20th International Conference on Electricity Distribution Prague, 8 – 11 June 2009 SVC Refurbishment Experience for Critical Coal Train Haulage Network OBJECTIVES Refurbishment of 10 SVCs for voltage support in a traction supply network Apply latest available well-proven technology Session 3 – Paper 0611 Authors Tuan VU Principal Consultant Powerlink Queensland, Australia, Anthony JOHNSON Marketing Manager Siemens Ltd., Australia APPROACH Installation and operation of a mobile SVC system during refurbishment works 48hr cut-in period and 48hr cut-out period for the mobile SVC providing minimum down-time for each substation RESULTS Security of the transportation system Minimization of SVC outage times during the transition phase Very fast re-energization of the existing SVC components Maximal reliability with minimal maintenance Improvement in network security
Transcript
Page 1: 20th International Conference on Electricity Distribution · PDF file · 2009-07-29down-time for each substation ... 132 kV AC Line Siemens is an Expert in Refurbishment of ... Microsoft

20th International Conference on Electricity DistributionPrague, 8 – 11 June 2009

SVC Refurbishment Experience for Critical Coal Train Haulage Network

OBJECTIVES• Refurbishment of 10 SVCs for

voltage support in a traction supply network

• Apply latest available well-proven technology

Session 3 – Paper 0611

AuthorsTuan VU Principal Consultant Powerlink Queensland, Australia,Anthony JOHNSON Marketing Manager Siemens Ltd., Australia

APPROACHInstallation and operation of a mobile SVC system during refurbishment works

48hr cut-in period and 48hr cut-out period for the mobile SVC providing minimum down-time for each substation

RESULTS• Security of the transportation system• Minimization of SVC outage times

during the transition phase• Very fast re-energization of the

existing SVC components• Maximal reliability with minimal

maintenance • Improvement in network security

Page 2: 20th International Conference on Electricity Distribution · PDF file · 2009-07-29down-time for each substation ... 132 kV AC Line Siemens is an Expert in Refurbishment of ... Microsoft

1 04-2009 Power Transmission DivisionE T PS SL/Re

Powerlink – Australia, Refurbishment of 10 SVCs for Voltage Support in a Traction Supply Network

Oonooie SVC

Grantleigh SVC

Mining CoalCoal Mining

Coal Hauling

Examples

Security of Transportation Systems

Page 3: 20th International Conference on Electricity Distribution · PDF file · 2009-07-29down-time for each substation ... 132 kV AC Line Siemens is an Expert in Refurbishment of ... Microsoft

2 04-2009 Power Transmission DivisionE T PS SL/Re

Powerlink – Australia, Refurbishment of 10 SVCs for Voltage Support in a Traction Supply Network

2007

9 SVCs with Advanced 48 hrs containerized Solution1 SVC with Standard Refurbishment Solution

Railway Line

275 kV AC Line132 kV AC Line

Siemens is an Expert in Refurbishment of Valves & Controls

Page 4: 20th International Conference on Electricity Distribution · PDF file · 2009-07-29down-time for each substation ... 132 kV AC Line Siemens is an Expert in Refurbishment of ... Microsoft

3 04-2009 Power Transmission DivisionE T PS SL/Re

Summary of the 9 QR SVCs – with the Advanced 48 hrs containerized Solution …

The Solution: a flexible, containerized QR Control & Protection System – fully matching 9 different SVC Configurations

… including Features for Unbalance Control

3 PTD

Page 5: 20th International Conference on Electricity Distribution · PDF file · 2009-07-29down-time for each substation ... 132 kV AC Line Siemens is an Expert in Refurbishment of ... Microsoft

4 04-2009 Power Transmission DivisionE T PS SL/Re

Summary of Nebo SVC with Standard Refurbishment Solution – and Requirements to all SVCs

Control System Requirements:

Refurbishment of:TCR/TSC Converter Valves

Control & Protection Systems – including all InterfacesConverter Cooling System

Control of Negative Sequence Voltage – Priority 1 *Control of Positive Sequence Voltage – Priority 2 *

* for QR SVCs

4 Power Transmission DivisionE T PS SL/Re04-2009

Page 6: 20th International Conference on Electricity Distribution · PDF file · 2009-07-29down-time for each substation ... 132 kV AC Line Siemens is an Expert in Refurbishment of ... Microsoft

5 04-2009 Power Transmission DivisionE T PS SL/Re

9 QR SVCs – with the Advanced 48 hrs containerized Solution

A unique Solution – for very fast Re-Energization of the existing SVC Components (Transformers, Reactors, Capacitors, Filters etc.

Page 7: 20th International Conference on Electricity Distribution · PDF file · 2009-07-29down-time for each substation ... 132 kV AC Line Siemens is an Expert in Refurbishment of ... Microsoft

6 04-2009 Power Transmission DivisionE T PS SL/Re

All-in-one Container:Valves & Cooling, Auxiliaries,Protection and Control

9 QR SVCs – The Advanced 48 hrs containerized Solution

Page 8: 20th International Conference on Electricity Distribution · PDF file · 2009-07-29down-time for each substation ... 132 kV AC Line Siemens is an Expert in Refurbishment of ... Microsoft

7 04-2009 Power Transmission DivisionE T PS SL/Re

9 QR SVCs – Benefits of the Advanced 48 hrs containerized Solution

Easy to connect:

From “Inside”to “Outside”

Page 9: 20th International Conference on Electricity Distribution · PDF file · 2009-07-29down-time for each substation ... 132 kV AC Line Siemens is an Expert in Refurbishment of ... Microsoft

8 04-2009 Power Transmission DivisionE T PS SL/Re

9 QR SVCs – the Advanced 48 hrs containerized Solution

Examples of Cable Crossbonding:Highly important

Page 10: 20th International Conference on Electricity Distribution · PDF file · 2009-07-29down-time for each substation ... 132 kV AC Line Siemens is an Expert in Refurbishment of ... Microsoft

9 04-2009 Power Transmission DivisionE T PS SL/Re

After 48 hrs – Step 1 finished and all SVC Functions available

Work is done –and the SVC operates properly

Step 2:

4 Weeks for full Refurbishment of Valves, Controls & Protection in the SVC Building

Step 3:

48 hrs for Disconnection of SVC Container and Energization of the fully refurbished QR SVC

Container ready fornext QR SVC Plant

Excellent Workof a great Team