wagman.com 33 rd & St. Paul Street Wagman’s Geotechnical Construcon group provided services for an earth retenon system in Balmore, MD, including ebacks, rakers with heel blocks, walers and bracing and e downs for a new apartment building with commercial space. Wagman successfully removed the top four feet of the earth retenon system. Addionally, edowns were installed into the mat slab foundaon for the elevator. The permanent anchors were drilled and grouted to 40 feet. The completed project will offer 157 apartments for Johns Hopkins University students, 31,500 SF of commerical space and a parking structure with 162 spaces for use by both tenants and the public. Addionally, a grocery store and pharmacy is planned for development. Project 33 rd St. Paul Street Location Baltimore, MD Project Type Micropiles, Sheeting & Shoring Construction Costs $508,000 Owner Hopkins Village, LLC Duration April 2015 - June 2015 KEY CHALLENGES & PROJECT DETAILS Installaon of the piles and ebacks was challenging due to the gneiss bedrock underlying the site at shallow depths. Drilling was performed at an angle so there was no damage to the caissons that were drilled prior to the start of Wagman’s work.
Transcript
Page 1: 33rd and St Paul

wagman.com

33rd & St. Paul Street

Wagman’s Geotechnical Construction group provided services for an earth retention system in Baltimore, MD, including tiebacks, rakers with heel blocks, walers and bracing and tie downs for a new apartment building with commercial space. Wagman successfully removed the top four feet of the earth retention system. Additionally, tiedowns were installed into the mat slab foundation for the elevator. The permanent anchors were drilled and grouted to 40 feet.

The completed project will offer 157 apartments for Johns Hopkins University students, 31,500 SF of commerical space and a parking structure with 162 spaces for use by both tenants and the public. Additionally, a grocery store and pharmacy is planned for development.

Project 33rd St. Paul Street

Location Baltimore, MD

Project Type Micropiles, Sheeting & Shoring

Construction Costs $508,000

Owner Hopkins Village, LLC

Duration April 2015 - June 2015

KEY CHALLENGES & PROJECT DETAILS• Installation of the piles and tiebacks was challenging due to the gneiss bedrock underlying the site at shallow depths. • Drilling was performed at an angle so there was no damage to the caissons that were drilled prior to the start of Wagman’s

work.