3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management,...

Date post: 31-Mar-2015
Category:
Upload: emmeline-torbet
View: 308 times
Download: 12 times
Share this document with a friend
Popular Tags:
56
3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint slides by Jeff Heyl
Transcript
Page 1: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

33 Project ManagementProject Management

PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e

PowerPoint slides by Jeff Heyl

Page 2: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

2

Outline

Project Management Overview Project Planning, Scheduling, and Control Project Organization Project Management Techniques: PERT and CPM

Activity-on-Node Example Activity-on-Arrow Example

Determining the Project Schedule Forward Pass Backward Pass Calculating Slack Time and Identifying the Critical Path(s)

Project Crashing

Page 3: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

3

Learning Objectives

1. Use a Gantt chart for scheduling

2. Draw an AON network

3. Complete forward and backward passes for a project

4. Determine a critical path

5. Calculate slack

6. Project crashing

Page 4: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

4

Bechtel Projects Building 26 massive distribution centers in just

two years for the internet company Webvan Group ($1 billion)

Constructing 30 high-security data centers worldwide for Equinix, Inc. ($1.2 billion)

Building and running a rail line between London and the Channel Tunnel ($4.6 billion)

Developing an oil pipeline from the Caspian Sea region to Russia ($850 million)

Expanding the Dubai Airport in the UAE ($600 million), and the Miami Airport in Florida ($2 billion)

Page 5: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

5

Single unit Many related activities Difficult production planning and

inventory control General purpose equipment High labor skills

Project Characteristics

Page 6: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

6

PlanningObjectivesResourcesWork break-down

structureOrganization

SchedulingProject activitiesStart & end timesNetwork

ControllingMonitor, compare, revise, action

Project Management Activities

Page 7: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

7

Project Planning, Scheduling, and Controlling

Figure 3.1

Before Start of project Duringproject Timeline project

Page 8: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

8

Project Planning, Scheduling, and Controlling

Figure 3.1

Before Start of project Duringproject Timeline project

Page 9: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

9

Project Planning, Scheduling, and Controlling

Figure 3.1

Before Start of project Duringproject Timeline project

Page 10: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

10

Project Planning, Scheduling, and Controlling

Figure 3.1

Before Start of project Duringproject Timeline project

Page 11: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

11

Project Planning, Scheduling, and Controlling

Figure 3.1

Before Start of project Duringproject Timeline project

BudgetsDelayed activities reportSlack activities report

Time/cost estimatesBudgetsEngineering diagramsCash flow chartsMaterial availability details

CPM/PERTGantt chartsMilestone chartsCash flow schedules

Page 12: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

12

The Role of the Project Manager

Highly visibleResponsible for making sure that:

1. All necessary activities are finished in order and on time

2. The project comes in within budget

3. The project meets quality goals

4. The people assigned to the project receive motivation, direction, and information

Project managers should be:

Good coaches Good communicators Able to organize activities

from a variety of disciplines

Page 13: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

13

Ethical Issues

1. Offers of gifts from contractors

2. Pressure to alter status reports to mask delays

3. False reports for charges of time and expenses

4. Pressure to compromise quality to meet schedules

Project managers face many ethical decisions on a daily basis

The Project Management Institute has established an ethical code to deal with problems such as:

Page 14: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

14

Work Breakdown Structure

Level

1. Project

2. Major tasks in the project

3. Subtasks in the major tasks

4. Activities (or work packages)to be completed

Page 15: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

15

Level 4 Compatible with Windows ME

Compatible with Windows Vista

Compatible with Windows XP 1.1.2.3

1.1.2.2

1.1.2.1

(Work packages)

Level 3 Develop GUIs Planning

Module Testing

Ensure Compatibility with Earlier Versions

Cost/Schedule Management

Defect Testing

1.1.1

1.2.2 1.3.2

1.3.11.2.1

1.1.2

Work Breakdown Structure

Figure 3.3

Level 2 Software Design

Project Management

System Testing1.1 1.2 1.3

Level 1 Develop Windows 7 Operating System 1.0

Page 16: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

16

Project Scheduling Identifying precedence

relationships Sequencing activities Determining activity

times & costs Estimating material &

worker requirements Determining critical

activities

Page 17: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

17

Gantt chart Critical Path Method

(CPM) Program Evaluation

and Review Technique (PERT)

Project Management Techniques

Page 18: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

18

A Simple Gantt Chart

TimeJ F M A M J J A S

Design

Prototype

Test

Revise

Production

Page 19: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

19

Service For a Delta Jet

Figure 3.4

Passengers

Baggage

Fueling

Cargo and mail

Galley servicing

Lavatory servicingDrinking water

Cabin cleaning

Cargo and mail

Flight services

Operating crewBaggagePassengers

DeplaningBaggage claimContainer offloadPumpingEngine injection waterContainer offloadMain cabin doorAft cabin doorAft, center, forwardLoadingFirst-class sectionEconomy sectionContainer/bulk loadingGalley/cabin checkReceive passengersAircraft checkLoadingBoarding

0 10 20 30 40Time, Minutes

Page 20: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

20

Network techniques Developed in 1950’s

CPM by DuPont for chemical plants (1957) PERT by Booz, Allen & Hamilton with the

U.S. Navy, for Polaris missile (1958)

Consider precedence relationships and interdependencies

Each uses a different estimate of activity times

PERT and CPM

Page 21: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

21

Six Steps PERT & CPM

1. Define the project and prepare the work breakdown structure

2. Develop relationships among the activities - decide which activities must precede and which must follow others

3. Draw the network connecting all of the activities

Page 22: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

22

Six Steps PERT & CPM

4. Assign time and/or cost estimates to each activity

5. Compute the longest time path through the network – this is called the critical path

6. Use the network to help plan, schedule, monitor, and control the project

Page 23: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

23

A Comparison of AON and AOA Network ConventionsActivity on Activity Activity onNode (AON) Meaning Arrow (AOA)

A comes before B, which comes before C.

(a) A B CBA C

A and B must both be completed before C can start.

(b)

A

CC

B

A

B

B and C cannot begin until A is completed.

(c)

B

A

CA

B

CFigure 3.5

Page 24: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

24

A Comparison of AON and AOA Network ConventionsActivity on Activity Activity onNode (AON) Meaning Arrow (AOA)

C and D cannot begin until both A and B are completed.

(d)A

B

C

D B

A C

D

C cannot begin until both A and B are completed; D cannot begin until B is completed. A dummy activity is introduced in AOA.

(e)CA

B D

Dummy activityA

B

C

D

Figure 3.5

Page 25: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

25

A Comparison of AON and AOA Network ConventionsActivity on Activity Activity onNode (AON) Meaning Arrow (AOA)

B and C cannot begin until A is completed. D cannot begin until both B and C are completed. A dummy activity is again introduced in AOA.

(f)

A

C

DB A B

C

D

Dummy activity

Figure 3.5

Page 26: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

26

AON Example

Activity DescriptionImmediate

Predecessors

A Build internal components —

B Modify roof and floor —

C Construct collection stack A

D Pour concrete and install frame A, B

E Build high-temperature burner C

F Install pollution control system C

G Install air pollution device D, E

H Inspect and test F, G

Milwaukee Paper Manufacturing'sActivities and Predecessors

Table 3.1

Page 27: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

27

AON Network for Milwaukee Paper

A

Start

BStart Activity

Activity A(Build Internal Components)

Activity B(Modify Roof and Floor)

Figure 3.6

Page 28: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

28

AON Network for Milwaukee Paper

Figure 3.7

C

D

A

Start

B

Activity A Precedes Activity C

Activities A and B Precede Activity D

Page 29: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

29

AON Network for Milwaukee Paper

G

E

F

H

CA

Start

DB

Arrows Show Precedence Relationships Figure 3.8

Page 30: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

30

H

(Inspect/ Test)

7Dummy Activity

AOA Network for Milwaukee Paper

6

F(Install

Controls)E

(Bu

ild B

urn

er)G

(Insta

ll

Pollutio

n

Device)

5D

(Pour Concrete/

Install Frame)

4C

(Construct Stack)

1

3

2

B(Modify

Roof/Floor)

A(B

uild In

tern

al

Componen

ts)

Figure 3.9

Page 31: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

31

Determining the Project Schedule

Perform a Critical Path Analysis The critical path is the longest path

through the network The critical path is the shortest time in

which the project can be completed Any delay in critical path activities

delays the project Critical path activities have no slack

time

Page 32: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

32

Determining the Project Schedule

Perform a Critical Path Analysis

Table 3.2

Activity Description Time (weeks)A Build internal components 2B Modify roof and floor 3C Construct collection stack 2D Pour concrete and install frame 4E Build high-temperature burner 4F Install pollution control system 3G Install air pollution device 5H Inspect and test 2

Total Time (weeks) 25

Page 33: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

33

Determining the Project Schedule

Perform a Critical Path Analysis

Table 3.2

Activity Description Time (weeks)A Build internal components 2B Modify roof and floor 3C Construct collection stack 2D Pour concrete and install frame 4E Build high-temperature burner 4F Install pollution control system 3G Install air pollution device 5H Inspect and test 2

Total Time (weeks) 25

Earliest start (ES) = earliest time at which an activity can start, assuming all predecessors have been completed

Earliest finish (EF) = earliest time at which an activity can be finished

Latest start (LS) = latest time at which an activity can start so as to not delay the completion time of the entire project

Latest finish (LF) = latest time by which an activity has to be finished so as to not delay the completion time of the entire project

Page 34: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

34

Determining the Project Schedule

Perform a Critical Path Analysis

Figure 3.10

A

Activity Name or Symbol

Earliest Start ES

Earliest FinishEF

Latest Start

LS Latest Finish

LF

Activity Duration

2

Page 35: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

35

Forward PassBegin at starting event and work forward

Earliest Start Time Rule: If an activity has only a single immediate predecessor, its

ES equals the EF of the predecessor If an activity has multiple immediate predecessors, its ES is

the maximum of all the EF values of its predecessors

ES = Max {EF of all immediate predecessors}

Earliest Finish Time Rule:

EF = ES + Activity time

Page 36: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

36

ES/EF Network for Milwaukee Paper

Start

0

0

ES

0

EF = ES + Activity time

Page 37: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

37

ES/EF Network for Milwaukee Paper

Start0

0

0

A

2

2

EF of A = ES of A + 2

0

ESof A

Page 38: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

38

B

3

ES/EF Network for Milwaukee Paper

Start0

0

0

A

2

20

3

EF of B = ES of B + 3

0

ESof B

Page 39: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

39

C

2

2 4

ES/EF Network for Milwaukee Paper

B

3

0 3

Start0

0

0

A

2

20

Page 40: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

40

C

2

2 4

ES/EF Network for Milwaukee Paper

B

3

0 3

Start0

0

0

A

2

20

D

4

73= Max (2, 3)

Page 41: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

41

D

4

3 7

C

2

2 4

ES/EF Network for Milwaukee Paper

B

3

0 3

Start0

0

0

A

2

20

Page 42: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

42

E

4

F

3

G

5

H

2

4 8 13 15

4

8 13

7

D

4

3 7

C

2

2 4

ES/EF Network for Milwaukee Paper

B

3

0 3

Start0

0

0

A

2

20

Figure 3.11

Page 43: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

43

Backward PassBegin with the last event and work backwardsLatest Finish Time Rule:

If an activity is an immediate predecessor for just a single activity, its LF equals the LS of the activity that immediately follows it

If an activity is an immediate predecessor to more than one activity, its LF is the minimum of all LS values of all activities that immediately follow it

LF = Min {LS of all immediate following activities}

Latest Start Time Rule:

LS = LF – Activity time

Page 44: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

44

LS/LF Times for Milwaukee Paper

E

4

F

3

G

5

H

2

4 8 13 15

4

8 13

7

D

4

3 7

C

2

2 4

B

3

0 3

Start0

0

0

A

2

20

LF = EF of Project

1513

LS = LF – Activity time

Page 45: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

45

LS/LF Times for Milwaukee Paper

E

4

F

3

G

5

H

2

4 8 13 15

4

8 13

7

13 15

D

4

3 7

C

2

2 4

B

3

0 3

Start0

0

0

A

2

20

LF = Min(LS of following activity)

10 13

Page 46: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

46

LS/LF Times for Milwaukee Paper

E

4

F

3

G

5

H

2

4 8 13 15

4

8 13

7

13 15

10 13

8 13

4 8

D

4

3 7

C

2

2 4

B

3

0 3

Start0

0

0

A

2

20

LF = Min(4, 10)

42

Page 47: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

47

LS/LF Times for Milwaukee Paper

E

4

F

3

G

5

H

2

4 8 13 15

4

8 13

7

13 15

10 13

8 13

4 8

D

4

3 7

C

2

2 4

B

3

0 3

Start0

0

0

A

2

20

42

84

20

41

00

Page 48: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

48

Computing Slack Time

After computing the ES, EF, LS, and LF times for all activities, compute the slack or free time for each activity

Slack is the length of time an activity can be delayed without delaying the entire project

Slack = LS – ES or Slack = LF – EF

Page 49: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

49

Computing Slack Time

Table 3.3

Earliest Earliest Latest Latest OnStart Finish Start Finish Slack Critical

Activity ES EF LS LF LS – ES Path

A 0 2 0 2 0 YesB 0 3 1 4 1 NoC 2 4 2 4 0 YesD 3 7 4 8 1 NoE 4 8 4 8 0 YesF 4 7 10 13 6 NoG 8 13 8 13 0 YesH 13 15 13 15 0 Yes

Page 50: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

50

Critical Path for Milwaukee Paper

E

4

F

3

G

5

H

2

4 8 13 15

4

8 13

7

13 15

10 13

8 13

4 8

D

4

3 7

C

2

2 4

B

3

0 3

Start0

0

0

A

2

20

42

84

20

41

00

Page 51: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

51

ES – EF Gantt Chartfor Milwaukee Paper

A Build internal components

B Modify roof and floor

C Construct collection stack

D Pour concrete and install frame

E Build high-temperature burner

F Install pollution control system

G Install air pollution device

H Inspect and test

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

Page 52: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

52

LS – LF Gantt Chartfor Milwaukee Paper

A Build internal components

B Modify roof and floor

C Construct collection stack

D Pour concrete and install frame

E Build high-temperature burner

F Install pollution control system

G Install air pollution device

H Inspect and test

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

Page 53: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

53

What Project Management Has Provided So Far

1. The project’s expected completion time is 15 weeks

2. Five activities (A, C, E, G, and H) are on the critical path

3. Three activities (B, D, F) are not on the critical path and have slack time

4. A detailed schedule is available

Page 54: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

54

Trade-Offs and Project Crashing

The project is behind schedule The completion time has been

moved forward

It is not uncommon to face the following situations:

Shortening the duration of the project is called project crashing

Page 55: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

Factors to Consider When Crashing a Project

The amount by which an activity is crashed is, in fact, permissible

Taken together, the shortened activity durations will enable us to finish the project by the due date

The total cost of crashing is as small as possible

Page 56: 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint.

56

In-Class Problems from the Lecture Guide Practice Problems

Activity Immediate Predecessor

A -

B -

C A

D B

E B

F C, E

G D

H F, G

Problem 1:The following represent activities in a major construction project. Draw the network to represent this project.