[23/1-19/2] MOM report. Zisman. Apollonio. 23/1/09. 19/2/09. 12/2/09. Relevant Issues: NO target since december accident  no data taking  we have 80 days (to ISIS startup) Try to turn a failure into an opportunity?. Hogdson. A pretty dense schedule! - PowerPoint PPT Presentation
Popular Tags:
5
MICE VC 12/2/2009 1 [23/1-19/2] MOM report Hogdson Apollonio Zisman 23/1/09 12/2/09 19/2/09 Relevant Issues: - NO target since december accident no data taking we have 80 days (to ISIS startup) Try to turn a failure into an opportunity?
Transcript
Page 1: [23/1-19/2]      MOM report

MICE VC 12/2/2009 1

[23/1-19/2] MOM report

Hogdson Apollonio

Zisman

23/1/0912/2/09

19/2/09

Relevant Issues:- NO target since december accident no data taking we have 80 days (to ISIS startup)

Try to turn a failure into an opportunity?

Page 2: [23/1-19/2]      MOM report

MICE VC 12/2/2009 2

A pretty dense schedule!

- target re-design (J. Tarrant, this VC)- fixing the solenoid (M. Courthold et al., this VC) - levelling the floor downstream Q9 - minor issues

Page 3: [23/1-19/2]      MOM report

MICE VC 12/2/2009 3

12/2/09 - DKsol vacuum done- Cooling down now

10xMLI sheets on DS end placed

Pumpvacuum

Cool down

DSA Accessible!11/2/09

DKsol readyNB: only 4 days fromISIS startup!

(see M.C. talk for further details)

MLI sheets on US end: need Beam shield removal!

Page 4: [23/1-19/2]      MOM report

MICE VC 12/2/2009 4

Floor levelling

- floor DS of Q9 is not sufficiently flat- unevenness up to 2cm reported (T. Hayler)- a complete survey + levelling of the area is

needed prior to laying down the floor aluminium plate

- this (unfortunately) requires TOF1/KL to be temporarily moved

- TOF1/KL planned to be back on time for the next Data Taking

- Complete plan for un-cabling/move has been discussed with detector responsibles (M.Bonesini/L.Tortora)

- Experts from Milan/Rome on their way (18/2) to assist with operations (in particular KL horizontalisation)

- At the moment KL/TOF cables have been properly marked and de-cabled

Page 5: [23/1-19/2]      MOM report

MICE VC 12/2/2009 5

Two minor issues

Small leak noticed on Q7: mirror plates removed & being investigated (Spensley)

M. Bonesini requested some PMTs (from TOF0) back to Milan for test/repair. Cosmic Bar to be removedShould be easier now (DSA free access)