31 October 2017
CONTENTS
01 Nuclear Power
in Korea Challenges 03
Efforts for
Nuclear Safety
02
3
Nuclear Power
in Korea 1
[ 본사 ]
2 Company Profile
President
Prime Minister
Ministry of Trade,
Industry and Energy
Ministry of Strategy
And Finance
Ministry of Science,
ICT and Future Planning
Nuclear Safety and
Security Commission
National Assembly
KHNP
Operation
KEPCO E&C
Design &
Engineering
KEPCO NF
Nuclear Fuel
Supply
KEPCO KPS
Maintenance Construction
Doosan
Heavy Industry
Equipment
Supply
Constructors
KHNP (Operation &
Construction management)
Regulatory Body
Nuclear R&D Nuclear Industry
Civil Company
[ 본사 ]
2 Company Profile
AA (S&P), Aa2(Moody’s)
Hanbit Site
Kori & Saeul Site
Wolsong Site
Hanul Site
19.8%
31.4%
32.2%
3.6%
13.0%
Nuclear
161,995GWh
Coal
Gas
Installed Capacity (June 2017)
30.0%
39.6%
22.3%
2.6% 5.5%
Nuclear
22,529MW
Coal
Gas
Renewables
(incl. Hydro)
Oil
※ Source : The Monthly Report on Major Electric Power Statistics (KEPCO)
Power Generation (end of 2016)
Renewables
(incl. Hydro)
Oil
39.6%
7
Efforts
for Nuclear Safety 2
[ 본사 ]
2 Company Profile
APR1400
APR+
Type PWR
Life 40 Years
Output 1,000 MWe
Seismic SSE 0.2g
Type PWR
Life 60 Years
Output 1,400 MWe
Seismic SSE 0.3g
Type PWR
Life 60 Years
Output 1,500 MWe
Seismic SSE 0.3g
EU-APR
Acquisition of EUR certification (’17.10.9)
OPR1000
US-APR
NRC Design certification in process
The efforts to strengthen the nuclear safety in Korea are on a same line with the history of reactor development.
Safety Enhancement
[ 본사 ]
2 Company Profile
[ 본사 ]
2 Company Profile
Shin-Hanul Unit 1&2
- Capacity: 1,400 x 2
- Reactor type: PWR
(APR1400)
- Unit 1: Preparing for HFT
- Unit 2: Initial commissioning
- Progress rate: 95.29%
Shin-Kori Unit 5&6
- Capacity: 1,400 x 2
- Reactor type: PWR
(APR1400)
- Unit 5: Excavation work on
Intake/Drain
- Unit 6: Ground excavation
- Progress rate: 29.93%
[ 본사 ]
2 Company Profile
Barakah Unit 1~4 (APR1400 x 4)
< EPC Progress rate >
- Unit 1&2: 94%
- Unit 3&4: 68%
- Total : 83% ※ Source : ENEC homepage
12
Challenges 3
2 Company Profile
Improve Operation/ Equipment Reliability
Enhance
Safety
Culture
Expand
Investment in
Safety
Safety First Policy Enhancing Nuclear Security
Collaborating with
Government & Regulator & Operators
Raising Awareness to Nuclear Security
Maintaining
Independent
IT System
Declaration for Nuclear Safety Charter
2 Company Profile
Paradigm
Shift 4.5 Decision by
Government
Social
Consensus
Securing Public
Acceptance through
transparency and
accurate information is
a shortcut to enhance
the Nuclear Safety.
Fulfilling Social Responsibility
Trans-
parency
Cooperation
with Local
Communities
Acceptance
of
Local opinion
Safety
First
Operation
Boost
Local
Economy
2 Company Profile
Saturation of on-site storage in Korea
Developing NPP D&D Technologies
Approval for decommissioning /
Preparation for decommissioning plan
Site
restoration
Decommissioning
of S.S.C
Shutdown
(June 2017)
Preparation of
decommissioning plan
Public hearing
with residents
Request
approval for DP
Approval of DP
SF transfer complete
Termination of
operation approval
Saturation
of
on-site storage
Wolsong
Hanbit/Kori Hanul Shin wolsong
2 Company Profile
Decommissioning
HRD for
Nuclear
Power
Plants
New Build
Life
Extension
Safe
Operation
20~31 May, 2018, Gyeongju in Korea
2 Company Profile
KEPCO