+ All Categories
Home > Documents > 3. Precast Concrete Pavement

3. Precast Concrete Pavement

Date post: 03-Apr-2018
Category:
Upload: babjichetan
View: 228 times
Download: 0 times
Share this document with a friend

of 31

Transcript
  • 7/28/2019 3. Precast Concrete Pavement

    1/31

    PRECAST CONCRETE PAVEMENT

    CHAPTER-1

    INTRODUCTION

    1.1 PRECAST CONCRETE PAVEMENT

    Precast concrete is a form of construction, where concrete is cast in a reusable mould

    or "form" which is then cured in a controlled environment, transported to the construction site

    and lifted into place. In contrast, standard concrete is poured into site specific forms and

    cured on site. Precast stone is distinguished from precast concrete by using a fine aggregate

    in the mixture so the final product approaches the appearance of naturally occurring rock or

    stone.

    Precast pavement technology comprises new and innovative construction methods

    that can be used to meet the need for rapid pavement repair and construction. Precast

    pavement components are fabricated or assembled off-site, transported to the project site, and

    installed on a prepared foundation (existing pavement or re-graded foundation). The system

    components require minimal field curing time to achieve strength before opening to traffic.

    These systems are primarily used for rapid repair, rehabilitation, and reconstruction of bothasphalt and portland cement concrete (PCC) pavements in high-volume-traffic roadways. The

    precast technology can be used for intermittent repairs or full-scale, continuous rehabilitation.

    In intermittent repair of PCC pavement, isolated full-depth repairs at joints and cracks

    or full-panel replacements are conducted using precast concrete panels. The repairs are

    typically full-lane width. The process is similar for full-depth repairs and full-panel

    replacement. Key features of this application are slab panel seating and load transfer at joints.

    Use of precast concrete pavements for reconstruction and rehabilitation is a very

    viable alternative to conventional cast-in-place concrete pavement construction, especially in

    situations where high traffic volumes and consideration of the delay costs to users due to lane

    closures favor reconstruction and rehabilitation solutions that allow expedited opening to

    traffic. Precast concrete also offers the advantage of being factory made in a more

    controlled environment than cast-in-place construction and thus is potentially more durable

    and less susceptible to construction and material variability.

    Dept of Highway Technology, DSCE Page 1

    http://en.wikipedia.org/wiki/Concretehttp://en.wikipedia.org/wiki/Construction_aggregatehttp://en.wikipedia.org/wiki/Construction_aggregatehttp://en.wikipedia.org/wiki/Concrete
  • 7/28/2019 3. Precast Concrete Pavement

    2/31

    PRECAST CONCRETE PAVEMENT

    1.2 PAVEMENT TYPES

    Hard surfaced pavements are typically categorized into flexible and rigid pavements:

    1.2.1 FLEXIBLE PAVEMENTS:

    Those which are surfaced with bituminous (or asphalt) materials. These types of

    pavements are called "flexible" since the total pavement structure "bends" or "deflects" due

    to traffic loads. A flexible pavement structure is generally composed of several layers of

    materials which can accommodate this "flexing".

    1.2.2 RIGID PAVEMENTS:

    Those which are surfaced with portland cement concrete (PCC). These types of

    pavements are called "rigid" because they are substantially stiffer than flexible pavements

    due to PCC's high stiffness.

    Each of these pavement types distributes load over the subgrade in a different fashion.

    Rigid pavement, because of PCC's high stiffness, tends to distribute the load over a relatively

    wide area of subgrade. The concrete slab itself supplies most of a rigid pavement's structuralcapacity. Flexible pavement uses more flexible surface course and distributes loads over a

    smaller area. It relies on a combination of layers for transmitting load to the subgrade .

    This Guide focuses on flexible pavements. In general, both flexible and rigid

    pavements can be designed for long life (e.g., in excess of 30 years) with only minimal

    maintenance. Both types have been used for just about every classification of road. Certainly

    there are many different reasons for choosing one type of pavement or the other, some

    practical, some economical, and some political.

    Dept of Highway Technology, DSCE Page 2

    http://www.hawaiiasphalt.com/HAPI/modules/05_materials/05_asphalt.htmhttp://www.hawaiiasphalt.com/HAPI/modules/06_design_factors/06_subgrade.htmhttp://www.hawaiiasphalt.com/HAPI/modules/08_structural_design/08_pavement_structure.htm#surfacehttp://www.hawaiiasphalt.com/HAPI/modules/05_materials/05_asphalt.htmhttp://www.hawaiiasphalt.com/HAPI/modules/06_design_factors/06_subgrade.htmhttp://www.hawaiiasphalt.com/HAPI/modules/08_structural_design/08_pavement_structure.htm#surface
  • 7/28/2019 3. Precast Concrete Pavement

    3/31

    PRECAST CONCRETE PAVEMENT

    1.3 BENEFITS OF PRECAST PRESTRESSED CONCRETE

    PAVEMENT

    1.3.1 FASTER CONSTRUCTION:

    What do we mean by faster construction? We're not necessarily talking about how

    fast the pavement can be constructed, but rather how fast it can be opened to traffic.

    Conventional cast-in-place pavement requires several days of additional curing time after the

    concrete is placed before it is strong enough to withstand traffic loading. While "fast-setting"

    concrete mixtures have been developed for this purpose, these can be cost-prohibitive for

    large-scale pavement construction.

    1.3.2 REDUCED USER DELAY COSTS:

    What are user delay costs? These are costs to the drivers of the roadway that are

    directly attributable to congestion caused by construction activities. Increased fuel

    consumption, lost work time, increased vehicle wear and tear, and increased air pollution are

    just a few of these costs. The savings in user delay costs realized through limiting

    construction to only off-peak travel times (at night or over a weekend) can be substantial.

    This is where the primary economic benefit of precast pavement will be realized.

    1.3.3 IMPROVED DURABILITY AND PERFORMANCE:

    Precast concrete has a proven track record as a durable high-performance product for

    bridge and commercial building construction. This is the result of a high degree of quality

    control that can be achieved at a precast fabrication plant. High strength, low permeability

    concrete mixtures with a low water-cement ratio and uniform aggregate gradation are used

    routinely by precast fabrication plants. At most plants concrete batching and quality control

    is done on-site and the concrete is transported only a short distance from the batch plant to

    the forms, minimizing changes in concrete properties between the mixing and placing

    operations. What's more, precast fabrication plants offer tremendous flexibility over the

    curing operation. Precast concrete elements can be fabricated indoors, they can be wet-mat

    cured, steam cured, and curing can be maintained as long as necessary after casting.

    Problems that can plague cast-in-place pavement construction such as surface strength loss,

    "built-in" curling, and inadequate air entrainment, can all be eliminated with precast concrete

    Dept of Highway Technology, DSCE Page 3

  • 7/28/2019 3. Precast Concrete Pavement

    4/31

    PRECAST CONCRETE PAVEMENT

    1.3.4 WHY PRESTRESSED PRECAST PAVEMENT?

    Prestressing has a proven track record for enhancing the performance and durability

    of concrete structures. And though it has seen very limited use in pavements, there are

    clearly benefits of prestressed concrete pavement, such as...

    1.3.5 REDUCED CRACKING:

    While conventional pavements are "designed" to crack at specific locations or at

    regular intervals, in general cracking is not desirable. Cracks can spall, they can permit water

    to penetrate the underlying base, they can fault, and they can eventually lead to severe

    pavement failures such as punch outs. Prestressing helps to minimize or even eliminate

    cracking. By putting a pavement in compression there is less likelihood of cracking due to

    tensile stresses. What's more, the so-called "elasto-plastic" behavior of prestressed concrete

    will help keep any cracks that do form tightly closed.

    1.3.6 REDUCED SLAB THICKNESS:

    While the underlying pavement structure is also a factor, the primary controlling

    factor in pavement thickness design is the magnitude and number of wheel load repetitions on

    the pavement over its expected design life. For a given pavement support structure and a

    given wheel load, tensile stresses in a thinner pavement will be higher than those in a thicker

    pavement. These higher stresses wear out or fatigue a concrete pavement faster. Prestressing

    can be used to reduce the tensile stresses in a thinner pavement slab to those of a much

    thicker pavement slab, increasing the design life of the pavement.

    1.3.7 BRIDGING CAPABILITY:

    Prestressing gives the pavement a certain "bridging" capability that permits the

    pavement slab to span small voids and "soft" base materials beneath the pavement. This is

    critical for pavement removal and replacement operations that are limited to short

    (overnight) construction windows when it is often not possible to recondition or replace the

    underlying base material.

    Dept of Highway Technology, DSCE Page 4

  • 7/28/2019 3. Precast Concrete Pavement

    5/31

    PRECAST CONCRETE PAVEMENT

    CHAPTER-2

    PRECAST PAVEMENT CONCEPT

    The basic precast prestressed pavement concept consists of a series of individual

    precast panels that are post-tensioned together in the longitudinal direction after installation

    on site. Each panel can be pretensioned in the transverse direction (long axis of the panel)

    during fabrication, and ducts for longitudinal post-tensioning are cast into each of the panels.

    The basic features (typical) of the PPCP system are as follows:

    1. Panel size: up to 38 ft (11.6 m) wide, typically 10 ft (3 m) long, and 7 to 8 in. (178

    to 203 mm) thick (or as per design).

    2. Panel types: a. Base, joint, and central stressing panels (as originally developed).

    b. Base and joint stressing panels (as installed at a demonstration project in Missouri).

    3. Tongue-and-groove transverse epoxied joints.

    4. Post-tensioning details:

    a. 0.6-in. (15 mm) diameter 7-wire monostrand tendons typically spaced at 24 in.

    (600 mm).

    b. Tendon load: 75 percent of ultimate tendon load, typically.

    c. Prestress force: sufficient to ensure about 150 to 200 lbf/in2 (1.0 to 1.4 MPa)

    residual prestress at the mid-point of each series of prestressed panels.

    d. Grouted post-tensioning ducts.

    5. Expansion joint spacing: ~ 250 ft (76 m), typically.

    6. Base type:

    a. Hot-mix asphalt concrete base with polyethylene sheet over base or asphaltconcrete interlayer in the case of an overlay application.

    b. Permeable base (as used in the Missouri demonstration project).

    c. Lean concrete base (as used in the California demonstration project).

    d. Aggregate base (as used in the Iowa demonstration project).

    7. Injection of bedding grout to firmly seat panels (after post-tensioning).

    Dept of Highway Technology, DSCE Page 5

  • 7/28/2019 3. Precast Concrete Pavement

    6/31

    PRECAST CONCRETE PAVEMENT

    Figure 2.1. Cross section of the precast panels

    Figure 2.2. PPCP design details and panel types.

    Figure 2.2 illustrates the design concept underlying this precast pavement technology.

    The base panels make up the majority of the post-tensioned pavement section and are placed

    between the joint panels and central stressing panels, if used. All of the panels havecontinuous tongue-and-groove keyways along the transverse face of the panels (see figure

    2.3). The joint panels are located at the ends of each post-tensioned section of pavement. The

    joint panels contain dowelled expansion joints that allow the expansion and contraction

    movements of the post-tensioned section. The joint panels also contain the post-tensioning

    anchorage for the longitudinal post-tensioning tendons. The anchors are cast into the joint

    panels on either side of the expansion joint. Block outs or pockets cast into the joint panels

    provide access to the post-tensioning anchors. Figure 2.4 shows the placement of a panel on

    a prepared base.

    Dept of Highway Technology, DSCE Page 6

  • 7/28/2019 3. Precast Concrete Pavement

    7/31

    PRECAST CONCRETE PAVEMENT

    Figure 2.3. Tongue-and-groove keyway. Figure 2.4. PPCP panel being placed over

    polyethylene sheet placed over a base.

    When the central stressing panels are used, the post-tensioning strands are fed into the

    ducts at the large block outs cast into the central stressing panels. Strands are fed in either

    direction from each block out down to the anchors in the joint panels. The strands from

    either side of the block out are then coupled together and tensioned. The post-tensioning canalso be applied at the joint panels without use of the central stressing panels.

    2.1 PANEL ASSEMBLY:

    The basic precast prestressed pavement concept consists of a series of individual

    precast panels that are post-tensioned together in the longitudinal direction after installationon site. Each of the panels are pretensioned in the transverse direction (long axis of the

    panel) during fabrication, and ducts for longitudinal post-tensioning are cast into each of the

    panels. The basic panel layout consists of three types of panels.

    Dept of Highway Technology, DSCE Page 7

  • 7/28/2019 3. Precast Concrete Pavement

    8/31

    PRECAST CONCRETE PAVEMENT

    2.2 BASE PANELS:

    Base panels make up the majority of the post-tensioned pavement section and are

    placed between the joint panels and central stressing panels. All of the panels have

    continuous tongue and groove keyways along the edges of the panels. The pretensioning

    strands extend along the length (long axis) of the panels, and the post-tensioning ducts are

    oriented across the width (short axis) of the panels.

    Figure 2.5. Base Panel

    2.3 JOINT PANELS:

    The joint panels are located at the ends of each post-tensioned section of pavement.

    The joint panels contain dowelled expansion joints which "absorb" the expansion and

    contraction movements of the post-tensioned section. Each half of the joint panel is tied to

    the panels on either side of the actual expansion joint. The joint panels also contain the post-

    tensioning anchorage for the longitudinal post-tensioning tendons. The anchors are cast into

    the joint panels on either side of the expansion joint. Block outs or pockets cast into the joint

    panels provide access to the post-tensioning anchors.

    Dept of Highway Technology, DSCE Page 8

  • 7/28/2019 3. Precast Concrete Pavement

    9/31

    PRECAST CONCRETE PAVEMENT

    2.4 CENTRAL STRESSING PANELS:

    Post-tensioning is completed at the central stressing panels. The post-tensioning

    strands are fed into the ducts at the large block outs cast into the central stressing panels.Strands are fed in either direction from each block out down to the anchors in the joint

    panels. The strands from either side of the block out are then coupled together and tensioned.

    Figure 2.6. Joint Panels

    2.5 PANEL JOINTS:

    As described above, tongue and groove keyways are cast into the edges of the precast

    panels. These keyways help ensure vertical alignment between panels as the panels are

    installed. The keyways also provide temporary load transfer between panels prior to post-

    tensioning. It should be noted that the panels are not match-cast. The tolerances of the

    keyway dimensions are such that the panels can be fabricated on a long-line casting bed

    without the need to match-cast. What's more, match-casting requires the panels to be

    installed in a very specific sequence, whereas "standard" panels can be utilized for long-line

    fabrication.

    Dept of Highway Technology, DSCE Page 9

  • 7/28/2019 3. Precast Concrete Pavement

    10/31

    PRECAST CONCRETE PAVEMENT

    A highly viscous epoxy is normally applied to the keyways prior to assembling the

    panels. The epoxy acts as a lubricant during panel installation and also seals the joints

    between panels to prevent the intrusion of water and incompressibles. The epoxy also bonds

    the panels together so that they act as a continuous slab after post-tensioning.

    Figure 2.7 Panel Joints

    2.6 EXPANSION JOINTS:

    As described above, the joint panels contain the expansion joints at the end of each

    post-tensioned section of pavement. Up to four inches of movement can be expected at the

    expansion joints, so they must be robust and able to withstand repeated heavy wheel loading.

    Both armored joints (similar to those used for bridge decks) and plain dowelled joints have

    been utilized on projects to date. The type of joint will depend on the expected traffic loading

    and movement of the pavement slab. Regardless of the type of joint used, dowels across the

    joint are essential for providing load transfer.

    CHAPTER-3

    Dept of Highway Technology, DSCE Page 10

  • 7/28/2019 3. Precast Concrete Pavement

    11/31

    PRECAST CONCRETE PAVEMENT

    PANEL FABRICATION

    3.1 PROCEDURE

    The precast panels are fabricated at an established precast plant, preferably as close as

    possible to the installation site. For larger jobs, particularly in remote locations, it may be

    possible to set up a temporary precast bed near the jobsite. The concrete mixtures used are

    similar to those utilized for other precast prestressed elements and are not be restricted to

    "paving" mixtures. Steam curing, wet mat curing, or membrane curing are all options for

    precast pavement panels.

    The panels were fabricated on a wide flat steel casting table which was long enough

    to produce up to two panels end to end. Steel sideforms and bulkheads were custom made

    for the panels. The pretensioning strands extended through both panels, anchored at

    bulkheads at either end of the self-stressing casting bed. Bulkheads between the precast

    panels, bolted down to the casting bed, were used to hold the pretensioning strands at the

    proper elevation at the ends of the precast panels. Steel chairs were used to harp the strands

    within the precast panels to match the strand profile provided in the panel detail drawings.

    Figure.8 shows the forms as the pretensioning strands are threaded through the forms.

    In general, two base panels were cast each day. Panels were normally stripped from

    the forms in the morning and the bed was cleaned and set up for an afternoon pour. Joint

    panels required additional form set-up time due to the anchor blockouts and additional

    reinforcement and post- tensioning anchors. Joint panels were each cast in two halves on

    separate days.

    A separate sideform was used to hold the dowel bars in place and form the recess

    for the header material at the expansion joint. The first half of the joint panel was cast and

    steam cured, but the pretensioning strands were not released until after the second half had

    been subsequently cast and cured.

    3.2 PANEL TREATMENT

    Dept of Highway Technology, DSCE Page 11

  • 7/28/2019 3. Precast Concrete Pavement

    12/31

    PRECAST CONCRETE PAVEMENT

    3.2.1 REINFORCMENT

    Minimal mild-steel (non-prestressed) reinforcement was provided in the base

    panels. As the panel detail drawings in the Appendix show, only perimeter steel at the

    top and bottom of the panel was provided for the base panels. Joint panels also had

    perimeter steel, but were heavily reinforced with stirrups around the stressing pockets

    and post-tensioning anchors. Epoxy-coated grade 60 No. 4 deformed bars were specified

    for all non-prestressed reinforcement. For the joint panels abutting the existing cast-in-

    place pavement, the half of the panel not post-tensioned was reinforced with mild steel in

    the longitudinal direction. No. 6 epoxy-coated reinforcing bars spaced at 200 mm (8inches) on center provided approximately 0.65 percent steel for this portion of the

    precast panel. Figure 3.1 shows the reinforcement for the non-post-tensioned half of a

    joint panel prior to concrete placement.

    Figure 3.1. Reinforcement for the non-post-tensioned joint panel.

    3.2.2 PRETENSIONING

    Dept of Highway Technology, DSCE Page 12

  • 7/28/2019 3. Precast Concrete Pavement

    13/31

    PRECAST CONCRETE PAVEMENT

    All pretensioning steel was 13 mm (0.5 inch) diameter, Grade 270 low relaxation 7-

    wire strand. For the base panels, eight strands were required. The strands were spaced

    evenly across the width of the base panels and alternated above and below the post-

    tensioning ducts to minimize any prestress eccentricity. For the joint panels, the

    pretensioning strands were concentrated in the outer edges and along the expansion joint to

    avoid crossing through the post-tensioning blockouts. Twelve strands were specified for the

    joint panels for to provide additional flexural strength for handling panels with post-

    tensioning blockouts. For both the base panels and joint panels, the strands were

    maintained at a constant depth over the portion of the panel which was 200 mm (8 inches)

    or thicker (traffic lanes). However, in the shoulder regions of the panels, it was necessary to

    harp the strands slightly to follow the top surface of the panels.

    It should be noted that the pretensioning strands were only tensioned to 75 percent of

    theirultimate strength, rather than 80 percent assumed during the design process. While this

    will reduce the effective prestress in the panels, the lump-sum prestress loss assumed in the

    design calculations is likely very conservative anyway. Based on actual lifting and handling

    of the precast panels, the pretensioning level was clearly adequate to prevent cracking

    3.2.3 POST-TENSIONING

    Monostrand post-tensioning ducts with an inside diameter of 23 mm (0.9 inches)

    were used for the longitudinal post-tensioning tendons. The ducts were developed

    specifically for monostrand post-tensioning and are made of corrosion-proof polyethylene

    material. The ducts are ideal for monostrand bonded tendons, with ribs to facilitate bond

    with the concrete and two continuous channels along the length of the duct to facilitate the

    flow of grout. The ducts are flexible and required adequate chairing and the use of bar

    stiffeners inserted in the ducts during concrete placement to prevent sagging and bowing of

    the duct under the mass of fresh concrete.

    Encapsulated monostrand anchors were used for the post-tensioning anchors. The

    anchors were cast into the joint panels and bolted to the post-tensioning blockout formers.

    Dept of Highway Technology, DSCE Page 13

  • 7/28/2019 3. Precast Concrete Pavement

    14/31

    PRECAST CONCRETE PAVEMENT

    Grout ports were located just in front of the anchors and in every 5th base panel along the

    length of each post- tensioned section of pavement. Trumpeted openings and recesses for the

    foam gaskets were formed at the ends of the post-tensioning ducts in each panel using

    machined steel recess formers. Figure 3.2 shows the post-tensioning duct, anchor, and

    blockout former used in the joint panels.

    Figure 3.2. Post-tensioning duct, anchor, and blockout former in a joint panel.

    3.2.4 CONCRETE PLACEMENT, FINISHING, AND CURING

    Dept of Highway Technology, DSCE Page 14

  • 7/28/2019 3. Precast Concrete Pavement

    15/31

    PRECAST CONCRETE PAVEMENT

    The concrete mixture was transported from the batch plant to the forms. Concrete

    was placed in the forms in two lifts; the first filling the forms to the level of the post-

    tensioning ducts, and the second, immediately following the first, filling the forms to the top

    surface. The flowable nature of the mixture required only minimal vibration to consolidate

    the concrete around the reinforcement, ducts, and blockouts.

    A hand screed was used to initially strike off the concrete surface, flowed by a

    vibratory screed to achieve a uniform, smooth surface. An intermediate curing compound

    was sprayed over the surface between the hand screed and vibratory screed to minimize

    moisture loss from the large surface area of the fresh concrete. Immediately following the

    vibratory screed, a light broom texture was applied along the length of the panels (transverse

    to the direction of traffic flow). A carpet drag texture was specified in the original Job

    Special Provisions, but was changed to a broom finish after problems were experienced with

    the carpet drag. Figure 3.3 show the screeding and texturing operations.

    .

    Figure 3.3. Application of the light texture to the panel surface.

    After application of the surface textures,the panels were covered with tarps and

    steam cured overnight. The steam was generally turned off by 5 am at which time strength

    Dept of Highway Technology, DSCE Page 15

  • 7/28/2019 3. Precast Concrete Pavement

    16/31

    PRECAST CONCRETE PAVEMENT

    was checked. If the strength was adequate for release, the tarps were removed and the

    pretensioning strands de-tensioned. If strength was not adequate, the steam was turned

    back on for 1-2 hours until adequate strength had been achieved. While steam curing was

    used to achieve the necessary release strength overnight, some additional form of curing

    on the top surface and sides of the panels was required for a minimum of 72 hours after

    concrete placement or until the 28-day strength had been achieved. This requirement was

    satisfied by covering the panels with wet burlap and plastic sheeting for an additional 24

    hours after they were moved from the forms to the storage area, as shown in Figure 3.4.

    Figure 3.4. Curing and Storage.

    CHAPTER-4

    PAVEMENT CONSTRUCTION

    Dept of Highway Technology, DSCE Page 16

  • 7/28/2019 3. Precast Concrete Pavement

    17/31

    PRECAST CONCRETE PAVEMENT

    4.1 BASE PREPARATION

    The reconstructed base beneath the PPCP section consisted of 100 mm (4 inches) ofpermeable asphalt treated base over 100 mm (4 inches) of dense graded granular base. To

    better ensure that the precast panels would be properly supported and the polyethylene

    sheeting used as friction-reducing material beneath the precast panels was rolled out just

    prior to placement of each panel. Figure show the construction of the permeable base and

    the final surface.

    Figure 4.1. Construction of the permeable asphalt treated base.

    4.2PANEL INSTALLATION

    4.2.3 TRANSPORTATION AND STAGING

    Dept of Highway Technology, DSCE Page 17

  • 7/28/2019 3. Precast Concrete Pavement

    18/31

    PRECAST CONCRETE PAVEMENT

    Delivery of the precast panels to the site is a critical aspect of the installation process.

    Enough delivery trucks must be available to meet the required installation rate. Care must be

    taken during the delivery process to ensure that the panels are not damaged in any way during

    shipment

    The panels were transported to the job site on flat bed tractor trailers truck. The

    crawler crane used for panel installation was positioned on the base in front of the panel

    installation. Panel delivery trucks lined up on the existing pavement south of the project, then

    pulled onto the shoulder next to the PPCP section where the crane picked the panels off the

    truck and lowered them into place, as shown in Figure 4.2.

    Figure 4.2. Staging of delivery trucks and the installation crane.

    4.3 INSTALLATION PROCEDURE

    Prior to lifting each panel from the delivery truck, epoxy (segmental bridge adhesive)

    was applied to the mating faces of the panels, and the compressible foam gaskets were

    Dept of Highway Technology, DSCE Page 18

  • 7/28/2019 3. Precast Concrete Pavement

    19/31

    PRECAST CONCRETE PAVEMENT

    installed in the recess around each post-tensioning duct on the recessed keyway side of the

    panel. After the polyethylene sheeting was rolled out each panel was installed. In general,

    two precast panels were installed before moving the crane.

    A laser was used to align the precast panels to the centerline of the pavement. The

    laser was set on the panels already in place and aligned to nail heads marking the

    pavement centerline, pre- surveyed into the base. An alignment guide was installed in the

    post-tensioning duct at the centerline of each precast panel, and aligned the laser. Figure

    36 shows the alignment laser and the alignment guide installed in a panel.

    After two consecutive panels were installed, two temporary post-tensioning strands,

    located approximately at the quarter points, were fed through the panels. Post-tensioning

    rams were then used to temporarily post-tension the panels together from the face of the

    newly installed panels.

    Figure 4.3. Laser and alignment guide used to align the precast panels.

    4.4 POST- TENSIONING

    4.4.1 STRAND INSTALLATION

    Dept of Highway Technology, DSCE Page 19

  • 7/28/2019 3. Precast Concrete Pavement

    20/31

  • 7/28/2019 3. Precast Concrete Pavement

    21/31

    PRECAST CONCRETE PAVEMENT

    Both armored joints (similar to those used for bridge decks) and plain dowelled joints have

    been utilized on projects to date. The type of joint will depend on the expected traffic loading

    and movement of the pavement slab. Regardless of the type of joint used, dowels across the

    joint are essential for providing load transfer.

    4.4.4 FILLING POCKETS

    After completion of final longitudinal post-tensioning, the stressing pockets and mid-

    slab anchor sleeves were filled and finished flush with the pavement surface using a pea

    gravel concrete mixture. Subsequent diamond grinding of the pavement surface removed

    any roughness associated with the stressing pockets.

    4.5 TENDON GROUTING

    Grouting of the post-tensioning tendons was essentially the final step in the

    construction process, and was completed following post-tensioning and filling of the

    stressing pockets. The post-tensioning system used for precast prestressed pavement is a

    bonded post-tensioning system. Grouting not only provides an additional layer of corrosion

    protection for the post-tensioning strands, but also bonds the tendons to the pavement so that

    if it is necessary to remove a precast panel at a later time, the post-tensioning system will

    remain intact.

    In addition to tendon grouting, underslab grouting may also be required to fill any

    voids beneath the pavement. Grout ports can either be cast into the panels or drilled on site.

    Underslab grouting is essentially a "gravity" fed process as applying pressure can actually lift

    the pavement.

    Similarly to post-tensioning, grouting can be completed during a subsequent

    construction operation if time constraints do not permit grouting immediately following panel

    placement. Grouting should not be completed, however, until all post-tensioning tendons are

    stressed and the pockets in the joint panels are filled.

    Dept of Highway Technology, DSCE Page 21

  • 7/28/2019 3. Precast Concrete Pavement

    22/31

    PRECAST CONCRETE PAVEMENT

    4.6 DIAMOND GRINDING

    Diamond grinding to meet Interstate Highway smoothness requirements was

    expected. While the finished pavement surface was smooth enough to open to traffic ifnecessary, it did not meet smoothness specifications for concrete pavement. Diamond

    grinding was used to bring the pavement surface back into specification.

    No major surface repairs were required for the finished pavement. While a number of

    minor spalls were observed at the joints between panels, diamond grinding removed many of

    these spalls. Deeper spalls will be monitored over time so that repairs can be made if needed.

    Figure 4.5. Final pavement surface after diamond grinding.

    4.7 OPEN TO TRAFFIC:

    Precast pavement can be opened to traffic as soon as the panels are installed. Post-

    tensioning and grouting operations can be completed during a subsequent operation if

    necessary. The surface will be smooth enough to open to traffic and can be diamond ground

    during a subsequent operation if necessary.

    Dept of Highway Technology, DSCE Page 22

  • 7/28/2019 3. Precast Concrete Pavement

    23/31

    PRECAST CONCRETE PAVEMENT

    4.8 RECOMMENDATIONS FOR FUTURE CONSTRUCTION

    This demonstration project showed once again the adaption of PPCP technology to

    specific project needs. Future projects should focus on applying PPCP technology under

    circumstances where lane closures for construction are severely limited, such as busy urban

    corridors. This type of project will require very careful planning and preparation to ensure

    that none of the issues encountered on this initial demonstration project will occur during

    short construction window projects.

    Figure 4.6. Finished precast pavement after opening to traffic.

    CHAPTER-5

    CASE STUDIES

    CASE STUDY-1

    Dept of Highway Technology, DSCE Page 23

  • 7/28/2019 3. Precast Concrete Pavement

    24/31

    PRECAST CONCRETE PAVEMENT

    5.1 THE TEXAS PILOT PROJECT

    Figure 5.1 Georgetown PPCP project layout.

    The first PPCP project was constructed in Georgetown, Texas, during 2001 (Merritt

    2001). Texas DOT placed approximately 2,300 ft (700 m) of two-lane pavement (plus

    shoulders) on the frontage road along I-35. The project layout and panel systems used are

    shown in figure 6.1. The project details are as follows:

    Constructed: Fall 2001

    Project location: Northbound I-35 frontage road near Georgetown, Texas

    Project length: 2,300 ft (701 m) (2 lanes plus shoulders)

    Panel dimensions: 10 ft x 36 ft (3.1 m x 11.0 m), 10 ft x 20 ft (3.1 m x 6.1 m), and 10

    ft x 16 ft (3 m x 4.9 m)

    Panel thickness: 8 in. (200 mm)

    Number of panels: 339

    Dept of Highway Technology, DSCE Page 24

  • 7/28/2019 3. Precast Concrete Pavement

    25/31

    PRECAST CONCRETE PAVEMENT

    Number of post-tensioned sections: 7 at 250 ft (76.2 m), 1 at 225 ft (68.6 m), 1 at

    325 ft (99.1 m)

    Panel installation rate: 25 panels/6 hours

    Features: Both full-width and partial-width construction. Project was the first

    application of precast prestressed concrete pavement on a large scale.

    For this project, it was decided to use both full-width (36 ft [11 m]) and partial-width

    (16 ft and 20 ft [5 m and 6 m]) panels for the frontage road to test the concept for partial-

    width panel construction. The partial-width panels were tied together transversely through

    post-tensioning with an additional post-tensioning duct cast into each of the partial-width

    panels. The precast, pretensioned panels were placed over a well-finished hot-mix asphalt

    leveling course overlain with polyethylene sheets and then post-tensioned together in the

    longitudinal direction. The tongue-and-groove connection at the transverse joints ensured

    satisfactory vertical alignment during installation.

    As the contractor became more familiar with the construction process, approximately

    25 panelsequaling 250 ft (76 m) of pavementwere installed

    Figure 5.1 Georgetown PPCP project layout. in a 6-hour period. Texas DOT found

    that post-tensioning, completed after the panels were installed, generally took just a few

    hours for each section of pavement. Aside from demonstrating the efficacy of placing the

    slabs on grade, the Georgetown project demonstrated the viability of post-tensioning the

    panels together in place. The project also showed that match-casting, which is commonly

    used for precast segmental bridge construction, was not required to ensure a tight fit

    between panels and to align the post-tensioning ducts. Because match casting is not

    necessary, the manufacturer can fabricate the panels faster, and shipment and installation

    are simplified.

    The Georgetown pilot project presented many challenges for precast pavement

    implementation (Merritt 2001). The most difficult aspect of the project was considered to be

    the meshing of precast concrete and concrete pavement specifications.

    This required flexibility on the part of both the precast supplier and Texas DOT. This

    pilot project also represented unknown territory for the contractor, precast supplier, and

    Texas DOT. Flexibility and a willingness to develop new techniques on the part of all parties

    Dept of Highway Technology, DSCE Page 25

  • 7/28/2019 3. Precast Concrete Pavement

    26/31

    PRECAST CONCRETE PAVEMENT

    were essential for the success of this project. After almost 7 years (as of November 2008), the

    project is performing well and no maintenance-related issues have been reported.

    Figure 5.2. Installation of the precast prestressed concrete pavement system in

    Georgetown, Texas.

    CASE STUDY-2

    6.2 THE CALIFORNIA DEMONSTRATION PROJECT

    Dept of Highway Technology, DSCE Page 26

  • 7/28/2019 3. Precast Concrete Pavement

    27/31

    PRECAST CONCRETE PAVEMENT

    The Caltrans demonstration project used the PPCP system as a part of the widening

    project on I-10 to provide high-occupancy vehicle lanes and reduce traffic congestion. Most

    of the construction work was completed at night. The construction added 27 ft (8 m) of traffic

    lanes and 10 ft (3 m) of shoulder to the existing lanes on the eastbound direction. The project

    details are as follows:

    Constructed: April 2004

    Project location: Eastbound I-10, El Monte, California

    Project length: 248 ft (76 m) (2 lanes plus shoulder)

    Panel dimensions: 8 ft x 37 ft (2.4 x 11.3 m)

    Panel thickness: 10 to 13 in. (254 to 330 mm)

    Number of panels: 31

    Number of post-tensioned sections: 2 at 124 ft (37.8 m)

    Panel installation rate: 15 panels/3 hours

    Features: Nighttime construction. Change in cross slope cast into the panel surface.

    Photographs of the installation are shown in Figure 6. The project was located on a

    section of the Interstate that had no change in vertical curvature and very minimal horizontal

    curvature. The longitudinal geometry of the pavement was simple, but the pavement cross

    section was more complex, with a change in cross slope from 1.5 percent in the traffic lanes

    to 5 percent in the shoulders, which required variable thickness in the panel.

    CASE STUDY-3

    6.3 THE MISSOURI DEMONSTRATION PROJECT:

    Dept of Highway Technology, DSCE Page 27

  • 7/28/2019 3. Precast Concrete Pavement

    28/31

    PRECAST CONCRETE PAVEMENT

    The Missouri DOT evaluated the feasibility of using the PPCP as an alternative

    solution for rapid pavement construction and rehabilitation. The project details are as follows:

    Completed: December 2005

    Project location:Northbound I-57 near Sikeston, Missouri (~ 10 mi (16 km) north of

    I-55/I-57 interchange)

    Project length: 1,010 ft (307.9 m) (2 lanes plus shoulders)

    Panel dimensions: 10 ft x 38 ft (3.0 m x 11.6 m)

    Panel thickness: 5.7511 in. (146280 mm)

    Number of panels: 101

    Number of post-tensioned sections: 4 at 250 ft (76.2 m)

    Panel installation rate: 12 panels/6 hours

    Features: Pavement crown cast into the panel surface. Non continuous keyways

    between panels

    The existing pavement was a jointed reinforced concrete pavement with 61.5-ft (18.8

    m) joint spacing. The cross section consisted of an 8-in. (203 mm) slab resting on a 4-in.

    (102 mm) granular base. The new PCPP cross section consists of a concrete slab of variable

    thickness ranging from 10.9 in. (275 mm) at the peak crown to 7 in. (178 mm) at the edge of

    the inside shoulder and 5.6 in. (142 mm) at the edge of the outside shoulder. The variable

    thickness was necessary to accommodate the 2 percent crown. The PCPP slab rests on a 4-

    in. (102 mm) permeable asphalt base. The panels were fabricated in Memphis and

    transported to the project site, a distance of over 200 miles (320 km). Two panels were

    fabricated each day. Figure 7 illustrates the construction process of the precast panels.

    A few panels exhibited full-depth hairline longitudinal cracking at the fabrication

    plant. It is believed that the panels may have experienced thermal shock during removal of

    the panels from the forms. The temperature and strain data collected during the fabrication

    process did indicate high and rapid changes in concrete temperature during fabrication.

    Dept of Highway Technology, DSCE Page 28

  • 7/28/2019 3. Precast Concrete Pavement

    29/31

    PRECAST CONCRETE PAVEMENT

    CHAPTER-6

    CONCLUSION

    Dept of Highway Technology, DSCE Page 29

  • 7/28/2019 3. Precast Concrete Pavement

    30/31

    PRECAST CONCRETE PAVEMENT

    1. As discussed above, precast concrete pavement technology is ready for

    implementation, excellent concrete quality with respect to strength and durability and

    with respect to continuous applications.

    2. The short-term performance of the installed PPCP systems indicates that PPCP

    systems can provide rapid reconstruction and rehabilitation that will be durable.

    3. The quality of the concrete used for the precast panels appears to meet the

    expectations for durable concrete and there is no evidence of early age concrete

    failures.

    4. Precast pavements may have a higher first cost, the rapid installation that minimizes

    lane closures and the long-term durability can easily offset the higher initial costs.

    5. It is expected that innovations in this technology will ensure a permanent place for the

    application of the precast concretepavement technology for durable, rapid repair and

    rehabilitation of existing pavements and will help reduce the cost of panel fabrication

    and installation.

    6. Rapid construction techniques can significantly minimize the impact on the driving

    public, as lane closures and traffic congestion are kept to a minimum.

    CHAPTER-7

    REFERENCES

    1. FHWA Concrete Pavement Technology Program Update:

    Precast Prestressed Concrete Pavement - CPTP Project Update.

    Dept of Highway Technology, DSCE Page 30

    http://www.fhwa.dot.gov/pavement/concrete/cptu305.cfmhttp://www.fhwa.dot.gov/pavement/concrete/cptu305.cfmhttp://www.fhwa.dot.gov/pavement/concrete/cptu305.cfmhttp://www.fhwa.dot.gov/pavement/concrete/cptu305.cfm
  • 7/28/2019 3. Precast Concrete Pavement

    31/31

    PRECAST CONCRETE PAVEMENT

    2.FHWA Concrete Pavement Technology Program.

    3. MoDOT/FHWA Precast Prestressed Concrete Pavement Showcasing Workshop update.

    4. Shiraz Tayabji, Dan Ye, and Neeraj Buch.,Precast concrete pavements Technology

    overview and technical considerations Journal.

    5. Tinu Mishra, Phil French, and Ziad Sakkal., Engineering a better road: Use of two-way

    prestressed precast concrete pavement for rapid rehabilitation journal.

    6. Shabbir Hossain and Celik Ozyildirim., Evaluation of Concrete Pavement Repair Using

    Precast Technology Journal.

    7. Shiraz Tayabji and Neeraj Buch., Precast Concrete Pavement Technology Journal.

    http://www.fhwa.dot.gov/pavement/concrete/index.cfmhttp://www.fhwa.dot.gov/pavement/concrete/index.cfm

Recommended