MICE VC 12/2/2009 1
[23/1-19/2] MOM report
Hogdson Apollonio
Zisman
23/1/0912/2/09
19/2/09
Relevant Issues:- NO target since december accident no data taking we have 80 days (to ISIS startup)
Try to turn a failure into an opportunity?
MICE VC 12/2/2009 2
A pretty dense schedule!
- target re-design (J. Tarrant, this VC)- fixing the solenoid (M. Courthold et al., this VC) - levelling the floor downstream Q9 - minor issues
MICE VC 12/2/2009 3
12/2/09 - DKsol vacuum done- Cooling down now
10xMLI sheets on DS end placed
Pumpvacuum
Cool down
DSA Accessible!11/2/09
DKsol readyNB: only 4 days fromISIS startup!
(see M.C. talk for further details)
MLI sheets on US end: need Beam shield removal!
MICE VC 12/2/2009 4
Floor levelling
- floor DS of Q9 is not sufficiently flat- unevenness up to 2cm reported (T. Hayler)- a complete survey + levelling of the area is
needed prior to laying down the floor aluminium plate
- this (unfortunately) requires TOF1/KL to be temporarily moved
- TOF1/KL planned to be back on time for the next Data Taking
- Complete plan for un-cabling/move has been discussed with detector responsibles (M.Bonesini/L.Tortora)
- Experts from Milan/Rome on their way (18/2) to assist with operations (in particular KL horizontalisation)
- At the moment KL/TOF cables have been properly marked and de-cabled
MICE VC 12/2/2009 5
Two minor issues
Small leak noticed on Q7: mirror plates removed & being investigated (Spensley)
M. Bonesini requested some PMTs (from TOF0) back to Milan for test/repair. Cosmic Bar to be removedShould be easier now (DSA free access)