2018 - 2019 C 450,000.00$ Roof work low slope 3 ply & Barrel 2018 - 2019 C 825,000.00$

Page 7: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 7 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

Drauden PointRepair wet turf area at entrance to fields 2011 - 2012 B 1,500.00$ Main Office carpet replaced 2013 - 2014 A 60 10,000.00$ 25,000.00$ Carpet upstairs replaced rooms to LVT 2013 - 2014 A 60 20,000.00$ 25,000.00$ Floor tile repairs 2014 - 2015 B 3,000.00$ Lightning alert and warning system 2015 - 2016 B 6,668.00$ Roof work EPDM flat roof 2015 - 2016 A 60 614,700.00$ Roof work steep slope shingle replacement 2015 - 2016 B 400,000.00$ Lighting upgrade outside LED (PSD 202 maintenance) 2016 - 2017 A 60 88,700.00$ 40,435.00$ Paint classrooms 2016 - 2017 A O&M 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ Replace carpet 2nd floor hall (2nd 1/2) 2017 - 2018 A 60 17,500.00$ Paint roof library "Vegas Gold" 2017 - 2018 C 12,000.00$ Storage in front by band room 2017 - 2018 C 425,000.00$ Clean and refinish gym floors 2017 - 2018 C 1,800.00$ 1,800.00$ Asphalt work 2017 - 2018 C 90,000.00$ Flashing LED lights exterior 2018 - 2019 B 8,600.00$ Surveillance System (new number) 2018 - 2019 B 71,000.00$ Tuck Pointing 2018 - 2019 A 60 20,000.00$ Replace rusted entry G 2018 - 2019 C 10,000.00$ Replace rusted entry I & J 2018 - 2019 B 20,000.00$ Chiller replacement 2018 - 2019 C 240,000.00$ Classroom 100 replace carpet to LVT 2018 - 2019 A 60 6,500.00$ Sound system gym 2018 - 2019 C 22,000.00$ Sound system cafeteria 2018 - 2019 C 20,000.00$ 10 year life safety 2018 - 2018 C 18,000.00$

Page 8: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 8 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

Heritage GroveImprovements to sports field by side area 2012 - 2013 C 70,000.00$ Install wrestling mat hoist 2013 - 2014 C 18,000.00$ Resurface sewing cabinets 2015 - 2016 C 6,000.00$

Painting in all Core Hallways - Trim and doorways 2015 - 2016 B 2,000.00$ Lightning alert and warning system 2015 - 2016 C 6,668.00$ Asphalt work 2016 - 2017 B 85,000.00$ Paint classrooms 2016 - 2017 A O&M 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ Lighting upgrade outside LED (PSD 202 maintenance) 2016 - 2017 A 60 56,200.00$ 28,739.00$ Parking lot light base replacement 2016 - 2017 C 6,985.00$ LVT floor tile for rooms 104, 106 & 110 2017 - 2018 A 60 24,999.00$ 20,000.00$ 13,000.00$ Storage to front by band room 2017 - 2018 C 425,000.00$ Clean and refinish gym floor 2017 - 2018 C O&M 1,800.00$ 1,800.00$ PE locker paint electrostatic 2017 - 2018 C 20,000.00$ Flashing LED lights exterior 2018 - 2019 B 8,600.00$ Surveillance System (new number) 2018 - 2019 B 71,000.00$ Replace rusted entry G 2018 - 2019 C 10,000.00$ Replace rusted entry I & J 2018 - 2019 C 20,000.00$ Concrete work back TL 2018 - 2019 B 12,000.00$ 8,000.00$ 2nd floor LVT 1/2 FVT 2018 - 2019 B 21,000.00$ 15,000.00$ Concrete Pad in front like DP 2018 - 2019 A Principal 10,000.00$ Scoreboard replacements 2018 - 2019 C 9,000.00$ Sound system gym 2018 - 2019 B 22,000.00$ Sound system cafeteria side 2018 - 2019 C 20,000.00$ 10 year life safety survey 2018 - 2019 C 18,000.00$

Page 9: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 9 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

Indian TrailAdd storage for wrestling mats - gym area 2011 - 2012 B 150,000.00$ Replace main office carpet 2012 - 2013 B 50,000.00$ Replace piping for domestic hot & cold water 2014 - 2015 B 300,000.00$ Replace boilers 2014 - 2015 B 190,000.00$ 190,000.00$ Floor tile repairs 2014 - 2015 C 3,000.00$ Lightning alert and warning system 2015 - 2016 B 6,668.00$ Air condition to gymnasium 2015 - 2016 B 88,000.00$ Lighting upgrade outside LED (PSD 202 maintenance) 2016 - 2017 A 60 15,000.00$ 7,980.00$ Paint classrooms 2016 - 2017 A O&M 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ Replace chiller 2017 - 2018 A 60 240,000.00$ Asphalt work 2017 - 2018 C 70,000.00$ Clean and refinish gym floor 2017 - 2018 A O&M 1,500.00$ 1,500.00$ 1,500.00$ Asbestos three year compliance 2017 - 2018 C 750.00$ Replace mirrors 2017 - 2018 A O&M 5,000.00$ Replace heating/cooling valves for uninvents 2017 - 2018 A 60 21,000.00$ Paint gym all 2017 - 2018 C 18,000.00$ Replace Entrance "A" street door/frame 2018 - 2019 A 60 24,999.00$ Concrete work by Gym 2018 - 2019 B 12,000.00$ Flashing LED lights exterior 2018 - 2019 B 6,600.00$ Surveillance System (new number) 2018 - 2019 B 61,500.00$ Replace scoreboards LED 2018 - 2019 B 9,000.00$ Replace Gym Sound System 2018 - 2019 C 23,000.00$ 10 year life safety survey 2018 - 2019 C 20,000.00$

Page 10: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 10 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

Ira JonesBroken tiles by entryways A, F, G and K 2014 - 2015 C Settling issueDoor frames B, K, G and J needs to be repaired or replaced 2014 - 2015 Settling issueBegin replacing carpet starting 8th grade hallway 2014 - 2015 Settling issueWall cracks: Across from 220, corner of 226, across from the elevator downstairs, 2014 - 2015 Settling issueLightning alert and warning system 2015 - 2016 B 6,668.00$ Roof work EPDM flat roof 2015 - 2016 750,000.00$ Asphalt work 2016 - 2017 A Tort 92,000.00$ 100,000.00$ Lighting upgrade outside LED (PSD 202 maintenance) 2016 - 2017 A 60 82,200.00$ 132,244.00$ Paint classrooms 2016 - 2017 A O&M 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ Storage to front by band 2017 - 2018 C 425,000.00$ Clean and refinish gym floor 2017 - 2018 C O&M 1,800.00$ 1,800.00$ Concrete work 2017 - 2018 A 60 8,000.00$ 8,000.00$ 8,000.00$ Paint gym all 2017 - 2018 C 18,000.00$ Light pole base covers 2018 - 2019 A 60 18,000.00$ Flashing LED lights exterior 2018 - 2019 B 8,600.00$ Surveillance System (new number) 2018 - 2019 B 71,000.00$ Doors and frame replacement I, J 2018 - 2019 C 20,000.00$ Doors and frame replacement B, K 2018 - 2019 B 20,000.00$ Doors and frame rusted replacement G 2018 - 2019 A 60 10,000.00$ Roof work shingles replacement 2018 - 2019 C 400,000.00$ Scoreboard LED 2018 - 2019 C 9,000.00$ Sound system gym 2018 - 2019 C 22,000.00$ Sound system cafeteria 2018 - 2019 C 20,000.00$ Restoration work 2019 - 2020 B 60 500,000.00$ 500,000.00$ 10 year life safety survey 2018 - 2019 C 18,000.00$ 18,000.00$

Page 11: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 11 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

John F. KennedyTile repairs - main office hallway, teachers lounge and teacher workroom 2013 - 2014 B Settling issueRemove tile on stairways and replace with rubber material 2013 - 2014 C 25,000.00$ Floor tile repairs 2014 - 2015 B Settling issueGlycol to 2 pipe HVAC system 2014 - 2015 B 16,500.00$ Lightning alert and warning system 2015 - 2016 B 6,668.00$ Lighting upgrade outside LED (PSD 202 maintenance) 2016 - 2017 A 60 77,200.00$ 39,277.00$ Paint classrooms 2016 - 2017 A O&M 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ Gym magnetic hold opens 2017 - 2018 C 2,500.00$ Carpet 2nd floor hallway 2017 - 2018 C 25,000.00$ 15,000.00$ Asphalt work 2017 - 2018 C 75,000.00$ Storage to front of building 2017 - 2018 C 425,000.00$ Clean and refinish gym floor 2017 - 2018 C 1,800.00$ 1,800.00$ Ash tree replacement (10) 2017 - 2018 A 60 5,000.00$ Bleacher work 1st step 2017 - 2018 A 60 1,500.00$ Flashing LED lights exterior 2018 - 2019 B 8,600.00$ Surveillance System (new number) 2018 - 2019 B 71,000.00$ Replacement rusted entry F, G 2018 - 2019 C 20,000.00$ Replace rusted entry I, H 2018 - 2019 C 20,000.00$ Scoreboard LED 2018 - 2019 C 4,000.00$ Sound system gym 2018 - 2019 C 22,000.00$ Sound System cafeteria 2018 - 2019 C 20,000.00$ Restoration work 2018 - 2019 B 500,000.00$ 500,000.00$ Concrete work 2018 - 2019 C 10,000.00$ 10 year life safety survey 2018 - 2019 C(2028) 18,000.00$

Page 12: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 12 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

Timber RidgePainting/sealing locker room floors with speckled paint 2013 - 2014 B 16,000.00$ 16,000.00$ Paint classrooms 2016 - 2017 A O&M 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ Lighting upgrade outside LED (PSD 202 maintenance) 2017 - 2018 A 60 56,800.00$ 30,605.00$ Asphalt work 2017 - 2018 C Tort 90,000.00$ Storage front of building by band room 2017 - 2018 C 425,000.00$ Clean and refinish gym floor 2017 - 2018 C 1,800.00$ 1,800.00$ Replace tile to Optima 24 x 24 teacher lounge LVT 2017 - 2018 A 60 6,000.00$ Concrete work 2017 - 2018 A 60 8,000.00$ 8,000.00$ 8,000.00$ Media Center Carpet 2017 - 2018 A 60 18,000.00$ Entrance "B" floor tile replacement 2017 - 2018 A 60 5,000.00$ Paint full gym 2017 - 2018 C 18,000.00$ Gym sound system 2018 - 2019 C 22,000.00$ Flashing LED lights exterior 2018 - 2019 B 8,600.00$ Repair lockers 500 (6th) "A" 2018 - 2019 A 60 20,000.00$ Surveillance System (new number) 2018 - 2019 B 71,000.00$ Gym score board(s) 2018 - 2019 B 10,000.00$ Cafeteria sound system 2018 - 2019 C 20,000.00$ 10 year life safety survey 2018 - 2019 C 18,000.00$

Page 13: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 13 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

Bonnie McBethFloor tile repairs 2014 - 2015 B 12,000.00$ Move storage island cabinets to walls 2015 - 2016 B 25,650.00$ Lighting upgrade outside LED (PSD 202 maintenance) 2016 - 2017 A 60 74,000.00$ 34,782.00$ Paint classroom 2016 - 2017 A O&M $ - 0 - 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ Covered walkways 2017 - 2018 C 1,800,000.00$ Concrete work 2017 - 2018 C 5,000.00$ Asphalt work 2017 - 2018 A 52,000.00$ 70,000.00$ Flashing LED lights exterior 2018 - 2019 B 5,600.00$ Surveillance System (new number) 2018 - 2019 B 49,500.00$ Playground set A 2018 - 2019 C 110,000.00$ Playground set B 2018 - 2019 C(2024) 110,000.00$ Paint Multipurpose, pillars, conference 2018 - 2019 A O&M 1,500.00$ Tile to main office 2018 - 2019 CRoof replacement EPDM low slope 2018 - 2019 C 400,000.00$ Heritage lower level lease 2018 - 2019 A 60 104,000.00$ 104,000.00$ 104,000.00$ 104,000.00$ 104,000.00$ Heritage lower level construction 2018 - 2019 A 60 100,000.00$ 10 year Life Safety Survey 2018 - 2019 C(2031) 22,000.00$ 18,000.00$

Page 14: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 14 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

Central Elementary Lightning alert and warning system 2015 - 2016 B 6,668.00$ Restoration work 2016 - 2017 B 1,000,000.00$ Lighting upgrade outside LED (PSD 202 maintenance) 2016 - 2017 B 70,700.00$ $ 29,123.00 Paint classrooms 2016 - 2017 A O&M 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ Asphalt work 2017 - 2018 A Tort $ 72,000.00 80,000.00$ Restoration engineering work 2017 - 2018 B 24,000.00$ Concrete work by dumpster 2017 - 2018 A 60 8,000.00$ 8,000.00$ 8,000.00$ Flashing LED lights exterior 2018 - 2019 B 5,600.00$ Surveillance System (new number) 2018 - 2019 B 71,000.00$ Playground set A 2018 - 2019 C(2029) 110,000.00$ Playground set B 2018 - 2019 C(2030) 110,000.00$ LVT flooring 113, 104, 112 2018 - 2019 A O&M 20,000.00$ LVT flooring 115, 121 2018 - 2019 B 17,000.00$ Concrete work out in front 2018 - 201910 year life safety survey 2018 - 2019 C(2028) 16,000.00$ Roof replacement Epdm to 3ply & shingles 2018 - 2019 C 700,000.00$

Page 15: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 15 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

Charles ReedReplace carpet in all classrooms. This will be year 10 for the original carpets. 2014 - 2015 C $ 130,000.00 Magnetic hold door opens for the media center & multipurpose room 2014 - 2015 C 5,000.00$ Floor tile repairs 2014 - 2015 B HoldGlycol to 2 pipe HVAC system 2014 - 2015 B 14,000.00$ Addition of concrete to dumpster area 2014 - 2015 A 60 10,000.00$ Paint classrooms 2016 - 2017 A O&M 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ Lighting upgrade outside LED (PSD 202 maintenance) 2016 - 2017 B 63,600.00$ 29,842.00$ Asphalt work 2017 - 2018 ? Tort 70,000.00$ Restoration engineering 2017 - 2018 B 24,999.00$ Playground border 2017 - 2018 A 60 4,000.00$ Media Center paint/carpet 2017 - 2018 C 26,000.00$ Concrete work 2017 - 2018 A 60 8,000.00$ Roof replacement Epdm to 3ply w/ barrel rest. 2017 - 2018 C 700,000.00$ Restoration work 2017 - 2018 B $ 1,000,000.00 Flashing LED lights exterior 2018 - 2019 B 5,600.00$ Surveillance System (new number) 2018 - 2019 B 61,500.00$ Playground Set A 2018 - 2019 C(2027) 110,000.00$ Playground Set B 2018 - 2019 C(2028) 110,000.00$ Blinds (Four Point O) 2018 - 2019 B $ 6,500.00$ 10 year life safety survey 2018 - 2019 C(2025) 16,000.00$

Page 16: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 16 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

CreeksideGlycol to 2 pipe HVAC system 2014 - 2015 B 14,000.00$ Lightning alert and warning system 2015 - 2016 B 6,668.00$ Additional card reader to door "G" 2015 - 2016 A 60 5,000.00$ Painting classrooms 2016 - 2017 A O&M 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ Lighting upgrade outside LED (PSD 202 maintenance) 2016 - 2017 B 40,600.00$ 21,440.00$ Asphalt work 2017 - 2018 C 80,000.00$ Playground border 2017 - 2018 A 60 4,000.00$ Media Center Carpet and Paint 2017 - 2018 A 60 24,999.00$ Concrete work 2017 - 2018 8,000.00$ Flashing LED lights exterior 2018 - 2019 B 5,600.00$ Surveillance System (new number) 2018 - 2019 B 65,000.00$ Concrete work back receiving 2018 - 2019 A 60 15,000.00$ Playground Set A 2018 - 2019 C 110,000.00$ Playground Set B 2018 - 2019 C 110,000.00$ 10 year life safety survey 2018 - 2019 C(2031) 16,000.00$

Page 17: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 17 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

Crystal LawnsReplace old single-pane/steel frame windows w/ energy efficient windows 2011 - 2012 B 380,000.00$ Install floor drain slop sink in J-closet 2011 - 2012 C 6,500.00$ Replace old drinking fountains with refrigerator units with bottle fillers 2012 - 2013 B 6,000.00$ Replace gym floor 2012 - 2013 A 60 44,999.00$ Fascia needs replacement 2014 - 2015 B 48,000.00$ Repair/replace floor tile 2014 - 2015 A 60 2,000.00$ Lightning alert and warning system 2015 - 2016 B 6,668.00$ Lighting upgrade outside LED (PSD 202 maintenance) 2016 - 2017 B 18,800.00$ 6,384.00$ Paint classroom 2016 - 2017 A O&M 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 3 Year Asbestos Compliance 2017 - 2018 C 750.00$ 10 year Life Safety Survey 2017 - 2018 A 60 10,000.00$ Playground border 2017 - 2018 C 4,000.00$ Asphalt work 2017 - 2018 C 35,000.00$ Chiller replacement 2017 - 2018 A 60 200,000.00$ Gutter on canopy 2017 - 2018 B 7,500.00$ Raise concrete by boiler room 2017 - 2018 B 2,000.00$ Pocket tables 2018 - 2019 A 60 50,000.00$ Flashing LED lights exterior 2018 - 2019 B 5,600.00$ Mobile classroom (1) removed 2018 - 2019 C 15,000.00$ Surveillance System (new number) 2018 - 2019 B 41,500.00$ Playground Set A 2018 - 2019 C(2031) 110,000.00$ Playground Set B 2018 - 2019 C(2035) 110,000.00$ Mobile Classroom Leases (1) 2018 - 2019 A 60 13,000.00$ 13,000.00$ 13,000.00$ 13,000.00$ 13,000.00$ Terrazzo repairs washrooms 2018 - 2019 A 60 24,999.00$ Partition replacement 2018 - 2019 A 60 16,000.00$ Site, building, HVAC improvements 2018 - 2019 C 13,000,000.00$ 10 year life safety survey 2018 - 2019 C(2024) 16,000.00$

Page 18: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 18 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

Eagle PointeLightning alert and warning system 2015 - 2016 B 6,668.00$ Lighting upgrade multipurpose room 2015 - 2016 A 60 15,000.00$ Paint classrooms 2016 - 2017 A O&M 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ Lighting upgrade outside LED (PSD 202 maintenance) 2016 - 2017 B 55,800.00$ 28,868.00$ Asphalt work 2017 - 2018 B 80,000.00$ Replacement EPDM roof low slope & shingled roof barrel res 2017 - 2018 A 60 $ 637,800.00 Playground border 2017 - 2018 B 5,000.00$ Concrete work 2017 - 2018 C 8,000.00$ 8,000.00$ Tuck Pointing Gym 2017 - 2018 BFinish tile work 2nd floor 2017 - 2018 BADS 2nd station main office 2017 - 2018 CReplace cover base multipurpose room 2017 - 2018 BReplace classrooms carpet with tile 133, 126, 127 & 2nd floor hallway tile 2017 - 2018 A 60 18,000.00$ Flashing LED lights exterior 2018 - 2019 B 5,600.00$ Surveillance System (new number) 2018 - 2019 B 61,500.00$ Chiller replacement 2018 - 2019 C(2024) 200,000.00$ Playground Set A 2018 - 2019 C(2026) 110,000.00$ Playground Set B 2018 - 2019 C(2027) 110,000.00$ LVT on landings (4) middle 2018 - 2019 A 60 6,000.00$ Tee on first floor area tile 2018 - 2019 $Multipurpose room exterior door and frames 2018 - 2019 B 20,000.00$ 10 year life safety survey 2018 - 2019 C(2033) 16,000.00$ Aspalt work 2018 - 2019 C Tort 120,000.00$

Page 19: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 19 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

EichelbergerRepair/replace floor tile, lift stabilize restoration work 2014 - 2015 B 1,000,000.00$ Lightning alert and warning system 2015 - 2016 B 6,668.00$ Paint classrooms 2016 - 2017 A O&M 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ Lighting upgrade outside LED (PSD 202 maintenance) 2016 - 2017 B 47,800.00$ 39,334.00$ Concrete work 2017 - 2018 B 8,000.00$ 8,000.00$ Entrance "B" door swipe 2017 - 2018 A 60 5,000.00$ Playground border 2017 - 2018 C 4,000.00$ Asphalt Work 2017 - 2018 A Tort 72,000.00$ 80,000.00$ Flashing LED lights exterior 2018 - 2019 B 5,600.00$ Surveillance System (new number) 2018 - 2019 B 61,500.00$ Playground Set A 2018 - 2019 C(2033) 110,000.00$ Playground Set B 2018 - 2019 C(2035) 110,000.00$ Restoration engineering, study 2019 - 2020 B 24,000.00$ ? ?10 year life safety survey 2018 - 2019 C(2028) 16,000.00$

Page 20: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 20 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

FreedomLightning alert and warning system 2015 - 2016 B 6,668.00$ Lighting upgrade outside LED (PSD 202 maintenance) 2016 - 2017 B 69,100.00$ 31,297.00$ Paint classrooms 2016 - 2017 A O&M 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ Repair/replace floor tile 2017 - 2018 B 3,000.00$ Settling issues "watch" 2017 - 2018 C -$ Playground border 2017 - 2018 A 60 4,000.00$ Asphalt work 2017 - 2018 C 70,000.00$ Concrete work 2017 - 2018 A 60 8,000.00$ 8,000.00$ Carpet main office 2018 - 2019 C 12,000.00$ Flashing LED lights exterior 2018 - 2019 B 8,600.00$ Surveillance System (new number) 2018 - 2019 B 61,500.00$ Playground Set A 2018 - 2019 C(2030) 110,000.00$ Playground Set B 2018 - 2019 C(2032) 110,000.00$ Settlement Survey 2018 - 2019 A 60 24,999.00$ Settlement Survey Ground Radar 2018 - 2019 B 24,999.00$ 10 year life safety survey 2018 - 2019 C(2028) 16,000.00$ LVT rooms 215, 217 2018 - 2019 A 60 17,560.00$ Roof replacement low slope, shingle, barrel 2018 - 2019 C 700,000.00$

Page 21: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 21 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

Grand PrairieImprovements to playfield 2012 - 2013 30,000.00$ Replace exterior doors 2013 - 2014 C 12,000.00$ Carpet replacement - 7 rooms per year 2013 - 2014 B 25,000.00$ Shed in back for storage 2014 - 2015 B $ 450,000.00 Trim on outside of building replaced or painted 2015 - 2016 $ 6,000.00 Lightning alert and warning system 2015 - 2016 B 6,668.00$ A/C gymnasium roof top (gym only) 2015 - 2016 B 60,000.00$ Paint classrooms 2016 - 2017 A O&M 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ Lighting upgrade outside LED (PSD 202 maintenance) 2016 - 2017 B 28,000.00$ 14,082.00$ Asphalt work 2017 - 2018 A Tort 52,000.00$ 60,000.00$ 3 Year asbestos compliance 2017 - 2018 C 750.00$ Concrete work 2017 - 2018 A 60 18,000.00$ 10,000.00$ 5,000.00$ Playground replacement B 2018 - 2019 A 60 110,000.00$ Stairs by kitchen door/walk concrete 2018 - 2019 A 60 12,000.00$ Flashing LED lights exterior 2018 - 2019 B 5,600.00$ Surveillance System (new number) 2018 - 2019 B 71,000.00$ Playground Set A 2018 - 2019 C(2036) 110,000.00$ Playground Set B 2018 - 2019 C(2039) 110,000.00$ 10 year life safety survey 2018 - 2019 C 16,000.00$

Page 22: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 22 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

Lakewood FallsLightning alert and warning system 2015 - 2016 B 6,668.00$ Expansion of entrance drive 2015 - 2016 C 337,000.00$ Paint classrooms 2016 - 2017 A O&M 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ Lighting upgrade outside LED (PSD 202 maintenance) 2016 - 2017 B 35,100.00$ 20,642.00$ Asphalt work 2017 - 2018 C 80,000.00$ Playground Border 2017 - 2018 A 60 4,000.00$ Chiller Replacement 2017 - 2018 C 200,000.00$ Concrete work 2017 - 2018 A 60 8,000.00$ 8,000.00$ Paint gym multipurpose room 2017 - 2018 C 15,000.00$ Playground Set B 2018 - 2019 B 110,000.00$ Lunch Pocket Tables 2018 - 2019 B 50,000.00$ Flashing LED lights exterior 2018 - 2019 B 5,600.00$ Surveillance System (new number) 2018 - 2019 B 65,000.00$ Playgroud Set A 2018 - 2019 C(2034) 110,000.00$ Parking spaces and handicapped ramp 2018 - 2019 B $10 year life safety survey 2018 - 2019 C 16,000.00$

Page 23: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 23 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

LibertyGlycol to 2 pipe HVAC system 2014 - 2015 B 14,000.00$ Lightning alert and warning system 2015 - 2016 C 6,668.00$ Asphalt work 2016 - 2017 C 90,000.00$ Lighting upgrade outside LED (PSD 202 maintenance) 2016 - 2017 B 64,800.00$ 19,817.00$ Restoration work 2016 - 2017 B 1,000,000.00$ ? ? ?Paint classrooms 2016 - 2017 A O&M 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ Replacement EPDM low slope roof 2017 - 2018 C(22) 375,000.00$ Replacement of shingle steep slope roof 2017 - 2018 C(25) 375,000.00$ Room 109 tile remove carpet LVT 2017 - 2018 A 60 8,000.00$ Engineer for restoration work 2017 - 2018 B 24,000.00$ Multipurpose room lighting H10 to LED 2017 - 2018 A 60 15,000.00$ Playground border 2017 - 2018 C 4,000.00$ Flashing LED lights exterior 2018 - 2019 B 5,600.00$ Surveillance System (new number) 2018 - 2019 B 61,500.00$ Playground Set A 2018 - 2019 C(2028) 110,000.00$ Playground Set B 2018 - 2019 C(2029) 110,000.00$ Hallway floor tile repairs 2018 - 2019 A 60 10,000.00$ Concrete work 2018 - 2019 C 5,000.00$ 10 year life safety survey 2018 - 2019 C(2025) 16,000.00$

Page 24: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 24 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

LincolnRepair/replace floor tile on treads and risers stairs 2011 - 2012 A 60 12,000.00$ Carpet replaced in classrooms/offices 2013 - 2014 B 160,000.00$ Glycol to 2 pipe HVAC system 2014 - 2015 B 14,000.00$ Lightning alert and warning system 2015 - 2016 C 6,668.00$ Roof work EPDM flat roof area 2015 - 2016 B 350,000.00$ Lighting upgrade outside LED 2016 - 2017 B 53,300.00$ Paint classrooms 2016 - 2017 A O&M 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ Roof work steep slope shingle 2017 - 2018 C 325,000.00$ Asphalt work 2017- 2018 C 90,000.00$ Carpet or tile main office 2017 - 2018 A 60 9,000.00$ Carpet media center 2017 - 2018 B 25,000.00$ Construction room 119 2017 - 2018 B 25,000.00$ Provide door to gym storage café side 2017 - 2018 A 60 20,000.00$ Media paint/carpet 2017 - 2018 C 26,000.00$ Concrete work 2017 - 2018 C 5,000.00$ Flashing LED lights exterior 2018 - 2019 B 8,600.00$ Surveillance System (new number) 2018 - 2019 B 61,500.00$ Playground Set A 2018 - 2019 C(2025) 110,000.00$ Playground Set B 2018 - 2019 C(2026) 110,000.00$ LVT to staff lounge 2018 - 2019 A 60 8,500.00$ Mobile storage unit 2018 - 2019 A Principal 5,000.00$ 10 year life safety survey 2018 - 2019 C(2033) 16,000.00$

Page 25: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 25 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

Meadow ViewReplace carpet in main office 2013 - 2014 B 10,000.00$ Glycol to 2 pipe HVAC system 2014 - 2015 B 14,000.00$ Lightning alert and warning system 2015 - 2016 B 6,668.00$ Asphalt work 2015 - 2016 C 80,000.00$ Lighting upgrade outside LED (PSD 202 maintenance) 2016 - 2017 B 44,000.00$ 23,619.00$ Paint classrooms 2016 - 2017 A O&M 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 10 year Life Safety Survey 2017 - 2018 C(2031) 16,000.00$ 13,727.00$ Carpet for Media center 2017 -2018 C 25,000.00$ Paint Gym all 2017 -2018 C 18,000.00$ Concrete work 2017 -2018 A 60 8,000.00$ 8,000.00$ Flashing LED lights exterior 2018 - 2019 B 5,600.00$ Surveillance System (new number) 2018 - 2019 B 65,000.00$ Chiller Replacement 2018 - 2019 C 200,000.00$ Playground set A 2018 - 2019 C 110,000.00$ Playground set B 2018 - 2019 C(2034) 110,000.00$ Replace carpet to LVT 2018 - 2019 B 24,999.00$ 24,999.00$

Page 26: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 26 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

Ridge5 rooms of carpeting to LVT 2013 - 2014 B 25,000.00$ 24,999.00$ 24,999.00$ Repair/replace floor tile 2014 - 2015 B 5,000.00$ Lightning alert and warning system 2015 - 2016 C 6,668.00$ Roof work EPDM flat roof area 2015 - 2016 C 350,000.00$ Lighting upgrade outside LED (PSD 202 maintenance) 2016 - 2017 B 81,200.00$ 39,494.00$ Paint classrooms 2016 - 2017 A O&M 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ Stairwells flooring from vinyl to rubber 2017 - 2018 A 60 21,000.00$ Asphalt work 2017 - 2018 C 90,000.00$ Roof work shingle steep slope 2017 - 2018 C 325,000.00$ 10 year life safety survey 2017 - 2018 C 11,727.00$ Magnet lease hallway door "buzz" 2017 - 2018 A 60 4,500.00$ Concrete work 2017 - 2018 C 8,000.00$ 8,000.00$ Paint gym 2017 - 2018 A O&M 18,000.00$ Paint all door/window frames 2017 - 2018 COptima title to replace carpet 2017 - 2018 CFlashing LED lights exterior 2018 - 2019 B 5,600.00$ Surveillance System (new number) 2018 - 2019 B 61,500.00$ Chiller Replacement 2018 - 2019 C 200,000.00$ Playground set A 2018 - 2019 C(2024) 110,000.00$ Playground set B 2018 - 2019 C(2025) 110,000.00$

Page 27: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 27 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

River ViewCarpet replacement - 7 rooms per year to LVT 2012 - 2013 B 25,000.00$ 24,999.00$ Repair/replace floor tile 2014 - 2015 B 25,000.00$ Lightning alert and warning system 2015 - 2016 B 6,668.00$ Lighting upgrade outside LED (PSD 202 maintenance) 2016 - 2017 B 37,800.00$ 20,466.00$ Paint classrooms 2016 - 2017 A O&M 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ Asphalt work 2017 - 2018 C 90,000.00$ 10 year Life Safety Survey 2017 - 2018 C(2031) 16,000.00$ 13,727.00$ Paint multipurpose room 2017 - 2018 C 15,000.00$ Carpet office 2017 - 2018 A 60 9,000.00$ Carpet Media Center 2017 - 2018 B 25,000.00$ Rubber replacement stairs and landings 2017 - 2018 C 21,000.00$ Concrete work 2017 - 2018 C 8,000.00$ 8,000.00$ Teachers staff lunge woman stalls 2018 - 2019 BWindow seal/caulk 2018 - 2019 A O&M 1,000.00$ Flashing LED lights exterior 2018 - 2019 B 5,600.00$ Surveillance System (new number) 2018 - 2019 B 61,500.00$ Playground set A 2018 - 2019 C 110,000.00$ Playground set B 2018 - 2019 C 110,000.00$

Page 28: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 28 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

Thomas JeffersonRepair/replace floor tile to LVT 2014 - 2015 B 25,000.00$ Lightning alert and warning system 2015 - 2016 B 6,668.00$ Lighting upgrade outside LED (PSD 202 maintenance) 2016 - 2017 B 68,900.00$ 27,601.00$ Paint classrooms 2016 - 2017 A O&M 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ Asphalt work 2017 - 2018 A Tort 52,000.00$ 80,000.00$ Carpet replacement - FBI rooms 107, 108, 127 2017 - 2018 B 25,000.00$ Tile rooms SVT all first floor rooms 2017 - 2018 ? 160,000.00$ Concrete work 2017 - 2018 C 8,000.00$ 8,000.00$ 8,000.00$ Flashing LED lights exterior 2018 - 2019 B 5,600.00$ Surveillance System (new number) 2018 - 2019 B 61,500.00$ Playground set A 2018 - 2019 C(2032) 110,000.00$ Playground set B 2018 - 2019 C(2033) 110,000.00$ LVT 108, 107 and office/storage 2018 - 2019 BLVT 119, 127 and office/storage 2018 - 2019 B10 year life safety survey 2018 - 2019 C(2028) 16,000.00$ Roof replacement low slope, shingle, barrel 2018 - 2019 C 700,000.00$

Page 29: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 29 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

Walker's GroveLightning Alert and Warning System 2015 - 2016 B 6,668.00$ Site lighting to LED (PSD 202 maintenance) 2016 - 2017 B 29,400.00$ 12,593.00$ Chiller/Boiler or HVAC 2016 - 2017 B 3,000,000.00$ Paint classrooms 2016 - 2017 A O&M 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ Concrete work 2017 - 2018 C 8,000.00$ 8,000.00$ 8,000.00$ Paint cafeteria walls & gym walls all high 2017 - 2018 18,000.00$ Asphalt work 2017 - 2018 C 70,000.00$ Cove base replacement Gym & Cafeteria 2017 - 2018 BPaint electrostatic outdoor vents 2017 - 2018 BTeachers work room replace carpet 2017 - 2018 BClean and fire treat auditorium curtain 2017 - 2018 C 12,000.00$ Basketball back board replacement 2017 - 2018 BFlashing LED lights exterior 2018 - 2019 B 5,600.00$ Paint exterior grills electrostatic 2018 - 2019 A O&M 8,000.00$ Surveillance System (new number) 2018 - 2019 B 65,000.00$ Playground set A 2018 - 2019 C(2031) 110,000.00$ Playground set B 2018 - 2019 C(2036) 110,000.00$ 10 year life safety survey 2018 - 2019 C(2025) 16,000.00$

Page 30: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 30 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

WesmereLightning alert and warning system 2015 - 2016 B 6,668.00$ Lighting upgrade outside LED (PSD 202 maintenance) 2016 - 2017 B 45,900.00$ 21,921.00$ Paint classrooms 2016 - 2017 A O&M 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ Replace floor tile hallways 1st and 2nd floor addition 2017 - 2018 A 60 13,000.00$ 10 year Life Safety Survey 2017 - 2018 C(2030) 16,000.00$ 13,727.00$ Barrel Roof renovation work 2017 - 2018 A 60 82,700.00$ Paint Gym all 2017 - 2018 C 18,000.00$ Asphalt work 2017 - 2018 C 70,000.00$ Concrete work 2017 - 2018 C 8,000.00$ 8,000.00$ 8,000.00$ Work room floor 2018 - 2019 B 3,000.00$ Flashing LED lights exterior 2018 - 2019 B 5,600.00$ Surveillance System (new number) 2018 - 2019 B 61,500.00$ Playground set A 2018 - 2019 A 60 110,000.00$ Playground set B 2018 - 2019 B 110,000.00$ Concrete work receiving 2018 - 2019 A 60 12,000.00$ Reception desk 2018 - 2019 B 5,300.00$ Flip 201, 202, 204 and 205 2018 - 2019 A O&M $ - 0 -Replace carpet to LVT 2018 - 2019 C 24,999.00$

Page 31: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 31 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

OMTWarehouse lighting upgrade to LED 2015 - 2016 A 60 16,000.00$ Exterior lighting to LED (PSD 202 maintenance) 2015 - 2016 A 60 5,709.00$ Roof 2015 - 2016 C 550,000.00$ Asphalt work 2017 - 2018 A Tort 92,000.00$ 100,000.00$ Paint exterior metal 2017 - 2018 A 60 24,999.00$ Flashing LED lights exterior 2018 - 2019 B 3,800.00$ Surveillance System (new number) 2018 - 2019 B 24,250.00$ Asbestos compliance 2018 - 2019 800.00$

Page 32: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 32 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

AdministrationCarpet 2016 - 2017 C Paint offices 2016 - 2017 A O&M 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ 1,500.00$ Asphalt work 2017 - 2018 A Tort 52,000.00$ 60,000.00$ Flashing LED lights exterior (2) 2018 - 2019 B 3,800.00$ Surveillance System (new number) 2018 - 2019 B 61,500.00$

Roof EPDM re 2018 - 2019 C

Page 33: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 33 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

Ft. Beggs GarageAsphalt work 2017 - 2018 A Tort 32,000.00$ 40,000.00$ Install (3) B.A. fans 2017 - 2018 A 60 5,000.00$ Garage door replacement 2017 - 2018 A 60 12,000.00$ Flashing LED lights exterior (1) 2018 - 2019 B 1,800.00$ Surveillance System (new number) 2018 - 2019 41,500.00$

Page 34: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 34 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

Technology Bldg.Lighting upgrade to outside LED (PSD 202 maintenance) 2015 - 2016 A 60 16,900.00$ 6,661.00$ Asphalt work 2017 - 2018 A Tort 22,000.00$ 30,000.00$ Flashing LED lights exterior (2) 2018 - 2019 B 3800Surveillance System (new number) 2018 - 2019 B 90,000.00$

Page 35: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 35 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

ERPS Construction 2018 - 2019 A 60 25,000,000.00$

Page 36: 2019 - 2023 Five Year Plan

Rev. 5/1/2019 Page 36 of 36 PLAINFIELD COMMUNITY SCHOOL DISTRICT 202

5-YEAR OPERATIONAL/CAPITAL IMPROVEMENT PLANDISTRICT WIDE

2019 - 2023TortOperations and MaintenanceSite Improvement (paid by construction accounts)School/PrincipalGrant Funded

2023SCHOOL PROJECT DESCRIPTION, LOCALE INITIALREPORTING

YEAR

STATUSC - Completed

PRIORITY LEVELA - High

B - MediumC - Low

FUND ALLOCATION

FUTURE ESTIMATED 2019 2020 2021 2022

TORT TOTALS -$ 730,980.00$ O&M TOTALS 38,548,600.00$ 129,249.00$ 60 TOTALS 38,548,600.00$ 4,594,414.00$ PRINCIPAL TOTALS -$ 30,000.00$

TOTAL 77,395,535.00$ 5,484,643.00$ 5,689,173.00$ 5,276,044.00$ 9,566,999.00$ 12,327,473.00$