+ All Categories
Home > Documents > 3.05 Advances in Power Quality Requirements for … in Power Quality Requirements for RPPs Company...

3.05 Advances in Power Quality Requirements for … in Power Quality Requirements for RPPs Company...

Date post: 23-May-2018
Category:
Upload: trankhanh
View: 215 times
Download: 2 times
Share this document with a friend
26
Electricity Supply to Africa and Developing Economies: Challenges and Opportunities Gerhard Botha North-West University Paper Number: 3.05 Session Number: 3 15 November 2017 Advances in Power Quality Requirements for RPPs Company Logo (this slide only)
Transcript

Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

Gerhard BothaNorth-West University

Paper Number: 3.05

Session Number: 3

15 November 2017

Advances in Power Quality

Requirements for RPPs

Company

Logo (this

slide only)

Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

Overview

• Background

• Basic requirements

• Concerns from stakeholders

• Context of concerns

• Apportioning

• Impedance envelope

• Network information

• Assessment clarifications and methods

• Conclusions

Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

Background

• REIPPPP since 2011

• RPP Grid Code first published 2012

• Management of PQ

– Apportionment

– Monitoring and enforcing

• Power Quality requirements

– Concerns from developers

– Harmonic

Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

Background

• First RPPs nearing completion

• Consultants engaged Eskom:

– PQ requirements were unclear to consultants

– difficult to prove and achieve

• Harmonics Working Group established

Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

Basic Requirements

• The basic PQ requirements provided for in the

grid code are summarised as follows:

– Which parameters are to be regulated

– Assessment shall be done at the POC

– Responsibilities of stakeholders

Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

Basic Requirements

• Stakeholder responsibilities:

• NSP:

– Calculate appropriate emission limits

– Define the network conditions, e.g.

– PQ levels

– Network characteristics

• Fault levels

• Three-times impedance envelope

• RPP:

– Ensure the RPP is appropriately designed and operated

Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

Concerns: RPP Developers

• Grid code requirements were unclear

• Few consultants had sufficient PQ background

• Connection agreement terms

– E.g. harmonic emission mixture of tables and text

• Different requirements to e.g. European countries

– IEC 61000 apportioning not universally applied

• Compliance is based on the rms harmonic currents

– Absorb harmonic voltage and current (beneficial)

– Deemed non-compliant

• Three-times impedance criticized

Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

Concerns: NSP

• NSP is legally responsible

�Risk

• PQ at each customer point of supply

– Limiting the impact of any customer on PQ

(generally via contracts such as the CUOSA)

– Coordinating the combined impact of customers at a point of common coupling (PCC)

– Monitoring the PQ at all PCCs

– Limiting the network’s impact on PQ to customers

– Communicating to customers on all relevant aspects

Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

Context of Concerns

• Eskom had reasonable experience

• But

• Number of new challenges brought by RPPs

• Handful of specialists with experience in contracting

• Municipalities lack – staff

– network information for detailed studies

• Processes to take into account

�Easy to implement by inexperienced staff.

Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

Context of Concerns

• Framework for customer contracts– Flexible

– Negotiable

– Managed over time

• Major differences between South African and European networks, e.g. – base load generation location

– transmission line lengths

– overhead vs. underground (affecting system capacitance)

– use of shunt capacitors

– interconnections to other countries

• These factors affect the typical system strength and harmonic impedance.

1.1 million82 million

Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

Context of Concerns

• RPPs connecting at relatively weak locations in

the network

• Short-circuit ratio ≈ 3 times

• European-based rules and regulations

• Not realistic for South Africa

Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

Apportioning: A brief history

• IEC/TR 61000-3-6/7 and 13

• Describe principles for fair allocation

• Customers and network contribute

Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

Apportioning: A brief history

0

0.05

0.1

0.15

0.2

0.25

0.3

0.35

0.4

0.45

0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 2

Pro

ba

bil

ity

of

Exce

ed

ing

a v

alu

e

Normalised QOS level

System

Performance

Equipment

Performance

Compatibility

LevelPlanning Level

Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

Apportioning: A brief history

• Edition 1

– Measure and allocate

remaining part

• Edition 2

– Allocate proportionally

– Legacy customers?

Compatibility LevelPlanning Level

Background

Available to

share

New

Future

Customers

Compatibility LevelPlanning Level

Upstream

This busbarFuture

Existing

New

Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

Impedance Envelope: Allowance

Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

Impedance Envelope Simulations

Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

Impedance Envelope Simulations

Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

Network Information Provided

Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

Network Information Provided

Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

Assessment Clarifications

• Basic Assessment

– NRS 048-2

– One week

– 95th percentile

– Representative

-4 -2 0 2 40

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1Gaussian / Normal CDF

Mag

nitu

de

Random variable

-4 -2 0 2 40

0.05

0.1

0.15

0.2

0.25

0.3

0.35

0.4

0.45

0.5Gaussian / Normal PDF

Mag

nitu

de

Random variable

Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

Assessment Clarifications

• Harmonic Voltage vs. Harmonic Current

– IEC 61000-3-6/7/13

– Voltage emission limits

– Current and Ohm’s law

– Network changes

– Impedance envelope

– Current driving force and

– Critical assessment criterion

Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

Assessment Clarifications

• CT and VT accuracy

• Specification at fundamental

– VTs up to 25th harmonic

• CT ratio error: 0.2%

• Emission limit minimum

– Voltage: 0.1%

– Current: 0.1 A → 0.1%

Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

Assessment Methods

• The impedance slope method

• Negative correlation: harmonic current and voltage

• Zero harmonic voltage measured throughout the measurement period– allowing for up to 300% of the current emission limit

• The impedance scaling method– measured harmonic voltage scaled

– ratio of the three-times impedance envelope vs. the simulated system impedance

• Group harmonic distortion levels– individual harmonic emissions may exceed the emission

limit by up to 50%.

Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

Summary

• RPPGC version 2.9 towards the end of 2016

• Key improvements are:

– the clarification of the requirements

– high-level guidance for simulating and measuring compliance

– relaxation of emission limits under certain conditions

– emission limits for rapid voltage changes and inter-harmonics have been removed

– group harmonic emission limit was introduced with allowance up to 150% of individual emission limits when the group harmonic emission limit is met.

– preferred analysis methods from the CIGRE C4.109 brochure are discussed

– without restricting the analysis methods that may be used

Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

Conclusions

• Significant learning curve

• Guideline available

• PQ requirements and guideline not yet perfect

• Further research and analysis

• Updates will be published as better solutions are

found

Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

• Thank you

• Acknowledgements:

– Brandon Peterson, Hennie Mostert, Ulrich Minnaar

– Consultants who contributed to the WG and

Guideline


Recommended