Date post: | 21-Jul-2016 |
Category: |
Documents |
Upload: | obsession-magazine |
View: | 33 times |
Download: | 3 times |
08.3.1 Hidroenergia 2008 – Bled/Slovenia
The Gran-olo sula Project:
MHP implementation in the Hinterland of Surinam
by
Dr. Eduard DOUJAK
and
Dr. Sieuwnath NAIPAL
08.3.2 Main Objective
Design, construct and implement locally a
Micro Hydropower Plant for the conditions of
Suriname aiming to provide electricity on a
sustainable way
08.3.3 General overview and background
Annual average rainfall
N-E Trade winds Dec - Jan
S-E Trade winds April – August
08.3.4 Location of the project
• District Sipaliwini
• Lower Tapanahony river
• Study area encompasses about 13 villages
with Drietabbetje as main of the local
government.
• The villages are found within a radius of
about 7-8 km from the Energy source (MHP
site).
08.3.5 One way to access the Hinterland
Site at the
Tapanahony river
08.3.6 Infrastructure
• Two airstrips: (1) at Puketi, and (2) at
Drietabbetje. Flight duration Paramaribo-
Dritabbetje 50-60 min.
• A railway at Futupasie for facilitating
transport of goods.
• Duration water transport from Albina to
Dritabbetje ±2days
• Some of the villages are not foreseen with
electricity
• Telephone connection with Paramaribo
08.3.7 Aerial view
09 feb 2008
08.3.8 Electricity provisions
• Some of the villages are for seen with
electricity (by diesel generators)
• Electricity generation only between
18:00 – 11:00 our.
• Is being subsidized by the central
Government (Paramaribo, about 10
barrel diesel per “village”).
08.3.9 Sectors in need of electricity
• Health care
• Lightning during the nocturnal hours
• Schools and other public places
• Private persons for conserving of food
• Tourism (industries)
• Sawmill units
• In the near future Telecom and Television
08.3.10 Aerial view of the Gran-olo sula (2005)
Potential location
08.3.11 Gran-olo sula
213
45
08.3.12 Electricity distribution
Name village Electricity need (kW)
Kisai 25
Pikien kondre 15
Pikienprisiri 15
Sanbidoemi 15
Luabi 20
Prolokaba 10
Pipa-kondre 10
Dritabiki 60
Mainsi 15
Jawsa 25
Moitaki 25
Puketi 20
Sangamasoesa 15
Sum 245
08.3.13 Hydrological features of the river
• Serious fluctuations of water levels observed. In
general 4-6m, with an average fluctuation of
about 4m.
• Minimum head 2m.
• Maximum head 6m
• Design head 3m
• Estimated minimum discharge at the
surroundings of the site - 15 m3/s
• Estimated maximum discharge >50 m3/s
08.3.14 Hydrological data (waterlevel)
08.3.15 Flow duration curve
Flow duration / head of a year
0
30
60
90
120
150
180
210
240
270
0 30 60 90 120 150 180 210 240 270 300 330 360
days
Dis
ch
arg
e [
m³/
s]
0
1
2
3
4
5
6
7
8
9
He
ad
[m
]
Mean Flow
Mean Head
La
yo
ut
po
int
08.3.16 Turbine layout parameters
Layout parameters
Rated discharge 5 m³/s per turbine
Design head 3 m
Site elevation 100 m
Water temperature 20°
System frequency 60 Hz
08.3.17 Main turbine design parameters
1min14.25714
606060
p
fnsSynchronous speed:
1
75.075.0min24.252
3
514.257
H
QnnqSpecific speed:
“A hydraulic machine works cavitation free if the specific energy
of the plant YHA is higher than the specific energy of the
machine YH.”
mhs 85.665.581.9
67.429.30
81.92
5.0
81.93.998
2337129100 2
Turbine suction head:
"" operationfreecavitationYY HHACavitation criterion:
mDmn
HkD u 1083.1
14.257
39.16.846.84 1
11Runner diameter:
mDDD
Dn
n 4.04.04.0 1
1
Hub diameter:
kWHQgP 2.1329.03581.93.998Power output:
08.3.18 Turbine design process
Main data
„Kaplan“ software
Runner layout data
Design by using
“SolidEdge” software
Runner geometry
Input: nq,Q,H,YHA,
D1, Dn, …
08.3.19
View inlet and turbine 2D cross-section view
Total power house view 3D cross-section view
Power house layout
08.3.20
02/2008
11/2007 11/200710/2007
11/200712/200702/2008
Some impression from the construction site
10/2007
Water diversion works
11/2007
Water inlet adjustmentThree water inlets for the turbines
11/2007
Food preparation at the construction site
11/2007
Turbine outlets, construction impression
12/2007
Construction of the power house
02/2008
The power house at the moment (H~3m, Q -> enough)
02/2008
08.3.21 Possible situations (flooding 2006)
Flooding in may 2006; destroyed all the infrastructure: as seen from
the hydrograph, suitable period for construction is October
November
08.3.22 Final
VIENNA UNIVERSITY OF TECHNOLOGY
Institute for Thermodynamics and Energy Conversion
RG Fluid-Flow Machinery
Getreidemarkt 9/302
A-1060 Vienna/AUSTRIA
Tel.: +43/1/58801-30515 , FAX: +43/1/58801-31399
Email: [email protected]
Thank for your attention!
ANTON DE KOM UNIVERSITY OF SURINAME
Leysweg, POB 9212,
Paramaribo, Suriname
Phone 597 8715714 , FAX 597 495005
Email: [email protected]