Date post: | 06-Apr-2018 |
Category: |
Documents |
Upload: | drhelmi7256 |
View: | 215 times |
Download: | 0 times |
of 19
8/3/2019 4-Koehler-presentation 4 - Innovative Utilization of Smart i
1/19
Innovative Utilization ofSmart Instrumentation at aNuclear Power Plant
Jeff Kerker, Bruce Power Design Team Leader
Terry Koehler, Lakeside Process Controls Project Technical Lead
Eddie Saab, Lakeside Process Controls Account Manager
8/3/2019 4-Koehler-presentation 4 - Innovative Utilization of Smart i
2/19
IntroductionIntroductionIntroductionIntroduction
HX5 History
Basic System Operating Philosophy
Project Scope
Design Issues
Control Retrofit Challenges and Solutions
Results Achieved
Summary Lessons Learned
8/3/2019 4-Koehler-presentation 4 - Innovative Utilization of Smart i
3/19
HX5 HistoryHX5 HistoryHX5 HistoryHX5 History
Steam hammers discovered and documented inHX5 drain lines. Station Condition Record (SCRs)were raised and Operating Experience (OPEX)was reviewed for similar events.
Various fixes applied that did not really addressthe root causes (e.g. boosters, time delay relays,valve changes, diffuser mods etc.)
Several steam hammer mechanisms wereoccurring, at various system conditions, thatconfused the investigations.
8/3/2019 4-Koehler-presentation 4 - Innovative Utilization of Smart i
4/19
BasicOperatingPhilosophyBasicOperatingPhilosophyBasicOperatingPhilosophyBasicOperatingPhilosophy
P&ID Sketch for HP FW Heater Circuit
8/3/2019 4-Koehler-presentation 4 - Innovative Utilization of Smart i
5/19
ProjectScopeProjectScopeProjectScopeProjectScope
Remove inverted loop in HX5 drains lines
Upgrade HX5 level control system identified as acontributing factor to various steam hammers.
Maintain independent, hard-wired turbine water induction
protection. (e.g. level switches)
Operator actions to be minimized.
HX5 to operate as per original design.
Modification required for the next unit outage. (7 months)
8/3/2019 4-Koehler-presentation 4 - Innovative Utilization of Smart i
6/19
DesignIssuesDesignIssuesDesignIssuesDesignIssues
Where and how to bore the hole between thereheater drains pit and the condenser pit toeliminate the inverted loop?
8/3/2019 4-Koehler-presentation 4 - Innovative Utilization of Smart i
7/19
DesignIssuesDesignIssuesDesignIssuesDesignIssues
Original Piping Configuration
Pit Bottom el. 571
Bruce B
Bruce A
CL
CL
Condensate Trench
HP Heater Drain Line 12 dia.
pipe el. 582-4pipe el. 582-3
Condenser Pit el. 578
CondenserCD1
pipe el. 592-0
36 Condensate Line
Ground Floor el. 591
pipe el. 592-6
pipe el. 583
el. 595-3
HP Heater45 35 28 35
Pit Bottom el. 571
pipe el. 585
el. 595-3
HP Heater
pipe el. 589-10
Ground Floor el. 591
HP Heater Drain Line 16 dia
HP Heater Drain Line in shallow trenchCondenserCD1
40 60 35
Condenser Pit el. 578
pipe el. 585-3
pipe el. 593-6
8/3/2019 4-Koehler-presentation 4 - Innovative Utilization of Smart i
8/19
DesignIssuesDesignIssuesDesignIssuesDesignIssues
New Configuration
LCV relocated to East wall of CD1
CondenserCD1
Condensate Line Trench
Tunnel bored for relocated Drains Line
15
3762
HP Heater Drains Line reduced in sizefrom 16 to 12 dia.
HP Heaterel. 595-3
Condenser Pit el. 57836 Condensate Line
pipe el. 583
Pit Bottom el. 571
CL
8/3/2019 4-Koehler-presentation 4 - Innovative Utilization of Smart i
9/19
Where and how to bore the hole between thereheater drains pit and the condenser pit toeliminate the inverted loop?
The drains line contains saturated water at lowpower conditions. How do we deal with smallersecondary steam hammers caused by steambubble formation and collapse?
DesignIssuesDesignIssuesDesignIssuesDesignIssues
8/3/2019 4-Koehler-presentation 4 - Innovative Utilization of Smart i
10/19
Significantly reduce size of possible steambubble by:
Reducing line length
Reducing line diameter
Continuous upward sloping line
Design the line to withstand 45,000 lbf steam
hammer at all locations.
SolutionSolutionSolutionSolution
8/3/2019 4-Koehler-presentation 4 - Innovative Utilization of Smart i
11/19
FusedPipe SupportFusedPipe SupportFusedPipe SupportFusedPipe Support
8/3/2019 4-Koehler-presentation 4 - Innovative Utilization of Smart i
12/19
Where and how to bore the hole between thereheater drains pit and the condenser pit toeliminate the inverted loop?
The drains line contains saturated water at lowpower conditions. How do we deal with smallersecondary steam hammers caused by steambubble formation and collapse?
Upgrade pneumatic controls to Smart electronic.
DesignIssuesDesignIssuesDesignIssuesDesignIssues
8/3/2019 4-Koehler-presentation 4 - Innovative Utilization of Smart i
13/19
ControlRetrofitChallengesControlRetrofitChallengesControlRetrofitChallengesControlRetrofitChallenges
Challenges
1. Analog and existing safety controls separate yetintegrated
Valves to integrate with existing safety logic from
existing level switches / pump starters Only one wire pair to be run from controller to control
valves
Controller required to sense the state of the safety logiccircuits to ensure bumpless transfer and avoid fast
transients which could cause water hammer
2. Hot commissioning time extremely limited one try only
8/3/2019 4-Koehler-presentation 4 - Innovative Utilization of Smart i
14/19
ControlRetrofitSolutionControlRetrofitSolutionControlRetrofitSolutionControlRetrofitSolution
Deaerator and Dump Valves
New valves have DVC 6000PD, integrated solenoidsand junction box
On loss of power to the solenoid, positioner air supply isblocked and actuator air bled to achieve fail position
Through HART signal (3rd variable configured for supplypressure), trip of solenoid can be detected by controllerenclosure equipment
Allows for controller tracking mode to be engaged anddisengaged based on the state of the solenoid to avoidreset windup and unbalanced transfer
Smart positioner also allows position feedback and onlinevalve diagnostics (Performance Diagnostics)
Old DA Valve
Solution1. Smart utilization of Smart Equipment
New DA Valve
8/3/2019 4-Koehler-presentation 4 - Innovative Utilization of Smart i
15/19
ControlRetrofitSolutionControlRetrofitSolutionControlRetrofitSolutionControlRetrofitSolution
Controller Enclosure
A. ABB Micromod MC53000B Dual LoopController
Had internal software already verified byBruce Power to meet the requirements ofCATIII
Was used in the control room and henceoperators were familiar with operation
B. Valve Position Indicators
C. Rosemount 333U Triloops
Used to extract HART signals for valveposition and positioner air supply pressure
D. MC53000 Analog Expansion Board
Used to receive analog signals ofpositioner air supply pressure
E. Line Break Detection LEDs
Solution2. Smart utilization of Smart Equipment
A
B C
D
E
8/3/2019 4-Koehler-presentation 4 - Innovative Utilization of Smart i
16/19
ControlRetrofitSolutionControlRetrofitSolutionControlRetrofitSolutionControlRetrofitSolution
Complete hardware (all valves and controllerenclosure) in the loop simulation executedutilizing a high fidelity process model
Valve solenoids actuated by plant trip logic alsosimulated
Simulation used to verify individualcomponents worked correctly together tosatisfy the process requirements
Simulation was made an integral part of theFactory Acceptance test and ISO Quality
Program Simulation used to test response to expected
plant events (DA pump starts / switches, etc.)and abnormal events (pump failures / singlebank operation, etc.)
Solution3. Hardware in-the-loop Simulation
8/3/2019 4-Koehler-presentation 4 - Innovative Utilization of Smart i
17/19
ControlRetrofitSolutionControlRetrofitSolutionControlRetrofitSolutionControlRetrofitSolution
HP Feedwater Heater DA Pump Start-up
0
10
20
30
40
50
60
3:03:36
PM
3:04:19
PM
3:05:02
PM
3:05:46
PM
3:06:29
PM
3:07:12
PM
3:07:55
PM
3:08:38
PM
3:09:22
PM
3:10:05
PM
3:10:48
PM
ValvePositionCommand(%
Open)
-3
-1
1
3
5
7
9
11
Level(inchesaboveNWL)
DA Valve Position Command
Dump Valve Position Command
HX5B Level
Simulation
Actual
Simulation Allowed for control strategy
tuning and testing in asafe environment
Predicted many actualcases which were abnormalconditions which could notbe field tested
Predicted 5 minutes tostabilization on deaeratorpump start
Successful prediction ofevents tested in
commissioning giveconfidence that predictionsof behaviour underabnormal events aresimilarly accurate
8/3/2019 4-Koehler-presentation 4 - Innovative Utilization of Smart i
18/19
Results AchievedResults AchievedResults AchievedResults Achieved
7 months from design
to implementation
8/3/2019 4-Koehler-presentation 4 - Innovative Utilization of Smart i
19/19
Tunnels were bored, old piping was removed, newpiping installed, control system installed and coldcommissioned completed in 28 days.
Unit ran up with HX5A and HX5B in service with
no level alarms or transients. Only operator action required was to turn on the
drains pumps.
Small system disturbances occurred that were
later corrected with minor control changes andmodified system line-up. The next unit start-upconfirmed that these changes solved the problem.
Results AchievedResults AchievedResults AchievedResults Achieved