+ All Categories
Home > Documents > 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL …atc578.com/files/Publication%2026[1].pdf ·...

2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL …atc578.com/files/Publication%2026[1].pdf ·...

Date post: 10-Mar-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
16
2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL INTEGRITY OF PROCESS PIPING January 30 - February 1, 1996 Houston, Texas U.S.A. Refinery Piping Fires Resulting from Variations in Chemical Composition of Piping Materials Richard B. Setterlund, P.E. Metallurgical Consultants, Inc. P. O. Box 88046 Houston, TX 77288-0046 Abstract A number of refinery fires in recent years are traceable to variations in the chemical composition of piping materials. These fires are typically more destructive than those due to other causes and can take place without warning. Some, but not all, were the result of the inadvertent use of carbon steel in alloy steel piping systems. Others were the result of alloy welds in carbon steel systems while still others were due to variations in residual elements leading to anomalous corrosion behavior. Recommendations are given on areas of refinery units where the greatest need for close control of material composition exists. Key Terms: Positive Material Identification, Refinery Fires, Piping Systems, Wet H 2 S service, Sulfidation, HF Alkylation Introduction This paper is directed to failures in petroleum refinery piping systems that have caused serious fires. Many refinery services involve highly flammable hydrocarbon liquid and gasses under conditions of high pressure and/or temperature and while hydrocarbons alone are not corrosive, impurities such as sulfur components or chemical agents added during processing can cause loss of metal which generally occurs in a uniform manner. The combination of flammable contents and uniform metal wastage suggests the possibility of a massive release of hydrocarbons due to failure of thinned piping. However, this rarely occurs due to the combination of knowledge of the corrosiveness of various systems and by closely monitoring the wall thickness of piping. Despite these safeguards, a number of "catastrophic-type" failures have occurred in refinery piping because one or more components had less resistance to corrosion or environmental deterioration than the balance of the piping system. Five examples are given, all from refinery failures investigated by our firm. Examples Example 1 The first example is the failure of a slurry recycle line in a delayed coker unit in Canada in 1984. The line in question was specified to be NPS 6, 1 schedule 40 ASTM A 335 2 grade P5 (UNS K41545) seamless
Transcript
Page 1: 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL …atc578.com/files/Publication%2026[1].pdf · 2017-05-09 · 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL INTEGRITY OF PROCESS PIPING

2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL INTEGRITY OF PROCESS PIPINGJanuary 30 - February 1, 1996 Houston, Texas U.S.A.

Refinery Piping Fires Resulting from Variations in Chemical Composition ofPiping Materials

Richard B. Setterlund, P.E.Metallurgical Consultants, Inc.P. O. Box 88046Houston, TX 77288-0046

Abstract

A number of refinery fires in recent years are traceable to variations in the chemical composition of pipingmaterials. These fires are typically more destructive than those due to other causes and can take placewithout warning. Some, but not all, were the result of the inadvertent use of carbon steel in alloy steelpiping systems. Others were the result of alloy welds in carbon steel systems while still others were dueto variations in residual elements leading to anomalous corrosion behavior. Recommendations are givenon areas of refinery units where the greatest need for close control of material composition exists.

Key Terms: Positive Material Identification, Refinery Fires, Piping Systems, Wet H2S service,Sulfidation, HF Alkylation

Introduction

This paper is directed to failures in petroleum refinery piping systems that have caused serious fires. Manyrefinery services involve highly flammable hydrocarbon liquid and gasses under conditions of high pressureand/or temperature and while hydrocarbons alone are not corrosive, impurities such as sulfur componentsor chemical agents added during processing can cause loss of metal which generally occurs in a uniformmanner. The combination of flammable contents and uniform metal wastage suggests the possibility of amassive release of hydrocarbons due to failure of thinned piping. However, this rarely occurs due to thecombination of knowledge of the corrosiveness of various systems and by closely monitoring the wallthickness of piping.

Despite these safeguards, a number of "catastrophic-type" failures have occurred in refinery piping becauseone or more components had less resistance to corrosion or environmental deterioration than the balanceof the piping system. Five examples are given, all from refinery failures investigated by our firm.

ExamplesExample 1

The first example is the failure of a slurry recycle line in a delayed coker unit in Canada in 1984. The linein question was specified to be NPS 6,1 schedule 40 ASTM A 3352 grade P5 (UNS K41545) seamless

Page 2: 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL …atc578.com/files/Publication%2026[1].pdf · 2017-05-09 · 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL INTEGRITY OF PROCESS PIPING

pipe having a nominal composition of 5-percent chromium and 1/2-percent molybdenum. The linecontained oil with sulfur compounds and coke particles at a temperature of 705 EF (374 EC) and apressure of 240 psig (1.66 MPa).

The fire was traced to the rupture of a 16-in. (406-mm) long section of carbon steel, shown in Figure 1,that had been welded into the line approximately five years previously. The carbon steel section had athickness of only 0.090 to 0.125 in. (2.3 to 3.2 mm) prior to the failure while the adjacent pipe wasbetween 0.250 and 0.260 in. (6.4 to 6.6 mm) thick. The thin pipe had split longitudinally showering theunit with hot oil and causing a fire to spread through the unit resulting in a half dozen additional pipe failures.Figure 2 is a longitudinal metallographic section of one of the girth welds at the end of the carbon steelsection illustrating the abrupt change in wall thickness between the carbon steel section and the adjacent5-percent chromium steel pipe and weld.

This failure was followed a number of years later by a similar failure in another coker unit in Louisiana. Thissecond failure was also due to the inadvertent use of a carbon steel piping component in a 5-percentchromium, 1/2-percent molybdenum alloy steel line and also resulted in a devastating fire. In this case,however, the carbon steel component was not from a modification but from the original constructionapproximately 16 years earlier.

The unit was subjected to a item by item verification of every alloy piping component prior to being placedback in service. The oil company expected that there would be about one component per each five or sixfeet of run but found that there was approximately one component for each foot of piping. Even moredisconcerting was the finding of an approximate 1.5% error rate in the piping components. Many errorswere relatively innocuous such as chemical compositions being slightly off, higher-alloys being used, orwelded pipe in systems calling for seamless, however, at least one deeply-corroded carbon steelcomponent was detected.

Partly as a result of these findings, the American Petroleum Institute3 has undertaken the establishment ofan industry-wide document on positive material identification (PMI). The document, RP 578,4 is now inits initial draft and is based on PMI practices currently in use by a number of major oil companies.

Example 2

The second example is of the failure of a recycle hydrogen line in a Gulf Coast hydrocracker unit in 1994.The failure was in a section of NPS 6 carbon steel pipe that had been welded into a 1-1/4 Cr - 1/2 Mo(UNS K11597) hydrogen recycle line. The line contained hydrogen at a temperature of 600 EF (315 EC)at a hydrogen partial pressure of 2000 psi (13.8 MPa). The total pressure was 2400 psig (16.5 MPa).Chromium-molybdenum alloy steel is required for this application to prevent high temperature hydrogenattack as described in API Publication 941.5

Following the fire, a section of pipe was found to be "missing" from the pipe rack. Fragments, such asshown in Figure 3, were recovered. The fracture surfaces were flat and brittle appearing.

Page 3: 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL …atc578.com/files/Publication%2026[1].pdf · 2017-05-09 · 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL INTEGRITY OF PROCESS PIPING

The failure was the result of high temperature hydrogen attack. The microstructure near the outside surfaceof the pipe in Figure 4 shows hydrogen attack in its initial form. The iron carbides in the pearlite grains arebeing reduced by dissolved hydrogen producing methane gas pressure in the grain boundaries producingfissures. At the midwall of the pipe, shown in Figure 5, about one-half the carbides had been reducedproducing many cracks. Near the inside nearly all the carbides had been decomposed leaving a networkof cracked grain boundaries. See Figure 6.

Investigation revealed that the failed line had been installed twelve years previously during emergencyrepairs to the unit following a fire. The line containing hydrogen gas and hydrocarbons was not consideredcorrosive and no ultrasonic testing had been done. Over the years the soundness of the carbon steel pipedeteriorated due to hydrogen attack; increasing the number of internal cracks and pressure from thesecracks added to the pressure inside the pipe produced stresses sufficient to blow the pipe apart. Theexplosion and resulting fire from this line had caused failures of other piping in the unit resulting in an intensefire.

Example 3

In both previous examples, the failures were due to carbon steel components inadvertently installed inchromium-molybdenum alloy piping systems. This is probably the most common materials error; however,serious fires can result from the use of chromium-molybdenum filler metal in carbon steel pipe. A recentfire was due to a welding error in a valve shop during rework of a high pressure carbon steel pressureletdown valve from a hydrocracker unit. Five percent chromium, one-half percent alloy steel weld fillermetal was used to join carbon steel piping components.

The service conditions for the pressure letdown valve consisted of light hydrocarbons, hydrogen sulfide andmoisture at a temperature of 130 EF (54 EC) and a pressure of 2714 psig (18.7 MPa). The weld failedby sulfide-stress cracking (SSC) after approximately 1-1/2 years service. The weld broke open producinga horizontal V-shaped torch fire pattern which produced secondary flammable liquid fires in downstreampiping and equipment. The failed weld had a chromium content of approximately 4% with approximately0.5% molybdenum. The weld root had a hardness of HRC 296 and the weld cap had a hardness of HRC34. The cracking was confined to the hard weld deposit.

Refinery welds for carbon steel in wet H2S service are required to have a maximum hardness of 200 HB7

per NACE RP04728 to prevent SSC. This hardness limit is equivalent to less than HRC 20 on theRockwell hardness scale and could have been met without a postweld heat treatment (PWHT) had carbonsteel filler metal been used for the weld. The 5 Cr - 1/2 Mo filler metal that was used is hard in the as-welded condition and even if its use had been allowed it would have been required to be PWHT by therefinery piping code.

Page 4: 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL …atc578.com/files/Publication%2026[1].pdf · 2017-05-09 · 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL INTEGRITY OF PROCESS PIPING

Example 4

The first three examples all were the result of the wrong material being used and could have been preventedby a PMI program. The final two examples, however, show that similar type fractures can occur due tocompositional differences in material of the same classification.

The failure was in a NPS 4 schedule 80 ASTM A 539 grade B carbon steel line at the outlet of ahydrodesulfurizer (HDS) charge heater. The line carried heavy naphtha with 0.06 percent sulfur at atemperature of 610 EF (321 EC) and a pressure of 450 psig (3.1 MPa). The failure was in a short sectionof pipe welded between two 90-degree ells as shown in Figure 7. It was believed that this section hadbeen added in the field in order to correct an interference problem.

Figure 8 shows the components from the failed line. It was determined that all components other than thesection that failed were silicon-killed carbon steel having between 0.15 and 0.30 percent silicon. Thesilicon content of the part that failed was only 0.016 weight percent. Both met the ASTM A 53 grade Bspecification for carbon steel pipe which has no minimum silicon requirement.

The average wall thickness of the piece that failed was only 0.05 in. (1.3 mm) while the five silicon-killedcomponents had average wall thicknesses of 0.18 to 0.26 in.(4.6 to 6.6 mm) as shown in Figure 9. Thesecomponents had been thinned below the minimum wall thickness for new pipe but were above the piperetirement thickness shown in the API guide for inspection of refinery equipment then in force.10

Figure 10 shows a longitudinal section of a weld between the failed pipe and adjacent ell.

Field experiences have shown that the silicon content of carbon steel can have a significant effect on therate of sulfidation in hot oil service.11, 12 A failure very similar to that of Example 4 was reported to haveoccurred in the feed line to a vacuum heater in a crude unit.13

Example 5

The final example, like the first example given, involved a field splice piece or "pup piece." The pup piecewas believed to have been added in the field to adjust the elevation of the inlet piping to the depropanizercolumn in an HF Alkylation Unit. The depropanizer feed line was NPS 3 schedule 80 pipe having anoriginal nominal wall thickness of 0.216 in. (5.49 mm). It contained mostly C3 to C5 hydrocarbons alongwith 0.52 percent HF and a trace of moisture at a temperature of 120 EF (48.9 EC).

The 6 in. (15 cm) pup section was thinned to less than 0.05 in. (1.3 mm) wall thickness and failed. Wallthickness measurements on the balance of the piping showed thicknesses between 0.13 and 0.20 in. (3.3and 5.1 mm) as shown in Figure 11. The as-received sample is shown inFigure 12. Note the uniformity of the thinning. Shortly after removal from the line, the failed section hada rusty color as opposed to the adjacent pipe which retained a metallic color.

Page 5: 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL …atc578.com/files/Publication%2026[1].pdf · 2017-05-09 · 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL INTEGRITY OF PROCESS PIPING

Chemical analyses of the corroded pup piece and the adjacent pipe showed that both conformed to therequirements for ASTM A 53 grade B pipe and that the two samples had similar compositions. The failedsection had been deoxidized with aluminum while the adjacent pipe was semi-killed steel. Also, the puppiece had a somewhat higher level of residual alloying elements.

ASTM A 53Adjacent Pipe Pup Piece grade B

Carbon, % 0.24 0.24 0.30 max.Manganese, % 0.73 0.99 1.20 max.Phosphorus, % 0.006 0.007 0.05 max.Sulfur, % 0.026 0.024 0.06 max.Silicon, % 0.03 0.04 -Aluminum, % N.D. 0.02 -Copper, % 0.01 0.01 -Nickel, % 0.02 0.09 -Chromium, % 0.02 0.06 -Molybdenum, % 0.02 0.07 -(Cu+Ni+Cr), % 0.05 0.16 -

Carbon steel has good resistance to anhydrous hydrogen fluoride (HF) at temperatures up to approximately160 EF (71 EC). The corrosion resistance is the result of the formation of a protective iron fluoride scalethat protects the metal from corrosion. The scale restricts the outward diffusion of iron and inward diffusionof fluoride and the maintenance of an adherent and continuous scale is needed to keep the metal loss at aminimum. Chromium and silicon which both reduce the rate of corrosion of carbon steel by hot H2S canincrease the rate of corrosion by hot HF.14, 15 Also, chromium, nickel, and copper have all been shownto be detrimental to the corrosion resistance of steel to hot HF since they affect the formation of theprotective iron fluoride film.16

A recommended maximum combined content of (Cr+Ni+Cu) of 0.2 percent has been proposed for HFservice.17 The failed pup piece met the 0.2 percent combined limit illustrating that composition limits maynot be the proper criterion. The problem was not that the failed section of pipe was "bad" but rather thatit was a short section welded into "better" pipe. Had the piping system been constructed of piping with ahigher impurity level, the loss of wall thickness would have been detected and the piping replaced beforethere was a risk of a fire.

Summary

The common factor in the five examples is the unexpected complete failure of a piping component resultingin a large release of flammable contents. All took place without warning while the units were under normaloperating conditions and, in the five cases presented, the release of hydrocarbon resulted in a major fire.

Page 6: 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL …atc578.com/files/Publication%2026[1].pdf · 2017-05-09 · 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL INTEGRITY OF PROCESS PIPING

Examples 1 and 2 were cases where carbon steel components were installed in low alloy steel lines. Errorsof this type are now unlikely to occur during new construction since major contractors, as well as mostrefiners have strict PMI programs in force. Older units are most likely to contain material errors due toconstruction before PMI programs were universally employed and, due to their age, are more likely to havematerial errors due to greater amounts of maintenance welding during unit turnarounds, modifications, andrepairs. Individual alloy and carbon steel piping components can easily be segregated by field analysesprior to construction; however, once fabricated and insulated, verification becomes difficult.

The use of incorrect welding materials can also result in serious problems as shown by Example 3. Thiscan be overcome by quality control procedures during construction followed by PMI of alloy steel weldsto ensure that the correct filler metal is used. Field hardness testing of all welds in wet H2S environmentsare recommended to ensure that errors have not produced welds that are susceptible to sulfide-stresscracking.

Based on Examples 1, 2, and 3 and others mentioned, the following services demand use of a rigorous PMIprogram.

1. Hot sulfur-bearing piping systems where chromium-molybdenum or other alloy steels areneeded for sulfidation resistance.

2. Hot hydrogen-bearing piping systems requiring chromium-molybdenum or other alloysteels to prevent decarburization or fissuring.

3. Piping containing water and sulfide requiring control of hardness and/or stress to preventsulfide stress cracking.

The effect of residual elements on corrosion shown by Examples 4 and 5 represent problems that are moredifficult to control. This is due to the fact that residual elements may not be at a high enough level to bemeasured by field analyses. Work is continuing on methods to separate silicon-killed steels (>0.1% Si)from semi-killed steels (<0.1% Si), but at the present time there is no simple and reliable method to do this.It should be noted, however, that the presence of silicon generally becomes critical only in sulfidingconditions over approximately 550 EF (288 EC).

Corrosion by hot hydrogen fluoride is another service condition where field analyses are not appropriatesince very small amounts of alloying elements can produce a large change in the corrosion rate. Thisproblem is now under study by an NACE Task Group.(18) In most HF Alkylation units corrosion is not aproblem since careful control of the moisture content can keep the corrosion rates of both high and lowimpurity steels at very low levels. In those cases where a significant rate of metal loss is found it may benecessary to make a component-by component check to ensure that the least corrosion resistantcomponent is located.

Page 7: 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL …atc578.com/files/Publication%2026[1].pdf · 2017-05-09 · 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL INTEGRITY OF PROCESS PIPING

References

1. NPS 6 refers to six-inch nominal pipe size. This pipe has an outside diameter of 6.625 inches(168.3 mm).

2. ASTM A 335 "Standard Specification for Seamless Ferritic Alloy-Steel Pipe for HighTemperature," Annual Book of ASTM Standards, Volume 01.01.

3. American Petroleum Institute, 1220 L. Street N.W. Washington, D.C. 20005.

4. API RP 578 "Recommend Practice for Positive Materials Identification (PMI)" (Issue Pending).

5. API Publication 941 "Steels for Hydrogen Service at Elevated Temperature and Pressures inPetroleum Refineries and Petrochemical Plants," Fourth Edition (1990).

6. Hardness Rockwell C per ASTM E 18 "Rockwell Hardness and Rockwell Superficial Hardnessof Metallic Materials."

7. Hardness Brinell per ASTM E 103 "Rapid Indentation Hardness Testing of Metallic Materials."

8. NACE RP0472 "Methods and Controls to Prevent In-Service Environmental Cracking of CarbonSteel Weldments in Corrosive Petroleum Refining Environments."

9. ASTM A 53 "Pipe, Steel, Black and Hot-Dipped Zinc Coated, Welded and Seamless."

10. Guide for Inspection of Refinery Equipment, Second Edition (1974), American Petroleum Institute,Chapter XI pp. 21-24.

11. API Publication 943 "High-Temperature Crude Oil Corrosivity Studies," (1974) p. 23.

12. R. B. Setterlund, "Selecting Process Piping Materials," Hydrocarbon Processing, August 1991, pp.93-100.

13. R. P. Buhrow, "Know Areas of Vulnerability, Safety Guidelines," Hydrocarbon Processing, August1986, pp. 19-102.

14. Corrosion Engineering, Fontana and Greene, 2nd Edition (1978) p. 257.

15. G. Trabonellie, et al, Materials Performance, Vol. 24, June (1985) p. 33.

16. T. F. Degnan, "Materials of Construction for Hydrofluoric Acid and Hydrogen Fluoride," ProcessIndustries Corrosion, NACE (1986) p. 277.

17. H. H. Hashim and W. L. Valerioti, "Effect of Residual copper, Nickel and Chromium on theCorrosion Resistance of Carbon Steel in Hydrofluoric Acid Alkylation Service," paper 623, Corrosion/93(1993).

18. NACE Task Group T-8-20, "Materials Considerations for HF Alkylation Units."

Page 8: 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL …atc578.com/files/Publication%2026[1].pdf · 2017-05-09 · 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL INTEGRITY OF PROCESS PIPING

Figure 1

Drawing showing location of failed carbon steel pup piece in Example 1.

Figure 2

Section through weld showing the difference in wall thickness between carbonsteel pup piece at right and 5% Cr - 1/2% Mo pipe at left.

Page 9: 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL …atc578.com/files/Publication%2026[1].pdf · 2017-05-09 · 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL INTEGRITY OF PROCESS PIPING

Figure 3

Fractured carbon steel pipe from hydrogen recycle line in Example 2.

600XFigure 4 Nital Etch

Microstructure showing onset of hydrogen attack.

Page 10: 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL …atc578.com/files/Publication%2026[1].pdf · 2017-05-09 · 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL INTEGRITY OF PROCESS PIPING

600XFigure 5 Nital Etch

Microstructure showing hydrogen attack inadvanced stage.

600XFigure 6 Nital Etch

Microstructure showing hydrogen attack in finalstage.

Page 11: 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL …atc578.com/files/Publication%2026[1].pdf · 2017-05-09 · 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL INTEGRITY OF PROCESS PIPING

Figure 7

View of failed piping after fire in Example 4. A pup section between the arrows hadfailed.

Page 12: 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL …atc578.com/files/Publication%2026[1].pdf · 2017-05-09 · 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL INTEGRITY OF PROCESS PIPING

Figure 8

Failed sections reassembled in laboratory.

Page 13: 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL …atc578.com/files/Publication%2026[1].pdf · 2017-05-09 · 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL INTEGRITY OF PROCESS PIPING

Figure 9

Silicon contents and averaged wall thickness measurements ofNPS 4 schedule 80 pipe components.

Page 14: 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL …atc578.com/files/Publication%2026[1].pdf · 2017-05-09 · 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL INTEGRITY OF PROCESS PIPING

Figure 10

Weld area between failed pup section at right and 90-degree ell at left.

Page 15: 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL …atc578.com/files/Publication%2026[1].pdf · 2017-05-09 · 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL INTEGRITY OF PROCESS PIPING

Figure 11

Wall thickness readings made after failure of pup piece in HFAlkylation Depropanizer Column feed line in Example 5.

.20".20"

.20"SCH 40 ELL

.19"

.19"

.14"

.14"

.14"

.15".14"

SCH 40-45

6" PUP PIECE THINNED TO LESSTHAN .05" AND THEN FAILED

.19"

.15"

.15"

.14"

.14"

.15"

.22" MIN

.24" MIN

.14"

.15"

.16"

.15"

.16"

.16".16"

.16".19"

.13"

.13"

Page 16: 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL …atc578.com/files/Publication%2026[1].pdf · 2017-05-09 · 2ND INTERNATIONAL SYMPOSIUM ON THE MECHANICAL INTEGRITY OF PROCESS PIPING

Figure 12

Samples from HF alkylation feed line.The failed pup piece is at the top and the adjacent pipe atthe bottom.


Recommended