Appendix K Needs Plan Project Costs, Purpose and Need
February 7, 2015
This page is intentionally blank.
Path Forward 2040 Long Range Transportation Plan
PURPOSE AND NEED STATEMENTS The Needs Plan included a six county area consisting of Baker, Clay, Duval, Nassau, Putnam and St. Johns counties. The Needs Plan is not a prioritized list of projects, nor is it constrained by financial resources.
The Needs Plan leveraged prior studies development by the Florida Department of Transportation, the North Florida Transportation Planning Organization and local governments. Maintaining the public consensus continuity of these efforts was essential to the credibility of the planning process.
Because of the level of visioning and planning that occurred within these studies, the known needs greatly exceeded the resources anticipated to be available. Building on the community consensus that was achieved, the development of the Needs Plan began with a review and confirmation of these studies. The following sources were used to define the needs.
2035 Envision Long Range Transportation Plan City of Jacksonville Mobility Plan Committed Development Projects Provided by Local Governments Coordination with local governments and stakeholders on additional needs FDOT’s Strategic Intermodal Systems Needs Plan and Cost Feasible Plan (includes 1st Five Year and 2nd Five
Year) FDOT’s Adopted Work Program First Coast Regional Greenways and Trails Plan Jacksonville Transportation Authority Blueprint 2020 Local Government Comprehensive Plans North Florida TPO Congestion Management Plan North Florida TPO Freight, Logistics and Intermodal Planning Framework Plan North Florida TPO ITS Master Plan North Florida TPO Regional Bicycle and Pedestrian Plan North Florida TPO Strategic Safety Plan North Florida TPO Transportation Improvement Program
As part of the planning process, these needs were confirmed through an analysis of the safety, congestion, mobility and emergency evacuation needs.
The following tables summarize the needs plan costs in present day dollars and provide a summary of the purpose and need for each project of the road and transit capacity projects.
1
Path Forward 2040 Long Range Transportation Plan
Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars)Facility County Map ID From To Improvement Type 2013 Cost
(millions)O&M Cost (millions)
Abaco Island Drive Extension Nassau 988 Abaco Island Drive Zion Court New 2 Lane Road $0.72 $0.00Alta Drive Duval 3 SR 105 Heckscher Drive I‐295 Widen to 4 Lanes $8.85 $0.21Alta Drive / Yellow Bluff Road Duval 2 I‐295 New Berlin Road (north ) Widen to 5 Lanes $14.50 $0.15Alta Drive Realignment Duval 1 SR 105 Zoo Parkway North of New Berlin Road (south) New 4 Lane Road $15.15 $0.10Amelia Island Parkway Nassau 704 South 14th Street CR 105A Buccaneer Trail Widen to 4 Lanes* $4.17 $0.10Argyle Forest Boulevard Duval 936 SR 23 First Coast Expressway Old Middleburg Road Widen to 6 Lanes $8.49 $0.48Arrigo‐Parliament Reconnection Nassau 980 Arrigo Boulevard Parliament Drive New 2 Lane Road $0.59 $0.00Barnwell‐0' Neil Scott Connector Nassau 1001 Barnwell Road O'Neil Scott Road New 2 Lane Road $2.89 $0.02Baxley Road Clay 900 CR 220 Doctors Inlet Road SR 21 Blanding Boulevard Widen to 4 Lanes $4.61 $0.05Blount Island Boulevard Extension Duval 1006 Spoil Island Jacksonville Port Authority New 2 Lane Bridge $80.21 $0.08Braddock Parkway Duval 939 SR 115 Lem Turner Road Pecan Park Road New 2 Lane Road $47.68 $0.24Brady Point‐Clements Connector Nassau 1002 Brady Point Road Clements Road New 2 Lane Road $2.89 $0.02Brinkhoff Road St. Johns 801 SR 207 Wildwood Drive New 2 Lane Road $4.32 $0.04Buffalo Road Putnam 503 Buffalo Road west Buffalo east New 2 Lane Bridge $34.71 $0.05Cahoon Road Duval 1016 Lenox Avenue US 90 Beaver Street Reconstruct 2 Lanes $10.20 $0.07Cardinal Street North Extension Nassau 976 Cardinal Avenue SR 200 SR AIA Yulee Backage Roads New 2 Lane Road $1.44 $0.01Cardinal Street South Extension Nassau 975 Spring Meadow Avenue William Burgess Boulevard New 2 Lane Road $0.48 $0.00Cecil Field Connector Duval 972 Commerce Center SR 23 First Coast Expressway New 2 Lane Road $12.57 $0.07Chaffee Road Duval 971 SR 228 Normandy Boulevard Crystal Springs Road Widen to 5 Lanes $30.00 $0.39Cheswick Oak Avenue Extension Clay 13 Oakleaf Plantation Parkway Savannah Glen Boulevard New 4 Lane Road $23.08 $0.30Christian Way Extension Nassau 995 Christian Way Hampton Club Way New 2 Lane Road $6.49 $0.04Clark Road Extension Duval 1020 Broward Road Clark Road New 3 Lane Road $0.90 $0.04College Drive Clay 902 CR 220 Doctors Inlet Road SR 21 Blanding Boulevard Widen to 6 Lanes $16.29 $0.31College Drive Extension Clay 14 SR 21 Blanding Boulevard Challenger Drive (Branan Field Road) New 4 Lane Road $30.08 $0.23Collins Road Duval 930 Shindler Drive Rampart Road Widen to 4 Lanes $11.30 $0.22Collins Road Duval 932 Old Middleburg Road S Shindler Drive Widen to 4 Lanes $4.10 $0.15Collins Road Duval 15 SR 21 Blanding Boulevard Pine Verde Widen to 4 Lanes $4.30 $0.15Collins Road Duval 16 at US 17 Roosevelt Boulevard New Interchange $36.00 $0.19Collins Road Realignment Duval 16B Pine Verde US 17 Roosevelt Boulevard New 4 Lane Road, Two Overpass and New Interchange $104.84 $0.07
Comfort Road Putnam 505 Port Road US 17 Widen to 4 Lanes $5.86 $0.07Commodore Point Drive Extension Nassau 996 Commodore Point Drive Blackrock Road New 2 Lane Road $3.61 $0.02Concourse Loop Road Nassau 501 License Road Amelia Concourse New 2 Lane Road $3.17 $0.03Connector Road Putnam 502 US 17 Distribution Center New 2 Lane Road $0.95 $0.95CR 105A Buccaneer Trail Nassau 705 South Fletcher Avenue Canopy Drive Turn Lane Improvements* $1.41 $0.05CR 16A St. Johns 803 SR 16 Connector SR 13 Widen to 4 Lanes $24.85 $0.72CR 16A Extension St. Johns 802 CR 16A Leo Maguire Parkway New 2 Lane Road $1.41 $0.02CR 209 Russell Road Clay 905 CR 739 Henley Road US 17 Widen to 4 Lanes $71.88 $0.77CR 209 South Clay 906 Decoy Road US 17 Reconstruct 2 Lanes $68.15 $0.30CR 210 St. Johns 805 I‐95 near US 1 Widen to 6 Lanes $10.10 $0.44CR 210 St. Johns 807 Greenbriar Road Cimarrone Road Widen to 4 Lanes $19.90 $0.22CR 210 W St. Johns 849 Longleaf Pine Parkway Greenbriar Road Widen to 4 Lanes $10.08 $0.29CR 214 St. Johns 809 Holmes Boulevard US 1 Widen to 3 Lanes* $0.92 $0.13CR 218 Clay 1026 US 301 Cosmos Avenue Widen to 4 Lanes $90.98 $0.96CR 218 Clay 1027 Cosmos Avenue Pine Tree Lane Widen to 4 Lanes $7.50 $0.25CR 218 Clay 24 SR 21 Blanding Boulevard CR 739 Henley Road Widen to 4 Lanes $42.39 $0.45CR 218 Clay 909 SR 16 CR 739 Henley Road Widen to 4 Lanes $31.33 $0.33CR 218 Extension Clay 25 CR 739 Henley Road SR 23 First Coast Expressway New 4 Lane Road $33.40 $0.20CR 218 Extension Clay 26 SR 23 First Coast Expressway CR 315 New 4 Lane Road $26.00 $0.30CR 220 Doctors Inlet Road Clay 33 SR 21 Blanding Boulevard Knight Boxx Road Widen to 4 Lanes $36.86 $0.30CR 220 Doctors Inlet Road Clay 34 College Drive US 17 Widen to 6 Lanes $40.74 $0.77CR 2209 St. Johns 810 SR 23 First Coast Expressway CR 210 New 6 Lane Road $20.30 $0.52CR 2209 St. Johns 811 SR 16 Connector SR 23 First Coast Expressway New 6 Lane Road $17.75 $0.45CR 2209 St. Johns 812 International Golf Parkway SR 16 Connector New 6 Lane Road $11.50 $0.42CR 2209 St. Johns 813 CR 214 CR 208 New 4 Lane Road $27.13 $0.42CR 2209 St. Johns 814 SR 207/CR 305 CR 214 New 4 Lane Road $39.51 $0.61CR 2209 St. Johns 815 SR 16 International Golf Parkway New 4 Lane Road $11.50 $0.06CR 2209 St. Johns 816 CR 208 SR 16 New 4 Lane Road $26.22 $0.41CR 2209 St. Johns 843 at CR 210 New Interchange $35.23 $0.19CR 305 St. Johns 818 CR 204 SR 206 New 2 Lane Road $10.00 $0.16
Page 1 of 13
Path Forward 2040 Long Range Transportation Plan
Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars)Facility County Map ID From To Improvement Type 2013 Cost
(millions)O&M Cost (millions)
CR 305 St. Johns 850 SR 206 SR 207 Widen to 4 Lanes $13.39 $0.39CR 315 Clay 31 SR 16 CR 315B Widen to 4 Lanes $29.50 $0.30CR 315 Clay 32 CR 315B US 17 Widen to 4 Lanes $7.10 $0.10CR 739B Sandridge Road Clay 904 CR 739 Henley Road CR 209 Russell Road Widen to 4 Lanes $34.10 $0.36Crosby Avenue Extension Nassau 993 US 17 SR 5 Pinewood Drive New 2 Lane Road $0.72 $0.00Davis / 9B Parcel Duval 1036 SR 9B SR 152 Baymeadows Road Widen to 4 Lanes $3.15 $0.42Decoy Road Clay 907 US 17 CR 209 South Reconstruct 2 Lanes $3.37 $0.02Dixie Highway / Pellicer Lane St. Johns 1025 SR 207 CR 214 West of King Street Reconstruct 2 Lanes and Widen to add Sidewalks and Bike
Lanes$2.27 $0.03
Dove Road Extension {west} Nassau 991 Harper Chapel Road Extension Mentoria Road New 2 Lane Road $2.78 $0.03Durbin Parkway St. Johns 819 9B Extension Nocatee Parkway New 4 Lane Road $52.52 $0.43Durbin Parkway St. Johns 844 at US 1/SR 5 Dixie Highway Modify Interchange $35.23 $0.19Duval Station Road Duval 942 US 17/SR 5 Main Street Starratt Road Widen to 4 Lanes $14.48 $0.13east Dove Road Extension Nassau 974 Harper Chapel Road William Burgess Boulevard New 2 Lane Road $0.30 $0.00East Nassau Connector Nassau 36 I‐95 Chester Road New 4 Lane Road $93.40 $0.82East Nassau Connector Nassau 969 at I‐95 New Interchange $35.23 $0.19Eastport Road Duval 37 SR 105 Heckscher Drive Pulaski Road Widen to 3 Lanes $11.80 $0.18Flora Parke‐Wal Mart Connector Nassau 986 Flora Parke Boulevard Walmart Supercenter New 2 Lane Road $1.44 $0.01Florida Boulevard Duval 1021 Penman Road SR 10 Atlantic Boulevard Widen to 3 Lanes $5.30 $0.14Future Corridor Initiative Baker/Clay/Duv
al721 Tampa Bay Northeast Florida Future Corridor $2,000.00 $5.10
Gator Bowl Boulevard Duval 43 Liberty Street Hart / Mathews Bridge Widen to 6 Lanes and Remove Ramps $40.50 $0.00
Gene Lasserre Boulevard Extension Nassau 985 Gene Lassere Boulevard SR 200A Pages Dairy Road New 2 Lane Road and Roundabout $1.44 $0.01Goodbread Road Reconstruction Nassau 977 US 17 SR 5 Hamilton Street New 2 Lane Road $1.98 $0.04Governors Park Road Clay 46 US 17 SR 16 New 4 Lane Road $71.80 $0.59Hamilton Street Extension Nassau 1000 Goodbread Circle New 2 Lane Road $2.37 $0.02Harlow Boulevard Duval 943 SR 134 103rd Street Lane Avenue Widen to 3 Lanes $1.89 $0.02Harper Chapel Extension Nassau 989 Harper Chapel Road Dove Road Extension New 2 Lane Road $0.49 $0.01Hart Expressway Ramps Duval 43B Liberty Street Hart / Mathews Bridge Remove Ramps $6.30 ‐$0.19Hartley Road Duval 49 SR 13 San Jose Boulevard Old St. Augustine Road Widen to 3 Lanes $8.40 $0.09Harts Road Duval 963 SR 104 Dunn Avenue I‐295 Widen to 4 Lanes $18.83 $0.22Holmes Boulevard St. Johns 821 CR 214 Four Mile Road Widen to 6 Lanes $5.08 $0.10I‐10 Duval 401 SR 23 First Coast Expressway I‐295 Add 4 Express Lanes $219.54 $7.00I‐10 Nassau 402* Baker/Nassau County Line Nassau/Duval County Line Add 4 Express Lanes $4.58 $0.71I‐10 Duval 403* Nassau/Duval County Line US 301 Add 4 Express Lanes $56.25 $3.28I‐10 Baker 404* W of CR 125 W of SR 121 Add 4 Express Lanes $50.57 $1.17I‐10 Baker 405* W of SR 121 Baker/Nassau County Line Add 4 Express Lanes $16.96 $3.28I‐10 Duval 406 US 301 SR 23 First Coast Expressway Add 4 Express Lanes $101.87 $6.32I‐10 Duval 432 I‐295 I‐95 Add 4 Express Lanes $372.32 $5.58I‐10 Baker 453 Baker/Columbia County Line CR 125 Add 4 Express Lanes $155.61 $18.49I‐10 Duval 454 at I‐295 Modify Interchange $131.63 $0.19I‐10/US 90 Parallel Reliever Baker 720 South Mac Clenny East Baldwin Future Corridor $144.00 $0.37I‐295 Duval/Clay 57 SR 13 San Jose Boulevard W of US 17 Roosevelt Boulevard Add 4 Express Lanes on Bridge $177.64 $5.20I‐295 Duval 119 SR 9B I‐295 Add 4 Express Lanes $12.30 $3.00I‐295 Duval 407 I‐95 North SR 105 Dames Point Bridge/Heckscher
DriveAdd 4 Express Lanes $123.30 $6.08
I‐295 Duval 408 North of Trout River I‐95 Add 4 Express Lanes $87.38 $5.18I‐295 Duval 409 US 1 New Kings Road North of Trout River Add 4 Express Lanes $28.17 $1.16I‐295 Duval 410 SR 134 103rd Street I‐10 Add 4 Express Lanes $180.57 $6.22I‐295 Duval 411 I‐10 US 1 South of New Kings Road Add 4 Express Lanes $66.47 $5.47I‐295 Duval 431 US 17 Roosevelt Boulevard SR 134 103rd Street Add 4 Express Lanes $52.45 $6.31I‐295 Duval 964 at US 17 Roosevelt Boulevard Modify Interchange $34.10 $0.19I‐295 Duval 1022 I‐95 South SR 13 San Jose Boulevard Add 2 Express Lanes $0.85 $4.46I‐295 Duval 1023 SR 202 J. T. Butler Boulevard SR 9B Add 2 Express Lanes $0.85 $4.86I‐295 Duval 121 SR 113 Southside Connector SR 202 J. T. Butler Boulevard Add 4 Express Lanes $176.80 $8.39I‐95 Duval 68 at SR 102 Airport Road Modify Interchange $9.00 $0.19I‐95 St. Johns 138 at US 1/SR 5 Ponce De Leon Boulevard and at SR Modify Interchange $13.18 $0.19I‐95 St. Johns 400 St. Johns/Flagler County Line SR 206 Add 4 Express Lanes $92.49 $8.00I‐95 Duval 413 SR 104 Dunn Avenue SR 102 Airport Road Add 4 Express Lanes $456.58 $3.62
Page 2 of 13
Path Forward 2040 Long Range Transportation Plan
Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars)Facility County Map ID From To Improvement Type 2013 Cost
(millions)O&M Cost (millions)
I‐95 Duval 414 North of Fuller Warren Bridge SR 104 Dunn Avenue Add 4 Express Lanes $2,167.51 $11.00I‐95 Duval 418A Duval/St. Johns County Line I‐295 Add 4 Express Lanes $67.16 $5.47I‐95 St. Johns 418B International Golf Parkway St. Johns/Duval County Line Add 4 Express Lanes $106.25 $8.64I‐95 Duval 419 at US 1/SR 15 MLK Modify Interchange $59.50 $0.19I‐95 St. Johns 420 SR 206 International Golf Parkway Add 4 Express Lanes $850.86 $18.00I‐95 Duval 433 SR 202 J. T. Butler Boulevard SR 10 Atlantic Boulevard Add 4 Express Lanes $301.38 $5.16I‐95 Duval 434 I‐295 SR 202 J. T. Butler Boulevard Add 4 Express Lanes $361.45 $6.21I‐95 St. Johns 846 at CR 210 Modify Interchange $36.00 $0.19I‐95 Duval 962 at SR 115 Southside Boulevard Modify Interchange $35.23 $0.19International Golf Parkway St. Johns 823 I‐95 Turn/Bend Widen to 4 Lanes* $0.43 $0.09Jones Road Duval 944 US 90 Beaver Street Pritchard Road Intersection Improvements $5.40 $0.18Kernan Boulevard Duval 73 SR 202 J. T. Butler Boulevard Glen Kernan Parkway Widen to 6 Lanes $4.50 $0.29Kernan Boulevard Duval 933 SR 10 Atlantic Boulevard SR 116 McCormick Road Widen to 6 Lanes $7.50 $0.55Knight Boxx Road Clay 901 CR 220 Doctors Inlet Road SR 21 Blanding Boulevard Widen to 6 Lanes $12.22 $0.23Lake Asbury East West 1 Clay 915 NS3 CR 209 Russell Road New 2 Lane Road $15.15 $0.08Lake Asbury North South Road 3 Clay 914 CR 739B Sandridge Road CR 209 Russell Road New 2 Lane Road $18.51 $0.10Lofton Creek Crossing Nassau 710 Hendricks Road Avant Road New 2 Lane Bridge $70.03 $0.12Long Bay Road Extension North Clay 911 Old Jennings Road Long Bay Road New 2 Lane Road $5.05 $0.03Macaw Avenue Extension Nassau 982 Cardinal Street US 17 SR 5 New 2 Lane Road $4.69 $0.03McDuff Avenue / 5th Street Duval 1019 Melson Avenue Huron Street Widen to 3 Lanes $25.09 $0.04Mentoria‐Wm Burgess Connector Nassau 990 William Burgess Boulevard Harper Chapel Road New 2 Lane Road $1.44 $0.01Merrill Road Duval 945 Hartsfield Road SR 113 Southside Connector Widen to 6 Lanes $5.03 $0.30Mickler Road St. Johns 825 Palm Valley Road SR A1A Widen to 4 Lanes $12.10 $0.13Monument Road Duval 946 Tredinick Parkway I‐295 Widen to 6 Lanes $6.15 $0.05Monument Road Duval 947 I‐295 Lee Road Widen to 6 Lanes $6.15 $0.25National Cemetery Road Duval 1033 Lannie Road Arnold Road New 2 Lane Road $25.00 $0.12New Berlin Road Duval 948 Pulaski Road Yellow Bluff Road Widen to 4 Lanes $42.67 $0.28New Berlin Road Duval 949 Yellow Bluff Road Cedar Point Road Widen to 4 Lanes $42.67 $0.10New World Avenue Duval 1034 SR 23 First Coast Expressway Chaffee Road New 2 Lane Road $4.30 $0.07New World Avenue Duval 1035 SR 23 First Coast Expressway Chaffee Road Widen to 4 Lanes $4.30 $0.17Norfolk Southern Railroad Overpass Duval 85 West 12th Street US 23 New Kings Road New 3 Lane Road / Bridge $24.90 $0.07Northern Cross Town Corridor Baker 500 CR 125 SR 121 New 2 Lane Road $6.65 $6.65Northern Outer Beltway Duval/Nassau 88 I‐10 I‐95 Future Corridor $787.90 $4.08Oakleaf Village Parkway Extension Clay 913 Oakleaf Plantation Parkway Oakleaf Village Parkway New 2 Lane Road $10.10 $0.05Old Kings Road Duval 951 SR 111 Edgewood Avenue Plummer Road Intersection Improvements $12.96 $0.30Old Middleburg Road Duval 1015 Argyle Forest Boulevard SR 134 103rd Street Widen to 4 Lanes $23.10 $0.39Old St. Augustine Road Duval 90 Bartram Park Boulevard US 1/SR 5 Phillips Highway Widen to 6 Lanes and Overpass $458.55 $0.36Old St. Augustine Road Duval 1010 at Greenland Road Intersection Improvements / Add 1 Lane $0.60 $0.05
Outer Loop Facility Baker/Duval 91 SR 228 Normandy Boulevard SR 228 Normandy Boulevard Future Corridor $1,600.00 $4.08Pages Dairy Road East Extension Nassau 987 Chester Road Blackrock Road New 2 Lane Road $7.22 $0.04Pages Dairy Road South Extension Nassau 983 SR 200 SR A1A Sowell Road New 2 Lane Road $1.70 $0.01Palm Valley Road St. Johns 826 Intracoastal Waterway Mickler Road Widen to 4 Lanes $11.43 $0.13Pecan Park Road Duval 952 Braddock Boulevard JIA North Access Road Widen to 4 Lanes $22.43 $0.09Pecan Park Road Duval 92 I‐95 US 17 Main Street Widen to 4 Lanes $5.40 $0.06Pulaski Road Duval 953*** Eastport Road I‐295 Widen to 4 Lanes $3.09 $0.03Pulaski Road / Starratt Road Duval 97 I‐295 Duval Station Road Widen to 4 Lanes $25.10 $0.28Race Track Road St. Johns 827 St. Johns Parkway Bartram Park Boulevard Widen to 4 Lanes $40.80 $0.17Race Track Road St. Johns 828 Bartram Park Boulevard Bartram Springs Widen to 4 Lanes $30.00 $0.15Race Track Road Connector St. Johns 851 Durbin Parkway / 9B Extension Race Track Road New 2 Lane Road $3.99 $0.03Ramona Boulevard Duval 935 Hammond Boulevard Cahoon Road South Widen to 5 Lanes $2.70 $0.07Rampart / Firestone Road Duval 98 Collins Road SR 134 103rd Street Widen to 4 Lanes $26.24 $0.30Ranch Road Duval 1038 Tradeport Road SR 102 North of Airport Road Widen to 4 Lanes $2.10 $0.03Ricker Road Duval 934 Morse Avenue Old Middleburg Road Widen to 3 Lanes $9.40 $0.21Salisbury Road Extension Duval 99 SR 152 Baymeadows Boulevard Belfort Road New 3 Lane Road $16.10 $0.13San Pablo Road Duval 1009 US 90 Beach Boulevard SR 10 Atlantic Boulevard Widen to 3 Lanes $35.19 $0.18Shindler Drive Duval 101 Collins Road SR 134 103rd Street Widen to 3 Lanes $11.40 $0.21SR 10 Atlantic Boulevard Duval 714 at Girvin Road Intersection Improvements $7.57 $0.05SR 10 Atlantic Boulevard Duval 715 at Hodges Boulevard Intersection Improvements $7.57 $0.05SR 10 Atlantic Boulevard Duval 716 at San Pablo Boulevard Intersection Improvements $7.57 $0.05
Page 3 of 13
Path Forward 2040 Long Range Transportation Plan
Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars)Facility County Map ID From To Improvement Type 2013 Cost
(millions)O&M Cost (millions)
SR 100 Clay 450 Clay/Bradford County Line Clay/Putnam County Line Widen to 4 Lanes $20.59 $0.49SR 100 Putnam 451 Clay/Putnam County Line US 17 SR 5 Widen to 4 Lanes $96.87 $2.06SR 101 Mayport Road Duval 152B SR 116 Wonderwood Drive Mayport Main Gate Add 2 Northbound Lanes $0.49 $0.12SR 101 Mayport Road Duval 152 at SR 116 Wonderwood Drive Intersection Improvements $0.50 $0.05SR 102 Airport Road Duval 421 Airport Entrance I‐95 Widen to 6 Lanes $8.47 $0.39SR 104 Dunn Avenue Duval 940 US 1/SR 15 New Kings Road I‐295 Widen to 4 Lanes $25.71 $0.23SR 104 Dunn Avenue Duval 941 Old Kings Road US 23 New Kings Road Intersection Improvements $3.00 $0.05SR 115 Arlington Expressway Duval 100 SR 109 University Boulevard SR 10 Atlantic Boulevard Widen to 6 Lanes* $31.66 $0.64SR 115 Arlington Expressway * Duval 153 at SR 109 University Boulevard Modify Interchange $12.50 $0.19SR 115 Lem Turner Road Duval/Nassau 74 I‐295 US 1 / Callahan S Kings Road Widen to 4 Lanes $87.00 $1.56SR 115 Southside Boulevard Duval 102 US 1/SR 5 Philips Highway I‐95 Ramps Widen to 6 Lanes* $0.97 $0.37SR 115 Southside Boulevard Duval 103 SR 202 J. T. Butler Boulevard US 90 Beach Boulevard Widen to 6 Lanes* $8.50 $0.50SR 115 Southside Boulevard Duval 104 US 90 Beach Boulevard SR 10 Atlantic Boulevard Widen to 6 Lanes* $1.22 $0.47SR 115 Southside Boulevard Duval 960 Hogan Road Gate Parkway Intersection Improvements $25.50 $0.05SR 115 Southside Boulevard Duval 966 at SR 202 J. T. Butler Boulevard Modify Interchange $35.23 $0.19SR 115 Southside Boulevard Duval 967 at SR 152 Baymeadows Road Underpass $12.50 $0.19SR 115 Southside Boulevard Duval 968 at SR 10 Atlantic Boulevard Intersection Improvements $10.30 $0.05SR 152 Baymeadows Road Duval 937 I‐95 SR 115 Southside Boulevard Widen to 6 Lanes $10.52 $0.20SR 152 Baymeadows Road Duval 938 US 1 /SR 5 Philips Highway I‐95 Widen to 6 Lanes* $0.43 $0.16SR 16 Clay 106 CR 218 SR 15A Oakridge Avenue Widen to 4 Lanes $54.70 $0.69SR 16 St. Johns 110 I‐95 SR 313 Widen to 6 Lanes $20.25 $0.50SR 16 Clay 908 US 17 Shands Bridge Widen to 4 Lanes $37.78 $0.40SR 16 St. Johns 835 South Francis Road International Golf Parkway Widen to 4 Lanes $5.90 $0.17SR 16 St. Johns 836 CR 208 Outlet Mall South Francis Road Widen to 4 Lanes $15.59 $0.45SR 16 Connector St. Johns 829 SR 16/CR 16A CR 2209 New 4 Lane Road $26.00 $0.16SR 19 Connector Putnam 965 SR 19 Putnam County Boulevard New 4 lane road / bridge $198.93 $0.34SR 20 Putnam 422 Putnam/Alachua County Line SW 56th Avenue Widen to 4 Lanes $57.95 $0.72SR 20 Putnam 423 SW 56th Avenue CR 315 Interlachen Widen to 4 Lanes $44.68 $0.34SR 200 Overpass Nassau 1003 at US 17 SR 5 and Railroad Tracks Overpass $83.20 $0.19SR 200 William Burgess Connector Nassau 998 William Burgess Boulevard SR 200 SR A1A New 2 Lane Road $4.14 $0.03SR 200 Yulee Backage Roads Nassau 992 Cardinal Street North Extension Old Yulee Road New 2 Lane Road $4.26 $0.02SR 200 SR A1A Nassau 427 at US 17 Intersection Improvements $3.00 $0.05SR 200 SR A1A Nassau 703 Amelia Island Parkway Sadler Road Widen to 6 Lanes $3.79 $0.19SR 200A Pages Dairy Road Nassau 979 at Felmor Road Roundabout Projects $0.80 $0.02SR 207 St. Johns 113 I‐95 South Holmes Boulevard Widen to 6 Lanes $26.00 $0.65SR 207 St. Johns 830 Holmes Boulevard SR 312 Widen to 6 Lanes $26.00 $0.08SR 21 Blanding Boulevard Duval 9 I‐295 Wilson Boulevard Widen to 6 Lanes $75.18 $1.01SR 21 Blanding Boulevard Clay 114 SR 16 CR 215 Blanding Boulevard Widen to 4 Lanes $34.30 $0.39SR 21 Blanding Boulevard Duval 957A at Collins Road Intersection Improvements $5.80 $0.05SR 21 Blanding Boulevard Duval 957B at SR 134 103rd Street Intersection Improvements $5.80 $0.05SR 21 Blanding Boulevard Duval 957C at Cedar Hills Boulevard Intersection Improvements $5.80 $0.05SR 228 Hart Bridge Duval 47 SR 228 Hart Expressway ‐ Downtown SR 10 Atlantic Boulevard New 6 Lane Bridge $198.00 $0.23SR 228 Normandy Boulevard Duval 86 US 301 Bell Road (Equestrian Park ) Widen to 4 Lanes $54.70 $0.66SR 228 Normandy Boulevard Duval 87 SR 23 First Coast Expressway SR 111 Cassat Avenue Widen to 6 Lanes $69.30 $1.66SR 23 First Coast Expressway Clay 41 at CR 218 New Interchange $42.19 $42.19SR 23 First Coast Expressway Clay 8202 SR 21 Blanding Boulevard US 17 New 4 Lane Road $518.83 $518.83SR 23 First Coast Expressway Clay 1011 at SR 21 Blanding Boulevard New Interchange $35.43 $35.43SR 23 First Coast Expressway Clay 1012 at CR 739 New Interchange $35.43 $35.43SR 23 First Coast Expressway Clay 1013 at SR 16 New Interchange $35.43 $35.43SR 23 First Coast Expressway Clay/Duval 8201 I‐10 SR 21 Blanding Boulevard Widen to 6 Lanes $123.66 $123.66SR 23 First Coast Expressway Clay/St. Johns 8203 US 17 I‐95 New 6 Lane Road $706.26 $706.26SR 23 First Coast Expressway St. Johns 840 at I‐95 New Interchange $35.43 $35.43SR 23 First Coast Expressway St. Johns 841 at CR 16 A New Interchange $35.43 $35.43SR 23 First Coast Expressway St. Johns 847 at CR 2209 New Interchange $42.19 $42.19SR 243 JIA North Access Road Duval 701 SR 102 Airport Road Pecan Park Road Widen to 4 Lanes $32.40 $0.34SR 312 St. Johns 115 US 1/SR 5 Dixie Highway SR A1A Widen to 6 Lanes $22.80 $0.50SR 313 St. Johns 831 SR 207 SR 16 New 6 Lane Road $39.26 $0.82SR 313 St. Johns 832 SR 16 US 1 Dixie Highway New 4 Lane Road $34.35 $0.58SR 313 St. Johns 839 at US 1/SR 5 Dixie Highway New Interchange $35.23 $0.19SR 9B Duval 1024 US 1/SR 5 Philips Highway I‐295 Add 2 Auxiliary Lanes $0.85 $3.22
Page 4 of 13
Path Forward 2040 Long Range Transportation Plan
Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars)Facility County Map ID From To Improvement Type 2013 Cost
(millions)O&M Cost (millions)
SR 9B Duval 18 US 1/SR 5 Philips Highway I‐295 Widen to 6 Lanes $31.20 $1.06SR 9B Extension St. Johns 833 St. Johns Parkway Race Track Road Widen to 6 Lanes $23.87 $0.48SR 9B Extension St. Johns 842 at Durbin Parkway New Interchange $35.23 $0.19SR A1A St. Johns 128 Solana Road SR 202 J. T. Butler Boulevard Widen to 6 Lanes* $0.99 $0.38SR A1A Nassau 706 South Fletcher Avenue Amelia Island Parkway Turn Lane Improvements* $3.00 $0.06SR A1A St. Johns 1008 at Red Cox/Coquina Rd Intersection Improvements $3.00 $0.05SR A1A St. Johns 800 Mickler Road Palm Valley Road Widen to 4 Lanes $27.00 $0.27SR A1A Duval 151 SR 116 Wonderwood Drive Naval Station Mayport North Gate Widen to 4 Lanes* $3.00 $0.16SR A1A Anastasia Boulevard St. Johns 1031 Casanova Road Bridge of Lions CSS $2.10 $0.06SR A1A St Johns River Ferry Duval 2331 Ferry Slip Replacement $8.00St. Johns Parkway St. Johns 848 CR 2209 9B Extension Widen to 6 Lanes $11.12 $0.23Starratt Road Duval 954 Duval Station Road Yellow Bluff Road Widen to 4 Lanes $27.26 $0.25Touchton Road Duval 129 Belfort Road SR 115 Southside Boulevard Widen to 4 Lanes $7.00 $0.07Town Center Boulevard Clay 903 US 17 CR 220 Doctors Inlet Road Widen to 4 Lanes $34.10 $0.36Trout River Boulevard Duval 955 Old Kings Road US 23 New Kings Road Widen to 4 Lanes $6.60 $0.06Tynes Road Clay 912 Pipit Place Oakleaf Plantation Parkway New 2 Lane Road $11.78 $0.06US 1 SR 5 St. Johns 845 at CR 210 Modify Interchange $17.53 $0.19US 1/SR 15 New Kings Road Duval 82 Soutel Drive I‐295 Widen to 6 Lanes $24.50 $0.61US 1/SR 15 New Kings Road Duval 83 I‐295 Old Kings Road Widen to 6 Lanes $40.10 $1.05US 1/SR 15 New Kings Road Duval 950 SR 111 Edgewood Avenue Soutel Drive Intersection Improvements $1.08 $0.06US 1/SR 5 Dixie Highway St. Johns 130 SR 206 Lewis Point Road Widen to 6 Lanes $47.50 $1.27US 1/SR 5 Dixie Highway St. Johns 131 SR 313 International Golf Parkway Widen to 6 Lanes $22.20 $0.56US 1/SR 5 Dixie Highway St. Johns 132 International Golf Parkway Race Track Road Widen to 6 Lanes $60.90 $1.58US 1/SR 5 Philips Highway Duval 93 Nocatee Parkway / Race Track Road SR 9B Widen to 6 Lanes $19.90 $0.50US 1/SR 5 Philips Highway Duval 94 SR 9B I‐295 Widen to 6 Lanes* $6.56 $0.58US 1/SR 5 Philips Highway Duval 95 I‐95 at the Avenues SR 202 J. T. Butler Boulevard Widen to 6 Lanes* $7.00 $0.94US 1/SR 5 Philips Highway Duval 96 SR 202 J. T. Butler Boulevard SR 126 Emerson Street Widen to 6 Lanes $31.60 $0.70US 17 Clay 133 CR 315 Town Center Boulevard Widen to 6 Lanes $18.10 $0.39US 17 Nassau 707 Nassau/Duval County Line Harts Road Intersection Improvements $2.97 $0.09US 17 Nassau 709 SR 200 SR A1A Georgia State Line Widen to 4 Lanes $79.74 $0.91US 17 Clay 1037 Governor Street Haven Avenue Widen to 4 Lanes $7.15 $0.05US 17 Main Street Duval/Nassau 78 Pecan Park Road SR 200 / SR A1A Widen to 4 Lanes $69.80 $0.40US 17 Main Street Duval 1017 New Berlin Road Pecan Park Road Widen to 4 Lanes $78.50 $0.39US 17 Main Street Duval 959 at Eastport Road New Interchange $21.41 $0.19US 17 Pages Dairy Connector w/roundabout Nassau 984 US 17 SR 5 SR 200A Pages Dairy Road New 2 Lane Road and Roundabout $3.55 $0.03
US 17 Powerline Corridor Nassau 994 Vegas Boulevard Radio Avenue New 2 Lane Road $4.26 $0.06US 17 SR 15 Putnam 428 West of Dunn Creek Bridge Horse Landing Road Widen to 4 Lanes $50.70 $0.20US 17 SR 15 Putnam 429 CR 309 Satsuma West of Dunn Creek Bridge Widen to 4 Lanes $19.07 $0.28US 17 SR 15 Putnam 430 Putnam/Volusia County Line Pomona Park/Feagle Avenue Widen to 4 Lanes $66.47 $1.28US 17 SR 15 Putnam 452 Pomona Park/Feagle Avenue CR 309 Satsuma Widen to 4 Lanes $6.72 $0.46US 17 Yulee Backage Roads Nassau 999 US 17 SR 5 North of Koen Lane New 2 Lane Road $0.85 $0.00US 1B King Street St. Johns 1029 US 1 Ponce de Leon Boulevard Avenida Menendez Context Sensitive Solutions (CSS) $3.15 $0.04US 1B San Marco Avenue St. Johns 1030 Bridge of Lions SR 16 Context Sensitive Solutions (CSS) $7.15 $0.07US 301 SR 200 Duval 123 US 90 Duval/Nassau County Line Widen to 4 Lanes $146.09 $0.43US 301 SR 200 Clay 424 Clay/Bradford County Line Duval/Clay County Line Widen to 6 Lanes $28.05 $1.16US 301 SR 200 Nassau 708 US 1 at S Kings Road Intersection Improvements $7.16 $0.05US 301 SR 201 Duval 425 Duval/Clay County Line I‐10 Widen to 6 Lanes $25.08 $1.35US 90 / SR 115 Mathews Bridge Duval 79 Alt. US 1 MLK Jr. Parkway SR 109 University Boulevard New 6 Lane Bridge and Transit $1,175.00 $0.34US 90 Beaver Street Duval 6 SR 23 First Coast Expressway Cahoon Road Widen to 4 Lanes $60.71 $0.58US 90 Beaver Street Duval 7 Cahoon Road McDuff Avenue Widen to 4 Lanes $40.82 $0.46Various SR 200 Intersections Modifications Nassau 981 Intersection Improvements $8.00 $0.05
Veterans Parkway St. Johns 834 Greenbriar Road Longleaf Pine Parkway New 4 Lane Road $36.37 $0.30Wells Road Clay 910 Aquarius Concourse SR 21 Blanding Boulevard Reconstruct and New 2 Lane Road $0.31 $0.00Woodbridge Parkway Extension Nassau 997 Woodbrigde Parkway Clements Road New 2 Lane Road $1.44 $0.01Yellow Bluff Road Duval 956 Starratt Road New Berlin Road (north) Widen to 4 Lanes $33.06 $0.28* Candidates for context sensitive solutions
Page 5 of 13
Path Forward 2040 Long Range Transportation Plan
Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars)Facility County Map ID From To Improvement Type 2013 Cost
(millions)O&M Cost (millions)
Anastasia Island (Amphitheatre) St. Johns 2380 Park and Ride Lots $0.25 $0.00Area wide Baker 2303 Local Bus Service $1.00Area wide Clay 2310 Local Bus Service $1.00Area wide Duval 2332 Local Bus Service $69.00Area wide Nassau 2370 Local Bus Service $1.00Area wide Putnam 2374 Local Bus Service $1.00Area wide St. Johns 2378 Local Bus Service $1.10Center Street Duval 2304 North of Drew Street (Baldwin) Park and Ride Lots $0.25 $0.00CR 210 St. Johns 2381 east of US 1 Park and Ride Lots $0.25 $0.00CR 220 Doctors Inlet Road Clay 2316 at Hollow Road Park and Ride Lots $0.25 $0.00Cumberland Island Ferry Nassau 2369 Fernandina Cumberland Island Ferry Service $5.00 $1.00Downtown ‐ Sports Complex Duval 2349 Downtown Jacksonville (Bay Street & Main Street) Jacksonville Municipal Stadium Streetcar $38.50 $0.41Downtown Facility Duval 2355 Transportation Center $60.00 $2.55Drew Street Duval 2305 at Center Street (Baldwin) Park and Ride Lots $0.25 $0.00Duval Road Duval 2336 at I‐95 Park and Ride Lots $0.25 $0.00East First Coast Flyer Duval 2385 Downtown Jacksonville (Duval County) 3rd Street (Jacksonville Beach) BRT $28.00 $7.08Five Points/Core/Brooklyn Duval 2347 Central Station Brooklyn Station Skyway Extension $26.60 $6.37Five Points/Core/Brooklyn Duval 2350 Five Points Downtown Jacksonville (Bay Street & Ma Streetcar $85.00 $0.41I‐95 Duval 2326 Gateway Mall Jacksonville International Airport BRT $12.20 $3.89I‐95 Duval 2330 Downtown Jacksonville (Duval County) Yulee (Nassau County) Express Bus Service $1.71La Villa/Core Duval 2351 Transportation Center Duval Street & Monroe Street to Ocean Streetcar $31.50 $0.41Mayport Road Duval 2338 at SR A1A Park and Ride Lots $0.25 $0.00North (CSX) Duval 2356 Downtown Jacksonville (Duval County) Yulee (Nassau County) Commuter Rail $271.69 $0.00North Extension (CSX) Nassau 2366 Yulee Fernandina Beach Commuter Rail $122.90 $4.49Northwest (CSX) Duval 2357 Downtown Jacksonville (Duval County) Callahan (Nassau County) Commuter Rail $179.60 $15.96Racetrack Road St. Johns 2382 at US 1 Park and Ride Lots $0.25 $0.00Riverside/Avondale Duval 2352 Riverside (King Street) Five Points Streetcar $26.25 $0.41South of Glen St. Mary Baker 2306 Park and Ride Lots $0.25 $0.00Southbank/San Marco Duval 2348 Kings Avenue Station Southwest of Railroad Tracks (SouthbankSkyway Extension $52.50 $4.24Southbank/San Marco Duval 2353 Kings Avenue Station Baptist Hospital / MOSH & Atlantic Boule Streetcar $52.50 $0.41Southeast (FEC) Duval 2327 St. Augustine (St. Johns County) Downtown Jacksonville (Duval County) Commuter Rail $0.00 $0.00Southeast Extension (FEC) St. Johns 2377 Palm Coast (Flagler County) City of St. Augustine Commuter Rail $255.20 $14.97Southwest (CSX) Duval 2358 Green Cove Springs (Clay County) Downtown Jacksonville (Duval County) Commuter Rail $294.01 $0.00Southwest Extension (CSX) Clay 2319 Palatka (Putnam County) Green Cove Springs (Clay County) Commuter Rail $236.30 $14.97Southwest First Coast Flyer Duval 2386 Wells Road Downtown Jacksonville (Duval County) BRT $19.00 $4.96Springfield Duval 2354 FSCJ Station 8th Street/ Medical Complex Streetcar $46.17 $0.41SR 115 Lem Turner Road Duval 2337 at SR 104 Dunn Avenue Park and Ride Lots $0.25 $0.00SR 115 Lem Turner Road Duval 2361 at Soutel Park and Ride Lots $0.25 $0.00SR 115 Lem Turner Road Duval 2362 at I‐295 Park and Ride Lots $0.25 $0.00SR 115 Southside Boulevard Duval 2325 Avenues Mall Regency Square Mall BRT $18.00 $2.83SR 134 103rd Street Duval 2321 SR 228 Normandy Boulevard SR 21 Blanding Boulevard BRT $38.35 $2.16SR 134 103rd Street Duval 2334 at SR 228 Normandy Boulevard Park and Ride Lots $0.25 $0.00SR 16*** St. Johns 2385 Park and Ride Lots $0.25 $0.00SR 200 SR A1A Nassau 2371 at I‐95 Park and Ride Lots $0.25 $0.00SR 200 SR A1A Nassau 2372 east of Yulee Park and Ride Lots $0.25 $0.00SR 207*** St. Johns 2386 Park and Ride Lots $0.25 $0.00SR 21 Blanding Boulevard Clay 2308 CR 218 Wells Road BRT $37.50 $3.01SR 21 Blanding Boulevard Clay 2311 at Tanglewood Park and Ride Lots $0.25 $0.00SR 21 Blanding Boulevard Clay 2312 at Old Jennings Road Park and Ride Lots $0.25 $0.00SR 21 Blanding Boulevard Clay 2313 at Edson Drive Park and Ride Lots $0.25 $0.00SR 21 Blanding Boulevard Clay 2314 at Wells Road Park and Ride Lots $0.25 $0.00SR 21 Blanding Boulevard Clay 2315 at SR 224 Kingsley Avenue Park and Ride Lots $0.25 $0.00SR 21 Blanding Boulevard Clay 2318 North and South of Bolton Road Park and Ride Lots $0.25 $0.00SR 21 Blanding Boulevard Duval 2335 at Weconnett Boulevard Park and Ride Lots $0.25 $0.00SR 21 Blanding Boulevard Duval 2340 North and South of Wilson Boulevard Park and Ride Lots $0.09 $0.00SR 21 Blanding Boulevard Duval 2341 North and South of SR 134 103rd Street Park and Ride Lots $0.25 $0.00SR 21 Blanding Boulevard Duval 2360 at 105th Street Park and Ride Lots $0.25 $0.00SR 21 Blanding Boulevard Duval 2364 North of I‐295 Park and Ride Lots $0.25 $0.00SR 228 Normandy Boulevard Duval 2322 SR 134 103rd Street Downtown Jacksonville (Duval County) BRT $97.45 $5.49
Transit Capacity Projects
Page 6 of 13
Path Forward 2040 Long Range Transportation Plan
Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars)Facility County Map ID From To Improvement Type 2013 Cost
(millions)O&M Cost (millions)
SR A1A Duval 2343 North and South of SR 202 J. T. Butler Boulevard Park and Ride Lots $0.25 $0.00SR A1A St. Johns 2379 at Palm Valley Road Park and Ride Lots $0.25 $0.00SR A1A St Johns River Ferry Duval 2329 Drydock / Ferry Repairs $13.00 $13.00SR A1A St Johns River Ferry Duval 2331 Ferry Slip Replacement $8.00SR A1A St Johns River Ferry Duval 2333 Ft. George/Mayport Long Term Site Improvements $8.00SR A1A St Johns River Ferry Duval 2344 JPA Property Mayport Terminal Relocation of Ferry offices $0.29SR A1A St Johns River Ferry Duval 2345 Mayport Ft. George Island Service & Capital Improvements $7.00 $0.80SR A1A St Johns River Ferry Duval 2346 Ft. George/Mayport Site Improvements $0.89St. Augustine Airport St. Johns 2383 Park and Ride Lots $0.25 $0.00US 1 St. Johns 2384 at Lewis Speedway Road Park and Ride Lots $0.25 $0.00US 1 Duval 2324 Lewis Speedway (St. Johns County) Avenues Mall (Duval County) BRT $132.03 $7.43US 1 St. Johns 2375 Lewis Speedway (St. Johns County) Avenues Mall (Duval County) BRTUS 1/SR 15 New Kings Road Duval 2323 Downtown Jacksonville (Duval County) Edgewood Avenue BRT $29.55 $1.66US 1/SR 15 New Kings Road Duval 2363 Timucuan DRI Park and Ride Lots $0.25 $0.00US 17 Roosevelt Boulevard Clay 2320 at Wells Road Park and Ride Lots $0.25 $0.00US 17 Roosevelt Boulevard Duval 2342 at SR 128 San Juan Avenue Park and Ride Lots $0.25 $0.00US 90 Baker 2302 MacClenny (Baker County) Downtown Jacksonville (Duval County) Local Bus Service $2.14US 90 Beach Boulevard Duval 2339 West and East of Kernan Boulevard Park and Ride Lots $1.08 $0.00US 90 Beach Boulevard Duval 2359 at San Pablo Road Park and Ride Lots $0.25 $0.00West (CSX) Duval 2328 Baldwin (Duval County) Downtown Jacksonville (Duval County) Commuter Rail $170.10 $9.48West Extension (CSX) Baker 2301 MacClenny (Baker County) Baldwin (Duval County) Commuter Rail $85.10 $5.49Yellow Water Road Duval 2307 North of I‐10 Park and Ride Lots $0.25 $0.00Youngerman Circle Clay 2317 at Argyle Forest Boulevard Park and Ride Lots $0.25 $0.00
SR 121 Rail Trail Corridor Baker 2000 Baker/Union County Line Baker/Nassau County Line Florida Greenway $3.08 $0.12Cecil Field Conservation Corridor Clay 2001 CR 218 Duval/Clay County Line Land Trail Opportunities $2.54 $0.10CR 218 Clay 2002 SR 16 SR 21 Florida Greenway $1.73 $0.07CR 220 Doctors Inlet Road Clay 2004 College Drive US 17 Multi‐Use Trail $0.93 $0.04CR 220 Doctors Inlet Road Clay 2003 SR 21 College Drive Florida Greenway $1.62 $0.06Long Bay Road Clay 2005 SR 21 Blanding Boulevard Old Jennings Road Multi‐Use Trail $1.28 $0.03Old Jennings Road Clay 2006 Long Bay Road SR 23 First Coast Expressway Multi‐Use Trail $0.46 $0.02US 17 Clay 2007 at CR 220 (Fleming Island Area) Accommodate Pedestrians and Bicyclist $0.34 $0.00US 17 Roosevelt Boulevard / Park Avenue Clay 2009 Palatka Clay/Duval County Line Florida Greenway $18.14 $0.72US 17 Park Avenue Clay 2008 at Kingsley Avenue (Orange Park) Accommodate Pedestrians and Bicyclist $0.04 $0.00SR 16 Clay / St. Johns 2010 Kingsley Lake Drive SR 13 San Jose Boulevard Florida Greenway ‐ Multi‐Use Trail $6.48 $0.265th Street Duval 2012 Lane Avenue Melson Avenue Bike Lane $0.40 $0.02Arlington Road Duval 2013 Lone Star Road King Arthur Road Bike Lane $0.01 $0.00Arlington Road West Duval 2014 Cesery Road King Arthur Road Bike Lane $0.11 $0.00Bay Street Duval 2019 Myrtle Avenue Lee Street Bike Lane $0.09 $0.00Baymeadows Road Duval 2020 SR 115 at Southside Boulevard Accommodate Pedestrians and Bicyclist $0.03 $0.00Beauclerc Road Duval 2023 I‐295 SR 13 San Jose Boulevard Bi‐directional 12 ft. Shared Use Path $0.64 $0.03Boulevard Street Duval 2026 5th Street 12th Street Bike Lane $0.15 $0.01Bowden Road Duval 2028 Spring Park Road Southpoint Parkway Bike Lane $0.06 $0.00Bowden Road Duval 2027 US 1 Philips Highway Spring Park Road Bike Lane $0.14 $0.01Broad Street Duval 2029 Water Street 5th Street Bike Lane $0.27 $0.01Cecil Field Conservation Corridor Duval 2031 Duval/Clay County Line US 90 Beaver Street Florida Greenway $2.78 $0.11Clark Road Duval 2032 Broward Road US 17 Main Street Bike Lane $0.19 $0.01Commonwealth Avenue Duval 2033 Imeson Road Lane Avenue Bike Lane $0.30 $0.01CSX Corridor North Duval 2034 US 17 Main Street / S Rail Line US 17 Main Street / Trout River Drive Multi‐Use Path $0.71 $0.03Deerwood Area Duval 2035 Deerwood Park Boulevard Gate Parkway Multi‐Use Path $0.17 $0.01Downtown Jacksonville Duval 2036 Accommodate Pedestrians and Bicyclist $1.45 $0.02Downtown Neptune/Atlantic Beach Duval 2037 at Sherry Drive, 2nd Street, Ocean Street, Cherry Stre Accommodate Pedestrians and Bicyclist $0.07 $0.00Duval Road Duval 2039 Airport Road Airport Center Drive Bike Lane $0.15 $0.01Duval Street Duval 2040 Lee Street Georgia Street Bike Lane $0.41 $0.02East Coast Greenway ‐ Duval County Corridor Duval 2041 St. Johns/ Duval County Line Nassau/Duval County Line Florida Greenway $11.30 $0.21Edgewood Avenue Duval 2043 St. Johns Avenue Post Street Bike Lane $0.32 $0.01Forest Street Duval 2045 Acosta Street Lime Street Bike Lane $0.13 $0.01Forsyth Street Duval 2046 Myrtle Avenue Lee Street Bike Lane $0.09 $0.00Gate Parkway East Duval 2047 Gate Parkway St. Johns Town Center Boulevard Multi‐Use Path $0.05 $0.00
Bicycle and Pedestrian Projects
Page 7 of 13
Path Forward 2040 Long Range Transportation Plan
Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars)Facility County Map ID From To Improvement Type 2013 Cost
(millions)O&M Cost (millions)
Gate Parkway South East Duval 2048 Deerwood Parkway St. Johns Town Center Boulevard Bike Lane $0.11 $0.00Hogan's Creek Greenway Duval 2052 Market Street North Riverbank Multi‐Use Path $0.23 $0.01Hubbard Street Duval 2053 Orange Street 14th Street Bike Lane $0.11 $0.01Imeson Road Duval 2054 Commonwealth Avenue Baldwin Rail Trail Bike Lane $0.08 $0.00Jacksonville Baldwin / East Coast Corridor Duval 2055 Bulls Bay Highway (Jacksonville Baldwin Corridor) St Johns River Ferry (East Coast GreenwayFlorida Greenway $17.47 $0.26Jacksonville Beach Area Duval 2056 at 3rd Avenue, Ocean Street, 2nd Avenue, South 10t Accommodate Pedestrians and Bicyclist $0.23 $0.00Jefferson Street Duval 2057 Water Street 1st Street Bike Lane $0.21 $0.01Kernan Boulevard Duval 2058 Baymeadows Road (SR 152) SR 116 Fort Caroline Road Florida Greenway $3.05 $0.12Laura Street Duval 2059 8th Street S‐Line Pavement Markings and Signage $0.06 $0.00Laura Street Duval 2060 Bay Street 8th Street Pavement Markings and Signage $0.06 $0.00Lee Street Duval 2061 Water Street Duval Street Bike Lane $0.07 $0.00Lone Star Road Duval 2062 Mill Creek Road SR 113 Southside Connector Bike Lane $0.11 $0.00Mandarin Road Duval 2065 San Jose Boulevard (SR 13) I‐295 Bi‐directional 12 ft. Shared Use Path $1.50 $0.06Mary Street Duval 2089 San Marco Boulevard US 17 Main Street Bridge Bike Lane $0.03 $0.00McCoys Creek Boulevard / Fitzgerald Street Duval 2067 Nixon Street Forest Street Multi‐Use Path $0.03 $0.00McCoys Creek Boulevard / Fitzgerald Street Duval 2066 McDuff Avenue Leland Street Bike Lane $0.10 $0.00Moncrief Road Duval 2068 13th Street Golfair Boulevard Bike Lane $0.30 $0.01Monument Road and SR 10 Atlantic Boulevard Duval 2069 SR 113 Southside Boulevard N Regency Square Boulevard Bike Lane $0.33 $0.01Myrtle Avenue Duval 2070 Forest Street Kings Road Bike Lane $0.29 $0.01Newnan Street Duval 2071 Bay Street Orange Street Pavement Markings and Signage $0.07 $0.00Old Kings Road Duval 2073 S‐line Martha Street Bike Lane $0.05 $0.00Old Middleburg Road Duval 2074 Herlong Road Lenox Avenue Bike Lane $0.28 $0.01Old St Augustine Road Duval 2075 Losco Road SR 13 San Jose Boulevard Bike Lane $0.05 $0.00Riverplace Boulevard Duval 2078 Prudential Drive US 1 Main Street Bike Lane $0.08 $0.00Riverside/Five Point Area Duval 2080 at Stockton Street, Rossell Street, I‐95, St. Johns Rive Accommodate Pedestrians and Bicyclist $0.67 $0.01Southpoint Parkway Duval 2090 Belfort Road Bowden Road Bike Lane $0.38 $0.02SR 10 Atlantic Boulevard Duval 2017 Kings Road US 90 Beach Boulevard Bike Lane $0.18 $0.01SR 10 Atlantic Boulevard Duval 2016 US 90 Beach Boulevard SR 228 Alt. US 1 Hart Expressway Bike Lane $0.23 $0.01SR 10 Atlantic Boulevard Duval 2018 SR 228 Hart Expressway SR 109 University Boulevard Bike Lane $0.29 $0.01SR 10 Atlantic Boulevard Duval 2015 Hart Expressway (SR 228 Alt. US 1) SR A1A Bi‐directional 12 ft. Shared Use Path $3.16 $0.12SR 104 Dunn Avenue Duval 2038 Biscayne Avenue US 17 Main Street Bike Lane $0.37 $0.02SR 105 Zoo Parkway Duval 2049 Busch Drive I‐295 Bike Lane $0.12 $0.01SR 105 Zoo Parkway Duval 2050 US 17 Main Street SR A1A Multi‐Use Path $0.14 $0.01SR 109 University Boulevard North Duval 2102 SR 10 Atlantic Boulevard Cesery Boulevard Bike Lane $0.11 $0.00SR 109 University Boulevard North Duval 2103 University Boulevard / Cesery Boulevard Gable Lane Bike Lane $0.36 $0.01SR 111 Cassat Avenue Duval 2030 SR 21 Blanding Boulevard SR 111 Edgewood Avenue Bike Lane $0.77 $0.03SR 111 Edgewood Avenue Duval 2042 SR 111 Cassat Avenue US 1/SR 15 New Kings Road Bike Lane $0.77 $0.03SR 111 Tallulah Avenue Duval 2099 US 17 Main Street 68th Street Bike Lane $0.22 $0.01SR 115 Southside Boulevard Duval 2094 Gate Parkway Touchton Road Sidewalk Improvements $0.14 $0.00SR 115 Southside Boulevard Duval 2095 US 1 Philips Highway Belle Rive Boulevard Sidewalk Improvements $0.48 $0.00SR 115 Southside Boulevard Duval 2093 Deerwood Park Boulevard US 90 Beach Boulevard Sidewalk Improvements $0.72 $0.00SR 115 Southside Boulevard Duval 2092 US 1 Philips Highway Belle Rive Boulevard Multi‐Use Path $0.43 $0.02SR 115 Southside Boulevard Duval 2091 Avenues Mall (US 1) SR 10 Atlantic Boulevard / Regency SquarBi‐directional 12 ft. Shared Use Path $2.30 $0.09SR 126 Emerson Street Duval 2044 Hendricks Avenue US 1 Philips Highway Bike Lane $0.25 $0.01SR 128 San Juan Avenue Duval 2088 SR 21 Blanding Boulevard SR 211 Herschel Street Bike Lane $0.20 $0.01SR 13 Hendricks Avenue Duval 2051 SR 13 San Jose Boulevard San Marco Boulevard Bike Lane $0.50 $0.02SR 13 San Jose Boulevard Duval 2086 Julington Creek Road Plummers Cove Road Bike Lane $0.07 $0.00SR 13 San Jose Boulevard Duval 2085 Old St. Augustine Road SR 152 Baymeadows Road Bike Lane $0.22 $0.01SR 13 San Jose Boulevard Duval 2084 SR 152 Baymeadows Road Hendricks Avenue Bike Lane $1.07 $0.04SR 13 San Jose Boulevard Duval 2087 Loretto Road SR 152 Baymeadows Road Accommodate Pedestrians and Bicyclist $3.18 $0.04SR 13 San Jose Boulevard Duval 2083 Racetrack Road Downtown (Southbank) Bi‐directional 12 ft. Shared Use Path $3.10 $0.12SR 134 103rd Street Duval 2011 Old Middleburg Road Old Middleburg Road North Bike Lane $0.19 $0.01SR 21 Blanding Boulevard Duval 2024 Blackburn Road Appleton Avenue Bike Lane $0.09 $0.00SR 21 Blanding Boulevard Duval 2025 Harlow Boulevard Wilson Boulevard Bike Lane $0.15 $0.01SR 211 Riverside Avenue Duval 2079 St. Johns Avenue Forest Street Bike Lane $0.36 $0.01SR 211 St. Johns Avenue Duval 2098 Woodmere Street Talbot Avenue Bike Lane $0.22 $0.01SR 228 Normandy Boulevard Duval 2072 SR 103 Lane Avenue SR 111 Cassat Avenue Bike Lane $0.30 $0.01SR A1A Duval 2096 SR 202 J. T. Butler Boulevard SR 10 Atlantic Boulevard Bi‐directional 12 ft. Shared Use Path $1.09 $0.04SR A1A Duval 2097 St. Johns River Ferry Duval/Nassau County Line Bi‐directional 12 ft. Shared Use Path $2.27 $0.09UNF East Duval 2100 Kernan Boulevard UNF West Bike Lane $0.20 $0.01
Page 8 of 13
Path Forward 2040 Long Range Transportation Plan
Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars)Facility County Map ID From To Improvement Type 2013 Cost
(millions)O&M Cost (millions)
UNF West Duval 2101 I‐295 UNF East Bike Lane $0.43 $0.02US 1 Philips Highway Duval 2077 Southside Boulevard (SR 115) Southbank Riverwalk Rails‐W‐Trails $2.46 $0.11US 1 Philips Highway Duval 2076 Racetrack Road Downtown (Southbank) Bi‐directional 12 ft. Shared Use Path $4.39 $0.17US 17 Main Street Duval 2064 Trout River Bridge New Berlin Road Rails‐W‐Trails $0.98 $0.04US 17 Main Street Duval 2063 Eastport Road Pecan Park Road Bi‐directional 12 ft. Shared Use Path $2.30 $0.09US 17 Roosevelt Boulevard Duval 2082 Duval/Clay County Line Forest Street Rails‐W‐Trails $2.28 $0.10US 17 Roosevelt Boulevard Duval 2081 I‐295 Edison Avenue Bi‐directional 12 ft. Shared Use Path $2.28 $0.09US 17 Roosevelt Boulevard Duval 2104 Duval/Clay County Line Forest Street Florida Greenway $4.13 $0.16US 90 Beach Boulevard Duval 2022 at Hodges Boulevard Accommodate Pedestrians and Bicyclist $0.00 $0.00US 90 Beach Boulevard Duval 2021 San Pablo Boulevard Downtown (Southbank) Bi‐directional 12 ft. Shared Use Path $1.97 $0.08Water Street Duval 2105 Lee Street Pearl Street Bike Lane $0.10 $0.00Jacksonville Baldwin Corridor Duval / Nassau 2106 West of Baldwin Bulls Bay Highway Florida Greenway $1.40 $0.158th Street Nassau 2107 at Sadler Road Accommodate Pedestrians and Bicyclist $0.00 $0.00Amelia Island Parkway Nassau 2108 at Amelia Road Accommodate Pedestrians and Bicyclist $0.01 $0.00Amelia Island Parkway Path Segment 1 Nassau 2109 Bailey Road 8th Street/ SR A1A Multi‐Use Trail $0.63 $0.01Amelia Island Parkway Path Segment 2 Nassau 2110 14th Street Bailey Road Multi‐Use Trail $0.63 $0.01Amelia Island Parkway Path Segment 3 Nassau 2111 Via Del Rey 14th Steet Multi‐Use Trail $0.63 $0.01Amelia Island Parkway Path Segment 4 Nassau 2112 SR A1A Fletcher Avenue / Amelia Island Trail Via Del Rey Multi‐Use Trail $0.63 $0.01Amelia Island Trial ‐ Central (1st Ave) Nassau 2113.1 Bill Melton Matanzas Way Trail $0.16 $0.01Amelia Island Trial ‐ South (Buccaneer Trail) Nassau 2113 Fletcher Avenue Amelia Island Pkwy Trail $0.29 $0.01Amelia Island Trial‐ North ( Friendly/Clinch) Nassau 2113.2 Bailey Road Atlantic Avenue Trail $0.96 $0.04American Beach Loop Nassau 2114 American Beach Loop Julia Street Segment American Beach Bike Lane $0.11 $0.00American Beach Loop Nassau 2116 American Beach Loop Ocean Avenue Segment American Beach Multi‐Use Path $0.36 $0.00American Beach Loop Nassau 2115 American Beach Loop Burney Road Segment American Beach Multi‐Use Path $0.60 $0.01Crandall Parkway Corridor Nassau 2117 East Coast Greenway (US 17) SR A1A East Coast Greenway Corridor Florida Greenway $1.75 $0.07East Coast Greenway ‐ Nassau County Corridor Nassau 2118 Nassau/Duval County Line Fernandina Beach Florida Greenway $2.02 $0.11ENCPA DSAP 1‐ Central (Old Yulee Vicinity) Nassau 2120.1 East Nassau Community Planning Area East Nassau Community Planning Area Multi‐Use Path $4.03 $0.16ENCPA DSAP 1‐ North (Owens Rd Vicinity) Nassau 2120.2 East Nassau Community Planning Area East Nassau Community Planning Area Multi‐Use Path $0.78 $0.03ENCPA DSAP 1‐ South (Harper Chapel Vicinity) Nassau 2120 East Nassau Community Planning Area East Nassau Community Planning Area Multi‐Use Path $0.66 $0.03Highland Broom Street Nassau 2121 Proposed Highland Broom Street Multi‐use Trail Proposed Highland Broom Street Multi‐Use Path $0.36 $0.01Maxine Street Nassau 2123 Maxine Street Path Maxine Street Path Multi‐Use Path $0.13 $0.01Ocklawaha Trail Nassau 2124 Via Del Rey / Bill Melton Road Sadler Road Multi‐Use Trail $0.94 $0.03Orange Avenue Nassau 2125 Orange Avenue Path Orange Avenue Path Multi‐Use Path $0.25 $0.01Simmons Connector Nassau 2126 Simmons/AIP Connector Simmons/AIP Connector Multi‐Use Trail $1.72 $0.02SR 200 SR A1A Nassau 2127 at SR 200 Bridge Accommodate Pedestrians and Bicyclist $0.71 $0.01US 17 Nassau 2129 Nassau/Duval County Line SR 200 SR A1A Bi‐directional 12 ft. Shared Use Path $3.13 $0.12US 17 / SR A1A East Coast Greenway Nassau 2119 Fernandina Beach Georgia State Line Florida Greenway $30.08 $0.19US 301/ SR 200 Trans Nassau Trail Corridor Nassau 2128 CR 119 US 17 Main Street / Yulee Florida Greenway $6.58 $0.26William Burgess Boulevard Nassau 2130 SR 200 SR A1A US 17 Multi‐Use Trail $0.79 $0.03CR 121/CR 119 Jacksonville Baldwin Rail Trail Northern Extension CorridNassau / Duval 2122 Beaver Street (US 90) US 301/SR 200 Trans Nassau Trail Corrid Florida Greenway $3.09 $0.12CR 216 Putnam 2131 SR 100 US 17 Multi‐Use Path $0.58 $0.02Cross Florida Greenway Corridor Putnam 2132 Existing Cross Florida Greenway Trail Palatka Florida Greenway $6.05 $0.08SR 100 Putnam 2133 Clay/Putnam County Line Palatka Florida Greenway $9.43 $0.23SR 20 Putnam 2134 Hawthorne Palatka Florida Greenway $15.23 $0.24US 17 Putnam 2135 Putnam/Volusia County Line Palatka Florida Greenway $38.54 $0.25US 17 Crescent City (parallel facilities) Putnam 2136 Prospect Street CR 308 Multi‐Use Path $0.58 $0.02SR 207 Putnam / St. Joh 2137 Palatka St. Augustine Florida Greenway $10.48 $0.23County Road 214 Corridor St. Johns 2138 SR 13 San Jose Boulevard SR 207 Florida Greenway $2.74 $0.11CR 13 Spuds Palmo Trail Corridor St. Johns 2149 Spuds (SR 207) SR 13 San Jose Boulevard Florida Greenway $5.10 $0.20CR210 St. Johns 2139 at SR A1A Accommodate Pedestrians and Bicyclist $0.02 $0.00Deep Creek to ECG Corridor St. Johns 2140 SR 207 SR A1A Florida Greenway $3.21 $0.13Downtown and Uptown St. Augustine St. Johns 2141 at US 1, Park Avenue, River, South Street, Riberia Str Accommodate Pedestrians and Bicyclist $1.13 $0.01East Coast Greenway ‐ St. Johns County Corridor St. Johns 2142 St. Johns/Flagler County Line St. Johns/Duval County Line Florida Greenway $27.88 $0.41Nocatee Corridor St. Johns 2143 San Jose Boulevard (SR 13) SR A1A Florida Greenway $5.10 $0.20Race Track Road St. Johns 2147 San Jose Boulevard (SR 13) US 1 Philips Highway Bi‐directional 12 ft. Shared Use Path $2.14 $0.08Racetrack Corridor St. Johns 2148 San Jose Boulevard (SR 13) Nocatee Corridor Florida Greenway $2.14 $0.09SR 13 San Jose Boulevard St. Johns 2150 Roberts Road Julington Creek Bi‐directional 12 ft. Shared Use Path $0.65 $0.03SR 13 William Bartram Trail Corridor St. Johns 2155 CR 13 St. Johns/Duval County Line Florida Greenway $3.76 $0.15SR 16 St. Johns 2151 I‐95 Collins Avenue Bi‐directional 12 ft. Shared Use Path $0.77 $0.03SR A1A St. Johns 2152 at SR 312 Accommodate Pedestrians and Bicyclist $0.03 $0.00
Page 9 of 13
Path Forward 2040 Long Range Transportation Plan
Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars)Facility County Map ID From To Improvement Type 2013 Cost
(millions)O&M Cost (millions)
St. Augustine Bike Plan St. Johns 2153 Areawide Areawide Bicycle accommodations $1.17 $0.00US 1 Dixie Highway St. Johns 2146 at SR 312 Accommodate Pedestrians and Bicyclist $0.00 $0.00US 1 Dixie Highway St. Johns 2145 Putnam/Flagler County Line SR 207 Bi‐directional 12 ft. Shared Use Path $3.77 $0.15US 1 Dixie Highway / Ponce De Leon Boulevard St. Johns 2144 San Marco Avenue (US 1 B) (St. Augustine) Racetrack Road Bi‐directional 12 ft. Shared Use Path $3.88 $0.15US 1 St. Augustine to Nocatee Corridor St. Johns 2154 St. Augustine Nocatee Corridor Florida Greenway $3.79 $0.15
CSX Transportation Clay 2200 at Wells Road Grade Separation $56.74 $0.10CSX Transportation Clay 2201 at SR 224 Kingsley Avenue Grade Separation $56.74 $0.10CSX Transportation Duval 2202 at SR 104 Busch Drive Grade Separation $90.78 $0.10CSX Transportation Nassau 2203 at SR A1A (SR 200) / Yulee Grade Separation $68.08 $0.10CSX Transportation Duval 2204 Beaver Street Interlocking Capacity Upgrade $6.00 $0.10CSX Transportation Duval 2205 North Rail Corridors Phase 1 Multi Modal Corridor $40.00 $0.10CSX Transportation Duval 2206 Westlake Cecil Commerce Connector Multi Modal Corridor $30.00 $0.10Florida East Coast Railway Duval 2207 at Bowden Intermodal Capacity Upgrade $14.36 $0.10Florida East Coast Railway Duval 2208 at Jacksonville Bridge Bridge $8.84 $0.10Jacksonville International Airport Duval 2209 Construction of Runway 7R/25L Construct Runway $53.50 $0.10Jacksonville International Airport Duval 2210 Air Cargo Ramp Improvements Expand Apron $2.82 $0.10Jacksonville International Airport Duval 2211 Air Cargo Surface Storage Expand Apron $0.54 $0.10Jacksonville International Airport Duval 2212 Design & Construct By‐Pass Taxiways Construct Taxiway $8.65 $0.10Jacksonville International Airport Duval 2213 Intermodal Terminal Facility Development Terminal Development $99.42 $0.10Norfolk Southern Duval 2214 at Norfolk Southern Railway (Near Simpson Yard) Grade Separation $14.75 $0.10Jacksonville Port Authority Duval 2215 Blount Island / Dames Point Marine Terminals Rail Internal Rail $32.42 $0.10Jacksonville Port Authority Duval 2216 Blount Island Marine Terminal Berth Upgrades Docks $32.42 $0.10Jacksonville Port Authority Duval 2217 Blount Island Marine Terminal Facility Upgrades Intermodal Transfer Improvement $97.26 $0.10Jacksonville Port Authority Duval 2218 Dames Point Marine Terminal Berth Upgrades Docks $54.04 $0.10Jacksonville Port Authority Duval 2219 Dames Point Marine Terminal Facility Upgrades Intermodal Transfer Improvement $97.26 $0.10Jacksonville Port Authority Duval 2220 New Cranes for Talleyrand and Blount Island Marine Terminals Intermodal Transfer Improvement $86.45 $0.10Jacksonville Port Authority Duval 2221 Talleyrand Marine Terminal Berth Upgrades Docks $43.23 $0.10Jacksonville Port Authority Duval 2222 Talleyrand Marine Terminal Facility Upgrades Intermodal Transfer Improvement $32.42 $0.10Jacksonville Port Authority Duval 2223 Talleyrand Marine Terminal Rail Internal Rail $21.62 $0.10Jacksonville Port Authority Duval 2224 Blount Island Marine Terminal Facility Upgrades Intermodal Transfer Improvement $81.05 $0.10Jacksonville Port Authority Duval 2225 Dames Point Marine Terminal Facility Upgrades Intermodal Transfer Improvement $37.82 $0.10Jacksonville Port Authority Duval 2226 New Cranes for Talleyrand and Blount Island Marine Terminals Intermodal Transfer Improvement $43.23 $0.10Jacksonville Port Authority Duval 2227 Talleyrand Marine Terminal Facility Upgrades Intermodal Transfer Improvement $21.62 $0.10Jacksonville Port Authority Duval 2228 Blount Island / Dames Point Terminals ‐ Rail and Bridge Internal Rail $270.18 $0.10Jacksonville Port Authority Duval 2229 Blount Island Marine Terminal Berth Upgrades Docks $43.23 $0.10Jacksonville Port Authority Duval 2230 Blount Island Marine Terminal Facility Upgrades Intermodal Transfer Improvement $81.50 $0.10Jacksonville Port Authority Duval 2231 Dames Point Marine Terminal Berth Upgrades Docks $32.42 $0.10Jacksonville Port Authority Duval 2232 Dames Point Marine Terminal Facility Upgrades Intermodal Transfer Improvement $32.42 $0.10Jacksonville Port Authority Duval 2233 Harbor Deepening Dredging Harbor $648.42 $0.10Jacksonville Port Authority Duval 2234 New Cranes for Talleyrand and Blount Island Marine Terminals Intermodal Transfer Improvement $32.42 $0.10Jacksonville Port Authority Duval 2235 Talleyrand Marine Terminal Berth Upgrades Docks $27.02 $0.10Jacksonville Port Authority Duval 2236 Talleyrand Marine Terminal Facility Upgrades Intermodal Transfer Improvement $21.61 $0.10Jacksonville Port Authority Duval 2237 Talleyrand Marine Terminal Rail Internal Rail $10.81 $0.10CSX Transportation Duval/Baker 2238 MacClenny to Jacksonville Upgrade to Accommodate Freight and Passenger Service* $85.10CSX Transportation Duval/Clay 2239 Green Cove Springs to Jacksonville Upgrade to Accommodate Freight and Passenger Service $294.00CSX Transportation Duval/Nassau 2240 Jacksonville to Yulee Upgrade to Accommodate Freight and Passenger Service $271.69Florida East Coast Railway Duval/St. Johns 2241 St. Augustine to Jacksonville Upgrade to Accommodate Freight and Passenger Service $0.00CSX Transportation Duval 2242 at US 301 (SR 200) / Baldwin Grade Separation $53.33 $0.10CSX Transportation Nassau 2243 at US 301 / Crawford Diamond Grade Separation $32.42 $0.10Port of Fernandina Nassau 2244 Berth Improvements Docks $0.86 $0.10Port of Fernandina Nassau 2245 Cruise / Cargo Berth Docks $10.81 $0.10Port of Fernandina Nassau 2246 Rail Track Improvements Internal Rail $0.65 $0.10Port of Fernandina Nassau 2247 at Fernandina Port Access Improvements $5.00 $0.10City of Palatka Putnam 2248 SR 100 CR 309D Runway expansion $15.00 $0.10County Putnam 2249 Barge Port Operational and Capital Improvements $15.00 $0.10CSX Transportation Putnam 2250 at SR 15 Reid Street Grade Separation $49.75 $0.10City of Saint Augustine St. Johns 2251 Historic Commercial Areas Mobility & Distribution Improvements $10.00 $0.10Florida East Coast Railway Statewide 2252 Amtrak Service Miami to Jacksonville New Passenger Service $162.16 $0.10
Multimodal Freight Projects
Page 10 of 13
Path Forward 2040 Long Range Transportation Plan
Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars)Facility County Map ID From To Improvement Type 2013 Cost
(millions)O&M Cost (millions)
Florida East Coast Railway Statewide 2253 Miami to Jacksonville Upgrade Bolt and Clip System Track Upgrade $21.67 $0.10Intercity Passenger Rail Statewide 2254 New Orleans to Jacksonville New Passenger Service TBD $0.10Intercity Passenger Rail Statewide 2255 Jacksonville to Savannah New Passenger Service TBD $0.10Intercity Passenger Rail Statewide 2256 Orlando to Jacksonville New Passenger Service TBD $0.10Norfolk Southern Duval 2257 Soutel Drive to Norfolk Southern Intermodal Yard New Connector $14.65 $0.10CSX Transportation Duval 2258 North Rail Corridors Phase 2 Multi Modal Corridor $5.00 $0.10Florida East Coast Railway Duval 2259 at Sunbeam Road Grade Separation $52.82Downtown Transportation Center* Duval 2355 Downtown Facility Transportation Center $60.00Jacksonville Port Authority Duval 1006 Spoil Island Connector Bridge New 2 Lane Bridge $80.21Florida East Coast Railway Duval 2260 at Shad Road Grade Separation $40.00* Project costs are identified in the Transit Capacity Needs table.
SR 21 Blanding Boulevard Clay 209 at Arora Boulevard Safety Projects ‐ Intersections $1.50 $0.05
SR 21 Blanding Boulevard Clay 212 at SR 16 Safety Projects ‐ Intersections $1.50 $0.05
SR 21 Blanding Boulevard Clay 215 at Youngerman Circle Safety Projects ‐ Intersections $1.50 $0.05
SR 21 Blanding Boulevard Clay 219 at Argyle Forest Boulevard Safety Projects ‐ Intersections $1.50 $0.05
SR 21 Blanding Boulevard Clay 221 at Wells Road Safety Projects ‐ Intersections $1.50 $0.05
SR 21 Blanding Boulevard Clay 231 at CR 215 Safety Projects ‐ Intersections $1.50 $0.05
SR 21 Blanding Boulevard Clay 605 Everett Avenue Old Jennings Road Safety Projects ‐ Corridors $7.05 $0.46
SR 21 Blanding Boulevard Clay 606 Old Jennings Road Argyle Forest Boulevard Safety Projects ‐ Corridors $11.10 $0.73
SR 21 Blanding Boulevard Clay 241 SR 16 CR 218 Safety Projects ‐ Corridors $11.85 $0.78
CR 215 Clay 202 SR 16 SR 21 Blanding Boulevard Safety Projects ‐ Corridors $9.30 $0.61
CR 218 Clay 203 N Mimosa Avenue CR 739 Henley Road Safety Projects ‐ Corridors $9.90 $0.65
CR 220 Doctors Inlet Road Clay 608 SR 21 Blanding Boulevard CR 224 College Drive Safety Projects ‐ Corridors $8.25 $0.54
CR 220A Long Bay Road Clay 204 CR 220 Doctors Inlet Road Old Jennings Road Safety Projects ‐ Corridors $2.85 $0.19
CR 209 Russell Road Clay 201 Old Ferry Road CR 220 Doctors Inlet Road Safety Projects ‐ Corridors $2.85 $0.19
US 17 SR 15 Clay 327 CR 315 Kingsley Avenue Arterial Management System $1.37 $0.08
SR 134 103rd Street Duval 207 at New World Avenue Safety Projects ‐ Intersections $1.50 $0.05
SR 134 103rd Street Duval 218 at Firestone Road , I‐295 Interchanges Safety Projects ‐ Intersections $1.50 $0.05
SR 134 103rd Street Duval 222 at Harlow Boulevard Safety Projects ‐ Intersections $1.50 $0.05
SR 134 103rd Street Duval 225 at SR 21 Blanding Boulevard Safety Projects ‐ Intersections $1.50 $0.05
SR 134 103rd Street Duval 226 at Shindler Drive , Old Middleburg Road Safety Projects ‐ Intersections $1.50 $0.05
SR 134 103rd Street Duval 311 SR 228 Normandy Boulevard I‐295 Arterial Management System $0.77 $0.04
SR 134 103rd Street Duval 603 SR 228 Normandy Boulevard Wesconnett Boulevard Safety Projects ‐ Corridors $13.20 $0.87
SR 13 Acosta Bridge Duval 310 I‐95 Broad Street Freeway Management System $0.28 $0.01
SR 115 Arlington Expressway Duval 301 US 17 / US 17 SR 228 State Street SR 10 Atlantic Boulevard Freeway Management System $1.77 $0.06
SR 10 Atlantic Boulevard Duval 650 Monument Road Intracoastal Waterway Arterial Management System $1.04 $0.06
SR 10 Atlantic Boulevard Duval 651 Hart Bridge Expressway SR 109 University Boulevard Arterial Management System $0.23 $0.01
US 90 Beach Boulevard Duval 223 at Forest Boulevard Safety Projects ‐ Intersections $1.50 $0.05
US 90 Beach Boulevard Duval 652 Parental Home Road San Pablo Road Arterial Management System $1.16 $0.07
SR 21 Blanding Boulevard Duval 230 at Collins Road Safety Projects ‐ Intersections $1.50 $0.05
SR 21 Blanding Boulevard Duval 232 at I‐295 NB Off Ramp Safety Projects ‐ Intersections $1.50 $0.05
SR 21 Blanding Boulevard Duval 242 Argyle Forest Boulevard US 17 Roosevelt Boulevard Safety Projects ‐ Corridors $9.00 $0.59
SR 21 Blanding Boulevard Duval 317 Collins Road US 17 Roosevelt Boulevard Arterial Management System $1.07 $0.06
SR 109 Cesery Boulevard Duval 653 SR 109 University Boulevard SR 115 Arlington Expressway Arterial Management System $0.27 $0.02
Collins Road Duval 200 Shindler Drive Rampart Road Safety Projects ‐ Corridors $3.00 $0.20
SR 126 Emerson Street Duval 304 I‐95 Bedford Road Traffic Operations Improvements $2.42 $0.08
Firestone Road Duval 205 Morse Avenue SR 208 Wilson Boulevard Safety Projects ‐ Corridors $4.65 $0.31
SR 23 First Coast Expressway Duval 213 at US 90 , I‐10 Beaver Street Safety Projects ‐ Intersections $1.50 $0.05
SR 116 Fort Caroline Road Duval 654 Merrill Road McCormick Road Arterial Management System $0.15 $0.01
Harlow Boulevard Duval 206 SR 134 103rd Street SR 21 Blanding Boulevard Safety Projects ‐ Corridors $2.70 $0.18
Alt US 1 Hart Bridge Expressway Duval 300 Monroe Street US 90 Beach Boulevard Freeway Management System $0.91 $0.03
I‐295 Duval 607 Old St Augustine Road SR 228 Normandy Boulevard Safety Projects ‐ Corridors $33.00 $2.16
Safety and Operations Improvements
Page 11 of 13
Path Forward 2040 Long Range Transportation Plan
Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars)Facility County Map ID From To Improvement Type 2013 Cost
(millions)O&M Cost (millions)
I‐295 Duval 610 SR 228 Normandy Boulevard SR 115 Lem Turner Road Safety Projects ‐ Corridors $18.30 $1.20
SR 202 J. T. Butler Boulevard Duval 315 US 1/SR 5 Philips Highway SR A1A Freeway Management System $65.06 $2.16
SR 202 J. T. Butler Boulevard Duval 712 SR 115 Southside Boulevard Hodges Boulevard Safety Projects ‐ Corridors $7.65 $0.50
Jammes Road Duval 233 Morse Avenue San Juan Avenue Safety Projects ‐ Corridors $5.85 $0.38
SR 115 Lem Turner Road Duval 305 I‐95 I‐295 Arterial Management System $1.20 $0.07
US 17 Main Street Duval 326 Bay Street I‐295 Arterial Management System $1.29 $0.07
US 1 Main Street Bridge Duval 324 I‐95 Bay Street Arterial Management System $0.28 $0.01
SR 106 Merrill Road Duval 663 SR 109 University Boulevard SR 113 Southside Connector Arterial Management System $0.37 $0.02
US 1 MLK Parkway Duval 325 SR 115 Arlington Expressway I‐95 Freeway Management System $18.69 $0.62
Monument Road Duval 306 SR 10 Atlantic Boulevard Fort Caroline Road Arterial Management System $0.82 $0.05
Morse Avenue Duval 234 Ricker Road Jammes Road Safety Projects ‐ Corridors $2.25 $0.15
Mt. Pleasant Road Duval 657 McCormick Road Girvin Road Arterial Management System $0.14 $0.01
US 1/SR 15 New Kings Road Duval 224 at Moncrief Road Safety Projects ‐ Intersections $1.50 $0.05
US 1/SR 15 New Kings Road Duval 307 I‐95 I‐295 Arterial Management System $2.07 $0.12
SR 228 Normandy Boulevard Duval 208 at Fouraker Road Safety Projects ‐ Intersections $1.50 $0.05
SR 228 Normandy Boulevard Duval 220 at Blair Road South Safety Projects ‐ Intersections $1.50 $0.05
SR 228 Normandy Boulevard Duval 318 SR 134 103rd Street I‐295 Arterial Management System $0.79 $0.04
SR 228 Normandy Boulevard Duval 609 I‐295 SR 111 Cassat Avenue Safety Projects ‐ Corridors $3.90 $0.26
SR 228 Normandy Boulevard Duval 611 SR 23 First Coast Expressway I‐295 Safety Projects ‐ Corridors $12.90 $0.85
Old Middleburg Road Duval 235 Argyle Forest Boulevard SR 134 103rd Street Safety Projects ‐ Corridors $7.20 $0.47
Old Middleburg Road Duval 236 SR 134 103rd Street Lenox Avenue Safety Projects ‐ Corridors $6.15 $0.40
Old St. Augustine Road Duval 658 I‐95 US 1/ SR 5 Philips Highway Arterial Management System $0.03 $0.00
US 1/SR 5 Philips Highway Duval 229 at Bowden Road Safety Projects ‐ Intersections $1.50 $0.05
Rampart Road Duval 237 Argyle Forest Boulevard Park City Drive Safety Projects ‐ Corridors $1.50 $0.10
Ricker Road Duval 238 Morse Avenue SR 134 103rd Street Safety Projects ‐ Corridors $1.50 $0.10
Ricker Road Duval 239 SR 134 103rd Street Old Middleburg Road Safety Projects ‐ Corridors $2.10 $0.14
Shindler Drive Duval 240 Collins Road SR 134 103rd Street Safety Projects ‐ Corridors $4.50 $0.30
US 17 / US 17 SR 228 State Street Duval 322 I‐95 Liberty Street Arterial Management System $0.16 $0.01
SR 134 Timuquana Road Duval 602 Wesconnett Boulevard US 17 Roosevelt Boulevard Safety Projects ‐ Corridors $3.90 $0.26
US 17 / US 17 SR 228 Union Street Duval 323 I‐95 Liberty Street Arterial Management System $0.16 $0.01
SR 109 University Boulevard Duval 659 St. Augustine Road US 90 Beach Boulevard Arterial Management System $0.28 $0.01
SR 109 University Boulevard Duval 660 Arlington Road Merrill Road Arterial Management System $0.17 $0.01
SR 109 University Boulevard Duval 661 SR 10 Atlantic Boulevard SR 109 Cesery Boulevard Arterial Management System $0.04 $0.00
US 301 SR 200 Duval 313 SR 228 Normandy Boulevard US 90 Beaver Street Rural ITS $0.36 $0.01
Wesconnett Boulevard Duval 600 SR 21 Blanding Boulevard SR 21 Blanding Boulevard Safety Projects ‐ Corridors $2.85 $0.19
SR 208 Wilson Boulevard Duval 601 Fouraker Road SR 103 Lane Avenue Safety Projects ‐ Corridors $2.25 $0.15
SR 116 Wonderwood Connector Duval 655 Fort Caroline Road East Mt. Pleasant Road Arterial Management System $0.32 $0.02
SR 116 Wonderwood Connector Duval 656 SR 113 Southside Connector Fort Caroline Road East Arterial Management System $0.07 $0.00
SR 116 Wonderwood Connector Duval 662 Mt. Pleasant Road SR 101 Mayport Road Arterial Management System $0.40 $0.02
US 301 SR 200 Duval / Nassau314 US 90 Beaver Street Mickler Street (Callahan) Rural ITS $0.97 $0.04
SR 9B Duval / St. Joh319 CR 2209 I‐295 Freeway Management System $1.13 $0.03
SR 200 SR A1A Nassau 320 I‐95 Fernandina Beach Arterial Management System $0.82 $0.04
SR 200 SR A1A Nassau 604 I‐95 Chester Road Safety Projects ‐ Corridors $19.80 $1.30
US 1/SR 5 Dixie Highway St. John's 210 at SR 312 Safety Projects ‐ Intersections $1.50 $0.05
US 1/SR 5 Dixie Highway St. John's 214 at SR 206 Safety Projects ‐ Intersections $1.50 $0.05
US 1/SR 5 Dixie Highway/Ponce De Leon Boulevard St. John's 328 SR 312 SR 16 Arterial Management System $0.34 $0.02
International Golf Parkway St. John's 216 at SR 16 Safety Projects ‐ Intersections $1.50 $0.05
International Golf Parkway St. John's 217 at US 1/SR 5 Dixie Highway Safety Projects ‐ Intersections $1.50 $0.05
CR 214 King Street/Anastasia Boulevard St. John's 303 I‐95 SR A1A Arterial Management System $0.69 $0.04
CR 210 Palm Valley Road St. John's 302 SR 13 SR A1A Rural ITS $1.65 $0.08
US 1/SR 5 Ponce De Leon Boulevard St. John's 329 SR 5A King Street SR 16 Access Management Plan $0.19 $0.01
Race Track Road St. John's 308 SR 13 San Jose Boulevard US 1 Arterial Management System $0.83 $0.04
Page 12 of 13
Path Forward 2040 Long Range Transportation Plan
Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars)Facility County Map ID From To Improvement Type 2013 Cost
(millions)O&M Cost (millions)
SR 13 St. John's 309 Shands Bridge Julington Creek Road Arterial Management System $0.87 $0.04
SR 16 St. John's 312 CR 13 US 1 Arterial Management System $1.26 $0.07
SR 16/SR 13 St. John's 211 at CR 13 Safety Projects ‐ Intersections $1.50 $0.05
SR 207/SR 312 St. John's 316 I‐95 SR A1A Rural ITS $0.92 $0.05
SR A1A St. John's 321 SR 206 CR 214 Rural ITS $1.20 $0.06
US 1, A1A & SR 5A St. John's 330 Transportation Management Plan $37.50 $1.23
Page 13 of 13
1
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Road Capacity Projects
Abaco Island Drive Extension Nassau 988 Abaco Island Drive Zion Court New 2 Lane Road Local government coordination
The project's purpose is to construct a new two‐lane road called Abaco Island Drive Extension from Abaco Island Drive to Zion Court to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Alta Drive Duval 3 SR 105 Heckscher Drive I‐295 Widen to 4 Lanes 2035 Needs Plan
The project's purpose is to widen Alta Drive to four lanes from SR 105 Heckscher Drive to I‐295 to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Alta Drive / Yellow Bluff Road Duval 2 I‐295 New Berlin Road (north ) Widen to 5 Lanes 2035 Needs Plan
The project's purpose is to widen to Alta Drive / Yellow Bluff Road to five lanes from I‐295 to New Berlin Road (north) to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Alta Drive Realignment Duval 1 SR 105 Zoo Parkway North of New Berlin Road (south) New 4 Lane Road 2035 Needs Plan
The project's purpose is to construct a new four‐lane road and realign Alta Drive from SR 105 Zoo Parkway to North of New Berlin Road (south) to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Amelia Island Parkway Nassau 704 South 14th Street CR 105A Buccaneer Trail Widen to 4 Lanes* Local government coordination
The project's purpose is to widen Amelia Island Parkway to four lanes from South 14th Street to CR 105A Buccaneer Trail to address congestion needs and improve mobility. This project was also identified as candidate for context sensitive solutions.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
2
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Argyle Forest Boulevard Duval 936 SR 23 First Coast Expressway Old Middleburg Road Widen to 6 Lanes Argyle Traffic
Circulation Study
The project's purpose is to widen Argyle Forest Boulevard to six lanes from SR 23 First Coast Expressway to Old Middleburg Road to address congestion needs and improve mobility.
The project need was established during a corridor planning study performed by the North Florida TPO to address congestion, mobility and safety needs.
Arrigo‐Parliament Reconnection Nassau 980 Arrigo Boulevard Parliament Drive New 2 Lane Road Local government
coordination
The project's purpose is to construct a new two lane road called Arrigo‐Parliament Reconnection from Arrigo Boulevard to Parliament Drive to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Barnwell‐0' Neil Scott Connector Nassau 1001 Barnwell Road O'Neil Scott Road New 2 Lane Road Local government
coordination
The project's purpose is to construct a new two‐lane road called Barnwell‐0' Neil Scott Connector from Barnwell Road to O'Neil Scott Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Baxley Road Clay 900 CR 220 Doctors Inlet Road SR 21 Blanding Boulevard Widen to 4 Lanes Other Local Government Priority
The project's purpose is to widen Baxley Road to four lanes CR 220 Doctors Inlet Road to SR 21 Blanding Boulevard to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Blount Island Boulevard Extension Duval 1006 Spoil Island Jacksonville Port Authority New 2 Lane Bridge
Other Local Government Priority
The project's purpose is to New two Lane Bridge along Blount Island Boulevard Extension from Spoil Island to Jacksonville Port Authority to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
3
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Braddock Parkway Duval 939 SR 115 Lem Turner Road Pecan Park Road New 2 Lane Road Local government coordination
The project's purpose is to construct a new tow lane road called Braddock Parkway from SR 115 Lem Turner Road to Pecan Park Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Brady Point‐Clements Connector Nassau 1002 Brady Point Road Clements Road New 2 Lane Road Local government
coordination
The project's purpose is to construct a new two‐lane road called Brady Point‐Clements Connector from Brady Point Road to Clements Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Brinkhoff Road St Johns 801 SR 207 Wildwood Drive New 2 Lane Road Other Local Government Priority
The project's purpose is to construct a new two‐lane road called Brinkhoff Road from SR 207 to Wildwood Drive to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Buffalo Road Putnam 503 Buffalo Road west Buffalo east New 2 Lane Bridge Other Local Government Priority
The project's purpose is to construct new two‐lane bridge along Buffalo Road from Buffalo Road West to Buffalo East to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Cahoon Road Duval 1016 Lenox Avenue US 90 Beaver Street Reconstruct 2 Lanes Local Government CIP
The project's purpose is to reconstruct two lanes of Cahoon Road from Lenox Avenue to US 90 Beaver Street to address congestion needs and improve mobility and provide bicycle and pedestrian accommodations.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
4
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Cardinal Street North Extension Nassau 976 Cardinal Avenue SR 200 SR AIA Yulee Backage
Roads New 2 Lane Road Local government coordination
The project's purpose is to construct a new two‐lane road called Cardinal Street North Extension from Cardinal Avenue to SR 200 SR AIA Yulee Backage Roads to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Cardinal Street South Extension Nassau 975 Spring Meadow Avenue William Burgess Boulevard New 2 Lane Road Local government
coordination
The project's purpose is to construct a new two‐lane road called Cardinal Street South Extension from Spring Meadow Avenue to William Burgess Boulevard to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Cecil Field Connector Duval 972 Commerce Center SR 23 First Coast Expressway New 2 Lane Road Local Government CIP
The project's purpose is to construct a new two‐lane road called Cecil Field Connector from Commerce Center to SR 23 First Coast Expressway to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
Chaffee Road Duval 971 SR 228 Normandy Boulevard Crystal Springs Road Widen to 5 Lanes Local
Government CIP
The project's purpose is to widen Chaffee Road to five lanes from SR 228 Normandy Boulevard to Crystal Springs Road to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
Cheswick Oak Avenue Extension Clay 13 Oakleaf Plantation
Parkway Savannah Glen Boulevard New 4 Lane Road 2035 Cost Feasible Plan
The project's purpose is to construct a new four‐lane road called Cheswick Oak Avenue Extension from Oakleaf Plantation Parkway to Savannah Glen Boulevard to address congestion needs and improve mobility.
The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process.
5
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Christian Way Extension Nassau 995 Christian Way Hampton Club Way New 2 Lane Road Local government coordination
The project's purpose is to construct a new two‐lane road called Christian Way Extension from Christian Way to Hampton Club Way to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Clark Road Extension Duval 1020 Broward Road Clark Road New 3 Lane Road Local Government CIP
The project's purposes to construct a new three‐lane road called Clark Road Extension from Broward Road to Clark Road to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
College Drive Clay 902 CR 220 Doctors Inlet Road SR 21 Blanding Boulevard Widen to 6 Lanes 2035 Needs Plan
The project's purpose is to widen College Drive to six lanes from CR 220 Doctors Inlet Road to SR 21 Blanding Boulevard to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
College Drive Extension Clay 14 SR 21 Blanding Boulevard Challenger Drive (Branan Field Road ) New 4 Lane Road 2035 Cost
Feasible Plan
The project's purpose is to construct a new four‐lane road called College Drive Extension from SR 21 Blanding Boulevard to Challenger Drive (Branan Field Road) to address congestion needs and improve mobility.
The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process.
Collins Road Duval 930 Shindler Drive Rampart Road Widen to 4 Lanes Local Government CIP
The project's purpose is to widen Collins Road to four lanes from Shindler Drive to Rampart Road to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
6
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Collins Road Duval 932 Old Middleburg Road S Shindler Drive Widen to 4 Lanes Local Government CIP
The project's purpose is to widen Collins Road to four lanes from Old Middleburg Road S to Shindler Drive to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
Collins Road Duval 15 SR 21 Blanding Boulevard Pine Verde Widen to 4 Lanes 2035 Needs Plan
The project's purpose is to widen Collins Road to four lanes from SR 21 Blanding Boulevard to Pine Verde to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Collins Road Duval 16 at US 17 Roosevelt Boulevard New Interchange 2035 Needs Plan
The project's purpose is to construct a new interchange along Collins Road at US 17 Roosevelt Boulevard to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Collins Road Realignment Duval 16B Pine Verde US 17 Roosevelt Boulevard New 4 Lane Road, Two Overpass and New Interchange
Local government coordination and the project was part of the Better Jacksonville Plan
The project's purpose is to construct a new four‐lane road, two overpasses and a new interchange along the Collins Road Realignment from Pine Verde to US 17 Roosevelt Boulevard to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Comfort Road Putnam 505 Port Road US 17 Widen to 4 Lanes Other Local Government Priority
The project's purpose is to widen Comfort Road to four lanes from Port Road to US 17 to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
7
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Commodore Point Drive Extension Nassau 996 Commodore Point Drive Blackrock Road New 2 Lane Road Local government
coordination
The project's purpose is to construct a new two‐lane road called Commodore Point Drive Extension from Commodore Point Drive to Blackrock Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Concourse Loop Road Nassau 501 License Road Amelia Concourse New 2 Lane Road Other Local Government Priority
The project's purpose is to construct a new two‐lane road called Concourse Loop Road from License Road to Amelia Concourse to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Connector Road Putnam 502 US 17 Distribution Center New 2 Lane Road SIS CFP
The project's purpose is to construct a new two‐lane road called Connector Road from US 17 to Distribution Center to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
CR 105A Buccaneer Trail Nassau 705 South Fletcher Avenue Canopy Drive Turn Lane Improvements* Local government coordination
The project's purpose is to construct turn lane improvements along CR 105A Buccaneer Trail from South Fletcher Avenue to Canopy Drive to address congestion needs and improve mobility. This project was also identified as a candidate for context sensitive solutions.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
CR 16A St Johns 803 SR 16 Connector SR 13 Widen to 4 Lanes Other Local Government Priority
The project's purpose is to widen CR 16A to four lanes from SR 16 Connector to SR 13 to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
8
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
CR 16A Extension St Johns 802 CR 16A Leo Maguire Parkway New 2 Lane Road Local government coordination
The project's purpose is to construct a new two‐lane road called CR 16A Extension from CR 16A to Leo Maguire Parkway to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
CR 209 Russell Road Clay 905 CR 739 Henley Road US 17 Widen to 4 Lanes 2035 Needs Plan
The project's purpose is to CR 209 Russell Road to four lanes from CR 739 Henley Road to US 17 to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
CR 209 South Clay 906 Decoy Road US 17 Reconstruct 2 Lanes Other Local Government Priority
The project's purpose is to reconstruct two lanes along CR 209 South from Decoy Road to US 17 to address congestion needs and improve mobility and provide bicycle and pedestrian accommodations.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
CR 210 St Johns 805 I‐95 near US 1 Widen to 6 Lanes Other Local Government Priority
The project's purpose is to widen CR 210 to six lanes from I‐95 to near US 1 to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
CR 210 St Johns 807 Greenbriar Road Cimarrone Road Widen to 4 Lanes 2035 Needs Plan
The project's purpose is to widen CR 210 to four lanes from Greenbriar Road to Cimarrone Road to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
9
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
CR 210 West St Johns 849 Longleaf Pine Parkway Greenbriar Road Widen to 4 Lanes Other Local Government Priority
The project's purpose is to widen CR 210 West to four lanes from Longleaf Pine Parkway to Greenbriar Road to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
CR 214 St Johns 809 Holmes Boulevard US 1 Widen to 3 Lanes* Other Local Government Priority
The project's purpose is to widen CR 214 to three lanes from Holmes Boulevard to US 1 to address congestion needs and improve mobility. This project was also identified as a candidate for context sensitive solutions in lieu of widening.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
CR 218 Clay 1026 US 301 Cosmos Avenue Widen to 4 Lanes Local Government CIP
The project's purpose is to widen CR 218 to four lanes from US 301 to Cosmos Avenue to address congestion needs and improve mobility.
The project need was established in the Local Government CIP and confirmed as part of the planning process.
CR 218 Clay 1027 Cosmos Avenue Pine Tree Lane Widen to 4 Lanes 2035 Needs Plan
The project's purpose is to widen to CR 218 to four lanes from Cosmos Avenue to Pine Tree Lane to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
CR 218 Clay 24 SR 21 Blanding Boulevard CR 739 Henley Road Widen to 4 Lanes Local Government CIP
The project's purpose is to widen CR 218 to dour lanes from SR 21 Blanding Boulevard to CR 739 Henley Road to address congestion needs and improve mobility.
The project need was established in the Local Government CIP and confirmed as part of the planning process.
10
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
CR 218 Clay 909 SR 16 CR 739 Henley Road Widen to 4 Lanes 2035 Needs Plan
The project's purpose is to widen CR 218 to four lanes from SR 16 to CR 739 Henley Road to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
CR 218 Extension Clay 25 CR 739 Henley Road SR 23 First Coast Expressway New 4 Lane Road 2035 Needs Plan
The project's purpose is to construct a new four‐lane road called CR 218 Extension from CR 739 Henley Road to SR 23 First Coast Expressway to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
CR 218 Extension Clay 26 SR 23 First Coast Expressway CR 315 New 4 Lane Road 2035 Needs Plan
The project's purpose is to construct a new four‐lane road called CR 218 Extension from SR 23 First Coast Expressway to CR 315 to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
CR 220 Doctors Inlet Road Clay 33 SR 21 Blanding Boulevard Knight Boxx Road Widen to 4 Lanes 2035 Needs Plan
The project's purpose is to widen CR 220 Doctors Inlet Road to four lanes from SR 21 Blanding Boulevard to Knight Boxx Road to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
CR 220 Doctors Inlet Road Clay 34 College Drive US 17 Widen to 6 Lanes 2035 Needs Plan
The project's purpose is CR 220 Doctors Inlet Road from College Drive to US 17 to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
11
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
CR 2209 St Johns 810 SR 23 First Coast Expressway CR 210 New 6 Lane Road 2035 Cost
Feasible Plan
The project's purpose is to construct a new six‐lane road called CR 2209 from SR 23 First Coast Expressway to CR 210 to address congestion needs and improve mobility.
The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process.
CR 2209 St Johns 811 SR 16 Connector SR 23 First Coast Expressway New 6 Lane Road 2035 Cost Feasible Plan
The project's purpose is to construct a new six‐lane road called CR 2209 from SR 16 Connector to SR 23 First Coast Expressway to address congestion needs and improve mobility.
The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process.
CR 2209 St Johns 812 International Golf Parkway SR 16 Connector New 6 Lane Road 2035 Cost
Feasible Plan
The project's purpose is to construct a new six‐lane road called CR 2209 from International Golf Parkway to SR 16 Connector to address congestion needs and improve mobility.
The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process.
CR 2209 St Johns 813 CR 214 CR 208 New 4 Lane Road 2035 Needs Plan
The project's purpose is to construct a new four‐lane road called CR 2209 from CR 214 to CR 208 to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
CR 2209 St Johns 814 SR 207/CR 305 CR 214 New 4 Lane Road 2035 Needs Plan
The project's purpose is to construct a new four‐lane road called CR 2209 from SR 207/CR 305 to CR 214 to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
12
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
CR 2209 St Johns 815 SR 16 International Golf Parkway New 4 Lane Road 2035 Needs Plan
The project's purpose is to construct a new four‐lane road called CR 2209 from SR 16 to International Golf Parkway to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
CR 2209 St Johns 816 CR 208 SR 16 New 4 Lane Road 2035 Needs Plan
The project's purpose is to construct a new four‐lane road called CR 2209 from CR 208 to SR 16 to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
CR 2209 St Johns 843 at CR 210 New Interchange 2035 Needs Plan
The project's purpose is to construct a new interchange along CR 2209 at CR 210 to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
CR 305 St Johns 818 CR 204 SR 206 New 2 Lane Road 2035 Needs Plan
The project's purpose is to construct a new two‐lane road called CR 305 from CR 20four to SR 206 to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
CR 305 St Johns 850 SR 206 SR 207 Widen to 4 Lanes Other Local Government Priority
The project's purpose is to widen CR 305 to four lanes from SR 206 to SR 207 to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
13
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
CR 315 Clay 31 SR 16 CR 315B Widen to 4 Lanes 2035 Needs Plan
The project's purpose is to widen CR 315 to four lanes from SR 16 to CR 315B to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
CR 315 Clay 32 CR 315B US 17 Widen to 4 Lanes 2035 Needs Plan
The project's purpose is to widen CR 315 to four lanes from CR 315B to US 17 to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
CR 739B Sandridge Road Clay 904 CR 739 Henley Road CR 209 Russell Road Widen to 4 Lanes Other Local Government Priority
The project's purpose is to widen CR 739B Sandridge Road to four lanes from CR 739 Henley Road to CR 209 Russell Road to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Crosby Avenue Extension Nassau 993 US 17 SR 5 Pinewood Drive New 2 Lane Road Local government coordination
The project's purpose is to construct a new two‐lane road called Crosby Avenue Extension from US 17 SR 5 to Pinewood Drive to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Davis / 9B Parcel Duval 1036 SR 9B SR 152 Baymeadows Road Widen to 4 Lanes Local government coordination
The project's purpose is to widen Davis / 9B Parcel Road to four lanes from SR 9B to SR 152 Baymeadows Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
14
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Decoy Road Clay 907 US 17 CR 209 South Reconstruct 2 Lanes Other Local Government Priority
The project's purpose is to reconstruct two lanes of Decoy Road from US 17 to CR 209 South to address congestion needs and improve mobility and provide bicycle and pedestrian accommodations.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Dixie Highway / Pellicer Lane St Johns 1025 SR 207 CR 214 West of King Street Reconstruct 2 Lanes and Widen to add Sidewalks and Bike Lanes
2035 Needs Plan
The project's purpose is to reconstruct two lanes and widen Dixie Highway / Pellicer Lane to add sidewalks and bike lanes from SR 207 to CR 214 West of King Street to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Dove Road Extension {west} Nassau 991 Harper Chapel Road Extension Mentoria Road New 2 Lane Road Local government
coordination
The project's purpose is to construct a new two‐lane road called Dove Road Extension {west} from Harper Chapel Road Extension to Mentoria Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Durbin Parkway St Johns 819 SR 9B Extension Nocatee Parkway New 4 Lane Road Other Local Government Priority
The project's purpose is to construct a new four‐lane road called Durbin Parkway from the SR 9B Extension to Nocatee Parkway to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Durbin Parkway St Johns 844 at US 1 SR 5 Dixie Highway Modify Interchange
Other Local Government Priority
The project's purpose is to modify the interchange of Durbin Parkway at US 1 SR 5 Dixie Highway to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
15
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Duval Station Road Duval 942 US 17 SR 5 Main Street Starratt Road Widen to 4 Lanes Local government coordination
The project's purpose is to widen Duval Station Road to four lanes from US 17 SR 5 Main Street to Starratt Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
East Dove Road Extension Nassau 974 Harper Chapel Road William Burgess Boulevard New 2 Lane Road Local government coordination
The project's purpose is to construct a new two‐lane road called east Dove Road Extension from Harper Chapel Road to William Burgess Boulevard to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
East Nassau Connector Nassau 36 I‐95 Chester Road New 4 Lane Road Local Government CIP
The project's purpose is to construct a new four‐lane road called East Nassau Connector from I‐95 to Chester Road to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
East Nassau Connector Nassau 969 at I‐95 New Interchange Local government coordination
The project's purpose is to construct a new interchange along East Nassau Connector at I‐95 to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Eastport Road Duval 37 SR 105 Heckscher Drive Pulaski Road Widen to 3 Lanes Local Government CIP
The project's purpose is to widen Eastport Road to three lanes from SR 105 Heckscher Drive to Pulaski Road to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
16
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Flora Parke‐Wal‐Mart Connector Nassau 986 Flora Parke Boulevard Walmart Supercenter New 2 Lane Road Local government
coordination
The project's purpose is to construct a new two‐lane road called Flora Parke‐Wal‐Mart Connector from Flora Parke Boulevard to Walmart Supercenter to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Florida Boulevard Duval 1021 Penman Road SR 10 Atlantic Boulevard Widen to 3 Lanes Local Government CIP
The project's purpose is to widen Florida Boulevard to three lanes from Penman Road to SR 10 Atlantic Boulevard to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
Future Corridor Initiative Baker/Clay/Duval 721 Tampa Bay Northeast Florida Future Corridor SIS Unfunded Needs
The project's purpose is to construct a new limited‐access roadway from Tampa Bay to Northeast Florida to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
Gator Bowl Boulevard Duval 43 Liberty Street SR 228 Hart Bridge Expressway and SR 115 Mathews Bridge
Widen to 6 Lanes and Remove Ramps 2035 Needs Plan
The project's purpose is to widen Gator Bowl Boulevard to six lanes and remove ramps from Liberty Street to Hart SR 115 Mathews Bridge to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Gene Lassere Boulevard Extension Nassau 985 Gene Lassere Boulevard SR 200A Pages Dairy Road New 2 Lane Road and
Roundabout Local government coordination
The project's purpose is to construct a new two lane road and roundabout called Gene Lassere Boulevard Extension from Gene Lassere Boulevard to SR 200A Pages Dairy Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
17
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Goodbread Road Reconstruction Nassau 977 US 17 SR 5 Hamilton Street New 2 Lane Road Local government
coordination
The project's purpose is to construct a new two‐lane road called Goodbread Road Reconstruction from US 17 SR 5 to Hamilton Street to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Governors Park Road Clay 46 US 17 SR 16 New 4 Lane Road 2035 Needs Plan
The project's purpose is to construct a new four‐lane road called Governors Park Road from US 17 to SR 16 to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Hamilton Street Extension Nassau 1000 Goodbread Circle New 2 Lane Road Local government coordination
The project's purpose is to construct a new two‐lane road called Hamilton Street Extension from Goodbread Circle to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Harlow Boulevard Duval 943 SR 134 103rd Street Lane Avenue Widen to 3 Lanes Local government coordination
The project's purpose is to widen Harlow Boulevard to three lanes from SR 134 103rd Street to Lane Avenue to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Harper Chapel Extension Nassau 989 Harper Chapel Road Dove Road Extension New 2 Lane Road Local government coordination
The project's purpose is to construct a new two‐lane road called Harper Chapel Extension from Harper Chapel Road to Dove Road Extension to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
18
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Hart Expressway Ramps Duval 43B Liberty Street SR 228 Hart Expressway and SR 115 Mathews Bridge Remove Ramps Phases in TIP or
Work Program
The project's purpose is to remove Ramps along SR 228 Hart Expressway ramps from Liberty Street to the SR 228 Hart Bridge and SR 115 Mathews Bridge to address congestion needs and improve mobility.
The project need was established in the Phases in TIP or Work Program and confirmed as part of the planning process.
Hartley Road Duval 49 SR 13 San Jose Boulevard Old St. Augustine Road Widen to 3 Lanes Local Government CIP
The project's purpose is to widen Hartley Road to three lanes from SR 13 San Jose Boulevard to Old St. Augustine Road to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
Harts Road Duval 963 SR 104 Dunn Avenue I‐295 Widen to 4 Lanes Other Local Government Priority
The project's purpose is to widen Harts Road to four lanes from SR 104 Dunn Avenue to I‐295 to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Holmes Boulevard St Johns 821 CR 214 Four Mile Road Widen to 6 Lanes Other Local Government Priority
The project's purpose is to widen Holmes Boulevard to six lanes from CR 214 to Four Mile Road to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
I‐10 Duval 401 SR 23 First Coast Expressway I‐295 Add 4 Express Lanes SIS CFP
The project's purpose is to add four express lanes along I‐10 from SR 23 First Coast Expressway to I‐295 to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
19
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
I‐10 Nassau 402* Baker/Nassau County Line Nassau/Duval County Line Add 4 Express Lanes SIS CFP
The project's purpose is to add four express lanes along I‐10 from Baker/Nassau County Line to Nassau/Duval County Line to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
I‐10 Duval 403* Nassau/Duval County Line US 301 Add 4 Express Lanes SIS CFP
The project's purpose is to add four express lanes along I‐10 from Nassau/Duval County Line to US 301 to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
I‐10 Baker 404* W of CR 125 W of SR 121 Add 4 Express Lanes SIS CFP
The project's purpose is to add four express lanes along I‐10 from west of CR 125 to west of SR 121 to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
I‐10 Baker 405* W of SR 121 Baker/Nassau County Line Add 4 Express Lanes SIS CFP
The project's purpose is to add four express lanes along I‐10 from west of SR 121 to Baker/Nassau County Line to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
I‐10 Duval 406 US 301 SR 23 First Coast Expressway Add 4 Express Lanes Phases in TIP or Work Program
The project's purpose is to add four express lanes along I‐10 from US 301 to SR 23 First Coast Expressway to address congestion needs and improve mobility.
The project need was established in the Phases in TIP or Work Program and confirmed as part of the planning process.
20
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
I‐10 Duval 432 I‐295 I‐95 Add 4 Express Lanes SIS CFP
The project's purpose is to add four express lanes along I‐10 from I‐295 to I‐95 to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
I‐10 Baker 453 Baker/Columbia County Line CR 125 Add 4 Express Lanes SIS Unfunded
Needs
The project's purpose is to add four express lanes along I‐10 from Baker/Columbia County Line to CR 125 to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
I‐10 Duval 454 at I‐295 Modify Interchange SIS Unfunded Needs
The project's purpose is to modify the interchange of I‐10 at I‐295 to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
I‐10/US 90 Parallel Reliever Baker 720 South MacClenny East Baldwin Future Corridor 2035 Needs Plan
The project's purpose is to construct a new roadway called the I‐10 US 90 Parallel Reliever from South MacClenny to East Baldwin to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
I‐295 Duval/Clay 57 SR 13 San Jose Boulevard W of US 17 Roosevelt Boulevard Add 4 Express Lanes on Bridge SIS CFP
The project's purpose is to add four express lanes on the Buckman Bridge along I‐295 from SR 13 San Jose Boulevard to west of US 17 Roosevelt Boulevard to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
21
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
I‐295 Duval 119 SR 9B I‐295 Add 4 Express Lanes SIS Unfunded Needs
The project's purpose is to add four express lanes along I‐295 from SR 9B to I‐295 to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
I‐295 Duval 407 I‐95 North SR 105 Dames Point Bridge/Heckscher Drive Add 4 Express Lanes Phases in TIP or
Work Program
The project's purpose is to add four express lanes along I‐295 from I‐95 North to SR 105 Dames Point Bridge/Heckscher Drive to address congestion needs and improve mobility.
The project need was established in the Phases in TIP or Work Program and confirmed as part of the planning process.
I‐295 Duval 408 North of Trout River I‐95 Add 4 Express Lanes SIS CFP
The project's purpose is to add four express lanes along I‐295 from north of the Trout River to I‐95 to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
I‐295 Duval 409 US 1 New Kings Road North of Trout River Add 4 Express Lanes SIS CFP
The project's purpose is to add four express lanes along I‐295 from US 1 New Kings Road to north of Trout River to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
I‐295 Duval 410 SR 134 103rd Street I‐10 Add 4 Express Lanes SIS CFP
The project's purpose is to add four express lanes along I‐295 from SR 134 103rd Street to I‐10 to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
22
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
I‐295 Duval 411 I‐10 US 1 South of New Kings Road Add 4 Express Lanes SIS CFP
The project's purpose is to add four express lanes along I‐295 from I‐10 to US 1 South of New Kings Road to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
I‐295 Duval 431 US 17 Roosevelt Boulevard SR 134 103rd Street Add 4 Express Lanes SIS CFP
The project's purpose is to add four express lanes along I‐295 from US 17 Roosevelt Boulevard to SR 134 103rd Street to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
I‐295 Duval 964 at US 17 Roosevelt Boulevard Modify Interchange Phases in TIP or
Work Program
The project's purpose is to modify the interchange of I‐295 at US 17 Roosevelt Boulevard to address congestion needs and improve mobility.
The project need was established in the Phases in TIP or Work Program and confirmed as part of the planning process.
I‐295 Duval 1022 I‐95 South SR 13 San Jose Boulevard Add 2 Express Lanes SIS CFP
The project's purpose is to add two express lanes along I‐295 from I‐95 South to SR 13 San Jose Boulevard to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
I‐295 Duval 1023 SR 202 J. T. Butler Boulevard SR 9B Add 2 Express Lanes SIS CFP
The project's purpose is to add two express lanes along I‐295 from SR 202 J. T. Butler Boulevard to SR 9B to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
23
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
I‐295 Duval 121 SR 113 Southside Connector SR 202 J. T. Butler Boulevard Add 4 Express Lanes SIS CFP
The project's purpose is to add four express lanes along I‐295 from SR 113 Southside Connector to SR 202 J. T. Butler Boulevard to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
I‐95 Duval 68 at SR 102 Airport Road Modify Interchange 2035 Cost Feasible Plan
The project's purpose is to modify the interchange of I‐95 at SR 102 Airport Road to address congestion needs and improve mobility.
The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process.
I‐95 St Johns 138 at US 1/SR 5 Ponce De Leon Boulevard and at SR 206
Modify Interchange SIS Unfunded Needs
The project's purpose is to modify the interchange of I‐95 from US 1 SR 5 Ponce De Leon Boulevard to SR 206 to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
I‐95 St Johns 400 St. Johns/Flagler County Line SR 206 Add 4 Express Lanes SIS Unfunded
Needs
The project's purpose is to add four express lanes along I‐95 from St. Johns/Flagler County Line to SR 206 to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
I‐95 Duval 413 SR 104 Dunn Avenue SR 102 Airport Road Add 4 Express Lanes SIS Unfunded Needs
The project's purpose is to add four express lanes along I‐95 from SR 104 Dunn Avenue to SR 102 Airport Road to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
24
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
I‐95 Duval 414 North of Fuller Warren Bridge SR 104 Dunn Avenue Add 4 Express Lanes SIS Unfunded
Needs
The project's purpose is to add four express lanes along I‐95 from North of Fuller Warren Bridge to SR 104 Dunn Avenue to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
I‐95 Duval 418A Duval/St. Johns County Line I‐295 Add 4 Express Lanes SIS CFP
The project's purpose is to add four express lanes along I‐95 from Duval/St. Johns County Line to I‐295 to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
I‐95 St Johns 418B International Golf Parkway St. Johns/Duval County Line Add 4 Express Lanes SIS CFP
The project's purpose is to add four express lanes along I‐95 from International Golf Parkway to St. Johns/Duval County Line to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
I‐95 Duval 419 at US 1/SR 15 MLK Modify Interchange SIS CFP
The project's purpose is to modify the interchange of I‐95 at US 1/SR 15 MLK to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
I‐95 St Johns 420 SR 206 International Golf Parkway Add 4 Express Lanes SIS Unfunded Needs
The project's purpose is to add four express lanes along I‐95 from SR 206 to International Golf Parkway to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
25
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
I‐95 Duval 433 SR 202 J. T. Butler Boulevard SR 10 Atlantic Boulevard Add 4 Express Lanes SIS CFP
The project's purpose is to add four express lanes along I‐95 from SR 202 J. T. Butler Boulevard to SR 10 Atlantic Boulevard to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
I‐95 Duval 434 I‐295 SR 202 J. T. Butler Boulevard Add 4 Express Lanes SIS Unfunded Needs
The project's purpose is to add four express lanes along I‐95 from I‐295 to SR 202 J. T. Butler Boulevard to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
I‐95 St Johns 846 at CR 210 Modify Interchange 2035 Needs Plan The project's purpose is to modify the interchange of I‐95 at CR 210 to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
I‐95 Duval 962 at SR 115 Southside Boulevard Modify Interchange
SR 115 Southside Boulevard Corridor Study
The project's purpose is to modify the interchange of I‐95 at SR 115 Southside Boulevard to address congestion needs and improve mobility.
The project need was established in the SR 115 Southside Boulevard Corridor Study and confirmed as part of the planning process.
International Golf Parkway St Johns 823 I‐95 Turn/Bend Widen to 4 Lanes* 2035 Needs Plan
The project's purpose is to widen International Golf Parkway to four from I‐95 to Turn/Bend to address congestion needs and improve mobility. This corridor was also identified as a candidate for context sensitive solutions in lieu of widening.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
26
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Jones Road Duval 944 US 90 Beaver Street Pritchard Road Intersection Improvements Local government coordination
The project's purpose is to construct intersection improvements along Jones Road from US 90 Beaver Street to Pritchard Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Kernan Boulevard Duval 73 SR 202 J. T. Butler Boulevard Glen Kernan Parkway Widen to 6 Lanes Local
Government CIP
The project's purpose is wide Kernan Boulevard to six lanes from SR 202 J. T. Butler Boulevard to Glen Kernan Parkway to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
Kernan Boulevard Duval 933 SR 10 Atlantic Boulevard SR 116 McCormick Road Widen to 6 Lanes Local Government CIP
The project's purpose is to widen Kernan Boulevard to six lanes from SR 10 Atlantic Boulevard to SR 116 McCormick Road to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
Knight Boxx Road Clay 901 CR 220 Doctors Inlet Road SR 21 Blanding Boulevard Widen to 6 Lanes Other Local Government Priority
The project's purpose is to widen Knight Boxx Road to six lanes from CR 220 Doctors Inlet Road to SR 21 Blanding Boulevard to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Lake Asbury East West 1 Clay 915 NS3 CR 209 Russell Road New 2 Lane Road Local government coordination
The project's purpose is to construct a new two‐lane road called Lake Asbury East West 1 from NS3 to CR 209 Russell Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
27
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Lake Asbury North South Road 3 Clay 914 CR 739B Sandridge Road CR 209 Russell Road New 2 Lane Road Local government
coordination
The project's purpose is to construct a new two‐lane road called Lake Asbury North South Road 3 from CR 739B Sandridge Road to CR 209 Russell Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Lofton Creek Crossing Nassau 710 Hendricks Road Avant Road New 2 Lane Bridge Other Local Government Priority
The project's purpose is to construct a new two‐lane bridge called the Lofton Creek Crossing from Hendricks Road to Avant Road to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Long Bay Road Extension North Clay 911 Old Jennings Road Long Bay Road New 2 Lane Road
Other Local Government Priority
The project's purpose is to construct a new two‐lane road called Long Bay Road Extension North from Old Jennings Road to Long Bay Road to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Macaw Avenue Extension Nassau 982 Cardinal Street US 17 SR 5 New 2 Lane Road Local government coordination
The project's purpose is to construct a new two‐lane road called Macaw Avenue Extension from Cardinal Street to US 17 SR 5 to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
McDuff Avenue / 5th Street Duval 1019 Melson Avenue Huron Street Widen to 3 Lanes Local Government CIP
The project's purpose is to widen 5th Street to three lanes from Melson Avenue to Huron Street to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
28
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Mentoria‐William Burgess Connector Nassau 990 William Burgess
Boulevard Harper Chapel Road New 2 Lane Road Local government coordination
The project's purpose is to construct a new two‐lane road called Mentoria‐William Burgess Connector from William Burgess Boulevard to Harper Chapel Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Merrill Road Duval 945 Hartsfield Road SR 113 Southside Connector Widen to 6 Lanes Local government coordination
The project's purpose is to widen Merrill Road to six lanes from Hartsfield Road to SR 113 Southside Connector to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Mickler Road St Johns 825 Palm Valley Road SR A1A Widen to 4 Lanes 2035 Needs Plan
The project's purpose is to widen Mickler Road to four lanes from Palm Valley Road to SR A1A to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Monument Road Duval 946 Tredinick Parkway I‐295 Widen to 6 Lanes Local government coordination
The project's purpose is to widen Monument Road to six lanes from Tredinick Parkway to I‐295 to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Monument Road Duval 947 I‐295 Lee Road Widen to 6 Lanes Local government coordination
The project's purpose is to widen Monument Road to six lanes from I‐295 to Lee Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
29
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
National Cemetery Road Duval 1033 Lannie Road Arnold Road New 2 Lane Road 2035 Cost Feasible Plan
The project's purpose is to construct a new two‐lane road called National Cemetery Road from Lannie Road to Arnold Road to address congestion needs and improve mobility.
The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process.
New Berlin Road Duval 948 Pulaski Road Yellow Bluff Road Widen to 4 Lanes Local government coordination
The project's purpose is to widen New Berlin Road to four lanes from Pulaski Road to Yellow Bluff Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
New Berlin Road Duval 949 Yellow Bluff Road Cedar Point Road Widen to 4 Lanes Local government coordination
The project's purpose is to widen New Berlin Road to four lanes from Yellow Bluff Road to Cedar Point Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
New World Avenue Duval 1034 SR 23 First Coast Expressway Chaffee Road New 2 Lane Road Local
Government CIP
The project's purpose is to construct a new two‐lane road called New World Avenue from SR 23 First Coast Expressway to Chaffee Road to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
New World Avenue Duval 1035 SR 23 First Coast Expressway Chaffee Road Widen to 4 Lanes Local government
coordination
The project's purpose is to widen New World Avenue from SR 23 First Coast Expressway to Chaffee Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
30
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Norfolk Southern Railroad Overpass Duval 85 West 12th Street US 23 New Kings Road New 3 Lane Road / Bridge 2035 Needs Plan
The project's purpose is to construct a new three lane road and bridge called the Norfolk Southern Railroad Overpass from West 12th Street to US 23 New Kings Road to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Northern Cross Town Corridor Baker 500 CR 125 SR 121 New 2 Lane Road Other Local Government Priority
The project's purpose is to construct a new two‐lane road called Northern Cross Town Corridor from CR 125 to SR 121 to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Northern Outer Beltway Duval/Nassau 88 I‐10 I‐95 Future Corridor 2035 Needs Plan
The project's purpose is to construct a new limited‐access facility called the Northern Outer Beltway from I‐10 to I‐95 to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Oakleaf Village Parkway Extension Clay 913 Oakleaf Plantation
Parkway Oakleaf Village Parkway New 2 Lane Road Other Local Government Priority
The project's purpose is to construct a new two‐lane road called Oakleaf Village Parkway Extension from Oakleaf Plantation Parkway to Oakleaf Village Parkway to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Old Kings Road Duval 951 SR 111 Edgewood Avenue Plummer Road Intersection Improvements Local government coordination
The project's purpose is to construct intersection improvements along Old Kings Road from SR 111 Edgewood Avenue to Plummer Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
31
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Old Middleburg Road Duval 1015 Argyle Forest Boulevard SR 134 103rd Street Widen to 4 Lanes Local Government CIP
The project's purpose is to widen Old Middleburg Road from Argyle Forest Boulevard to SR 134 103rd Street to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
Old St. Augustine Road Duval 90 Bartram Park Boulevard US 1/SR 5 Phillips Highway Widen to 6 Lanes and Overpass 2035 Needs Plan
The project's purpose is to widen Old St. Augustine Road to six lanes and construct an overpass of US 1 SR 5 Philips Highway from Bartram Park Boulevard to US 1 SR 5 Phillips Highway to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Old St. Augustine Road Duval 1010 at Greenland Road Intersection Improvements / Add 1 Lane
Local Government CIP
The project's purpose is to construct intersection improvements and add one lane along Old St. Augustine Road at Greenland Road to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
Outer Loop Facility Baker/Duval 91 SR 228 Normandy Boulevard SR 228 Normandy Boulevard Future Corridor 2035 Needs Plan
The project's purpose is to construct a new roadway called the Outer Loop Facility from SR 228 Normandy Boulevard to SR 228 Normandy Boulevard to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Pages Dairy Road East Extension Nassau 987 Chester Road Blackrock Road New 2 Lane Road Local government
coordination
The project's purpose is to construct a new two‐lane road called Pages Dairy Road East Extension from Chester Road to Blackrock Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
32
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Pages Dairy Road South Extension Nassau 983 SR 200 SR A1A Sowell Road New 2 Lane Road Local government
coordination
The project's purpose is to construct a new two‐lane road called Pages Dairy Road South Extension from SR 200 SR A1A to Sowell Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Palm Valley Road St Johns 826 Intracoastal Waterway Mickler Road Widen to 4 Lanes Other Local Government Priority
The project's purpose is to widen Palm Valley Road from Intracoastal Waterway to Mickler Road to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Pecan Park Road Duval 952 Braddock Boulevard JIA North Access Road Widen to 4 Lanes Local government coordination
The project's purpose is to widen Pecan Park Road from Braddock Boulevard to JIA North Access Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Pecan Park Road Duval 92 I‐95 US 17 Main Street Widen to 4 Lanes 2035 Needs Plan
The project's purpose is to widen Pecan Park Road from I‐95 to US 17 Main Street to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Pulaski Road Duval 953*** Eastport Road I‐295 Widen to 4 Lanes Local government coordination
The project's purpose is to widen Pulaski Road from Eastport Road to I‐295 to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
33
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Pulaski Road / Starratt Road Duval 97 I‐295 Duval Station Road Widen to 4 Lanes 2035 Needs Plan
The project's purpose is to widen Pulaski Road / Starratt Road from I‐295 to Duval Station Road to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Race Track Road St Johns 827 St. Johns Parkway Bartram Park Boulevard Widen to 4 Lanes 2035 Needs Plan
The project's purpose is to widen Race Track Road from St. Johns Parkway to Bartram Park Boulevard to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Race Track Road St Johns 828 Bartram Park Boulevard Bartram Springs Widen to 4 Lanes Other Local Government Priority
The project's purpose is to widen Race Track Road from Bartram Park Boulevard to Bartram Springs to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Race Track Road Connector St Johns 851 Durbin Parkway / 9B Extension Race Track Road New 2 Lane Road
Other Local Government Priority
The project's purpose is to construct a new two‐lane road called Race Track Road Connector from Durbin Parkway and 9B Extension to Race Track Road to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Ramona Boulevard Duval 935 Hammond Boulevard Cahoon Road South Widen to 5 Lanes Local Government CIP
The project's purpose is to widen Ramona Boulevard to five lanes from Hammond Boulevard to Cahoon Road South to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
34
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Rampart / Firestone Road Duval 98 Collins Road SR 134 103rd Street Widen to 4 Lanes 2035 Needs Plan
The project's purpose is to widen Rampart / Firestone Road to four lanes from Collins Road to SR 134 103rd Street to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Ranch Road Duval 1038 Tradeport Road SR 102 North of Airport Road Widen to 4 Lanes SIS Unfunded Needs
The project's purpose is to widen Ranch Road to four lanes from Tradeport Road to SR 102 North of Airport Road to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
Ricker Road Duval 934 Morse Avenue Old Middleburg Road Widen to 3 Lanes Local Government CIP
The project's purpose is to widen Ricker Road to three lanes from Morse Avenue to Old Middleburg Road to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
Salisbury Road Extension Duval 99 SR 152 Baymeadows Boulevard Belfort Road New 3 Lane Road 2035 Needs Plan
The project's purpose is to construct a new three‐lane road called Salisbury Road Extension from SR 152 Baymeadows Boulevard to Belfort Road to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
San Pablo Road Duval 1009 US 90 Beach Boulevard SR 10 Atlantic Boulevard Widen to 3 Lanes Local Government CIP
The project's purpose is to widen San Pablo Road to three lanes from US 90 Beach Boulevard to SR 10 Atlantic Boulevard to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
35
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Shindler Drive Duval 101 Collins Road SR 134 103rd Street Widen to 3 Lanes Local Government CIP
The project's purpose is to widen Shindler Drive to three lanes from Collins Road to SR 134 103rd Street to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
SR 10 Atlantic Boulevard Duval 714 at Girvin Road Intersection Improvements
Phases are currently included in a local government capital improvement program.
The project's purpose is to construct intersection improvements along SR 10 Atlantic Boulevard at Girvin Road to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
SR 10 Atlantic Boulevard Duval 715 at Hodges Boulevard Intersection Improvements Local Government CIP
The project's purpose is to construct intersection improvements along SR 10 Atlantic Boulevard at Hodges Boulevard to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
SR 10 Atlantic Boulevard Duval 716 at San Pablo Boulevard Intersection Improvements
Phases are currently included in a local government capital improvement program.
The project's purpose is to construct intersection improvements along SR 10 Atlantic Boulevard at San Pablo Boulevard to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
SR 100 Clay 450 Clay/Bradford County Line Clay/Putnam County Line Widen to 4 Lanes SIS Unfunded Needs
The project's purpose is to widen SR 100 to four lanes from Clay/Bradford County Line to Clay/Putnam County Line to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
36
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
SR 100 Putnam 451 Clay/Putnam County Line US 17 SR 5 Widen to 4 Lanes SIS Unfunded Needs
The project's purpose is to widen SR 100 to four lanes from Clay/Putnam County Line to US 17 SR 5 to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
SR 101 Mayport Road Duval 152B SR 116 Wonderwood Drive Mayport Main Gate Add 2 Northbound Lanes
Through coordination with Mayport Naval Station
The project's purpose is to add two northbound lanes along SR 101 Mayport Road from SR 116 Wonderwood Drive to Mayport Main Gate to address congestion needs and improve mobility.
The project need was established in the through coordination with Mayport Naval Station and local government coordination.
SR 101 Mayport Road Duval 152 at SR 116 Wonderwood Drive Intersection Improvements
Through coordination with Mayport Naval Station
The project's purpose is to construct intersection improvements along SR 101 Mayport Road at SR 116 Wonderwood Drive to address congestion needs and improve mobility.
The project need was established in the through coordination with Mayport Naval Station and local government coordination.
SR 102 Airport Road Duval 421 Airport Entrance I‐95 Widen to 6 Lanes SIS Unfunded Needs
The project's purpose is to widen SR102 Airport Road to 6 lanes from the Airport Entrance to I‐95 to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
SR 104 Dunn Avenue Duval 940 US 1/SR 15 New Kings Road I‐295 Widen to 4 Lanes 2035 Needs Plan
The project's purpose is to widen SR 104 Dunn Avenue to four lanes from US 1/SR 15 New Kings Road to I‐295 to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
37
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
SR 104 Dunn Avenue Duval 941 Old Kings Road US 23 New Kings Road Intersection Improvements 2035 Needs Plan
The project's purpose is to construct intersection improvements along SR 104 Dunn Avenue from Old Kings Road to US 23 New Kings Road to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
SR 115 Arlington Expressway Duval 100 SR 109 University Boulevard SR 10 Atlantic Boulevard Widen to 6 Lanes*
New need identified in the 2040 LRTP.
The project's purpose is to widen SR 115 Arlington Expressway to six lanes from SR 109 University Boulevard to SR 10 Atlantic Boulevard to address congestion needs and improve mobility. This project was also identified as a candidate for context sensitive solutions in lieu of widening.
The project was identified as a candidate for context sensitive solutions through the planning process based on the lack of accessibility and mobility within the corridor.
SR 115 Arlington Expressway Duval 153 at SR 109 University Boulevard Modify Interchange
Established as part of the SR 115 Mathews Bridge Replacement PD&E Study and included in the Duval County LOGT program for PE.
The project's purpose is to modify the interchange of SR 115 Arlington Expressway at SR 109 University Boulevard to address congestion needs and improve mobility.
The project need was established as part of the SR 115 Mathews Bridge Replacement PD&E Study and included in the Duval County LOGT program for PE. The need for this project was confirmed as part of the planning process.
SR 115 Lem Turner Road Duval/Nassau 74 I‐295 US 1 / Callahan S Kings Road Widen to 4 Lanes 2035 Cost Feasible Plan
The project's purpose is to widen SR 115 Lem Turner Road to four lanes from I‐295 to US 1 / Callahan S Kings Road to address congestion needs and improve mobility.
The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process.
SR 115 Southside Boulevard Duval 102 US 1/SR 5 Philips Highway I‐95 Ramps Widen to 6 Lanes*
SR115SouthsideBoulevardCorridorStudy
The project's purpose is to widen SR 115 Southside Boulevard to six lanes from US 1/SR 5 Philips Highway to the I‐95 Ramps to address congestion needs and improve mobility. This project was also identified as a candidate for context sensitive solutions in lieu of widening.
The project need was established in the 0 and confirmed as part of the planning process.
38
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
SR 115 Southside Boulevard Duval 103 SR 202 J. T. Butler Boulevard US 90 Beach Boulevard Widen to 6 Lanes*
SR115SouthsideBoulevardCorridorStudy
The project's purpose is to widen SR 115 Southside Boulevard to six lanes from SR 202 J. T. Butler Boulevard to US 90 Beach Boulevard to address congestion needs and improve mobility. This project was also identified as a candidate for context sensitive solutions in lieu of widening.
The project need was established in the 0 and confirmed as part of the planning process.
SR 115 Southside Boulevard Duval 104 US 90 Beach Boulevard SR 10 Atlantic Boulevard Widen to 6 Lanes* 2035 Needs Plan
The project's purpose is to widen SR 115 Southside Boulevard to six lanes from US 90 Beach Boulevard to SR 10 Atlantic Boulevard to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
SR 115 Southside Boulevard Duval 960 Hogan Road Gate Parkway Intersection Improvements Local Government CIP
The project's purpose is to construct intersection improvements along SR 115 Southside Boulevard from Hogan Road to Gate Parkway to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
SR 115 Southside Boulevard Duval 966 at SR 202 J. T. Butler Boulevard Modify Interchange
SR115SouthsideBoulevardCorridorStudy
The project's purpose is to modify the interchange of SR 115 Southside Boulevard at SR 202 J. T. Butler Boulevard to address congestion needs and improve mobility.
The project need was established in the 0 and confirmed as part of the planning process.
SR 115 Southside Boulevard Duval 967 at SR 152 Baymeadows Road Underpass
SR115SouthsideBoulevardCorridorStudy
The project's purpose is to construct an underpass where SR 152 Baymeadows Road would go under SR 115 Southside Boulevard to address congestion needs and improve mobility.
The project need was established in the 0 and confirmed as part of the planning process.
39
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
SR 115 Southside Boulevard Duval 968 at SR 10 Atlantic Boulevard Intersection Improvements Local
Government CIP
The project's purpose is to construct intersection improvements along SR 115 Southside Boulevard at SR 10 Atlantic Boulevard to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
SR 152 Baymeadows Road Duval 937 I‐95 SR 115 Southside Boulevard Widen to 6 Lanes 2035 Needs Plan
The project's purpose is to widen SR 152 Baymeadows Road to 6 lanes from I‐95 to SR 115 Southside Boulevard to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
SR 152 Baymeadows Road Duval 938 US 1 /SR 5 Philips Highway I‐95 Widen to 6 Lanes* 2035 Needs Plan
The project's purpose is to widen SR 152 Baymeadows Road to six lanes from US 1 SR 5 Philips Highway to I‐95 to address congestion needs and improve mobility. This project was also identified as a candidate for context sensitive solutions in lieu of widening.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
SR 16 Clay 106 CR 218 SR 15A Oakridge Avenue Widen to 4 Lanes 2035 Needs Plan
The project's purpose is to widen SR 16 to four lanes from CR two18 to SR 15A Oakridge Avenue to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
SR 16 St Johns 110 I‐95 SR 313 Widen to 6 Lanes 2035 Needs Plan
The project's purpose is to widen SR 16 to six lanes from I‐95 to SR 313 to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
40
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
SR 16 Clay 908 US 17 Shands Bridge Widen to 4 Lanes Other Local Government Priority
The project's purpose is to widen SR 16 to four lanes from US 17 to Shands Bridge to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
SR 16 St Johns 835 South Francis Road International Golf Parkway Widen to 4 Lanes Other Local Government Priority
The project's purpose is to widen SR 16 to four lanes from South Francis Road to International Golf Parkway to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
SR 16 St Johns 836 CR 208 Outlet Mall South Francis Road Widen to 4 Lanes Other Local Government Priority
The project's purpose is to widen SR 16 to four lanes from CR 208 Outlet Mall to South Francis Road to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
SR 16 Connector St Johns 829 SR 16/CR 16A CR 2209 New 4 Lane Road 2035 Needs Plan
The project's purpose is to construct a new four‐lane road called SR 16 Connector from SR 16/CR 16A to CR 2209 to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
SR 19 Connector Putnam 965 SR 19 Putnam County Boulevard New 4 lane road / bridge Other Local Government Priority
The project's purpose is to construct a new four‐lane road / bridge called SR 19 Connector from SR 19 to Putnam County Boulevard to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
41
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
SR 20 Putnam 422 Putnam/Alachua County Line SW 56th Avenue Widen to 4 Lanes Phases in TIP or
Work Program
The project's purpose is to widen SR 20 to four lanes from Putnam/Alachua County Line to SW 56th Avenue to address congestion needs and improve mobility.
The project need was established in the Phases in TIP or Work Program and confirmed as part of the planning process.
SR 20 Putnam 423 SW 56th Avenue CR 315 Interlachen Widen to 4 Lanes Phases in TIP or Work Program
The project's purpose is to widen SR20 to four lanes from SW 56th Avenue to CR 315 in Interlachen to address congestion needs and improve mobility.
The project need was established in the Phases in TIP or Work Program and confirmed as part of the planning process.
SR 200 Overpass Nassau 1003 at US 17 SR 5 and Railroad Tracks Overpass 2035 Needs Plan
The project's purpose is to construct an overpass along SR 200 at US 17 SR 5 and the railroad tracks to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
SR 200 William Burgess Connector Nassau 998 William Burgess
Boulevard SR 200 SR A1A New 2 Lane Road Local government coordination
The project's purpose is to construct a new two‐lane Road called SR 200 William Burgess Connector from William Burgess Boulevard to SR 200 SR A1A to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
SR 200 Yulee Backage Roads Nassau 992 Cardinal Street North Extension Old Yulee Road New 2 Lane Road Local government
coordination
The project's purpose is to construct a new two‐lane road called SR 200 Yulee Backage Roads from the Cardinal Street North Extension to Old Yulee Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
42
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
SR 200 SR A1A Nassau 427 at US 17 Intersection Improvements SIS CFP
The project's purpose is to construct intersection improvements along SR 200 SR A1A at US 17 to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
SR 200 SR A1A Nassau 703 Amelia Island Parkway Sadler Road Widen to 6 Lanes Local government coordination
The project's purpose is to widen SR 200 SR A1A to six lanes from Amelia Island Parkway to Sadler Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
SR 200A Pages Dairy Road Nassau 979 at Felmor Road Roundabout Projects Local government coordination
The project's purpose is to construction a roundabout along SR 200A Pages Dairy Road at Felmor Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
SR 207 St Johns 113 I‐95 South Holmes Boulevard Widen to 6 Lanes 2035 Needs Plan
The project's purpose is to SR 207 widen to six lanes from I‐95 to South Holmes Boulevard to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
SR 207 St Johns 830 Holmes Boulevard SR 312 Widen to 6 Lanes 2035 Needs Plan
The project's purpose is to widen SR 207 to 6 lanes from Holmes Boulevard to SR 312 to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
43
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
SR 21 Blanding Boulevard Duval 9 I‐295 Wilson Boulevard Widen to 6 Lanes 2035 Needs Plan
The project's purpose is to widen SR 21 Blanding Boulevard to six lanes from I‐295 to Wilson Boulevard to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
SR 21 Blanding Boulevard Clay 114 SR 16 CR 215 Blanding Boulevard Widen to 4 Lanes 2035 Needs Plan
The project's purpose is to widen SR 21 Blanding Boulevard to four lanes from SR 16 to CR two15 Blanding Boulevard to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
SR 21 Blanding Boulevard Duval 957A at Collins Road Intersection Improvements Local Government CIP
The project's purpose is to construct intersection improvements along SR 21 Blanding Boulevard at Collins Road to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
SR 21 Blanding Boulevard Duval 957B at SR 134 103rd Street Intersection Improvements Local Government CIP
The project's purpose is to construct intersection improvements along SR 21 Blanding Boulevard at SR 134 103rd Street to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
SR 21 Blanding Boulevard Duval 957C at Cedar Hills Boulevard Intersection Improvements Local Government CIP
The project's purpose is to construct intersection improvements along SR 21 Blanding Boulevard at Cedar Hills Boulevard to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
44
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
SR 228 Hart Bridge Duval 47 SR 228 Hart Expressway ‐ Downtown SR 10 Atlantic Boulevard New 6 Lane Bridge 2035 Needs Plan
The project's purpose is to construct a replace the SR 228 Hart Bridge from SR 228 Hart Expressway ‐ Downtown to SR 10 Atlantic Boulevard to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
SR 228 Normandy Boulevard Duval 86 US 301 Bell Road (Equestrian Park ) Widen to 4 Lanes 2035 Needs Plan
The project's purpose is to widen SR 228 Normandy Boulevard to four lanes from US 301 to Bell Road (Equestrian Park) to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
SR 228 Normandy Boulevard Duval 87 SR 23 First Coast Expressway SR 111 Cassatt Avenue Widen to 6 Lanes 2035 Needs Plan
The project's purpose is to widen SR 228 Normandy Boulevard to six lanes from SR 23 First Coast Expressway to SR 111 Cassatt Avenue to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
SR 23 First Coast Expressway Clay 41 at CR 218 New Interchange SIS CFP
The project's purpose is to construct a new interchange along SR 23 First Coast Expressway at CR two18 to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
SR 23 First Coast Expressway Clay 8202 SR 21 Blanding Boulevard US 17 New 4 Lane Road SIS CFP
The project's purpose is to construct a new four‐lane road called SR 23 First Coast Expressway from SR 21 Blanding Boulevard to US 17 to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
45
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
SR 23 First Coast Expressway Clay 1011 at SR 21 Blanding Boulevard New Interchange SIS CFP
The project's purpose is to construct a new interchange along SR 23 First Coast Expressway at SR 21 Blanding Boulevard to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
SR 23 First Coast Expressway Clay 1012 at CR 739 New Interchange SIS CFP
The project's purpose is to construct a new interchange along SR 23 First Coast Expressway at CR 739 to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
SR 23 First Coast Expressway Clay 1013 at SR 16 New Interchange SIS CFP
The project's purpose is to construct a new interchange along SR 23 First Coast Expressway at SR 16 to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
SR 23 First Coast Expressway Clay/Duval 8201 I‐10 SR 21 Blanding Boulevard Widen to 6 Lanes SIS CFP
The project's purpose is to widen SR 23 First Coast Expressway from I‐10 to SR 21 Blanding Boulevard to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
SR 23 First Coast Expressway Clay/St. Johns 8203 US 17 I‐95 New 6 Lane Road SIS CFP
The project's purpose is to construct a new six‐lane road called SR 23 First Coast Expressway from US 17 to I‐95 to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
46
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
SR 23 First Coast Expressway St Johns 840 at I‐95 New Interchange SIS CFP
The project's purpose is to construct a new interchange along SR 23 First Coast Expressway at I‐95 to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
SR 23 First Coast Expressway St Johns 841 at CR 16 A New Interchange SIS CFP
The project's purpose is to construct a new interchange along SR 23 First Coast Expressway at CR 16 A to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
SR 23 First Coast Expressway St Johns 847 at CR 2209 New Interchange SIS CFP
The project's purpose is to construct a new interchange along SR 23 First Coast Expressway at CR 2209 to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
SR 243 JIA North Access Road Duval 701 SR 102 Airport Road Pecan Park Road Widen to 4 Lanes 2035 Needs Plan
The project's purpose is to widen SR 243 JIA North Access Road to four lanes from SR 102 Airport Road to Pecan Park Road to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
SR 312 St Johns 115 US 1/SR 5 Dixie Highway SR A1A Widen to 6 Lanes 2035 Needs Plan
The project's purpose is to widen SR 312 to six lanes from US 1/SR 5 Dixie Highway to SR A1A to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
47
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
SR 313 St Johns 831 SR 207 SR 16 New 6 Lane Road 2035 Needs Plan
The project's purpose is to construct a new six lane road called SR 313 from SR 207 to SR 16 to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
SR 313 St Johns 832 SR 16 US 1 Dixie Highway New 4 Lane Road 2035 Needs Plan
The project's purpose is to construct a new four‐lane road called SR 313 from SR 16 to US 1 Dixie Highway to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
SR 313 St Johns 839 at US 1/SR 5 Dixie Highway New Interchange
Other Local Government Priority
The project's purpose is to construct a new interchange along SR 313 at US 1 SR 5 Dixie Highway to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
SR 9B Duval 1024 US 1/SR 5 Philips Highway I‐295 Add 2 Auxiliary Lanes SIS CFP
The project's purpose is to add two auxiliary lanes along SR 9B from US 1/SR 5 Philips Highway to I‐295 to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
SR 9B Duval 18 US 1/SR 5 Philips Highway I‐295 Widen to 6 Lanes SIS CFP
The project's purpose is to widen SR 9B to six lanes from US 1 SR 5 Philips Highway to I‐295 to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
48
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
SR 9B Extension St Johns 833 St. Johns Parkway Race Track Road Widen to 6 Lanes Other Local Government Priority
The project's purpose is to widen the SR 9B Extension to six lanes from St. Johns Parkway to Race Track Road to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
SR 9B Extension St Johns 842 at Durbin Parkway New Interchange 2035 Needs Plan
The project's purpose is to construct a new interchange along the SR 9B Extension at Durbin Parkway to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
SR A1A St Johns 128 Solana Road SR 202 J. T. Butler Boulevard Widen to 6 Lanes* 2035 Needs Plan
The project's purpose is to widen SR A1A to six lanes from Solana Road to SR 202 J. T. Butler Boulevard to address congestion needs and improve mobility. This project was also identified as a candidate for context sensitive solutions in lieu of widening.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
SR A1A Nassau 706 South Fletcher Avenue Amelia Island Parkway Turn Lane Improvements* Local government coordination
The project's purpose is to construct turn lane improvements along SR A1A from South Fletcher Avenue to Amelia Island Parkway to address congestion needs and improve mobility. This project was also identified as a candidate for context solutions.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
SR A1A St Johns 1008 at Red Cox/Coquina Road Intersection Improvements Other Local Government Priority
The project's purpose is to construct intersection improvements along SR A1A at Red Cox/Coquina Road to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
49
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
SR A1A St Johns 800 Mickler Road Palm Valley Road Widen to 4 Lanes 2035 Needs Plan
The project's purpose is to widen SR A1A to four lanes from Mickler Road to Palm Valley Road to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
SR A1A Duval 151 SR 116 Wonderwood Drive Naval Station Mayport North Gate Widen to 4 Lanes* 2035 Needs Plan
The project's purpose is to widen SR A1A to four lanes from SR 116 Wonderwood Drive to Naval Station Mayport North Gate to address congestion needs and improve mobility. This project was also identified as a candidate for context sensitive solutions in lieu of widening.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
SR A1A Anastasia Boulevard St Johns 1031 Casanova Road Bridge of Lions CSS St. Augustine Mobility Institute
The project's purpose is to construct context sensitive solutions along SR A1A Anastasia Boulevard from Casanova Road to Bridge of Lions to address congestion needs and improve mobility.
The project need was established in the St. Augustine Mobility Institute and confirmed as part of the planning process.
SR A1A St Johns River Ferry Duval 2331 Ferry Slip Replacement 2035 Cost Feasible Plan
The project's purpose is to replace the St. Johns River ferry slip to maintain service, address congestion needs and improve mobility.
The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process.
St. Johns Parkway St Johns 848 CR 2209 9B Extension Widen to 6 Lanes Other Local Government Priority
The project's purpose is to widen the St. Johns Parkway to six lanes from CR 2209 to 9B Extension to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
50
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Starratt Road Duval 954 Duval Station Road Yellow Bluff Road Widen to 4 Lanes Local government coordination
The project's purpose is to widen Starratt Road to four lanes from Duval Station Road to Yellow Bluff Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Touchton Road Duval 129 Belfort Road SR 115 Southside Boulevard Widen to 4 Lanes 2035 Needs Plan
The project's purpose is to widen Touchton Road to four lanes from Belfort Road to SR 115 Southside Boulevard to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Town Center Boulevard Clay 903 US 17 CR 220 Doctors Inlet Road Widen to 4 Lanes Other Local Government Priority
The project's purpose is to widen Town Center Boulevard to four lanes from US 17 to CR 220 Doctors Inlet Road to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Trout River Boulevard Duval 955 Old Kings Road US 23 New Kings Road Widen to 4 Lanes Local government coordination
The project's purpose is to widen Trout River Boulevard to four lanes from Old Kings Road to US two3 New Kings Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Tynes Road Clay 912 Pipit Place Oakleaf Plantation Parkway New 2 Lane Road Other Local Government Priority
The project's purpose is to construct a new two‐lane road called Tynes Road from Pipit Place to Oakleaf Plantation Parkway to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
51
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
US 1 SR 15 New Kings Road Duval 82 Soutel Drive I‐295 Widen to 6 Lanes 2035 Needs Plan
The project's purpose is to widen US 1 SR 15 New Kings Road to six lanes from Soutel Drive to I‐295 to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
US 1 SR 15 New Kings Road Duval 83 I‐295 Old Kings Road Widen to 6 Lanes 2035 Needs Plan
The project's purpose is to widen US 1 SR 15 New Kings Road to six lanes from I‐295 to Old Kings Road to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
US 1 SR 15 New Kings Road Duval 950 SR 111 Edgewood Avenue Soutel Drive Intersection Improvements Local government coordination
The project's purpose is to construct intersection improvements along US 1 SR 15 New Kings Road at SR 111 Edgewood Avenue to Soutel Drive to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
US 1 SR 5 St Johns 845 at CR 210 Modify Interchange Phases in TIP or Work Program
The project's purpose is to modify the interchange of US 1 SR 5 at CR 210 to address congestion needs and improve mobility.
The project need was established in the Phases in TIP or Work Program and confirmed as part of the planning process.
US 1 SR 5 Dixie Highway St Johns 130 SR 206 Lewis Point Road Widen to 6 Lanes 2035 Needs Plan
The project's purpose is to widen US 1 SR 5 Dixie Highway to six lanes from SR 206 to Lewis Point Road to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
52
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
US 1 SR 5 Dixie Highway St Johns 131 SR 313 International Golf Parkway Widen to 6 Lanes 2035 Needs Plan
The project's purpose is to widen US 1 SR 5 Dixie Highway to six lanes from SR 313 to International Golf Parkway to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
US 1 SR 5 Dixie Highway St Johns 132 International Golf Parkway Race Track Road Widen to 6 Lanes 2035 Needs Plan
The project's purpose is to widen US 1 SR 5 Dixie Highway to six lanes from International Golf Parkway to Race Track Road to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
US 1 SR 5 Philips Highway Duval 93 Nocatee Parkway / Race Track Road SR 9B Widen to 6 Lanes 2035 Needs Plan
The project's purpose is to widen US 1 SR 5 Philips Highway to six lanes from Nocatee Parkway / Race Track Road to SR 9B to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
US 1/SR 5 Philips Highway Duval 94 SR 9B I‐295 Widen to 6 Lanes* 2035 Needs Plan
The project's purpose is to widen US 1 SR 5 Philips Highway to six lanes from SR 9B to I‐295 to address congestion needs and improve mobility. This project was also identified as a candidate for context sensitive solutions in lieu of widening.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
US 1/SR 5 Philips Highway Duval 95 I‐95 at the Avenues SR 202 J. T. Butler Boulevard Widen to 6 Lanes* 2035 Needs Plan
The project's purpose is to widen to US 1 SR 5 Philips Highway to six lanes from I‐95 at the Avenues to SR 202 J. T. Butler Boulevard to address congestion needs and improve mobility. This project was also identified as a candidate for context sensitive solutions in lieu of widening.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
53
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
US 1/SR 5 Philips Highway Duval 96 SR 202 J. T. Butler Boulevard SR 126 Emerson Street Widen to 6 Lanes 2035 Needs Plan
The project's purpose is to widen to US 1 SR 5 Philips Highway to six lanes from SR 202 J. T. Butler Boulevard to SR 1two6 Emerson Street to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
US 17 Clay 133 CR 315 Town Center Boulevard Widen to 6 Lanes 2035 Needs Plan
The project's purpose is to widen US 17 to six lanes from CR 315 to Town Center Boulevard to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
US 17 Nassau 707 Nassau/Duval County Line Harts Road Intersection Improvements Local government coordination
The project's purpose is to construct intersection improvements along US 17 from Nassau/Duval County Line to Harts Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
US 17 Nassau 709 SR 200 SR A1A Georgia State Line Widen to 4 Lanes I‐95 Parallel Corridor Study
The project's purpose is to widen US 17 to four lanes from SR 200 SR A1A to Georgia State Line to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
US 17 Clay 1037 Governor Street Haven Avenue Widen to 4 Lanes 2035 Cost Feasible Plan
The project's purpose is to widen US 17 to four lanes from Governor Street to Haven Avenue to address congestion needs and improve mobility.
The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process.
54
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
US 17 Main Street Duval/Nassau 78 Pecan Park Road SR 200 / SR A1A Widen to 4 Lanes 2035 Needs Plan
The project's purpose is to widen US 17 Main Street to four lanes from Pecan Park Road to SR 200 / SR A1A to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
US 17 Main Street Duval 1017 New Berlin Road Pecan Park Road Widen to 4 Lanes 2035 Cost Feasible Plan
The project's purpose is to widen US 17 to four lanes from New Berlin Road to Pecan Park Road to address congestion needs and improve mobility.
The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process.
US 17 Main Street Duval 959 at Eastport Road New Interchange Local Government CIP
The project's purpose is to construct a new interchange along US 17 Main Street at Eastport Road to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
US 17 Pages Dairy Connector w/roundabout Nassau 984 US 17 SR 5 SR 200A Pages Dairy Road New 2 Lane Road and
Roundabout Local government coordination
The project's purpose is to construct a new road called US 17 Pages Dairy Connector from US 17 SR 5 to SR 200A Pages Dairy Road and roundabout at SR 200A Paiges Dairy Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
US 17 Powerline Corridor Nassau 994 Vegas Boulevard Radio Avenue New 2 Lane Road Local government coordination
The project's purpose is to construct a new two‐lane road called US 17 Powerline Corridor from Vegas Boulevard to Radio Avenue to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
55
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
US 17 SR 15 Putnam 428 West of Dunn Creek Bridge Horse Landing Road Widen to 4 Lanes SIS Unfunded
Needs
The project's purpose is to widen US 17 SR 15 to four lanes from West of Dunn Creek Bridge to Horse Landing Road to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
US 17 SR 15 Putnam 429 CR 309 Satsuma West of Dunn Creek Bridge Widen to 4 Lanes SIS Unfunded Needs
The project's purpose is to widen US 17 SR 15 from CR 309 Satsuma to West of Dunn Creek Bridge to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
US 17 SR 15 Putnam 430 Putnam/Volusia County Line Pomona Park/Feagle Avenue Widen to 4 Lanes SIS Unfunded
Needs
The project's purpose is to widen to US 17 SR 15 to four lanes from the Putnam/Volusia County Line to Pomona Park/Feagle Avenue to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
US 17 SR 15 Putnam 452 Pomona Park/Feagle Avenue CR 309 Satsuma Widen to 4 Lanes SIS CFP
The project's purpose is to widen US 17 SR 15 to four lanes from Pomona Park/Feagle Avenue to CR 309 Satsuma to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
US 17 Yulee Backage Roads Nassau 999 US 17 SR 5 North of Koen Lane New 2 Lane Road Local government coordination
The project's purpose is to construct a new two‐lane road called the US 17 Yulee Backage Roads from US 17 SR 5 to North of Koen Lane to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
56
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
US 1B King Street St Johns 1029 US 1 Ponce de Leon Boulevard Avenida Menendez Context Sensitive Solutions St. Augustine
Mobility Institute
The project's purpose is to construct context sensitive solutions along US 1B King Street from US 1 Ponce de Leon Boulevard to Avenida Menendez to address congestion needs and improve mobility.
The project need was established in the St. Augustine Mobility Institute and confirmed as part of the planning process.
US 1B San Marco Avenue St Johns 1030 Bridge of Lions SR 16 Context Sensitive Solutions St. Augustine Mobility Institute
The project's purpose is to construct context sensitive solutions along US 1B San Marco Avenue from Bridge of Lions to SR 16 to address congestion needs and improve mobility.
The project need was established in the St. Augustine Mobility Institute and confirmed as part of the planning process.
US 301 SR 200 Duval 123 US 90 Duval/Nassau County Line Widen to 4 Lanes 2035 Needs Plan
The project's purpose is to widen US 301 SR 200 to four lanes from US 90 to Duval/Nassau County Line to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
US 301 SR 200 Clay 424 Clay/Bradford County Line Duval/Clay County Line Widen to 6 Lanes SIS Unfunded Needs
The project's purpose is to widen US 301 SR 200 to six lanes from the Clay/Bradford County Line to Duval/Clay County Line to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
US 301 SR 200 Nassau 708 US 1 at S Kings Road Intersection Improvements Local government coordination
The project's purpose is to construct intersection improvements along US 301 SR 200 from US 1 at South Kings Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
57
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
US 301 SR 200 Duval 425 Duval/Clay County Line I‐10 Widen to 6 Lanes SIS Unfunded Needs
The project's purpose is to widen US 301 SR 200 to six lanes from Duval/Clay County Line to I‐10 to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
US 90 / SR 115 Mathews Bridge Duval 79 Alt. US 1 MLK Jr. Parkway SR 109 University Boulevard New 6 Lane Bridge and Transit 2035 Needs Plan
The project's purpose is to reconstruct the US 90 / SR 115 Mathews Bridge as a six lane bridge and provide transit accommodations from Alt. US 1 MLK Jr. Parkway to SR 109 University Boulevard to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
US 90 Beaver Street Duval 6 SR 23 First Coast Expressway Cahoon Road Widen to 4 Lanes 2035 Needs Plan
The project's purpose is to widen US 90 Beaver Street to four lanes from SR 23 First Coast Expressway to Cahoon Road to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
US 90 Beaver Street Duval 7 Cahoon Road McDuff Avenue Widen to 4 Lanes 2035 Needs Plan
The project's purpose is to widen US 90 Beaver Street to four lanes from Cahoon Road to McDuff Avenue to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Various SR 200 Intersections Modifications Nassau 981 Intersection Improvements Local government
coordination
The project's purpose is to construct intersection improvements along SR 200 at various locations to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
58
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Veterans Parkway St Johns 834 Greenbriar Road Longleaf Pine Parkway New 4 Lane Road Other Local Government Priority
The project's purpose is to construct a new four‐lane road called Veterans Parkway from Greenbriar Road to Longleaf Pine Parkway to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Wells Road Clay 910 Aquarius Concourse SR 21 Blanding Boulevard Reconstruct and New 2 Lane Road
Other Local Government Priority
The project's purpose is to reconstruct Wells Road and construct new two‐lane road extension of Wells Road from Aquarius Concourse to SR 21 Blanding Boulevard to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Woodbridge Parkway Extension Nassau 997 Woodbrigde Parkway Clements Road New 2 Lane Road Local government
coordination
The project's purpose is to construct a new two‐lane road called Woodbridge Parkway Extension from Woodbrigde Parkway to Clements Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Yellow Bluff Road Duval 956 Starratt Road New Berlin Road (north) Widen to 4 Lanes Local government coordination
The project's purpose is to widen Yellow Bluff Road from Starratt Road to New Berlin Road (north) to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Transit Capacity Projects
East First Coast Flyer Duval 2385 Downtown Jacksonville (Duval County) 3rd Street (Jacksonville Beach) BRT Blueprint 2020
and 2035 LRTP
This project's purpose is to provide higher quality bus services throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
59
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Southwest First Coast Flyer Duval 2386 Wells Road Downtown Jacksonville (Duval County) BRT Blueprint 2020
and 2035 LRTP
This project's purpose is to provide higher quality bus services throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
SR 134 103rd Street Duval 2321 SR 228 Normandy Boulevard SR 21 Blanding Boulevard BRT Blueprint 2020
and 2035 LRTP
This project's purpose is to provide higher quality bus services throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
SR 21 Blanding Boulevard Clay 2308 CR 218 Wells Road BRT Blueprint 2020 and 2035 LRTP
This project's purpose is to provide higher quality bus services throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
SR 228 Normandy Boulevard Duval 2322 SR 134 103rd Street Downtown Jacksonville (Duval County) BRT Blueprint 2020
and 2035 LRTP
This project's purpose is to provide higher quality bus services throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
US 1 Duval 2324 Lewis Speedway (St. John's County) Avenues Mall (Duval County) BRT Blueprint 2020
and 2035 LRTP
This project's purpose is to provide higher quality bus services throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
60
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
US 1 St. John's 2375 Lewis Speedway (St. John's County) Avenues Mall (Duval County) BRT Blueprint 2020
and 2035 LRTP
This project's purpose is to provide higher quality bus services throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
US 1/SR 15 New Kings Road Duval 2323 Downtown Jacksonville (Duval County) Edgewood Avenue BRT Blueprint 2020
and 2035 LRTP
This project's purpose is to provide higher quality bus services throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
SR 115 Southside Boulevard Duval 2325 Avenues Mall Regency Square Mall BRT Blueprint 2020 and 2035 LRTP
This project's purpose is to provide higher quality bus services throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
I‐95 Duval 2326 Gateway Mall Jacksonville International Airport BRT Blueprint 2020 and 2035 LRTP
This project's purpose is to provide higher quality bus services throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
North (CSX) Duval 2356 Downtown Jacksonville (Duval County) Yulee (Nassau County) Commuter Rail Blueprint 2020
and 2035 LRTP
The project's purpose is the provide accessibility to additional mobility options for longer commuter trips throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
61
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
North Extension (CSX) Nassau 2366 Yulee Fernandina Beach Commuter Rail Blueprint 2020 and 2035 LRTP
The project's purpose is the provide accessibility to additional mobility options for longer commuter trips throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
Northwest (CSX) Duval 2357 Downtown Jacksonville (Duval County) Callahan (Nassau County) Commuter Rail Blueprint 2020
and 2035 LRTP
The project's purpose is the provide accessibility to additional mobility options for longer commuter trips throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
Southeast (FEC) Duval 2327 St. Augustine (St. John's County)
Downtown Jacksonville (Duval County) Commuter Rail Blueprint 2020
and 2035 LRTP
The project's purpose is the provide accessibility to additional mobility options for longer commuter trips throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
Southeast Extension (FEC) St. John's 2377 Palm Coast (Flagler County) City of St. Augustine Commuter Rail Blueprint 2020
and 2035 LRTP
The project's purpose is the provide accessibility to additional mobility options for longer commuter trips throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
Southwest (CSX) Duval 2358 Green Cove Springs (Clay County)
Downtown Jacksonville (Duval County) Commuter Rail Blueprint 2020
and 2035 LRTP
The project's purpose is the provide accessibility to additional mobility options for longer commuter trips throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
62
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Southwest Extension (CSX) Clay 2319 Palatka (Putnam County) Green Cove Springs (Clay County) Commuter Rail Blueprint 2020 and 2035 LRTP
The project's purpose is the provide accessibility to additional mobility options for longer commuter trips throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
West (CSX) Duval 2328 Baldwin (Duval County) Downtown Jacksonville (Duval County) Commuter Rail Blueprint 2020
and 2035 LRTP
The project's purpose is the provide accessibility to additional mobility options for longer commuter trips throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
West Extension (CSX) Baker 2301 MacClenny (Baker County) Baldwin (Duval County) Commuter Rail Blueprint 2020
and 2035 LRTP
The project's purpose is the provide accessibility to additional mobility options for longer commuter trips throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
I‐95 Duval 2330 Downtown Jacksonville (Duval County) Yulee (Nassau County) Express Bus Service Blueprint 2020
The project's purpose is the provide accessibility to additional mobility options for longer commuter trips throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
Cumberland Island Ferry Nassau 2369 Fernandina Cumberland Island Ferry Service Nassau County
The project's purpose is to provide direct access to Cumberland Island from Florida allowing travelers to avoid crossing the St. Mary's River to access this National Park.
The need for this project was identified based on the Florida East Coast Greenway study and confirmed as part of the planning process.
63
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
SR A1A St Johns River Ferry Duval 2331 Ferry Slip Replacement St. Johns River Ferry Commission
This project's purpose is to provide safer and more efficient operations of the St. Johns River Ferry. The project will replace the ferry slips.
The need for this project was identified through coordination with the St. Johns River Ferry Commission and confirmed as part of the planning process.
SR A1A St Johns River Ferry Duval 2329 Drydock / Ferry Repairs St. Johns River Ferry Commission
This project's purpose is to provide safer and more efficient operations of the St. Johns River Ferry.
The need for this project was identified through coordination with the St. Johns River Ferry Commission and confirmed as part of the planning process.
SR A1A St Johns River Ferry Duval 2333 Ft. George/Mayport Long Term Site Improvements St. Johns River Ferry Commission
This project's purpose is to provide safer and more efficient operations of the St. Johns River Ferry by improving the vehicular access and storage.
The need for this project was identified through coordination with the St. Johns River Ferry Commission and confirmed as part of the planning process.
SR A1A St Johns River Ferry Duval 2344 JPA Property Mayport Terminal Relocation of Ferry offices St. Johns River Ferry Commission
This project's purpose is to provide safer and more efficient operations of the St. Johns River Ferry by improving the vehicular access and storage.
The need for this project was identified through coordination with the St. Johns River Ferry Commission and confirmed as part of the planning process.
SR A1A St Johns River Ferry Duval 2345 Mayport Ft. George Island Service & Capital Improvements
St. Johns River Ferry Commission
This project's purpose is to provide safer and more efficient operations of the St. Johns River Ferry by improving the vehicular access and storage and long‐term service.
The need for this project was identified through coordination with the St. Johns River Ferry Commission and confirmed as part of the planning process.
64
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
SR A1A St Johns River Ferry Duval 2346 Ft. George/Mayport Site Improvements St. Johns River Ferry Commission
This project's purpose is to provide safer and more efficient operations of the St. Johns River Ferry by improving the vehicular access and storage with short‐term enhancements.
The need for this project was identified through coordination with the St. Johns River Ferry Commission and confirmed as part of the planning process.
Area wide **** Putnam 2374 Local Bus Service Blueprint 2020
This project's purpose is to provide local bus service throughout the region to enhance accessibility and mobility choices.
The need for this project was identified through coordination with local governments and confirmed as part of the planning process.
US 90 Baker 2302 MacClenny (Baker County)
Downtown Jacksonville (Duval County) Local Bus Service Blueprint 2020
This project's purpose is to provide local bus service throughout the region to enhance accessibility and mobility choices.
The need for this project was identified through coordination with local governments and confirmed as part of the planning process.
Area wide **** Baker 2303 Local Bus Service Blueprint 2020
This project's purpose is to provide local bus service throughout the region to enhance accessibility and mobility choices.
The need for this project was identified through coordination with local governments and confirmed as part of the planning process.
Area wide **** Clay 2310 Local Bus Service Blueprint 2020
This project's purpose is to provide local bus service throughout the region to enhance accessibility and mobility choices.
The need for this project was identified through coordination with local governments and confirmed as part of the planning process.
65
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Area wide **** Duval 2332 Local Bus Service Blueprint 2020
This project's purpose is to provide local bus service throughout the region to enhance accessibility and mobility choices.
The need for this project was identified through coordination with local governments and confirmed as part of the planning process.
Area wide **** Nassau 2370 Local Bus Service Blueprint 2020
This project's purpose is to provide local bus service throughout the region to enhance accessibility and mobility choices.
The need for this project was identified through coordination with local governments and confirmed as part of the planning process.
Area wide **** St. John's 2378 Local Bus Service Blueprint 2020
This project's purpose is to provide local bus service throughout the region to enhance accessibility and mobility choices.
The need for this project was identified through coordination with local governments and confirmed as part of the planning process.
Anastasia Island (Amphitheatre) St. John's 2380 Park and Ride Lots Blueprint 2020
The project's purpose is to provide off‐site parking for the Amphitheatre to provide additional transit access.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Center Street Duval 2304 North of Drew Street (Baldwin) Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
66
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
CR 210 St. John's 2381 east of US 1 Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
CR 220 Doctors Inlet Road Clay 2316 at Hollow Road Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Drew Street Duval 2305 at Center Street (Baldwin) Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Duval Road Duval 2336 at I‐95 Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Mayport Road Duval 2338 at SR A1A Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
67
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Racetrack Road St. John's 2382 at US 1 Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
South of Glen St. Mary Baker 2306 Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
SR 115 Lem Turner Road Duval 2337 at SR 104 Dunn Avenue Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
SR 115 Lem Turner Road Duval 2361 at Soutel Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
SR 115 Lem Turner Road Duval 2362 at I‐295 Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
68
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
SR 134 103rd Street Duval 2334 at SR 228 Normandy Boulevard Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
SR 16*** St. John's 2385 Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
SR 200 SR A1A Nassau 2371 at I‐95 Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
SR 200 SR A1A Nassau 2372 east of Yulee Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
SR 207*** St. John's 2386 Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
69
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
SR 21 Blanding Boulevard Clay 2311 at Tanglewood Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
SR 21 Blanding Boulevard Clay 2312 at Old Jennings Road Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
SR 21 Blanding Boulevard Clay 2313 at Edson Drive Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
SR 21 Blanding Boulevard Clay 2314 at Wells Road Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
SR 21 Blanding Boulevard Clay 2315 at SR 224 Kingsley Avenue Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
70
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
SR 21 Blanding Boulevard Clay 2318 North and South of Bolton Road Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
SR 21 Blanding Boulevard Duval 2335 at Weconnett Boulevard Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
SR 21 Blanding Boulevard Duval 2340 North and South of Wilson Boulevard Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
SR 21 Blanding Boulevard Duval 2341 North and South of SR 134 103rd Street Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
SR 21 Blanding Boulevard Duval 2360 at 105th Street Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
71
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
SR 21 Blanding Boulevard Duval 2364 North of I‐295 Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
SR A1A Duval 2343 North and South of SR 202 J. T. Butler Boulevard Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
SR A1A St. John's 2379 at Palm Valley Road Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
St. Augustine Airport St. John's 2383 Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
US 1 St. John's 2384 at Lewis Speedway Road Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
72
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
US 1/SR 15 New Kings Road Duval 2363 Timucuan DRI Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
US 17 Roosevelt Boulevard Clay 2320 at Wells Road Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
US 17 Roosevelt Boulevard Duval 2342 at SR 128 San Juan Avenue Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
US 90 Beach Boulevard Duval 2339 West and East of Kernan Boulevard Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
US 90 Beach Boulevard Duval 2359 at San Pablo Road Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
73
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Yellow Water Road Duval 2307 North of I‐10 Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Youngerman Circle Clay 2317 at Argyle Forest Boulevard Park and Ride Lots Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Five Points/Core/Brooklyn Duval 2347 Central Station Brooklyn Station Skyway Extension ** Blueprint 2020 and 2035 LRTP
The project's purpose is to provide an extension of the Automated Skyway Express to the Five Points and Brooklyn neighborhoods from the urban core.
The need for enhanced transit service to these areas was confirmed through the planning process. ** The specific technology that will be the efficient and cost effective to provide this service will be determined in subsequent Alternatives Analysis phases.
Southbank/San Marco Duval 2348 Kings Avenue Station Southwest of Railroad Tracks (Southbank) Skyway Extension ** Blueprint 2020
and 2035 LRTP
The project's purpose is to provide an extension of the Automated Skyway Express to the Southbank and San Marco neighborhoods from the urban core.
The need for enhanced transit service to these areas was confirmed through the planning process. ** The specific technology that will be the efficient and cost effective to provide this service will be determined in subsequent Alternatives Analysis phases.
Downtown ‐ Sports Complex Duval 2349 Downtown Jacksonville (Bay Street & Main Street) Jacksonville Municipal Stadium Streetcar ** Blueprint 2020
and 2035 LRTP
The project's purpose is to provide a streetcar or other fixed‐guideway transit service to the Downtown Sports Complex neighborhoods from the urban core.
The need for enhanced transit service to these areas was confirmed through the planning process. ** The specific technology that will be the efficient and cost effective to provide this service will be determined in subsequent Alternatives Analysis phases.
74
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Five Points/Core/Brooklyn Duval 2350 Five Points Downtown Jacksonville (Bay Street & Main Street) Streetcar ** Mobility 2030
Plan
The project's purpose is to provide a new streetcar service to the Five Points and Brooklyn neighborhoods from the urban core.
The need for enhanced transit service to these areas was confirmed through the planning process. ** The specific technology that will be the efficient and cost effective to provide this service will be determined in subsequent Alternatives Analysis phases.
La Villa/Core Duval 2351 Transportation Center Duval Street & Monroe Street to Ocean Streetcar ** Mobility 2030
Plan
The project's purpose is to provide a new streetcar service to the La Villa neighborhood from the urban core.
The need for enhanced transit service to these areas was confirmed through the planning process. ** The specific technology that will be the efficient and cost effective to provide this service will be determined in subsequent Alternatives Analysis phases.
Riverside/Avondale Duval 2352 Riverside (King Street) Five Points Streetcar ** Mobility 2030 Plan
The project's purpose is to provide a new streetcar service to the Riverside and Avondale neighborhoods from the urban core.
The need for enhanced transit service to these areas was confirmed through the planning process. ** The specific technology that will be the efficient and cost effective to provide this service will be determined in subsequent Alternatives Analysis phases.
Southbank/San Marco Duval 2353 Kings Avenue Station Baptist Hospital / MOSH & Atlantic Boulevard Streetcar ** Mobility 2030
Plan
The project's purpose is to provide a new streetcar service to the Southbank and San Marco neighborhoods from the urban core.
The need for enhanced transit service to these areas was confirmed through the planning process. ** The specific technology that will be the efficient and cost effective to provide this service will be determined in subsequent Alternatives Analysis phases.
Springfield Duval 2354 FSCJ Station 8th Street/ Medical Complex Streetcar ** Mobility 2030 Plan
The project's purpose is to provide a new streetcar service to the Springfield neighborhood from the urban core.
The need for enhanced transit service to these areas was confirmed through the planning process. ** The specific technology that will be the efficient and cost effective to provide this service will be determined in subsequent Alternatives Analysis phases.
75
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Downtown Facility Duval 2355 Transportation Center Blueprint 2020 and 2035 LRTP
This project's purpose is to construct a new Downtown Transit hub to integrate services between all modes.
The need for the construction of a new Downtown transit hub was confirmed during the planning process.
Transit Capacity Projects
CSX Transportation Clay 2200 at Wells Road Grade Separation SIS Multimodal Needs Plan
This project's purpose is to construct a highway‐rail grade separation to improve safety and traffic flow.
The need for this project was identified through the SIS Multimodal Needs Planning process which included an analysis of the safety record and crossroad congestion. The need was confirmed as part of this planning process.
CSX Transportation Clay 2201 at SR 224 Kingsley Avenue Grade Separation SIS Multimodal Needs Plan
This project's purpose is to construct a highway‐rail grade separation to improve safety and traffic flow.
The need for this project was identified through the SIS Multimodal Needs Planning process which included an analysis of the safety record and crossroad congestion. The need was confirmed as part of this planning process.
CSX Transportation Duval 2202 at SR 104 Busch Drive Grade Separation SIS Multimodal Needs Plan
This project's purpose is to construct a highway‐rail grade separation to improve safety and traffic flow.
The need for this project was identified through the SIS Multimodal Needs Planning process which included an analysis of the safety record and crossroad congestion.
CSX Transportation Nassau 2203 at SR A1A (SR 200) / Yulee Grade Separation SIS Multimodal Needs Plan
This project's purpose is to construct a highway‐rail grade separation to improve safety and traffic flow.
The need for this project was identified through the SIS Multimodal Needs Planning process which included an analysis of the safety record and crossroad congestion. The need was confirmed as part of this planning process.
76
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
CSX Transportation Duval 2204 Beaver Street Interlocking Capacity Upgrade SIS Multimodal Needs Plan
This project's purpose is to improve capacity at the Beaver Street interlock to enhance service reliability.
The need for this project was identified based on coordination with railroads during the development of the SIS Multimodal Plan. The need was confirmed as part of this planning process.
CSX Transportation Duval 2205 North Rail Corridors Phase 1 Multi Modal Corridor North Rail Corridor Feasibility Study
This project's purpose is the construct a new rail connector to reduce rail traffic through downtown which will improve safety. The project will also enhance rail access to the Dames Point and Blount Island terminals.
The need for this project was identified based on coordination with railroads during the development of the SIS Multimodal Plan. The need was confirmed as part of this planning process.
CSX Transportation Duval 2206 Westlake Cecil Commerce Connector Multi Modal Corridor SIS Multimodal Needs Plan
This project's purpose is the enhance access to the Westlake and Cecil Commerce center to support economic development.
The need for this project was identified based on coordination with railroads during the development of the SIS Multimodal Plan. The need was confirmed as part of this planning process.
Florida East Coast Railway Duval 2207 at Bowden Intermodal Capacity Upgrade SIS Multimodal Needs Plan
This project's purpose is to improve track capacity near the Bowden Intermodal Yard to reduce rail crossing blockings and enhance service quality.
The need for this project was identified based on coordination with railroads during the development of the SIS Multimodal Plan. The need was confirmed as part of this planning process.
Florida East Coast Railway Duval 2208 at Jacksonville Bridge Bridge SIS Multimodal Needs Plan
The project will provide repairs and train control technologies on the St. Johns River bridge.
The need for this project was identified based on coordination with railroads during the development of the SIS Multimodal Plan. The need was confirmed as part of this planning process.
77
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Jacksonville International Airport Duval 2209 Construction of Runway 7R/25L Construct Runway SIS Multimodal
Needs Plan This project will construct a new parallel runway to meet future demand.
The project need was identified as part of the Jacksonville International Airport's planning process. The need was confirmed as part of this planning process.
Jacksonville International Airport Duval 2210 Air Cargo Ramp Improvements Expand Apron SIS Multimodal
Needs Plan This project will construct additional air cargo capacity to meet future demand.
The project need was identified as part of the Jacksonville International Airport's planning process. The need was confirmed as part of this planning process.
Jacksonville International Airport Duval 2211 Air Cargo Surface Storage Expand Apron SIS Multimodal
Needs Plan This project will construct additional air cargo capacity to meet future demand.
The project need was identified as part of the Jacksonville International Airport's planning process. The need was confirmed as part of this planning process.
Jacksonville International Airport Duval 2212 Design & Construct By‐Pass Taxiways Construct Taxiway SIS Multimodal
Needs Plan
This project will construct by‐pass taxiways to improve the operational efficiencies.
The project need was identified as part of the Jacksonville International Airport's planning process. The need was confirmed as part of this planning process.
Jacksonville International Airport Duval 2213 Intermodal Terminal Facility Development Terminal Development SIS Multimodal
Needs Plan This project will construct additional air cargo capacity to meet future demand.
The project need was identified as part of the Jacksonville International Airport's planning process. The need was confirmed as part of this planning process.
78
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Norfolk Southern Duval 2214 at Norfolk Southern Railway (Near Simpson Yard) Grade Separation NS CSX SIS Intermodal Connector PD&E
This project's purpose is to construct a highway‐rail grade separation to improve safety and traffic flow.
The need for this project was identified through the SIS Multimodal Needs Planning process which included an analysis of the safety record and crossroad congestion. The need was confirmed as part of this planning process.
Jacksonville Port Authority Duval 2215 Blount Island / Dames Point Marine Terminals Rail Internal Rail JAXPORT Master Plan
This project will provide additional on‐dick rail capacity to meet future demand.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
Jacksonville Port Authority Duval 2216 Blount Island Marine Terminal Berth Upgrades Docks JAXPORT Master Plan
This project will provide additional capacity at berths in the Blount Island marine terminal to improve efficiencies and meet future demand.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
Jacksonville Port Authority Duval 2217 Blount Island Marine Terminal Facility Upgrades Intermodal Transfer Improvement
JAXPORT Master Plan
This project will provide on‐dock rail capacity at berths in the Blount Island marine terminal to improve efficiencies and meet future demand.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
Jacksonville Port Authority Duval 2218 Dames Point Marine Terminal Berth Upgrades Docks JAXPORT Master Plan
This project will provide additional capacity at berths in the Blount Island marine terminal to improve efficiencies and meet future demand.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
79
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Jacksonville Port Authority Duval 2219 Dames Point Marine Terminal Facility Upgrades Intermodal Transfer Improvement
JAXPORT Master Plan
This project will provide gates and other facilities within the marine terminal to improve efficiencies and meet future demand.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
Jacksonville Port Authority Duval 2220 New Cranes for Talleyrand and Blount Island Marine Terminals Intermodal Transfer Improvement
JAXPORT Master Plan
This project will provide new cranes to meet future demand at the port.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
Jacksonville Port Authority Duval 2221 Talleyrand Marine Terminal Berth Upgrades Docks JAXPORT Master Plan
This project will provide additional capacity at berths in the Talleyrand marine terminal to improve efficiencies and meet future demand.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
Jacksonville Port Authority Duval 2222 Talleyrand Marine Terminal Facility Upgrades Intermodal Transfer Improvement
JAXPORT Master Plan
This project will provide gates and other facilities within the marine terminal to improve efficiencies and meet future demand.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
Jacksonville Port Authority Duval 2223 Talleyrand Marine Terminal Rail Internal Rail JAXPORT Master Plan
This project will provide on‐dock rail capacity at berths in the Blount Island marine terminal to improve efficiencies and meet future demand.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
80
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Jacksonville Port Authority Duval 2224 Blount Island Marine Terminal Facility Upgrades Intermodal Transfer Improvement
JAXPORT Master Plan
This project will provide gates and other facilities within the marine terminal to improve efficiencies and meet future demand.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
Jacksonville Port Authority Duval 2225 Dames Point Marine Terminal Facility Upgrades Intermodal Transfer Improvement
JAXPORT Master Plan
This project will provide gates and other facilities within the marine terminal to improve efficiencies and meet future demand.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
Jacksonville Port Authority Duval 2226 New Cranes for Talleyrand and Blount Island Marine Terminals Intermodal Transfer Improvement
JAXPORT Master Plan
This project will provide new cranes to meet future demand at the port.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
Jacksonville Port Authority Duval 2227 Talleyrand Marine Terminal Facility Upgrades Intermodal Transfer Improvement
JAXPORT Master Plan
This project will provide gates and other facilities within the marine terminal to improve efficiencies and meet future demand.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
Jacksonville Port Authority Duval 2228 Blount Island / Dames Point Terminals ‐ Rail and Bridge Internal Rail JAXPORT Master Plan
This project will provide on‐dock rail capacity at berths in the Blount Island marine terminal to improve efficiencies and meet future demand.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
81
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Jacksonville Port Authority Duval 2229 Blount Island Marine Terminal Berth Upgrades Docks JAXPORT Master Plan
This project will provide additional capacity at berths in the marine terminal to improve efficiencies and meet future demand.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
Jacksonville Port Authority Duval 2230 Blount Island Marine Terminal Facility Upgrades Intermodal Transfer Improvement
JAXPORT Master Plan
This project will provide gates and other facilities within the marine terminal to improve efficiencies and meet future demand.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
Jacksonville Port Authority Duval 2231 Dames Point Marine Terminal Berth Upgrades Docks JAXPORT Master Plan
This project will provide additional capacity at berths in the marine terminal to improve efficiencies and meet future demand.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
Jacksonville Port Authority Duval 2232 Dames Point Marine Terminal Facility Upgrades Intermodal Transfer Improvement
JAXPORT Master Plan
This project will provide gates and other facilities within the marine terminal to improve efficiencies and meet future demand.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
Jacksonville Port Authority Duval 2233 Harbor Deepening Dredging Harbor JAXPORT Master Plan
This project will deepen the St. Johns River main channel to 48‐ft to meet demand for post‐Panamax ships.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
82
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Jacksonville Port Authority Duval 2234 New Cranes for Talleyrand and Blount Island Marine Terminals Intermodal Transfer Improvement
JAXPORT Master Plan
This project will provide new cranes to meet future demand at the port.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
Jacksonville Port Authority Duval 2235 Talleyrand Marine Terminal Berth Upgrades Docks JAXPORT Master Plan
This project will provide additional capacity at berths in the marine terminal to improve efficiencies and meet future demand.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
Jacksonville Port Authority Duval 2236 Talleyrand Marine Terminal Facility Upgrades Intermodal Transfer Improvement
JAXPORT Master Plan
This project will provide gates and other facilities within the marine terminal to improve efficiencies and meet future demand.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
Jacksonville Port Authority Duval 2237 Talleyrand Marine Terminal Rail Internal Rail JAXPORT Master Plan
This project will provide on‐dock rail capacity at berths in the Blount Island marine terminal to improve efficiencies and meet future demand.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
CSX Transportation Duval/Baker 2238 MacClenny to Jacksonville Upgrade to Accommodate
Freight and Passenger Service* Blueprint 2020 This project will improve track capacity to accommodate future passenger rail and meet freight capacity needs.
The need for additional track capacity to accommodate freight and transit operations was identified in the SIS Multimodal Needs Plan and confirmed through the Blueprint 2020 and Commuter Rail feasibility studies.
83
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
CSX Transportation Duval/Clay 2239 Green Cove Springs to Jacksonville Upgrade to Accommodate Freight and Passenger Service Blueprint 2020
This project will improve track capacity to accommodate future passenger rail and meet freight capacity needs.
The need for additional track capacity to accommodate freight and transit operations was identified in the SIS Multimodal Needs Plan and confirmed through the Blueprint 2020 and Commuter Rail feasibility studies.
CSX Transportation Duval/Nassau 2240 Jacksonville to Yulee Upgrade to Accommodate Freight and Passenger Service Blueprint 2020
This project will improve track capacity to accommodate future passenger rail and meet freight capacity needs.
The need for additional track capacity to accommodate freight and transit operations was identified in the SIS Multimodal Needs Plan and confirmed through the Blueprint 2020 and Commuter Rail feasibility studies.
Florida East Coast Railway Duval/St. Johns 2241 St. Augustine to Jacksonville Upgrade to Accommodate Freight and Passenger Service Blueprint 2020
This project will improve track capacity to accommodate future passenger rail and meet freight capacity needs.
The need for additional track capacity to accommodate freight and transit operations was identified in the SIS Multimodal Needs Plan and confirmed through the Blueprint 2020 and Commuter Rail feasibility studies.
CSX Transportation Duval 2242 at US 301 SR 200 Baldwin Grade Separation This project's purpose is to construct a highway‐rail grade separation to improve safety and traffic flow.
The need for this project was identified through the SIS Multimodal Needs Planning process which included an analysis of the safety record and crossroad congestion.
CSX Transportation Nassau 2243 at US 301 Crawford Diamond Grade Separation This project's purpose is to construct a highway‐rail grade separation to improve safety and traffic flow.
The need for this project was identified through the SIS Multimodal Needs Planning process which included an analysis of the safety record and crossroad congestion. The need was confirmed as part of this planning process.
84
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Port of Fernandina Nassau 2244 Berth Improvements Docks Port Master Plan
This project will provide additional capacity at berths in the marine terminal to improve efficiencies and meet future demand.
The need for the project was defined during the development of the OHPA Master Plan. The need was confirmed as part of this planning process.
Port of Fernandina Nassau 2245 Cruise / Cargo Berth Docks Port Master Plan The project will construct new berths needed to accommodate cruise and larger cargo ships.
The need for the project was defined during the development of the OHPA Master Plan. The need was confirmed as part of this planning process.
Port of Fernandina Nassau 2246 Rail Track Improvements Internal Rail Port Master Plan This project will enhance near‐dock and on‐dock rail services.
The need for the project was defined during the development of the OHPA Master Plan. The need was confirmed as part of this planning process.
Port of Fernandina Nassau 2247 at Fernandina Port Access Improvements Port Master Plan
This project's purpose is to improve truck access to the port within the context of the historic district in Fernandina.
The need for the project was defined during the development of the OHPA Master Plan. The need was confirmed as part of this planning process.
City of Palatka Putnam 2248 SR 100 CR 309D Runway expansion SIS Multimodal Needs Plan
This project's purpose is to expand the runway.
The need for the project was defined during the development of airport master plan. The need was confirmed as part of this planning process.
85
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Nassau County Putnam 2249 Barge Port Operational and Capital Improvements
SIS Multimodal Needs Plan
This project's purpose is to construct capital improvements to improve the operations at the port.
The need for the project was defined during the development of airport master plan. The need was confirmed as part of this planning process.
CSX Transportation Putnam 2250 at SR 15 Reid Street Grade Separation SIS Multimodal Needs Plan
This project's purpose is to construct a highway‐rail grade separation to improve safety and traffic flow.
The need for this project was identified through the SIS Multimodal Needs Planning process which included an analysis of the safety record and crossroad congestion.
City of Saint Augustine St. Johns 2251 Historic Commercial Areas Mobility & Distribution Improvements
SIS Multimodal Needs Plan
This project's purpose is to develop strategies to improve parking management within the historic district of St. Augustine.
The need was identified by the City of St. Augustine. The need was confirmed as part of this planning process.
Florida East Coast Railway Statewide 2252 Amtrak Service Miami to Jacksonville New Passenger Service SIS Multimodal Needs Plan
This project will improve track capacity to accommodate future passenger rail and meet freight capacity needs.
The need was identified through the SIS Multimodal Needs Plan. The need was confirmed as part of this planning process.
Florida East Coast Railway Statewide 2253 Miami to Jacksonville Upgrade Bolt and Clip System Track Upgrade SIS Multimodal Needs Plan
This project will improve track capacity to accommodate future passenger rail and meet freight capacity needs.
The need was identified through the SIS Multimodal Needs Plan. The need was confirmed as part of this planning process.
86
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Intercity Passenger Rail Statewide 2254 New Orleans to Jacksonville New Passenger Service SIS Multimodal Needs Plan
This project will improve track capacity to accommodate future passenger rail and meet freight capacity needs.
The need was identified through the SIS Multimodal Needs Plan. The need was confirmed as part of this planning process.
Intercity Passenger Rail Statewide 2255 Jacksonville to Savannah New Passenger Service SIS Multimodal Needs Plan
This project will improve track capacity to accommodate future passenger rail and meet freight capacity needs.
The need was identified through the SIS Multimodal Needs Plan. The need was confirmed as part of this planning process.
Intercity Passenger Rail Statewide 2256 Orlando to Jacksonville New Passenger Service SIS Multimodal Needs Plan
This project will improve track capacity to accommodate future passenger rail and meet freight capacity needs.
The need was identified through the SIS Multimodal Needs Plan. The need was confirmed as part of this planning process.
Norfolk Southern Duval 2257 Soutel Drive to Norfolk Southern Intermodal Yard New Connector SIS Multimodal Needs Plan
This project will improve track capacity to accommodate future passenger rail and meet freight capacity needs.
The need was identified through the NS CSX SIS Connector study performed by FDOT to improve access and operations of the Norfolk Southern intermodal yard.
CSX Transportation Duval 2258 North Rail Corridors Phase 2 Multi Modal Corridor North Rail Corridor Feasibility Study
The purpose of this project is to consider extensions of the North Rail corridor and to construct a two‐lane roadway within the corridor right of way.
This need was identified through the freight capacity analysis performed in the LRTP to address future rail and truck access needs. The need was confirmed as part of this planning process.
87
Table 2. Project Purpose and Need Statements for Major Capacity Projects
Facility County Map ID From To Improvement Type Source Purpose Need
Florida East Coast Railway Duval 2259 at Sunbeam Road Grade Separation SIS Multimodal Needs Plan
This project's purpose is to construct a highway‐rail grade separation to improve safety and traffic flow.
The need for this project was identified through the SIS Multimodal Needs Planning process which included an analysis of the safety record and crossroad congestion. The need was confirmed as part of this planning process.
Downtown Transportation Center Duval 2355 Downtown Facility Transportation Center SIS Multimodal
Needs Plan
This project's purpose is to construct a downtown intermodal facility where multiple transit modes can be connected.
This project's need was identified in the 2035 LRTP and confirmed as part of the Blueprint 2020 plan to provide greater systems integration of the transit modes. The need was confirmed as part of this planning process.
Jacksonville Port Authority Duval 1006 Spoil Island Connector Bridge New 2 Lane Bridge
New need identified in the 2040 LRTP by JAXPORT.
This project's purpose is to construct a new bridge for the management and distribution of spoil material associated with dredging the St. Johns River.
The need for this project was identified by JAXPORT as an opportunity to better manage spoil and reduce environmental impacts.
Florida East Coast Railway Duval 2260 at Shad Road Grade Separation New need identified in the 2040 LRTP.
This project's purpose is to construct a highway‐rail grade separation to improve safety and traffic flow.
The need for this project was identified through a process which included an analysis of the safety record and crossroad congestion.
Intermodal Logistics Center Intermodal Logistics Center New capacity
New need identified in the 2040 LRTP.
This project's purpose is to construct an intermodal logistics center in North Florida to improve rail efficiencies and the interchange of intermodal traffic between railroads and over the road trucking.
The need for this project was identified as part of the rail system capacity analysis performed during the planning process.
This page is intentionally blank.