+ All Categories
Home > Documents > 24 m Span Pre Stressed Bridge

24 m Span Pre Stressed Bridge

Date post: 23-Nov-2014
Category:
Upload: kathir1956
View: 648 times
Download: 8 times
Share this document with a friend
152
Prestressed Concrete Since concrete is weak in tension in normal reinforced concrete construction c Prestressing involves inducing compressive stresses in the zone which will ten The prestressing force has to be produced by a high tensile steel, and it is n There are two methods of prestressing concrete : 1) Pre-cast Pre-tensioned 2) Pre-cast Post-tensioned Stage 1 Tendons and reinforcement are positioned in the beam mould. Stage 2 Tendons are stressed to about 70% of their ultimate strength. Stage 3 Concrete is cast into the beam mould and allowed to cure to the required initi Stage 4 When the concrete has cured the stressing force is released and the tendons an Stage 1 Cable ducts and reinforcement are positioned in the beam mould. The ducts are Stage 2 Concrete is cast into the beam mould and allowed to cure to the required initi Stage 3 Tendons are threaded through the cable ducts and tensioned to about 70% of the Stage 4 Wedges are inserted into the end anchorages and the tensioning force on the te Loss of Prestress When the tensioning force is released and the tendons are anchored to the conc a. relaxation of the steel tendons b. elastic deformation of the concrete c. shrinkage and creep of the concrete d. slip or movement of the tendons at the anchorages during anchoring e. other causes in special circumstances , such as when steam curing is used Total losses in prestress can amount to about 30% of the initial tensioning st Prestressed Concrete Beam Design to BS 5400 Part 4 Problem: The prestressing force also reduces the magnitude of the principal tensile str Both methods involve tensioning cables inside a concrete beam and then anchori 1) Pre-tensioned Beams 2) Post-tensioned Beams Design a simply supported prestressed concrete Y beam which carries a 150mm t γconc. = 24kN/mm 3
Transcript
Page 1: 24 m Span Pre Stressed Bridge

Prestressed Concrete

Since concrete is weak in tension in normal reinforced concrete construction cracks develop in the tension zone at working loads and therefore all concrete in tension is ignored in design.Prestressing involves inducing compressive stresses in the zone which will tend to become tensile under external loads. This compressive stress neutralizes the tensile stress so that no resultant tension exists, (or only very small values, within the tensile strength of the concrete). Cracking is therefore eliminated under working load and all of the concrete may be assumed effective in carrying load. Therefore lighter sections may be used to carry a given bending moment, and prestressed concrete may be used over much longer spans than reinforced concrete.

The prestressing force has to be produced by a high tensile steel, and it is necessary to use high quality concrete to resist the higher compressive stresses that are developed.There are two methods of prestressing concrete :1) Pre-cast Pre-tensioned2) Pre-cast Post-tensioned

Stage 1Tendons and reinforcement are positioned in the beam mould.Stage 2Tendons are stressed to about 70% of their ultimate strength.Stage 3Concrete is cast into the beam mould and allowed to cure to the required initial strength.Stage 4When the concrete has cured the stressing force is released and the tendons anchor themselves in the concrete.

Stage 1Cable ducts and reinforcement are positioned in the beam mould. The ducts are usually raised towards the neutral axis at the ends to reduce the eccentricity of the stressing force.Stage 2Concrete is cast into the beam mould and allowed to cure to the required initial strength.Stage 3Tendons are threaded through the cable ducts and tensioned to about 70% of their ultimate strength.Stage 4Wedges are inserted into the end anchorages and the tensioning force on the tendons is released. Grout is then pumped into the ducts to protect the tendons.

Loss of PrestressWhen the tensioning force is released and the tendons are anchored to the concrete a series of effects result in a loss of stress in the tendons. The effects are:

a. relaxation of the steel tendonsb. elastic deformation of the concretec. shrinkage and creep of the concreted. slip or movement of the tendons at the anchorages during anchoringe. other causes in special circumstances , such as when steam curing is used with pre-tensioning.

Total losses in prestress can amount to about 30% of the initial tensioning stress.

Prestressed Concrete Beam Design to BS 5400 Part 4

Problem:

The prestressing force also reduces the magnitude of the principal tensile stress in the web so that thin-webbed 

Both methods involve tensioning cables inside a concrete beam and then anchoring the stressed cables to the concrete. 

1) Pre-tensioned Beams 

2) Post-tensioned Beams 

Design a simply supported prestressed concrete Y beam which  carries a 150mm thick concrete slab and 100mm of surfacing, together with a nominal live load udl of 10.0 kN/m2 and kel of 33kN/m . The span of the beam is 24.0m centre to centre of bearings and the beams are spaced at 1.0m intervals.

γconc. = 24kN/mm3

Page 2: 24 m Span Pre Stressed Bridge

25 units of HB to be considered at SLS for load combination 1 only (BS 5400 Pt4 Cl. 4.2.2)

Nominal Dead Loads : slab = 24 x 0.15 x 1.0 = 3.6 kN/m

beam = say Y5 beam = 10.78 kN/m

surfacing = 24 x 0.1= 2.4 kN/m

Nominal Live Load : HA = 10 x 1.0 + 33.0 = 10 kN/m + 33kN

25 units HB = 25 x = 62.5 kN per wheel

Load factors for serviceability and ultimate limit state from BS 5400 Part 2 (or BD 37/01) Table 1:

SLS

Comb.1 Comb.3

Dead Load 1.0 1.15 1.15

Superimposed Dead Load 1.2 1.75 1.75

Live Load 1.2 1.0 1.5

1.1 -

Temperature Difference - 0.8 - 1.0

BS 5400 Pt. 4

Section Properties

cl.7.4.1 Modular ratio effect for different concrete strengths between beam and slab may be ignored.

Property Beam Section Composite Section

Loading per beam (at 1.0m c/c)

γfL concrete1.0

γfL surfacing1.2

γfL HA

γfL HB

γfL

Concrete Grades 

Beam   fcu = 50 N/mm2, 

fci = 40 N/mm2 

Slab    fcu = 40 N/mm2

Page 3: 24 m Span Pre Stressed Bridge

### ###

Centroid(mm) 456 623

### ###

### ###

### ###

Modulus @ Level 3(mm3) - ###

Temperature Difference Effects

Apply temperature differences given in BS 5400 Pt2 Fig.9 (Group 4)to a simplified beam section.

Force F to restrain temperature strain :

Moment M about centroid of section to restrain curvature due to temperature strain :

Force F to restrain temperature strain :

Moment M about centroid of section to restrain curvature due to temperature strain :

= - 194.5 - 0.6 + 153.8 = - 41.3 kNm

Area(mm2)

2nd Moment of Area(mm4)

Modulus @ Level 1(mm3)

Modulus @ Level 2(mm3)

Cl. 5.4.6 - Coefficient of thermal expansion = 12 x 10-6 per ºC.

From BS 5400 Pt4 Table 3 : Ec = 34 kN/mm2 for fcu = 50N/mm2 

Hence restrained temperature stresses per °C = 34 x 103 x 12 x 10-6 = 0.408 N/mm2

  

a) Positive temperature difference 

0.408 x 1000 x [ 150 x ( 3.0 + 5.25 ) ] x 10-3 +

0.408 x ( 300 x 250 x 1.5 + 750 x 200 x 1.25 ) x 10-3 = 504.9 + 122.4 = 627.3 kN

0.408 x 1000 x [ 150 x ( 3.0 x 502 + 5.25 x 527 ) ] x 10-6 +

0.408 x ( 300 x 250 x 1.5 x 344 - 750 x 200 x 1.25 x 556 ) x 10-6 = 261.5 - 26.7 = 234.8 kNm

b) Reverse temperature difference

- 0.408 x [ 1000 x 150 x ( 3.6 + 2.3 ) + 300 x 90 x ( 0.9 + 1.35 ) ] x 10-3 

- 0.408 x 300 x ( 200 x 0.45 + 150 x 0.45 ) x 10-3 

- 0.408 x 750 x [ 50 x ( 0.9 + 0.15 ) + 240 x ( 1.2 + 2.6 ) ] x 10-3 = - 385.9 - 19.3 - 295.1 = - 700.3 kN

- 0.408 x [ 150000 x ( 3.6 x 502 + 2.3 x 527 ) + 27000 x ( 0.9 x 382 + 1.35 x 397 ) ] x 10-6 

- 0.408 x 300 x ( 200 x 0.45 x 270 - 150 x 0.45 x 283 ) x 10-6 

+ 0.408 x 750 x [ 50 x ( 0.9 x 358 + 0.15 x 366 ) + 240 x ( 1.2 x 503 + 2.6 x 543 ) ] x 10-6 

Page 4: 24 m Span Pre Stressed Bridge

Differential Shrinkage Effects

BS 5400 Pt.4 Use cl.6.7.2.4 Table 29 :

cl.7.4.3.4

BS 5400 Pt.4

cl.7.4.3.5

Self weight of beam and weight of deck slab is supported by the beam. When the deck slab concrete has cured then any further loading (superimposed and live loads) is supported by the composite section of the beam and slab.

Total load for serviceability limit state = (1.0 x 3.6)+(1.0 x 10.78) = 14.4kN/m

Combination 1 Loading

Super. & HA live load for

Super. & HB live load for

Total load for ultimate limi

Total shrinkage of insitu concrete = 300 x 10-6

Assume that 2/3 of the total shrinkage of the precast concrete takes place before the deck slab is cast and that the residual shrinkage is 100 x 10-6 ,

hence the differential shrinkage is 200 x 10-6

Force to restrain differential shrinkage : F = - εdiff x Ecf x Acf x φ 

F = -200 x 10-6 x 34 x 1000 x 150 x 0.43 = -439 kN

Eccentricity acent = 502mm

Restraint moment Mcs = -439 x 0.502 = -220.4 kNm

Dead Loading (beam and slab)

Design serviceability moment = 14.4 x 242 / 8 = 1037 kNm

= [(1.2 x 2.4)+(1.2 x 10)]udl & [(1.2 x 33)]kel

= (2.88 + 12.0)udl & 39.6kel

= 14.9 kN/m & 39.6kN

=  2.88 & 4 wheels @ 1.1 x 62.5

= 2.9 kN/m & 4 wheels @ 68.75 kN

=  [(1.15 x 3.6)+(1.15 x 10.78)+(1.75 x 2.4)+(1.5 x 10)]udl & [(1.5 x 33)]kel

= (4.14 + 12.40 + 4.20 + 15.0)udl & 49.5kel

= 35.7 kN/m & 49.5kN

Page 5: 24 m Span Pre Stressed Bridge

HA Design serviceability

25 units HB Design SLS m

Design ultimate moment

Combination 3 Loading

Super. & HA live load for

Total load for ultimate limi

Design serviceability mom

Allowable stresses in precast concrete

cl.6.3.2.2 b)

cl.6.3.2.4 b)

At serviceability limit state :

cl.7.4.3.2 Compression (1.25 x Table 22)

= 14.9 x 24.02 / 8 + 39.6 x 24 / 4

=1310 kNm

= 2.9 x 24.02 / 8 + 982.3(from grillage analysis)

= 1191.1 kNm

= 35.7 x 24.02 / 8 + 49.5 x 24 / 4

= 2867 kNm

=  [(1.2 x 2.4)+(1.0 x 10)]udl & [(1.0 x 33)]kel

= (2.88 + 10.0)udl & 33kel

= 12.9 kN/m & 33kN

=  [(1.15 x 3.6)+(1.15 x 10.78)+(1.75 x 2.4)+(1.25 x 10)]udl & [(1.25 x 33)]kel

=  (4.14 + 12.40 + 4.20 + 12.5)udl & 41.3kel

= 33.2 kN/m & 41.3kN

= 12.9 x 24.02 / 8 + 33 x 24 / 4

= 1127 kNm

 At transfer :

Compression ( Table 23 ) 

0.5fci (<=0.4fcu) = 20 N/mm2 max.

Tension = 1.0 N/mm2

1.25 x 0.4fcu = 25 N/mm2 

Tension = 0 N/mm2 (class 1) & 3.2 N/mm2 (class 2 - Table 24)

Page 6: 24 m Span Pre Stressed Bridge

Comb. Comb.1 Comb.3

(HA)

- 8.94 - 8.94 - 8.94

- 7.88 - 7.17 - 6.78

- - -1.35

Differential shrinkage -0.60 -0.60

Total Stress at Level 1 = -17.42 -16.71

Hence Combination 3 is critical

Prestressing Force and Eccentricity

Using straight, fully bonded tendons (constant force and eccentricity).

Allow for 20% loss of prestress after transfer.

Initial prestress at Level 1 to satisfy class 2 requirement for SLS (Comb. 3).

The critical section at transfer occurs at the end of the transmission zone. The moment due to the self weight at this section is near zero and initial stress conditions are:

Hence 32 tendons required.

Stresses at Level 1 due to SLS loads (N/mm2) :

Dead Load   M / Z = (1037 x 106) / (116.020 x 106)

Super. & Live Load  M / Z = M / (166.156 x 106)

Reverse Temperature = γ

Stress at transfer = ( 17.67 - 3.2 ) / 0.8 = 18.1 N/mm2 (use allowable stress of 20 N/mm2)

P/A + Pe/Zlevel 1 = 20

P/A - Pe/Zlevel 2 >= - 1.0

(eqn. 1) x Zlevel 1 + (eqn. 2) x Zlevel 2 gives :

P >= A x (20 x Zlevel 1 - 1.0 x Zlevel 2) / (Zlevel 1 + Zlevel 2)

P = 449.22 x 103 x ( 20 x 116.02 - 89.066) / ( 116.02 + 89.066) x 10-3 = 4888 kN

Allow 10% for loss of force before and during transfer, then the initial force Po = 4888 / 0.9 = 5431kN

Using 15.2mm class 2 relaxation standard strand at maximum initial force of 174kN (0.75 x Pu)

Area of tendon = 139mm2

Nominal tensile strength = fpu =1670 N/mm2

Initial force Po = 32 x 174 = 5568 kN

P = 0.9 x 5568 = 5011 kN

Page 7: 24 m Span Pre Stressed Bridge

Substituting P = 5011 kN in (eqn. 2)

Arrange 32 tendons symmetrically about the Y-Y axis to achieve an eccentricity of about 216mm.

Taking moments about bottom of beam :

1000 = 2000

900 = 1800

260 = 1040

160 = 1280

10 @ 110 = 1100

60 = 360

7580

Allowing for 1% relaxation loss in steel before transfer and elastic deformation of concrete at transfer :

cl. 6.7.2.3

Initial stresses due to prestress at end of transmission zone :

Stress due to self weight of beam at mid span :

e <= Zlevel 2 / A + Zlevel 2 / P = (89.066 x 106 / 449.22 x 103) + (89.066 x 106 / 5011 x 103)

e = 198 + 18 = 216 mm

 2 @

 2 @

 4 @

 8 @

6 @

32  

e = 456 - 7580 / 32 = 456 - 237 =219mm

P = 0.99 Po / [ 1 + Es x (Aps / A) x (1 + A x e2 / I) / Eci ]

P = 0.99 x Po / [ 1 + 196 x ( 32 x 139 / 449220) x (1 + 449220 x 2192 / 52.905 x 109) / 31 ]

P = 0.91 Po = 0.91 x 5568 = 5067 kN

 Level 1   : P / A x ( 1 + A x e / Zlevel 1 ) = 11.3 x ( 1 + 219 / 258 ) = 20.89 N/mm2

Level 2   : P / A x ( 1 - A x e / Zlevel 2 ) = 11.3 x ( 1 - 219 / 198 ) = - 1.20 N/mm2

Moment due to self weight of beam at mid span = 10.78 x 242 / 8 = 776.2 kNm

@ Level 1 = - 776.2 / 116.02 = - 6.69 N/mm2

Page 8: 24 m Span Pre Stressed Bridge

Initial stresses at mid span :

cl. 6.7.2.5

Loss of force after transfer due to :

cl. 6.7.2.2 Steel relaxation = 0.02 x 5568 = 111

cl. 6.7.2.4

cl. 6.7.2.5

Total Loss = 111 + 262 + 550 = 923 kN

Final stresses due to prestress after all loss of prestress at :

Level 1

Level 2

Combined stresses in final condition for worst effects of design loads, differential shrinkage and temperature difference :

Level 2, combination 1 : f = - 0.98 + 1037 / 89.066 + 1310 / 242.424 + 1.64 = 17.71 (< 25 O.K.)

Ultimate Capacity of Beam and Deck Slab

(Composite Section)

cl. 6.3.3 Only steel in the tension zone is to be considered :

@ Level 2 = 776.2 / 89.066 = 8.71 N/mm2

Allowing for 2% relaxation loss in steel after transfer, concrete shrinkage εcs = 300 x 10-6

and concrete specific creep ct = 1.03 x 48 x 10-6 per N/mm2

Concrete shrinkage = (εcs x Es x Aps ) = 300 x 10-6 x 196 x 32 x 139 = 262

Concrete creep = ( ct x  fco x Es x Aps ) = 1.03 x 48 x 10-6 x 12.76 x 196 x 32 x 139 = 550

Final force after all loss of prestress = Pe = 5067 - 923 = 4144 kN  (Pe/P = 0.82)

f1,0.82P =  0.82 x 20.89 = 17.08 N/mm2

f2,0.82P = 0.82 x - 1.20 = - 0.98 N/mm2

Level 1, combination 1 HB : f = 17.08 - 16.71 = 0.37 N/mm2 (> 0 hence O.K.)

Level 1, combination 3 : f = 17.08 - 17.67 = - 0.59 N/mm2 (> - 3.2 hence O.K.)

Level 3. combination 3 : f = (1127 / 179.402) + (0.8 x 3.15) = 8.8 N/mm2 (< 25 O.K.)

Ultimate Design Moment = γf3 x M = 1.1 x 2867 = 3154 kNm

Page 9: 24 m Span Pre Stressed Bridge

Effective depth from Level 3 = 1200 - 135 = 1065mm

Assume that the maximum design stress is developed in the tendons, then :

Tensile force in tendons Fp = 0.87 x 28 x 139 x 1670 x 10-3 = 5655 kN

Compressive force in concrete flange :

Let X = depth to neutral axis.

Compressive force in concrete web :

Equating forces to obtain X :

X = 659 mm

Determine depth to neutral axis by an iterative strain compatibility analysis

Try X = 659 mm as an initial estimate

Width of web at this depth = 247mm

Centroid of tendons in tension zone = (6x60 + 10x110 +  8x160 + 4x260) / 28 = 135mm

Ff = 0.4 x 40 x 1000 x 150 x 10-3 = 2400 kN

Fw = 0.4 x 50 x [393 - (393 - 200) x (X - 150) / (671 x 2)] x (X - 150) x 10-3 

Fw = ( -2.876X2 + 8722.84X - 1243717) x 10-3

5655 = 2400 + ( -2.876X2 + 8722.84X - 1243717) x 10-3

Stress in tendon after losses = fpe = 4144 x 103 / (32 x 139) = 932 N/mm2

Prestrain εpe = fpe / Es = 932 / 200 x 103 = 0.0047

εpb6 = ε6 + εpe = -459 x 0.0035 / 659 + 0.0047 = 0.0022

εpb5 = ε5 + εpe = -359 * 0.0035 / 659 + 0.0047 = 0.0028

εpb4 = ε4 + εpe = 281 * 0.0035 / 659 + 0.0047 = 0.0062

εpb3 = ε3 + εpe = 381 * 0.0035 / 659 + 0.0047 = 0.0067

εpb2 = ε2 + εpe = 431 * 0.0035 / 659 + 0.0047 = 0.0069

εpb1 = ε1 + εpe = 481 * 0.0035 / 659 + 0.0047 = 0.0072

fpb6 = 0.0022 x 200 x 103 = 444 N/mm2

fpb5 = 0.0028 x 200 x 103 = 551 N/mm2

fpb4 = 1162 + 290 x (0.0062 - 0.0058) / 0.0065 = 1178 N/mm2

fpb3 = 1162 + 290 x (0.0067 - 0.0058) / 0.0065 = 1201 N/mm2

fpb2 = 1162 + 290 x (0.0069 - 0.0058) / 0.0065 = 1213 N/mm2

fpb1 = 1162 + 290 x (0.0072 - 0.0058) / 0.0065 = 1225 N/mm2

Page 10: 24 m Span Pre Stressed Bridge

Tensile force in tendons :

4976 kN

Compressive force in concrete :

5658 kN

Fc > Ft therefore reduce depth to neutral axis and repeat the calculations.

Using a depth of 565mm will achieve equilibrium.

The following forces are obtained :

Taking Moments about the neutral axis :

Fp6 = 2 x 139 x 444 x 10-3  = 124

Fp5 = 2 x 139 x 551 x 10-3 = 153

Fp4 = 4 x 139 x 1178 x 10-3 = 655

Fp3 = 8 x 139 x 1201 x 10-3 = 1336

Fp2 = 10 x 139 x 1213 x 10-3= 1686

Fp1 = 6 x 139 x 1225 x 10-3 = 1022

Ff = 0.4 x 40 x 1000 x 150 x 10-3= 2400

Fw = 0.4 x 50 x 0.5 x (393 + 247) x (659 - 150) x 10-3= 3258

Fp6 = 134 Ff = 2400

Fp5 = 168  Fw = 2765

Fp4 = 675 Fc = 5165

Fp3 = 1382

Fp2 = 1746

Fp1 = 1060

Ft = 5165

Fp6 = 134 x -0.365 =-49

Fp5 = 168 x -0.265 = -45

Page 11: 24 m Span Pre Stressed Bridge

cl. 6.3.3.1 Mu / M = 4192 / 3154 = 1.33 ( > 1.15 ) hence strain in outermost tendon O.K.

Abutment Design Example to BD 30

Design the fixed and free end cantilever abutments to the 20m span deck shown to carry HA and 45 units of HB loading. Analyse the abutments using a unit strip method. The bridge site is located south east of Oxford (to establish the range of shade air temperatures).

The proposed deck consists of 11No. Y4 prestressed concrete beams and concrete deck slab as shown.

Loading From the DeckA grillage analysis gave the following reactions for the various load cases:

Critical Reaction U Total Reaction on Each Abutment

Concrete Deck 180 230 1900Surfacing 30 60 320HA udl+kel 160 265 114045 units HB 350 500 1940

Nominal loading on 1m length of abutment:

Fp4 = 675 x 0.375 = 253

Fp3 = 1382 x 0.475 = 656

Fp2 = 1746 x 0.525 =917

Fp1 = 1060 x 0.575 = 610

Ff = 2400 x 0.49 = 1176

Fw = 3258 x 0.207 = 674

Mu = 4192 kNm > 3154 kNm hence O.K.

The ground investigation report shows suitable founding strata about 9.5m below the proposed road level. Test results show the founding strata to be a cohesionless soil having an angle of shearing resistance (φ) = 30

Backfill material will be Class 6N with an effective angle of internal friction (ϕ') = 35o and density (γ) = 19kN/m

Nominal Reaction( Ultimate ReactionNominal ReactionUltimate Reaction(kN)

Deck Dead Load = (1900 + 320) / 11.6 = 191kN/mHA live Load on Deck = 1140 / 11.6 = 98kN/mHB live Load on Deck = 1940 / 11.6 = 167kN/m

From BS 5400 Part 2 Figures 7 and 8 the minimum and maximum shade air temperatures are -19 and +37

For a Group 4 type strucutre (see fig. 9) the corresponding minimum and maximum effective bridge temperatures are -11 and +36

Hence the temperature range = 11 + 36 = 47oC.

From Clause 5.4.6 the range of movement at the free end of the 20m span deck = 47 x 12 x 10-6

The ultimate thermal movement in the deck will be ± [(11.3 / 2) γf3 γfL] = ±[11.3 x 1.1 x 1.3 /2] = ± 8mm.

Option 1 - Elastomeric Bearing:With a maximum ultimate reaction = 230 + 60 + 500 = 790kN then a suitable elastomeric bearing would be Ekspan's Elastomeric Pad Bearing EKR35:

Page 12: 24 m Span Pre Stressed Bridge

Horizontal load at bearing for 10mm contraction = 12.14 x 10 = 121kN.This is an ultimate load hence the nominal horizontal load = 121 / 1.1 / 1.3 = 85kN at each bearing.

Alternatively using BS 5400 Part 9.1 Clause 5.14.2.6:

Using the Ekspan bearing EKR35

This correllates with the value obtained above using the shear stiffness from the manufacturer's data sheet.

BS 5400 Part 2 - Clause 5.4.7.3:Average nominal dead load reaction = (1900 + 320) / 11 = 2220 / 11 = 200kN

Nominal Load for HA = 8kN/m x 20m + 250kN = 410kNNominal Load for HB = 25% of 45units x 10kN x 4axles = 450kN450 > 410kN hence HB braking is critical.

When this load is applied on the deck it will act on the fixed abutment only.

Nominal Load = 300kN300 < 450kN hence braking load is critical in the longitudinal direction.When this load is applied on the deck it will act on the fixed abutment only.

Loading at Rear of Abutment

Backfill

·         Maximum Load = 1053kN·         Shear Deflection = 13.3mm·         Shear Stiffness = 12.14kN/mm·         Bearing Thickness = 19mm

Note: the required shear deflection (8mm) should be limited to between 30% to 50% of the thickness of the bearing. The figure quoted in the catalogue for the maximum shear deflection is 70% of the thickness. 

A tolerance is also required for setting the bearing if the ambient temperature is not at the mid range temperature. The design shade air temperature range will be -19 to +37

Total horizontal load on each abutment = 11 x 85 = 935 kN ≡ 935 / 11.6 = 81kN/m.

H = AGδr/tq

·         Maximum Load = 1053kN

·         Area = 610 x 420 = 256200mm2

·         Nominl hardness = 60 IRHD·         Bearing Thickness = 19mm

Shear modulus G from Table 8 = 0.9N/mm2

H = 256200 x 0.9 x 10-3 x 10 / 19 = 121kN

Option 2 - Sliding Bearing:With a maximum ultimate reaction of 790kN and longitudinal movement of ± 8mm then a suitable bearing from the Ekspan EA Series would be /80/210/25/25:

·         Maximum Load = 800kN·         Base Plate A dimension = 210mm·         Base Plate B dimension = 365mm·         Movement ± X = 12.5mm

Contact pressure under base plate = 200000 / (210 x 365) = 3N/mm2

As the mating surface between the stainless steel and PTFE is smaller than the base plate then the pressure between the sliding faces will be in the order of 5N/mm

From Table3 of BS 5400 Part 9.1 the Coefficient of friction = 0.08 for a bearing stress of 5N/mmHence total horizontal load on each abutment when the deck expands or contracts = 2220 x 0.08 = 180kN

Traction and Braking Load - BS 5400 Part 2 Clause 6.10:

Braking load on 1m width of abutment = 450 / 11.6 = 39kN/m.

Skidding Load - BS 5400 Part 2 Clause 6.11:

For Stability calculations use active earth pressures = Ka γ hKa for Class 6N material = (1-Sin35) / (1+Sin35) = 0.27

Density of Class 6N material = 19kN/m3

Page 13: 24 m Span Pre Stressed Bridge

Assume a surchage loading for the compaction plant to be equivalent to 30 units of HB

1) Stability Check

Initial Sizing for Base Dimensions

Alternatively a simple spreadsheet will achieve a result by trial and error.

Load Combinations

Fixed Abutment OnlyBackfill + HA surcharge + Deck dead load + HA on deck + Braking on deck

Weight of wall stem = 1.0 x 6.5 x 25 = 163kN/mWeight of base = 6.4 x 1.0 x 25 = 160kN/mWeight of backfill = 4.3 x 6.5 x 19 = 531kN/mWeight of surcharge = 4.3 x 12 = 52kN/m

Surcharge Force Fs = 0.27 x 12 x 7.5 = 24 kN/m

Restoring Effects:Weight Lever Arm Moment About A

Stem 163 1.6 261Base 160 3.2 512Backfill 531 4.25 2257Surcharge 52 4.25 221∑ = 906 ∑ =3251Overturning Effects:

F Lever Arm Moment About ABackfill 144 2.5 361Surcharge 24 3.75 91

∑ =168 ∑ =452

Active Pressure at depth h = 0.27 x 19 x h = 5.13h kN/m2

Hence Fb = 5.13h2/2 = 2.57h2kN/m

Surcharge - BS 5400 Part 2 Clause 5.8.2:

For HA loading surcharge = 10 kN/m2

For HB loading surcharge = 20 kN/m2

Hence Compaction Plant surcharge = 12 kN/m2.

For surcharge of w kN/m2 :Fs = Ka w h = 0.27wh kN/m

There are a number of publications that will give guidance on base sizes for free standing cantilever walls, Reynolds's Reinforced Concrete Designer's Handbook being one such book.

Backfill + Construction surcharge

Backfill + Construction surcharge

Sackfill + HA surcharge + Deck dead load + Deck contraction

Backfill + HA surcharge + Braking behind abutment + Deck dead load

Backfill + HB surcharge + Deck dead load

Backfill + HA surcharge + Deck dead load + HB on deck

CASE 1 - Fixed Abutment

Density of reinforced concrete = 25kN/m3.

Backfill Force Fb = 0.27 x 19 x 7.52 / 2 = 144kN/m

Page 14: 24 m Span Pre Stressed Bridge

For sliding effects:Active Force = Fb + Fs = 168kN/m

Bearing Pressure:Check bearing pressure at toe and heel of base slab = (P / A) ± (P x e / Z) where P x e is the moment about the centre of the base.P = 906kN/m

Nett moment = 3251 - 452 = 2799kNm/mEccentricity (e) of P about centre-line of base = 3.2 - (2799 / 906) = 0.111mPressure under base = (906 / 6.4) ± (906 x 0.111 / 6.827)

Hence the abutment will be stable for Case 1.

Fixed Abutment:

F of S Overturning F Be Bearing Pressure at HeelCase 1 7.16 3.09 156Case 2 2.87 2.13 386Case 2a 4.31 2.64 315Case 3 3.43 2.43 351Case 4 4.48 2.63 322Case 5 5.22 3.17 362Case 6 3.8 2.62 378

Free Abutment:

F of S Overturning F of S Sli Bearing PrBearing Pressure at HeelCase 1 7.15 3.09 168Case 2 2.91 2.14 388Case 2a 4.33 2.64 318Case 3 3.46 2.44 354Case 4 4.5 2.64 325Case 5 5.22 3.16 365It can be seen that the use of elastomeric bearings (Case 2) will govern the critical design load cases on the abutments. We shall assume that there are no specific requirements for using elastomeric bearings and design the abutments for the lesser load effects by using sliding bearings.

2) Wall and Base Design

Loads on the back of the wall are calculated using 'at rest' earth pressures. Serviceability and Ultimate load effects need to be calculated for the load cases 1 to 6 shown above. Again, these are best carried out using a simple spreadsheet.Using the Fixed Abutment Load Case 1 again as an example of the calculations:Wall Design

Factor of Safety Against Overturning = 3251 / 452 = 7.2 > 2.0 ∴ OK.

Frictional force on underside of base resisting movement = W tan(φ) = 906 x tan(30o) = 523kN/mFactor of Safety Against Sliding = 523 / 168 = 3.1 > 2.0 ∴ OK.

A = 6.4m2/m

Z = 6.42 / 6 = 6.827m3/m

Pressure under toe = 142 + 15 = 157kN/m2 < 400kN/m2 ∴ OK.

Pressure under heel = 142 - 15 = 127kN/m2

Analysing the fixed abutment with Load Cases 1 to 6 and the free abutment with Load Cases 1 to 5 using a simple spreadsheet the following results were obtained:

Ko = 1 - Sin(ϕ') = 1 - Sin(35o) = 0.426γfL for horizontal loads due to surcharge and backfill from BS 5400 Part 2 Clause 5.8.1.2:

Page 15: 24 m Span Pre Stressed Bridge

Serviceability = 1.0Ultimate = 1.5

Surcharge Force Fs on the rear of the wall = 0.426 x 12 x 6.5 = 33kN/mAt the base of the Wall:

Fixed Abutment:

Moment Moment Moment ShearSLS Dead SLS Live ULS ULS

Case 1 371 108 790 337Case 2a 829 258 1771 566Case 3 829 486 2097 596Case 4 829 308 1877 602Case 5 829 154 1622 543Case 6 829 408 1985 599

Free Abutment:Moment Moment Moment ShearSLS Dead SLS Live ULS ULS

Case 1 394 112 835 350Case 2a 868 265 1846 581Case 3 868 495 2175 612Case 4 868 318 1956 619Case 5 868 159 1694 559

Concrete to BS 8500:2006

Reinforced concrete walls are designed to BS 5400 Part 4 Clause 5.6.Check classification to clause 5.6.1.1:Ultimate axial load in wall from deck reactions = 2400 + 600 + 2770 = 5770 kN

Bending

γf3 = 1.0 for serviceability and 1.1 for ultimate (from BS 5400 Part 4 Clauses 4.2.2 and 4.2.3)

Backfill Force Fb on the rear of the wall = 0.426 x 19 x 6.52 / 2 = 171kN/m

Serviceability moment = (171 x 6.5 / 3) + (33 x 6.5 / 2) = 371 + 107 = 478kNm/mUltimate moment = 1.1 x 1.5 x 478 = 789kNm/mUltimate shear = 1.1 x 1.5 x (171 + 33) = 337kN/m

Analysing the fixed abutment with Load Cases 1 to 6 and the free abutment with Load Cases 1 to 5 using a simple spreadsheet the following results were obtained for the design moments and shear at the base of the wall:

Use strength class C32/40 with water-cement ratio 0.5 and minimum cement content of 340kg/m

Nominal cover to reinforcement = 60mm (45mm minimum cover plus a tolerance Δc of 15mm).Reinforcement to BS 4449:2005 Grade B500B:   fy = 500N/mm2

Design for critical moments and shear in Free Abutment: 

0.1fcuAc = 0.1 x 40 x 103 x 11.6 x 1 = 46400 kN > 5770 ∴ design as a slab in accordance with clause 5.4

Page 16: 24 m Span Pre Stressed Bridge

Shear

Shear requirements are designed to BS 5400 clause 5.4.4:

ULS shear at Section 7H/8 for load case 4 = 487 kN

Hence height requiring strengthening = 1.073 x (0.673 - 0.62) / (0.673 - 0.53) = 0.4m < d.

Early Thermal Cracking

Base Design

Maximum bending and shear effects in the base slab will occur at sections near the front and back of the wall. Different load factors are used for serviceability and ultimate limit states so the calculations need to be carried out for each limit state using 'at rest pressures'Using the Fixed Abutment Load Case 1 again as an example of the calculations:

Weight of wall stem = 1.0 x 6.5 x 25 x 1.0 = 163kN/mWeight of base = 6.4 x 1.0 x 25 x 1.0 = 160kN/mWeight of backfill = 4.3 x 6.5 x 19 x 1.0 = 531kN/mWeight of surcharge = 4.3 x 12 x 1.0 = 52kN/m

Surcharge Force Fs = 0.426 x 12 x 7.5 x 1.0 = 38 kN/m

Restoring Effects:

Weight Le Moment About AStem 163 1.6 261Base 160 3.2 512Backfill 531 4.25 2257Surcharge 52 4.25 221

BS 5400 Part 4 Clause 5.4.2 → for reisitance moments in slabs design to clause 5.3.2.3:z = {1 - [ 1.1fyAs) / (fcubd) ]} dUse B40 @ 150 c/c:

As = 8378mm2/m,    d = 1000 - 60 - 20 = 920mmz = {1 - [ 1.1 x 500 x 8378) / (40 x 1000 x 920) ]} d = 0.875d < 0.95d ∴ OK

Mu = (0.87fy)Asz = 0.87 x 500 x 8378 x 0.875 x 920 x 10-6 = 2934kNm/m > 2175kNn/m ∴ OK

Carrying out the crack control calculation to Clause 5.8.8.2 gives a crack width of 0.2mm < 0.25mm.Also the steel reinforcement and concrete stresses meet the limitations required in clause 4.1.1.3

v = V / (bd) = 619 x 103 / (1000 x 920) = 0.673 N/mm2

No shear reinforcement is required when v < ξsvc

ξs = (500/d)1/4 = (500 / 920)1/4 = 0.86

vc = (0.27/γm)(100As/bwd)1/3(fcu)1/3 = (0.27 / 1.25) x ({100 x 8378} / {1000 x 920})1/3 x (40)1/3 = 0.72

ξsvc = 0.86 x 0.72 = 0.62 N/mms < 0.673 hence shear reinforcement should be provided, however check shear at distance H/8 (8.63 / 8 = 1.079m) up the wall.

v = V / (bd) = 487 x 103 / (1000 x 920) = 0.53 N/mm2 < 0.62

Provide a 500 x 500 splay at the base of the wall with B32 @ 150c/c bars in sloping face.

Considering the effects of casting the wall stem onto the base slab by complying with the early thermal cracking of concrete to BD 28 then B16 horizontal lacer bars @ 150 c/c will be required in both faces in the bottom half of the wall.

Minimum area of secondary reinforcement to Clause 5.8.4.2 = 0.12% of bad = 0.0012 x 1000 x 920 = 1104 mm2/m (use B16 @ 150c/c - As = 1340mm2/m)

CASE 1 - Fixed Abutment Serviceability Limit StateγfL = 1.0     γf3 = 1.0

B/fill Force Fb = 0.426 x 19 x 7.52 x 1.0 / 2 = 228kN/m

Page 17: 24 m Span Pre Stressed Bridge

∑ = 906 ∑ = 3251Overturning Effects:

F Le Moment About ABackfill 228 2.5 570Surcharge 38 3.75 143∑ = 266 ∑ = 713

Bearing Pressure at toe and heel of base slab = (P / A) ± (P x e / Z)P = 906kN/m

Nett moment = 3251 - 713 = 2538kNm/mEccentricity (e) of P about centre-line of base = 3.2 - (2538 / 906) = 0.399mPressure under base = (906 / 6.4) ± (906 x 0.399 / 6.827)

Weight of wall stem = 1.0 x 6.5 x 25 x 1.15 = 187kN/mWeight of base = 6.4 x 1.0 x 25 x 1.15 = 184kN/mWeight of backfill = 4.3 x 6.5 x 19 x 1.2 = 637kN/mWeight of surcharge = 4.3 x 12 x 1.2 = 62kN/m

Surcharge Force Fs = 0.426 x 12 x 7.5 x 1.5 = 58 kN/m

Restoring Effects:

Weight Lever Arm Moment About A

A = 6.4m2/m

Z = 6.42 / 6 = 6.827m3/m

Pressure under toe = 142 + 53 = 195kN/m2

Pressure under heel = 142 - 53 = 89kN/m2

Pressure at front face of wall = 89 + {(195 - 89) x 5.3 / 6.4} = 177kN/m2

Pressure at rear face of wall = 89 + {(195 - 89) x 4.3 / 6.4} = 160kN/m2

SLS Moment at a-a = (177 x 1.12 / 2) + ([195 - 177] x 1.12 / 3) - (25 x 1.0 x 1.12 / 2) = 99kNm/m (tension in bottom face). 

SLS Moment at b-b = (89 x 4.32 / 2) + ([160 - 89] x 4.32 / 6) - (25 x 1.0 x 4.32 / 2) - (531 x 4.3 / 2) - (52 x 4.3 / 2) = -443kNm/m (tension in top face). 

CASE 1 - Fixed Abutment Ultimate Limit StateγfL for concrete = 1.15γfL for fill and surcharge(vetical) = 1.2γfL for fill and surcharge(horizontal) = 1.5

Backfill Force Fb = 0.426 x 19 x 7.52 x 1.5 / 2 = 341kN/m

Page 18: 24 m Span Pre Stressed Bridge

Stem 187 1.6 299Base 184 3.2 589Backfill 637 4.25 2707Surcharge 62 4.25 264∑ = 1070 ∑ = 3859

Overturning Effects:F Lever Arm Moment About ABackfill 341 2.5 853Surcharge 58 3.75 218∑ = 399 ∑ = 1071

Bearing Pressure at toe and heel of base slab = (P / A) ± (P x e / Z)P = 1070kN/m

Nett moment = 3859 - 1071 = 2788kNm/mEccentricity (e) of P about centre-line of base = 3.2 - (2788 / 1070) = 0.594mPressure under base = (1070 / 6.4) ± (1070 x 0.594 / 6.827)

ULS Shear at a-a = 1.1 x {[(260 + 228) x 1.1 / 2] - (1.15 x 1.1 x 25)} = 260kN/m

/ 2) - (62 x 4.3 / 2)} = -769kNm/m (tension in top face).

A = 6.4m2/m

Z = 6.42 / 6 = 6.827m3/m

Pressure under toe = 167 + 93 = 260kN/m2

Pressure under heel = 167 - 93 = 74kN/m2

Pressure at front face of wall = 74 + {(260 - 74) x 5.3 / 6.4} = 228kN/m2

Pressure at rear face of wall = 74 + {(260 - 74) x 4.3 / 6.4} = 199kN/m2

γf3 = 1.1

ULS Shear at b-b = 1.1 x {[(199 + 74) x 4.3 / 2] - (1.15 x 4.3 x 25) - 637 - 62} = 259kN/m 

ULS Moment at a-a = 1.1 x {(228 x 1.12 / 2) + ([260 - 228] x 1.12 / 3) - (1.15 x 25 x 1.0 x 1.12 / 2)} = 148kNm/m (tension in bottom face). 

SLS Moment at b-b = 1.1 x {(74 x 4.32 / 2) + ([199 -

74] x 4.32 / 6) - (1.15 x 25 x 1.0 x 4.32 / 2) - (637 x 4.3

Page 19: 24 m Span Pre Stressed Bridge

Fixed Abutment Base:

Section a-a Section b-b

ULSShear SLSMomenULSMoment ULS ShearSLS MomeULS MomentCase 1 261 99 147 259 447Case 2a 528 205 302 458 980Case 3 593 235 340 553 1178Case 4 550 208 314 495 1003Case 5 610 241 348 327 853Case 6 637 255 365 470 1098

Free Abutment Base:Section a-a Section b-b

ULSShear SLSMomenULSMoment ULSShear SLSMoment ULSMomentCase 1 267 101 151 266 475Case 2a 534 207 305 466 1029Case 3 598 236 342 559 1233Case 4 557 211 317 504 1055Case 5 616 243 351 335 901

Design for shear and bending effects at sections a-a and b-b for the Free Abutment:

Bending

Use B32 @ 150 c/c:

For the Serviceability check for Case 3 an approximation of the dead load moment can be obtained by removing the surcharge and braking loads. The spreadsheet result gives the dead load SLS moment for Case 3 as 723kNm, thus the live load moment = 1233 - 723 = 510kNm.

This could be corrected by reducing the bar spacing, but increase the bar size to B40@150 c/c as this is required to avoid the use of links (see below).

ShearShear on Toe - Use Fixed Abutment Load Case 6:By inspection B32@150c/c will be adequate for the

Shear requirements are designed to BS 5400 clause 5.7.3.2(a) checking shear at d away from the front face of the wall to clause 5.4.4.1:ULS Shear on toe = 1.1 x {(620 + 599) x 0.5 x 0.176 -

Analysing the fixed abutment with Load Cases 1 to 6 and the free abutment with Load Cases 1 to 5 using a simple spreadsheet the following results were obtained:

BS 5400 Part 4 Clause 5.7.3 → design as a slab for reisitance moments to clause 5.3.2.3:z = {1 - [ 1.1fyAs) / (fcubd) ]} d

As = 5362mm2/m,    d = 1000 - 60 - 16 = 924mmz = {1 - [ 1.1 x 500 x 5362) / (40 x 1000 x 924) ]} d = 0.92d < 0.95d ∴ OK

Mu = (0.87fy)Asz = 0.87 x 500 x 5362 x 0.92 x 924 x 10-6 = 1983kNm/m > 1922kNm/m ∴ OK(1983kNm/m also > 1834kNm/m ∴ B32 @ 150 c/c suitable for fixed abutment.

Carrying out the crack control calculation to Clause 5.8.8.2 gives a crack width of 0.27mm > 0.25mm

Using B40@150c/c the crack control calculation gives a crack width of 0.17mm < 0.25mm OK.∴Also the steel reinforcement and concrete stresses meet the limitations required in clause 4.1.1.3

bending effects in the toe (Muls = 365kNm < 1983kNm)

Page 20: 24 m Span Pre Stressed Bridge

1.15 x 1 x 0.176 x 25} = 112kN

Shear on Heel - Use Free Abutment Load Case 3:Shear requirements are designed at the back face of the wall to clause 5.4.4.1:Length of heel = (6.5 - 1.1 - 1.0) = 4.4mULS Shear on heel = 1.1 x {348 x 0.5 x (5.185 - 2.1) - 1.15 x 1 x 4.4 x 25 - 1.2 x 4.4 x (8.63 x 19 + 10)} = 559kN

Using B32@150 c/c then:

Early Thermal Cracking

Local Effects

Curtain WallThis wall is designed to be cast onto the top of the abutment after the deck has been built. Loading will be applied from the backfill, surcharge and braking loads on top of the wall.HB braking load to BS 5400 clause 6.10 = 25% x 45units x 10kN on each axle = 112.5kN per axle.

1st axle load on back of abutment = 112.5 / 3.0 = 37.5kN/m2nd axle load on back of abutment = 112.5 / 6.6 = 17.0kN/m3rd & 4th axle loads on back of abutment = 2 x 112.5 / 11.6 = 19.4kN/m

Maximum load on back of abutment = 37.5 + 17.0 + 19.4 = = 73.9kN/mBending and Shear at Base of 3m High Curtain Wall

v = V / (bd) = 112 x 103 / (1000 x 924) = 0.121 N/mm2

No shear reinforcement is required when v < ξsvc

Reinforcement in tension = B32 @ 150 c/c

ξs = (500/d)1/4 = (500 / 924)1/4 = 0.86

vc = (0.27/γm)(100As/bwd)1/3(fcu)1/3 = (0.27 / 1.25) x ({100 x 5362} / {1000 x 924})1/3 x (40)1/3 = 0.62

ξsvc = 0.86 x 0.62 = 0.53 N/mms > 0.121N/mms ∴ OK

v = V / (bd) = 559 x 103 / (1000 x 924) = 0.605 N/mm2

No shear reinforcement is required when v < ξsvc

ξs = (500/d)1/4 = (500 / 924)1/4 = 0.86

vc = (0.27/γm)(100As/bwd)1/3(fcu)1/3 = (0.27 / 1.25) x ({100 x 5362} / {1000 x 924})1/3 x (40)1/3 = 0.62

ξsvc = 0.86 x 0.62 = 0.53 N/mms < 0.605N/mms ∴ FailRather than provide shear reinforcement try increasing bars to B40 @ 150 c/c (also required for crack control as shown above).

vc = (0.27/γm)(100As/bwd)1/3(fcu)1/3 = (0.27 / 1.25) x ({100 x 8378} / {1000 x 920})1/3 x (40)1/3 = 0.716

ξsvc = 0.86 x 0.716 = 0.616 N/mms > 0.605N/mms ∴ OK

Considering the effects of casting the base slab onto the blinding concrete by complying with the early thermal cracking of concrete to BD 28 then B16 distribution bars @ 250 c/c will be required.

Minimum area of main reinforcement to Clause 5.8.4.1 = 0.15% of bad = 0.0015 x 1000 x 924 = 1386 mm2/m (use B20 @ 200c/c - As = 1570mm2/m).

Assume a 45o dispersal to the curtain wall and a maximum dispersal of the width of the abutment (11.6m) then:

Page 21: 24 m Span Pre Stressed Bridge

Horizontal load due to HB surcharge = 0.426 x 20 x 3.0 = 25.6 kN/m

SLS Moment = (73.9 x 3.0) + (25.6 x 1.5) + (36.4 x 1.0) = 297 kNm/m (36 dead + 261 live)ULS Moment = 1.1 x {(1.1 x 73.9 x 3.0) + (1.5 x 25.6 x 1.5) + (1.5 x 36.4 x 1.0)} = 392 kNm/mULS Shear = 1.1 x {(1.1 x 73.9) + (1.5 x 25.6) + (1.5 x 36.4)} = 192kN/m

Last Updated : 05/09/09For more information :

Horizontal load due to backfill = 0.426 x 19 x 3.02 / 2 = 36.4 kN/m

400 thick curtain wall with B32 @ 150 c/c :Mult = 584 kNm/m > 392 kNm/m ∴ OKSLS Moment produces crack width of 0.21mm < 0.25 ∴ OK

ξsvc = 0.97 N/mm2 > v = 0.59 N/mm2 ∴ Shear OK

Back to Abutment Tutorial  |  Back to Tutorial Index

Email: [email protected]

Page 22: 24 m Span Pre Stressed Bridge

Since concrete is weak in tension in normal reinforced concrete construction cracks develop in the tension zone at working loads and therefore all concrete in tension is ignored in design.Prestressing involves inducing compressive stresses in the zone which will tend to become tensile under external loads. This compressive stress neutralizes the tensile stress so that no resultant tension exists, (or only very small values, within the tensile strength of the concrete). Cracking is therefore eliminated under working load and all of the concrete may be assumed effective in carrying load. Therefore lighter sections may be used to carry a given bending moment, and prestressed concrete may be used over much longer spans than reinforced concrete.

The prestressing force has to be produced by a high tensile steel, and it is necessary to use high quality concrete to resist the higher compressive stresses that are developed.

When the concrete has cured the stressing force is released and the tendons anchor themselves in the concrete.

Cable ducts and reinforcement are positioned in the beam mould. The ducts are usually raised towards the neutral axis at the ends to reduce the eccentricity of the stressing force.

Tendons are threaded through the cable ducts and tensioned to about 70% of their ultimate strength.

Wedges are inserted into the end anchorages and the tensioning force on the tendons is released. Grout is then pumped into the ducts to protect the tendons.

When the tensioning force is released and the tendons are anchored to the concrete a series of effects result in a loss of stress in the tendons. The effects are:

e. other causes in special circumstances , such as when steam curing is used with pre-tensioning.

The prestressing force also reduces the magnitude of the principal tensile stress in the web so that thin-webbed I - sections may be used without the risk of diagonal tension failures and with further savings in self-weight.

Both methods involve tensioning cables inside a concrete beam and then anchoring the stressed cables to the concrete. 

Design a simply supported prestressed concrete Y beam which  carries a 150mm thick concrete slab and 100mm of surfacing, together with a nominal live load udl of 10.0 kN/m2 and kel of 33kN/m . The span of the beam is 24.0m centre to centre of bearings and the beams are spaced at 1.0m intervals.

Page 23: 24 m Span Pre Stressed Bridge

= 10.78 kN/m

Load factors for serviceability and ultimate limit state from BS 5400 Part 2 (or BD 37/01) Table 1:

ULS

Comb.1 Comb.3

1.25

- -

Modular ratio effect for different concrete strengths between beam and slab may be ignored.

Page 24: 24 m Span Pre Stressed Bridge

Apply temperature differences given in BS 5400 Pt2 Fig.9 (Group 4)to a simplified beam section.

 = - 385.9 - 19.3 - 295.1 = - 700.3 kN

Page 25: 24 m Span Pre Stressed Bridge

Self weight of beam and weight of deck slab is supported by the beam. When the deck slab concrete has cured then any further loading (superimposed and live loads) is supported by the composite section of the beam and slab.

Assume that 2/3 of the total shrinkage of the precast concrete takes place before the deck slab is cast and that the residual shrinkage is 100 x 10-6 ,

 x Ecf x Acf x φ 

=  [(1.15 x 3.6)+(1.15 x 10.78)+(1.75 x 2.4)+(1.5 x 10)]udl & [(1.5 x 33)]kel

Page 26: 24 m Span Pre Stressed Bridge

=  [(1.15 x 3.6)+(1.15 x 10.78)+(1.75 x 2.4)+(1.25 x 10)]udl & [(1.25 x 33)]kel

Page 27: 24 m Span Pre Stressed Bridge

(HB)

-0.60

-17.67*

The critical section at transfer occurs at the end of the transmission zone. The moment due to the self weight at this section is near zero and initial stress conditions are:

.....................(eqn. 1)

.....................(eqn. 2)

 = 4888 / 0.9 = 5431kN

Page 28: 24 m Span Pre Stressed Bridge

Arrange 32 tendons symmetrically about the Y-Y axis to achieve an eccentricity of about 216mm.

Allowing for 1% relaxation loss in steel before transfer and elastic deformation of concrete at transfer :

P = 0.99 x Po / [ 1 + 196 x ( 32 x 139 / 449220) x (1 + 449220 x 2192 / 52.905 x 109) / 31 ]

Page 29: 24 m Span Pre Stressed Bridge

Final stresses due to prestress after all loss of prestress at :

Combined stresses in final condition for worst effects of design loads, differential shrinkage and temperature difference :

Level 2, combination 1 : f = - 0.98 + 1037 / 89.066 + 1310 / 242.424 + 1.64 = 17.71 (< 25 O.K.)

Allowing for 2% relaxation loss in steel after transfer, concrete shrinkage εcs = 300 x 10-6

) = 300 x 10-6 x 196 x 32 x 139 = 262

) = 1.03 x 48 x 10-6 x 12.76 x 196 x 32 x 139 = 550

= 5067 - 923 = 4144 kN  (Pe/P = 0.82)

Page 30: 24 m Span Pre Stressed Bridge

Centroid of tendons in tension zone = (6x60 + 10x110 +  8x160 + 4x260) / 28 = 135mm

Page 31: 24 m Span Pre Stressed Bridge

Mu / M = 4192 / 3154 = 1.33 ( > 1.15 ) hence strain in outermost tendon O.K.

Design the fixed and free end cantilever abutments to the 20m span deck shown to carry HA and 45 units of HB loading. Analyse the abutments using a unit strip method. The bridge site is located south east of Oxford (to establish the range of shade air temperatures).

The proposed deck consists of 11No. Y4 prestressed concrete beams and concrete deck slab as shown.

2400600

18802770

The ground investigation report shows suitable founding strata about 9.5m below the proposed road level. Test results show the founding strata to be a cohesionless soil having an angle of shearing resistance (φ) = 30

 and density (γ) = 19kN/m3.

From BS 5400 Part 2 Figures 7 and 8 the minimum and maximum shade air temperatures are -19 and +37oC respectively. 

For a Group 4 type strucutre (see fig. 9) the corresponding minimum and maximum effective bridge temperatures are -11 and +36oC from tables 10 and 11. 

From Clause 5.4.6 the range of movement at the free end of the 20m span deck = 47 x 12 x 10-6 x 20 x 103 = 11.3mm.] = ±[11.3 x 1.1 x 1.3 /2] = ± 8mm.

With a maximum ultimate reaction = 230 + 60 + 500 = 790kN then a suitable elastomeric bearing would be Ekspan's Elastomeric Pad Bearing EKR35:

Page 32: 24 m Span Pre Stressed Bridge

This is an ultimate load hence the nominal horizontal load = 121 / 1.1 / 1.3 = 85kN at each bearing.

This correllates with the value obtained above using the shear stiffness from the manufacturer's data sheet.

Note: the required shear deflection (8mm) should be limited to between 30% to 50% of the thickness of the bearing. The figure quoted in the catalogue for the maximum shear deflection is 70% of the thickness. 

A tolerance is also required for setting the bearing if the ambient temperature is not at the mid range temperature. The design shade air temperature range will be -19 to +37oC which would require the bearings to be installed at a shade air temperature of 9

With a maximum ultimate reaction of 790kN and longitudinal movement of ± 8mm then a suitable bearing from the Ekspan EA Series would be /80/210/25/25:

As the mating surface between the stainless steel and PTFE is smaller than the base plate then the pressure between the sliding faces will be in the order of 5N/mm2.

From Table3 of BS 5400 Part 9.1 the Coefficient of friction = 0.08 for a bearing stress of 5N/mm2

Hence total horizontal load on each abutment when the deck expands or contracts = 2220 x 0.08 = 180kN ≡ 180 / 11.6 = 16kN/m.

Page 33: 24 m Span Pre Stressed Bridge

There are a number of publications that will give guidance on base sizes for free standing cantilever walls, Reynolds's Reinforced Concrete Designer's Handbook being one such book.

Page 34: 24 m Span Pre Stressed Bridge

Check bearing pressure at toe and heel of base slab = (P / A) ± (P x e / Z) where P x e is the moment about the centre of the base.

1275

7639838143

1207

78428482

It can be seen that the use of elastomeric bearings (Case 2) will govern the critical design load cases on the abutments. We shall assume that there are no specific requirements for using elastomeric bearings and design the abutments for the lesser load effects by using sliding bearings.

Loads on the back of the wall are calculated using 'at rest' earth pressures. Serviceability and Ultimate load effects need to be calculated for the load cases 1 to 6 shown above. Again, these are best carried out using a simple spreadsheet.

o) = 523kN/m

Analysing the fixed abutment with Load Cases 1 to 6 and the free abutment with Load Cases 1 to 5 using a simple spreadsheet the following results were obtained:

Page 35: 24 m Span Pre Stressed Bridge

Analysing the fixed abutment with Load Cases 1 to 6 and the free abutment with Load Cases 1 to 5 using a simple spreadsheet the following results were obtained for the design moments and shear at the base of the wall:

Use strength class C32/40 with water-cement ratio 0.5 and minimum cement content of 340kg/m3 for exposure condition XD2.

 of 15mm).Reinforcement to BS 4449:2005 Grade B500B:   fy = 500N/mm2

Page 36: 24 m Span Pre Stressed Bridge

Maximum bending and shear effects in the base slab will occur at sections near the front and back of the wall. Different load factors are used for serviceability and ultimate limit states so the calculations need to be carried out for each limit state using 'at rest pressures'

Also the steel reinforcement and concrete stresses meet the limitations required in clause 4.1.1.3 ∴ serviceability requirements are satisfied.

 x (40)1/3 = 0.72

 < 0.673 hence shear reinforcement should be provided, however check shear at distance H/8 (8.63 / 8 = 1.079m) up the wall.

Considering the effects of casting the wall stem onto the base slab by complying with the early thermal cracking of concrete to BD 28 then B16 horizontal lacer bars @ 150 c/c will be required in both faces in the bottom half of the wall.

d = 0.0012 x 1000 x 920 = 1104 mm2/m (use B16 @ 150c/c - As = 1340mm2/m)

Page 37: 24 m Span Pre Stressed Bridge

 / 2) = 99kNm/m (tension in bottom face). 

 / 2) - (531 x 4.3 / 2) - (52 x 4.3 / 2) = -443kNm/m (tension in top face). 

Page 38: 24 m Span Pre Stressed Bridge

 / 3) - (1.15 x 25 x 1.0 x 1.12 / 2)} = 148kNm/m (tension in bottom face). 

Page 39: 24 m Span Pre Stressed Bridge

76815961834170014021717

ULSMoment816

1678192217861480

For the Serviceability check for Case 3 an approximation of the dead load moment can be obtained by removing the surcharge and braking loads. The spreadsheet result gives the dead load SLS moment for Case 3 as 723kNm, thus the live load moment = 1233 - 723 = 510kNm.

This could be corrected by reducing the bar spacing, but increase the bar size to B40@150 c/c as this is required to avoid the use of links (see below).

Analysing the fixed abutment with Load Cases 1 to 6 and the free abutment with Load Cases 1 to 5 using a simple spreadsheet the following results were obtained:

Carrying out the crack control calculation to Clause 5.8.8.2 gives a crack width of 0.27mm > 0.25mm ∴ Fail.

Also the steel reinforcement and concrete stresses meet the limitations required in clause 4.1.1.3 ∴ serviceability requirements are satisfied.

Page 40: 24 m Span Pre Stressed Bridge

ULS Shear on heel = 1.1 x {348 x 0.5 x (5.185 - 2.1) - 1.15 x 1 x 4.4 x 25 - 1.2 x 4.4 x (8.63 x 19 + 10)} = 559kN

This wall is designed to be cast onto the top of the abutment after the deck has been built. Loading will be applied from the backfill, surcharge and braking loads on top of the wall.HB braking load to BS 5400 clause 6.10 = 25% x 45units x 10kN on each axle = 112.5kN per axle.

 x (40)1/3 = 0.62

 x (40)1/3 = 0.62

 (also required for crack control as shown above).

 x (40)1/3 = 0.716

Considering the effects of casting the base slab onto the blinding concrete by complying with the early thermal cracking of concrete to BD 28 then B16 distribution bars @ 250 c/c will be required.

d = 0.0015 x 1000 x 924 = 1386 mm2/m (use B20 @ 200c/c - As = 1570mm2/m).

 dispersal to the curtain wall and a maximum dispersal of the width of the abutment (11.6m) then:

Page 41: 24 m Span Pre Stressed Bridge

ULS Moment = 1.1 x {(1.1 x 73.9 x 3.0) + (1.5 x 25.6 x 1.5) + (1.5 x 36.4 x 1.0)} = 392 kNm/m

116.020 166.15689.066 242.424

179.402

Page 42: 24 m Span Pre Stressed Bridge

Since concrete is weak in tension in normal reinforced concrete construction cracks develop in the tension zone at working loads and therefore all concrete in tension is ignored in design.Prestressing involves inducing compressive stresses in the zone which will tend to become tensile under external loads. This compressive stress neutralizes the tensile stress so that no resultant tension exists, (or only very small values, within the tensile strength of the concrete). Cracking is therefore eliminated under working load and all of the concrete may be assumed effective in carrying load. Therefore lighter sections may be used to carry a given bending moment, and prestressed concrete may be used over much longer spans than reinforced concrete.

 - sections may be used without the risk of diagonal tension failures and with further savings in self-weight.

Design a simply supported prestressed concrete Y beam which  carries a 150mm thick concrete slab and 100mm of surfacing, together with a nominal live load udl of 10.0 kN/m2 and kel of 33kN/m . The span of the beam is 24.0m centre to centre of bearings and the beams are spaced at 1.0m intervals.

Page 43: 24 m Span Pre Stressed Bridge

Self weight of beam and weight of deck slab is supported by the beam. When the deck slab concrete has cured then any further loading (superimposed and live loads) is supported by the composite section of the beam and slab.

Page 44: 24 m Span Pre Stressed Bridge

Design the fixed and free end cantilever abutments to the 20m span deck shown to carry HA and 45 units of HB loading. Analyse the abutments using a unit strip method. The bridge site is located south east of Oxford (to establish the range of shade air temperatures).

The ground investigation report shows suitable founding strata about 9.5m below the proposed road level. Test results show the founding strata to be a cohesionless soil having an angle of shearing resistance (φ) = 30o and a safe bearing capacity of 400kN/m2.

Page 45: 24 m Span Pre Stressed Bridge

Note: the required shear deflection (8mm) should be limited to between 30% to 50% of the thickness of the bearing. The figure quoted in the catalogue for the maximum shear deflection is 70% of the thickness. oC which would require the bearings to be installed at a shade air temperature of 9oC to achieve the ± 8mm movement. If the bearings are set at a maximum shade air temperature of 16

Page 46: 24 m Span Pre Stressed Bridge

It can be seen that the use of elastomeric bearings (Case 2) will govern the critical design load cases on the abutments. We shall assume that there are no specific requirements for using elastomeric bearings and design the abutments for the lesser load effects by using sliding bearings.

Loads on the back of the wall are calculated using 'at rest' earth pressures. Serviceability and Ultimate load effects need to be calculated for the load cases 1 to 6 shown above. Again, these are best carried out using a simple spreadsheet.

Page 47: 24 m Span Pre Stressed Bridge

Analysing the fixed abutment with Load Cases 1 to 6 and the free abutment with Load Cases 1 to 5 using a simple spreadsheet the following results were obtained for the design moments and shear at the base of the wall:

Page 48: 24 m Span Pre Stressed Bridge

Maximum bending and shear effects in the base slab will occur at sections near the front and back of the wall. Different load factors are used for serviceability and ultimate limit states so the calculations need to be carried out for each limit state using 'at rest pressures'

Considering the effects of casting the wall stem onto the base slab by complying with the early thermal cracking of concrete to BD 28 then B16 horizontal lacer bars @ 150 c/c will be required in both faces in the bottom half of the wall.

Page 49: 24 m Span Pre Stressed Bridge

For the Serviceability check for Case 3 an approximation of the dead load moment can be obtained by removing the surcharge and braking loads. The spreadsheet result gives the dead load SLS moment for Case 3 as 723kNm, thus the live load moment = 1233 - 723 = 510kNm.

Page 50: 24 m Span Pre Stressed Bridge

Prestressing involves inducing compressive stresses in the zone which will tend to become tensile under external loads. This compressive stress neutralizes the tensile stress so that no resultant tension exists, (or only very small values, within the tensile strength of the concrete). Cracking is therefore eliminated under working load and all of the concrete may be assumed effective in carrying load. Therefore lighter sections may be used to carry a given bending moment, and prestressed concrete may be used over much longer spans than reinforced concrete.

 and kel of 33kN/m . The span of the beam is 24.0m centre to centre of bearings and the beams are spaced at 1.0m intervals.

Page 51: 24 m Span Pre Stressed Bridge

C to achieve the ± 8mm movement. If the bearings are set at a maximum shade air temperature of 16oC then, by proportion the deck will expand 6mm and contract 10mm. Let us assume that this maximum shade air temperature of 16

Page 52: 24 m Span Pre Stressed Bridge

It can be seen that the use of elastomeric bearings (Case 2) will govern the critical design load cases on the abutments. We shall assume that there are no specific requirements for using elastomeric bearings and design the abutments for the lesser load effects by using sliding bearings.

Page 53: 24 m Span Pre Stressed Bridge

For the Serviceability check for Case 3 an approximation of the dead load moment can be obtained by removing the surcharge and braking loads. The spreadsheet result gives the dead load SLS moment for Case 3 as 723kNm, thus the live load moment = 1233 - 723 = 510kNm.

Page 54: 24 m Span Pre Stressed Bridge

Prestressing involves inducing compressive stresses in the zone which will tend to become tensile under external loads. This compressive stress neutralizes the tensile stress so that no resultant tension exists, (or only very small values, within the tensile strength of the concrete). Cracking is therefore eliminated under working load and all of the concrete may be assumed effective in carrying load. Therefore lighter sections may be used to carry a given bending moment, and prestressed concrete may be used over much longer spans than reinforced concrete.

Page 55: 24 m Span Pre Stressed Bridge

C to achieve the ± 8mm movement. If the bearings are set at a maximum shade air temperature of 16oC then, by proportion the deck will expand 6mm and contract 10mm. Let us assume that this maximum shade air temperature of 16

Page 56: 24 m Span Pre Stressed Bridge

Prestressing involves inducing compressive stresses in the zone which will tend to become tensile under external loads. This compressive stress neutralizes the tensile stress so that no resultant tension exists, (or only very small values, within the tensile strength of the concrete). Cracking is therefore eliminated under working load and all of the concrete may be assumed effective in carrying load. Therefore lighter sections may be used to carry a given bending moment, and prestressed concrete may be used over much longer spans than reinforced concrete.

Page 57: 24 m Span Pre Stressed Bridge

C then, by proportion the deck will expand 6mm and contract 10mm. Let us assume that this maximum shade air temperature of 16oC for fixing the bearings is specified in the Contract and design the abutments accordingly.

Page 58: 24 m Span Pre Stressed Bridge

Prestressing involves inducing compressive stresses in the zone which will tend to become tensile under external loads. This compressive stress neutralizes the tensile stress so that no resultant tension exists, (or only very small values, within the tensile strength of the concrete). Cracking is therefore eliminated under working load and all of the concrete may be assumed effective in carrying load. Therefore lighter sections may be used to carry a given bending moment, and prestressed concrete may be used over much longer spans than reinforced concrete.

Page 59: 24 m Span Pre Stressed Bridge

C for fixing the bearings is specified in the Contract and design the abutments accordingly.

Page 60: 24 m Span Pre Stressed Bridge

Prestressed Concrete

Since concrete is weak in tension in normal reinforced concrete construction cracks develop in the tension zone at working loads and therefore all concrete in tension is ignored in design.

Prestressing involves inducing compressive stresses in the zone which will tend to become tensile under external loads. This compressive stress neutralizes the tensile stress so that no resultant tension exists, (or only very small values, within the tensile strength of the concrete). Cracking is therefore eliminated under working load and all of the concrete may be assumed effective in carrying load. Therefore lighter sections may be used to carry a given bending moment, and prestressed concrete may be used over much longer spans than reinforced concrete.

The prestressing force has to be produced by a high tensile steel, and it is necessary to use high quality concrete to resist the higher compressive stresses that are developed.

There are two methods of prestressing concrete :

1) Pre-cast Pre-tensioned

2) Pre-cast Post-tensioned

Stage 1

Tendons and reinforcement are positioned in the beam mould.

Stage 2

Tendons are stressed to about 70% of their ultimate strength.

Stage 3

Concrete is cast into the beam mould and allowed to cure to the required initial strength.

Stage 4

When the concrete has cured the stressing force is released and the tendons anchor themselves in the concrete.

Stage 1

Cable ducts and reinforcement are positioned in the beam mould. The ducts are usually raised towards the neutral axis at the ends to reduce the eccentricity of the stressing force.

Stage 2

Concrete is cast into the beam mould and allowed to cure to the required initial strength.

Stage 3

Tendons are threaded through the cable ducts and tensioned to about 70% of their ultimate strength.

Stage 4

Wedges are inserted into the end anchorages and the tensioning force on the tendons is released. Grout is then pumped into the ducts to protect the tendons.

Loss of Prestress

When the tensioning force is released and the tendons are anchored to the concrete a series of effects result in a loss of stress in the tendons. The effects are:

The prestressing force also reduces the magnitude of the principal tensile stress in the web so that thin-webbed I - sections may be used without the risk of diagonal tension failures and with further savings in self-weight.

Both methods involve tensioning cables inside a concrete beam and then anchoring the stressed cables to the concrete. 

1) Pre-tensioned Beams 

2) Post-tensioned Beams 

Page 61: 24 m Span Pre Stressed Bridge

a. relaxation of the steel tendons

b. elastic deformation of the concrete

c. shrinkage and creep of the concrete

d. slip or movement of the tendons at the anchorages during anchoring

e. other causes in special circumstances , such as when steam curing is used with pre-tensioning.

Total losses in prestress can amount to about 30% of the initial tensioning stress.

Prestressed Concrete Beam Design to BS 5400 Part 4

Problem:

25 units of HB to be considered at SLS for load combination 1 only (BS 5400 Pt4 Cl. 4.2.2)

Nominal Dead Loads : slab = 24 x 0.15 x 1.0 = 3.6 kN/m

beam = say Y5 beam = 10.78 kN/m

surfacing = 24 x 0.1 x 1.0 = 2.4 kN/m

Nominal Live Load : HA = 10 x 1.0 + 33.0 = 10 kN/m + 33kN

25 units HB = 25 x 10 / 4 per wheel = 62.5 kN per wheel

Load factors for serviceability and ultimate limit state from BS 5400 Part 2 (or BD 37/01) Table 1:

Comb.1

Dead Load

Design a simply supported prestressed concrete Y beam which  carries a 150mm thick concrete slab and 100mm of surfacing, together with a nominal live load udl of 10.0 kN/m2 and kel of 33kN/m . The span of the beam is 24.0m centre to centre of bearings and the beams are spaced at 1.0m intervals.

γconc. = 24kN/mm3

Loading per beam (at 1.0m c/c)

γfL concrete1.0

Page 62: 24 m Span Pre Stressed Bridge

Superimposed Dead Load

Live Load 1.2

1.1

Temperature Difference -

BS 5400 Pt. 4

Section Properties

cl.7.4.1 Modular ratio effect for different concrete strengths between beam and slab may be ignored.

Property Beam Section Composite Section

4.49E+05

Centroid(mm) 456

###

###

###

Modulus @ Level 3(mm3) -

Temperature Difference Effects

γfL surfacing1.2

γfL HA

γfL HB

γfL

Concrete Grades 

Beam   fcu = 50 N/mm2, 

fci = 40 N/mm2 

Slab    fcu = 40 N/mm2

Area(mm2)

2nd Moment of Area(mm4)

Modulus @ Level 1(mm3)

Modulus @ Level 2(mm3)

Page 63: 24 m Span Pre Stressed Bridge

Apply temperature differences given in BS 5400 Pt2 Fig.9 (Group 4)to a simplified beam section.

Force F to restrain temperature strain :

Moment M about centroid of section to restrain curvature due to temperature strain :

Force F to restrain temperature strain :

Cl. 5.4.6 - Coefficient of thermal expansion = 12 x 10-6 per ºC.

From BS 5400 Pt4 Table 3 : Ec = 34 kN/mm2 for fcu = 50N/mm2 

Hence restrained temperature stresses per °C = 34 x 103 x 12 x 10-6 = 0.408 N/mm2

  

a) Positive temperature difference 

0.408 x 1000 x [ 150 x ( 3.0 + 5.25 ) ] x 10-3 +

0.408 x ( 300 x 250 x 1.5 + 750 x 200 x 1.25 ) x 10-3 = 504.9 + 122.4 = 627.3 kN

0.408 x 1000 x [ 150 x ( 3.0 x 502 + 5.25 x 527 ) ] x 10-6 +

0.408 x ( 300 x 250 x 1.5 x 344 - 750 x 200 x 1.25 x 556 ) x 10-6 = 261.5 - 26.7 = 234.8 kNm

b) Reverse temperature difference

- 0.408 x [ 1000 x 150 x ( 3.6 + 2.3 ) + 300 x 90 x ( 0.9 + 1.35 ) ] x 10-3 

- 0.408 x 300 x ( 200 x 0.45 + 150 x 0.45 ) x 10-3 

Page 64: 24 m Span Pre Stressed Bridge

Moment M about centroid of section to restrain curvature due to temperature strain :

= - 194.5 - 0.6 + 153.8 = - 41.3 kNm

Differential Shrinkage Effects

BS 5400 Pt.4 Use cl.6.7.2.4 Table 29 :

cl.7.4.3.4

BS 5400 Pt.4

cl.7.4.3.5

- 0.408 x 750 x [ 50 x ( 0.9 + 0.15 ) + 240 x ( 1.2 + 2.6 ) ] x 10-3 = - 385.9 - 19.3 - 295.1 = - 700.3 kN

- 0.408 x [ 150000 x ( 3.6 x 502 + 2.3 x 527 ) + 27000 x ( 0.9 x 382 + 1.35 x 397 ) ] x 10-6 

- 0.408 x 300 x ( 200 x 0.45 x 270 - 150 x 0.45 x 283 ) x 10-6 

+ 0.408 x 750 x [ 50 x ( 0.9 x 358 + 0.15 x 366 ) + 240 x ( 1.2 x 503 + 2.6 x 543 ) ] x 10-6 

Total shrinkage of insitu concrete = 300 x 10-6

Assume that 2/3 of the total shrinkage of the precast concrete takes place before the deck slab is cast and that the residual shrinkage is 100 x 10-6 ,

hence the differential shrinkage is 200 x 10-6

Force to restrain differential shrinkage : F = - εdiff x Ecf x Acf x φ 

F = -200 x 10-6 x 34 x 1000 x 150 x 0.43 = -439 kN

Eccentricity acent = 502mm

Restraint moment Mcs = -439 x 0.502 = -220.4 kNm

Page 65: 24 m Span Pre Stressed Bridge

Self weight of beam and weight of deck slab is supported by the beam. When the deck slab concrete has cured then any further loading (superimposed and live loads) is supported by the composite section of the beam and slab.

Total load for serviceability limit state = (1.0 x 3.6)+(1.0 x 10.78) = 14.4kN/m

Combination 1 Loading

Super. & HA live load for

Super. & HB live load for

Total load for ultimate limi

HA Design serviceability

25 units HB Design SLS m

Design ultimate moment

Combination 3 Loading

Dead Loading (beam and slab)

Design serviceability moment = 14.4 x 242 / 8 = 1037 kNm

= [(1.2 x 2.4)+(1.2 x 10)]udl & [(1.2 x 33)]kel

= (2.88 + 12.0)udl & 39.6kel

= 14.9 kN/m & 39.6kN

=  2.88 & 4 wheels @ 1.1 x 62.5

= 2.9 kN/m & 4 wheels @ 68.75 kN

=  [(1.15 x 3.6)+(1.15 x 10.78)+(1.75 x 2.4)+(1.5 x 10)]udl & [(1.5 x 33)]kel

= (4.14 + 12.40 + 4.20 + 15.0)udl & 49.5kel

= 35.7 kN/m & 49.5kN

= 14.9 x 24.02 / 8 + 39.6 x 24 / 4

=1310 kNm

= 2.9 x 24.02 / 8 + 982.3(from grillage analysis)

= 1191.1 kNm

= 35.7 x 24.02 / 8 + 49.5 x 24 / 4

= 2867 kNm

Page 66: 24 m Span Pre Stressed Bridge

Super. & HA live load for

Total load for ultimate limi

Design serviceability mom

Allowable stresses in precast concrete

cl.6.3.2.2 b)

cl.6.3.2.4 b)

At serviceability limit state :

cl.7.4.3.2 Compression (1.25 x Table 22)

Comb.1 Comb.1 Comb.3

- 8.94 - 8.94 - 8.94

=  [(1.2 x 2.4)+(1.0 x 10)]udl & [(1.0 x 33)]kel

= (2.88 + 10.0)udl & 33kel

= 12.9 kN/m & 33kN

=  [(1.15 x 3.6)+(1.15 x 10.78)+(1.75 x 2.4)+(1.25 x 10)]udl & [(1.25 x 33)]kel

=  (4.14 + 12.40 + 4.20 + 12.5)udl & 41.3kel

= 33.2 kN/m & 41.3kN

= 12.9 x 24.02 / 8 + 33 x 24 / 4

= 1127 kNm

 At transfer :

Compression ( Table 23 ) 

0.5fci (<=0.4fcu) = 20 N/mm2 max.

Tension = 1.0 N/mm2

1.25 x 0.4fcu = 25 N/mm2 

Tension = 0 N/mm2 (class 1) & 3.2 N/mm2 (class 2 - Table 24)

Stresses at Level 1 due to SLS loads (N/mm2) :

Dead Load   M / Z = (1037 x 106) / (116.020 x 106)

Page 67: 24 m Span Pre Stressed Bridge

- 7.88 - 7.17 - 6.78

- - -1.35

Differential shrinkage -0.60

Total Stress at Level 1 = -17.42

Hence Combination 3 is critical

Prestressing Force and Eccentricity

Using straight, fully bonded tendons (constant force and eccentricity).

Allow for 20% loss of prestress after transfer.

Initial prestress at Level 1 to satisfy class 2 requirement for SLS (Comb. 3).

The critical section at transfer occurs at the end of the transmission zone. The moment due to the self weight at this section is near zero and initial stress conditions are:

Hence 32 tendons required.

Super. & Live Load  M / Z = M / (166.156 x 106)

Reverse Temperature = γfL x -1.69 = 0.8 x -1.69

Stress at transfer = ( 17.67 - 3.2 ) / 0.8 = 18.1 N/mm2 (use allowable stress of 20 N/mm2)

P/A + Pe/Zlevel 1 = 20

P/A - Pe/Zlevel 2 >= - 1.0

(eqn. 1) x Zlevel 1 + (eqn. 2) x Zlevel 2 gives :

P >= A x (20 x Zlevel 1 - 1.0 x Zlevel 2) / (Zlevel 1 + Zlevel 2)

P = 449.22 x 103 x ( 20 x 116.02 - 89.066) / ( 116.02 + 89.066) x 10-3 = 4888 kN

Allow 10% for loss of force before and during transfer, then the initial force Po = 4888 / 0.9 = 5431kN

Using 15.2mm class 2 relaxation standard strand at maximum initial force of 174kN (0.75 x Pu)

Area of tendon = 139mm2

Nominal tensile strength = fpu =1670 N/mm2

Initial force Po = 32 x 174 = 5568 kN

P = 0.9 x 5568 = 5011 kN

Page 68: 24 m Span Pre Stressed Bridge

Substituting P = 5011 kN in (eqn. 2)

Arrange 32 tendons symmetrically about the Y-Y axis to achieve an eccentricity of about 216mm.

Taking moments about bottom of beam :

1000 = 2000

900 = 1800

260 = 1040

160 = 1280

10 @ 110 = 1100

60 = 360

7580

Allowing for 1% relaxation loss in steel before transfer and elastic deformation of concrete at transfer :

cl. 6.7.2.3

Initial stresses due to prestress at end of transmission zone :

e <= Zlevel 2 / A + Zlevel 2 / P = (89.066 x 106 / 449.22 x 103) + (89.066 x 106 / 5011 x 103)

e = 198 + 18 = 216 mm

 2 @

 2 @

 4 @

 8 @

6 @

32  

e = 456 - 7580 / 32 = 456 - 237 =219mm

P = 0.99 Po / [ 1 + Es x (Aps / A) x (1 + A x e2 / I) / Eci ]

P = 0.99 x Po / [ 1 + 196 x ( 32 x 139 / 449220) x (1 + 449220 x 2192 / 52.905 x 109) / 31 ]

P = 0.91 Po = 0.91 x 5568 = 5067 kN

 Level 1   : P / A x ( 1 + A x e / Zlevel 1 ) = 11.3 x ( 1 + 219 / 258 ) = 20.89 N/mm2

Page 69: 24 m Span Pre Stressed Bridge

Stress due to self weight of beam at mid span :

Initial stresses at mid span :

cl. 6.7.2.5

Loss of force after transfer due to :

cl. 6.7.2.2 Steel relaxation = 0.02 x 5568 = 111

cl. 6.7.2.4

cl. 6.7.2.5

Total Loss = 111 + 262 + 550 = 923 kN

Final stresses due to prestress after all loss of prestress at :

Level 1

Level 2

Combined stresses in final condition for worst effects of design loads, differential shrinkage and temperature difference :

Level 2   : P / A x ( 1 - A x e / Zlevel 2 ) = 11.3 x ( 1 - 219 / 198 ) = - 1.20 N/mm2

Moment due to self weight of beam at mid span = 10.78 x 242 / 8 = 776.2 kNm

@ Level 1 = - 776.2 / 116.02 = - 6.69 N/mm2

@ Level 2 = 776.2 / 89.066 = 8.71 N/mm2

Allowing for 2% relaxation loss in steel after transfer, concrete shrinkage εcs = 300 x 10-6

and concrete specific creep ct = 1.03 x 48 x 10-6 per N/mm2

Concrete shrinkage = (εcs x Es x Aps ) = 300 x 10-6 x 196 x 32 x 139 = 262

Concrete creep = ( ct x  fco x Es x Aps ) = 1.03 x 48 x 10-6 x 12.76 x 196 x 32 x 139 = 550

Final force after all loss of prestress = Pe = 5067 - 923 = 4144 kN  (Pe/P = 0.82)

f1,0.82P =  0.82 x 20.89 = 17.08 N/mm2

f2,0.82P = 0.82 x - 1.20 = - 0.98 N/mm2

Level 1, combination 1 HB : f = 17.08 - 16.71 = 0.37 N/mm2 (> 0 hence O.K.)

Level 1, combination 3 : f = 17.08 - 17.67 = - 0.59 N/mm2 (> - 3.2 hence O.K.)

Page 70: 24 m Span Pre Stressed Bridge

Level 2, combination 1 : f = - 0.98 + 1037 / 89.066 + 1310 / 242.424 + 1.64 = 17.71 (< 25 O.K.)

Ultimate Capacity of Beam and Deck Slab

(Composite Section)

cl. 6.3.3 Only steel in the tension zone is to be considered :

Effective depth from Level 3 = 1200 - 135 = 1065mm

Assume that the maximum design stress is developed in the tendons, then :

Tensile force in tendons Fp = 0.87 x 28 x 139 x 1670 x 10-3 = 5655 kN

Compressive force in concrete flange :

Let X = depth to neutral axis.

Compressive force in concrete web :

Equating forces to obtain X :

X = 659 mm

Determine depth to neutral axis by an iterative strain compatibility analysis

Try X = 659 mm as an initial estimate

Width of web at this depth = 247mm

Level 3. combination 3 : f = (1127 / 179.402) + (0.8 x 3.15) = 8.8 N/mm2 (< 25 O.K.)

Ultimate Design Moment = γf3 x M = 1.1 x 2867 = 3154 kNm

Centroid of tendons in tension zone = (6x60 + 10x110 +  8x160 + 4x260) / 28 = 135mm

Ff = 0.4 x 40 x 1000 x 150 x 10-3 = 2400 kN

Fw = 0.4 x 50 x [393 - (393 - 200) x (X - 150) / (671 x 2)] x (X - 150) x 10-3 

Fw = ( -2.876X2 + 8722.84X - 1243717) x 10-3

5655 = 2400 + ( -2.876X2 + 8722.84X - 1243717) x 10-3

Stress in tendon after losses = fpe = 4144 x 103 / (32 x 139) = 932 N/mm2

Prestrain εpe = fpe / Es = 932 / 200 x 103 = 0.0047

Page 71: 24 m Span Pre Stressed Bridge

Tensile force in tendons :

4976 kN

εpb6 = ε6 + εpe = -459 x 0.0035 / 659 + 0.0047 = 0.0022

εpb5 = ε5 + εpe = -359 * 0.0035 / 659 + 0.0047 = 0.0028

εpb4 = ε4 + εpe = 281 * 0.0035 / 659 + 0.0047 = 0.0062

εpb3 = ε3 + εpe = 381 * 0.0035 / 659 + 0.0047 = 0.0067

εpb2 = ε2 + εpe = 431 * 0.0035 / 659 + 0.0047 = 0.0069

εpb1 = ε1 + εpe = 481 * 0.0035 / 659 + 0.0047 = 0.0072

fpb6 = 0.0022 x 200 x 103 = 444 N/mm2

fpb5 = 0.0028 x 200 x 103 = 551 N/mm2

fpb4 = 1162 + 290 x (0.0062 - 0.0058) / 0.0065 = 1178 N/mm2

fpb3 = 1162 + 290 x (0.0067 - 0.0058) / 0.0065 = 1201 N/mm2

fpb2 = 1162 + 290 x (0.0069 - 0.0058) / 0.0065 = 1213 N/mm2

fpb1 = 1162 + 290 x (0.0072 - 0.0058) / 0.0065 = 1225 N/mm2

Fp6 = 2 x 139 x 444 x 10-3  = 124

Fp5 = 2 x 139 x 551 x 10-3 = 153

Fp4 = 4 x 139 x 1178 x 10-3 = 655

Fp3 = 8 x 139 x 1201 x 10-3 = 1336

Fp2 = 10 x 139 x 1213 x 10-3= 1686

Fp1 = 6 x 139 x 1225 x 10-3 = 1022

Page 72: 24 m Span Pre Stressed Bridge

Compressive force in concrete :

5658 kN

Fc > Ft therefore reduce depth to neutral axis and repeat the calculations.

Using a depth of 565mm will achieve equilibrium.

The following forces are obtained :

Taking Moments about the neutral axis :

Ff = 0.4 x 40 x 1000 x 150 x 10-3= 2400

Fw = 0.4 x 50 x 0.5 x (393 + 247) x (659 - 150) x 10-3= 3258

Fp6 = 134 Ff = 2400

Fp5 = 168  Fw = 2765

Fp4 = 675 Fc = 5165

Fp3 = 1382

Fp2 = 1746

Fp1 = 1060

Ft = 5165

Fp6 = 134 x -0.365 =-49

Fp5 = 168 x -0.265 = -45

Fp4 = 675 x 0.375 = 253

Fp3 = 1382 x 0.475 = 656

Fp2 = 1746 x 0.525 =917

Fp1 = 1060 x 0.575 = 610

Page 73: 24 m Span Pre Stressed Bridge

cl. 6.3.3.1 Mu / M = 4192 / 3154 = 1.33 ( > 1.15 ) hence strain in outermost tendon O.K.

Abutment Design Example to BD 30

Design the fixed and free end cantilever abutments to the 20m span deck shown to carry HA and 45 units of HB loading. Analyse the abutments using a unit strip method. The bridge site is located south east of Oxford (to establish the range of shade air temperatures).

Concrete Deck 180 230 1900 2400

Surfacing 30 60 320 600

HA udl+kel 160 265 1140 1880

45 units HB 350 500 1940 2770

Nominal loading on 1m length of abutment:

Ff = 2400 x 0.49 = 1176

Fw = 3258 x 0.207 = 674

Mu = 4192 kNm > 3154 kNm hence O.K.

The ground investigation report shows suitable founding strata about 9.5m below the proposed road level. Test results show the founding strata to be a cohesionless soil having an angle of shearing resistance (φ) = 30o and a safe bearing capacity of 400kN/m2.

Backfill material will be Class 6N with an effective angle of internal friction (ϕ') = 35o and density (γ) = 19kN/m3.

Nominal Reaction(kN) Ultimate Reaction(kN)Nominal Reaction(kN) Ultimate Reaction(kN)

Page 74: 24 m Span Pre Stressed Bridge

Horizontal load at bearing for 10mm contraction = 12.14 x 10 = 121kN.

This is an ultimate load hence the nominal horizontal load = 121 / 1.1 / 1.3 = 85kN at each bearing.

Alternatively using BS 5400 Part 9.1 Clause 5.14.2.6:

Using the Ekspan bearing EKR35

This correllates with the value obtained above using the shear stiffness from the manufacturer's data sheet.

BS 5400 Part 2 - Clause 5.4.7.3:

Deck Dead Load = (1900 + 320) / 11.6 = 191kN/m

HA live Load on Deck = 1140 / 11.6 = 98kN/m

HB live Load on Deck = 1940 / 11.6 = 167kN/m

From BS 5400 Part 2 Figures 7 and 8 the minimum and maximum shade air temperatures are -19 and +37oC respectively. 

For a Group 4 type strucutre (see fig. 9) the corresponding minimum and maximum effective bridge temperatures are -11 and +36oC from tables 10 and 11. 

Hence the temperature range = 11 + 36 = 47oC.

From Clause 5.4.6 the range of movement at the free end of the 20m span deck = 47 x 12 x 10-6 x 20 x 103 = 11.3mm.

The ultimate thermal movement in the deck will be ± [(11.3 / 2) γf3 γfL] = ±[11.3 x 1.1 x 1.3 /2] = ± 8mm.

Option 1 - Elastomeric Bearing:

With a maximum ultimate reaction = 230 + 60 + 500 = 790kN then a suitable elastomeric bearing would be Ekspan's Elastomeric Pad Bearing EKR35:

·         Maximum Load = 1053kN

·         Shear Deflection = 13.3mm

·         Shear Stiffness = 12.14kN/mm

·         Bearing Thickness = 19mm

Note: the required shear deflection (8mm) should be limited to between 30% to 50% of the thickness of the bearing. The figure quoted in the catalogue for the maximum shear deflection is 70% of the thickness. 

A tolerance is also required for setting the bearing if the ambient temperature is not at the mid range temperature. The design shade air temperature range will be -19 to +37oC which would require the bearings to be installed at a shade air temperature of 9oC to achieve the ± 8mm movement. If the bearings are set at a maximum shade air temperature of 16oC then, by proportion the deck will expand 6mm and contract 10mm. Let us assume that this maximum shade air temperature of 16oC for fixing the bearings is specified in the Contract and design the abutments accordingly.

Total horizontal load on each abutment = 11 x 85 = 935 kN ≡ 935 / 11.6 = 81kN/m.

H = AGδr/tq

·         Maximum Load = 1053kN

·         Area = 610 x 420 = 256200mm2

·         Nominl hardness = 60 IRHD

·         Bearing Thickness = 19mm

Shear modulus G from Table 8 = 0.9N/mm2

H = 256200 x 0.9 x 10-3 x 10 / 19 = 121kN

Option 2 - Sliding Bearing:

With a maximum ultimate reaction of 790kN and longitudinal movement of ± 8mm then a suitable bearing from the Ekspan EA Series would be /80/210/25/25:

·         Maximum Load = 800kN

·         Base Plate A dimension = 210mm

·         Base Plate B dimension = 365mm

·         Movement ± X = 12.5mm

Page 75: 24 m Span Pre Stressed Bridge

Average nominal dead load reaction = (1900 + 320) / 11 = 2220 / 11 = 200kN

Nominal Load for HA = 8kN/m x 20m + 250kN = 410kN

Nominal Load for HB = 25% of 45units x 10kN x 4axles = 450kN

450 > 410kN hence HB braking is critical.

When this load is applied on the deck it will act on the fixed abutment only.

Nominal Load = 300kN

300 < 450kN hence braking load is critical in the longitudinal direction.

When this load is applied on the deck it will act on the fixed abutment only.

Loading at Rear of Abutment

Backfill

Assume a surchage loading for the compaction plant to be equivalent to 30 units of HB

1) Stability Check

Initial Sizing for Base Dimensions

Alternatively a simple spreadsheet will achieve a result by trial and error.

Contact pressure under base plate = 200000 / (210 x 365) = 3N/mm2

As the mating surface between the stainless steel and PTFE is smaller than the base plate then the pressure between the sliding faces will be in the order of 5N/mm2.

From Table3 of BS 5400 Part 9.1 the Coefficient of friction = 0.08 for a bearing stress of 5N/mm2

Hence total horizontal load on each abutment when the deck expands or contracts = 2220 x 0.08 = 180kN ≡ 180 / 11.6 = 16kN/m.

Traction and Braking Load - BS 5400 Part 2 Clause 6.10:

Braking load on 1m width of abutment = 450 / 11.6 = 39kN/m.

Skidding Load - BS 5400 Part 2 Clause 6.11:

For Stability calculations use active earth pressures = Ka γ h

Ka for Class 6N material = (1-Sin35) / (1+Sin35) = 0.27

Density of Class 6N material = 19kN/m3

Active Pressure at depth h = 0.27 x 19 x h = 5.13h kN/m2

Hence Fb = 5.13h2/2 = 2.57h2kN/m

Surcharge - BS 5400 Part 2 Clause 5.8.2:

For HA loading surcharge = 10 kN/m2

For HB loading surcharge = 20 kN/m2

Hence Compaction Plant surcharge = 12 kN/m2.

For surcharge of w kN/m2 :

Fs = Ka w h = 0.27wh kN/m

There are a number of publications that will give guidance on base sizes for free standing cantilever walls, Reynolds's Reinforced Concrete Designer's Handbook being one such book.

Page 76: 24 m Span Pre Stressed Bridge

Load Combinations

Fixed Abutment Only

Backfill + HA surcharge + Deck dead load + HA on deck + Braking on deck

Weight of wall stem = 1.0 x 6.5 x 25 = 163kN/m

Weight of base = 6.4 x 1.0 x 25 = 160kN/m

Weight of backfill = 4.3 x 6.5 x 19 = 531kN/m

Weight of surcharge = 4.3 x 12 = 52kN/m

Surcharge Force Fs = 0.27 x 12 x 7.5 = 24 kN/m

Restoring Effects:

Weight Lever Arm Moment About A

Stem 163 1.6

Base 160 3.2

Backfill 531 4.25

Surcharge 52 4.25

∑ = 906 ∑ =3251

Overturning Effects:

F Lever Arm Moment About A

Backfill 144 2.5

Surcharge 24 3.75

∑ =168 ∑ =452

Backfill + Construction surcharge

Backfill + Construction

Sackfill + HA surcharge + Deck dead load + Deck contraction

Backfill + HA surcharge +

Backfill + HB surcharge + Deck

Backfill + HA surcharge + Deck

CASE 1 - Fixed Abutment

Density of reinforced concrete = 25kN/m3.

Backfill Force Fb = 0.27 x 19 x 7.52 / 2 = 144kN/m

Page 77: 24 m Span Pre Stressed Bridge

For sliding effects:

Active Force = Fb + Fs = 168kN/m

Bearing Pressure:

Check bearing pressure at toe and heel of base slab = (P / A) ± (P x e / Z) where P x e is the moment about the centre of the base.

P = 906kN/m

Nett moment = 3251 - 452 = 2799kNm/m

Eccentricity (e) of P about centre-line of base = 3.2 - (2799 / 906) = 0.111m

Pressure under base = (906 / 6.4) ± (906 x 0.111 / 6.827)

Hence the abutment will be stable for Case 1.

Fixed Abutment:

F of S Overturning F of S Sliding Bearing Pressure at Toe

Case 1 7.16 3.09

Case 2 2.87 2.13

Case 2a 4.31 2.64

Case 3 3.43 2.43

Case 4 4.48 2.63

Case 5 5.22 3.17

Case 6 3.8 2.62

Free Abutment:

F of S Overturning F of S Sliding

Factor of Safety Against Overturning = 3251 / 452 = 7.2 > 2.0 ∴ OK.

Frictional force on underside of base resisting movement = W tan(φ) = 906 x tan(30o) = 523kN/m

Factor of Safety Against Sliding = 523 / 168 = 3.1 > 2.0 ∴ OK.

A = 6.4m2/m

Z = 6.42 / 6 = 6.827m3/m

Pressure under toe = 142 + 15 = 157kN/m2 < 400kN/m2 ∴ OK.

Pressure under heel = 142 - 15 = 127kN/m2

Analysing the fixed abutment with Load Cases 1 to 6 and the free abutment with Load Cases 1 to 5 using a simple spreadsheet the following results were obtained:

Page 78: 24 m Span Pre Stressed Bridge

Case 1 7.15 3.09

Case 2 2.91 2.14

Case 2a 4.33 2.64

Case 3 3.46 2.44

Case 4 4.5 2.64

Case 5 5.22 3.16

It can be seen that the use of elastomeric bearings (Case 2) will govern the critical design load cases on the abutments. We shall assume that there are no specific requirements for using elastomeric bearings and design the abutments for the lesser load effects by using sliding bearings.

2) Wall and Base Design

Loads on the back of the wall are calculated using 'at rest' earth pressures. Serviceability and Ultimate load effects need to be calculated for the load cases 1 to 6 shown above. Again, these are best carried out using a simple spreadsheet.

Using the Fixed Abutment Load Case 1 again as an example of the calculations:

Wall Design

Serviceability = 1.0

Ultimate = 1.5

Surcharge Force Fs on the rear of the wall = 0.426 x 12 x 6.5 = 33kN/m

At the base of the Wall:

Fixed Abutment:

Moment Moment Moment

SLS Dead SLS Live ULS

Case 1 371 108 790

Case 2a 829 258 1771

Case 3 829 486 2097

Case 4 829 308 1877

Case 5 829 154 1622

Case 6 829 408 1985

Free Abutment:

Moment Moment Moment

Ko = 1 - Sin(ϕ') = 1 - Sin(35o) = 0.426

γfL for horizontal loads due to surcharge and backfill from BS 5400 Part 2 Clause 5.8.1.2:

γf3 = 1.0 for serviceability and 1.1 for ultimate (from BS 5400 Part 4 Clauses 4.2.2 and 4.2.3)

Backfill Force Fb on the rear of the wall = 0.426 x 19 x 6.52 / 2 = 171kN/m

Serviceability moment = (171 x 6.5 / 3) + (33 x 6.5 / 2) = 371 + 107 = 478kNm/m

Ultimate moment = 1.1 x 1.5 x 478 = 789kNm/m

Ultimate shear = 1.1 x 1.5 x (171 + 33) = 337kN/m

Analysing the fixed abutment with Load Cases 1 to 6 and the free abutment with Load Cases 1 to 5 using a simple spreadsheet the following results were obtained for the design moments and shear at the base of the wall:

Page 79: 24 m Span Pre Stressed Bridge

SLS Dead SLS Live ULS

Case 1 394 112 835

Case 2a 868 265 1846

Case 3 868 495 2175

Case 4 868 318 1956

Case 5 868 159 1694

Concrete to BS 8500:2006

Reinforced concrete walls are designed to BS 5400 Part 4 Clause 5.6.

Check classification to clause 5.6.1.1:

Ultimate axial load in wall from deck reactions = 2400 + 600 + 2770 = 5770 kN

Bending

Shear

Use strength class C32/40 with water-cement ratio 0.5 and minimum cement content of 340kg/m3 for exposure condition XD2.

Nominal cover to reinforcement = 60mm (45mm minimum cover plus a tolerance Δc of 15mm).Reinforcement to BS 4449:2005 Grade B500B:   fy = 500N/mm2

Design for critical moments and shear in Free Abutment: 

0.1fcuAc = 0.1 x 40 x 103 x 11.6 x 1 = 46400 kN > 5770

∴ design as a slab in accordance with clause 5.4

BS 5400 Part 4 Clause 5.4.2 → for reisitance moments in slabs design to clause 5.3.2.3:

z = {1 - [ 1.1fyAs) / (fcubd) ]} d

Use B40 @ 150 c/c:

As = 8378mm2/m,    d = 1000 - 60 - 20 = 920mm

z = {1 - [ 1.1 x 500 x 8378) / (40 x 1000 x 920) ]} d = 0.875d < 0.95d ∴ OK

Mu = (0.87fy)Asz = 0.87 x 500 x 8378 x 0.875 x 920 x 10-6 = 2934kNm/m > 2175kNn/m ∴ OK

Carrying out the crack control calculation to Clause 5.8.8.2 gives a crack width of 0.2mm < 0.25mm.

Also the steel reinforcement and concrete stresses meet the limitations required in clause 4.1.1.3 ∴ serviceability requirements are satisfied.

Page 80: 24 m Span Pre Stressed Bridge

Shear requirements are designed to BS 5400 clause 5.4.4:

ULS shear at Section 7H/8 for load case 4 = 487 kN

Hence height requiring strengthening = 1.073 x (0.673 - 0.62) / (0.673 - 0.53) = 0.4m < d.

Early Thermal Cracking

Base Design

Maximum bending and shear effects in the base slab will occur at sections near the front and back of the wall. Different load factors are used for serviceability and ultimate limit states so the calculations need to be carried out for each limit state using 'at rest pressures'

Using the Fixed Abutment Load Case 1 again as an example of the calculations:

Weight of wall stem = 1.0 x 6.5 x 25 x 1.0 = 163kN/m

Weight of base = 6.4 x 1.0 x 25 x 1.0 = 160kN/m

Weight of backfill = 4.3 x 6.5 x 19 x 1.0 = 531kN/m

Weight of surcharge = 4.3 x 12 x 1.0 = 52kN/m

Surcharge Force Fs = 0.426 x 12 x 7.5 x 1.0 = 38 kN/m

Restoring Effects:

Weight Lever ArmMoment About A

Stem 163 1.6 261

Base 160 3.2 512

Backfill 531 4.25 2257

Surcharge 52 4.25 221

v = V / (bd) = 619 x 103 / (1000 x 920) = 0.673 N/mm2

No shear reinforcement is required when v < ξsvc

ξs = (500/d)1/4 = (500 / 920)1/4 = 0.86

vc = (0.27/γm)(100As/bwd)1/3(fcu)1/3 = (0.27 / 1.25) x ({100 x 8378} / {1000 x 920})1/3 x (40)1/3 = 0.72

ξsvc = 0.86 x 0.72 = 0.62 N/mms < 0.673 hence shear reinforcement should be provided, however check shear at distance H/8 (8.63 / 8 = 1.079m) up the wall.

v = V / (bd) = 487 x 103 / (1000 x 920) = 0.53 N/mm2 < 0.62

Provide a 500 x 500 splay at the base of the wall with B32 @ 150c/c bars in sloping face.

Considering the effects of casting the wall stem onto the base slab by complying with the early thermal cracking of concrete to BD 28 then B16 horizontal lacer bars @ 150 c/c will be required in both faces in the bottom half of the wall.

Minimum area of secondary reinforcement to Clause 5.8.4.2 = 0.12% of bad = 0.0012 x 1000 x 920 = 1104 mm2/m (use B16 @ 150c/c - As = 1340mm2/m)

CASE 1 - Fixed Abutment Serviceability Limit State

γfL = 1.0     γf3 = 1.0

B/fill Force Fb = 0.426 x 19 x 7.52 x 1.0 / 2 = 228kN/m

Page 81: 24 m Span Pre Stressed Bridge

∑ = 906 ∑ = 3251

Overturning Effects:

F Lever ArmMoment About A

Backfill 228 2.5 570

Surcharge 38 3.75 143

∑ = 266 ∑ = 713

Bearing Pressure at toe and heel of base slab = (P / A) ± (P x e / Z)

P = 906kN/m

Nett moment = 3251 - 713 = 2538kNm/m

Eccentricity (e) of P about centre-line of base = 3.2 - (2538 / 906) = 0.399m

Pressure under base = (906 / 6.4) ± (906 x 0.399 / 6.827)

A = 6.4m2/m

Z = 6.42 / 6 = 6.827m3/m

Pressure under toe = 142 + 53 = 195kN/m2

Pressure under heel = 142 - 53 = 89kN/m2

Pressure at front face of wall = 89 + {(195 - 89) x 5.3 / 6.4} = 177kN/m2

Pressure at rear face of wall = 89 + {(195 - 89) x 4.3 / 6.4} = 160kN/m2

SLS Moment at a-a = (177 x 1.12 / 2) + ([195 - 177] x 1.12 / 3) - (25 x 1.0 x 1.12 / 2) = 99kNm/m (tension in bottom face). 

SLS Moment at b-b = (89 x 4.32 / 2) + ([160 - 89] x 4.32 / 6) - (25 x 1.0 x 4.32 / 2) - (531 x 4.3 / 2) - (52 x 4.3 / 2) = -443kNm/m (tension in top face). 

CASE 1 - Fixed Abutment Ultimate Limit State

γfL for concrete = 1.15

γfL for fill and surcharge(vetical) = 1.2

Page 82: 24 m Span Pre Stressed Bridge

Weight of wall stem = 1.0 x 6.5 x 25 x 1.15 = 187kN/m

Weight of base = 6.4 x 1.0 x 25 x 1.15 = 184kN/m

Weight of backfill = 4.3 x 6.5 x 19 x 1.2 = 637kN/m

Weight of surcharge = 4.3 x 12 x 1.2 = 62kN/m

Surcharge Force Fs = 0.426 x 12 x 7.5 x 1.5 = 58 kN/m

Restoring Effects:

Weight Lever Arm Moment About A

Stem 187 1.6

Base 184 3.2

Backfill 637 4.25

Surcharge 62 4.25

∑ = 1070 ∑ =

Overturning Effects:

F Lever Arm Moment About A

Backfill 341 2.5

Surcharge 58 3.75

∑ = 399 ∑ =

γfL for fill and surcharge(horizontal) = 1.5

Backfill Force Fb = 0.426 x 19 x 7.52 x 1.5 / 2 = 341kN/m

Page 83: 24 m Span Pre Stressed Bridge

Bearing Pressure at toe and heel of base slab = (P / A) ± (P x e / Z)

P = 1070kN/m

Nett moment = 3859 - 1071 = 2788kNm/m

Eccentricity (e) of P about centre-line of base = 3.2 - (2788 / 1070) = 0.594m

Pressure under base = (1070 / 6.4) ± (1070 x 0.594 / 6.827)

ULS Shear at a-a = 1.1 x {[(260 + 228) x 1.1 / 2] - (1.15 x 1.1 x 25)} = 260kN/m

/ 2) - (62 x 4.3 / 2)} = -769kNm/m (tension in top face).

Fixed Abutment Base:

Section a-a Section b-b

ULSShear SLSMoment ULSMomenULS Shear

Case 1 261 99 147 259

Case 2a 528 205 302 458

Case 3 593 235 340 553

Case 4 550 208 314 495

Case 5 610 241 348 327

Case 6 637 255 365 470

A = 6.4m2/m

Z = 6.42 / 6 = 6.827m3/m

Pressure under toe = 167 + 93 = 260kN/m2

Pressure under heel = 167 - 93 = 74kN/m2

Pressure at front face of wall = 74 + {(260 - 74) x 5.3 / 6.4} = 228kN/m2

Pressure at rear face of wall = 74 + {(260 - 74) x 4.3 / 6.4} = 199kN/m2

γf3 = 1.1

ULS Shear at b-b = 1.1 x {[(199 + 74) x 4.3 / 2] - (1.15 x 4.3 x 25) - 637 - 62} = 259kN/m 

ULS Moment at a-a = 1.1 x {(228 x 1.12 / 2) + ([260 - 228] x 1.12 / 3) - (1.15 x 25 x 1.0 x 1.12 / 2)} = 148kNm/m (tension in bottom face). 

SLS Moment at b-b = 1.1 x {(74 x 4.32 / 2) + ([199 -

74] x 4.32 / 6) - (1.15 x 25 x 1.0 x 4.32 / 2) - (637 x 4.3

Analysing the fixed abutment with Load Cases 1 to 6 and the free abutment with Load Cases 1 to 5 using a simple spreadsheet the following results were obtained:

Page 84: 24 m Span Pre Stressed Bridge

Free Abutment Base:

Section a-a Section b-b

ULSShear SLSMoment ULSMoment ULSShear

Case 1 267 101 151 266

Case 2a 534 207 305 466

Case 3 598 236 342 559

Case 4 557 211 317 504

Case 5 616 243 351 335

Design for shear and bending effects at sections a-a and b-b for the Free Abutment:

Bending

Use B32 @ 150 c/c:

For the Serviceability check for Case 3 an approximation of the dead load moment can be obtained by removing the surcharge and braking loads. The spreadsheet result gives the dead load SLS moment for Case 3 as 723kNm, thus the live load moment = 1233 - 723 = 510kNm.

This could be corrected by reducing the bar spacing, but increase the bar size to B40@150 c/c as this is required to avoid the use of links (see below).

Shear

Shear on Toe - Use Fixed Abutment Load Case 6:

By inspection B32@150c/c will be adequate for the

Shear requirements are designed to BS 5400 clause

5.7.3.2(a) checking shear at d away from the front face

of the wall to clause 5.4.4.1:

ULS Shear on toe = 1.1 x {(620 + 599) x 0.5 x 0.176 -

1.15 x 1 x 0.176 x 25} = 112kN

BS 5400 Part 4 Clause 5.7.3 → design as a slab for reisitance moments to clause 5.3.2.3:

z = {1 - [ 1.1fyAs) / (fcubd) ]} d

As = 5362mm2/m,    d = 1000 - 60 - 16 = 924mm

z = {1 - [ 1.1 x 500 x 5362) / (40 x 1000 x 924) ]} d = 0.92d < 0.95d ∴ OK

Mu = (0.87fy)Asz = 0.87 x 500 x 5362 x 0.92 x 924 x 10-6 = 1983kNm/m > 1922kNm/m ∴ OK

(1983kNm/m also > 1834kNm/m ∴ B32 @ 150 c/c suitable for fixed abutment.

Carrying out the crack control calculation to Clause 5.8.8.2 gives a crack width of 0.27mm > 0.25mm ∴ Fail.

Using B40@150c/c the crack control calculation gives a crack width of 0.17mm < 0.25mm OK.∴

Also the steel reinforcement and concrete stresses meet the limitations required in clause 4.1.1.3 ∴ serviceability requirements are satisfied.

bending effects in the toe (Muls = 365kNm < 1983kNm)

Page 85: 24 m Span Pre Stressed Bridge

Shear on Heel - Use Free Abutment Load Case 3:

Shear requirements are designed at the back face of the wall to clause 5.4.4.1:

Length of heel = (6.5 - 1.1 - 1.0) = 4.4m

ULS Shear on heel = 1.1 x {348 x 0.5 x (5.185 - 2.1) - 1.15 x 1 x 4.4 x 25 - 1.2 x 4.4 x (8.63 x 19 + 10)} = 559kN

Using B32@150 c/c then:

Early Thermal Cracking

v = V / (bd) = 112 x 103 / (1000 x 924) = 0.121 N/mm2

No shear reinforcement is required when v < ξsvc

Reinforcement in tension = B32 @ 150 c/c

ξs = (500/d)1/4 = (500 / 924)1/4 = 0.86

vc = (0.27/γm)(100As/bwd)1/3(fcu)1/3 = (0.27 / 1.25) x ({100 x 5362} / {1000 x 924})1/3 x (40)1/3 = 0.62

ξsvc = 0.86 x 0.62 = 0.53 N/mms > 0.121N/mms ∴ OK

v = V / (bd) = 559 x 103 / (1000 x 924) = 0.605 N/mm2

No shear reinforcement is required when v < ξsvc

ξs = (500/d)1/4 = (500 / 924)1/4 = 0.86

vc = (0.27/γm)(100As/bwd)1/3(fcu)1/3 = (0.27 / 1.25) x ({100 x 5362} / {1000 x 924})1/3 x (40)1/3 = 0.62

ξsvc = 0.86 x 0.62 = 0.53 N/mms < 0.605N/mms ∴ Fail

Rather than provide shear reinforcement try increasing bars to B40 @ 150 c/c (also required for crack control as shown above).

vc = (0.27/γm)(100As/bwd)1/3(fcu)1/3 = (0.27 / 1.25) x ({100 x 8378} / {1000 x 920})1/3 x (40)1/3 = 0.716

ξsvc = 0.86 x 0.716 = 0.616 N/mms > 0.605N/mms ∴ OK

Considering the effects of casting the base slab onto the blinding concrete by complying with the early thermal cracking of concrete to BD 28 then B16 distribution bars @ 250 c/c will be required.

Page 86: 24 m Span Pre Stressed Bridge

Local Effects

Curtain Wall

This wall is designed to be cast onto the top of the abutment after the deck has been built. Loading will be applied from the backfill, surcharge and braking loads on top of the wall.

HB braking load to BS 5400 clause 6.10 = 25% x 45units x 10kN on each axle = 112.5kN per axle.

1st axle load on back of abutment = 112.5 / 3.0 = 37.5kN/m

2nd axle load on back of abutment = 112.5 / 6.6 = 17.0kN/m

3rd & 4th axle loads on back of abutment = 2 x 112.5 / 11.6 = 19.4kN/m

Maximum load on back of abutment = 37.5 + 17.0 + 19.4 = = 73.9kN/m

Bending and Shear at Base of 3m High Curtain Wall

Horizontal load due to HB surcharge = 0.426 x 20 x 3.0 = 25.6 kN/m

SLS Moment = (73.9 x 3.0) + (25.6 x 1.5) + (36.4 x 1.0) = 297 kNm/m (36 dead + 261 live)

ULS Moment = 1.1 x {(1.1 x 73.9 x 3.0) + (1.5 x 25.6 x 1.5) + (1.5 x 36.4 x 1.0)} = 392 kNm/m

ULS Shear = 1.1 x {(1.1 x 73.9) + (1.5 x 25.6) + (1.5 x 36.4)} = 192kN/m

Minimum area of main reinforcement to Clause 5.8.4.1 = 0.15% of bad = 0.0015 x 1000 x 924 = 1386 mm2/m (use B20 @ 200c/c - As = 1570mm2/m).

Assume a 45o dispersal to the curtain wall and a maximum dispersal of the width of the abutment (11.6m) then:

Horizontal load due to backfill = 0.426 x 19 x 3.02 / 2 = 36.4 kN/m

400 thick curtain wall with B32 @ 150 c/c :

Mult = 584 kNm/m > 392 kNm/m ∴ OK

SLS Moment produces crack width of 0.21mm < 0.25 ∴ OK

ξsvc = 0.97 N/mm2 > v = 0.59 N/mm2 ∴ Shear OK

Page 87: 24 m Span Pre Stressed Bridge
Page 88: 24 m Span Pre Stressed Bridge

Since concrete is weak in tension in normal reinforced concrete construction cracks develop in the tension zone at working loads and therefore all concrete in tension is ignored in design.

Prestressing involves inducing compressive stresses in the zone which will tend to become tensile under external loads. This compressive stress neutralizes the tensile stress so that no resultant tension exists, (or only very small values, within the tensile strength of the concrete). Cracking is therefore eliminated under working load and all of the concrete may be assumed effective in carrying load. Therefore lighter sections may be used to carry a given bending moment, and prestressed concrete may be used over much longer spans than reinforced concrete.

The prestressing force has to be produced by a high tensile steel, and it is necessary to use high quality concrete to resist the higher compressive stresses that are developed.

When the concrete has cured the stressing force is released and the tendons anchor themselves in the concrete.

Cable ducts and reinforcement are positioned in the beam mould. The ducts are usually raised towards the neutral axis at the ends to reduce the eccentricity of the stressing force.

Tendons are threaded through the cable ducts and tensioned to about 70% of their ultimate strength.

Wedges are inserted into the end anchorages and the tensioning force on the tendons is released. Grout is then pumped into the ducts to protect the tendons.

When the tensioning force is released and the tendons are anchored to the concrete a series of effects result in a loss of stress in the tendons. The effects are:

The prestressing force also reduces the magnitude of the principal tensile stress in the web so that thin-webbed I - sections may be used without the risk of diagonal tension failures and with further savings in self-weight.

Both methods involve tensioning cables inside a concrete beam and then anchoring the stressed cables to the concrete. 

Page 89: 24 m Span Pre Stressed Bridge

e. other causes in special circumstances , such as when steam curing is used with pre-tensioning.

= 3.6 kN/m

= 10.78 kN/m

= 2.4 kN/m

= 10 kN/m + 33kN

= 62.5 kN per wheel

Load factors for serviceability and ultimate limit state from BS 5400 Part 2 (or BD 37/01) Table 1:

SLS ULS

Comb.3 Comb.1 Comb.3

1.0 1.15 1.15

Design a simply supported prestressed concrete Y beam which  carries a 150mm thick concrete slab and 100mm of surfacing, together with a nominal live load udl of 10.0 kN/m2 and kel of 33kN/m . The span of the beam is 24.0m centre to centre of bearings and the beams are spaced at 1.0m intervals.

Page 90: 24 m Span Pre Stressed Bridge

1.2 1.75 1.75

1.0 1.5 1.25

- - -

0.8 - 1.0

Modular ratio effect for different concrete strengths between beam and slab may be ignored.

Composite Section

5.99E+05

623

###

###

2.42E+08

###

Page 91: 24 m Span Pre Stressed Bridge

Apply temperature differences given in BS 5400 Pt2 Fig.9 (Group 4)to a simplified beam section.

 = 261.5 - 26.7 = 234.8 kNm

Page 92: 24 m Span Pre Stressed Bridge

 = - 385.9 - 19.3 - 295.1 = - 700.3 kN

- 0.408 x [ 150000 x ( 3.6 x 502 + 2.3 x 527 ) + 27000 x ( 0.9 x 382 + 1.35 x 397 ) ] x 10-6 

Assume that 2/3 of the total shrinkage of the precast concrete takes place before the deck slab is cast and that the residual shrinkage is 100 x 10-6 ,

Force to restrain differential shrinkage : F = - εdiff x Ecf x Acf x φ 

Page 93: 24 m Span Pre Stressed Bridge

Self weight of beam and weight of deck slab is supported by the beam. When the deck slab concrete has cured then any further loading (superimposed and live loads) is supported by the composite section of the beam and slab.

=  [(1.15 x 3.6)+(1.15 x 10.78)+(1.75 x 2.4)+(1.5 x 10)]udl & [(1.5 x 33)]kel

Page 94: 24 m Span Pre Stressed Bridge

(HA) (HB)

=  [(1.15 x 3.6)+(1.15 x 10.78)+(1.75 x 2.4)+(1.25 x 10)]udl & [(1.25 x 33)]kel

Page 95: 24 m Span Pre Stressed Bridge

-0.60 -0.60

-16.71 -17.67*

The critical section at transfer occurs at the end of the transmission zone. The moment due to the self weight at this section is near zero and initial stress conditions are:

.....................(eqn. 1)

.....................(eqn. 2)

 = 4888 / 0.9 = 5431kN

Using 15.2mm class 2 relaxation standard strand at maximum initial force of 174kN (0.75 x Pu)

Page 96: 24 m Span Pre Stressed Bridge

Arrange 32 tendons symmetrically about the Y-Y axis to achieve an eccentricity of about 216mm.

Allowing for 1% relaxation loss in steel before transfer and elastic deformation of concrete at transfer :

/ 52.905 x 109) / 31 ]

P = 0.91 Po = 0.91 x 5568 = 5067 kN

Page 97: 24 m Span Pre Stressed Bridge

Final stresses due to prestress after all loss of prestress at :

Combined stresses in final condition for worst effects of design loads, differential shrinkage and temperature difference :

Allowing for 2% relaxation loss in steel after transfer, concrete shrinkage εcs = 300 x 10-6

) = 300 x 10-6 x 196 x 32 x 139 = 262

) = 1.03 x 48 x 10-6 x 12.76 x 196 x 32 x 139 = 550

= 5067 - 923 = 4144 kN  (Pe/P = 0.82)

Page 98: 24 m Span Pre Stressed Bridge

Level 2, combination 1 : f = - 0.98 + 1037 / 89.066 + 1310 / 242.424 + 1.64 = 17.71 (< 25 O.K.)

Page 99: 24 m Span Pre Stressed Bridge
Page 100: 24 m Span Pre Stressed Bridge

Mu / M = 4192 / 3154 = 1.33 ( > 1.15 ) hence strain in outermost tendon O.K.

Design the fixed and free end cantilever abutments to the 20m span deck shown to carry HA and 45 units of HB loading. Analyse the abutments using a unit strip method. The bridge site is located south east of Oxford (to establish the range of shade air temperatures).

The ground investigation report shows suitable founding strata about 9.5m below the proposed road level. Test results show the founding strata to be a cohesionless soil having an angle of shearing resistance (φ) = 30o and a safe bearing capacity of 400kN/m2.

') = 35o and density (γ) = 19kN/m3.

Page 101: 24 m Span Pre Stressed Bridge

This is an ultimate load hence the nominal horizontal load = 121 / 1.1 / 1.3 = 85kN at each bearing.

This correllates with the value obtained above using the shear stiffness from the manufacturer's data sheet.

From BS 5400 Part 2 Figures 7 and 8 the minimum and maximum shade air temperatures are -19 and +37oC respectively. 

For a Group 4 type strucutre (see fig. 9) the corresponding minimum and maximum effective bridge temperatures are -11 and +36oC from tables 10 and 11. 

From Clause 5.4.6 the range of movement at the free end of the 20m span deck = 47 x 12 x 10-6 x 20 x 103 = 11.3mm.

] = ±[11.3 x 1.1 x 1.3 /2] = ± 8mm.

With a maximum ultimate reaction = 230 + 60 + 500 = 790kN then a suitable elastomeric bearing would be Ekspan's Elastomeric Pad Bearing EKR35:

Note: the required shear deflection (8mm) should be limited to between 30% to 50% of the thickness of the bearing. The figure quoted in the catalogue for the maximum shear deflection is 70% of the thickness. 

A tolerance is also required for setting the bearing if the ambient temperature is not at the mid range temperature. The design shade air temperature range will be -19 to +37oC which would require the bearings to be installed at a shade air temperature of 9oC to achieve the ± 8mm movement. If the bearings are set at a maximum shade air temperature of 16oC then, by proportion the deck will expand 6mm and contract 10mm. Let us assume that this maximum shade air temperature of 16oC for fixing the bearings is specified in the Contract and design the abutments accordingly.

With a maximum ultimate reaction of 790kN and longitudinal movement of ± 8mm then a suitable bearing from the Ekspan EA Series would be /80/210/25/25:

Page 102: 24 m Span Pre Stressed Bridge

As the mating surface between the stainless steel and PTFE is smaller than the base plate then the pressure between the sliding faces will be in the order of 5N/mm2.

From Table3 of BS 5400 Part 9.1 the Coefficient of friction = 0.08 for a bearing stress of 5N/mm2

Hence total horizontal load on each abutment when the deck expands or contracts = 2220 x 0.08 = 180kN ≡ 180 / 11.6 = 16kN/m.

There are a number of publications that will give guidance on base sizes for free standing cantilever walls, Reynolds's Reinforced Concrete Designer's Handbook being one such book.

Page 103: 24 m Span Pre Stressed Bridge

261

512

2257

221

361

91

Page 104: 24 m Span Pre Stressed Bridge

Check bearing pressure at toe and heel of base slab = (P / A) ± (P x e / Z) where P x e is the moment about the centre of the base.

Bearing Pressure at Toe Bearing Pressure at Heel

156 127

386 5

315 76

351 39

322 83

362 81

378 43

Bearing Pressure at Bearing Pressure at Heel

Frictional force on underside of base resisting movement = W tan(φ) = 906 x tan(30o) = 523kN/m

Analysing the fixed abutment with Load Cases 1 to 6 and the free abutment with Load Cases 1 to 5 using a simple spreadsheet the following results were obtained:

Page 105: 24 m Span Pre Stressed Bridge

168 120

388 7

318 78

354 42

325 84

365 82

It can be seen that the use of elastomeric bearings (Case 2) will govern the critical design load cases on the abutments. We shall assume that there are no specific requirements for using elastomeric bearings and design the abutments for the lesser load effects by using sliding bearings.

Loads on the back of the wall are calculated using 'at rest' earth pressures. Serviceability and Ultimate load effects need to be calculated for the load cases 1 to 6 shown above. Again, these are best carried out using a simple spreadsheet.

Shear

ULS

337

566

596

602

543

599

Shear

 = 1.0 for serviceability and 1.1 for ultimate (from BS 5400 Part 4 Clauses 4.2.2 and 4.2.3)

Analysing the fixed abutment with Load Cases 1 to 6 and the free abutment with Load Cases 1 to 5 using a simple spreadsheet the following results were obtained for the design moments and shear at the base of the wall:

Page 106: 24 m Span Pre Stressed Bridge

ULS

350

581

612

619

559

Use strength class C32/40 with water-cement ratio 0.5 and minimum cement content of 340kg/m3 for exposure condition XD2.

Nominal cover to reinforcement = 60mm (45mm minimum cover plus a tolerance Δc of 15mm).Reinforcement to BS 4449:2005 Grade B500B:   fy = 500N/mm2

 > 2175kNn/m ∴ OK

Also the steel reinforcement and concrete stresses meet the limitations required in clause 4.1.1.3 ∴ serviceability requirements are satisfied.

Page 107: 24 m Span Pre Stressed Bridge

Maximum bending and shear effects in the base slab will occur at sections near the front and back of the wall. Different load factors are used for serviceability and ultimate limit states so the calculations need to be carried out for each limit state using 'at rest pressures'

1/3 x (40)1/3 = 0.72

 < 0.673 hence shear reinforcement should be provided, however check shear at distance H/8 (8.63 / 8 = 1.079m) up the wall.

Considering the effects of casting the wall stem onto the base slab by complying with the early thermal cracking of concrete to BD 28 then B16 horizontal lacer bars @ 150 c/c will be required in both faces in the bottom half of the wall.

d = 0.0012 x 1000 x 920 = 1104 mm2/m (use B16 @ 150c/c - As = 1340mm2/m)

Page 108: 24 m Span Pre Stressed Bridge

 / 2) = 99kNm/m (tension in bottom face). 

 / 2) - (531 x 4.3 / 2) - (52 x 4.3 / 2) = -443kNm/m (tension in top face). 

Page 109: 24 m Span Pre Stressed Bridge

299

589

2707

264

3859

853

218

1071

Page 110: 24 m Span Pre Stressed Bridge

SLS MomeULS Moment

447 768

980 1596

1178 1834

1003 1700

853 1402

1098 1717

 / 3) - (1.15 x 25 x 1.0 x 1.12 / 2)} = 148kNm/m (tension in bottom face). 

Analysing the fixed abutment with Load Cases 1 to 6 and the free abutment with Load Cases 1 to 5 using a simple spreadsheet the following results were obtained:

Page 111: 24 m Span Pre Stressed Bridge

SLSMoment ULSMoment

475 816

1029 1678

1233 1922

1055 1786

901 1480

For the Serviceability check for Case 3 an approximation of the dead load moment can be obtained by removing the surcharge and braking loads. The spreadsheet result gives the dead load SLS moment for Case 3 as 723kNm, thus the live load moment = 1233 - 723 = 510kNm.

This could be corrected by reducing the bar spacing, but increase the bar size to B40@150 c/c as this is required to avoid the use of links (see below).

 > 1922kNm/m ∴ OK

Carrying out the crack control calculation to Clause 5.8.8.2 gives a crack width of 0.27mm > 0.25mm ∴ Fail.

Also the steel reinforcement and concrete stresses meet the limitations required in clause 4.1.1.3 ∴ serviceability requirements are satisfied.

Page 112: 24 m Span Pre Stressed Bridge

ULS Shear on heel = 1.1 x {348 x 0.5 x (5.185 - 2.1) - 1.15 x 1 x 4.4 x 25 - 1.2 x 4.4 x (8.63 x 19 + 10)} = 559kN

1/3 x (40)1/3 = 0.62

1/3 x (40)1/3 = 0.62

 (also required for crack control as shown above).

1/3 x (40)1/3 = 0.716

Considering the effects of casting the base slab onto the blinding concrete by complying with the early thermal cracking of concrete to BD 28 then B16 distribution bars @ 250 c/c will be required.

Page 113: 24 m Span Pre Stressed Bridge

This wall is designed to be cast onto the top of the abutment after the deck has been built. Loading will be applied from the backfill, surcharge and braking loads on top of the wall.

HB braking load to BS 5400 clause 6.10 = 25% x 45units x 10kN on each axle = 112.5kN per axle.

SLS Moment = (73.9 x 3.0) + (25.6 x 1.5) + (36.4 x 1.0) = 297 kNm/m (36 dead + 261 live)

ULS Moment = 1.1 x {(1.1 x 73.9 x 3.0) + (1.5 x 25.6 x 1.5) + (1.5 x 36.4 x 1.0)} = 392 kNm/m

116.020 166.156

d = 0.0015 x 1000 x 924 = 1386 mm2/m (use B20 @ 200c/c - As = 1570mm2/m).

 dispersal to the curtain wall and a maximum dispersal of the width of the abutment (11.6m) then:

Page 114: 24 m Span Pre Stressed Bridge

89.066 242.424

179.402

Page 115: 24 m Span Pre Stressed Bridge

Since concrete is weak in tension in normal reinforced concrete construction cracks develop in the tension zone at working loads and therefore all concrete in tension is ignored in design.

Prestressing involves inducing compressive stresses in the zone which will tend to become tensile under external loads. This compressive stress neutralizes the tensile stress so that no resultant tension exists, (or only very small values, within the tensile strength of the concrete). Cracking is therefore eliminated under working load and all of the concrete may be assumed effective in carrying load. Therefore lighter sections may be used to carry a given bending moment, and prestressed concrete may be used over much longer spans than reinforced concrete.

 - sections may be used without the risk of diagonal tension failures and with further savings in self-weight.

Page 116: 24 m Span Pre Stressed Bridge

Design a simply supported prestressed concrete Y beam which  carries a 150mm thick concrete slab and 100mm of surfacing, together with a nominal live load udl of 10.0 kN/m2 and kel of 33kN/m . The span of the beam is 24.0m centre to centre of bearings and the beams are spaced at 1.0m intervals.

Page 117: 24 m Span Pre Stressed Bridge

Self weight of beam and weight of deck slab is supported by the beam. When the deck slab concrete has cured then any further loading (superimposed and live loads) is supported by the composite section of the beam and slab.

Page 118: 24 m Span Pre Stressed Bridge

Design the fixed and free end cantilever abutments to the 20m span deck shown to carry HA and 45 units of HB loading. Analyse the abutments using a unit strip method. The bridge site is located south east of Oxford (to establish the range of shade air temperatures).

The ground investigation report shows suitable founding strata about 9.5m below the proposed road level. Test results show the founding strata to be a cohesionless soil having an angle of shearing resistance (φ) = 30o and a safe bearing capacity of 400kN/m2.

Page 119: 24 m Span Pre Stressed Bridge

Note: the required shear deflection (8mm) should be limited to between 30% to 50% of the thickness of the bearing. The figure quoted in the catalogue for the maximum shear deflection is 70% of the thickness. 

A tolerance is also required for setting the bearing if the ambient temperature is not at the mid range temperature. The design shade air temperature range will be -19 to +37oC which would require the bearings to be installed at a shade air temperature of 9oC to achieve the ± 8mm movement. If the bearings are set at a maximum shade air temperature of 16oC then, by proportion the deck will expand 6mm and contract 10mm. Let us assume that this maximum shade air temperature of 16oC for fixing the bearings is specified in the Contract and design the abutments accordingly.

Page 120: 24 m Span Pre Stressed Bridge

It can be seen that the use of elastomeric bearings (Case 2) will govern the critical design load cases on the abutments. We shall assume that there are no specific requirements for using elastomeric bearings and design the abutments for the lesser load effects by using sliding bearings.

Loads on the back of the wall are calculated using 'at rest' earth pressures. Serviceability and Ultimate load effects need to be calculated for the load cases 1 to 6 shown above. Again, these are best carried out using a simple spreadsheet.

Analysing the fixed abutment with Load Cases 1 to 6 and the free abutment with Load Cases 1 to 5 using a simple spreadsheet the following results were obtained for the design moments and shear at the base of the wall:

Page 121: 24 m Span Pre Stressed Bridge

Maximum bending and shear effects in the base slab will occur at sections near the front and back of the wall. Different load factors are used for serviceability and ultimate limit states so the calculations need to be carried out for each limit state using 'at rest pressures'

Considering the effects of casting the wall stem onto the base slab by complying with the early thermal cracking of concrete to BD 28 then B16 horizontal lacer bars @ 150 c/c will be required in both faces in the bottom half of the wall.

Page 122: 24 m Span Pre Stressed Bridge

For the Serviceability check for Case 3 an approximation of the dead load moment can be obtained by removing the surcharge and braking loads. The spreadsheet result gives the dead load SLS moment for Case 3 as 723kNm, thus the live load moment = 1233 - 723 = 510kNm.

Page 123: 24 m Span Pre Stressed Bridge

Prestressing involves inducing compressive stresses in the zone which will tend to become tensile under external loads. This compressive stress neutralizes the tensile stress so that no resultant tension exists, (or only very small values, within the tensile strength of the concrete). Cracking is therefore eliminated under working load and all of the concrete may be assumed effective in carrying load. Therefore lighter sections may be used to carry a given bending moment, and prestressed concrete may be used over much longer spans than reinforced concrete.

Page 124: 24 m Span Pre Stressed Bridge

 and kel of 33kN/m . The span of the beam is 24.0m centre to centre of bearings and the beams are spaced at 1.0m intervals.

Page 125: 24 m Span Pre Stressed Bridge

C to achieve the ± 8mm movement. If the bearings are set at a maximum shade air temperature of 16oC then, by proportion the deck will expand 6mm and contract 10mm. Let us assume that this maximum shade air temperature of 16oC for fixing the bearings is specified in the Contract and design the abutments accordingly.

Page 126: 24 m Span Pre Stressed Bridge

It can be seen that the use of elastomeric bearings (Case 2) will govern the critical design load cases on the abutments. We shall assume that there are no specific requirements for using elastomeric bearings and design the abutments for the lesser load effects by using sliding bearings.

Page 127: 24 m Span Pre Stressed Bridge

For the Serviceability check for Case 3 an approximation of the dead load moment can be obtained by removing the surcharge and braking loads. The spreadsheet result gives the dead load SLS moment for Case 3 as 723kNm, thus the live load moment = 1233 - 723 = 510kNm.

Page 128: 24 m Span Pre Stressed Bridge

Prestressing involves inducing compressive stresses in the zone which will tend to become tensile under external loads. This compressive stress neutralizes the tensile stress so that no resultant tension exists, (or only very small values, within the tensile strength of the concrete). Cracking is therefore eliminated under working load and all of the concrete may be assumed effective in carrying load. Therefore lighter sections may be used to carry a given bending moment, and prestressed concrete may be used over much longer spans than reinforced concrete.

Page 129: 24 m Span Pre Stressed Bridge

C to achieve the ± 8mm movement. If the bearings are set at a maximum shade air temperature of 16oC then, by proportion the deck will expand 6mm and contract 10mm. Let us assume that this maximum shade air temperature of 16oC for fixing the bearings is specified in the Contract and design the abutments accordingly.

Page 130: 24 m Span Pre Stressed Bridge

Prestressing involves inducing compressive stresses in the zone which will tend to become tensile under external loads. This compressive stress neutralizes the tensile stress so that no resultant tension exists, (or only very small values, within the tensile strength of the concrete). Cracking is therefore eliminated under working load and all of the concrete may be assumed effective in carrying load. Therefore lighter sections may be used to carry a given bending moment, and prestressed concrete may be used over much longer spans than reinforced concrete.

Page 131: 24 m Span Pre Stressed Bridge

C then, by proportion the deck will expand 6mm and contract 10mm. Let us assume that this maximum shade air temperature of 16oC for fixing the bearings is specified in the Contract and design the abutments accordingly.

Page 132: 24 m Span Pre Stressed Bridge

Prestressing involves inducing compressive stresses in the zone which will tend to become tensile under external loads. This compressive stress neutralizes the tensile stress so that no resultant tension exists, (or only very small values, within the tensile strength of the concrete). Cracking is therefore eliminated under working load and all of the concrete may be assumed effective in carrying load. Therefore lighter sections may be used to carry a given bending moment, and prestressed concrete may be used over much longer spans than reinforced concrete.

Page 133: 24 m Span Pre Stressed Bridge

C for fixing the bearings is specified in the Contract and design the abutments accordingly.


Recommended