  • 7/28/2019 27917455 BQ and Preparation of BQ

    1/32

    BILL OF QUANTITIES

    UNIVERSITI MALAYSIA SARAWAK

    Faculty Of Engineering

    KNS 3333 CONSTRUCTION TECHNOLOGY

  • 7/28/2019 27917455 BQ and Preparation of BQ

    2/32

    BILL OF QUANTITIES

    What IsBQ?

    BQ Format,Description,

    Content

    BQ in

    Engineering

    BQPreparation

  • 7/28/2019 27917455 BQ and Preparation of BQ

    3/32

    Traditional Method (Building Works)

    Traditional General Contracting (TGC)

    Client engages architect or engineer toprepare design.

    Upon completion of design, the QS

    prepares a Bill of Quantities based ondrawings and specification.

    Contractors are invited to price the bill.

    Contractor submitting the lowest tenderusually will be awarded the contract.

  • 7/28/2019 27917455 BQ and Preparation of BQ

    4/32

    Design

    Construction

    Sequential

    Client engages Architectand Engineers to design

    Contractor constructs

    TRADITIONAL METHODS

    QS prepares BQ & Compiles Tender Document

    Tender Exercise

  • 7/28/2019 27917455 BQ and Preparation of BQ

    5/32

    What Is A Tender ?

    A tender or a bid is an offer made by acontractor to do certain work for a price,stated in the form of tender and given

    in detail in a priced Bill of Quantities.

  • 7/28/2019 27917455 BQ and Preparation of BQ

    6/32

    Tender exercise is a process of sending out

    drawings and other tender documents to contractorsfor them to prepare a tender price in competitionwith each other and to be submitted at a fixed date.

    Tenders submitted are later opened on a set dateand evaluated before the contract can be awardedto the most suitable contractor.

    What Is Tender Exercise ?

  • 7/28/2019 27917455 BQ and Preparation of BQ

    7/32

    What Is BQ?

  • 7/28/2019 27917455 BQ and Preparation of BQ

    8/32

    What is Bill of Quantities (BQ) ?

    A document produced by Quantity Surveyors (QS).

  • 7/28/2019 27917455 BQ and Preparation of BQ

    9/32

    Who is a Quantity Surveyor?

    A person who calculates the quantity ofmaterials needed for constructing

    buildings, etc. and how much they will cost.

  • 7/28/2019 27917455 BQ and Preparation of BQ

    10/32

    Bill of Quantities (BQ)

    Translate drawings, schedules and specificationby Architect and Engineers into a documentfully describing and accurately representing

    the quantity and quality of the works.

    Quantity Quality

  • 7/28/2019 27917455 BQ and Preparation of BQ

    11/32

    Why produce Bills of Quantities?

    BQ enables all Contractors tenderingfor a contract to price exactly

    on the same information

    Provides a basis for valuation ofvariations or changes to the works

    Can be used by the Contractor to assistin ordering of building materials and

    for assessing his labour requirements

    Provides good basis for cost analysis for useon future contracts in Cost Planning Works,

    e.g. approximate estimating and settingcost targets for budgeting purposes.

  • 7/28/2019 27917455 BQ and Preparation of BQ

    12/32

    BQ Preparation

  • 7/28/2019 27917455 BQ and Preparation of BQ

    13/32

    4 Stages Of BQ Preparation (Traditional)

    Taking Off / Squaring / Abstracting / Billing

    Taking OffTaking off is a process of transferring the dimension scaled orread from the drawings to a specially ruled paper called thedimension paper.

    SquaringSquaring is a process of getting the total quantity whether innumber, length, area or volume for each set of measurement inthe dimension paper.

  • 7/28/2019 27917455 BQ and Preparation of BQ

    14/32

    4 Stages Of BQ Preparation (Traditional)

    AbstractingAbstracting is a process of transferring the squared dimensionsto the abstract where they are written in a recognised orderunder the appropriate work section headings and subsequentlytotaled and converted to the required units or billing as stated in

    the Standard Method of Measurement.

    BillingBilling is a process of re-writing all the items including their

    quantities taken from the abstract for the whole project, into thebilling papers in a recognised format of a Bill of Quantities.

    Taking Off / Squaring / Abstracting / Billing

  • 7/28/2019 27917455 BQ and Preparation of BQ

    15/32

    BQ Preparation - Development

    Taking Off

    Working Up

    Squaring

    AbstractingProcess is verylengthy and tedious

    Various ways of simplifying the process have been developed

    Bill direct i.e. by transferring the items directly from the dimensionsheet to the bill, eliminating the need for an abstract.

    Further methods: cut and shuffle and computers systems were developed.

  • 7/28/2019 27917455 BQ and Preparation of BQ

    16/32

    BQ Preparation - Development

    DRAWINGS DIMENSIONPAPER

    BILLINGPAPER

    BILL OFQUANTITIES

    (BQ)

    Taking Off

    Measurement of quantities

    Squaring

    DirectBilling

  • 7/28/2019 27917455 BQ and Preparation of BQ

    17/32

    BQ Format, Descriptions,Content

  • 7/28/2019 27917455 BQ and Preparation of BQ

    18/32

    Measured work needs to be arranged in a sequencethat is recognised by the industry and can be easilyunderstood and priced by the contractor

    BQ Format

    Elemental Bills

    Annotated Bills

    Trade Bills

    Operational BillsMost Common

    Activity Bills

  • 7/28/2019 27917455 BQ and Preparation of BQ

    19/32

    Elemental Bills

    BQ Format

    Widely used in Malaysia in private consultancy firm andgovernment departments.

    BQ can be abstracted easily and quickly, as measurementis already grouped in the elemental format.

    Under each element, the order of works generally followstrade or construction sequence.

    Terms of element used as per standard classificationspublished by Institution of Surveyors Malaysia (ISM).

  • 7/28/2019 27917455 BQ and Preparation of BQ

    20/32

    Elemental Bills

    1. Piling works2. Work below lowest floor3. Frame4. Upper Floors

    5. Roof6. Staircases7. External Walls8. Windows and External Doors

    8. Internal Walls and Partitions9. Internal Doors10. Internal Wall Finishes11. Internal Floor Finishes12. Internal Ceiling Finishes

    13. External Finishes14. Fittings and Furnishings15. Sanitary Appliances16. Plumbing Installation

  • 7/28/2019 27917455 BQ and Preparation of BQ

    21/32

    Elemental Bills

    17. Refuse Disposal18. Air Conditioning and Ventilation System19. Electrical Installation20. Fire Protection Installation

    21. Lift and Conveyor Installation22. Communication Installation23. Specialised Installation24. Profit and Attendance on Services

    25. Builders Work in Connection with Services26. Site Work27. Drainage28. External Services29. Ancillary Buildings

    30. Recreational Facilities

  • 7/28/2019 27917455 BQ and Preparation of BQ

    22/32

    Trade Bills

    BQ Format

    Works measured in trade formats not popular assubsequent preparation of bills of quantities is difficult if theformat is not in trade formats.

    Under each type of trade, the works is broken down intovarious items.

  • 7/28/2019 27917455 BQ and Preparation of BQ

    23/32

    Trade Bills

    1. Excavator2. Concretor3. Bricklayer4. Drainlayer

    5. Asphalter6. Pavior7. Mason8. Roofer

    9. Carpenter10. Joiner11. Steel and Ironworker12. Plasterer13. Plumber

    14. Heating and Ventilating Engineer15. Electrician16. Glazier17. Painter

  • 7/28/2019 27917455 BQ and Preparation of BQ

    24/32

    BQ DescriptionsA good and concise description is essential for proper pricing.

    The essential ingredients of a good description are as follows:

    Must include all information which estimator will require tobuild up a realistic price;

    First few words should indicate clearly nature of works. Order of stating dimensions shall be consistent and

    generally in sequence of length, width and height. Where sequence is not appropriate or where ambiguity

    could arise, dimensions shall be specifically identified. If an item of work cannot be accurately or fully described,

    proper reference shall be made to drawn information orproduct details for construction, manufacture orassembly of work.

    Description must be concise and not too lengthy, can beshortened by references to specification.

  • 7/28/2019 27917455 BQ and Preparation of BQ

    25/32

    BQ ContentBill of quantities must contain the basic information presented

    in format that is easily understood

    Preliminaries

    Explains type and scope of works, clients needs, temporary sitefacilities and other items affecting the implementation of the works.

    IItems involved need not be measured but need to be described in

    details and the contractor will have to price the items that will affectthe cost of the works in a lump sum figure. Items in this section will

    not be incorporated into the works but are essential for thecompletion of the works.

    Specifications

    Describe the quality of materials and workmanship of the works,

    usually not practical to be presented in the drawings; including otherinformation necessary for the contractor to price the BQ.

  • 7/28/2019 27917455 BQ and Preparation of BQ

    26/32

    BQ ContentMeasured Quantities

    Measured quantities are produced from the measurement of all theworks measurable based on the approved Standard Method ofMeasurement document. These quantities shall be measured as

    accurately as possible so that no parties will make a loss during theimplementation of works.

    Provisional QuantitiesProvisional quantities are produced similarly as above but it is for

    works which cannot be accurately measured at the time ofpreparation of bill of quantities. This situation happens due toincomplete information of work or in cases whereby the extent of

    work cannot be fully determined until the work is completed. Suchwork will be subjected to remeasurement after the works has been

    carried out.

  • 7/28/2019 27917455 BQ and Preparation of BQ

    27/32

    BQ ContentPrime Cost Sum

    Prime cost sum is included for work or services to be executed by anominated sub-contractor, a government or a statutory authority orfor material or goods to be supplied by a nominated supplier. Such

    sum excludes the profit and attendance of the main contractor, ofwhich provision are made in the document for such inclusion by the

    contractor.

    Provisional Sum

    Provisional sum is included for work or for costs that cannot beentirely defined or detailed at the time the bill of quantities areprepared.

    Contingency Sum

    Contingency sum is a sum allocated for any unforeseen work thatcannot be determined at the time of bill of quantities preparation. Itwill be a saving to the client if such contingency sum is not expendeddue to no unforeseen work.

  • 7/28/2019 27917455 BQ and Preparation of BQ

    28/32

    BQ In Engineering

  • 7/28/2019 27917455 BQ and Preparation of BQ

    29/32

    Standard Method Of Measurement

    (SMM)

    Provides a uniform basis for measurement

    Act as a standardise reference

    Embodies the essentials of a good practice

    SMM 2 = SMM for Building Works

    CESMM = SMM for Civil Engineering Works

  • 7/28/2019 27917455 BQ and Preparation of BQ

    30/32

    Malaysian Standard Method Of Measurement

    Unnecessary disputes

    Loss of productivity

    Delays

    Ad-hoc, randomuncontrolled practices

    Uniform basis,standardise references,

    embodies good practices

    Efficient

    Competitive

    Productive

    SMM 2CESMM

    Non-specificreference

  • 7/28/2019 27917455 BQ and Preparation of BQ

    31/32

    BQ In Engineering

    Rare for a civil engineering project to befully designed and detailed during the pre-tender stage due to its nature.

    The most common type of contract used isa remeasurement type.

    BQ has a different role in civil engineering:

    (a) Basis for comparison of tenders;(b) Provide schedule of rates for

    remeasurement;(c) Tool for continued cost monitoring and

    financial control.

  • 7/28/2019 27917455 BQ and Preparation of BQ

    32/32

    BQ In Engineering

    Codifications

    Method Related Charges

    Work Classifications

    Main Differences Between CESMM And SMM2