+ All Categories
Home > Documents > 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile...

3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile...

Date post: 27-Aug-2021
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
44
1 | ASD774-D Operating & Maintenance Manual 3UK RFC Bowler Cabinet Operation & Maintenance Manual ASD774-D
Transcript
Page 1: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

1 | ASD774-D

Operating & Maintenance Manual

3UK RFC Bowler Cabinet

Operation & Maintenance

Manual

ASD774-D

Page 2: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

2 | ASD774-D

Operating & Maintenance Manual

Contents 1 Introduction .................................................................................................................................................................................... 5

1.1 Authorship .............................................................................................................................................................................. 5

1.2 Amendment Record ............................................................................................................................................................ 5

1.3 Health and Safety ................................................................................................................................................................ 5

1.4 Introduction and Scope ..................................................................................................................................................... 5

2 General Description...................................................................................................................................................................... 6

2.1 Overview.................................................................................................................................................................................. 6

2.2 Quality Assurance ................................................................................................................................................................ 6

2.3 Mechanical Information .................................................................................................................................................... 6

2.4 Dimensions ............................................................................................................................................................................. 7

2.5 Finish ......................................................................................................................................................................................... 7

2.6 Ingress Protection ................................................................................................................................................................ 7

2.7 Lifting........................................................................................................................................................................................ 7

2.8 Mounting ................................................................................................................................................................................ 7

2.9 Electrical .................................................................................................................................................................................. 8

2.10 Cable and Feeder Identification ..................................................................................................................................... 8

2.11 Cable Entry ............................................................................................................................................................................. 8

2.12 Earthing ................................................................................................................................................................................... 8

2.13 Thermal Management ........................................................................................................................................................ 8

2.14 Order Part Numbers ........................................................................................................................................................... 8

3 Logistics ......................................................................................................................................................................................... 10

3.1 Handling Information ...................................................................................................................................................... 10

3.2 Dimensions .......................................................................................................................................................................... 10

3.3 Lifting Slings ....................................................................................................................................................................... 10

3.4 Lifting Lugs .......................................................................................................................................................................... 10

3.5 Assessment for Lifting ..................................................................................................................................................... 10

3.6 Details for Forklift Handling .......................................................................................................................................... 10

3.7 Transportation.................................................................................................................................................................... 10

4 Alarms Information ................................................................................................................................................................... 11

4.1 Thermal Management Alarms ..................................................................................................................................... 12

5 Operating Information ............................................................................................................................................................. 13

5.1 Cabinet Overview .............................................................................................................................................................. 13

5.2 Door Locks ........................................................................................................................................................................... 14

Page 3: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

3 | ASD774-D

Operating & Maintenance Manual

5.3 Door Stays ........................................................................................................................................................................... 14

5.4 Lightning Protection ........................................................................................................................................................ 15

5.5 Equipment Earth Bar ........................................................................................................................................................ 15

5.6 Thermal Management System ..................................................................................................................................... 16

6 Maintenance Information ....................................................................................................................................................... 17

6.1 Mechanical Schedule ....................................................................................................................................................... 17

6.2 Door Hinges ........................................................................................................................................................................ 17

6.3 Door Seals............................................................................................................................................................................ 17

6.4 Paintwork ............................................................................................................................................................................. 17

6.4.1 Preparation ................................................................................................................................................................. 17

6.4.2 Priming ........................................................................................................................................................................ 17

6.4.3 Finish ............................................................................................................................................................................ 17

6.5 Fan Controller ..................................................................................................................................................................... 18

6.6 Fan Module ......................................................................................................................................................................... 19

7 Installation Information ........................................................................................................................................................... 20

7.1 RRU Installation ................................................................................................................................................................. 20

7.2 Template Installation ....................................................................................................................................................... 22

7.3 Combiner Installation ...................................................................................................................................................... 23

8 Huawei Version ........................................................................................................................................................................... 25

8.1 DC Distribution .................................................................................................................................................................. 26

9 Ericsson Version .......................................................................................................................................................................... 27

9.1 DC Distribution .................................................................................................................................................................. 28

10 Appendix A – Additional Reference Documents ....................................................................................................... 29

11 Appendix B – Paint Specifications ................................................................................................................................... 30

12 Appendix C – Layout Drawing G-100875 ..................................................................................................................... 31

13 Appendix D – Layout Drawing G-100903 ..................................................................................................................... 32

14 Appendix E – Lift Diagram ................................................................................................................................................. 33

15 Appendix F – Fitting to Existing Huawei Root ............................................................................................................ 34

16 Appendix G – Fitting to Bowler Root ............................................................................................................................. 37

17 Appendix H – Fan Specification ....................................................................................................................................... 40

18 Appendix I – Noise Data ..................................................................................................................................................... 41

19 Appendix J – Spare Parts List ............................................................................................................................................ 43

Page 4: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

4 | ASD774-D

Operating & Maintenance Manual

Table of Figures

Figure 1: Cabinet Dimensions ............................................................................................................................................................ 7

Figure 2: Krone Connections ........................................................................................................................................................... 11

Figure 3: Huawei Bowler Overview ............................................................................................................................................... 13

Figure 4: Ericsson Bowler Overview .............................................................................................................................................. 13

Figure 5: Swing Handle Lock ........................................................................................................................................................... 14

Figure 6: Stay in Open Position...................................................................................................................................................... 14

Figure 7: Closing Door Stay ............................................................................................................................................................. 14

Figure 8: Lightning Protection Point ............................................................................................................................................ 15

Figure 9: Equipment Earth Bar ........................................................................................................................................................ 15

Figure 10: Fan Controller Position ................................................................................................................................................ 16

Figure 11: Fan Controller .................................................................................................................................................................. 18

Figure 12: Fan Connections ............................................................................................................................................................. 19

Figure 13: Removing Fan Module 1 ............................................................................................................................................. 19

Figure 14: Removing Fan Module 2 ............................................................................................................................................. 19

Figure 15: Radio Mounting Brackets ............................................................................................................................................ 20

Figure 16: Radio Bracket Fitting ..................................................................................................................................................... 20

Figure 17: Radio Mount Positions ................................................................................................................................................. 20

Figure 18: Location on LH Radio Mounts .................................................................................................................................. 21

Figure 19: Location on RH Radio Mounts .................................................................................................................................. 21

Figure 20: Radio Final Position ....................................................................................................................................................... 21

Figure 21: Radio Template ............................................................................................................................................................... 22

Figure 22: Combiner Template ...................................................................................................................................................... 22

Figure 23: CommScope Combiners .............................................................................................................................................. 23

Figure 24: Kathrein Combiners....................................................................................................................................................... 23

Figure 25: Radio Design Combiners ............................................................................................................................................. 23

Figure 26: Combiners in Position .................................................................................................................................................. 24

Figure 27: Huawei Configuration .................................................................................................................................................. 25

Figure 28: Ericsson Configuration ................................................................................................................................................. 27

Figure 29: Lifting Diagram ............................................................................................................................................................... 33

Figure 30: Transfer Plinth Installation .......................................................................................................................................... 34

Figure 31: Duct Positions (Huawei)............................................................................................................................................... 35

Figure 32: Bowler Root Installation .............................................................................................................................................. 37

Figure 33: Duct Positions (Ericsson) ............................................................................................................................................. 38

Figure 34: Fan Performance ............................................................................................................................................................ 40

Page 5: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

5 | ASD774-D

Operating & Maintenance Manual

1 Introduction

1.1 Authorship

Original Author – Dipen Rai 19/05/2020

Original Approver – David Streets 19/05/2020

1.2 Amendment Record

Date Document Reference Issue Raised Revision Details Amended By

19/05/2020 Full Document A Original Issue D Rai

26/05/2020 Section 6, 11, & 13 B Cabinet Configuration Added D Rai

17/06/2020 Section 2, 6 & 12 C Electrical Schedule Added D Rai

24/11/2020 Full Document D Ericsson Configuration Added T Petch

1.3 Health and Safety

The Health and Safety at Work Act 1974 places a duty upon employers to provide such information,

instruction, training and supervision as is necessary to ensure, as far as is reasonably practicable, the health

and safety at work of their employees.

We have ensured that the CommScope equipment has been designed and constructed to be safe and

without risk to health, providing that statutory health and safety regulations are adhered to and that the

equipment is handled and maintained in accordance with the supplier instructions.

Correct maintenance procedures and all necessary safety precautions must always be used.

It is important that the personnel, using this document, are aware of both their employers' safety

procedures and the specific regulations to be observed when working with equipment and materials

covered by this manual.

1.4 Introduction and Scope

This manual provides information on the operation of the CommScope 3UK RFC Bowler Cabinet

manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G

UK (H3G).

CommScope reserves the right to modify, add or delete any part of this manual in accordance with product

changes or improvement. Every effort has been made to ensure that all information in this manual is

correct, however CommScope cannot be held responsible for errors or omissions. Should alterations be

required within the scope of the manual, the manual will be reissued as appropriate.

Operatives including mechanical and electrical engineers must be familiar with all relevant site procedures,

codes of practice and Health and Safety regulations related to the operation and maintenance of the

cabinet.

Page 6: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

6 | ASD774-D

Operating & Maintenance Manual

2 General Description

2.1 Overview

The Bowler is a single-compartment cabinet designed for use in the UK on cell site locations.

The cabinet provides a secure enclosure (IP33) for the safe housing of Radios and Combiners.

All the equipment inside the cabinet is IP rated, including the fan units which are outdoor rated. The non-IP

rated items such as fan controller are placed inside an IP 68 rated enclosure. The cabinet can house up to

12 RRUs, 6 pairs of filters and 6 diplexers.

The cabinet life expectancy under normal atmospheric conditions is 20 years, subject to regular routine

maintenance.

2.2 Quality Assurance

CommScope aims to provide defect free goods and services to its customers, on time and to budget. The

organisation operates a quality management system that has gained BS EN ISO 9001: 2000 certification.

2.3 Mechanical Information

The cabinet is made to a sheet metal design, fabricated to create a single piece rigid carcass with one

compartment and two doors. The door is lockable using a bespoke locking mechanism and a standard lock.

Page 7: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

7 | ASD774-D

Operating & Maintenance Manual

2.4 Dimensions

The cabinet footprint is 1900mm wide and 600mm deep.

The overall height of the cabinet is 1752mm.

Figure 1: Cabinet Dimensions

2.5 Finish

All metallic parts will be finished with polyester powder coat paint except where components are made

from corrosion resistant self-colour materials. Refer to Appendix B – Paint Specifications for further details.

2.6 Ingress Protection

The cabinet has been designed and tested to meet the standards of IP33 IEC 60529.

2.7 Lifting

The cabinet has been designed to be lifted by four detachable lifting lugs fitted to the front and rear of the

cabinet, at low level. The cabinet has been designed to withstand the loads applied under lifting conditions

using the two lifting brackets (Not supplied) attached to the cabinet. The all up lifting load should not

exceed 300Kg. Lifting details are provided on a label adhered to the inside of the doors. Refer to Appendix

E – Lift Diagram for lifting information.

2.8 Mounting

The cabinet can be mounted to a pre-installed in-ground root or a plinth for fitting to either a concrete

base or grillage. If the cabinet is fitted to a grillage then it would need to be mounted to a plinth as the

base of the cabinet is open.

Refer to Appendix F – or Appendix G – for installation information.

Page 8: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

8 | ASD774-D

Operating & Maintenance Manual

2.9 Electrical

The electrical installation which forms an integral part of the cabinet is designed and constructed in full

accordance with the latest requirements of the IEE Wiring Regulations, (BS 7671).

Each installation is factory assembled and tested by a competent person certified to issue a NIC EIC

certificate. A completed copy of this certificate is to be dispatched within each cabinet.

As standard the cabinet is supplied as a DC only solution. This power is to be supplied from a separate

power cabinet. This may be a Huawei APM or Ericsson 6130 depending on site type.

2.10 Cable and Feeder Identification

All pre-installed cables will be labelled, and an electrical schematic provided. The feeders are part

assembled to the correct location in the factory and identified with correct feeder tags according to MBNL

document RD10010.

2.11 Cable Entry

The cables entering the cabinet are routed through the side of the cabinet, where the power cabinet is

located. The feeders are routed through the base of the cabinet.

2.12 Earthing

The cabinet is fully bonded to a Main Earth Terminal 'MET'. The cabinet is not earthed until it is installed and

bonded to the earthing arrangement of the installation as required by BS7671.

2.13 Thermal Management

The cabinet is fitted with a thermal management system to regulate air movement through the cabinet so

that installed equipment remains within its operating temperature. The cabinet has been tested through the

use a temperature-controlled chamber to verify this system.

2.14 Order Part Numbers

Mounting Options:

Part Number Description Remarks

A-100381 Huawei APM Root To mount Huawei APM Cabinet

A-101382 Bowler Root To mount Cabinet on new build sites

A-101391 Bowler Transfer Plinth To mount Cabinet to existing Huawei Root

A-101410 Ericsson 6130 Plinth To mount Ericsson 6130 on existing Huawei APM Root

Huawei Cabinet Options:

Part Number Description Remarks

A-101377 Bowler RFC Cabinet Empty Cabinet without equipment

A-101386 Bowler RFC Bilateral Cabinet Cabinet Configured for Bilateral Sites

A-101387 Bowler RFC Unilateral Cabinet Cabinet Configured for Unilateral Sites

A-101388 Bowler RFC Bilateral Kit Electrical and Feeder kit for Bilateral Sites

A-101389 Bowler RFC Unilateral Kit Electrical and Feeder kit for Unilateral Sites

A-101399 Bowler RFC Cabinet with Combiners Cabinet for Bilateral Sites with Combiners

Page 9: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

9 | ASD774-D

Operating & Maintenance Manual

Ericsson Cabinet Options:

Part Number Description Remarks

A-101422 Bowler RFC Cabinet Empty Cabinet without equipment

A-101423 Bowler RFC Cabinet (Templates and

Combiners)

Empty Cabinet with RRU templates and

combiners

A-101430 Bowler RFC Cabinet (Templates Only) Empty Cabinet with RRU templates and

without combiners

Conversion Kits:

Part Number Description Remarks

A-101406 Huawei to Ericsson Mechanical Kit

(with Combiners)

To convert Huawei cabinet to Ericsson (with

Combiners). Requires Electrical Kit.

A-101407 Huawei to Ericsson Electrical Kit (with

Combiners)

Electrical and Feeder Kit for Huawei to Ericsson

conversions (with Combiners)

A-101408 Bowler Retrofit Kit (with Combiners) To convert empty cabinet to Ericsson (with

Combiners). Includes Electrical Kit.

A-101409 Bowler Retrofit Kit (without

Combiners)

To convert empty cabinet to Ericsson (without

Combiners). Includes Electrical Kit.

A-101411 Huawei to Ericsson Mechanical Kit

(without Combiners)

To convert Huawei cabinet to Ericsson (without

Combiners). Requires Electrical Kit.

A-101412 Huawei to Ericsson Electrical Kit

(without Combiners)

Electrical and Feeder Kit for Huawei to Ericsson

conversions (without Combiners)

Page 10: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

10 | ASD774-D

Operating & Maintenance Manual

3 Logistics

3.1 Handling Information

The completed cabinet mass as shipped (empty) is 110Kg. Not exceeding 220Kg when fully fitted. HSE

guidance on moving such a mass should be observed.

3.2 Dimensions

Refer to Section 2.4 for dimension information.

3.3 Lifting Slings

Four lifting slings of minimum length 3m should be used meeting at a single point over the centre of the

cabinet. The included angle should be less than 60 degrees. These are not supplied with the cabinet.

3.4 Lifting Lugs

Lifting lugs are not supplied with the cabinet. A number will have been issued to each installer. Please

contact CommScope on 01653 602890 if additional lugs are required. Each bracket is rated for a safe

working load of 225kg and is identified with a serial number stamped into the part. These may be re-used.

It is recommended that the bracket be re-tested every 6 months to ensure compliance with the Lifting

Operations and Lifting Equipment 1998 (LOLER) regulations.

3.5 Assessment for Lifting

Lifting operations should be planned and carried out by qualified and competent persons in accordance

with LOLER regulations. All lifting equipment should be visually examined before each lift.

3.6 Details for Forklift Handling

The cabinet may be moved by means of a forklift truck (FLT).

3.7 Transportation

The cabinet should be transported in an enclosed flatbed van or lorry. Restraints will be required to prevent

in transit damage, care must be taken not to damage cabinets with over tight restraints.

Page 11: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

11 | ASD774-D

Operating & Maintenance Manual

4 Alarms Information All alarms are normally closed. There alarms provided within the cabinet are routed to a Krone connection

block. The alarms are in a standard configuration as follows:

Krone Terminal CommScope Pair Colour From

1 Black/Red Temperature Stage 1 (Major)

2 Black/White Temperature Stage 2 (Critical)

3 Not Used Not Used

4 Not Used Not Used

5 Not Used Not Used

6 Not Used Not Used

7 Not Used Not Used

8 Not Used Not Used

9 Not Used Not Used

0 Blue/White Intruder (Door Loop)

The Bowler cabinet will contain an alarm block only when in Ericsson configuration. When deployed in

Huawei configuration all alarms are routed back to the APM alarm block.

When fitted, the Krone block is located in the centre of the rear of the cabinet (Figure 2). Note that

terminals 1b and 2b share a common connection.

Figure 2: Krone Connections

Page 12: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

12 | ASD774-D

Operating & Maintenance Manual

4.1 Thermal Management Alarms

Alarms are given for fan failure, sensor failure and over temperature (60°C).

Fan Failure Alarm:

If the speed of any fan drops below 70% of the speed of the other fans, the speed demand will increase to

maximum speed (approx. 4100RPM dependent on supply voltage and load). A General Alarm will be

indicated by de-energizing the Alarm 1 General Alarm relay and changing the LED to RED.

Open / Short Circuit Temperature Sensor Alarm:

If the thermistor connected to the input Temp 1 is detected as either being open or short circuit, then the

fans will operate at the normal high-speed of 4100 RPM and general alarm will be indicated by de-

energizing the General Alarm 1 Relay and changing the colour of the LED to flashing RED.

High Temperature Alarm:

If the temperature detected by the sensor connected to input Temp 1 reaches 60°C the controller will

indicate a High Temperature Alarm by opening the Normally Closed contacts of the Alarm 2 Relay and the

LED will flash RED/GREEN. The High Temperature alarm will be turned off if the temperature drops to 57°C.

In the event of multiple alarms, the controller will prioritise them as follows:

1. Fan Failure as indicated by a continuous RED LED.

2. Temperature sensor failure as indicated by a flashing RED LED.

3. Filter alarm as indicated by a flashing AMBER LED.

4. Over temperature as indicated by a RED/GREEN flashing LED.

In the event of a controller failure such that there is no output from the microcontroller the fans will operate

at maximum speed (approx. 4100RPM) and the General Alarm relay will be de-energized. There will typically

be no LED indication. In this unlikely situation, the over temperature and under temperature alarms will not

give an alarm indication.

Page 13: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

13 | ASD774-D

Operating & Maintenance Manual

5 Operating Information

5.1 Cabinet Overview

Cabinet layouts show for both Huawei (Figure 3) and Ericsson (Figure 4) configurations.

Figure 3: Huawei Bowler Overview

Figure 4: Ericsson Bowler Overview

Page 14: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

14 | ASD774-D

Operating & Maintenance Manual

5.2 Door Locks

All doors have a locking mechanism requiring a key for security. The front and rear doors are fitted with a

swing handle lock (Figure 5), this contains 3UK standard cylinder Ruko 5CA22. Refer to the Spare Parts List.

Figure 5: Swing Handle Lock

5.3 Door Stays

The doors are fitted with stays to restrain them open at 110°. When opening the door, the stay will drop

and lock into place to restrain the door when it reaches its maximum opening angle (Figure 6).

The release the door, push the stay upwards into the slot while closing the door (Figure 7). The stay will

then slide backwards to its starting position as the door is closed.

Figure 6: Stay in Open Position

Figure 7: Closing Door Stay

Page 15: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

15 | ASD774-D

Operating & Maintenance Manual

5.4 Lightning Protection

Located at the bottom of the left-hand side of the base there is an M10 bolt provided for lightning

protection (Figure 8).

Figure 8: Lightning Protection Point

5.5 Equipment Earth Bar

The cabinet also contains two earth bars in the main section of the cabinet, located on both vertical

supports (Figure 9). Equipment fitted within this compartment should be connected to this point in

accordance with the manufacturer’s guidance.

Figure 9: Equipment Earth Bar

Page 16: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

16 | ASD774-D

Operating & Maintenance Manual

5.6 Thermal Management System

The fan controller is mounted in the centre of the cabinet roof, in an IP rated enclosure (Figure 10).

Figure 10: Fan Controller Position

The thermal management system is self-managing and requires no manual input. During normal operation

the controller should show a GREEN LED. Refer to Section 4.1 for alarms information.

The fan controller is not designed for ‘hot pluggable’ operation. Isolate power to the controller before

adding or removing any connection.

Page 17: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

17 | ASD774-D

Operating & Maintenance Manual

6 Maintenance Information

6.1 Mechanical Schedule

An annual check should be made to ensure the cabinet is in good condition. An exterior check should be

made for mechanical damage. Any damage which could affect the life expectancy of the cabinet should

receive corrective attention as soon as is practicable. The exterior surface of the cabinet should be wiped to

remove dust and dirt; this will help to keep the paint in good condition.

6.2 Door Hinges

The hinges used on the cabinet are stainless steel and do not require any maintenance during normal use.

6.3 Door Seals

The door seals should not require any attention during normal use. If they become damaged, they must be

removed and replaced with new seal, otherwise the weather protection of the cabinet may be

compromised.

6.4 Paintwork

A thorough check of the condition of the external paint work should be made annually. Any damage which

could affect the life expectancy of the cabinet should receive immediate corrective attention.

Damage such as chips and scratches to paint work should be repaired using a colour matched synthetic

paint. Cellulose based paint should not be used.

6.4.1 Preparation

The damaged area and immediate surroundings should be sanded lightly with a fine sandpaper, ensuring

that there is no loose material on the affected areas.

6.4.2 Priming

A synthetic primer of appropriate colour should be applied to any bare metal in the prepared area.

6.4.3 Finish

Colour matched synthetic topcoat paint should be applied to the prepared area. When dry the area should

be buffed.

Page 18: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

18 | ASD774-D

Operating & Maintenance Manual

6.5 Fan Controller

The Fan controller is replaceable if required. Before proceeding turn off power to the thermal management

system, PSU Breaker F1. Locate the fan controller in the top of the cabinet (Figure 11).

First open the enclosure to gain access to the fan controller. Remove any connections to the controller and

the four M4 fixings to release the fan controller.

Figure 11: Fan Controller

The new controller is fitted by re-using the same fixings. Ensure all cables are reconnected to their original

position. Only after all connections have been made can power be restored to the controller. Ensure that

the waterproof enclosure is fitted.

Page 19: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

19 | ASD774-D

Operating & Maintenance Manual

6.6 Fan Module

The Fan module is replaceable if required. Before proceeding turn off power to the thermal management

system.

Figure 12: Fan Connections

Locate both the fan controller and the fan module. Trace the fan cable back to the controller and

disconnect it (Figure 12).

The fan module can now be removed be removing the four screws (Figure 13) and carefully lowering the

module (Figure 14). Take are the module does not fall after its fixings have been removed.

Figure 13: Removing Fan Module 1

Figure 14: Removing Fan Module 2

Fit the module by replacing the 4 screws that were removed earlier. Re-fit the power and earth connections

to the points they were removed from earlier.

To re-fit the roof; lift the roof panel back into position and re-fit the bolts that were removed earlier.

Only after all connections have been made can power be restored to the thermal management system.

Page 20: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

20 | ASD774-D

Operating & Maintenance Manual

7 Installation Information

7.1 RRU Installation

Mounting brackets are supplied with the cabinet, attached to the mounting rails (Figure 15), remove these

and attach the radio to the mounting bracket using the OEM fixing supplied with the radio (Figure 16)

Figure 15: Radio Mounting Brackets

Figure 16: Radio Bracket Fitting

Mount the complete assembly back to the mounting rail by using one fixing per bracket only.

Mounts on the left side of the cabinet use upper left fixing position (Figure 18). Mounts on the right side of

the cabinet use the upper right fixing position (Figure 19).

Figure 17: Radio Mount Positions

Page 21: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

21 | ASD774-D

Operating & Maintenance Manual

Figure 18: Location on LH Radio Mounts

Figure 19: Location on RH Radio Mounts

Repeat this process for all radios (Figure 20). Connect DC feeds and Earths in accordance with the Radio

manufacturers guidance.

Figure 20: Radio Final Position

Page 22: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

22 | ASD774-D

Operating & Maintenance Manual

7.2 Template Installation

Where the cabinet does not yet contain radios, but feeder and power cable must be routed, templates will

be provided to secure the connections in their relevant places. (Figure 21).

Figure 21: Radio Template

Fit the bracket in the same way as a radio. Secure the cables to the positions shown.

If Combiners are not pre-fitted but are required at a later date, templates will be provided to terminate the

feeder cables in the correct position (Figure 22).

Figure 22: Combiner Template

Route the feeder cables to the plates and secure in place.

Page 23: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

23 | ASD774-D

Operating & Maintenance Manual

7.3 Combiner Installation

The following combiner types are supported:

• Radio Design RD0840

• CommScope E14F05P63

• Kathrein 78211533

When using either CommScope (Figure 23) or Kathrein (Figure 24) combiners; these will retain their original

bracket and bolt onto the mounting plate using M8 fixings.

Figure 23: CommScope Combiners

Figure 24: Kathrein Combiners

When Using Radio Design combiners; remove the OEM bracket and re-use these same fixings to attach to

the Bowler bracket (Figure 25).

Figure 25: Radio Design Combiners

Page 24: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

24 | ASD774-D

Operating & Maintenance Manual

Finally mount the completed combiner and mount assembly to the mounting rail in the lower right-hand

side of the cabinet (Figure 26).

Figure 26: Combiners in Position

After Combiners are secured, feeders and earth cables can be connected.

Page 25: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

25 | ASD774-D

Operating & Maintenance Manual

8 Huawei Version The Huawei cabinet provides mounting for a total of 6 Huawei RRUs, as well as combiner space if required.

The standard radio positions are:

• Upper Left-Hand – 3x Huawei RRU 5301 providing 4G L800

• Upper Right-Hand – 3x Huawei RRU 5501 providing 4G L1800 & L2100

• Lower Left-Hand – 3x Huawei RRU 5301 4G L1400

• Lower Right-Hand – 3x combiner brackets (if required)

Figure 27: Huawei Configuration

Page 26: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

26 | ASD774-D

Operating & Maintenance Manual

8.1 DC Distribution

The Bowler cabinet is provided with the following DC feeds. Feeds to be taken from the Huawei APM

cabinet and connected to its designated position.

Source Label Rating Destination

APM D04/D05 FC 10A Bowler Fan Controller

APM D03 RRU1 25A RRU 5301 L08 Sector 1

APM D06 RRU2 25A RRU 5301 L08 Sector 2

APM D07 RRU3 25A RRU 5301 L08 Sector 3

APM D09 RRU4 25A RRU 5501 L18/21 Sector 1

APM D10 RRU5 25A RRU 5501 L18/21 Sector 2

APM D11 RRU6 25A RRU 5501 L18/21 Sector 3

APM D12 RRU7 25A RRU 5301 L14 Sector 1

APM D13 RRU8 25A RRU 5301 L14 Sector 2

APM D15 RRU9 25A RRU 5301 L14 Sector 3

All power and fibre cable should be routed out of the cabinet through the side entry panels.

Page 27: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

27 | ASD774-D

Operating & Maintenance Manual

9 Ericsson Version The Huawei cabinet provides mounting for a total of 6 Huawei RRUs, as well as combiner space if required.

The standard radio positions are:

• Upper Left-Hand – 3x Ericsson 4480 providing 4G L1800/L2100

• Upper Right-Hand – 6x Ericsson 2012 providing 4G L1400 with 6x Ericsson 1400 Filter

• Lower Left-Hand – 3x Ericsson 2460 providing 4G L800

• Lower Right-Hand – 3x combiner (If Combiners are not fitted a template is provided to terminate

feeders from pole).

Figure 28: Ericsson Configuration

Page 28: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

28 | ASD774-D

Operating & Maintenance Manual

9.1 DC Distribution

The Bowler cabinet is provided with the following DC feeds. Feeds to be taken from the Ericsson 6130

cabinet and connected to its designated position.

Source Label Rating Destination

Ericsson 6130 FC 10A Bowler Fan Controller

ERS1 25A Ericsson 4480 (1800/2100) 1

ERS2 25A Ericsson 4480 (1800/2100) 2

ERS3 25A Ericsson 4480 (1800/2100) 3

ERS4 25A Ericsson 2012 (1400) 1

ERS5 25A Ericsson 2012 (1400) 2

ERS6 25A Ericsson 2012 (1400) 3

ERS7 25A Ericsson 2460 (800) 1

ERS8 25A Ericsson 2460 (800) 2

ERS9 25A Ericsson 2460 (800) 3

ERS10 25A Ericsson 2012 (1400) 4

ERS11 25A Ericsson 2012 (1400) 5

ERS12 25A Ericsson 2012 (1400) 6

All power and fibre cable should be routed out of the cabinet through the side entry panel located at the

left-hand base of the cabinet.

Page 29: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

29 | ASD774-D

Operating & Maintenance Manual

10 Appendix A – Additional Reference Documents Refer to the following Documents for additional information about the cabinet:

General Arrangement Drawings

Document Reference Description

G-100875 3UK RFM Bowler Cabinet – Huawei Fit Out

G-100878 3UK RFM Bowler Cabinet with Huawei APM

G-100903 3UK RFM Bowler Cabinet – Ericsson Fit Out

G-100921 3UK RFM Bowler Huawei to Ericsson Conversion Kit

G-100922 3UK RFM Bowler Empty Cabinet to Ericsson Conversion Kit

G-100925 3UK RFM Bowler Cabinet with Ericsson 6130

Electrical Schematics

Document Reference Description

F-100477 3UK RFC Bowler Base Cable Kit

F-100478 3UK RFC Bowler Huawei Radio Feeds

F-100484 3UK RFC Bowler Ericsson Radio Feeds

Testing Information

Document Reference Description

ASD770 3UK RFC Bowler Huawei Thermal Test Report

ASD794 3UK RFC Bowler Ericsson Thermal Test Report

ASD780 3UK RFC Bowler IP33 Test Report

ASD775 3UK RFC Bowler Noise Test Report (2 Fan)

ASD796 3UK RFC Bowler Noise Test Report (4 Fan)

Additional Components

Document Reference Description

I-100350 Bowler Cabinet Feeder Schematics (Huawei)

I-100353 Bowler/APM Root Transfer Install Guide

I-100360 Bowler Cabinet Feeder Schematics (Ericsson)

I-100363 Ericsson 6130 Cabinet and Transfer Plinth Install Guide

I-100364 Ericsson Retrofit Kit Installation Guide

To request a document; please contact:

Telephone: 01653 602890

Email: [email protected]

Page 30: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

30 | ASD774-D

Operating & Maintenance Manual

11 Appendix B – Paint Specifications

ASD002-F SUMMARY: Specification of paint process and paint finish excluding colour. Leatherette finish 80 Microns.

The components and assemblies are to be coated by powder coating on all faces. The powder coating process must be approved by CommScope Design and Integration UK. The powder must be polyester based and approved by CommScope Design and Integration UK. Unless otherwise stated the powder coat finish after baking will always be a minimum thickness of 80 microns. This applies to all components and assemblies. Colours will be specified at point of order and are listed on enclosure painting lists. The finish must meet the following specification:

1. Impact resistance – ASTMP 2794 to 60lbs 2. Scratch resistance – BS 3900 PART E2. The cabinet finish shall resist a sharp point weighted to 4.5 kg 3. Coating adhesion – BS 3900 Part E6, Cross hatch 4. Light resistance – QUV O metal to 200 hours 5. Salt spray - Pass ASTMB 177 6. Sulphur Dioxide – BS 3900 Part F8 exposed for 250 hours. There shall be no colour change, softening,

blistering or loss of adhesion of the coating.

The gloss level for external surfaces is 60%, Leatherette

The bare component’s base material will be pre-galvanized mild steel, aluminium or Stainless Steel, according to drawings. Ink used by steel suppliers to identify sheet should have been removed when the parts are supplied for painting, any remaining ink must be removed before coating. It is expected that the coater will be able to paint parts to the agreed standard all over without modifying the parts, i.e. no additional holes will be included to hang the parts unless a written concession to do so is given to the coater from CommScope Design and Integration UK. Where Rivnuts, PEM’s or threaded studs are present, the threads must be masked off before coating.

Page 31: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

31 | ASD774-D

Operating & Maintenance Manual

12 Appendix C – Layout Drawing G-100875

Page 32: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

32 | ASD774-D

Operating & Maintenance Manual

13 Appendix D – Layout Drawing G-100903

Page 33: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

33 | ASD774-D

Operating & Maintenance Manual

14 Appendix E – Lift Diagram

Figure 29: Lifting Diagram

Lifting label details:

Lifting information.

Min sling length: 3m.

Max all up lift: 220Kg

Included angle max: 60°.

Use 0.5T D shackle on lugs.

Page 34: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

34 | ASD774-D

Operating & Maintenance Manual

15 Appendix F – Fitting to Existing Huawei Root THIS INSTALLATION DOCUMENT IS FOR GUIDANCE ONLY, SITE SPECIFIC CONDITIONS OR BUILD

GUIDANCE IS TO TAKE PRECEDENCE

Refer to I-100353 for additional guidance.

Figure 30: Transfer Plinth Installation

An additional Huawei 3900A root must be installed aligned with existing roots both vertically and

horizontally and butted up to existing roots with no gap or ground materials between. It is strongly

recommended that the transfer plinth is fastened to all three Huawei 3900A roots before concrete is poured

and cured to ensure alignment of the roots.

Page 35: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

35 | ASD774-D

Operating & Maintenance Manual

Figure 31: Duct Positions (Huawei)

Installing Root:

1. Align the transfer plinth on the roots with the slanted profile at the back. The transfer plinth should

be butted up against the existing Huawei cabinet or as close to it as possible. The transfer plinth is

20 mm narrower than the three roots so expect to see a small amount of spare root visible at the

right of the CommScope Bowler cabinet. Align the slots at the rear of the transfer plinth with the

holes in the top surface of the Huawei 3900A roots.

2. Place rectangular washers provided in the fixing kit over each slot at the rear of the transfer plinth

and insert a bolt through the special washer, transfer plinth and root.

3. Where the bolt emerges from the underside of the root top, add a flat washer, followed by spring

washer and thread the nut on to retain. Do this for all the rear fixing points and hand tighten only.

4. Repeat the process on the front slots of the transfer plate then tighten all the bolts another ½ turn

with a pair of 24 mm spanners.

5. Pour concrete and allow to cure for a minimum of 24 hours. The concrete inside the cabinet base

should be a minimum of 60 mm below the top of the root and sealed with a 2mm bitumen coating.

Page 36: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

36 | ASD774-D

Operating & Maintenance Manual

Installing Transfer Plinth

1. Remove the transfer plinth.

2. Apply a liberal bead of silicone sealant (supplied with the CommScope Bowler cabinet) to the

perimeter of the roots’ top surface.

3. Align the transfer plinth as described earlier.

4. Fasten the transfer plinth down to the roots as described earlier. Tighten the fasteners to 200 Nm.

5. Apply a neat bead of sealant round the outside of the transfer plinth at the joint with the root.

Installing Cabinet:

1. Place a liberal bead of sealant supplied on the top face of the transfer plinth.

2. Lift cabinet into final position.

3. The cabinet is to be secured to the transfer plinth using the 18 off M10 set screws supplied. These

are fitted with a large OD washer inside the cabinet (upward facing face) and a lock washer on the

underside to the face of the transfer plinth. Tighten M10 nuts and set screws to approximately

50 Nm.

4. Apply a neat bead of sealant round the outside of the cabinet at the joint with the transfer plinth.

5. Check that door opens and closes correctly. Shim the cabinet if required using the shims provided in

the fixing kit.

6. Following installation of all cables through the ducts, seal the ducts

7. Close and lock the cabinet door.

Page 37: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

37 | ASD774-D

Operating & Maintenance Manual

16 Appendix G – Fitting to Bowler Root THIS INSTALLATION DOCUMENT IS FOR GUIDANCE ONLY, SITE SPECIFIC CONDITIONS OR BUILD

GUIDANCE IS TO TAKE PRECEDENCE

Figure 32: Bowler Root Installation

Page 38: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

38 | ASD774-D

Operating & Maintenance Manual

Figure 33: Duct Positions (Ericsson)

Installing Root:

1. Check clearances when positioning near existing structures, 100mm gap must be provided at rear.

2. Excavate hole size of 2742 x 800 to accommodate both roots. Depth to suit local ground conditions.

3. Position ducts in approximate positions as indicated.

4. Infill the hole with compacted hardcore at least 150mm deep.

5. Place each end of the root on sand and position so approximately 20mm of the root protrudes

above ground level.

6. Top surface of the root must be level ±2mm in all directions. Pack under ends if required.

7. Infill with concrete inside and outside of the root.

8. Concrete to be left to set a minimum of 24 hours before fitting the cabinet.

Page 39: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

39 | ASD774-D

Operating & Maintenance Manual

Installing Cabinet:

1. Place a liberal bead of sealant supplied on the top face of the transfer plinth.

2. Lift cabinet into final position.

3. The cabinet is to be secured to the transfer plinth using the 18 off M10 set screws supplied. These

are fitted with a large OD washer inside the cabinet (upward facing face) and a lock washer on the

underside to the face of the transfer plinth. Tighten M10 nuts and set screws to approximately

50 Nm.

4. Apply a neat bead of sealant round the outside of the cabinet at the joint with the transfer plinth.

5. Check that door opens and closes correctly. Shim the cabinet if required using the shims provided in

the fixing kit.

6. Following installation of all cables through the ducts, seal the ducts

7. Close and lock the cabinet door.

For guidance on installing the Ericsson 6130 Cabinet and Plinth, Refer to I-100363.

Page 40: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

40 | ASD774-D

Operating & Maintenance Manual

17 Appendix H – Fan Specification

Nominal Voltage 48v

Operating Voltage 38v ~ 56v

Starting Voltage 36v

Fan Speed 4100 ±200 rpm

Max Air Flow 787 m³/hour

Max Pressure 686 Pa

Nominal Current 1.6A

Nominal Input Power 83.2W

Acoustic Noise 73dBA

Weight 1.2kg

Figure 34: Fan Performance

Page 41: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

41 | ASD774-D

Operating & Maintenance Manual

18 Appendix I – Noise Data Tested to meet the requirements of “Telcordia GR-487-CORE, Generic Requirements for Electrical

Equipment Cabinets. Section 3.34”. The noise level must be less than 65dBA at 1.5m from the cabinet.

Test 1 Fans High (4000RPM)

Test No 1 (35 oC /4000 rpm)

Ambient 44.9 dB A - 46.7 dB A

Position from Cabinet

1.5 m 2.5 m 3.5 m 4.5 m

Front 62.8 dB A 61.4 dB A 57.9 dB A 56.3 dB A

Front Right 61.7 dB A 56.3 dB A 55.2 dB A 51.9 dB A

Front Left 57.6 dB A 57.2 dB A 56.6 dB A 54.7 dB A

Rear 54.8 dB A 52.6 dB A 49.1 dB A 49.7 dB A

Rear Right 53.3 dB A 52.7 dB A 50.6 dB A 49.7 dB A

Rear Left 54.7 dB A 52.9 dB A 52.3 dB A 49.7 dB A

Left 53.6 dB A 52.1 dB A 49.3 dB A 49.5 dB A

Right 56.9 dB A 55.6 dB A 54.5 dB A 53.7 dB A

Average 56.9 dB A 55.1 dB A 53.2 dB A 51.9 dB A

Test 2 Fans Medium (2400RPM)

Test No 2 (25 oC /2400 rpm)

Ambient 44.8 dB A - 46.7 dB A

Position from Cabinet

1.5 m 2.5 m 3.5 m 4.5 m

Front 53.7 dB A 52.7 dB A 50.6 dB A 49.2 dB A

Front Right 51.6 dB A 51.9 dB A 51.6 dB A 50.6 dB A

Front Left 52.6 dB A 50.1 dB A 48.3 dB A 49.2 dB A

Rear 44.5 dB A 42.4 dB A 46.8 dB A 45.6 dB A

Rear Right 49.6 dB A 49.5 dB A 49.3 dB A 48.7 dB A

Rear Left 48.7 dB A 45.8 dB A 46.5 dB A 48.8 dB A

Left 49.2 dB A 47.9 dB A 46.8 dB A 46.7 dB A

Right 46.5 dB A 48.6 dB A 48.4 dB A 47.9 dB A

Average 49.6 dB A 48.6 dB A 48.5 dB A 48.3 dB A

Page 42: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

42 | ASD774-D

Operating & Maintenance Manual

Test 3 Fans Low (800RPM)

Test No 3 (15 oC /800 rpm)

Ambient 44.9 dB A - 50.2 dB A

Position from Cabinet

1.5 m 2.5 m 3.5 m 4.5 m

Front 48.2 dB A 47.5 dB A 45.6 dB A 45.4 dB A

Front Right 51.4 dB A 50.2 dB A 50.5 dB A 50.6 dB A

Front Left 50.5 dB A 49.7 dB A 49.9 dB A 49.9 dB A

Rear 49.9 dB A 49.5 dB A 48.8 dB A 49.3 dB A

Rear Right 50.6 dB A 50.4 dB A 50.1 dB A 49.6 dB A

Rear Left 50.9 dB A 50.9 dB A 50.5 dB A 50.4 dB A

Left 47.5 dB A 48.8 dB A 48.8 dB A 48.4 dB A

Right 50.1 dB A 50.2 dB A 49.9 dB A 49.1 dB A

Average 49.9 dB A 49.7 dB A 49.3 dB A 49.1 dB A

Refer to ASD775 and ASD796 for full details of the noise testing.

Page 43: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

43 | ASD774-D

Operating & Maintenance Manual

19 Appendix J – Spare Parts List

Description Part Number

Swing Handle Lock B-101078

Europrofile Single Side Lock Ruko 5CA22 B-102424

LH Lock Cam B-102607

Shoot Bolt Assembly S-100676

LH Upper Lock Rod 860653229

LH Lower Lock Rod 860653228

RH Lock Cam C-101436

RH Upper Lock Rod 860653230

RH Lower Lock Rod 860653234

Door Stay 860656195

LH Door Filter 860656194

RH Door Filter 860656197

Fan Controller B-104485

Fan Cartridge S-100340

Temp Sensor B-103707

Door Contact Switch B-100646

Lifting Bracket S-100649

For all spare parts enquiries:

Telephone: 01653 602890

Email: [email protected]

Page 44: 3UK RFC Bowler Cabinet Operation & Maintenance...manufactured to a specification laid out by Mobile Broadband Network Limited (MBNL) for Hutchinson 3G UK (H3G). CommScope reserves

44 | ASD774-D

Operating & Maintenance Manual

www.commscope.com

Visit our Web site or contact your local CommScope representative for more information.

© 2020 CommScope, Inc. All rights reserved.

All trademarks identified by ® or ™ are registered trademarks or trademarks, respectively, of CommScope, Inc.

This document is for planning purposes only and is not intended to modify or supplement any specifications or warranties relating to CommScope

products or services.


Recommended