+ All Categories

2

Date post: 27-May-2017
Category:
Upload: zankar-parikh
View: 234 times
Download: 6 times
Share this document with a friend
105
11 | Page CHAPTER -2 CONSTRUCTION MATERIALS 1.0 GENERAL Flood management and river training works in the form of embankment, bank revetment, spurs, porcupines, sluices, Gabions, Retaining walls, Diaphragm walls etc. are provided to manage/control the floods, to check the bank erosion and to improve drainage system. Construction of these works makes use of different kind of materials depending on the nature of problem and the structure provided. 2.0 TYPE OF CONSTRUCTION MATERIALS Different construction materials have their own uniqueness and are used according to the site conditions, availability, transportability, cost effectiveness, low maintenance cost etc. Materials like boulders, timber are in use since ages, but due to their increased usage in other sectors leading towards reduced supply and their environment un-friendly nature, use of them now-a-days is decreasing. High wear and tear of timber structures in underwater and near water situation makes it less suitable for their use in anti- erosion measures. Nowa-days, new innovative materials like Geo-textile in the form of Geo-textile bags, Geo-textile tubes, Sand filled Geo-mattress, Neo- web, submerged vanes and RCC porcupines, Gabions, Steel Sheet Piles ,Diaphragm walls are being increasingly used in construction of revetments, spurs, groynes, embankments etc. These materials are used due to their unique characteristics like durability, resistance to chemical waste, environment friendly nature, easiness in installation etc. Different construction materials being used for structural measures for flood management are described below in detail. 2.1.1 RIVER BED MATERIALS Considering economy and ease in availability, river bed materials including sand and boulders are widely used in flood management and Flood Protection works. However, rounded river boulders are used in contained forms like gabions/crates but avoided in loose for pitching of the banks. 2.1.1.1 SOIL The soil is used as a fill material for flood embankments and spurs. The soil is also used for filling Geo-textile bags, mattress and tubes. The soil shall preferably be coarse sand and free from organic material. Loamy and clayey type soil should be avoided
Transcript
Page 1: 2

11 | P a g e

CHAPTER -2 CONSTRUCTION MATERIALS

1.0 GENERAL

Flood management and river training works in the form of

embankment, bank revetment, spurs, porcupines, sluices, Gabions, Retaining walls, Diaphragm walls etc. are provided to manage/control the floods, to check the bank erosion and to improve drainage system. Construction of these works makes use of different kind of materials depending on the nature of problem and the structure provided.

2.0 TYPE OF CONSTRUCTION MATERIALS

Different construction materials have their own uniqueness and are used according to the site conditions, availability, transportability, cost effectiveness, low maintenance cost etc.

Materials like boulders, timber are in use since ages, but due to their

increased usage in other sectors leading towards reduced supply and their environment un-friendly nature, use of them now-a-days is decreasing. High wear and tear of timber structures in underwater and near water situation makes it less suitable for their use in anti- erosion measures.

Now–a-days, new innovative materials like Geo-textile in the form of Geo-textile bags, Geo-textile tubes, Sand filled Geo-mattress, Neo-web, submerged vanes and RCC porcupines, Gabions, Steel Sheet Piles ,Diaphragm walls are being increasingly used in construction of revetments, spurs, groynes, embankments etc. These materials are used due to their unique characteristics like durability, resistance to chemical waste, environment friendly nature, easiness in installation etc. Different construction materials being used for structural measures for flood management are described below in detail.

2.1.1 RIVER BED MATERIALS

Considering economy and ease in availability, river bed materials including sand and boulders are widely used in flood management and Flood Protection works. However, rounded river boulders are used in contained forms like gabions/crates but avoided in loose for pitching of the banks.

2.1.1.1 SOIL

The soil is used as a fill material for flood embankments and spurs. The soil is also used for filling Geo-textile bags, mattress and tubes. The soil shall preferably be coarse sand and free from organic material. Loamy and clayey type soil should be avoided

Page 2: 2

2

2.1.1.2

2.1.2

2.1.3

BOULDER

BouconembweibouthicTherela

GI WIRE

Figure 2-1

REVET-M

Revet-mamattressdouble where proportioRevet differentto its linto sediaphrag

.

RS

ulders arnstruction bankmentight, gradaulders in ackness. The bouldersatively flat

MESH

: A wire-me

MATTRES

attress s made twisted the dept

on to its mattre

tiated withlesser heieveral celgms.

e naturamaterial in, bank revation playsa revetmenhe boulderss should h faces. Rou

esh gabion

SS

is recwith h

steel wirth is slength an

ess canh the gabight. It islls by tr

lly availan various vetment, ss an impont should s used shohave sharpunded bou

When bouldersfilled witgabions hexagonfilled wiCrates Openingsmaller boulder/

ctangular hexagonal e mesh,

small in nd width. n be bions due s divided ransverse

able mateworks, inc

spurs etc. ortant role be well gr

ould be anp clean edulders shou

approprias are not ath the bou are rect

nal doubleith the smare small

g of the gathan

/cobble so

Figure 2-2steel wire

erials andcluding slo The boul in their eraded throgular and

dges at theuld be avoi

ate size available, gulders shotangular e twist s

mall size bler in sizabions or the size

o that they

2: Hexagon mesh, reve

12

d are usope protecders shapeffective uoughout th regular ine intersectided.

and gabions or

ould be useboxes ma

steel wire boulders/ce than gcrates shoe of s are kept i

nal double tt-mattress

2 | P a g e

sed as tion for

pe, size, se. The

he layer n shape. tions of

quality r crates ed. The ade of mesh

cobbles. abions. ould be mallest ntact.

twist

Page 3: 2

2.1.4

2.1.5

REINFOR

Figure

GEO-SYN

A synthetnon-wovequality afiltration,applicatiobags/tubname givstipulatedimportanttheir appl

The geo-functions

Table 2 : Id

Type of

Geo-textiGeo-grid Geo-net Geo-memGeo-syntLiner Geo-foamGeo-cellsGeo-comGeo-texti

RCED CEMPORC

e 2-3: A sketc

NTHETICS

tic materiaen, permeaand perfor separat

on in fles, geo-mven to ald by Indt productslication.

-syntheticss, as descri

dentification

f Geo-synthetic

ile

mbrane thetic Clay

m s posite ile tube & ba

MENT CONCUPINES

h of typical R

S

al in the able, waterrmance intion, reinood man

membrane, l these m

dian Roads of geosy

s have dibed below

n of the usu

Separatio

g

NCRETE

RCC porcupin

form of str tight men differentnforcemennagement

geo-grid, materials d Congresynthetic a

different aw in Table 2

ual primary synthetic

on Reinforcet

ne

Rein(RCconporeasdurFurporsectreplconscre

trong fleximbranes et applicatt and

works, geo-mattris referre

ss (IRC:SPare been d

application2-1 below:

function foc emen Filtrat

nforced cCC) is mnstruction cupine se of corability arther decupines tion 6. Thlacing th

nstruction eens.

ble sheetsetc is usedtions like protectionproducts

ress are ud as “geoP 59)publdescribed i

ns and p

or each type

tion Drainag

13

cement comainly us

of screens dnstructionand low tails of are give

he use of he timb

of por

s either wod to improlining, dr

n. For like geo

used. The o-syntheticlications n brief alo

perform d

e of geo-

ge Containm

3 | P a g e

oncrete ed for

RCC due to n,longer

cost. RCC

en in RCC is er in rcupine

oven or ove soil rainage, specific o-textile generic cs”. As major ng with

different

ment

Page 4: 2

2.

2.

2.

.1.5.1 G

.1.5.2 G

Gpsacdidd

.1.5.3 G

GEO-TEXT

GEO-MEM

Geo-membpolymeric mstorage faand othercontainmendifferent tyncreasing dams and density pol

GEO-GRID

TILE

MBRANE

brane matmaterial, ucilities. Th

r containmnt as a liqypes as pe in areas spillways

lyethylene)

D

terials areused primhis includ

ment facilquid or moer density of soil staetc. These) and LDPE

The bageo-texused ppolyestprocessas wovare mathroughgeo-texdistribuwhich therma

e relativelarily for lides all tylities. Thuoisture baand textu

abilization,e membranE (Low den

Adfoagm

(a)

(b)

(c)

asic raw mxtile is polpolymeres er. Baseds, geo- teven or nonanufactureh warp t

xtile is puted cont

are bonally or mech

ly thin ainings andypes of laus the prrrier or b

ure. Use of landfills, nes can bensity polye

A geo-grdeformed gformed byat junctiogeo-grid ismechanism

) Either sdirectionpropertie

) Made omachinemanufac

   By bondi

material wlymer and are po

d upon thextile is on woven. Wed by weathread. Wproduced tinuous o

nded togehanically

and imperd covers of andfills, rerimary funoth. Geo- f geo- mem lagoons, le classifiedthylene).

id is grid like py intersecons. Mains reinforcemm. Geo-grid

stretched ns for imes on weaviry by s

cturing meting rods or

14

which is ud the mostolypropylene manufaoften cateWoven geoaving weft While non

from raor staple ther chem

rvious shf liquids- oeservoirs, nction is membrane

mbrane is lining, pavd into HDP

deformed/olymeric m

cting ribs n functionment by ds are:

in one mproved p

ng or kstandard thods r straps tog

4 | P a g e

used in t widely ne and acturing egorized o-textile thread

woven andomly fibers mically,

eets of or solid-canals, always

e are of rapidly

vement, PE (high

/ non material

joined n of a friction

or two physical

knitting textile

gether.

Page 5: 2

2.

2

.1.5.4 G

Acgnffdrc

.1.5.5 G

Goda1Gwearbt

GEO-COM

A geo-cocombinatiogeo-nets numerous functions efunctions discussed reinforcemcontainmen

GEO‐TEXTI

Geo-textileor dredgeddiameter, application1.5 m to 5Geo-textilewhich areefficiency. and are prequired abreakwatertextile tub

Fi

MPOSITE

omposite on of geand/or g applicatioencompass

listed previo

ent, filtrant.

LETUBEA

tube is a d materiathough th

n. Today, g5.0 m are bags ar

e speciallyGeo-textileillow shap

applicationrs, etc to e and bag

gure 2-4: G

consistseo-textile, geo-membron areas. s the entir

for geoously: sation, drai

ANDBAGS

tube madal. These hey can bgeo-textileused in m

re made oy designee bags ranped, box s. Geo-textbuild erosg is show

Geo-textile b

s of ageo-grids

rane withThe majorre range oo-syntheticseparationinage, and

e of geo-tetubes aree customi tubes ran

many coastof woven

ed for gonge in volushaped ortile bags hsion protec

wn in the F

bag F

a ,

h r f c , d

extile and ie generallyized to annging in dtal and floor non

od soil tume from r mattresshave also ction measFigure 2-4

Figure 2-5:

is generally about

ny size dediameters ood protecwoven getightness 0.05 m3

s shaped d been usesures. A s

4 and Figur

Geo-textile

15

ly filled wit1 m to 3pending ofrom

ction appliceo- textile

and highto arounddepending ed as revesample of re 2-5.

e tube

5 | P a g e

th sand 3 m in on their

cations. fabrics

h seam d 5 m3, on the etment, a geo-

Page 6: 2

2.1.5.6 E

F

2.2 T

2.3 W

2.3.1.1 M

2.3.1.2 W

EROSION

Figure 2-6:

While synfibers thdimensionembankmbe reinforcompositesediment

TECHNICATEST

Matare propinnorecobelo

WIRE MES

ThismecTheStan

MATERIAL

Desmes

WIRE

All tests manufact

Tensile sthe lacing

CONTROL

Erosion con

thetic matat are h

nally stabments and

rced with e nature trapping f

AL SPECITING

terials inclused withposed struovative mommendedow in detai

SH GABIO

s work mchanically se specifindards EN

L /STRUC

sired propesh gabions

on the wturing the

trength: Bg, shall ha

L MAT

ntrol mat

ts consist heat bonle matrix embankm

galvanizeof reinforfunction o

FICATION

uding gabh specific sucture. Th

materials d values foil.

ONS

may conswoven do

ications aN 10223, E

TURAL PR

erties for s are as un

wire meshmesh.

oth the wave a tens

Erosiondegradacontrol control establisconditioplants.

Biodegrstraw term vegetatcoir or term vegetat

of UV stabded at for soil

ments withed mesh wrced mat of the geo-

NS OF CON

ions, revetstrength anhe detailealong wi

or each par

sist of fuouble twisare mainlyEN 10244

ROPERTI

various cnder

h, lacing w

wire used sile strengt

n control able or no mat pro and hish vegetatons for inv

radable mfibers wherosion ion Biodegstraw fibeerosion ion.

bilized nonthe contaerosion

h steeper with or w adds to-synthetic

NSTRUCT

t-mattressnd durabiled technicith the rameter ar

urnishing,t wire mey in acco

ES

component

wire shou

for the mth of 350-

mats con degradaovides imigh moisttion. It crvasion and

mats are mhich are control ugradable mrs which acontrol u

n-degradabact pointprotectionslopes, sy

without PV the eros matrix.

TION MAT

, geo-textility require

cal specifitest methre being d

assemblesh gabionordance w

ts for fabr

uld be pe

manufactur-500 N/m

16

can be oable type. Emmediate ture contreates hos

d establish

made of used for

unit growmats are mare used founit grow

ble polyprots to pro

n. For verynthetic m

VC coatinsion contr

TERIALS A

le tubes anements as ications ohods andescribed in

ling, and ns with bowith Intern

rication o

rformed p

re of gabiom2, in

6 | P a g e

of bio- Erosion erosion ent to spitable ment of

coir or r short wth of made of or short wth of

opylene ovide a ry high mat can ng. The rol and

AND

nd bags per the f these

d their n paras

filling oulders. national

f wire

prior to

ons and

Page 7: 2

17 | P a g e

accordance with EN 10223-3.

Elongation: Elongation shall not be less than 10%, in accordance with EN 10223-3.The length of the sample should be more than 25 cm for conducting this test

2.3.1.2.1 ZINC COATING

Minimum quantities of zinc should meet the requirements of EN 10244-2. The adhesion of the zinc coating to the wire shall be such that, when the wire is wrapped six turns around a mandrel having four times the diameter of the wire, it does not flake or crack when rubbing it with the bare fingers, in accordance with EN 10244. The mesh wire shall show no rusty spots on any part of the surface excluding the cut ends. Minimum quantity of zinc (gm/sqm) based on the internal diameters of 2.2 mm, 2.7 mm & 3.4 mm should be 230, 245 and 265 respectively

2.3.1.2.2 PVC COATING 

The initial properties of PVC coating material shall have a demonstrated ability to conform to the following requirements. The Specific Gravity should be in the range from 1.30 kg/dm3 to 1.35 kg/dm3, when tested in accordance with Test method ISO 1183. Tensile Strength should not less than 20.6 Mpa, when tested in accordance with test method ISO 527. Elongation at break should not be less than 200% in accordance with ISO 527. The PVC coating shall not show cracks or breaks after the wires are twisted in the fabrication of the mesh.

Wherever, there is high changes of corrosion, alternate wetting and

drying, high salinity, presence of shingles in water etc a further refinement in coating shall be used like Galmac (where Zinc + 10% Aluminum) coating to the main steel wire mesh. Further, if there is more severe condition, an additional coating of PVC coating shall be applied

2.3.1.2.3 MESH CHARACTERISTICS

Mesh wire: Diameter – Inner diameter shall be 2.7 mm for the Zinc coated wire and when measured with PVC coating the outer diameter shall be 3.7 mm.

Selvedge wire: Diameter – Inner diameter shall be 3.4 mm for the Zinc coated wire and when measured with PVC coating the outer diameter shall be 4.4 mm.

Mesh opening: Nominal Dimension D =100 mm.

Lacing and stiffener wire: Diameter – Inner diameter shall be 2.2 mm for the Zinc coated wire and when measured with PVC coating the outer diameter shall be 3.2 mm

Page 8: 2

18 | P a g e

2.3.1.2.4 BOULDERS

The boulders for gabions shall be hard, angular to round, durable and of such quality that they shall not disintegrate on exposure to water or weathering during the life of the structure. The size may be between 0.15 m and 0.25 m. The range in sizes shall allow for a variation of 5% oversize and/or 5% undersize rock, provided it is not placed on the gabion exposed surface. The size shall be such that a minimum of three layers of boulders must be achieved when filling the gabions of 1m thick

2.4 TOLERANCES

Wire: Wire tolerances based on the internal diameters of 2.2 mm, 2.7 mm & 3.4 mm should be ± 0.06 mm, ± 0.06 mm and ± 0.07 mm respectively in accordance with EN 10218-2.

Mesh opening: Tolerances on the hexagonal, double twisted wire mesh, opening shall not exceed -4% to 16% on the nominal dimension value.

Gabions: 5 % (±) on the length, width, and height

2.5 TESTS FOR THE GABIONS

Different tests to be carried on the gabion material are tabulated along with references and standards in Table 2-2.

Table 2-2: Tests for the gabions

Mesh Type 10' x 12' References of Specifications

Mesh Opening “D” mm 100 EN10223 Mesh Tolerance +16% to –4% EN10223 Unit Dimensions Tolerances in sizes of units ± 5% ASTM A975

Mesh Wire Diameter (mm) 2.7/3.7 (Inner Dia/Outer Dia) EN10223

Tolerance (±) mm 0.08 BS1052 Zn Coating Min (gsm) 240 ASTM A 641 Selvedge/Edge Wire Diameter (mm) 3.4/4.4 (Inner Dia/Outer Dia) EN10223

Tolerance (±) mm 0.10 BS1052 Zn Coating (Selvedge/Edge Wire) Min (gsm)

260

ASTM A 641

Lacing Wire Diameter (mm) 2.2/3.2 (Inner Dia/Outer Dia)

Tolerance (±) mm 0.06 BS1052 Zn Coating (Lacing Wire) Min (gsm) 220 ASTM A 641

Fasteners (mm) 3.0/4.0 (Inner Dia/Outer Dia)Stiffeners (mm) 2.2/3.2 (Inner Dia/Outer Dia)Zn coating on fastener/ stiffener (gsm) 240 ASTM A 641

PVC Coating Colour Grey-RAL 7037 ASTM D 1482Thickness Nominal (mm) 0.50 ASTM A 975

Page 9: 2

19 | P a g e

Thickness Minimum (mm) 0.38 ASTM A 975

Specific Gravity 1.30 – 1.35 ASTM D 792 Tensile strength Not less than 20.6 MPa ASTM D 412 Modulus of Elasticity Not less than 18.6 MPa ASTM D 412 Hardness Between 50 and 60 Shore D ASTM D 2240Brittleness temperature Not higher than –90C ASTM D 746

Weight loss Less than 5% after 24 hour at 1050 C

ASTM D 2287

Abrasion Resistance The percentage of weight loss shall be less than 12% ASTM D 1242

Salt spray Exposure and Ultraviolet Light exposure

a) The PVC shall show no effect after 3000 hours of salt spray exposure

b) The PVC shall show no effect of exposure to ultraviolet light with test exposure of 3000 hours using apparatus Type E at 630C c) After the salt spray test and exposure to ultraviolet light, the PVC coating shall not show cracks or noticeable change of colour, or blisters or splits. In addition, the specific gravity, tensile strength, hardness and resistance to abrasion shall not change more than 6%, 25%, 10% and 10% respectively from their initial values.

ASTM B 117 ASTM D 1499 and G 23

2.6 GEO-TEXTILE AS FILTER

The material should be woven with multifilament yarn in both warp and

weft direction or non-woven needle punched type with continuous filament. The geo-textile shall be preferably made of polypropylene. The material may have about 70% polypropylene and rest may be polyethylene or any other equivalent material. The standard roll length and width should be 100 m and 5 m.

Table 2-3: Properties of geo-textile as filter

Properties Marginal Value

Reference for Test Method

Mechanical Properties 1 Tensile strength (Warp/Weft)(=>) 28/26 KN/m IS 1969 2 Elongation at designated peak tensile load

(Warp/Weft)(<=) 25%/25% IS 1969

3 Trapezoid tear strength Warp/Weft) (=>) 300 N/300N ASTM D 4533 4 Puncture Strength(=>) 250 N ASTM D 4833

Hydraulic properties 1 Apparent opening size(<=) 75 microns ASTM D 4751 2 Permeability(=>) 10 l/m2/s ASTM D 4491

Physical Unit Weight(=>) 140g/sqm ASTM D 3776

Page 10: 2

20 | P a g e

2.7 GEO-TEXTILE BAGS.

Geo-textile bags are made of woven/non-woven polypropylene/polyester geo-textile. Double layer geo-textile bags using woven and non-woven geo-textile are used for harsh conditions. Geo-textile used to manufacture geo-textile bags should have high mechanical properties for enhanced durability along with enhanced puncture, abrasion and U.V. resistance characteristics. Geo-textile should be inert to biological degradation and resistant to naturally encountered chemicals, alkalis, and acids.

Geo-textile used to manufacture geo-textile bags made of non-

woven material may conform to the properties listed in Table 2-4.

Table 2-4: Properties of non-woven geo-textile bag

Properties Reference for Test Method

Unit Values

Properties of Geo-textilePolymer Type Polyester/PP Nominal Mass ISO 9864 Gms/Sq.

m≥400

Tensile' Strength ASTM D4595 kN/m ≥20Tensile Elongation ASTM D4595 % ≥40% & ≤ 90% Puncture Resistance ASTM D4833 kN ≥' .40Opening Size ASTM D 4751 mm ≥0.07mm & ≤0.16mmUV ' resistance ASTM' D 435 %/Hr 70/50

Properties of Geo-textile BagSeam Type Double Seam Preferably flat dimensions

103 cm x 70 cm

Geo-textile used to manufacture geo-textile bags having double layers both for woven and non-woven material should conform to the properties listed in Table 2-5.

Page 11: 2

21 | P a g e

Properties Reference for Unit Values

Woven

Properties of Geo-textile Polymer Type PP PP

Weight ISO 9864/ ASTM D5261 Gms/Sqm ≥300 ≥230

Tensile Strength ASTM D 4595 kN/m ≥12 ≥35

Tensile Elongation ASTM D 4595 % ≥30% & ≤90% ≥05% & ≤30%

Tensile Strength ASTM D4632 kN ≥0.80 ≥1.5

Grab Elongation ASTM D4632 % ≥30% & ≤90 ≥05% & ≤3' %

Puncture Resistance ASTM D4833 kN ≥' .40

Opening Size ASTM D4751 mm ≥0.06 & ≤0.17 ≥0.10 & ≤0.25

UV Resistance ASTM D4355 %/hrs 70/500 70/' 00 Properties of Geo-textile Bag

Seam Type Double Seam Preferably flat dimensions

2.00m x 1.50m

Table 2-5: Properties of double layer geo-textile bag

Test Method Non Woven

Page 12: 2

22 | P a g e

2.8 GEO‐TEXTILETUBES

Geo-textile tubes should be made of high-tenacity polypropylene yarns which are woven into a stable network such that the yarns retain their relative position. These geo-textile tubes are often filled hydraulically with slurry of sand and water, although many other fill materials may also be used. Each fill port may consist of a Geotextile sleeve having a length of at least 1.5 m and a circumference slightly greater than that of the filling pipe. Sometimes double layer of sheets of woven textiles may also be required in consideration of added UV protection for a prolonged life and sufficient abrasion resistance. The geo-textile tubes should be constructed to meet the dimensions, type of materials and properties mentioned in Table 2-6, table 2-6 and table 2-7 respectively.

Table 2-6: Dimensions for Geotextile tube

Property/Parameter Units Values Geotextile tube length M 20Geotextile tube diameter M 3Filling port length M 2Filling port diameter M 0.5Filling port spacing M 5Seam strength efficiency(=>) % 40

Table 2-7 contains type and structure of material to be used for geo- textile tubes.

Table 2-7: Type of fabric for geo-textile tube

Property Reference for Test Method

Units Values

Polymer n/a n/a Poly propylene Roll dimensions (LxW) n/a n/a 100mx5mStructure

n/a n/a Woven with multifilament yarn in both warp and weft directions

Weight per unit area ASTM D 3776 Gm/m2 >=330Properties of geo-textile tubes are given in and

Table 2-8 contains properties of geo-textile tubes.

Table 2-8: Properties for geo-textile tube

N Properties Marginal Value Reference for Test Method

Mechanical Properties 1 Tensile strength (Warp/Weft)(=>) 80/78 KN/m IS 1969 2 Elongation at designated peak tensile

load (Warp/Weft)(<=) 25%/25% IS 1969

3 Trapezoid tear strength Warp/Weft) (=>) 1600 N/1600N ASTM D 4533 4 Puncture Strength(=>) 600 N ASTM D 4833

Hydraulic properties 1 Apparent opening size(<=) 250 microns ASTM D 4751 2 Permeability(=>) 18 l/m2/s ASTM D 4491

Page 13: 2

23 | P a g e

2.9 VETIVER FOR BANK PROTECTION

The vetiver is a special type of grass having longer roots of length. This grass is infertile in nature. Due to their long roots and high tensile strength this grass is resistant to the high velocity streams and checks the erosion Desirable properties of the vetivers are given in Table 2-9.

Table 2-9: Properties of vetivers for bank protection

Sr Properties Mar Value 1 Average tensile strength 75 MPa 2 Root length Up to 3 m 3 Life under 14 m of water Up to 5 months 4 Air temperature range for sustainability -140C to 550C 5 Soil Ph 3.0 to 10

2.10 REFERENCES

Design practices and specifications adopted by the Maccafferi India Pvt Ltd.

Draft for 2nd revision of IS code 8408.

Page 14: 2

F

Ex

Sam Th

at Th

of Th

Pro To

is p Th

Pro To

FIGURE1SHOW

xisting Bankme shall be

he EmbankmOMC to 95

he Existing BEmbankme

he Embankmovision of B Prevent theproposed on

he Toe Proteovision of Bp of the Em

WINGEXITINGBA

ks of Sabarmconstructed

ment Constr5% Proctor Banks will bent . ment will beBIS. eft of Wire n the slope aection will bBIS. mbankment c

ANKSOFRIVERS

mati are uned in 2H:1V ruction will Density abube trimmed

e protected w

Crates, Conand which wbe carries ou

can be deve

SABARMATISTR

even with loSlope with be carried o

utting with Eat least by

with Stones

ncrete Lininwill give aeut with Laun

eloped as Ri

RENGTHENEDB

Figure

ots of Rain intermedia

out with selExisting Ba0.3 m for ab

s in Wire Cr

ng of 75 mmsthetically bnching Apr

iver Front S

BYCONSTRUCTIN

e 1

Cuts and inate Berm of ected Borro

anks. butting with

rates ( Gabio

m Thicknessbetter view.ron with Sto

Scheme or a

NGEMBANKMEN

n unstable co5 m width a

ow area in c

h Proposed

on Mattress

s over Stone. one in wire

as Various U

NTWITHSTONE

2

ondition . at Mid heigcontrol lift th

new constru

ses) as per

es in Wire C

crates as pe

Utilities.

EINWIRECRATE

24 | P a g e

ht. hickness

uction

Crates

er

ES

Page 15: 2

F

F

FIGURE2PROPO

FIGURE3AND4

OSEDBANKPRO

4COMPLETED

OTECTIONBYCO

DVIEWOFBA

ONSTRUCTINGE

ANKPROTECTIO

EMBANKMENTW

Figu

NBYCONSTRUCVARIOUSU

WITHSTONEINW

ure 2

CTINGEMBANKUTILITIES

Figure 3

WIRECRATESAN

KMENTWITHSTO

NDDEVELOPME

ONEINWIRECR

2

ENTOFVARIOUS

RATESANDDEVE

Various UtilitiDeveloped

Lining Over SIn Wire Cra

25 | P a g e

UTILITIES

ELOPMENTOF

ies

Stone ates

Page 16: 2

Figure 4

226 | P a g e

Page 17: 2

1.0GEN

A lgenbeh

Emhainulan

NERAL.

levee or dynerally parhind it from

mbankmenave been usundation, wnds, village

yke may berallel to thm overflow

nts are the sed extenswhen the ses and oth

e defined ae river cha

w of flood w oldest kno

sively for thstream spi

her propert

FIGURE 5:

as an earthannel and waters. own formshis purposills over itsies against

 SLOPE OF A T

hen embandesigned t

s of flood pse. These ss natural st damages

TYPICAL EMB

nkment extto protect t

rotection werve to pre

section, ans

ANKMENT 

tending the area

works and event

nd safeguar

2

rd

27 | P a g e

Page 18: 2

28 | P a g e

1.1.1 REQUIREMENT OF DATA

BIS code 12094: 2000 stipulates that the following data is required for planning of an embankment

1.1.2 TOPOGRAPHICAL DATA

Index plan showing area to be protected, contour survey plan of the area, past river courses, plan and section of earlier executed works

1.1.2.1 HYDROLOGICAL DATA

Discharge, gauge, velocity, carrying capacity, extent of spill of river, cross sections and longitudinal section of river, Design data of Sant Sarovar ,Design Flood of Sant Sarovar, Water Surface Elevation at Design Flood and Check Flood and river behavior like aggrading or degrading etc.

1.1.2.2 DEGREE OF PROTECTION

BIS code 12094: 2000 stipulates that the height of embankment and the corresponding cost and Benefit Cost Ratio will be worked out for Design Flood and Check Flood of Sant Sarovar. The degree of protection which gives the optimum Benefit Cost Ratio should be adopted.

1.1.2.3 EMBANKMENT FOR PREDOMINANTLY AGRICULTURAL AREAS

The design flood for this type of embankment is kept 25 years for fixation of crest level

1.1.2.4 EMBANKMENTS FOR GIFT CITY AREA

The design flood for Protection of GIFT City embankment will be carried out for Flood discharge of 7.25 Lacks Cusecs and Check Flood of 8.38 Lacks Cusecs as GIFT City is located just D/S of Sant Sarovar and no other Intermediate catchment between them.

BIS code 12094: 2000 stipulates following guidelines related with

the alignment and spacing of the embankment. 1.1.2.5 ALIGNMENT

The embankments will be aligned on the natural bank of the river, land is high and soil available for the construction of embankments. The alignment is planned such that important township, vital installations, properties, cropped area is well protected by the embankment. The alignment is such that high velocity flow is quite distant from the toe of embankment to avoid scouring of the same also slope and toe protection in the form of pitching along with launching apron using the stones in wire crates, geo-mattress, Diaphragm wall is proposed. Alignment should also be planned so that land acquisition is feasible and not prolonged.

Page 19: 2

29 | P a g e

1.1.2.6 SPACING.

The spacing of the embankment and their alignment needs careful consideration with respect to their vulnerability to the river and the rise of high flood levels on account of reduction in flood plain storage by construction of the embankment.

The spacing of embankments along the jacketed reach of the river

should be aligned according to existing Toe of the River Bank and which is almost equal to Lacey wetted perimeter for the design flood discharge. Lacey wetted perimeter Lacey wetted perimeter (P) =4.75 (Qdesign)½] respectively.

Length of the embankment: The length of the embankment directly

depends upon the alignment and both ends of the embankment will be tied up to some high ground or existing highway or railway or any other embankment nearby conforming to the design height of the embankment.

2.0 DESIGN OF EMBANKMENT

BIS code 12094: 2000 is used for design of the embankment

2.2.1 TYPES.

Type of Embankment proposed is Homogeneous Type of Embankment.

1) Homogenousembankment.

This is the simplest type of earthen embankment and consists of a single material and is homogeneous throughout. A blanket of relatively impervious material (stone pitching) shall be provided at river side. A purely homogenous section is used, when only one type of material is economically or locally available.

A purely homogenous section, abutting with the existing Banks is

proposed, there is no need of stability of D/S Slope only U/S Slope stability for sudden Draw down condition and other conditions mentioned in BIS Code 12094 for U/S Slope will be adopted.

2.2.2 FREE BOARD

The top of the embankment should be so fixed that there is no danger of overtopping, even with the intense wave wash or any other unexpected rise in water level due to sudden change in river course or aggradations of river bed or settlement of embankment.

Free board will be taken as 1.8 m for Design discharge of 7.25 Lacks Cusecs and Adequacy of Free Board will also be checked for Check Flood of 8.38 Lacks Cusecs.

Page 20: 2

30 | P a g e

2.2.3 TOP WIDTH

The top width of the embankment should be sufficiently enough to accommodate the vehicular traffic. The top width of the embankment is kept as 5.0 m. Turning platform of length 15 m to 30 m and 3 m width at C/S side slope at an interval of 1 km or more will be provided. An embankment should be provided with suitable soling over filter for proper drainage.. For embankments protecting towns, industrial and vital installations, necessity of providing all weather roads of 3 m to 3.5 m width will be provided.

2.2.4 SIDE SLOPE

The side slopes are dependent upon the material and height of the embankment. The side slope should be flatter than the angle of repose of the material of the embankment. For drainage purpose, longitudinal drains on the berm and cross drains at suitable places will be provided to drain out the water.

2.2.4.1 RIVER SIDE SLOPE

The river side (R/S) slope should be flatter than the under-water angle of repose of the material. The slope should not be steeper than 2H:1V and in case of high embankments, slope should not be steeper than 3H:1V, when the soil is good and to be used in the most favorable condition of saturation and drawdown.

In case of higher embankment protected by rip-rap/pitching, the slope

of embankment may be 2H:1V or 3H:1V depending upon the type of slope protection.

If the construction material is sandy, the slope should be protected with a cover of 0.6 m thick good soil; and It is usually preferable to have more or less free draining material on the river side to take care of sudden drawdown. In case of high and important embankment, slopes may be protected by the stone pitching, concrete blocks with open joints or sand filled geo-mattress to protected against sudden drawdown or erosive action of river flow.

Stability of Embankment will be carried by slip circle method for finalizing river side slope (IS 7894).

Page 21: 2

2

 

2

2

2.2.4.2 C

2.2.5 B

2.2.6 SAFE

COUNTRY

The High be carriedSlope is n Typical under as

          

BORROW P

As pborrdistadevethe Wheshaltowaprop

ETYMEASU

Strucondcondconshigh

Safe

settlparfounWellIn hthe densespesepa

Y SIDE SLO

Bank are d out abu

not required

cross ses Figure 6

                     F

PITS.

per BIS crow pit shoance of 2elopment odepth of b

en adding ll first be ards centrperly wette

URESIND

ucture widitions of ditions wilsidered foher than 1.

ety againstlements isameters

ndations pl graded hhigh emba

earth filsity with ecially in arated to s

OPE

available utting to ed.

ection of .

IGURE 6: TYP

code 1153ould be pr25 m fromof flow parborrow pits new eart cut and re of the ed so that n

ESIGN

ll be sta saturatioll be doneor high e.3.

t cracks ds not envand the roperly an

homogenouankments l in suitaappropriaclayey soafeguard a

on Countrexisting hi

f an ear

 

PICAL CROSS‐S

2, for takeferred on

m the toe rallel to ems @ 50-60thwork tobenched iembankm

new earth

able undon and dre to ensurembankme

due to unevisaged f same ca

nd by selecus materiait would bable layerate moistuoils is to against see

ry side anigh Banks

rthen em

SECTION OF A

king out sn the river

of embanmbankment

m c/c sh existing into steps

ment. Surf may adhe

er all strawdown. re safety. ents. The

equal settlfor Sabaran be largcting suitaals are mobe desirabrs with aure contebe done

epage/leak

d Embanks. Therefor

mbankmen

AN EMBANKM

soil for usside and lonkment. Int, cross-ba

hall be left embankm with treaface of olre to old W

tages of Stability Seismic f factor of

lement anrmati loogely avoideable materiost suitablble to meca view toent. Breakad organi

kage/pipin

kment Planre Stability

nt is sh

MENT 

se in embocated at mn order tars of widt in the bor

ment, the ads slopind work s

Work.

constructchecks foforces willf safety s

d wetting:oking to ed by prepial for consle for conschanically o achieve king of bic/vegetab

ng.

31 | P a g e

nning will y of D/S

hown as

 

ankment, minimum o obviate

th 8 times rrow pits. old bank g slightly hould be

tion and r various l also be hould be

Unequal the soi l

paring the struction. struction.

compact optimum

big clods ble matter

Page 22: 2

32 | P a g e

2.2.7 SLUICES

Sluices with regulating arrangements would be provided for country side drainage. The size of sluice will depend upon the intensity of rainfall and the catchment area to be drained. Sluices may be designed as per provision of BIS code IS 8835:1978.

2.2.8 CAUSES OF FAILURE OF EMBANKMENT

As stipulated by the CBIP publication - 1989 River Behavior Management and Training Volume-I, in the absence of proper maintenance and supervision, embankments are susceptible to breaches due to various causes given below.

(a) Improper compaction and settlement of embankment. (b) Transverse cracks due to unequal settlement. (c) Inadequate drainage and pore pressure development. (d) Erosion of riverside slope due to river current and wave wash. (e) Caving-in of the banks. (f) Increase in moisture content of the soil material.

2.2.9 PROPOSED PROTECTION WORK FOR EMBANKMENT

An embankment under direct attack of a river needs protection against failure. Different protective measures which are commonly employed to protect embankment are as under.

(a) Revetment/mattressing to protect against erosive action of river. (b) Spurs/groynes to deflect/dampen high velocity attacking the embankment (c) Improving shear strength of embankment soil by growing shallow rooted

vegetation.

Page 23: 2

33 | P a g e

3.0 STABILITY ANALYSIS FOR HIGH EMBANKMENTS

The criterion for stability analysis for high embankment is based on the stability analysis of embankment dams.

The most important cause of failure of an embankment is sliding. A

portion of the earth may slide downwards and outwards with respect to remaining part, generally along a well defined slice surface. The failure is caused when the average shearing stress exceeds the average shearing resistance along the sliding surface due to various loading conditions.

Slope stability is generally analyzed by “Swedish Slip Circle‟ method,

the rupture surface is assumed cylindrical or in the cross- section by an arc of a circle. The sliding wedge method assumes that the failure surface is approximated by a series of planes.

High embankments the section proposed should be checked for stability

by Swedish Circle method. The minimum factor of safety aimed at should be 1.3.

3.1.1 SELECTION OF DESIGN PARAMETERS

The embankment material shear strength is obtained by performing tri- axial tests of borrow area materials compacted to densities aimed at during construction. The foundation material strength is obtained by tests with undisturbed samples from tri-axial shear testing. Testing in each case shall be from zero to maximum normal stress expected in the embankment.

The design shear parameters for fill material is fixed at 75% availability

from an adequate number of samples, and for foundation soils minimum shear strength values along foundation obtained are adopted after rejecting extreme or freak values.

3.1.2 ANALYSIS PROCEDURE

The procedure of arriving at driving and resisting forces involves assumption of a tentative cross-section of the embankment, a possible circular failure surface, division of the slip circle mass into a number of slices, calculation of forces on each slice and summation of the forces. The factor of safety against sliding for assumed failure surface is obtained by the equation:

Page 24: 2

34 | P a g e

FS = ∑S/∑V = C + (N-U) tan/W sin

Where: FS = Factor of safety S = Resisting or stabilizing Force T = Driving or actuating force C = C1x (b/ Cos ) N = Force normal to the arc or slice U = Pore water pressure. = Angle of shearing resistance W = Weight of the slice Α = Angle made by the radius of the failure surface with the vertical at the centre of slice. C1 = Unit cohesion, and b = Width of the slice

3.1.3 STABILITY COMPUTATION

The slope stability analysis is carried out to get the minimum factor of safety for a tested section under different loading conditions for upstream slopes. The computer programmes used for static analysis are used for the computations

3.1.4 FINAL SELECTION OF EMBANKMENT SECTION

Based on the results of studies for slope stability by static and pseudo static method, final section of the embankment may be selected. In this selection, great emphasis is put on the experience of the designer and the data of behavior of embankments constructed in almost identicalsituations.

Page 25: 2

35 | P a g e

3.2 MERITS AND DEMERITS OF EMBANKMENTS

Merits and demerits of flood embankments have been listed out below:

MERITS

Merits of embankment as method of river training works are as under:

Embankments are the main mean of preventing inundation during flood season.

The initial cost of construction of embankment is low, although when raised subsequently, they may become a bit expensive.

Construction is easy and presents no difficulty, as it can be done by utilizing local resources in unskilled labor and materials. Maintenance is equally simple and cheap.

They can be executed in parts, provided that’s ends are properly protected DEMERITS

Embankments cause rising of high flood levels. In the event of a breach, there is a sudden and considerable inflow

of water which may cause damage in the country side and deposition of sand making the area infertile.

Embankments are susceptible to direct attack of the river flow which can erode and undermine them.

In the case of river carrying considerable amount of silt, then deposition of silt on the river bed causes rise in the water level which may be lead subsequent overtopping of the crest level of embankment.

3.3 REFERENCES

1. BIS code 12094:2000 2. BIS code11532:1995 3. Preliminary draft Guidelines for planning and design of river

embankment (Levees) (Second revision of IS 12094) (Feb, 2011) 4. Embankment manual (1960) 5. Irrigation Engineering and Hydraulic structures-1995 - S. K. Garg 6. River Behavior Management and Training Volume-I (Central

Irrigation and Power (CBIP), 1989

Page 26: 2

4

4.1 G

GENERAL

CBI198traiof rnecthe undtraineaproBecriveandfounsuslowther

TheActnorstro

L

IP-manual89” stipulaining workriver condicessitates p erosion. Tder Anti Eining of rivarby hydratection wo

cause of ther bank cod lower sndation fo

sceptible tower bank, p

re is sandy

e upper baion on thi

rmal to theong curren

“River Bates that pks because itions. Rivprotection

The protectErosion wver, protectaulic struorks are ahe high cosonsists of tections (Bor supporo erosion. particularly substrata

ank is the is bank poe bank. Dunt along th

FIGURE 7: A

Behavior Mprotection bank cavi

ver passing of adjacetion of rive

works. Thetion of adjctures likauxiliary tsts involvethe upper

Below the rting the Recessionly at toe. a below.

portion beortion is muring high

he bank

A TYPICAL BAN

Managemenof banks ing is one g through nt lands a

er bank fro purpose acent land

ke embankto river traed, all avai (above th LWL). Thupper ba

n of bank The reces

etween LWmost severeh stage of

NK PITCHING 

nt and Tris a part

of the cau populatedand propem the threof bank

d and propkments etcaining worilable mate

he Lowest whe lower

ank and, is causedssion is fa

WL and Hige when thfloods, ero

IN WIRE CRAT

raining Voand parce

uses of detd/agriculturties threa

eat of erosiprotection

perties, proc. Generarks and eerials are uwater levebank actis, genera

d by the east, especia

h Flood levhe current osion is al

TES

36 | P a g e

olume-I - el of river terioration ural areas atened by ion comes

n may be otection of ally, bank expensive. used. The l or LWL) s as the ally more erosion of ally when

vel (HFL). impinges so due to

Page 27: 2

4

4.2 C

4.3 P

4.3.1.1 R

4.3.1.2 T

4.3.1.3 H

CAUSESOF

CBI198

(a) Wash(b) Under

overh(c) Slidin

duratfurthe

(d) Pipingwhich

Cauundfrom

PLANNING

IS code 14revetment

REQUIREM

Following

TOPOGRAIndex planearlier exe

HYDROLO

Dischargeriver, bed

FBANKFA

IP-manual89” stipula

hing away ormining thanging ma

ng or Slougion. Saturer reducedg in sub-lah carries aw

uses (a) ander (c) is dm foundati

                   

G OF BAN

4262:1995t or pitchin

MENT OF

data is req

APHICAL Dn showing ecuted wor

OGICAL DA

, velocity, material g

ILURES

l “River Bates followi

of the soil phe toe of baaterial depghing of slration decrd by the prayers due way mater

nd (b) of badue to redion failure

           FIGURE

K REVET

mentioneng.

DATA

quired for

DATA area affecrks

ATA & OT

bank to grain size e

Behavior Ming causes

particles frank by eddrived of sulope when reases theessure of sto movem

rial with it.

ank failureduction in. An erode

 

E 8: A TYPICAL

MENTd following

planning o

cted, bank

THER DAT

bank crosetc.

Managemens of bank fa

rom the badies, curre

upport. saturated shear strseepage flo

ment of gro.

es may be n shear stred bank is

L ERODED RIV

g provision

of a bank r

k slope, typ

TA

ss sections

nt and Trailure as li

ank by stroent etc foll

d with watrength of sow. ound water

attributedrength andshown in

VER BANK 

ns regardin

revetment.

pe of soil,

s and long

raining Voisted below

ong currenowed by c

er by floodsoil. The s

r towards

d to erosiond under (dFigure 4-2

ng plannin

plan and s

gitudinal s

37 | P a g e

olume-I - w.

nt. ollapse of

ds of long tability is

the river,

n. Failure d) results 2.

ng of bank

section of

section of

Page 28: 2

38 | P a g e

4.3.1.4 DEGREE OF PROTECTION

The design flood for pitching/revetment will be calculated for Design Flood.

4.4 DESIGN OF BANK REVETMENT

IS code 14262:1995 provides for following provisions regarding design of bank revetment.

4.4.1 WEIGHT OF STONES/ BOULDERS

Stones/boulders, used in revetment for bank protection, are subjected to hydrodynamic drag and lift forces. These destabilizing forces are expressed in terms of velocity, tractive forces etc. The stabilizing forces acting against these are component of submerged weight of the stones and downward component of force caused by contact of the stones.

The weight of stones on slopes (W in kg) may be worked using the formula given below

:W (in kg) = 0.02323*Ss*V6 /K* (Ss-1)3 -------------------------------- (1) Where K (correction factor for slope) =[1-Sin2θ/Sin2Φ ]1/2

Ss=specific gravity of boulders (may be adopted as 2.65) Φ = Angle of repose of material of protection works (adopted as 300 for boulders) θ= Angle of sloping bank2 (H) :1 (V) (26.560) V= Velocity in m/s K =[1-Sin226.560/ Sin2300]1/2 = =0.447 Hence weight of stones for 2H:1V slope W (in kg) = 0.02323*Ss*V6/0.447* (Ss-1)3

For river training works, sub-base is to be graded to a stable slope depending upon the angle of repose and cohesion of bank material under saturated condition and height of the bank. For a high bank, berm needs to be provided. For important works, stability of bank with designed slope and berm should be checked by slip circle method. For normal bank protection works, a slope of 2H:1V or flatter is recommended

4.4.2 SIZE OF STONE/ BOULDER

Size of stone (Ds in m) may be determined from the following relationship.

Ds (in m) = 0.124* (W/Ss) 1/3 ------------------------------------------- (2) Where W= Weight of stone in kg Ss= Specific gravity of stone (may be adopted as 2.65) Minimum dimension of stones > Ds

Generally, the size of stone should be such that its length, width and thickness are more or less same ie stones should be more or less cubical. Round stones or very flat stones having small thickness should be avoided.

Page 29: 2

39 | P a g e

4.4.3 THICKNESS OF PITCHING

Minimum thickness of pitching (t) or protection layer is required to withstand the negative head created by the velocity. This may be determined by the following equation.

Minimum thickness of pitching (t in m) = V2/2g (Ss-1) ------------ (3) V= Velocity in m/sec g= Gravitational acceleration in m/sec2 Ss= Specific gravity of stone (may be adopted as 2.65).

Two layers of stones of minimum size should be provided, when pitching

is being provided with boulders in loose

4.4.4 PITCHING IN CRATES

At high velocity, required weight of stones (to be found by equation No (1) comes out to be higher, which makes handling and placing of stones a bit difficult. In such cases or in case when requisite sized stones are not available, small size stones filled in GI (Galvanized Iron) wire crates may be used for pitching purpose. In this case single layer of GI wire crates filled with stones having thickness more than may be used as pitching. The specific gravity of the crate is different from the boulders

due to presence of voids. Porosity of the crates (e) may be worked out using the following formula.

E = 0.245+ 0.0864/ (D50)0.21 --------------------------------------------- (4) Where D50= mean diameter of stones used in mm. let us assume D50

as 250 mm e = 0.245 + 0.0864/ (250)0.21= 0.27

The opening in the wire net used for crates should not be larger than the smallest size of stone used. The mass specific gravity of protection (Sm) can be worked out using the following relationship.

Sm = (1-e) *Ss-------------------------------------------------------------- (5)

Page 30: 2

4

4

4

4.4.5 FILT

4.4.6 PAN

4.4.7 TOP

Thithereq

CrabanaddlayGI

TER

A gthe synandsyn

NELING Pan

thadepof s

P KEY/BE

In cor ctop

is mass se crates aquired, wor

ates shounk. Cratesditional pryers shouldwire

raded filte pitching t

nthetic filted quality cnthetic filte

neling mayat slopes mpending upslope lengt

ERM

         

case of revcapping besurface.

specific grand this wrked out by

ld be laids must brotection. Id be tied t

r of size 15to preventer may alsocontrol is er may be l

y be providmay remaipon the lenh. A typica

   FIGURE 9: A

vetment onerm shoul

ravity mayweight shy the equa

d with lone tied toIf crates ao each oth

50 mm to t failure byo be used easy. A 1laid to avoi

ded in the n more stngth of riveal bank pit

A TYPICAL BAN

n slopes upd be provi

y be usedhould be ation No.1.

ng dimenso each otare being pher at suit

300 mm thy sucking as that is 50 mm thid rupture

pitching wtable. The er reach totching in c

NK PITCHING 

p to NSL, wided for al

to work more than

sion alongher by 5provided iable interv

hickness maction by easy to la

hick sand of fabric b

where slop size of pao be proteccrates is sh

IN CRATES 

which is bellowing flow

out the wn weight

g the slop5 mm GI in layers tval using t

may be laid high veloc

ay, durablelayer over

by the ston

pe length isanel may cted and thown in Fig

elow HFL, w of water

40 | P a g e

weight of of stone

pe of the wire as then each the 4 mm

d beneath city. Geo- e, efficient r the geo- nes

s more so be varied

the length gure 4-9.

a top key r over the

Page 31: 2

41 | P a g e

4.5 TOE PROTECTION

IS code 14262:1995 mentions following provisions regarding toe protection.

To prevent the sliding and failure of the revetment on slope, toe is

required to be protected. This may be in the form of simple toe-key, sheet pile/Diaphragm wall or launching apron.

4.5.1 TOE WALL

When hard strata is available below the river bed at a reasonable depth torecommended. The thickness of the toe wall depends upon height of wal anoverlaying pitching. The toe wall may be design as retaining wall and be comasonry along with provisions of weep holes etc

4.5.2 TOE KEY

Simple key may be provided at the toe (may be called as toe key) when rock or un-erodible strata is available just below the river bed and the overlaying banks are erodible. The key is in the form of stone/bricks or concrete blocks filled in the trench below the hard river bed for depth equal to the thickness of pitching “t” for proper anchorage. Sole purpose of this key is to provide lateral support to the pitching. The key may be of mortar or in geo-bags, if the pitching is provided in mortar or geo- bags.

4.5.3 SHEET PILES /DIAPHRAGM WALLS/CUT OFF WALLS OR LAUNCHING APRON

When firm strata is not available at reasonable depth below the river bed, toe protection in the form of sheet pile or launching apron may be provided. The sheet pile may be made of RCC, steel. The sheet piles/Diaphragm walls may be drilled below the river bed up to maximum scour depth.

Sheet piles/Diaphragm walls/Cut off walls are difficult to drive;

therefore Launching apron is preferred and provided with revetment. Launching apron should be laid at low water level (LWL). The launching apron may be laid using the stones or geo-bags. The stones/geo-bags in the apron should be designed to launch along the slope of scour and provide a protection layer so that scouring is checked. The size of launching apron should be such that it should form a protection layer up to level of maximum scour depth. Slope of launching apron may be taken as 2H:1V. Filter below the launching apron may also be provided so that river bed material is safe against suction.

Page 32: 2

42 | P a g e

4.5.4 SIZE OF LAUNCHING APRON

Width of the launching apron depends upon the scour depth below HFL. Depth of scour below HFL (D) may be worked out using the following formula:

D = 0.473 (Q/f)1/3 -------------------------------------------------------------- (6.1) and D= 1.33 (q2/f)1/3 ------------------------------------------------------------------ (6.2) Where Q = design discharge in cumecs and q = design discharge per unit width or design discharge intensity in cumecs/m f is silt factor. Silt factor (f) may be calculated using the following formula f= 1.76 (d) 1/2----------------------------------------------------------------------- (7) where d is mean particle diameter of river material in mm

Generally scour depth (D) below HFL should be calculated using the design discharge (equation no. 6.1). In some cases (for braided rivers) scour depth may be calculated using the design discharge intensity (equation no. 6.2).

Maximum scour depth (Dmax) below HFL= 1.5* Scour depth (D below HFL). Maximum Scour depth (Dmax) below LWL = (Dmax) below HFL – (HFL-LWL)

If the launching apron is being laid at LWL then width of the launching apron should be calculated using the following formula. Width of launching apron= 1.5 * (Dmax) below LWL

Thickness of launching apron (T) = 1.5* thickness of pitching (t). In some cases, thickness of the launching apron is kept different from “T” due to size of crates etc (if launching apron is being provided in crated stones), then width of the launching apron may be revised keeping the volume of stones/geo-bags same per unit length of the apron.

4.6 ANCHORING

IS code 14262:1995 mentions following provisions regarding anchoring. Proper anchor is required for keeping the revetment in place and serving the desired function. Upstream edge from where the revetment starts should be secured well to the adjoining bank. Similarly, downstream edge where the revetment ends also needs to be secured well .

Page 33: 2

5.1 G

5.2 G

5.2.1

GENERAL

SpuflowproThpropretyp

GENERAL

IS of s

ALIGNME

Spupoirepspuwitpoikndefspuflow11-ma

urs/Groynw and exotruding inese types one bank. event scopical spur i

            FIG

L DESIGN

code 840spurs

ENT

urs may inting towapels the flour/groynethout repeinting d/sown as flecting spurs may bw. Alignm-2 and 11ay be adop

nes are sxtended frnto river of works The spursuring undis shown i

GURE 10: GRO

FEATURE

8:1994 m

be aligneards u/s oow away f. When a elling, it s of the flattracting

purs are pbe kept at ent of spu-3 showinted.

tructures,rom the

come unare provid

s are provder the wn Figure 1

OYNES FIELD F

ES

mentions fo

d either nor d/s of thfrom the short lengis know

flow attracg spur/grprovided fo an angle urs at ben

ng orientati

construcbank into

nder purvded to keepvided alon

water and 10.

OR TRAINING

ollowing pr

normal tohe flow. A bank and

gth spur chwn as dects the floroyne. Ger anti eros of 50 to nd is showion and sh

cted transo the riveview of anp away flong with laconsequen

G A RIVER 

rovisions

o flow dir spur poin

d is knownhanges on

eflecting sow towardsenerally sion measu100 again

wn in Figuhapes spu

sverse to er. Spursnti erosionow from thaunching nt fall of

regarding

ection or nting u/s on as repelnly directiospur/groyns the banrepelling ures. Repenst the dirre 11-1 al

urs respect

43 | P a g e

the river /groynes, n works.

he erosion apron to spurs. A

planning

at angle of the flow lling type on of flow ne. Spur nk and is

type or elling type rection of lso Figure tively that

Page 34: 2

 

FIGURE 11‐

 FIGURE 11

FIGURE

1: ALIGNMEN

1‐2: SHOWING

E 11‐3: SHOW

NT OF SPURS A

G DIFFERENT 

ING DIFFEREN

AT BENDS TO

ORIENTATION

NT SHAPES OF

 INDUCE SILTA

N OF SPURS

F SPURS

ATION

44 | P a g e

Page 35: 2

5.2.2

5.2.3 R

FUNCTIO

Spurs ser

(a)

(b)

(c)

(d)

RECOMM

1) Impermand adcrates

2) In casepreferrmainteCommGeneraconstru

ONS OF SP

rve followi

Training concentra

Protecting

Creating avicinity of

Improving

MENDED T

meable or djacent shor Gryone

FIG

e of rivers red. The enance andon construally RCC uct, more

URS

ing functi

the rivertion of flow

g the bank

a slack flo the river b

g the depth

TYPE OF S

solid spuank portios.

URE 12: SHOW

carrying cpermeabled any alteuction maporcupine

durable an

ions:

r along w at the po

by keeping

ow with thbank.

hs for navig

PUR

urs are conon is prote

WING SOLID  

considerabe spurs oernation inaterial for e spurs nd give bet

the desiroint of atta

g the flow

he object o

gation purp

nstructed ected by h

SPURS BUILT

ble amounoffers flex

n later stagthese typare prefertter perform

red coursack.

away from

of silting u

pose

with earthheavy mate

T WITH STONE

t of silt, pxibility in ge, if requ

pe spurs irred as tmance

se to red

m it.

up the are

h or rock-erials like

E IN WIRE CRA

ermeable construc

uired, can s RCC pothese are

45 | P a g e

duce the

ea in the

-fill. Nose stones in

ATES

spurs are ction and be made.

orcupines. easy to

Page 36: 2

5

5

5.2.4 O

5.3 D

5.3.1 L

ORIENTAT

IS foll

DESIGN O

IS of s

LENGTH A

Theof porlenspufor thafrom2.5(dsto eddrivedis

TION OF S

code 840owing prov

OF IMPERM

code 840spurs

AND SPAC

e length oland on trtion whi

ngth givenur with h adoptionan that rem the ba

5H:1V and), the lengbank erosdies at noer and mcharge co

FIGURE 13:

SPURS

08:1994 &visions reg

MEABLE B

08:1994 m

CING

of spur shthe bankich is likn in the high groun as effecequired to ank. Thud anticipagth shouldsion at u/

ose. On thmay not oncentratio

:  RCC PROCU

& Draft fogarding ori

BOULDER

mentions f

hould be . Effectivekely to fspur only

und shoutive lengt keep the

us assumated maxd be more/s and d/

he other hwithstandon at the

PINE 

or revisionentation o

R SPURS.

following

decided e length face/couny for the

uld not bth of spur scour ho

ming angleximum scoe than 2.5/s of the

hand, too ld the attnose.

n of IS 8f spurs.

provisions

on the baof the sp

nter the e purposebe taken ir. Length

ole formede of repoour depth

5xds. Shorgroyne dulong spurtack on a

8408:1994

s regardin

asis of avpur shouldriver flowe of tagginto consi

h shouldnd at the noose of sah below rrt length mue to formr may obsaccount o

46 | P a g e

mention

ng design

vailability d be the w. Extra ging the ideration ’t be less ose away and tobe river bed may lead mation of truct the of heavy

Page 37: 2

47 | P a g e

Normally the effective length of spur shouldn’t exceed 1/5th of width of flow in case of single channel. In case of wide, shallow and braided rivers, the protrusion of spur in the deep channel should not exceed 1/5th of the width of channel on which the spur is proposed excluding the length over the bank. The spacing of spurs is normally 2 to 2.5 times its effective length.

5.3.2 TOP LEVEL/TOP WIDTH AND SIDE SLOPE

The top level of spur will be above design flood level with adequate free board. Free board may be adopted as 1m/1.5m. Non-submerged spur will be tied with the embankment, and top level of embankment and top level of spur may be kept same with similar free board and design HFL. The top width of spur should be 3 to 6 m as per requirement. Side slopes of the spur may be kept 2H:1V or 3H:1V depending upon the material being used for construction

5.3.3 WEIGHT OF STONES FOR PITCHING

Stones/boulders used in pitching are subjected to hydrodynamic drag and lift forces. These destabilizing forces are expressed in terms of velocity, tractive forces etc. the stabilizing forces acting against these are component of submerged weight of stones and downward component of force caused by contact of the stones.

The weight of stones on slopes (W in kg) may be worked using the formula given below.

W (in kg) = 0.02323*Ss*V6 /K* (Ss-1) 3 ---------------------------------------- (1) Where K (correction factor for slope) =[1-Sin2θ/Sin2Φ ]1/2

Ss = specific gravity of boulders (may be adopted as 2.65) Φ = Angle of repose of material of protection works (adopted as 300 for boulders) Θ = Angle of sloping bank 2 (H) :1 (V) (26.560) V = Velocity in m/s K = [1-Sin226.560/ Sin2300]1/2 = 0.447 Hence weight of stones for 2H:1V slope W (in kg) = 0.02323*Ss*V6/0.447* (Ss-1)3

Page 38: 2

48 | P a g e

5.3.3.1 SIZEOF STONE/BOULDER.

Size of stone (Ds in m) may be determined from the following relationship.

Ds (in m) = 0.124* (W/Ss) 1/3 --------------------------------------------------- (2) Where: W = Weight of stone in kg Ss = Specific gravity of stone (may be adopted as 2.65) Minimum diminution of stones > Ds

Generally, the size of stone should be such that its length, width and thickness are more or less same ie stones should be more or less cubical. Round stones or very flat stones having small thickness should be avoided.

5.3.4 THICKNESS OF PITCHING

Minimum thickness of pitching (t) or protection layer is required to withstand the negative head created by the velocity. This may be determined by the following equation.

Minimum thickness of pitching (t in m) = V2/2g (Ss-1) ------------------ (3) V= Velocity in m/sec g= Gravitational acceleration in m/sec2 Ss= Specific gravity of stone (Generally adopted as 2.65).

Therefore thickness of pitching should be higher than t (as obtained above). Two layers of stones of minimum size t should be provided when pitching is being provided with boulders in loose.

5.3.4.1 PITCHING IN CRATES

At high velocity, required weight of stones (to be found by equation no 1) comes out to be higher, which makes handling and placing of stones a bit difficult. In such cases or in case when requisite sized stones are not available, small size stones filled in GI (Galvanized Iron) wire crates may be used for pitching purpose. In this case single layer of GI wire crates

filled with stones having thickness more than „t‟ may be used as pitching. The specific gravity of the crate is different from the boulders due to presence of voids. Porosity of the crates (e) may be worked out using the following formula

e = 0.245+ 0.0864/ (D50) 0.21 ---------------------------------------------------(4) Where D50 = mean diameter of stones used in mm. let us assume D50 as 250 mm e = 0.245 + 0.0864/ (250)0.21

= 0.27

Page 39: 2

49 | P a g e

The opening in the wire net used for crates should not be larger

than the smallest size of stone used. The mass specific gravity of protection (Sm) can be worked out using the following relationship.

Sm= (1-e) *Ss------------------------------------------------------------------- (5)

This mass specific gravity may be used to work out the weight of

the crates and this weight should be more than weight of stone required, worked out by the equation no.1.

Crates should be laid with long dimension along the slope of the

bank. Crates must be tied to each other by 5 mm GI wire as additional protection. If crates are being provided in layers then each layers should be tied to each other at suitable interval using the 4 mm GI wire.

5.3.5 FILTER

A graded filter of size 150 mm to 300 mm thickness may be laid beneath the pitching to prevent failure by sucking action by high velocity. Geo- synthetic filter may also be used as that is easy to lay, durable, efficient and quality control is easy. A 150 mm thick sand layer over the Geo- synthetic filter may be laid to avoid rupture of fabric by the stones.

5.4 LAUNCHING APRON FOR SPUR

IS code 8408:1994 & 14262:1995 mentions following provisions regarding launching apron.

To prevent the sliding and failure of the spur due to scouring action by

the river current, provision of launching apron is kept to take care of the scouring at nose and at shank (portion in the river) of the spur.

Launching apron should be laid at low water level (LWL). The launching

apron may be laid using the stones or geo-bags. The stones/geo-bags in the apron should be designed to launch along the slope of scour and provide a protection layer so that scouring is checked. The size of launching apron should be such that it should form a protection layer up to level of maximum scour depth. Slope of launching apron may be taken as 2H:1V. Filter below the launching apron may also be provided so that river bed material is safe against suction

5.4.1 SIZEOFLAUNCHINGAPRON

Width of the launching apron depends upon the scour depth below HFL. Depth of scour below HFL (D) may be worked out suing the following formula.

D = 0.473 (Q/f) 1/3 -------------------------------------------------------------- (6.1) and D= 1.33 (q2/f) 1/3 ---------------------------------------------------------------- (6.2) Where Q= design discharge in cumecs and q= design discharge per unit width or design discharge intensity in cumecs/m. f is silt factor. Silt factor (f) may be calculated using the following formula f= 1.76 (d) 1/2---------------------------------------------------------------------- (7) where d is mean particle diameter of river material in mm

Page 40: 2

50 | P a g e

Generally scour depth (D) below HFL should be calculated using the design discharge (equation no.6.1). In some cases (for braided rivers) scour depth may be calculated using the design discharge intensity (equation no. 6.2).

Maximum scour depth (Dmax) below HFL= 1.5* Scour depth (Dbelow HFL). Maximum Scour depth (Dmax) below LWL = (Dmax)below HFL – (HFL-LWL)

If the launching apron is being laid at LWL then width of the launching apron should be calculated using the following formula at different locations of the groyne.

Thickness of launching apron (T) = 1.5* thickness of pitching (t).In some cases, thickness of the launching apron is kept different from due to size of crates etc (if launching apron is being provided in crated stones), then width of the launching apron may be revised keeping the volume of stones same per unit length of the apron.

5.5 DESIGN OF PERMEABLE SPURS

Draft for 2nd revision of IS code 14262:1995 mentions following provisions regarding permeable spurs

5.5.1 INTRODUCTION

Unlike impermeable spurs which do not allow any water to flow through its body (except seepage due to differential head),permeable porcupines are pervious enough so that the flow takes place across the groynes through their bodies. Up to 35% permeability (defined as the area of opening to the total area of flow intercepted by spurs i.e. the product of its length normal to the flow and the depth of flow), the behavior of a permeable spur, as far as its effectiveness in bank protection is concerned, is almost similar to that of an impermeable groyne. As the permeability increases, the length of the protected reach of bank gets reduced since eddies are reduced. As the flow passes through the permeable groynes, the micro eddies and the turbulence produced downstream of the groynes cause dampening of flow (due to energy dissipation) and consequent reduction in velocity. As a result the erosive power of the flow is reduced.

(i) Width of launching apron at nose (2-2.5) * (Dmax) below LWL

(ii) Width of launching apron at transition from nose to shank and first 30 m to 60 m in u/s

1.5 * (Dmax) below LWL

(iii) Width of launching apron in shank portion for next 30 m to 60 m

= 1.0 * (Dmax) below LWL

(iv) Width of launching apron at transition from nose to shank and first 15 m to 30 m in d/s

= 1.0 * (Dmax) below LWL

Page 41: 2

51 | P a g e

5.5.2 PORCUPINES SPURS

They are made of RCC having cubical shaped box at the central portion with their legs extending in different directions. The central box is filled with stones for the stability of the individual units of porcupines having size varying from 2 to 3 m. The individual units are placed side by side in a row and are tied. The spacing between the two consecutive units of porcupines will depend upon the desired permeability varying from 30 to 50%. The spacing of two consecutive rows of porcupines varies from 3L to 4L, where L is the length of spur.

5.5.3 SUBMERGENCE OF SPURS

Unlike impermeable spurs which are un-submerged with freeboard, permeable spurs may be either un-submerged or submerged. Submergence up to 50% is acceptable for porcupines.

5.5.4 LENGTH AND SPACING OF PERMEABLE SPURS

Considerations similar to those as already discussed for impermeable groynes under clause 5.2 should be followed in deciding length and spacing of permeable spurs. Very long spurs should not be provided due to difficulties in construction as well as maintenance against scour. The spacing of spurs will be determined by their lengths. Shorter spurs at closer interval is desirable in curved outer banks of a meandering stream compared to those in the straight reach of rivers. Arrangement of RCC Porcupine structure adopted in River Ganga is shown in Figure 14

Permeable spurs are less costly compared to impermeable ones. Submerged types is proposed for meandering reaches with deep water near concave bank. Due to dampening of flow, the sediment carrying capacity of flow behind the spurs get reduced resulting in deposition of sediments and building of banks along the affected reach.

Page 42: 2

   

FIGURE 14: PLAN SHOWINNG TEMPORARRY PROTECTIOON WORKS AGANGA 

ADOPTED  IN TTHE EROSION PRONE REAC

52 | P a g e

CH OF RIVER 

Page 43: 2

6

6

6.1 G

6.1.1 C

6.1.2 F

(((

(

GENERAL

General d

CONCEPT

Damthe and

If thvelopro

Onlin tin uthe requavo

FUNCTIONPermeabl

(a) Trainin(b) Reducin(c) Creatin

structu(d) Providin

bank.

Use of RC

L DESIGN F

design feat

T

mpening o flow is sed the chan

he flow is ocity can otected reac

ly partial othe design.undesired nose pouired to a

oided.

NS OF PERle structur

ng the riverng the inte

ng a slack fures and inng protecti

CC porcup

FEATURE

tures of RC

of velocity iediment lanel is shift

not carryresult. S

ch.

obstruction. Higher ob scouring

ortion. Addavoid such

RMEABLEres serve o

r along theensity of floflow to ind

n the d/s rion to the

ines for sla

FIGURE 15: R

ES

CC porcup

is achievedden, siltatted away fr

ying the suSedimentat

n to the flobstruction around thditional p scour. Th

E STRUCTne or more

e desired coow at the p

duce siltatieach. bank by d

ackening t

RCC PORCUPIN

pine are g

d by usingtion is indurom the pr

ufficient setion may

ow of abou causes mhe proposeprotection herefore, ob

URES e of the fol

ourse. point of rivon in the v

ampening

the flow is

NES FOR SLAC

given below

g the permuced in throtected re

ediments, not be a

ut 15 to 20ore diversied structuto the nbstruction

lowing fun

ver attack. vicinity of t

the velocit

shown in F

CKENING THE 

w in detail.

meable struhe slack floach.

only damachieved

% only is eion of flow

ures, particnose and n more tha

nctions:

the permea

ty of flow a

Figure 15.

FLOW

53 | P a g e

.

uctures. If ow region

pening of near the

envisaged w resulting cularly at flanks is

an 20% is

able

along the

Page 44: 2

54 | P a g e

6.1.3 STRUCTURAL ELEMENTS

The elements used in the RCC porcupine spurs are as under:

(a) Members: The porcupines are made of RCC members/elements. These members are casted in-situ at the site or location near the site. Generally six members are used to construct one porcupine.

(b) Nails: Standard commercially available nails of length 100 mm to 150 mm are used to join the porcupine members. Double nailing at critical joints may be provided.

(c) GI Wire: 4 to 5 strands of 4 mm GI wire should be used for inter- connecting the porcupines and may be anchored with the ground. Alternatively, 12 mm 3-4 strands wire ropes should be used for the interconnecting the porcupines.

6.2 LIMITATION OF RCC PORCUPINES

(a) In case of high velocity flows, implementation of only RCC porcupine works is not favored. However, use of RCC porcupine works in between the reach of two solid boulder spurs is more effective

(b) .Generally additional quantities of RCC porcupines is kept for placing the RCC porcupines in 2nd year or during consequent years at locations where partial silting has been taken place after implementation of RCC porcupines in 1st year. In the absence of placing additional porcupine, the silted region near the bank may not become firm.

6.3 REFERENCES

1. Guidelines for planning and design of Permeable structures in alluvial rivers

7.0 LIMITATION OF SPURS

CBIP-manual “River Behavior Management and Training Volume-I -1989” stipulates that the success of repelling type spur depends upon the extent and the quickness with which scour occurs at the nose, and also on how quickly the pockets between the spurs get filled up with sediment. This condition make the impermeable groynes useless in boulder rivers, in which the rate of silt deposition may be slow or in flashy rivers in which floods rise and fall so quickly that desired silting doesn’t take place. The spurs can’t be relied upon to afford immediate protection.

It is also observed that silting between the successive spurs can be accomplished only when their lengths are sufficient. Short spurs don’t offer sufficient protection.

In case of narrow and deep rivers, the cost of solid spurs above high water is substantial. Moreover, because of the narrow width of rivers, solid spurs can’t be extended much as otherwise they can cause harmful conditions on the opposite bank or further d/s. In such cases submerged spurs are recommended.

Page 45: 2

55 | P a g e

As the tractive force on the slope is maximum at 1/3 depth from the bottom, the top of spur should be kept at least half of depth of water. A single submerged spur may not be as effective as series of submerged spurs. Since flow over the spurs produces turbulence and scour below them, silting may not take place as rapidly as required. It may be concluded that permeable spurs are effective only in rivers which carry heavy suspended load.

8.0 REFERENCES

1. IS code 8408:1994. 2. Irrigation and Hydraulic structures- S. K. Garg. 3. River Behavior Management and Training Volume-I (Central Irrigation and Power (CBIP), 1989).

4. Draft for revision of IS code 8408:1994

Page 46: 2

56 | P a g e

9.0 Estimate Cost estimate per running meter for proposed bank protection work by constructions

of embankment with stones in wire crates and launching apron and constructions of embankment with stones in wire crates and cut off wall is calculated below .

The Rates for the proposed work are taken from following SOR.

1) SOR of Ahmedabad Irrigation Department of year 2012-2013 2) SOR of Narmada Water Resources water supply and Kalpsar Department 2012-

2013 for South Gujarat

Page 47: 2

57 | P a g e

SR   DESCRIPTION   NO  LENGTH  BREATH  DEPTH  UNIT  TOTAL 

Stripping the Canal Construction width and Borrow area in all sorts of soil soft murrum including depositing the materials as and where directed for inspection road etc with lead upto 1 KM and all lifts etc comp . SOR Ahmedabad Irrigation Department 2012-2013 Chapter No 1 Sr No 3

1 1 53.7 0.3 Cum 16.11

Trimming of Slope in 3.5H:1V

H=12m Therefore L=12*3.5 =42 m Slope length =(42^2+12^2)^0.5 =43.7 m

Slope length= 43.7 +10 =53.7 m

Earthwork in embankment from Borrow Pits in all sorts of soil and Soft murrum or other suitable Strata as directed including breaking the clods and dressing to the design sections including cutting the proud section with lead as under and all lift including site clearing etc complete . SOR Ahmedabad Irrigation Department 2012-2013 Chapter No 1 Sr No 3.

For Lead 200 to 1000 Mt.

EMBANKMENT QUANTITY

1 0.5 17.25 6.9 Cum 59.52 1 1 5 6.9 Cum 34.5 1 0.5 17.25 6.9 Cum 59.52

1 1 17.25 6.9 Cum 119.0

3 1 1 5 13.8 Cum 69 1 0.5 3.6 1.8 Cum 3.24

DEDUCTION 1 0.5 42 12 Cum 252 1 1 6.1 12 Cum 73.2

TOTAL 19.61

Page 48: 2

58 | P a g e

Compaction of Earth work in Embankment in layers of 15 cms to 23 cms thick at requisite moisture content to required dry density including necessary watering and rolling with roller of suitable type. SOR Ahmedabad Irrigation Department 2012-2013 Chapter 5 Sr no 10

1 Cum 19.61

4

Hexagonal Zn Pvc Coated Box Wire Mesh Gabions Size 4mx1m X1m Filled With 30 To 50 Kg. Trap Rubble Stone (Approximate 4.5) Tone With Mesh Size 10x12cm Including Packing Interlocking Of Stones And Fusing Top Of Gabion And Tying To Each Other & Laying To The Required Line Level Slope With All Leads & Lifts As Directed Etc. Comp In River Side Slope Sor Narmada Water Resources Water Supply And Kalpsar Department 2012-2013 For South Gujarat Region Chapter 6 Sr No 14

1  1  42  1  No  42 

5

Providing and laying Dry Rubble pitching with base of inverted filter as per design and Drawing including providing Headers or hand packing trimming and dressing of slopes etc complete for leads as specified and all lifts etc complete SOR Narmada Water Resources water supply and Kalpsar Department 2012-2013 for South Gujarat Region Chapter 1 Sr no 13

1  1  4.02  1  Sqm  4.02 

30 cm thick pitching with 15 cms filter.

                 

Page 49: 2

59 | P a g e

6

Hexagonal Zn Pvc Coated Box Wire Mesh Gabions Size 4mx1m X1m Filled With 30 To 50 Kg. Trap Rubble Stone (Approximate 4.5) Tone With Mesh Size 10x12cm Including Packing Interlocking Of Stones And Fusing Top Of Gabion And Tying To Each Other & Laying To The Required Line Level Slope With All Leads & Lifts As Directed Etc. Comp In Launching Apron Sor Narmada Water Resources Water Supply And Kalpsar Department 2012-2013 For South Gujarat Region Chapter 6 Sr No 14

1 1 9 1 No 9

Providing and laying 7.5 cms thick controlled cement concrete lining of M-15 grade in Bed ,side, slopes and curvature including weight ,batching, mixing, transportation, placing ,vibrating dressing the slopes and bed in earth to correct profile with finishing as required to the exposed surfaces making asphalt joints as directed and watering curing including dewatering where required etc complete SOR Ahmedabad Irrigation Department 2012-2013 Chapter No 4 Sr No 11.

1 1 42 1 Sqm 42

Proving And Laying Geo Fabric Filter (Gwf-50-300 Category ) Over The Excavated Surface As Per Specification Including Stitching With Overlap To Design Profile As Directed In Tidal Range Etc complete. SOR Narmada Water Resources water supply and Kalpsar Department 2012-2013 for South Gujarat Region Chapter 6 Sr no 1

1 1 51.1

6 1 Sqm 51.16

B = 42.16+9 =51.16 m 

Page 50: 2

60 | P a g e

Sr no 

DESCRIPTION  UNIT Quantit

y Rate  TOTAL 

1

Stripping the Canal Construction width and Borrow area in all sorts of soil soft murrum including depositing the materials as and where directed for inspection road etc with lead upto 1 KM and all lifts etc comp . SOR Ahmedabad Irrigation Department 2012-2013 Chapter No 1 Sr No 3

Cum 16.11 30.5 491.36

2

Earthwork in embankment from Borrow Pits in all sorts of soil and Soft murrum or other suitable Strata as directed including breaking the clods and dressing to the design sections including cutting the proud section with lead as under and all lift including site clearing etc complete . SOR Ahmedabad Irrigation Department 2012-2013 Chapter No 1 Sr No 3.

Cum

For Lead 200 to 1000 Mt. 19.61 61 1196.21

3

Compaction of Earth work in Embankment in layers of 15 cms to 23 cms thick at requisite moisture content to required dry density including necessary watering and rolling with roller of suitable type. SOR Ahmedabad Irrigation Department 2012-2013 Chapter 5 Sr no 10

Cum 19.61 16 313.76

4

Hexagonal Zn Pvc Coated Box Wire Mesh Gabions Size 4mx1m X1m Filled With 30 To 50 Kg. Trap Rubble Stone (Approximate 4.5) Tone With Mesh Size 10x12cm Including Packing Interlocking Of Stones And Fusing Top Of Gabion And Tying To Each Other & Laying To The Required Line Level Slope With All Leads & Lifts As Directed Etc. Comp In River Side Slope SOR Narmada Water Resources Water Supply And Kalpsar Department 2012-2013 For South Gujarat Region Chapter 6 Sr No 14

No 42 2299.75 96589.5

Note: Rate for Gabion Mesh Per meter Length = Gabion Mesh of Size 4x1x1/4

Page 51: 2

61 | P a g e

5

Providing and laying Dry Rubble pitching with base of inverted filter as per design and Drawing including providing Headers or hand packing trimming and dressing of slopes etc complete for leads as specified and all lifts etc complete SOR Narmada Water Resources water supply and Kalpsar Department 2012-2013 for South Gujarat Region Chapter 1 Sr no 13

Sqm 4.02 250 1005

30 cm thick pitching with 15 cms filter.

6

Hexagonal Zn Pvc Coated Box Wire Mesh Gabions Size 4mx1m X1m Filled With 30 To 50 Kg. Trap Rubble Stone (Approximate 4.5) Tone With Mesh Size 10x12cm Including Packing Interlocking Of Stones And Fusing Top Of Gabion And Tying To Each Other & Laying To The Required Line Level Slope With All Leads & Lifts As Directed Etc. Comp In Launching Apron Sor Narmada Water Resources Water Supply And Kalpsar Department 2012-2013 For South Gujarat Region Chapter 6 Sr No 14

No 9 2299.75 20697.75

Note: Rate for Gabion Mesh Per meter Length = Gabion Mesh of Size 4x1x1/4

7

Providing and laying 7.5 cms thick controlled cement concrete lining of M-15 grade in Bed ,side, slopes and curvature including weigh, batching, mixing, transportation, placing ,vibrating dressing the slopes and bed in earth to correct profile with finishing as required to the exposed surfaces making asphalt joints as directed and watering curing including dewatering where required etc complete SOR Ahmedabad Irrigation Department 2012-2013 Chapter No 4 Sr No 11.

Sqm 42 306 12852

8

Proving And Laying Geo Fabric Filter (Gwf-50-300 Category ) Over The Excavated Surface As Per Specification Including Stitching With Overlap To Design Profile As Directed In Tidal Range Etc. Complete. SOR Narmada Water Resources water supply and Kalpsar Department 2012-2013 for South Gujarat Region Chapter 6 Sr no 1

Sqm 51.16 78.9 4036.53

TOTAL RS PER RUNNING METER  137183 

Page 52: 2

62 | P a g e

SR NO 

DESCRIPTION  

NOLENGTH  BREATH  DEPTH  UNIT  TOTAL 

Stripping the Canal Construction width and Borrow area in all sorts of soil soft murrum including depositing the materials as and where directed for inspection road etc with lead upto 1 KM and all lifts etc comp . SOR Ahmedabad Irrigation Department 2012-2013 Chapter No 1 Sr No 3

1 1 53.7 0.3 Cum 16.11

Trimming of slope in 3.5H:1V

H=12m

Therefore L=12*3.5 =42 m

Slope length =(42^2+12^2)^0.5

Slope length= 43.7 +10 =53.7 m

Earthwork in embankment from Borrow Pits in all sorts of soil and Soft murrum or other suitable Strata as directed including breaking the clods and dressing to the design sections including cutting the proud section with lead as under and all lift including site clearing etc complete . SOR Ahmedabad Irrigation Department 2012-2013 Chapter No 1 Sr No 3.

For Lead 200 to 1000 Mt.

0.5 17.25 6.9 Cum 59.52

1 5 6.9 Cum 34.5

0.5 17.25 6.9 Cum 59.52

1 17.25 6.9 Cum 119.03

1 5 13.8 Cum 69

0.5 3.6 1.8 Cum 3.24

DEDUCTION 0.5 42 12 Cum 252

1 6.1 12 Cum 73.2

TOTAL 19.61

Page 53: 2

63 | P a g e

3

Compaction of Earth work in Embankment in layers of 15 cms to 23 cms thick at requisite moisture content to required dry density including necessary watering and rolling with roller of suitable type. SOR Ahmedabad Irrigation Department 2012-2013 Chapter 5 Sr no 10

1 Cum 19.61

4

Hexagonal Zn PVC Coated Box Wire Mesh Gabions Size 4mx1m X1m Filled With 30 To 50 Kg. Trap Rubble Stone (Approximate 4.5) Tone With Mesh Size 10x12cm Including Packing Interlocking Of Stones And Fusing Top Of Gabion And Tying To Each Other & Laying To The Required Line Level Slope With All Leads & Lifts As Directed Etc. Comp In River Side Slope SOR Narmada Water Resources Water Supply and Kalpsar Department 2012-2013 for South Gujarat Region Chapter 6 Sr no 14

1 1 42 1 No 42

5

Providing and laying Dry Rubble pitching with base of inverted filter as per design and Drawing including providing Headers or hand packing trimming nd dressing of slopes etc complete for leads as specified and all lifts etc complete SOR Narmada Water Resources water supply and Kalpsar Department 2012-2013 for South Gujarat Region Chapter 1 Sr no 13

1 1 4.02 1 Sqm 4.02

30 cm thick pitching with 15 cms filter.

6

Excavation in all sorts of soil with yellow ,sandy gravelly soil including sorting and stacking and depositing the excavated stuff in uniform layers as and where directed up to lead of 30 mt and lift as shown below including clearing the site etc complete.(including dewatering ).SOR Ahmedabad Irrigation Department 2012-2013 Chapter 5 Sr no 1

0 to 3 m Depth 1 1 0.6 3 Cum 1.8

3 to 6 m Depth 1 1 0.6 6 Cum 3.6

Page 54: 2

64 | P a g e

7

Providing and laying plain /Reinforced ordinary Portland cement concrete of M 25Grade in Cut off wall with cement sand and coarse aggregates including centering shuttering batching mixing transportation placing vibrating smooth finishing curing etc. complete for all leads and lift SOR Narmada Water Resources Water Supply and Kalpsar Department 2012-2013 for South Gujarat Region Chapter 4 Sr no 10

1 1 0.6 6 Cum 3.6

8

Providing and laying HYSD Steel bar reinforcement for R.C.C Works and anchor bars with providing binding wires including cutting ,bending, welding, binding in position hooking, placing in position with all leads and lift etc. SOR Ahmedabad Irrigation Department 2012-2013 Chapter 3 Sr no 7

1 80 kg/m3 Kg 288

9

Providing and laying 7.5 cms thick controlled cement concrete lining of M-15 grade in Bed ,side, slopes and curvature including weight ,batching, mixing, transportation, placing ,vibrating dressing the slopes and bed in earth to correct profile with finishing as required to the exposed surfaces making asphalt joints as directed and watering curing including dewatering where required etc complete SOR Ahmedabad Irrigation Department 2012-2013 Chapter No 4 Sr No 11.

1 1 42 1 Sqm 42

10

Proving And Laying Geo Fabric Filter (Gwf-50-300 Category ) Over The Excavated Surface As Per Specification Including Stitching With Overlap To Design Profile As Directed In Tidal Range Etc. Complete. SOR Narmada Water Resources water supply and Kalpsar Department 2012-2013 for South Gujarat Region Chapter 6 Sr no 1

1 1 42 1 Sqm 42

11

Providing and laying (Paralink 200) 200 KN/m High Strength uniaxial Geogrid with low creep characteristics, Geogrid consisting of PET and having an outer protective coating of low density polyethylene sheath conforming to detailed specifications and drawings.

1 1 10 1 Sqm 10

At Cut Off

Page 55: 2

65 | P a g e

SR NO  DESCRIPTION  UNITQUANTITY 

RATE  TOTAL 

1

Stripping the Canal Construction width and Borrow area in all sorts of soil soft murrum including depositing the materials as and where directed for inspection road etc with lead up to 1 KM and all lifts etc comp . SOR Ahmedabad Irrigation Department 2012-2013 Chapter No 1 Sr No 3

Cum 16.11 30.5 491.36

2

Earthwork in embankment from Borrow Pits in all sorts of soil and Soft murrum or other suitable Strata as directed including breaking the clods and dressing to the design sections including cutting the proud section with lead as under and all lift including site clearing etc complete . SOR Ahmedabad Irrigation Department 2012-2013 Chapter No 1 Sr No 3.

For Lead 200 to 1000 Mt.

TOTAL 19.61 61 1196.21

3

Compaction of Earth work in Embankment in layers of 15 cms to 23 cms thick at requisite moisture content to required dry density including necessary watering and rolling with roller of suitable type. SOR Ahmedabad Irrigation Department 2012-2013 Chapter 5 Sr no 10

Cum 19.61 16 313.76

4

Hexagonal Zn PVC Coated Box Wire Mesh Gabions Size 4mx1m X1m Filled With 30 To 50 Kg. Trap Rubble Stone (Approximate 4.5) Tone With Mesh Size 10x12cm Including Packing Interlocking Of Stones And Fusing Top Of Gabion And Tying To Each Other & Laying To The Required Line Level Slope With All Leads & Lifts As Directed Etc. Comp In River Side Slope SOR Narmada Water Resources Water Supply and Kalpsar Department 2012-2013 for South Gujarat Region Chapter 6 Sr no 14

No 42 2300 96600

Providing and laying Dry Rubble pitching with base of inverted filter as per design and Drawing including providing Headers or hand packing trimming and dressing of slopes etc complete for leads as specified and all lifts etc complete SOR Narmada Water Resources water supply and Kalpsar Department 2012-2013 for South Gujarat Region Chapter 1 Sr no 13

Sqm 4.02 250 1005

30 cm thick pitching with 15 cms filter.         

Page 56: 2

66 | P a g e

6

Excavation in all sorts of soil with yellow ,sandy gravelly soil including sorting and stacking and depositing the excavated stuff in uniform layers as and where directed up to lead of 30 mt and lift as shown below including clearing the site etc complete.(including dewatering ).SOR Ahmedabad Irrigation Department 2012-2013 Chapter 5 Sr no 1

0 to 3 m Depth Cum 1.8 54 97.2

3 to 6 m Depth Cum 3.6 56 201.6

7

Providing and laying plain /Reinforced ordinary Portland cement concrete of M 25Grade in Cut off wall with cement sand and coarse aggregates including centering shuttering batching mixing transportation placing vibrating smooth finishing curing etc complete for all leads and lift SOR Narmada Water Resources Water Supply and Kalpsar Department 2012-2013 for South Gujarat Region Chapter 10 Sr no 10 C

Cum 3.6 4639.4 16701.84

8

Providing and laying HYSD Steel bar reinforcement for R.C.C Works and anchor bars with providing binding wires including cutting ,bending, welding, binding in position hooking, placing in position with all leads and lift etc. SOR Ahmedabad Irrigation Department 2012-2013 Chapter 3 Sr no 7

Kg 288 53.86 15511.68

9

Providing and laying 7.5 cms thick controlled cement concrete lining of M-15 grade in Bed ,side,slopes and curvature including weight ,batching, mixing, transportation, placing ,vibrating dressing the slopes and bed in earth to correct profile with finishing as required to the exposed surfaces making asphalt joints as directed and watering curing including dewatering where required etc complete SOR Ahmedabad Irrigation Department 2012-2013 Chapter No 4 Sr No 11.

Sqm 42 306 12852

10

Proving And Laying Geo Fabric Filter (Gwf-50-300 Category ) Over The Excavated Surface As Per Specification Including Stitching With Overlap To Design Profile As Directed In Tidal Range Etc. Complete. SOR Narmada Water Resources water supply and Kalpsar Department 2012-2013 for South Gujarat Region Chapter 6 Sr no 1

Sqm 42 78.9 3313.8

Page 57: 2

67 | P a g e

11 

Providing and laying (Paralink 200) 200 KN/m High Strength uniaxial geogrid with low creep characteristics, Geogrid  consisting of PET and having an outer protective coating of low density polyethylene sheath conforming to detailed specifications and drawings.  

Sqm  10  220  2200 

TOTAL RS PER RUNNING METER  149994  

Page 58: 2

E

hath

Tdu

Tcr

Texre

Existing Bankaving erosivhe Bank becoThe Stone in

uring high FThe Gravity wrates will be

The Terramesxtending intoeduce the ma

FIGURE

ks of Sabarmve nature . Duome over ha

n Wire MeshFlood and pewall of Stone very difficush System coo the soil whassive Gravi

15SHOWINGGA

mati gets erouring each F

anging cliff w Gabion will

ermanent Reges in Wire Cult to obtain onsist of Fachich act as soity section.

ABIONRETAINGW

ded during HFlood the Bowhich collapl act as Rigidgime Condit

Crates will beand construccia Gabbion oil reinforce

WALLCONSTRUC

High Flood aottom of the pse after somd Wall and wtion is devele to massivect and involvand with a s

ement into th

CTEDUSINGTERR

as they mainBanks gets

me time and Bwithstand eroped

e and requireve huge costsection of thhe backfill so

RRAMESHSYSTEM

68 | P

nly consist sieroded and

Banks becomrosive forces

ed stones andt.

he mesh oil, which w

M

a g e

ilty sandy soTop portion

me eroded. s

d

ill

oil of

Page 59: 2

69 | P a g e

1.1 DEFINATIONS Terramesh is defined as PVC coated heavily galvanized steel wire mesh box-

shaped basket with a section of the mesh extending into the soil to act as soil reinforcement into the backfill soil. The basket is filled on site with clean-hard stones.

The selvedges of the Terramesh are the thicker perimeter and edge wires to

which the wire mesh is securely tied to withstand sudden or gradual stress from any direction.

The diaphragms are the internal wire mesh partitions which divide the

Terramesh box into approximately equal sized cells. Lacing and bracing wire is the wire used to assemble and join

the Terramesh units. Connecting wires are the internal wires used to prevent the Terramesh from

bulging during filling.

1.2 GENERAL DESCRIPTION

Terramesh is made from flexible woven wire Heavily Galvanized and PVC Coated 80mm type mesh boxes with integral panels of dimensions as specified in the Contract drawings or an approved equivalent.

Terramesh system can be placed in two ways

1)Terramesh with Vertical Face 2)Terramesh with a Battered Face.

Page 60: 2

  FIGURE 16

The front fcontinuouvertically oreinforcem

6: FIGURE SHO

face box ans mesh panon the gab

ment panel.

OWING TERRAM

nd the soil nel For Terion face an

MESH SYSTEM

reinforcemrramesh thnd perpend

M WITH VERTIC

ment tail shahe mesh twdicular to t

CAL FACE AND 

all be madewists are orthe front fa

70 | P

BATTERED FA

e from one riented ace in the

a g e

CE 

FIGURE 17: FIGURE SHOWING TERRAMESH SYSTEM WITH WIRE CRATES

Page 61: 2

71 | P a g e

  

1.3 STEEL WIRE

(i) General

All steel wire used in the fabrication of the Terramesh, and also in the wiring operations during construction, shall be to BS 1052, having a tensile strength of not less than 380 N/mm2 and not exceed 550 N/mm2.

(ii) Wire Diameter

Wire diameters and relevant tolerances shall be in accordance with the following table:

Wire Diamet

Wire use Tolerance

2.20 Lacing Wire ± 0.06 2.70 Body Wire ± 0.08 3.40 Selvedge Wire ± 0.10

(iii) Zinc Coating

All wire used in the fabrication of the Terramesh and in the wiring operations during construction shall be heavily galvanized and exceed BS 443, the minimum mass of the zinc coating shall be according to the figures shown in the table below:

Diameter of Wire

Weight of Coating

2.2 242.7 263.4 27

The adhesion of the zinc coating to the wire shall be such that when the wire is wrapped six times around a four wire diameter size mandrel it shall not flake or crack to such an extent that any zinc can be removed.

(iv) PVC Coating

All wire used in the fabrication of Terramesh and in the wiring operations during construction shall have extruded onto it (after coating it with zinc in accordance with the foregoing specification) a coating of Poly Vinyl Chloride, otherwise referred to as “PVC”, or other plastic material having superior characteristics than PVC as otherwise approved.

Page 62: 2

72 | P a g e

The coating shall be 0.50mm average thickness with a tolerance of ± 0.05mm, and nowhere shall be less than 0.40mm thickness.

The PVC shall be grey in colour.

It shall be capable of resisting deleterious effects of natural weather exposure, immersion in salt water and not show any material difference in its initial characteristics which are :

a) Specific GravityShall be 1.30 to 1.35 in accordance with ASTM D 792-91

a) Durometer HardnessShall be 50 to 60 shore D, in accordance with ASTM D 2240-91 (ISO 868-1985)

b) Volatile LossAt 105°C for 24 hours - Shall not be greater than 5% In accordance with ASTM D 2287-92 E2. Residual Ashes shall be less than 2% according to ASTM D2124-62T.

c) Tensile StrengthShall not be less than 210 kg/sq.cm in accordance with ASTM D 412-92.

d) ElongationShall not be less than 200% and not greater than 280% in accordance with ASTM D 412- 92.

e) Modulus of Elasticity at 100% of ElongationShall not be less than 190 kg/sq.cm in accordance with ASTM D 412-87.

f) Resistance of AbrasionThe loss in volume shall be less than 0.30cm3 in accordance with ASTM D 1242-56.

g) Creeping CorrosionMaximum penetration of corrosion of the wire core from a square cut end shall not be greater than 25mm when the specimen has been immersed for 2000 hours in a 50% solution of HCL (Hydrochloric Acid 12 BE).

Page 63: 2

73 | P a g e

Testing for deterioration shall be as described below. Variation of the initial characteristics may be allowed, as specified hereunder, when the specimen is submitted to the following tests :

Salt Spray

According to ASTM B 117-90 Period of test = 1500 hours

Exposure to Ultraviolet Light

According to ASTM D 1499-92 and ASTM G 23(93) apparatus type E. Period of test = 2000 hours at 63°C.

Exposure at High Temperature

According to ASTM D 1203-89, (ISO 176-1976) and ASTM D 2287-(92)E2. Period of test = 240 hours at 105°C.

Brittleness temperature : cold bend less than -30°C test method BS2782-104A; cold flex less than +15°C in accordance with BS2782-151A(84).

After the above tests have been performed, the PVC coating shall exhibit the following properties :

a) Appearance

The vinyl coating shall not crack, blister or split and shall not show any marked change in colour.

a) Specific Gravity

Shall not show change higher than 6% of its initial value.

b) Durometer Hardness Shall not show change higher than 10% of its initial value.

c) Tensile Strength

Shall not show change higher than 25% of its initial value.

d) Elongation Shall not show change higher than 25% of its initial value.

e) Resistance to Abrasion

Shall not show change higher than 10% of its initial value.

f) Brittleness Temperatures Cold-bend not exceeding -20°C; cold-flex not exceeding +18°C.

Page 64: 2

1.4 W

W

T

ththa

T

4Ceb

WIRE MES

Wire meshhexagonalpair of wirtwist), in s

Double

The tightnehan 1.7 khe other w

applied forc

The mesh 47 kN/m. Certain othngineer. T

below:

SH

h shall be l woven mres througsuch a ma

-twist mes

ess of the kN is requwire, provices, and t

tensile stAll wire u

her wire diThe wire m

mechanicmesh whergh three haanner that

sh is demo

twisted joired whenided each he wire is

trength, inused in Teiameters m

mesh dimen

ally pre-faein the joialf-turns (c unravelin

onstrated

oints shall n pulling owire is pr all in the

n soil, is erramesh umay be utinsional lay

abricated tints are forcommonly

ng is preve

in the ske

be such ton one wirevented fr same pla

to be equunits shalilized if spyout is as

to become rmed by tw

y known asented.

etch below

that a forcire to separom turnin

ane.

ual to or ll be PVC cpecified by per the d

74 | P

a uniformwisting eas double

w-

ce of not learate it frng under t

greater thcoated. y the

diagram

a g e

m ach

ess om the

han

Page 65: 2

75 | P a g e

Mesh X ( mm ) Y ( mm ) Tolerance % 8 82 122 + 5 %

1.5 SELVEDGES

The cut edges of all mesh used in the construction of Terramesh

System, except the bottom edges of diaphragms and the end of the soil reinforcing tail shall be tightly selvedged with a wire having a diameter of at least 3.40 mm.

The side selvedge of all and any mesh panels shall be woven

integrally with the main mesh as described in the above clause 1.5 with a selvedge wire of at least 3.40 mm in diameter.

Where the selvedge is not woven integrally with the mesh but has to

be fastened to the cut ends of the mesh, it must be attached by mechanically binding the cut ends of the mesh two and half turns around the selvedge wire or by other approved method, provided that the force of not less than 8.5 kN applied in the same plane as the mesh, at a point on the selvedge of a mesh sample one metre long, is required to separate it from the mesh.

1.6 DIAPHRAGMS AND END PANELS

The rear/side panels shall be selvedged on the top, bottom and vertical sides as described in clause1.6. The diaphragms shall be selvedged and on the top and vertical sides.

The rear and side panels of the box gabion section of the

Terramesh unit shall be formed by a continuous panel connected to the main panel, along the bottom of the rear panel, either by a spiral wire through the mesh openings or by being mechanically placed with four connecting rings.

1.7 LACING AND BRACING WIRE

Sufficient lacing and bracing wire must be supplied with the gabion

cages to perform all the wiring operations to be carried out in the construction of the Terramesh work.

Page 66: 2

76 | P a g e

The lacing and bracing wire shall be made from Heavily Galvanized

Wire, coated with PVC and have a core diameter of 2.20 mm.

1.8 UNIT SIZES

Terramesh shall be mechanically pre-fabricated in such a manner that the sides, ends and diaphragms can be assembled at the construction site into rectangular baskets of the standard sizes indicated below or as specified and shown in the contract drawings.

Mesh type 80mm Width (W) 2m

Length (L1) 1m Length (L2) To suit design Depth (D) 0.5m and 1m Diaphragm Every 1m

All Terramesh dimensions shall be within a tolerance limit of 5% of the required size.

Terramesh shall be mechanically pre-fabricated in such a manner that the

sides, ends and diaphragms can be assembled at the construction site into rectangular baskets of the standard sizes indicated below or as specified and shown in the contract drawings.

Mesh type 80mm Width (W) 2m Length (L1) 1m Length (L2) To suit design Depth (D) 0.5m and 1m Diaphragm Every 1m

All Terramesh dimensions shall be within a tolerance limit of 5% of the

required size.

1.9 STONE FILL FOR FACING BOX

The material used for Terramesh facing box fill shall be clean, dense hard

and durable stone, rounded and angular shape.

No rock shall exceed 250mm and at least 85% by weight of the stone shall have a size equal to or larger than 100mm. No rock shall pass through the mesh.

Page 67: 2

77 | P a g e

1.10 STRUCTURAL EMBANKMENT

The embankment forming the reinforced soil structure should be

constructed with material having the soil properties as specified in the design and approved by the Engineer.

Ideally, the backfill shall be granular, free draining and have the following

specification, unless otherwise approved by the Engineer : not more than 15% by mass of total material to be finer than 75 micron

sieve opening. at least 90% by mass of total material to be finer than the 100 mm sieve

opening maximum particle size to be limited to 125 mm.

The soil should not exhibit any deterioration in these characteristics with time

2.0 CONSTRUCTION METHODOLOGY FOR TERRAMESH SYSTEM UNIT REINFORCED WALLS

2.1 SCOPE

This part of the specification details the requirements from the assembly

stage through to the final wiring of the completed Terramesh units.

The contractor shall provide to the Engineer, for his approval, full details and specifications of the Terramesh he proposes to use in this contract. Only those products so approved by the Engineer shall be allowed to be incorporated in the works.

2.2 PREPARATION

The site shall be surveyed, cleared, trimmed level and the ground compacted

accordingly.

Prior to assembly, the Terramesh units shall be opened out flat on the ground and stretched to remove all kinks and bends.

The Terramesh units shall be assembled individually by raising the front panel (with lid), the hinged rear panel, and the two ends vertical ensuring that all creases are in the correct position and that tops of all four sides are even. The diaphragm panel should be located in a vertical plane centrally within the facing box.

Page 68: 2

78 | P a g e

The four corner edges of the facing box shall be laced first followed by the

edges of the internal diaphragm to the sides.

In all cases, lacing shall commence by twisting the end of the lacing wire

tightly around the selvedge/s. It shall then pass round the two edges being joined using alternate single and double loops at 100mm intervals and be securely tied off at the bottom. The ends of all lacing wires shall be turned to the inside of the box on completion of each lacing operation. Each loop shall be pulled tight to prevent the joint opening during filling.

3.1 ERECTION

Only assembled boxes, or groups of boxes, shall be positioned in the

structure. The side, or end, from which work is to proceed, shall be secured either to the completed work, or by rods or stakes driven into the ground at the corner. These stakes must be secure and be high enough to reach at least to the top of the gabion box.

Further gabion boxes shall be positioned in the structure as required, each

being securely laced to the preceding one along all common corners and diaphragms using the lacing technique described above.

Adjacent panels shall be laced longitudinally to provide a homogeneous

reinforcement layer. All lacing wire shall be PVC coated. 3.2 GEOTEXTILE

Non-woven geotextile, as specified in the contract drawings and approved by

the Engineer, shall be placed vertically at the back of each gabion box section of the Terramesh units, and extend backwards into the fill at least 0.5m parallel to the mesh of homogeonous lower panel and also 0.5m below the panel directly above the unit, to prevent migration of fines.

3.3 STRETCHING

Final stretching of the gabion boxes shall be carried out using a pull-lift of at least one tonne capacity, firmly secured to the free end of the assembled gabion boxes.

Whilst under tension, the gabion box section of the Terramesh units shall be securely laced along all edges (top, bottom and sides) and at diaphragm points, to all adjacent boxes.

Page 69: 2

79 | P a g e

3.4 FILLING

Filling shall be carried out whilst gabion boxes are under tension.

The front face and all other faces which will be exposed in the completed

structure shall be “hand packed” with the stones placed so as to produce a neat face free from excessive bulges, depressions

and voids.

Internal bracing wires shall be provided on the exposed faces at the rate of 4/cu.m at 330mm centres to prevent distortion of the units during filling and in the completed structure. These bracing wires shall be wrapped around two of the mesh wires and extend from front to back. Additional bracing wires shall be provided on exposed ends at a rate of 4/sq.m of face.

Mechanical filling equipment may be used with the approval of the Engineer, providing adequate precautions are taken to protect the PVC coating from abrasion during filling operations.

Tension on the gabion boxes shall be released only when fully laced and

sufficiently full to prevent the mesh from slackening. All gabions shall be overfilled by 25mm using flat stone to allow for minor

settlement and to provide a level surface for subsequent layers.

3.5 STRUCTURAL EMBANKMENT MATERIAL Select backfill shall be placed between each subsequent mesh panel layer to

the full extent of the mesh reinforcement at each level.

3.6 COMPACTION OF BACKFILL

The select backfill shall be compacted in lifts not exceeding 250-300 mm to 90% of maximum density as determined by Test or specified by the engineer.

Care shall be taken to ensure heavy compaction equipment does not come

into contact with the mesh panels or within 1.0 m of the front face. Tracked construction equipment shall not be operated directly upon the mesh reinforcement. A minimum fill thickness of 150mm is required prior to operation of tracked vehicles over the mesh.

During construction, the surface of fill should be kept horizontal. A slight

sloping surface shall be maintained to facilitate drainage of surface water run-off.

Page 70: 2

80 | P a g e

Compaction adjacent to the front edge should be done using hand operated rollers or plate compactors.

3.7 MERITS OF THE TERRAMESH SYSTEM:

Permeability of the front face, guaranteeing drainage of the backfill. Flexibility ,enabling the structure to tolerate differential ground settlement

without compromising structural integrity Ease of construction Significant soundproofing characteristics (18-28 decibels) The reduction of environmental impact through the use of vegetation

incorporated into the front face of the structure The Versatility of gabions, which allows the formation of a structure with

vertical, battered or stepped front face as required and minimization of environmental impact.

3.8 DEMERITS OF THE TERRAMESH SYSTEM: Maintenance

For very tall gabion stacks, any damage to the lower areas requires the removal of the upper wall elevations, which can be costly and time-consuming.

Wall Assembly and Cost Although gabion walls offer a good economic choice for most applications,

they remain more expensive to install. Gabion walls require heavy equipment to construct, since mechanical lifting is required to set heavy walls sections in place.

Endurance In instances of high velocity streams and wave interaction, gabion wall wire

mesh baskets can abrade and tear open, spilling the rock fill.

Page 71: 2

81 | P a g e

3.0 ESTIMATE

Cost estimate per running meter for proposed bank protection work by

construction of Gabbion Retaining Wall With Teramesh System.

The Rates for the proposed work are taken from following SOR.

1) SOR of Ahmedabad Irrigation Department of year 2012-2013 2) SOR of Narmada Water Resources water supply and Kalpsar Department 2012- 2013 for South Gujarat

Page 72: 2

82 | P a g e

SR NO 

DESCRIPTION NOS 

LENGTH

BREATH 

DEPTH 

UNIT  TOTAL 

1

Stripping the Canal Construction width and Borrow area in all sorts

of soil soft murrum including depositing the materials as and

where directed for inspection road etc with lead up to 1 KM and all lifts etc comp . SOR Ahmedabad Irrigation Department 2012-2013

Chapter No 1 Sr No 3

1 1 53.7 0.3 Cum 16.11

Trimming of slope in 3.5H:1V H=12m

Therefore L=12*3.5 =42 m Slope length =(42^2+12^2)^0.5 Slope length= 43.7 +10 =53.7 m

2

Earthwork in embankment from Borrow Pits in all sorts of soil and Soft murrum or other suitable

Strata as directed including breaking the clods and dressing to

the design sections including cutting the proud section with lead as under and all lift including site

clearing etc complete . SOR Ahmedabad Irrigation Department 2012-2013 Chapter No 1 Sr No 3.

1

For Lead 200 to 1000 Mt. 1 5 7 Cum 35 1 5 14 Cum 70 1 32 14 Cum 448 0.5 3.6 1.8 Cum 3.24

DEDUCTION 0.5 42 12 Cum 252

TOTAL 304.2

4

3

Compaction of Earth work in Embankment in layers of 15 cms to 23 cms thick at requisite moisture content to required dry density including necessary watering and rolling with roller of suitable type. SOR Ahmedabad Irrigation Department 2012-2013 Chapter 5 Sr no 10

1 Cum 304.2

4

Page 73: 2

83 | P a g e

4

Proving And Laying Geo Fabric Filter (Gwf-50-300 Category ) Over The Excavated Surface As Per Specification Including stitching With Overlap To Design Profile As Directed In Tidal Range Etc Complete.

1 1 1 14 SQM 14

5

Hexagonal Zn Pvc Coated Box Wire Mesh Gabions Size 4mx1m X1m Filled With 30 To 50 Kg. Trap Rubble Stone (Approximate 4.5) Tone With Mesh Size 10x12cm Including Packing Interlocking Of Stones And Fusing Top Of Gabion And Tying To Each Other & Laying To The Required Line Level Slope With All Leads & Lifts As Directed Etc. Comp In River Side Slope SOR Narmada Water Resources Water Supply And Kalpsar Department 2012-2013 For South Gujarat Region Chapter 6 Sr No 14

14 1 4 1 No 14

6

Providing and laying (Paralink 200) 200 KN/m High Strength uniaxial Geogrid with low creep characteristics, Geogrid consisting of PET and having an outer protective coating of low density polyethylene sheath conforming to detailed specifications and drawings.

14 1 6.75 1 Sqm 94.5

At Cut off 1 1 10 1 Sqm 10

TOTAL Sqm 104.5

7

Excavation in all sorts of soil with yellow ,sandy gravelly soil including sorting and stacking and depositing the excavated stuff in inform layers as and where directed up to lead of 30 mt and lift as shown below including clearing the site etc complete.(including dewatering ).SOR Ahmedabad Irrigation Department 2012-2013 Chapter 5 Sr no 1

0 to 3 m Depth 1 1 0.6 3 Cum 1.8 3 to 6.5 m Depth 1 1 0.6 3.5 Cum 2.1

Page 74: 2

84 | P a g e

8

Providing and laying plain /Reinforced ordinary Portland cement concrete of M 25Grade in Cut off wall with cement sand and coarse aggregates including centering shuttering batching missing transportation placing vibrating smooth finishing curing etc complete for all leads and lift SOR Narmada Water Resources Water Supply and Kalpsar Department 2012-2013 for South Gujarat Region Chapter 4 Sr no 10

1 1 0.6 6 Cum 3.6

9

Providing and laying HYSD Steel bar reinforcement for R.C.C Works and anchor bars with providing binding wires including cutting ,bending, welding, binding in position hooking, placing in position with all leads and lift etc. SOR Ahmedabad Irrigation Department 2012-2013 Chapter 3 Sr no 7

1 80 Kg/m3 Kg 288

10

Providing and laying plain /Reinforced ordinary Portland cement concrete of M 20 Grade in Anchor slab l with cement sand and coarse aggregates including centering shuttering batching missing transportation placing vibrating smooth finishing curing etc complete for all leads and lift SOR Narmada Water Resources Water Supply and Kalpsar Department 2012-2013 for South Gujarat Region Chapter 10 Sr no 10 B

1 1 5 0.2 Cum 1

11

Providing and laying HYSD Steel bar reinforcement for R.C.C Works and anchor bars with providing binding wires including cutting ,bending, welding, binding in position hooking, placing in position with all leads and lift etc. SOR Ahmedabad Irrigation Department 2012-2013 Chapter 3 Sr no 7

1 25 kg/m3 Kg 25

Page 75: 2

85 | P a g e

SR NO 

DESCRIPTION  UNITQUANTIT

YRATE  TOTAL 

1

Stripping the Canal Construction width and Borrow area in all sorts of soil soft murrum including depositing the materials as and where directed for inspection road etc with lead upto 1 KM and all lifts etc comp . SOR Ahmedabad Irrigation Department 2012-2013 Chapter No 1 Sr No 3

Cum

16.11 30.5 491.36

2

Earthwork in embankment from Borrow Pits in all sorts of soil and Soft murrum or other suitable Strata as directed including breaking the clods and dressing to the design sections including cutting the proud section with lead as under and all lift including site clearing etc complete . SOR Ahmedabad Irrigation Department 2012-2013 Chapter No 1 Sr No 3.

For Lead 200 to 1000 Mt.

TOTAL Cum

304.24 61 18558.64

3

Compaction of Earth work in Embankment in layers of 15 cms to 23 cms thick at requisite moisture content to required dry density including necessary watering and rolling with roller of suitable type. SOR Ahmedabad Irrigation Department 2012-2013 Chapter 5 Sr no 10

Cum

304.24 16 4867.84

4

Proving and Laying Geo Fabric Filter (Gwf-50-300 Category ) Over The Excavated Surface As Per Specification Including Stitching With Overlap To Design Profile As Directed In Tidal Range etc Complete.

SQM 14 78.9 1104.6

5

Hexagonal Zn Pvc Coated Box Wire Mesh Gabions Size 4mx1m X1m Filled With 30 To 50 Kg. Trap Rubble Stone (Approximate 4.5) Tone With Mesh Size 10x12cm Including Packing Interlocking Of Stones And Fusing Top Of Gabion And Tying To Each Other & Laying To The Required Line Level Slope With All Leads & Lifts As Directed

No 14 2300 32200

Page 76: 2

86 | P a g e

Etc. Comp In River Side Slope Sor Narmada Water Resources Water Supply And Kalpsar Department 2012-2013 For South Gujarat Region Chapter 6 Sr No 14

6

Providing and laying (Paralink 200) 200 KN/m High Strength uniaxial Geogrid with low creep characteristics, Geogrid consisting of PET and having an outer protective coating of low density polyethylene sheath conforming to detailed specifications and drawings. (Market Rate)

TOTAL Sqm 104.5 220 22990

7

Excavation in all sorts of soil with yellow ,sandy gravelly soil including sorting and stacking and depositing the excavated stuff in inform layers as and where directed up to lead of 30 mt and lift as shown below including clearing the site etc complete.(including dewatering ).SOR Ahmedabad Irrigation Department 2012-2013 Chapter 5 Sr no 1

Cum

0 to 3 m Depth 1.8 54 97.2 3 to 6.5 m Depth 2.1 56 117.6

8

Providing and laying plain /Reinforced ordinary Portland cement concrete of M 25 Grade in Cut off wall with cement sand and coarse aggregates including centering shuttering batching missing transportation placing vibrating smooth finishing curing etc complete for all leads and lift SOR Narmada Water Resources Water Supply and Kalpsar Department 2012-2013 for South Gujarat Region Chapter 10 Sr no 10 C

Cum

3.6 4639.

4 16701.84

9

Providing and laying HYSD Steel bar reinforcement for R.C.C Works and anchor bars with providing binding wires including cutting ,bending, welding, binding in position hooking, placing in position with all leads and lift etc. SOR Ahmedabad Irrigation Department 2012-2013 Chapter 3 Sr no 7

Kg 288 53.86 15511.68

Page 77: 2

87 | P a g e

10

Providing and laying plain /Reinforced ordinary Portland cement concrete of M 20 Grade in Anchor slab l with cement sand and coarse aggregates including centering shuttering batching missing transportation placing vibrating smooth finishing curing etc complete for all leads and lift SOR Narmada Water Resources Water Supply and Kalpsar Department 2012-2013 for South Gujarat Region Chapter 10 Sr no 10 B

Cum

1 4507.

1 4507.1

11

Providing and laying HYSD Steel bar reinforcement for R.C.C Works and anchor bars with providing binding wires including cutting ,bending, welding, binding in position hooking, placing in position with all leads and lift etc. SOR Ahmedabad Irrigation Department 2012-2013 Chapter 3 Sr no 7

Kg 25 53.86 1346.5

TOTAL RS PER RUNNING METER  118494.36 

Page 78: 2

The bank oland at top o

To eliminatFort wall is

Diaphragmsfoundation

These typesto the banks

FIGURE18SEC

of the rivers of the banks

te the erosioadopted to s

s walls / Shbelow scour

s of structures for a longer

CTIONSHOWING

is eroded duand shifting

on of the bansupport earth

heet Piles arr depth.

es though arer period com

GPROTECTIONW

uring strong of banks.

nks, the consh or loose stra

re constructe

e expensive gmpared to oth

WORKCONSISTO

current of fl

struction of Rata, which w

ed right fro

gives much bher type of str

OFDIAPHRAGMW

lood, resultin

R.C.C Retaiwould not be

m the toe o

better and foructures.

WALL/SHEETP

88 | P

ng into the l

ning wall/Costable.

of the banks

oolproof prot

PILEANDRETAIN

a g e

loss of

ounter

s with

tection

NWALL

Page 79: 2

FIGURE

19OVERVIEW

WOFRIVERSAABARMATIAFTGIFTCITY

TERCONSITRUUCTIONOFPRO

89 | P

OTECTIONWOR

a g e

RKAT

Page 80: 2

90 | P a g e

1.0 GENERAL

Diaphragm walling is a technique of constructing a continuous

underground wall from the ground level. Diaphragm walls provide

structural support and water tightness. These reinforced concrete

diaphragm walls are also called Slurry trench walls due to the reference

given to the construction technique where excavation is made possible

by filling and keeping the wall cavity full with bentonite-water mixture

during excavation to prevent collapse of vertical excavated surfaces.

These retaining structures find following applications: earth retention

walls for deep excavations; basements, and tunnels; High capacity

vertical foundation elements; Retaining wall foundations; water control.

Typical wall thickness varies between 0.6 to 1.1m. The wall is

constructed panel by panel in full depth. Panel width varies from 2.5m

to about 6m. Short widths of 2.5m are selected in less stable soils,

under very high surcharge or for very deep walls. Different panel shapes

other than the conventional straight section like T, L are possible to

form and used for special purposes. Traditionally, panel excavation is

carried out using cable supported Grab. Hydraulic grabs with Kelley

arrangement have recently been introduced in India on large

Infrastructural projects. More recently developed hydraulic cutter type

machines are not being used in India hence have not been discussed

here.

Page 81: 2

91 | P a g e

Slurry wall technique is a specialized technique and apart from the

crane mounted Grab, other equipment involved are cranes, pumps,

tanks, de- sanding equipment, air lifts, mixers etc.

Steps involved in the construction of diaphragm wall can be broadly listed as follows:

• Guide wall construction along alignment

• Trenching by crane operated Grab/ hydraulic grab

• Bentonite flushing

• Lowering reinforcement cage

It must be remembered that Diaphragm walls are constructed as a

series of alternating primary and secondary panels. Alternate primary panels are constructed first which are restrained on either side by stop-end pipes. Before the intermediate secondary panel excavation is taken up, the pipes are removed and the panel is cast against two primary panels on either side to maintain continuity. Water stoppers are sometimes used in the construction joints between adjacent panels to prevent seepage of ground water.

1.1 DESIGN PHILOSOPHY

Diaphragm walls are commonly designed as flexible retaining walls.

Such retaining systems are considered to be vertical cantilever

designed to resist lateral earth and ground water pressures, and to

rotate about some point b below the dredge level). The flexibility

leads to development of passive pressure at the toe in the backfill

side of the wall. Blum’s simplification replaces the passive pressure

behind the retaining wall with a force applied to the wall at some

height above the toe . The necessary depth of penetration is found by

taking moments about the replacement force position, C. Moment

equilibrium gives the required depth of penetration, provided that

the net pressure diagram is calculated including the effects of

groundwater. The computed may be increased by 20 to 40% beyond

the point required by equilibrium (Teng, 1962); or the effective

horizontal pressure on the passive side may be reduced by applying

a factor of safety of 1.5 to 2.1 before the embedment depth of pile is

computed. Unit length of diaphragm wall is considered for

determining its reinforcement requirements, whilst for contiguous

piles, the c/c spacing is used for estimating reinforcement quantity.

Page 82: 2

92 | P a g e

NE T P A S S I V E (P p- Pa)

A. C A N T I L EVE R SH E E T - P I L E W A L L D E SI G N PR I N C I PL E S

a

ACT I V E

NE T P A S S I V E

(P p- Pa)

( a ) ASSU M E D M O D E O F W A L L M O VE M E N T ( b ) I D EA L I Z E D P R ESSU R E D I STR I BU T I O N

A DESIGN PRINCIPLES OF DIAPHRAGM WALL SYSTEM 1.2 MERITS AND DEMERITS

Diaphragm wall construction is relatively quiet, and minimum

noise and vibration levels make it suitable for construction in

urban areas. The water tight walls formed can be used as

permanent structural walls and are most economical when

used in this manner. The finished structural wall formed prior

to excavation allows subsequent construction of the basement

in a water tight and clean environment. Once the diaphragm

walls are constructed, work can be planned to proceed

simultaneously above and below the ground level. There is a

minimum of space wasted. Work may be carried out right

against existing structures and the line of wall may be

adjusted to any shape in plan.

Page 83: 2

1.0 GENER

RAL

CouproThefor betcancouheecounot20.

B. D E

unterfort ojecting ue thicknes cantilevetween the ntileveredunterfortsel where munterfortst practica

FIG

E S I G N A S S U M

cantilevepward fross of the sered walls counterfo elements

s are tapermoments s and the l for walls

GURE 20 COUN

P TI O N F O R C A

red retainom the hestem betw) and spaort (wing)s and are red down are higheinfill stems less tha

NTERFORT RE

A N T I L E V ER S H

ning wallsel of the

ween counans horizo walls. Th structura to a wide

er. The higm walls man about 1

ETAINING WA

H EET- P I L E W A

s incorpor footing innterforts iontally, ashe counteally efficieer (deepergh cost of

make such16 feet hig

LL 

L L S

rate wing nto the stis thinners a beam,erforts actent becaur) base at f forming

h walls usugh. See Fi

93 | P a g e

walls em.

r (than t as se the the the ually igure

Page 84: 2

94 | P a g e

2.0 PROPORTIONING

The spacing between counterforts for economical design is usually

one-half to two-thirds the wall height. The width of the footing will usually be about two-thirds the wall height, or larger for surcharges or sloped backfill

3.0 DESIGN OVERVIEW

As per preliminary design following sections for counter Fort wall is adopted.

Top thickness of stem = 0.20m

Base thickness of stem = 0.75m

Width of Toe slab =2.00m

Width of Heel slab = 3.75m

Thickness of Slab = 0.75 m

Spacing of counterfort= 4.0 m c/c

Thickness of counterfort= 0.60m

Height of wall from the foundation =10.0m

Grade of Concrete = M25

Grade of steel= Fe-500 TMT/HYSD bar

The design of a counterfort wall can be somewhat complex because the number of components which must be designed differently than for a conventional cantilevered wall. The steps in the design of a reinforced concrete counterfort wall are as follows (each step will be discussed later):

a) After establishing the retained height, select a spacing for the counterforts,

usually one-half to two-thirds of the retained height. Determine the footing width required and soil bearing at both the toe and heel because you will need these dimensions to establish the counterfort dimensions, and for stability calculations design as if the wall is a continuous cantilevered wall. You can add an estimated weight of the counterforts prorated as a uniform longitudinal axial load.

b) Design the wall as described in the following section as a two-way slab, fixed at the base and at the counterfort crossings and free at the top.

c) Design the footing toe as a cantilever from the wall. d) Design the heel as a longitudinal beam spanning between counterforts. e) Design the counterfort. It will be a tapered trapezoidal shaped tension

member.

Check the final design for stability, overturning, sliding, and soil pressures

Page 85: 2

95 | P a g e

4.0 ESTIMATE

Cost Estimate Per Running Meter For By Construction Of Rigid RCC Counter Fort Wall With Diaphragm Wall Construction.

The Rates for the proposed work are taken from following SOR.

1) SOR of Ahmedabad Irrigation Department of year 2012-2013

2) SOR of Narmada Water Resources water supply and Kalpsar

Department 2012-2013 for South Gujarat

Page 86: 2

96 | P a g e

SR NO 

DESCRIPTION   NOLENGTH 

BREATH DEPTH  UNIT  TOTAL 

1

Stripping the Canal Construction width and Borrow area in all sorts of soil soft murrum including depositing the materials as and where directed for inspection road etc with lead upto 1 KM and all lifts etc comp . SOR Ahmedabad Irrigation Department 2012-2013 Chapter No 1 Sr No 3

1 1 53.7 0.3 Cum 16.11

Trimming of slope in 3.5H:1V H=12m Therefore L=12*3.5 =42 m Slope length =(42^2+12^2)^0.5 Slope length= 43.7 +10 =53.7 m

2

Earthwork in embankment from Borrow Pits in all sorts of soil and Soft murrum or other suitable Strata as directed including breaking the clods and dressing to the design sections including cutting the proud section with lead as under and all lift including site clearing etc complete . SOR Ahmedabad Irrigation Department 2012-2013 Chapter No 1 Sr No 3.

1 1 10.75 4 Cum 43 1 1 31.25 13.8 Cum 431.25 DEDUCTION 1 0.5 42 12 Cum 252 TOTAL Cum 222.25

3

Compaction of Earth work in Embankment in layers of 15 cms to 23 cms thick at requisite moisture content to required dry density including necessary watering and rolling with roller of suitable type. SOR Ahmedabad Irrigation Department 2012-2013 Chapter 5 Sr no 10

1 Cum 222.25

Page 87: 2

97 | P a g e

4

Excavation in all sorts of soil with yellow ,sandy gravelly soil including sorting and stacking and depositing the excavated stuff in inform layers as and where directed upto lead of 30 mt and lift as shown below including clearing the site etc complete.(including dewatering ).SOR Ahmedabad Irrigation Department 2012-2013 Chapter 5 Sr no 1

0 to 3 m Depth 1 1 0.6 3 Cum 1.8 3 to 6m Depth 1 1 0.6 3 Cum 1.8

5

Providing and laying plain /Reinforced ordinary Portland cement concrete of M 25Grade in Cut off wall with cement sand and coarse aggregates including centering shuttering batching mixing transportation placing vibrating smooth finishing curing etc complete for all leads and lift SOR Narmada Water Resources Water Supply and Kalpsar Department 2012-2013 for South Gujarat Region Chapter 4 Sr no 10

                 

Below River Bed 1 1 0.6 6  Cum  3.6

Above River Bed 1 1 0.6 4  Cum  2.4

TOTAL Cum  6

6

Providing and laying HYSD Steel bar reinforcement for R.C.C Works and anchor bars with providing binding wires including cutting ,bending, welding, binding in position hooking, placing in position with all leads and lift etc. SOR Ahmedabad Irrigation Department 2012-2013 Chapter 3 Sr no 7

1  80 kg/m3  Kg  480 

7

Providing and laying plain /Reinforced ordinary Portland cement concrete of M 20 Grade in Anchor slab l with cement sand and coarse aggregates including centering shuttering batching mixing transportation placing vibrating smooth finishing curing etc complete for all leads and lift SOR Narmada Water Resources Water Supply and Kalpsar Department 2012-2013 for South Gujarat Region Chapter 10 Sr no 10 B

1  1  8  0.2  Cum  1.6 

Page 88: 2

98 | P a g e

8

Providing and laying HYSD Steel bar reinforcement for R.C.C Works and anchor bars with providing binding wires including cutting ,bending, welding, binding in position hooking, placing in position with all leads and lift etc. SOR Ahmedabad Irrigation Department 2012-2013 Chapter 3 Sr no 7

1  25 kg/m3  Kg  40 

For Anchor Slab

9

Providing and laying plain /Reinforced ordinary Portland cement concrete of P.C.C M 15 Grade below Anchor slab with cement sand and coarse aggregates including centering shuttering batching mixing transportation placing vibrating smooth finishing curing etc complete for all leads and lift SOR Narmada Water Resources Water Supply and Kalpsar Department 2012-2013 for South Gujarat Region Chapter 10 Sr no 10 B

1 1  8  0.15  Cum  1.2 

COUNTER FORT RETAINING WALL

10 

Providing and laying plain /Reinforced ordinary Portland cement concrete of M 25 Grade in Bottom slab of Counter Fort Wall with cement sand and coarse aggregates including centering shuttering batching mixing transportation placing vibrating smooth finishing curing etc complete for all leads and lift SOR Narmada Water Resources Water Supply and Kalpsar Department 2012-2013 for South Gujarat Region Chapter 10 Sr no 10 C

1 1 6.5 0.75 Cum 4.87

5

11 

Providing and laying plain /Reinforced ordinary Portland cement concrete of M 25 Grade in Stem of Counter Fort Wall with cement sand and coarse aggregates including centering shuttering batching mixing transportation placing vibrating smooth finishing curing etc complete for all leads and lift SOR Narmada Water Resources Water Supply and Kalpsar Department 2012-2013 for

1 1 10 0.475 Cum 4.75

Page 89: 2

99 | P a g e

South Gujarat Region Chapter 10 Sr no 10 C

12 

Providing and laying plain /Reinforced ordinary Portland cement concrete of M 25 Grade in Counter Fort Placed at 4 m c/c with cement sand and coarse aggregates including centering shuttering batching mixing transportation placing vibrating smooth finishing curing etc complete for all leads and lift SOR Narmada Water Resources Water Supply and Kalpsar Department 2012-2013 for South Gujarat Region Chapter 10 Sr no 10 C

1 10 2.025 0.6 Cum 3.04

13 

Providing and laying HYSD Steel bar reinforcement for R.C.C Works and anchor bars with providing binding wires including cutting ,bending, welding, binding in position hooking, placing in position with all leads and lift etc. SOR Ahmedabad Irrigation Department 2012-2013 Chapter 3 Sr no 7

80 Kg/m3 Kg 1013

.2

For Counter Fort Retaining wall 

Page 90: 2

100 | P a g e

SR NO  DESCRIPTION   NOS  UNIT  QUANTITY  RATE  TOTAL 

Stripping the Canal Construction width and Borrow  area in all sorts of soil  soft murrum including depositing the materials as and where directed for inspection road etc with lead up to 1 KM and all lifts etc comp . SOR Ahmedabad Irrigation Department 2012‐2013  Chapter No 1 Sr No 3  

1  Cum  16.11  30.5  491.36 

Earthwork in embankment from Borrow Pits in all sorts of  soil and Soft murrum  or other  suitable Strata as directed including breaking the clods and dressing to the design sections including cutting the proud section with lead as under and all lift including site clearing etc complete . SOR Ahmedabad Irrigation Department 2012‐2013  Chapter No 1 Sr No 3. 

        

    

TOTAL  1  Cum  222.25 61 

13557.25 

Compaction of Earth work in Embankment in layers of 15 cms to 23 cms thick at requisite moisture content to required dry density including necessary watering and rolling with roller of suitable type. SOR Ahmedabad Irrigation Department 2012‐2013  Chapter 5 Sr no 10 

1  Cum  222.25  16  3556 

Excavation in all sorts of soil  with yellow ,sandy gravelly soil including sorting and stacking and depositing the excavated stuff in uniform layers as and where directed up to lead of 30 mt and lift as shown below including clearing the site etc complete.(including dewatering ).SOR Ahmedabad Irrigation Department 2012‐2013  Chapter 5 Sr no 1 

              

0 to 3 m Depth  1 Cum 1.8 54  97.2

3 to 6m Depth  1 Cum 1.8 56  100.8

Providing and laying plain /Reinforced ordinary Portland cement concrete of M 25Grade in Cut off wall with cement sand and coarse aggregates including centering shuttering batching mixing transportation placing vibrating smooth finishing curing etc complete for all leads and lift SOR Narmada Water Resources Water Supply and Kalpsar Department 2012‐2013 for South Gujarat Region   Chapter 4 Sr no 10 

1  Cum  6  4639.4  27836.4 

Page 91: 2

101 | P a g e

Providing and laying HYSD Steel bar reinforcement  for R.C.C Works and anchor bars with providing binding wires including cutting ,bending, welding, binding in position hooking, placing in position with all leads and lift etc. SOR Ahmedabad Irrigation Department 2012‐2013  Chapter 3 Sr no 7 

1  Kg  480  53.86  25852.8 

Providing and laying plain /Reinforced ordinary Portland cement concrete of M 20 Grade in Anchor slab with cement sand and coarse aggregates including centering shuttering batching mixing transportation placing vibrating smooth finishing curing etc complete for all leads and lift SOR Narmada Water Resources Water Supply and Kalpsar Department 2012‐2013 for South Gujarat Region   Chapter 10 Sr no 10 B 

1  Cum  1.6  4507.1  7211.36 

Providing and laying HYSD Steel bar reinforcement  for R.C.C Works and anchor bars with providing binding wires including cutting ,bending, welding ,binding in position hooking, placing in position with all leads and lift etc. SOR Ahmedabad Irrigation Department 2012‐2013  Chapter 3 Sr no 7 

1  Kg  40  53.86  2154.4 

For Anchor Slab 

Providing and laying plain /Reinforced ordinary Portland cement concrete of P.C.C  M 15 Grade below Anchor slab with cement sand and coarse aggregates including centering shuttering batching mixing transportation placing vibrating smooth finishing curing etc complete for all leads and lift SOR Narmada Water Resources Water Supply and Kalpsar Department 2012‐2013 for South Gujarat Region   Chapter 10 Sr no 10 B 

1  Cum  1.2  3963.9  4756.68 

                            COUNTER FORT RETAINING WALL     

10 

Providing and laying plain /Reinforced ordinary Portland cement concrete of M 25 Grade in Bottom slab of Counter Fort Wall with cement sand and coarse aggregates including centering shuttering batching missing transportation placing vibrating smooth finishing curing etc complete for all leads and lift SOR Narmada Water Resources Water Supply and Kalpsar Department 2012‐2013 for South Gujarat Region   Chapter 10 Sr no 10 C 

1  Cum  4.875  4639.4  22617.08 

Page 92: 2

102 | P a g e

11 

Providing and laying plain /Reinforced ordinary Portland cement concrete of M 25 Grade in Stem of Counter Fort Wall with cement sand and coarse aggregates including centering shuttering batching mixing transportation placing vibrating smooth finishing curing etc complete for all leads and lift SOR Narmada Water Resources Water Supply and Kalpsar Department 2012‐2013 for South Gujarat Region   Chapter 10 Sr no 10 C 

1  Cum  4.75  4639.4  22037.15 

12 

Providing and laying plain /Reinforced ordinary Portland cement concrete of M 25 Grade in  Counter Fort Placed at 4 m c/c with cement sand and coarse aggregates including centering shuttering batching mixing transportation placing vibrating smooth finishing curing etc complete for all leads and lift SOR Narmada Water Resources Water Supply and Kalpsar Department 2012‐2013 for South Gujarat Region   Chapter 10 Sr no 10 C

1  Cum  3.04  4639.4  14103.78 

13 

Providing and laying HYSD Steel bar reinforcement  for R.C.C Works and anchor bars with providing binding wires including cutting ,bending, welding, binding in position hooking, placing in position with all leads and lift etc. SOR Ahmedabad Irrigation Department 2012‐2013  Chapter 3 Sr no 7 

              

For Counter Fort Retaining wall  1  Kg  1013.2  53.86  54570.96 

TOTAL RS PER RUNNING METER  198944 

Page 93: 2

1.1 G

1.2 P

1.2.1

GENERAL

IS objedispopeavoto rwat

Theare somoutas f

Proinsufloo

PLANNIN

Varwordrabelo

1 REQUIR

Forwill

CH

L

code 8835ect of relieposing of serations. Thoid its percrise in the ter logging

e drains m generally

me cases intfall conditforced or d

viding adeufficient isods in the

        

NG OF DRA

rious asperks includains, alignmow.

REMENT O

r the plannl be collecte

HAPTER-3

5:1978 stieving excesurplus wahe proper colation do water tab.

may be natu aligned aln order to tions, the ddiversion re

equate dras the basiarea. A cro

      FIGURE 21

AINAGE IM

ects relatedding data ment of dr

OF DATA

ning of thed.

3DRAINA

ipulates thess water fater whichdisposal o

own to thele thereby

ural or artilong the va reduce thdrains are eaches.

ainage sysc requiremoss draina

 

1: A CROSS DR

MPROVEM

d to planncollection,ain, capac

he drainage

AGE IMP

hat drainsfrom agric

h is not reqof surplus re water lev aggravatin

ificial. As palley lines

he length o taken acr

tem wherement to leage work is

RAINAGE WO

MENT WO

ning of dra degree o

city of drain

e/channel

ROVEME

s are conscultural anquired for nrain water

vel which mng or crea

per accepte between r

of the drainross valleys

e natural ssen the d

s shown in

ORK 

ORKSainage/chaf protections etc. are

l improvem

1

NT WORK

structed wnd other anormal agrr is also esmay otherwting the pr

ed principlridges. Hon or to havs. These ar

drainage sdistress ca Figure 21

annel impon, classifie described

ment follow

03 | P a g e

KS

with the areas and ricultural sential to wise lead roblem of

les, these owever, in ve proper re known

system is aused by .

provement fication of d in paras

wing data

Page 94: 2

1.

1.

1

1.3

.2.1.1 TOP

Planarea

.2.1.2 HYD

Discsect

.2.2 DEG

IS dayrequmaybe jdescros

       

CLASSIF

IS Cintoare

(a) Outfriver

(b) Link

POGRAPHI

n showinga, plan and

DROLOGICA

charge, gtion of rive

GREEOFP

Code 883y rainfall uiring highy also be ajustified inigned for ss drain un

                    FI

FICATION

Code 8835o the follow construct

fall drainsr from a pak Drains- T

ICALDATA

g area afd section o

ALANDM

gauge, flower etc.

PROTECTI

5:1978 stof 5 yearher degreeadopted. An term of 3 day rainnder the e

GURE 22: CRO

N OF DRAI

5:1978 stiwing categed:

- These ararticular cThese are b

A

ffected, baof earlier ex

ETEOROL

w depth,

ION

tipulates tr return e of protecAdoption off economicnfall of 50mbankme

OSS DRAIN UN

NS

ipulates thgories acco

re the maincatchment.branch dra

ank slopexecuted wo

OGICALDA

velocity,

that drainperiod. H

ction, retuf higher recs. Cross 0 year retunt is show

NDER THE EM

hat the drording to th

n drains ou. ains draini

e, type of orks.

ATA

cross se

ns may beHowever, irn period eturn periodrainage w

urn periodwn in Figur

MBANKMENT

rains are bhe purpos

ut falling in

ing sub-ca

104

f soil, catc

ctions an

e designedn specificof 10 or 1

od rainfall works sho. Construcre 22.

broadly clae for which

nto a nalla

atchment i

4 | P a g e

chment

nd long

d for 3 c cases 15 year should ould be ction of

assified h these

ah or a

nto the

Page 95: 2

1.4 A

outf

 

ALIGNMEN

IS alig

Thevalloutdramafrompertakcondep

In far In emordin t

As thaslu

fall drain. T

                        

NTOFDRA

code 85gnment of

e drains sley line. Atfall draiained. If arshes, thm the drformanceke the drannect it tpression.

selecting as possithe forcebankmen

der to minthe emban

far as poat the fulluice with g

These are a

               FIGU

AINS

535:1978 f the drain

should geAs far asin shouldthe align

he drain difficultiese of the ain away to the dra

alignmenible theseed reachents of thenimize thenkments.

ossible, thl supply gates

aligned alo

URE 23: EMBA

envisagenage chan

enerally fs possibld be in nment crshould n in excadrain. Infrom the ain if it i

nts, care e do not s, care se drains e danger o

he alignmlevel is b

ong subsid

ANKMENT WIT

es follownnel.

follow thee the alithe cen

osses anynot pass avation, in such ca depressiois require

should bpass thr

should beare not o

of flooding

ment of thbelow the

diary valley

TH SLUICE 

wing guid

e drainageignment otre of thy depressthrough it affectsases, it ion or poned to dra

be taken rough ville taken tof an exceg in the ev

he drain s natural

105

y lines.

delines fo

e line ie. of the mhe area sions, ponthese, as the hydis preferand, and suain the po

to see tlage habito see thessive hevent of br

should besurface le

5 | P a g e

or the

lowest main or

to be nds or

s apart draulic able to uitably ond or

hat as itation.

hat the ight in eaches

e such evel. A

Page 96: 2

1.5 Capaci IS

cap

Nordisccasas Whporexcprounrcharetutheareacceveprominprosur

ty/desigcode 8

pacity/des

rmally thcharge w

ses, no emto allow

herever emrtion of cavated sovided in restricted annel capurn to the forced o, howeve

commodatn in suc

oper alignmnimum. Iovided in rrounding

FIGURE 24

gndischa8535:197sign disch

he drain where drambankmenw free flowmbankme

the desoil will

the emb inflows,

pacity, the channelor diversioer, providted withinch cases ment to kIn such c the em

g areas. A

4: A GATED S

 

argeofdr8 envis

harge of th

is providains follownts shoulw of watnts are nesign dibe very

bankmentand in ca

he water l freely whon reachded as tn the cuattempts

keep the hcases, inmbankme typical dr

LUICE 

rains. ages folhe drainag

ded to aw naturald be prover from tnecessaryscharge

y costly, ts on eithase of disshould s

hen the dhes, emba

he desigt section should height of lets of a

ents to rain is sh

llowing ge channe

ccommodal valley vided alonthe surro

y for accor wherlarge ga

her side scharges hspill over

discharge ankmentsgn discha of the dbe made the embadequate admit thown in Fi

106

guidelineel.

date the lines. In

ng the droundings commodare dispoaps shouso as tohigher thr the arein it reced on both

arge canndrain. Ho by selec

ankments size shouhe water gure 25.

6 | P a g e

es for

design n such rain so areas.

ting a sal of uld be o allow han the ea and des. In

h sides not be owever, cting a to the uld be from

Page 97: 2

Icdd

1.5.1

Ib

1.5.2

Intensity ocountry indays. Theduration s

1 DESIGN

In fixing tbe taken i

a) Econoccunevedraiacce

b) Perfto ddiscdraisize discfree

c) Landinvocult

d) Desday yearcaseyearneed

2 PERIOD

The the submsignshou10

of Rainfalndicates terefore, foshould be

NFREQUEN

the designinto accou

nomics- Drurrence prer designedinage projeepted. formance- Tdeterioratecharge freins tend to remain in

charges wit board. d requirem

olve larger ivated landign freque rainfall or frequences requirinr can alsod to be jus

DOFDISPO

period of tolerance mersion f

nificant dauld aim atdays. Ba

FIGURE 2

ll- Analysthat geneor designe taken

NCYOFRA

n capacityunt:

rains of a rove to bed to cater ect, occurr

The experie fast, as quently. o get siltedn a betterth margina

ment- On land acqd.

ency- Geneof 5 year fcy gives opng a highero be adoptified in te

OSAL

f disposal of individufor a periamage. Thet disposingsed on e

25: A TYPICAL 

sis of therally the n of the d

AINFALL

y of the d

bigger size costly cofor the wo

rence of d

ience indic these arConsequend soon. Onr conditional scour of

account oquisition r

erally the frequency.ptimum ber degree ofpted. Adoprms of the

of the excual crops. iod of 7 erefore, ing of the raiexperience

DRAIN 

e storm durationdrains, a

drain the

ze for cateompared torst conditamage at

cates that re not reqntly in cn the othen and canf bed and

of small laesulting in

drains sh. Studies enefit costf protectionption of sue economic

cess rainfaCrops Liketo 10 d

n paddy gin water in the follo

rainfall n of the sa storm r

following

ering a rainto the bentions. In otperiodical

drains of quired to carrying ser hand, Dn occasionsides and

and holdinn a perm

hould be dcarried out ratio. Hon, the frequch highecs

all is entire paddy caays witho

growing arn a periodowing per

10

throughostorm is arainfall of

g factors

nfall of innefits. Drather words intervals

a bigger scarry themaller di

Drains of anally carry encroachm

ngs, biggeranent loss

designed fut indicateowever, in quency of 1er frequenc

rely depenan generalout sufferreas, the d varying fr

riods of d

07 | P a g e

out the about 3 f 3 day

have to

frequent ains are s, in any is to be

size tend e design scharge,

a smaller y higher ment on

r drains s of the

for three e that 5 specific 10 or 15 cies will

ndent on lly stand ing any drainage rom 7 to disposal

Page 98: 2

108 | P a g e

are recommended.

# Crops Period of Disposal (i) Paddy 7 to 10 days(ii) Maize, bajra and other

similar crops 3 days

(iii) Sugarcane and bananas 7days(iv) Cotton 3 days(v) Vegetables 1 day (in case of vegetables, 24 hour rainfall

will have to be drained out in 24 hours)

1.5.3 RUN‐OFF

Run-off coefficients depends on the type of soil, crops, general topographical conditions like land slopes, etc. In plain areas, the run- off percentage is generally of the order of 15 to 20. In semi- hilly areas the percentage may be higher. Until precise data becomes available, the following run-off coefficients for different soils are recommended for plain areas.

# Type of catchment Run-off Coefficient

(i) Loam, lightly cultivated or covered 0.40 (ii) Loam, largely cultivated and suburbs with gardens, lawns,

macadamized roads 0.30

(iii) Sandy soils, light growth 0.20 (iv) Parks, lawns, meadows, gardens, cultivated area 0.05-0.20 (v) Plateaus lightly covered 0.70 (vi) Clayey soils stiff and bare and clayey soils lightly covered 0.55

1.5.4 RUN-OFF FOR COMPOSITE CROPS

In large areas, there are often different types of crops grown. In such cases, the field and link drains can be designed on the basis of the crops grown in a particular area. For the outfall drain, either a composite discharge can be worked out or the total discharge can be worked out by taking into account the discharges from individual link drains. As the area grows larger, the chances of synchronization of discharge from the entire area become less. As such, working out a composite discharge may also serve the purpose. However, individual cases will have to be studied on their own merit. A typical gated sluice for high embankment is shown in Figure 26.

Page 99: 2

1.6

1.7

6 CAPACIT

IS alwathe caushighdrainhighaparirrigmuc

All ta 3dsamshou

DESIGN D

Thesiltifor cha

Velocity oWhere Qworked obed mateHydraulArea of cQ/V We(Q) 1/2 an(3340*Q

IS cthe

FIGU

TY/DESIG

code 853ays designdrains. Th

sed to theher than tn. Besides

her dischart from igation canach dislocat

the cross day rainfal

me dependiuld be take

DISCHARG

e drain shoing/scourithe drain

annel by La

of the flowQ = design dout using erial size inic mean dechannel setted perimnd Bed slo

Q1/6)

code 8535 drainage c

URE 26: A TYP

GNDISCHA

35:1978 sned for a his is maie structurethe designs, any remarges will involving dals, etc. Thion. The p

drainage ll of 50 yeing on theen to see th

GE FOR C

ould be deng is occu

nage channaceys theor

w (V in m/sdischarge the formu

n mm epth (R in ection (A in

meter (P in mpe (S) = (f

5:1978 envchannel.

PICAL GATED S

ARGEFORC

stimulates higher di

inly on aces in the eed rainfal

modeling onot only

dislocationhe drains resent pra

structuresear frequene type of chat afflux

CROSS DRA

signed as urred in tnel may bry. The des

sec) = (Qf2/in cumecs

ula f = 1.7

m) = 2.5* (n m2) = m) = 4.75 5/3) /

visages fol

SLUICE DRAIN

CROSSDRA

that croischarge tccount of event of flol, can be

of the stru be costl

ns to facilcan, howe

actices vary

s should, ncy, time crop. In fiis within t

AINAGE W

per Laceyhe drain s

be done asign proce

/140)1/6

s and, f is 76 (d) 1/2, w

(V2/f)

llowing gu

AINAGEW

oss drainthan the the fact t

ows result much m

uctures at ly but tilities like ever, be remy considera

therefore, of disposa

fixing the he permiss

WORKS

s regime tsection. D

as per desdure is as

the silt facwhere d is

uidelines fo

109

WORKS.

nage workcut sectio

that the ding from rore than a later daime consuroads, raimodeled wably.

be designal remainiwaterwayssible limits

heory so tDesign procsign of irri under.

ctor, whichs the aver

or the des

9 | P a g e

ks are ons of

damage rainfall to the ate for uming, ilways,

without

ned for ng the s, care s

that no cedure igation

h can be rage

sign of

Page 100: 2

110 | P a g e

1.7.1 VELOCITY

The drain section shall be adequate to carry the designed discharge and the velocity shall be non-silting, non-scouring to be determined by Mannings formula.

1.7.2 DISCHARGE CAPACITY OF THE DRAIN

In order to obtain the discharge capacity of a drain it is necessary to know the mean velocity of flow as obtained above which when multiplied by the area of the cross section of the drain in square meters will give the discharge in m3/s.

1.7.3 SIDE SLOPES

In selecting the side slopes for the drain, it will be necessary to consider the kind of material through which the drain is to be excavated. Generally side slopes of 1.5H : 1V are provided.

1.7.4 CROSSSECTIONSOFTHEDRAIN

Although deeper sections of the drain may be desirable, the width to depth ratio should be so selected that the section is both hydraulically efficient as well as economical in excavation. In the case of drains with embankments, the berm width equal to the depth of the drain, subject to a minimum of 1 m should be provided between the toe of the embankment and the section of the drain. The top of the embankments should be 1 m higher than the design full supply level. Wherever, there is likelihood of backing up effect on account of floods in a river into which the drain outfalls, the top of the embankments should be so designed that the flood levels on account of back water conditions are accommodated within the section over which the minimum freeboard is to be provided.

1.7.5 FIXATIONOFFULLSUPPLYLEVEL(FSL)ATOUTFALL

Whenever the drain is out falling into a river, the FSL should be slightly higher than the dominant flood level. The dominant flood level is the stage of river/outfall which is (a) attained and not exceeded for more than 3 days at a time; and also (b) attained and not exceeded 75% of time over a period of preferably not less than 10 years. In cases where the topography permits, the FSL can be above the highest flood level. However, if such a level results in flatter slopes or in FSL becoming higher than the natural ground level, FSL at outfall should be kept slightly above the dominant flood level. In such cases, there will be backing up in the drain when the river rises above the dominant flood level.

Such occurrences being infrequent and of short duration can be

tolerated. Care shall, however, be taken in determining the dominant flood discharge and the level.

Page 101: 2

111 | P a g e

1.7.6 HYDRAULIC SLOPE

The FSL of the drain as far as possible should be at or below the ground level. Where it cannot be ensured, the FSL should in no case be more than 0.3 m above the average ground level at the starting point of the drain. The hydraulic should then be determined adopting the stipulation and the criteria laid down for fixation of FSL at outfall.

1.7.7 FALLS

Normally no falls should be provided in drains except in rare cases where there is a sudden appreciable drop in the natural surface level or where the FSL s likely to be more than natural surface level without provision of falls.

1.8 LONGITUDINALSECTION

IS code 8535:1978 envisages following guidelines for deciding the longitudinal profile of drainage channel.

1.8.1 COLLECTIONOFDATA

The following data should be collected while carrying out surveys along different alternatives alignments of drains:

(a) Cross section of drain. (b) Natural ground, design bed and full supply levels . (c) Locations of inlets of link/field drains with related hydraulic data. (d) Full data of all crossings like roads, railways, irrigation canals, etc.

1.8.2 PREPARATIONOFLONGITUDINALSECTION

(a) Fix outfall level considering the dominant flood levels in the river/drain and the likely backing up.

(b) Hydraulic slope to be determined on the basis of the ground levels, permissible submersion and the outfall levels determined in (a).

(c) Plot the natural ground levels, design bed levels, full sully levels.

1.9 REFERENCES

1. IS code 8535:1978: Guidelines of Planning and design of surface drains.

Page 102: 2

112 | P a g e

CHAPTER-4 CONCLUSIONS From the following studies and discussions the following conclusion can be drawn

1) As present site is located just 1200 meter d/s of Sant Sarovar weir ,the design flood of 7.25 Lack cusecs considered for Sant Sarovar Design will be adopted for protection work design between Shahpur Bridge and d/s of GIFT City. The check flood of 8.38 Lack cusecs adopted for Sant Sarovar will hold god for protection work also.

2) Looking to the Flood discharge and water way of River Sabarmati only existing alignment will be adopted for proposed protection work.

3) For the protection work existing bank alignment will be strictly adhered and eroded

Banks, Farms and agriculture land will be reclaimed by Flood protection schemes.

4) Embankment construction will be carried out from River Bed material and Borrow pits location will be adopted as specified in the IS 11532 and IS 12094.

5) The velocity calculated by model study for Sant Sarovar at 1200 m d/s and at Shahpur

Bridge varies from 4.86 m/s to 5.32 m/s on right and left bank respectively. Considering erosive effect due to these velocity on the banks the protection works will be designed accordingly.

6) The velocity mentioned above will be calculated by mathematical model study based on

Total station survey and cross section collected at certain interval along the river by HEC-2 Computer program developed by Hydrologic Engineering center, US Army corps of Engineers ,U.S.A and protection work will be designed accordingly.

7) Water surface elevation will be worked with protected banks/Jacketing river course for

adopted design flood as well as check flood by HEC 2 Computer program.

8) Free board of 1.8 m will be adopted and water surface elevation corresponding to check flood of 8.38 lacks cusecs will be contained within the Proposed free board will be ensured.

9) The foundation investigation will be carried out along the banks for engineering

classification, Grain size analysis , Silt factor and shape bearing capacity.

10) Silt factor will be adopted for working out scour depth and 1.27 times scour depth will be adopted for scour at the banks and design of Launching apron ,cut off ,Diaphragm ,sheet pile will be carried out accordingly.

11) Existing Drains outfall discharging from country side in to the river Sabarmati will be

effectively Drain into river by constructing appropriate structures.

Page 103: 2

113 | P a g e

12) For protecting erosion prone bank Spurs/Groynes type of structures can be proposed

transverse to the river flow and extending from the bank into the river. However additional scour at curvature and meandering of river additional depth of scour will be worked out and depth of cut off /Diaphragm wall/Sheet pile will be provided .Launching Apron length and thickness will be extended for addition la scour at curvature .The bank protection with additional erosive effect at curvature shall be protected with Rigid boundary protection on slopes and excessive scour by additional depth of cut off and additional length of launching apron will prevent construction of spur and groynes. Rigid boundary will create permanent regime condition and further change in course of river and meandering will be prevented.

13) Based on preliminary design for protection works 3 alternatives have been worked out and which are as follows

ALTERNATIVE 1: CONSTRUCTIONS OF EMBANKMENT WITH STONES IN WIRE CRATE The Homogeneous embankment will be constructed with River side slopes of 2.5:1

abutting with existing banks with berm of width 5 m at intermediate level with available River bed material as borrow area and protection works on Banks with Stone in Wire crates and Geo Fabric filter.

For Scour protection 2 alternatives are proposed 1) Launching apron in wire crates 2) Cut off wall/Diaphragm wall/Sheet pile.

Based on preliminary design following geometrical parameters are considered bank height required of 13.8 m, side slope of 2.5:1,intermediated berm of 5 m country side slope of 2:1

The protection works on the banks consist of Geo Fabric filter ,1 m thick stones in wire crates ,country side slopes protected with 300 mm thick dry stone pitching ,for aesthetic purpose as well as to improve conveyance carrying capacity of the river 7.5 cm thick lining with paver finish is proposed .

The river bed is protected with Launching Apron of 9 m length and 1m thick Gabion

Mattresses and Geo filter below mattresses .Alternatively River Bed protection with 600 mm thick cut off wall /Diaphragm wall/sheet pile with anchorage at top with Wire mesh is proposed.

The top of embankment can be developed as assess road all along the Bank as well as

river front and intermediate berm can act as lower promenade ,Jogging Street.

Page 104: 2

114 | P a g e

Cost of construction for Embankment with stones in wire crates and launching Apron is Rs 1,37,183 and for Embankment with stones in wire crates and Cut off wall is Rs 1,49,994

ALTERNATIVE 2: CONSTRUCTION OF GABION RETAINING WALL WITH TERRAMESH SYSTEM The Flood protection retaining wall with Terramseh system consisting of Fascia of stones

in wire crates and reinforced earth with Geo Mesh is proposed. The total height of retaining wall is divided in two parts of height 7 m each with intermediate berms of 5 m.

Granular material available in river bed is most adequate for reinforced earth technology

proposed here . Layers after Layer in control lift thickness of 30 cm will be constructed at OMC to 95% Proctor Density by vibratory roller and reinforcing with GEO Mesh will be carried out and stability of the same will be ensured by slip circle analysis.

Geo Fabric filter is proposed behind the stones in wire crates for preventing Fine particles

migration from the stones in wire crates. The river bed is protected with Ln with 600 mm thick cut off wall /Diaphragm wall/sheet

pile with anchorage at top with Wire mesh is proposed. Due to vertical Flood protection wall construction additional land of approximate width

of 30 to 35 m will be available at the top which can be developed as Service road/River Front Road with various recreational facilities.

For the above alternative cost of construction per running meter is calculated as Rs

1,18,494

Page 105: 2

115 | P a g e

ALTERNATIVE 3: RIGID R.C.C COUNTER FORT /CANTILEVER WALL WITH DIAPHRAGM WALL/SHEET PILE CONSTRUCTION. The Flood protection wall consist of R.C.C Retaining wall of approximate height of 10

m from the stagnant water pool / full reservoir level extending above lower promenade as proposed in Ahmedabad Sabarmati River FRONT Development is proposed .

Cut off wall /Diaphragm wall/sheet pile is proposed below river bed for scour protection

and same wall is extended above stagnant pool water level /full reservoir level with adequate free board and lower promenade of 10 m wide is proposed

The lower promenade will be submerged during high flood level and will act as a part of

River Front and other recreational facilities. The depth of cut off wall is worked out to 6 m based on check flood discharge of 8.38

lack cusecs and thickness provided is 0.6 m and same is extended up to lower promenade level i.e. above full reservoir level.

Due to vertical Flood protection wall construction additional land of approximate width

of 30 to 35 m will be available at the top which can be developed as Service road/River Front Road with various recreational facilities.

Cost of construction per running meter is calculated as Rs 1,98,944.


Recommended