Date post: | 25-Mar-2018 |
Category: |
Documents |
Upload: | nguyentram |
View: | 212 times |
Download: | 0 times |
20th International Conference on Electricity DistributionPrague, 8 – 11 June 2009
SVC Refurbishment Experience for Critical Coal Train Haulage Network
OBJECTIVES• Refurbishment of 10 SVCs for
voltage support in a traction supply network
• Apply latest available well-proven technology
Session 3 – Paper 0611
AuthorsTuan VU Principal Consultant Powerlink Queensland, Australia,Anthony JOHNSON Marketing Manager Siemens Ltd., Australia
APPROACHInstallation and operation of a mobile SVC system during refurbishment works
48hr cut-in period and 48hr cut-out period for the mobile SVC providing minimum down-time for each substation
RESULTS• Security of the transportation system• Minimization of SVC outage times
during the transition phase• Very fast re-energization of the
existing SVC components• Maximal reliability with minimal
maintenance • Improvement in network security
1 04-2009 Power Transmission DivisionE T PS SL/Re
Powerlink – Australia, Refurbishment of 10 SVCs for Voltage Support in a Traction Supply Network
Oonooie SVC
Grantleigh SVC
Mining CoalCoal Mining
Coal Hauling
Examples
Security of Transportation Systems
2 04-2009 Power Transmission DivisionE T PS SL/Re
Powerlink – Australia, Refurbishment of 10 SVCs for Voltage Support in a Traction Supply Network
2007
9 SVCs with Advanced 48 hrs containerized Solution1 SVC with Standard Refurbishment Solution
Railway Line
275 kV AC Line132 kV AC Line
Siemens is an Expert in Refurbishment of Valves & Controls
3 04-2009 Power Transmission DivisionE T PS SL/Re
Summary of the 9 QR SVCs – with the Advanced 48 hrs containerized Solution …
The Solution: a flexible, containerized QR Control & Protection System – fully matching 9 different SVC Configurations
… including Features for Unbalance Control
3 PTD
4 04-2009 Power Transmission DivisionE T PS SL/Re
Summary of Nebo SVC with Standard Refurbishment Solution – and Requirements to all SVCs
Control System Requirements:
Refurbishment of:TCR/TSC Converter Valves
Control & Protection Systems – including all InterfacesConverter Cooling System
Control of Negative Sequence Voltage – Priority 1 *Control of Positive Sequence Voltage – Priority 2 *
* for QR SVCs
4 Power Transmission DivisionE T PS SL/Re04-2009
5 04-2009 Power Transmission DivisionE T PS SL/Re
9 QR SVCs – with the Advanced 48 hrs containerized Solution
A unique Solution – for very fast Re-Energization of the existing SVC Components (Transformers, Reactors, Capacitors, Filters etc.
6 04-2009 Power Transmission DivisionE T PS SL/Re
All-in-one Container:Valves & Cooling, Auxiliaries,Protection and Control
9 QR SVCs – The Advanced 48 hrs containerized Solution
7 04-2009 Power Transmission DivisionE T PS SL/Re
9 QR SVCs – Benefits of the Advanced 48 hrs containerized Solution
Easy to connect:
From “Inside”to “Outside”
8 04-2009 Power Transmission DivisionE T PS SL/Re
9 QR SVCs – the Advanced 48 hrs containerized Solution
Examples of Cable Crossbonding:Highly important
9 04-2009 Power Transmission DivisionE T PS SL/Re
After 48 hrs – Step 1 finished and all SVC Functions available
Work is done –and the SVC operates properly
Step 2:
4 Weeks for full Refurbishment of Valves, Controls & Protection in the SVC Building
Step 3:
48 hrs for Disconnection of SVC Container and Energization of the fully refurbished QR SVC
Container ready fornext QR SVC Plant
Excellent Workof a great Team