2bm designed, built and delivered an operational class leading HPC Tier 3 data centre for ARM in less than three months. Above is slideshow of its development
Popular Tags:
42
High Performance Computing
Transcript
Page 1: 2bm ARM HPC Data Centre Design and Build

High Performance Computing

Page 2: 2bm ARM HPC Data Centre Design and Build

The Challenge

3 months on site to deliver a highly efficient Tier 3 data centre

….. in partnership with ARM

Page 3: 2bm ARM HPC Data Centre Design and Build

The Challenge

Only eight weeks to obtain planning permission

….. in partnership with ARM

Page 4: 2bm ARM HPC Data Centre Design and Build

The Challenge

Guaranteed annual PUE of below 1.20

….. in partnership with ARM

Page 5: 2bm ARM HPC Data Centre Design and Build

The Challenge

Significant onsite space constraints

….. in partnership with ARM

Page 6: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

DAY 1

Work begins on site

The clock is ticking!

….. in partnership with ARM

Page 7: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

Early progress

Data Centre floor prepared

….. in partnership with ARM

Page 8: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

Concrete slab poured

and ready

….. in partnership with ARM

Page 9: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

Meanwhile preparatory

work continues apace for

the cooling plant

….. in partnership with ARM

Page 10: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

New cable runs required

for new generators and

& UPS

….. in partnership with ARM

Page 11: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

…start of new diverse

power cable installation

….. in partnership with ARM

Page 12: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

Week 2

Ground works for

containerised generator

and UPS

….. in partnership with ARM

Page 13: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

New home for super low

transformer

….. in partnership with ARM

Page 14: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

Support structure goes

in for generators and

UPS containers

….. in partnership with ARM

Page 15: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

Meanwhile off-site

fabrication work carries on

UPS container in production

….. in partnership with ARM

Page 16: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

Off-site fitting out of UPS

container to ensure

timescales are met

….. in partnership with ARM

Page 17: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

Ready to be delivered

to site

….. in partnership with ARM

Page 18: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

Cooling towers are not far

behind

….. in partnership with ARM

Page 19: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

Modular pre-assembled

design

….. in partnership with ARM

Page 20: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

Data centre structure

taking shape….

….. in partnership with ARM

Page 21: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

Work progressing well

despite the best efforts of

the winter weather

….. in partnership with ARM

Page 22: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

Structure in place….

…work begins on interior

room cladding

….. in partnership with ARM

Page 23: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

….and the cooling system

….. in partnership with ARM

Page 24: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

Individual tap-offs to serve

each cabinet door

….. in partnership with ARM

Page 25: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

Co-ordinated programme…

…300 tonne crane arrives to

lift in generators, UPS, cooling

towers and transformers

….. in partnership with ARM

Page 26: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

UPS container is first to be

craned in

….. in partnership with ARM

Page 27: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

Generators in place

….. in partnership with ARM

Page 28: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

Cooling towers in position

….. in partnership with ARM

Page 29: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

New temporary road also

required for access and

egress

….. in partnership with ARM

Page 30: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

Pipework for cooling

towers and LPS system

….. in partnership with ARM

Page 31: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

Main flow and return

Pipework with redundant

circuits

….. in partnership with ARM

Page 32: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

Main pipework installation

nearing completion

….. in partnership with ARM

Page 33: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

Generators and UPS fully

possitioned

….. in partnership with ARM

Page 34: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

Internal fit out ongoing….

…raised floor starts

….. in partnership with ARM

Page 35: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

….and is quickly in place

….. in partnership with ARM

Page 36: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

Installation of the first

of 60 cabinets is started

….. in partnership with ARM

Page 37: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

Innovative real door cooling

in place

….. in partnership with ARM

Page 38: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

12 weeks in…

…job complete

….. in partnership with ARM

Page 39: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

Fully integrated solution

….. in partnership with ARM

Page 40: 2bm ARM HPC Data Centre Design and Build

2bm.co.uk

…with new roads for access

….. in partnership with ARM

Page 41: 2bm ARM HPC Data Centre Design and Build

Exceeding Expectations“Not only did we construct a Tier3 HPC data centre

in phenomenal time, we still pushed the boundaries of

innovation and efficiencies, ensuring 2bm provided

one of the most energy efficient data centres possible”

….. in partnership with ARM

Page 42: 2bm ARM HPC Data Centre Design and Build

Award Winning Solution•UK IT Industry Awards 2012 – ‘Data Centre Project of the Year’

•European Award for New Data Centre Facility 2012

•First ever CEEDA gold accreditation

….. in partnership with ARM