Date post: | 22-Dec-2015 |
Category: |
Documents |
Upload: | milton-davidson |
View: | 212 times |
Download: | 0 times |
21–2
Material Requirements Planning
Chapter Twenty-One
Copyright © 2014 by The McGraw-Hill Companies, Inc. All rights reserved.McGraw-Hill/Irwin
21–3
Cop
yri
gh
t ©
20
14
by M
cGra
w H
ill E
du
cati
on
(In
dia
) Pri
vate
Lim
ited
. A
ll ri
gh
ts
rese
rved
.
Learning Objectives
• LO21–1: Explain what material requirements planning (MRP) is.
• LO21–2: Understand how the MRP system is structured.
• LO21–3: Analyze an MRP problem.
• LO21–4: Evaluate and compare MRP lot-sizing techniques.
21–4
Cop
yri
gh
t ©
20
14
by M
cGra
w H
ill E
du
cati
on
(In
dia
) Pri
vate
Lim
ited
. A
ll ri
gh
ts
rese
rved
.
Enterprise Resource Planning (ERP) and
Material Requirements Planning (MRP)
ERP – a computer
system that integrates application programs in accounting,
sales, manufacturin
g, and the other
functions in a firm
MRP – a means for
determining the number
of parts, components,
and materials needed to produce a product
21–5
Cop
yri
gh
t ©
20
14
by M
cGra
w H
ill E
du
cati
on
(In
dia
) Pri
vate
Lim
ited
. A
ll ri
gh
ts
rese
rved
.
Material Requirements Planning (MRP)
• The logic that ties production functions together from a material planning and control view
• A logical, easily understood approach to the problem of managing the parts, components, and materials needed to produce end items
– How much of each part to obtain?
– When to order or produce the parts?
• Dependent demand drives the MPR system
21–6
Cop
yri
gh
t ©
20
14
by M
cGra
w H
ill E
du
cati
on
(In
dia
) Pri
vate
Lim
ited
. A
ll ri
gh
ts
rese
rved
.MRP Applications and Benefits
21–7
Cop
yri
gh
t ©
20
14
by M
cGra
w H
ill E
du
cati
on
(In
dia
) Pri
vate
Lim
ited
. A
ll ri
gh
ts
rese
rved
.Master Production Scheduling
• The master schedule deals with end items and is a major input to the MRP process.
• All production systems have limited capacity and limited resources.– The aggregate plan provides the general range of
operation; the master scheduler must specify exactly what is to be produced.
• To determine an acceptable feasible schedule to be released to the shop, trial master production schedules are tested using the MRP program.
21–8
Cop
yri
gh
t ©
20
14
by M
cGra
w H
ill E
du
cati
on
(In
dia
) Pri
vate
Lim
ited
. A
ll ri
gh
ts
rese
rved
.Master Production Scheduling
Week
Aggregate plan shows overall quantities to produce – without specifying type.
MPS shows quantities of each type, with information about the production time frame.
21–9
Cop
yri
gh
t ©
20
14
by M
cGra
w H
ill E
du
cati
on
(In
dia
) Pri
vate
Lim
ited
. A
ll ri
gh
ts
rese
rved
.
Time Fences
21–10
Cop
yri
gh
t ©
20
14
by M
cGra
w H
ill E
du
cati
on
(In
dia
) Pri
vate
Lim
ited
. A
ll ri
gh
ts
rese
rved
.
MRP System Structure
MRP system inputs
MRP system outputs
21–11
Cop
yri
gh
t ©
20
14
by M
cGra
w H
ill E
du
cati
on
(In
dia
) Pri
vate
Lim
ited
. A
ll ri
gh
ts
rese
rved
.Product Demand Sources
• Customers – specific orders placed by either external or internal customers
• Aggregate production plan – the firm’s strategy for meeting demand in the future, implemented through the master production schedule (MPS)
21–12
Cop
yri
gh
t ©
20
14
by M
cGra
w H
ill E
du
cati
on
(In
dia
) Pri
vate
Lim
ited
. A
ll ri
gh
ts
rese
rved
.
Bill of Materials (BOM)Contains the complete product
description, listing the materials, parts, and
components along with the sequence in which the product
is created.
Often called the product structure file or product tree
because it shows how a product is put together.
Modular bill of materials is a buildable item that can be produced and stocked as a
subassembly.
Super bill of materials includes items with fractional options.
The BOM shows how the product is put together.
21–13
Cop
yri
gh
t ©
20
14
by M
cGra
w H
ill E
du
cati
on
(In
dia
) Pri
vate
Lim
ited
. A
ll ri
gh
ts
rese
rved
.
BOM ExampleProduct A – the end item
Product A consists of 2 B and 3 C
Product C consists of 2 F, 5 G, and 4 H
Product B consists of 1 D and 4 E
21–14
Cop
yri
gh
t ©
20
14
by M
cGra
w H
ill E
du
cati
on
(In
dia
) Pri
vate
Lim
ited
. A
ll ri
gh
ts
rese
rved
.Alternate BOM Structures
21–15
Cop
yri
gh
t ©
20
14
by M
cGra
w H
ill E
du
cati
on
(In
dia
) Pri
vate
Lim
ited
. A
ll ri
gh
ts
rese
rved
.BOM Hierarchy (Levels)
Higher levels (Iower numbers) refer to end products.
Lower levels (higher numbers) refer to components and raw materials.
21–16
Cop
yri
gh
t ©
20
14
by M
cGra
w H
ill E
du
cati
on
(In
dia
) Pri
vate
Lim
ited
. A
ll ri
gh
ts
rese
rved
.Inventory Status Records
Information about part availability
Additional information that may be useful
Basic information describing the item
21–17
Cop
yri
gh
t ©
20
14
by M
cGra
w H
ill E
du
cati
on
(In
dia
) Pri
vate
Lim
ited
. A
ll ri
gh
ts
rese
rved
.
MRP Explosion ProcessThe requirements for end items are retrieved from the master schedule.• These are referred to as “gross requirements” by the MRP
program.
On-hand balance and schedule of orders are used to calculate the “net requirement.”
Net requirements data are used to calculate when orders should be received to meet these requirements.
Planned order releases are generated by offsetting to allow for lead time.
21–18
Cop
yri
gh
t ©
20
14
by M
cGra
w H
ill E
du
cati
on
(In
dia
) Pri
vate
Lim
ited
. A
ll ri
gh
ts
rese
rved
.
MRP Explosion Process (Continued)
Move to level 1 items.
Gross requirements for each level 1 item are calculated from the planned-order release schedule for the parents of each level 1 item.
Net requirements, planned-order receipts, and planned-order releases are calculated as described in steps 2–4.
Repeat for all items in bill of materials.
21–19
Cop
yri
gh
t ©
20
14
by M
cGra
w H
ill E
du
cati
on
(In
dia
) Pri
vate
Lim
ited
. A
ll ri
gh
ts
rese
rved
.MRP Example – Ampere, Inc.
• Ampere, Inc., produces a line of electric meters installed in residential buildings.
• Meters are of two basic types for different voltage and amperage ranges.– Some subassemblies are sold separately for repair or for
changeovers.
• The problem is to determine a production schedule to identify each item, the period it is needed, and the appropriate quantities.
• The schedule is then checked for feasibility, and the schedule is modified if necessary.
21–20
Cop
yri
gh
t ©
20
14
by M
cGra
w H
ill E
du
cati
on
(In
dia
) Pri
vate
Lim
ited
. A
ll ri
gh
ts
rese
rved
.Future Requirements – Meters A and B and Subassembly D
Assume that required quantity must be available during week 1 of each month.
Trial Master Schedule
21–21
Cop
yri
gh
t ©
20
14
by M
cGra
w H
ill E
du
cati
on
(In
dia
) Pri
vate
Lim
ited
. A
ll ri
gh
ts
rese
rved
.
Product Structure and Inventory Data
21–22
Cop
yri
gh
t ©
20
14
by M
cGra
w H
ill E
du
cati
on
(In
dia
) Pri
vate
Lim
ited
. A
ll ri
gh
ts
rese
rved
.MRP Planning Schedule
21–23
Cop
yri
gh
t ©
20
14
by M
cGra
w H
ill E
du
cati
on
(In
dia
) Pri
vate
Lim
ited
. A
ll ri
gh
ts
rese
rved
.
Example 21.1
21–24
Cop
yri
gh
t ©
20
14
by M
cGra
w H
ill E
du
cati
on
(In
dia
) Pri
vate
Lim
ited
. A
ll ri
gh
ts
rese
rved
.
Example 21.1
Without an order here, inventory will drop below the safety stock.To accommodate the lead
time, orders must be released ahead of time.
21–25
Cop
yri
gh
t ©
20
14
by M
cGra
w H
ill E
du
cati
on
(In
dia
) Pri
vate
Lim
ited
. A
ll ri
gh
ts
rese
rved
.
Example 21.1
Without an order here, inventory will drop below the safety stock.To accommodate the lead
time, orders must be released ahead of time.
21–26
Cop
yri
gh
t ©
20
14
by M
cGra
w H
ill E
du
cati
on
(In
dia
) Pri
vate
Lim
ited
. A
ll ri
gh
ts
rese
rved
.
Example 21.1Total demand from planned order releases of parent items
Planned order release offset by 3 periods due to lead time
21–27
Cop
yri
gh
t ©
20
14
by M
cGra
w H
ill E
du
cati
on
(In
dia
) Pri
vate
Lim
ited
. A
ll ri
gh
ts
rese
rved
.Lot Sizing in MRP Systems
• Determination of lot sizes in an MRP system is a complicated and difficult problem.
• Lot sizes – the part quantities issued in the planned order receipt and planned order release sections of an MRP schedule
Lot-for-lot (L4L)Economic order quantity (EOQ)
Least total cost (LTC)
Least unit cost (LUC)
Lot Sizing
Strategies
21–28
Cop
yri
gh
t ©
20
14
by M
cGra
w H
ill E
du
cati
on
(In
dia
) Pri
vate
Lim
ited
. A
ll ri
gh
ts
rese
rved
.
Lot-for-Lot
Sets planned orders to exactly
match the net requirements.
Produces exactly what is needed each week with
none carried over into future periods.
Minimizes carrying cost.
Does not take into account setup
costs or capacity limitations.
21–29
Cop
yri
gh
t ©
20
14
by M
cGra
w H
ill E
du
cati
on
(In
dia
) Pri
vate
Lim
ited
. A
ll ri
gh
ts
rese
rved
.Economic Order Quantity
Calculate reorder quantity based on
EOQ.
EOQ was not designed for a system with discrete time
periods such as MRP.
The lot sizes generated by EOQ
do not always cover the entire
number of periods.
21–30
Cop
yri
gh
t ©
20
14
by M
cGra
w H
ill E
du
cati
on
(In
dia
) Pri
vate
Lim
ited
. A
ll ri
gh
ts
rese
rved
.
Comparison – Lot-for-Lot and EOQ
EOQ
Lot-for-Lot
21–31
Cop
yri
gh
t ©
20
14
by M
cGra
w H
ill E
du
cati
on
(In
dia
) Pri
vate
Lim
ited
. A
ll ri
gh
ts
rese
rved
.
Least Total Cost
• Least total cost method (LTC) – a dynamic lot-sizing technique that calculates the order quantity by comparing the carrying cost and the setup costs for various lot sizes and then selects the lot in which these are most nearly equal
• Influenced by the length of the planning horizon
21–32
Cop
yri
gh
t ©
20
14
by M
cGra
w H
ill E
du
cati
on
(In
dia
) Pri
vate
Lim
ited
. A
ll ri
gh
ts
rese
rved
.
Least Total Cost
21–33
Cop
yri
gh
t ©
20
14
by M
cGra
w H
ill E
du
cati
on
(In
dia
) Pri
vate
Lim
ited
. A
ll ri
gh
ts
rese
rved
.
Least Unit Cost
• Least unit cost method – a dynamic lot-sizing technique that adds ordering and inventory carrying cost for each trial lot size and divides by the number of units in each lot size, picking the lot size with the lowest unit cost